Beruflich Dokumente
Kultur Dokumente
Arne Lislerud
Abstract--This paper is drawn from [our project reports, dealing R6sum6--Cet article est bask sur les rapports de quatre pro jets traitant
with: (1) hard rock tunnel boring; (2) drill-and-blast tunnelling-- les sujets suivants: (1) percement de tunnel dans les roches dures; (2)
prognosis; (3) drill-and-blast tunnelling--costs; and (4) a drillability pronostic des mkthodes tunnelibres par percement et par explosion;
and drilling rate index catalogue. The project reports are based on (3) co~ts des mbthodes tunnelibres par percement et par explosion; et
jobsite follow-up work o[ both bored and blasted tunnels. This paper (4) catalogue d'indexes de possibilitb de percement et de taux
summarizes some developments in T B M and cutter design, [actors d'avancbe de percement. Les rapports de projet sont basks sur le suivi
influencing the boring process and [actors that aI[ect tunnelling costs, des travaux sur site pour gtla ]ois des tunnels percbs et explosks. Ce
e.g. the increased productivity possible with TBMs. rapport rbsume quelques dbveloppements e]Iectuks sur les tunneliers,
sur la conception de dkcoupe, sur les [acteurs in[luenqant le procbdb
de perloration, et sur les [acteurs qui a[Iectent les co~ts de tunnelage
(comme un accroissement possible de la productivitb des tunneliers).
Tunnelling mid I 'nderground Space Technology, Voi. 3, No. 1, pp. 9-17, 1988. 0886-7798/8S $3,00 + .00
P ] i n w d in ( ;w ar Bill;fin. P e l g a m o n Plvss p h 9
Table 4. Rated rock mass and machine factors influencing T B M performance. the toughness (or lack ot IJriltlem's~)ot
~ertain rock tylWS.
Rock mass factors Machine factors
Machine Factors--
Rock mass jointing (k,) Thrust per cutter (M) T B M Performance
- - Type and continuity Cutter edge bluntness (b~)
- - Frequency Cutter spacing (,4) TBM performance is highly dependent
on machine design. Machine factors
- - Orientation Cutter diameter (d) that influence boring performance are
Rock porosity Torque capacity and RPM listed in Table 4.
Rock drillability (DRI) The machine's capacity for
handling large chips or Net Penetration
blocks The basic penetration in systematic-
ally jointed rock is shown in Fig. 3.
Stress in rock General solidity against blows
Net penetration is found by using the
and vibrations following formula:
Rock hardness/ Cutterhead curvature and i = it," k~ (mm/rev.)
abrasiveness (CLI) diameter (D) I = i" RPM • 60/1000 (m/h).
Backup equipment
The prognosis model for an earlier
project report (Norwegian Institute of
Technology 1983), did not combine
jointed and non-fractured rock in one
diagram (see Fig. 1). As a result, the
revised prognosis model is based on a
different concept, in which non-
fractured rock is easily included. The
influence of cutter spacing and cutter
bluntness also is included.
The 1987 project report model is
based on normalized penetration tests.
A typical test result in non-fractured
granite for a 15.5-in. cutter is shown in
Fig. 4.
The penetration test curve is normal-
ized to a power function:
i = (M/MI) ~' (mm/rev.)
M = thrust per cutter (kN)
M~ = "critical thrust" (the thrust
needed to bore 1.0 [mm/rev.])
b = slope of curve (b is an expression
for the chipping frequency).
Penetration parameters b and M~ are
dependent variables. A plot of b as a
function of M~ is shown in Fig. 5.
Likewise, a raw plot of M~ vs joint factor
k~ is shown in Fig. 6.
The work of finding the relationships
between b , A, d, DRI and k~ to M~ and b
in mathematical terms will be completed
in 1987.
Figure 1. Correction factor k~ as a f u n c t i o n of fissure class and angle between tunnel It should be noted that cutter
axis and planes of weakness. bluntness has its greatest effect on the
slope b, i.e. chipping frequency.
Rock Drillability The Sz0 value includes the effect of
rock brittleness and, therefore, grain size Medium-Pressure Water Jets
The ease with which rock can be and grain boundary strength. However, Recent boring tests with medium-
bored is measured by an indirect the effect of rock porosity is not pressure water jets (300-350 bar) in non-
method. The Drilling Rate Index (DRI) included in the test. fractured granite showed little or no
is a combination of the rock brittleness Recent follow-up work carried out in effect on boring performance. On the
value ($20) and Siever's miniature drill vesicular basalt on the Faroe Islands other hand, all of the water introduced
test (SJ). The test methods are described shows that porosity in the range 3-t2% by the water jets into the muck resulted
in the Drillability and Drilling Rate has a considerable effect on penetration in operating problems with the backup
Index Catalogue (Norwegian Institute rates and rock blastability. The bedrock equipment.
of Technology 1981). in Norway normally has little or no
The SJ value expresses rock surface porosity. Torque Demand
hardness. A useful correlation between The relationship between the compres- Required torque to rotate the cutter-
SJ and a calculated rock Vickers sive strength and the DRI is shown in head depends on:
Hardness from mineral content has Fig. 2 for 65 parallel tests grouped • Cutterhead diameter.
been found. T h e SJ value is very useful according to rock type. The plot shows • Number and position of cutters.
for determining the degree of rock that the compressive strength used for • Thrust per cutter.
weathering. rating drillability seems to underestimate • Cutter coefficient k.
U 100 ~ _ g n e i s s ~ ~.
~-. . P. h. y .l l i.t e I' ~" ic; :i ' t ' from the cutter shift reports determines
~lii ; : ;i!.;i i
20
!;
30
;:[i
i]
60
,
50 60
. ! l . ~ .,
70 80
.
90
I ShaIe
100
; i
. . . . . . . . . . . . . [ : ', :~-.~ Siltston, i --- the average cutter r i n g life a l o n g the
tunnel.
Drilling Rate Index,DRI Drilling Rate Index, DRI T h e expression used is:
[i
Figure 2. Relationship between Drilling Rate Index (DRI) and compressive strength
o~ (NTH), grouped according to rock type.
g h= (h/cutter)
=1
a i I I
ii l
JIIII
IlmlII
ImIIml
ImIml
iamm
Niinl
Hi = m a c h i n e hours for cutter No. i.
|IIIH
Haiti
IIIm
| I | Therefore, the average r o l l i n g distance
i li i I I Ni u ~ ~ i iniii ii ION ~ iiu i p - ~ n
per cutter is:
'- ~ ,ii ii~ ,~i ~, ." I ii~,~i i
i :,
:: jil;
~ !~ii i:;::"
~i :i. = "ir! ~ ! !! . . . ~ . 1 8 o -
RD = J 2rc R " RPM " 60 " Lh (m)
,, /r! , , ! Because cutter r i n g life Lh is an average
for the cutterhead, the effect of the ratio
g,, il. i:i:,-,;',, g r _ .1~ of center and g a u g e cutters to face
a!! 4"!! ,~
cutters has been included. T h i s ratio is
,, =,., -; ( . . .... the basis for the T B M d i a m e t e r
correction factor k~,.
Cutter c o n s u m p t i o n in m s is deter-
'" I~.~ ..... '~ L, ! : : m i n e d by six factors:
iJ~ , 7!! ,, ,"r ( 1) A m o u n t of wearable steel on discs.
(2) T i m e - d e p e n d e n t rock p o w d e r
ir . . abrasion on steel discs.
(3) R o c k hardness, w h i c h indirectly
~,, oo: determines where edge wear will take
"-, ,~-~ , ~.,.~ , ,'v"-
."4."
.. ~ ii ~ . . . - - ~ -
place, e.g. at the tip, sides or both.
i
-
_~..,,..,._,-
... "YT2!
.. : : _: _ ~' .m.
!: ; :: ~: ~ - (4) R o c k mass j o i n t i n g and rock
-
b o u n d a r y zones.
.,.......
(5) Cutterhead curvature and dia-
:::.. ti: ~,iiii i! '~ ,.~: '.~i i~; ; meter.
20 30 40 50 60 70 80
(6) Penetration rate ( m / h ) .
T h e Cutter Life I n d e x (CLI) includes
DPilling Rate Index, DRI both rock hardness and rock abrasiveness
i
on disc steel (see Fig. 8).
T h e prognosis for average cutter r i n g
Figure 3. Basic penetration ib in m m / rev. as a [unction of Drilling Rate Index (DRI), life in h o u r s is given by the f o l l o w i n g
average gross thrust per disc and cutter diameter. e q u a t i o n (see Fig. 9):
IOO
~ : :: -..~-'-,, :::
;:!:tii, P!?t:i!i
3 4 S
i~ 6 719 Io0
I I!1
I!~!
[qll
200
I:
[Ill
[i]
lit
I
3
I I I I I I I I I I I I
MI
Figure 5. Cutterhead characteristic curve.
-4-~-1- .-+H-
:- . . . . . . . . . . . . . . ~ ~ , ~ - - L -':J.............
l q I : : : : I ~ : I II v,i, r r-I , i-~'~-r=~;:=~r-
0.1 2 3 4 5 6 7 8 91.0 2 3 4 5
I I I I I I I I 1 I I i [ I
Joint Factor, k s
Figure 6. Raw plot o[ some M[ data as a [unction o[ join t [actor ks and cutter diameter•
- 6
====-::::::::::======:--------======--:,=:=::==,:~=i'"!
II IIIll I I I I I IIIHII I I I I I I I I I l l l I I I I I llr ~llllllII ~
main bearing failure.
II inllU
ii lllIl
IiiIflI
ilmg
IIHI
IIIII
BiB i I H I
IIIII I I I I
llgIll I I II
ii
II
II
i i i l l llIPf.dil
I I l l I I ~ I ~ l l I
I I i I W % . dIIlll
lllil
IIIP--
l ~ .liB I H I I
~IIlll l i I I l
I I W % dll I I I I I I I I l l
H I l l
IIIII
lllli
(m) Ground support work.
Illlll=lllIllllIIllllllI~--~-ll;~I~llIlllllllll=l Operations a - d above are (anne(ted
- 5 II liIll lllll llIII I I I I Ii I ~ - - i l l IP5~"~I111~IIIII I I I I I IIIII
ilmmuilllllllllllliii~,iiii ~. ~.biImil¢ llllIIIlllilli with the boring process itself, whereas
I I I I I I I lilil IIIII i I ~ ~,,,I, i I I I P P - ~,dd I I l l l II llllIlllIlllll
II lllllllllI UIUP~'~.,IIII I ~ d I I I I I I l
_-f:_-~ : t 2"I:_~[:2[: ~[ ~L'~"~Z"a_--- . , ~ i n i l U U l P ~ d
IlIlllllIIllllllI
IlNlllllIllll IIIII
e-k are related to the remaining
- 4 llnUllllllll nnlllp~ ¢i IIUmp~dllnlllnllllllIllllllIll tunnelling operations. Operation 1 and
t- inulIIIIIIllIIIII p~dl II iIi~c-,aiIIUIlllIIIIIllIIIIlllnII
_ ~ _~._~._a__~._ .L _ ~ "-"e''~: ~r- ~ ~'r-~--'r- - r ' " r " ~ : l l l I I I I I I I I I I I I l l l I I I m are not included in the machine
IIIIIII lllllUIal IIII II lllllIllIIIlllllllIIIIIllll
IIlIIIIIIIIIIIIIIIIIIIIIIIIIIIIILIII~IIUlIIIIIIIII utilization percentage, but rather are
- 3 IIl U l l IIIN I n l I III l l l m l l l ~lliIIIIII l U l l l llIll
HI
II
iIIII
IIIII
IIIII
IIIII
IIHI I
IIlll I
I
I
I I
i I
Ii I m
Ii I i
m i l i n
I i I i I I I I
II iI
II
IIIIIIIHIIIIII
IIIliIIIIIiIIl
included as additional time on the total
O I I i I I I I I I I l l l l l l l i I I i I I I I I I I I I I I I| IIIIIIIHIIIIII
project time-plan.
i I I I l IIl II I I llI l i II li I I I I I I
L
iiliii!iili!!ii!iiiiiiiiii|iiiiii
iiii,
HHIHIHHIIIIIIIIIIIIIIIIIIIIIHIIIIIIIIHIII
I IIIIIIIIIHIIIIIIIIIIIIHIIIIIIIIIHIIIIIIIHIII
A unit time for the listed operations
can be determined. These unit times
- 2 I I I lllIIIIIIIlll I ! l[ ]Ill
: f i l l] (h/kin) seem to vary little with regard to
4~ ;;~;I] ' I I i I I l [ I I I IllllIL]llll l [ ] [
i II i I~LLlLLlll !&-L4',!!l]!!li!i!i!!!l [ __tsAJ]
~I~ TBM diameter; rather, they vary with
~J I t[ll',;[il!i[ll
I I []l!i!illllll i i ------sharp cutters crew motivation and quality of jobsite
I IEIlilllllllll administration.
IIIN III111111 dull cutters
I IIIl!ll[llllll Table 5 provides an example of how
Illlltl][ll]lll I i ii_iiiiiiiii iiiiiiiiii iiiii to predict normal machine utilization
0,1
I }lllllltlllltl 4 I I ll]]]l]llllllIl[ll[lll IIIII through the use of unit operation time,
I 1 I i l i I I I given the following assumptions about
0,3 4 5 6 7 8 9 1,0 2,0 3 4 5
the tunnelling methods to be used:
I I I I I I I I I I I 1 Diameter of TBM 4.5 m
Joint Factor, ks Penetration rate 2.0 m / h
Cutter life 70 m ~
Figure 7. Envelope curves for the cutter constant C as a [unction of joint [actor k~, Boring stroke 1.5 m
cutter diameter and bluntness. Regrip time 5 min
Cutter change and
inspection time 40 min./cutter
L i mestone
Backup equipment 2 track.
Ca Icerous shale Trackless transport of muck is possible
and desirable for large-diameter TBMs,
Gr"een schist i.e. diameter > 7.3m. Martin and Wallis
Phyllite (1985) have described muck transport on
the Floyfjell twin-bore highway tunnels.
Mica schist
Mica gneiss
Boring vs Drill and Blast
Gr"ani te g n e i s s
In c o m p a r i n g boring with drill-and-
Amphibol. gneiss blast tunnelling in hard rock, each has
Quar"tz schist some specific advantages and dis-
Quar"tzite advantages. T o fully utilize the advan-
tages of each tunnelling method in
rqi te ,
tKondhje
uuart2 dtor'i tel construction planning, it is important
that the different methods be taken into
10 20 30 z¢0 50 60 70 80 90 100
account at an early stage (see the
Holandsfjord power plant example,
Cutter" Life Index CLI
below). Comparative advantages and
Figure 8. Cutter LiJe Index (CLI) Jar various rock types. disadvantages of the two methods are
listed in Table 6.
interest in i m p r o v i n g ring life by using longer period, depends on the net
carbide disc cutters. Unlike the case advance rate and the number of boring Tunnelling Costs
with steel disc cutters, carbide cutter hours during that period.
f a i l u r e f r e q u e n c i e s are i n f l u e n c e d Machine utilization is net boring It is difficult to write a short, general
immensely by utilized thrust. T o help time expressed in percent of total and interesting comparison of tunnel-
solve this problem, research and testing tunnelling time. Total tunnelling time ling costs. Each project is unique, with
of new steel alloys in discs are includes: specific considerations that must be
increasing. For discs to be used (a) Boring. taken into account.
successfully in hard and abrasive rock, (b) Regrip, including collaring (2- T h e Holandsfjord hydro power plant
the steel disc must be capable of 8 min. each time). project illustrates the different construc-
withstanding high cutter loads without (c) Inspection and change of cutters. tion, ownership and operating costs
c h i p p i n g , while at the same time (d) Service and maintenance of TBM that must be optimized in p l a n n i n g a
keeping the edge width as narrow as and backup equipment. major hydro project. 2
possible to enhance penetration. (e) Waiting for muck cars.
(f) Ventilation. Holandsfjord Hydro Power Plant
Machine Utilization--
(g) Installation of track (normally no Holandsfjord is the largest project of
waiting involved). the Svartisen Hydro Power Scheme,
Weekly Advance
(h) Maintenance of track. with an installation of 2 x 300 MW and
Gross advance rate, expressed in (i) Electrical installations. an average production of 2077 G W h / y r .
meters per week as an average for a (j) Travelling time, change of shift. T h e 7040-m-long headrace tunnel has
Additional downtime
- - Main bearing failure 65
- - Ground support in:
Granite and gneiss 5-20
Continuous spelling 30-80
Crushed zones per zone
Disadvantages: Disadvantages."
• Uneven tunnel contour, with • High capital costs (although the
loss of head in unlined hydro importance of capital costs can be
power, water and sewer reduced by leasing).
tunnels. • Long delivery time for new machines if
• Higher average ground suitable refurbished machines are not
support costs, especially for available.
poor jobsite client • Heavy equipment, time- and cost-
administration. consuming startup.
• Medium to low advance
rates.
.o :
< st. ¢ Adit Holandsfjord
Jobsite, roads, adit 17.5 20.8
F=87 m = o r
5820
2x6.1m TB
20~ 43590O
Tunnelling towards Storglomvatn 66.2 93.4
Ground support 23.2 7.5
Tunnel to pressure shaft, 29.7 29.7
(3(3 2X" . . . . . including ground support
STORGLOM" Gate installation 5.0
VATN ~ " g = 87m~