This weekly report details activities from June 3rd to March 12th conducting maintenance and repairs at a polyethelene plant in Ras Lanuf, Libya. Technicians surveyed the installation, checked components and software, mounted and tested fiber optic lines, debugged domain controllers after a long outage, uploaded tags from DCS controllers to graphics, configured control systems, and set up new operator stations. Minor issues addressed included a server motherboard problem and replacing cables. The customer signed off on the report.
Originalbeschreibung:
GG
Originaltitel
A08753 RAS LANUF SAT Activities Report 06 12 March 2013 En
This weekly report details activities from June 3rd to March 12th conducting maintenance and repairs at a polyethelene plant in Ras Lanuf, Libya. Technicians surveyed the installation, checked components and software, mounted and tested fiber optic lines, debugged domain controllers after a long outage, uploaded tags from DCS controllers to graphics, configured control systems, and set up new operator stations. Minor issues addressed included a server motherboard problem and replacing cables. The customer signed off on the report.
This weekly report details activities from June 3rd to March 12th conducting maintenance and repairs at a polyethelene plant in Ras Lanuf, Libya. Technicians surveyed the installation, checked components and software, mounted and tested fiber optic lines, debugged domain controllers after a long outage, uploaded tags from DCS controllers to graphics, configured control systems, and set up new operator stations. Minor issues addressed included a server motherboard problem and replacing cables. The customer signed off on the report.
Prepared by Dept. Date Language Revision Nr. Pages
Operation SSG 06/03/13 en 0 1 (1)
3BJT 202302 Weekly Report Mod. 006
CUSTOMER RAS LANUF OIL & GAS PROCESSING COMPANY
CUSTOMER ORDER 182 / 2010 (re-issued) PLANT POLIETHILENE SITE RAS LANUF (LIBYA) Activities description Technician Date Survey of the installation, check of the components already in service MALINVERNI A. 06/03/2013 and to be installed. Check of the system and application software. NAKHLI M. FO communication from Main Control Room to Harbour: spiders have MALINVERNI A. 07/03/2013 been mounted and connected to existing patch panels end testing of NAKHLI M.. the FO line has started. Testing activity of the F.O. line to Harbour completed successfully. MALINVERNI A. 08/03/2013 Debugging of the domain controllers DCAS1 & DCS2: the two Domain NAKHLI M. Controllers were turned off for long time (from Nov.2009 to May 2010) and an internal flag called “tombstone lifetime” was expired and no replication of the active directory data was possible (this may also lead to other problems reported in the punch list). Minor activities: modified operator workplace, checked Hardware Status of servers (connectivity server 1 gives error on Sata Cable B, this problem is probably due to the motherboard, KVM cable for DCAS2 not working properly and to be replaced). Equipment (200m FO cable, spiders and RJ cables) for connection of MALINVERNI A. 09/03/2013 OS5&6 to Compound Room laid down. NAKHLI M. Repair of ASDC2 (demoted to workstation and promoted again to Domain Controller) and testing of active directory functions. Uploaded tags from DCS Controllers to populate the control structure. Started checks and corrections on graphic displays. MALINVERNI A. 10/03/2013 Configuration of RTA board of CS1 and CS2 and Tag upload of NAKHLI M. Safeguard Nodes 71/72 and 81/82. Checks and corrections on graphic displays. MALINVERNI A. 11/03/2013 Screens and FX100 for operator stations 1,2,4 are were put in NAKHLI M. service. Fixed OS1 problem (not possible to see graphic displays). OS7 was mounted into the cabinet, connected to CS network and MALINVERNI A. 12/03/2013 spider and loaded with XP and 800xA software. NAKHLI M. Minor activities: screen saver and power saving options removed from clients, tuning of 800xA for OS6 (7). ABB Nome / Name Signature Date MALINVERNI A. NAKHLI M. Customer Company Name / Signature Date RAS LANUF OIL & GAS PROCESSING Ahmed Al zawawi COMPANY