Report date: 15-Jan-10

DCPP 4x135 MW Unit-1 Daily Commissioning Report Status updated for: 14-Jan-10

S.No. Status of commissioning activities Remarks


1 Trial run of Clarifier and flash mixer motors taken
2
3
4
5
6
7
8

S.No. Planning for today Remarks


1 Trial run of ID fan # 1B motor
2 Trial run of PA fan # 1A motor
3 Trial run of Clarifier agitator & scrapper and flash mixer
4 TG lube oil flushing through oil filters
5
6
7
8

S.No. Exceptions (Delays, if any) Remarks


1
2
3
4
5
6
7
8

S.No. Critical concerns Remarks

1. Feed water line flushing to be


completed before commencement of dry
1 Refractory dry out out. Agency for pre boiler system
cleaning getting delayed.
2. Compressed air of 6kg/cm2 is required.
3. CCOE clearance for filling LDO in
tanks is required
2
3
4
5
6
7
8