Beruflich Dokumente
Kultur Dokumente
• Overview
• PC Post Combustion Removal – Status, Studies, Chilled
Ammonia pilot
• Oxyfuel – Status, SaskPower
• IGCC/PC Studies DOE, EPRI - New Plants with and without
Capture
• Adding Capture to IGCC – Pre-Investment? Work in Progress
• IGCC/PC EPRI Study adding Capture to new plant designed
without Capture – CPS San Antonio
• Effect of Capital Cost increases on COE, CO2 cost, and
Strategic selection of power generation technologies
• Conclusions
CO2 to use
Fresh Water or Sequestration
% POWER REDUCTION 29 10
Source: Nexant
© 2007 Electric Power Research Institute, Inc. All rights reserved. 15
5 MW Chilled Ammonia CO2 Capture Pilot
Gas takeoff
Scrubber Module
O2/CO2 Combustion
• Small test facilities at Canmet, B&W,
Alstom
• Potential reuse of existing boiler
equipment
» Pulverizers, air heaters, etc.
» Potential “retrofit kit”
• CO2 recycled for temp. control
• SO2 removed from purge stream
» If higher purity CO2 required
• Requires large oxygen plant
• Large auxiliary power requirement
» Large net output reduction
» Make-up power source for
Retrofit of existing plant?
Coal
Gas CC
Clean POWER
Air ASU Gasifier Power
O2 Up Block
Slag
H2 & CO2
(e.g., FutureGen) Sulfur CO2
Coal
Gas CC
Air ASU Gasifier Shift Power POWER
Clean
O2 Block
Up
H2
Slag
Weyburn pipeline
http://www.ptrc.ca/access/DesktopDefault.aspx
• Water Quench is the least cost way of adding the moisture for
the Shift reaction.
• Higher pressure e.g. 800-1000 psig decreases the cost of CO2
removal and compression through use of a physical absorption
system (e.g. Selexol) where solvent recovery is largely
achieved through depressurization and without large steam
(energy) penalty. Some CO2 can be recovered at pressure
reducing the needed MW for compression.
• GE can offer high pressure and either Q or RQ provide more
moisture for shift
• COP E-Gas, Shell, Siemens and KBR are lower pressure (<
600 psig) and have lower moisture in the syngas
540 1,400
420 1,100
400 1,050
360 950
Jun-98 Jun-99 Jun-00 Jun-01 Jun-02 Jun-03 Jun-04 Jun-05 Jun-06 Jun-07
3,600
3,400
3,200
.
3,000
Total Plant Cost, $/kW (2006$)
2,800
2,600
2,400
2,200
2,000
1,800
1,600
1,400
GE Radiant Quench GE Total Quench Shell Gas Quench E-Gas FSQ
1,200
No Capture With No Capture With No Capture With No Capture With
Capture Capture Capture Capture
© 2007 Electric Power Research Institute, Inc. All rights reserved. 32
EPRI 600 MW (net) Cost of Electricity (COE)
June 2006 Estimates
(Illinois #6 Coal $1.50/MBtu; with and without CO2 capture, No spare gasifiers)
100
.
30-Yr levelized COE, $/MWh (Constant 2006$)
90
80
70
60
50
Syngas +
Diluent
Gen H2 + Dilue
nt 7FB/9FB Torque Limit
Output
SG Additional IGCC Output
Gas Turbine
7FA/9FA Torque Limit
• For slurry fed gasifiers the CO2 in the syngas can represent 20-
25% of the coal’s carbon that could be removed without using
the Shift reaction. This relatively small amount of capture is
unlikely to generate much support from Federal or State
Authorities.
• For all gasification technologies can use sour High
Temperature Shift followed by two column AGR. Maybe still
use standard syngas GT combustors ? This could result in 60 -
80 % CO2 capture which would satisfy California’s criteria that
the CO2/MWH be no more than from NGCC. Lower COE than
maximum capture option.
• If > 90% removal is required then both high and low
temperature shift beds can be used. Needs Hydrogen
combustors for GT. Higher COE.
0% Capture 25% Capture 35% Capture 55% Capture 75% Capture 90% Capture
40
1.40
Relative Levelized Cost of Electricity
35
25
1.20
20
1.10
LCOE
15
CO2 Avoided
1.00 10
Base No Shift Single Shift Single Shift Single Shift Two Stage Shift
© 2007 Electric Power Research Institute, Inc. All rights reserved. 38
IGCC Pre-Investment Options for later
addition of CO2 Capture
• Standard Provisions
– Space for additional equipment, BOP, and site access at later date
– Net power capacity, efficiency and cost penalty upon conversion to
capture
• Moderate Provisions
– Additional ASU, Gasification and gas clean-up is needed to fully load the
GT’s when Shift is added.
– If this oversizing is included in the initial IGCC investment the capacity
can be used in the pre-capture phase for supplemental firing or co-
production.
– This version of “capture ready” would then permit full GT output with
Hydrogen (at ISO) when capture is added. Mitigates the cost and
efficiency penalty.
– However when shift is added considerable AGR modifications will be
required (See following slides)
• Extensive Provisions
– Design with conversion-shift reactors, oversized components, AGR
absorber sized for shifted syngas but no CO2 absorber and compressor
– No need for major shutdown to complete the conversion to CO2 capture
CO 47 3 49 3 64 4
CO 2 14 58 12 58 2 62
N2 + A 2 2 3 3 6 6
• Addition of Sour Shift increases gas flow to the AGR particularly for
the dry coal fed gasifiers with high CO content (next slide). Unlikely
that the AGR would be able to take the extra flow unless there was
pre-investment oversizing. May need to add a parallel absorber or
replace the entire AGR plant (with a new two column absorption
system) if capture is to be added to an existing IGCC designed
without capture.
• Alternatively the original AGR (focused on H2S Removal) could be
retained and a Sweet shift added after the AGR with a simpler bulk
CO2 removal AGR (ADIP, MDEA, Selexol) added after shift. This
would minimize intrusion into existing plant. This trade off of Sour
versus Sweet Shift needs to be examined and may differ among the
Gasification Technologies. Sweet Shift may incur additional efficiency
and output penalties. Quench gasifiers would probably favor Sour
Shift.
Net Heat Rate, HHV (Btu/kWh) 9,220 9,070 9,150 12,800 12,911
EPC/TPC ($/kW) 2,390 2,330 1,950 3,630 1 3,440 1
20-yr LCOE ($/MWh) (Constant 2006$) 2 45.0 40.9 39.2 65.4 62.0
70
60 Range of
Levelized Cost of Electricity ($/MWhr)
uncertainty
50
40
D e lta fo r C a p tu re
W ith o u t C O 2 C a p tu re
30
20
10
0
IG C C + P R B IG C C + P e t c o k e & P R B SCPC+PRB
Total Makeup Water (acre-ft/yr) (85% CF) 6,830 7,170 7,950 8,430 10,640
CPS IOU
• COE
• CO2 Cost
• Continued Operation of Existing PC plants
• Strategic Selection of Future Generation
• Conclusions
100
Existing Nuclear
90
80 Existing PC with Venting
60 Venting
USC with venting
50
40 NGCC NG 6$/MBtu with Venting
120
110 Existing Nuclear
70 Venting
USC with venting
60
50 NGCC NG 6$/MBtu with Venting
40
30 Av IGCC with Capture
• US 2005 CO2 emissions 6 Billion stpy, 39% from Electricity, 36% from
coal (323 GW installed capacity)
• AEO 2006 BAU forecast for 2030 - today’s existing coal plants will be
66% of US Power CO2 emissions and 75% of all US coal CO2
emissions
• Which of today’s units are most likely to adopt CO2 capture under a
regulatory environment?
• Existing boilers > 300 MW and > 35 years old represent 184 GW. If
90% CO2 capture was applied to these units this would provide a 50%
reduction in coal power CO2 emissions
• Q. What is the cost of adding capture to these
existing plants and the cost and source of
replacement power?
540 1,400
420 1,100
400 1,050
360 950
Jun-98 Jun-99 Jun-00 Jun-01 Jun-02 Jun-03 Jun-04 Jun-05 Jun-06 Jun-07
IGCC
USC PC
IGCC
PSDF