Sie sind auf Seite 1von 16

MIAA vs. Olongapo Maintenance, G.R. 146184-85 Rules of Court, docketed as CA-G.R. SP Nos.

50087 and
50131.21
The antecedent facts are as follows:
Meanwhile, even as the cases were pending before the
OMSI and TCSI were among the five contractors of MIAA
CA, Branch 113 continued to hear the first TCSI case. On
which had janitorial and maintenance service contracts
February 1, 2001, the trial court rendered a Decision
covering various areas in the Ninoy Aquino International
declaring as null and void the negotiated contract award
Airport. Before their service contracts expired on October
to Goodline and the Resolution of the MIAA Board dated
31, 1998, the MIAA Board of Directors, through Antonio P.
October 2, 1998, which authorized Gana to negotiate the
Gana, then General Manager (GM) of MIAA, wrote OMSI
award of the service contract, and ordered the holding of
and TCSI informing them that their contracts would no
a public bidding on the janitorial service contract. Branch
longer be renewed after October 31, 1998.13
113 also ordered the writ of preliminary injunction in the
On September 28, 1998, TCSI, in a letter to Gana, case enforced until after a qualified bidder is
expressed its concern over the award of its concession determined.22
area to a new service contractor through a negotiated
In its Decision, the trial court said MIAA and Gana violated
contract. It said that to award TCSI’s contract by mere
TCSI’s right to equal protection and that the authority to
negotiation would violate its right to equal protection of
negotiate the MIAA Board granted to Gana was tainted
the law. TCSI thus suggested that a public bidding be
with grave abuse of discretion as Gana’s exercise of the
conducted and that the effectivity of its service contract
management’s prerogative to choose the awardee of a
be meanwhile extended until a winning bid is declared.
service contract was done arbitrarily. Gana, the RTC
A similar letter from OMSI to MIAA followed.14 added, should have conducted a public bidding, noting
that Gana erred in relying on the law and executive
In reply, MIAA wrote TCSI and OMSI reiterating its issuances he cited because those do not do away with the
disinclination to renew the latter’s contracts, adding that required public bidding, as held in National Food Authority
it was to the government’s advantage to instead just v. Court of Appeals.23
negotiate with other contractors. The MIAA said that
awarding a contract through negotiation was in Following the denial of Gana’s motion for reconsideration,
accordance with Section 9 of Executive Order No. (EO) MIAA and Gana appealed before the CA
903; Sec. 82 of Republic Act No. (RA) 8522, otherwise
Ruling: It is undisputed that the service contracts of OMSI
known as the General Appropriations Act for 1998; and
and TCSI expired on October 31, 1998 and were not
Sec. 417 of the Government Accounting and Auditing
extended by MIAA. Hence, all the rights and obligations
Manual (GAAM).15
arising from said contracts were extinguished on the last
Consequently, OMSI and TCSI instituted civil cases against day of the term. As a result, OMSI and TCSI had already
MIAA to forestall the termination of their contracts and lost their rights to render janitorial and maintenance
prevent MIAA from negotiating with other service services for MIAA starting November 1, 1998.
contractors.
Such being the case, the Court rules that the TROs and
Civil Case Nos. 98-1875 and 98-1885 writs of preliminary injunction issued in favor of OMSI and
TCSI are irregular and without legal basis for the following
On October 26, 1998, OMSI filed with the Pasay City RTC a reasons, to wit:
Complaint for Injunction and Damages with Prayer for
Issuance of a Temporary Restraining Order and/or Writ of (1) The November 18, 1998 injunctive writ in favor of
Preliminary Injunction16 against MIAA (OMSI case). OMSI in the OMSI case and the November 19, 1998
Docketed as Civil Case No. 98-1875, the case was raffled injunctive writ in favor of TCSI in the first TCSI case were
to Branch 119 of the court. in the nature of writs of mandatory preliminary injunction.
In Bautista v. Barcelona,46 we made clear that a
Two days after, TCSI filed Civil Case No. 98-1885 (first TCSI mandatory injunction is an extreme remedy and will be
case) for Prohibition, Mandamus and Damages with granted only on a showing that (a) the invasion of the right
Prayer for Temporary Restraining Order (TRO) and is material and substantial; (b) the right of the
Injunction17 against Gana and Goodline Staffers & Allied complainant is clear and unmistakable; and (c) there is an
Services, Inc. (Goodline), a service contractor that was urgent and paramount necessity for the writ to prevent
awarded the contract heretofore pertaining to TCSI. This serious damage.47 It is apparent that OMSI and TCSI have
was raffled to the RTC, Branch 113, Pasay City. The OMSI no more legal rights under the service contracts and,
and TCSI cases are now the consolidated cases G.R. Nos. therefore, they have not met the vital procedural
146184-85. requirement that they must have material and substantial
rights that have to be protected by courts.
Both Branches 113 and 119 granted TROs to OMSI and
TCSI.18 Subsequently, on November 18, 1998, Branch 119 (2) The service contracts of OMSI and TCSI may not be
granted a preliminary injunctive writ 19 in favor of OMSI. A extended through the instrumentality of an injunctive
day after, Branch 113 also granted a similar writ20 in favor writ. It is a doctrine firmly settled in this jurisdiction that
of TCSI. courts have no power to make a contract for the parties
nor can they construe contracts in such a manner as to
Without filing any motion for reconsideration, MIAA
change the terms of the contracts not contemplated by
assailed as void the issuance of the injunctive writs before
the parties.48Verily, under Art. 1308 of the Civil Code, the
the CA through petitions for certiorari under Rule 65 of the
contract between the parties is the law between them;
mutuality being an essential characteristic of contracts
giving rise to reciprocal obligations.49 And under Art. 1306 wrote then President Ferdinand Marcos and asked for
of the Code, the parties may establish stipulations assistance.17
mutually acceptable to them for as long as such are not
On July 21, 1981, President Marcos issued Letter of
contrary to law, morals, good customs, public order, or
Instructions No. 115518 addressed to the NDC, DBP, and
public policy. And where a determinate period for a
the Maritime Industry Authority.
contract’s effectivity and expiration has been mutually
agreed upon and duly stipulated, the lapse of such period On August 10, 1981,20 pursuant to Letter of Instructions
ends the contract’s effectivity and the parties cease to be No. 1155, Galleon's stockholders, represented by Cuenca,
bound by the contract. and NDC, through its then Chairman of the Board of
Directors, Roberto V. Ongpin (Ongpin) entered into a
It is undisputed that the service contracts were to
Memorandum of Agreement,21 where NDC and Galleon
terminate on October 31, 1998. Thus, by the lapse of such
undertook to prepare and sign a share purchase
date, where no contract extension had been mutually
agreement covering 100% of Galleon's equity for
agreed upon by the parties, the trial court cannot force the
₱46,740,755.00.22 The purchase price was to be paid after
parties nor substitute their mutual consent to a contract
five years from the execution of the share purchase
extension through an injunction.
agreement.23 The share purchase agreement also
Indeed, MIAA’s decision not to extend the service provided for the release of Sta. Ines, Cuenca, Tinio and
contracts of OMSI and TCSI is a valid exercise of Construction Development Corporation of the Philippines
management prerogative. Certainly, there is no law that from the personal counter-guarantees they issued in
prohibits management discretion, even if it be a DBP's favor under the Deed of Undertaking.
governmental agency or instrumentality or a government-
Acting as Galleon's guarantor, DBP paid off Galleon's debts
owned or controlled corporation, from extending or not
to its foreign bank creditor and, on January 25, 1982,
extending a service contract. Certainly, MIAA’s
pursuant to the Deed of Undertaking, Galleon executed a
management can determine, in the exercise of its sound
mortgage contract26 over seven of its vessels in favor of
discretion and the options available, given the factual and
DBP.
economic milieu prevailing, whether or not it is to its
interest to extend a service contract for janitorial and NDC took over Galleon's operations "even prior to the
maintenance services. signing of a share purchase agreement."27 However,
despite NDC's takeover, the share purchase agreement
From the foregoing premises, the RTCs in Civil Case Nos.
was never formally executed.28
98-1875 and 98-1885 have erred in issuing the assailed
writs of mandatory injunction. Hence, these writs must be Issue: WON the failure to execute the share purchase
nullified. agreement was brought about by NDC's delay in reviewing
the financial accounts submitted by Galleon's
DBP vs. Sta. Ines, G.R. 193068
stockholders.
Facts: National Galleon Shipping Corporation (Galleon),
Rulings: YES
"formerly known as Galleon Shipping Corporation, was
organized to operate a liner service between the When the "terms of a contract are clear and leave no
Philippines and its ... trading partners."8 Galleon's major doubt upon the intention of the contracting parties, the
stockholders were respondents Sta. Ines Melale Forest literal meaning of its stipulations shall control.
Products Corporation (Sta. Ines), Cuenca Investment
Corporation (Cuenca Investment), Universal Holdings It is not disputed that NDC and respondents Sta. Ines,
Corporation (Universal Holdings), Galleon's President Cuenca, Tinio, Cuenca Investment, and Universal Holdings
Rodolfo M. Cuenca (Cuenca), Manuel I. Tinio (Tinio), and executed a Memorandum of Agreement pursuant to the
the Philippine National Construction Corporation (PNCC).9 directives of Letter of Instructions No. 1155.

Galleon experienced financial difficulties and had to take Under the Memorandum of Agreement, NDC, as the
out several loans from different sources such as foreign Buyer, undertook to:
financial institutions, its shareholders (Sta. Ines, Cuenca
a) implement Letter of Instructions No. 1155 and acquire
Investment, Universal Holdings, Cuenca, and Tinio), and
100% of Galleon's shareholdings;
other entities "with whom it had ongoing commercial
relationships."10 b) assume actual control over Galleon's management and
operations prior to the execution of a formal share
DBP guaranteed Galleon's foreign loans. 11 In return,
purchase agreement and prior to the transfer to NDC of
Galleon and its stockholders Sta. Ines, Cuenca Investment,
Galleon's shareholdings;
Universal Holdings, Cuenca, and Tinio, executed a Deed of
Undertaking12 on October 10, 1979 and obligated c) designate five persons to sit in Galleon's Board of
themselves to guarantee DBP's potential liabilities.13 Directors;

To secure DBP's guarantee, Galleon undertook to secure a d) pay Galleon's stockholders the share purchase price
first mortgage on its five new vessels and two second- after five years from the date of the share purchase
hand vessels.14 However, despite the loans extended to it, agreement;
"[Galleon's] financial condition did not improve."15
e) issue each Galleon stockholder a negotiable promissory
Cuenca, as Galleon's president, wrote to the members of note with maturity on the date of the fifth annual
the Cabinet Standing Committee "for the consideration of anniversary of the share purchase agreement;
a policy decision to support a liner service." 16 Cuenca also
f) verify Galleon's special warranty on its liabilities and NDC asserts that the Memorandum of Agreement was
obligations by conducting an audit; and only a preliminary agreement between Galleon,
represented by Cuenca, and NDC, represented by Ongpin,
g) consider for priority in the repayment of accounts,
for the intended purchase of Galleon's equity pursuant to
Galleon's valid and duly authorized liabilities which are the
Letter of Instructions No. 1155.
subject of meritorious lawsuit or which have been
arranged and guaranteed by Cuenca. While respondents, NDC's assertion that the Memorandum of Agreement was
Galleon's stockholders, as the Sellers, undertook to: merely a preliminary agreement that was separate and
distinct from the share purchase agreement, finds support
a) implement Letter of Instructions No. 1155 by allowing
in clause 7 of the Memorandum of Agreement.
NDC to purchase 100% of their shareholdings;
Under clause 7 of the Memorandum of Agreement, NDC
b) consent for NDC to assume actual control over
and respondents agreed to include in the still-to-be-
Galleon's management and operations prior to the
executed share purchase agreement, provisions on: (a)
execution of a formal share purchase agreement and prior
standard warranties, including warranties on the accuracy
to the transfer to NDC of Galleon's shareholdings;
of Galleon's financials, disclosure of liabilities, etc; (b) the
c) elect NDC's designated five persons to Galleon's Board retention of Galleon's representatives in Galleon's board
of Directors; of directors prior to the payment of the share purchase
price; (c) the release of respondents from the counter-
d) warrant that ₱46,740,755.00 had been actually paid to guarantees they made in favor of DBP and other financial
Galleon, representing payment of 46,740,755 common institutions in connection with Galleon's various credit
shares to Galleon; accommodations; and (d) arbitration as a means of
settling disputes and differences of opinion regarding the
e) deliver to NDC, upon signing of the share purchase
stock purchase agreement.
agreement, 10,000,000 common shares of Galleon, duly
and validly endorsed for transfer, free from any and all Taking the provisions of the Memorandum of Agreement
liens and encumbrances whatsoever; and as a whole, it is clear that while there was an intention to
follow the directives of Letter of Instructions No. 1155, the
f) make special warranties under clause 8.
transfer of shares from respondents to NDC was to be
As parties to the Memorandum of Agreement, NDC and effected only with the execution of the share purchase
respondents jointly undertook to: agreement, the terms and conditions of which were laid
out in the Memorandum of Agreement.
a) immediately implement Letter of Instructions No. 1155;
NDC and the respondents undertook to prepare and sign
b) endeavor to prepare and sign a share purchase a share purchase agreement over 100% of respondents'
agreement covering 100% of Galleon's shareholdings not shares in Galleon not more than sixty days after the
more than 60 days after the signing of the Memorandum signing of the Memorandum of Agreement
of Agreement; and
The execution of a share purchase agreement was a
c) incorporate the conditions listed down in clause 7 in the condition precedent to the transfer of Galleon's shares to
share purchase agreement. NDC. However, the Court of Appeals found that the NDC
The law is categorical that "various stipulations of a prevented its execution by deliberately delaying its review
contract shall be interpreted together, attributing to the of Galleon's financial accounts.
doubtful ones that sense which may result from all of The Regional Trial Court likewise found that respondent
them taken jointly."74 Fernandez v. Court of Cuenca, as Galleon's representative, initiated moves for
Appeals75further emphasizes that " [t]he important task in the preparation and execution of the share purchase
contract interpretation is always the ascertainment of the agreement and NDC's takeover of Galleon.80 Nonetheless,
intention of the contracting parties and that task is of despite Cuenca's efforts, the share purchase agreement
course to be discharged by looking to the words they used was never formally executed.
to project that intention in their contract, all the words
not just a particular word or two, and words in context not NDC denies that it caused the delay in the execution of the
words standing alone."76 share purchase agreement and argues that it was Cuenca
who caused the delay for insisting on the payment first of
The Court of Appeals found that the Memorandum of the advances made in Galleon's favor before executing the
Agreement between NDC and Galleon was a perfected share purchase agreement and relinquishing control over
contract for NDC to purchase 100% of Galleon's Galleon.82
shareholdings. However, a careful reading of the
Memorandum of Agreement shows that what the parties NDC's bare denials cannot succeed in light of the
agreed to was the execution of a share purchase preponderance of evidence submitted by respondents.
agreement to effect the transfer of 100% of Galleon's
On April 26, 1982, Antonio L. Carpio, NDC's General
shareholdings to NDC, as seen in clause 3.
Manager,85 sent Ongpin a Memorandum,86 where Carpio
The second paragraph of clause 4 likewise makes the acknowledged reviewing Galleon's outstanding accounts
execution of a share purchase agreement a condition submitted by Cuenca.87 This supports Cuenca's statement
before the purchase price can be paid to respondents, that they submitted a statement of Galleon's outstanding
since the payment of the purchase price becomes due accounts for NDC's review, as per Ongpin's request, a fact
only after five years from the date of execution of the not denied by NDC.
share purchase agreement.
Upon receiving Galleon's outstanding accounts, NDC and Adworld alleged that it is the owner of a 75 ft. x 60 ft.
Sta. Ines, Cuenca, Tinio, Cuenca Investment and Universal billboard structure, which was misaligned and its
Holdings should have initiated the execution of the share foundation impaired when, on August 11, 2003, the
purchase agreement. However, the share purchase adjacent billboard structure owned by Transworld and
agreement was never executed, through no fault of used by Comark collapsed and crashed against it.
Galleon's stockholders. Resultantly, Adworld sent Transworld and Comark a letter
demanding payment for the repairs of its billboard as well
In clause 4 of the Memorandum of Agreement, NDC as the
asloss of rental income. On August 29, 2003, Transworld
buyer was to verify the warranty of the Galleon
sent its reply, admitting the damage caused by its
shareholders that ₱46,740,755.00 was paid for Ga1leon's
billboard structure on Adworld’s billboard, but
46,740,755 common shares with par value of ₱1.00 per
nevertheless, refused and failed to pay the amounts
share. The results of the verification would have
demanded by Adworld. As Adworld’s final demand letter
determined the final purchase price to be paid to the
also went unheeded, it was constrained to file the instant
Galleon shareholders. Nonetheless, despite the
complaint. In its Answer with Counterclaim, Transworld
verification still to be done, both parties agreed to execute
averred that the collapse of its billboard structure was due
the share purchase agreement as soon as possible but not
to extraordinarily strong winds that occurred instantly and
more than sixty days from the signing of the
unexpectedly, and maintained that the damage caused to
Memorandum of Agreement.
Adworld’s billboard structure was hardly noticeable.
We uphold the Court of Appeals' finding that the failure to Transworld likewise filed a Third-Party Complaint against
execute the share purchase agreement was brought about Ruks, the company which built the collapsed billboard
by NDC's delay in reviewing the financial accounts structure in the former’s favor.1âwphi1 It was alleged
submitted by Galleon's stockholders. The Memorandum therein that the structure constructed by Ruks had a weak
of Agreement was executed on August 10, 1981, giving the and poor foundation not suited for billboards, thus, prone
parties no more than sixty days or up to October 9, 1981, to collapse, and as such, Ruks should ultimately be held
to prepare and sign the share purchase agreement. liable for the damages caused to Adworld’s billboard
However, it was only on April 26, 1982, or more than eight structure.7
months after the Memorandum of Agreement was signed,
For its part, Comark denied liability for the damages
did NDC's General Director submit his recommendation
caused to Adworld’s billboard structure, maintaining that
on Galleon's outstanding account. Even then, there was
it does not have any interest on Transworld’s collapsed
no clear intention to execute a share purchase agreement
billboard structure as it only contracted the use of the
as compliance with the Memorandum of Agreement.
same. In this relation, Comark prayed for exemplary
Article 1186 of the Civil Code is categorical that a
damages from Transworld for unreasonably includingit as
"condition shall be deemed fulfilled when the obligor
a party-defendant in the complaint.8
voluntarily prevents its fulfilment." Considering NDC's
delay, the execution of the share purchase agreement Lastly, Ruks admitted that it entered into a contract with
should be considered fulfilled with NDC as the new owner Transworld for the construction of the latter’s billboard
of 100% of Galleon's shares of stocks. structure, but denied liability for the damages caused by
its collapse. It contended that when Transworld hired its
The due execution of the share purchase agreement is
services, there was already an existing foundation for the
further bolstered by Article 1198(4) of the Civil Code,
billboard and that it merely finished the structure
which states that the debtor loses the right to make use of
according to the terms and conditions of its contract with
the period when a condition is violated, making the
the latter.9
obligation immediately demandable:
Issue: Whether or not the CA correctly affirmed the ruling
Article 1198. The debtor shall lose every right to make use
of the RTC declaring Ruks jointly and severally liable with
of the period:
Transworld for damages sustained by Adworld.
(1) When after the obligation has been contracted, he
Ruling: Both Transworld and Ruks committed acts
becomes insolvent, unless he gives a guaranty or security
resulting in the collapse of the former’s billboard, which in
for the debt;
turn, caused damage to the adjacent billboard of Adworld.
(2) When he does not furnish to the creditor the
Jurisprudence defines negligence as the omission to do
guaranties or securities which he has promised;
something which a reasonable man, guided by those
(3) When by his own acts he has impaired said guaranties considerations which ordinarily regulate the conduct of
or securities after their establishment, and when through human affairs, would do, or the doing of something which
a fortuitous event they disappear, unless he immediately a prudent and reasonable man would not do.27 It is the
gives new ones equally satisfactory; failure to observe for the protection of the interest of
another person that degree of care, precaution, and
(4) When the debtor violates any undertaking, in vigilance which the circumstances justly demand,
consideration of which the creditor agreed to the period; whereby such other person suffers injury.28
(5) When the debtor attempts to abscond. In this case, the CA correctly affirmed the RTC’s finding
that Transworld’s initial construction of its billboard’s
lower structure without the proper foundation, and that
Ruks Consult vs. Adworld Sign of Ruks’s finishing its upper structure and just merely
assuming that Transworld would reinforce the weak
The Facts foundation are the two (2) successive acts which were the
direct and proximate cause of the damages sustained by and the delivery of the transfer certificate of title. PEPI
Adworld. Worse, both Transworld and Ruks were fully claimed that the title was still with the Philippine
aware that the foundation for the former’s billboard was National Bank (PNB) and could not be released due to
weak; yet, neither of them took any positive step to economic crisis. Sanvictores followed up with PEPI but
reinforce the same. They merely relied on each other’s the latter did not communicate with Sanvictores for a
word that repairs would be done to such foundation, but period of 4 years. Sanvictores then filed a complaint for
none was done at all. Clearly, the foregoing circumstances rescission of the contract to sell, refund of payment,
show that both Transworld and Ruks are guilty of damages, and attorney’s fees against PEPI and AFPRSBS
negligence in the construction of the former’s billboard, before the HLURB. AFPRSBS countered that it was not
and perforce, should be held liable for its collapse and the the owner and developer of Village East Executive Homes
resulting damage to Adworld’s billboard structure. As joint but PEPI, that PEPI alone was the seller, and that the
tortfeasors, therefore, they are solidarily liable to signatory to the contract, Norma Espina, was neither the
Adworld. Verily, "[j]oint tortfeasors are those who treasurer nor the authorized representative of AFPRSBS
command, instigate, promote, encourage, advise, but the Treasurer of PEPI. The HLURB Arbiter rendered a
countenance, cooperate in, aid or abet the commission of decision in favor of Sanvictores and ordered PEPI and
a tort, or approve of it after it is done, if done for their AFPRSBS to pay jointly and severally the complainant. On
benefit. They are also referred to as those who act appeal of PEPI and AFPRSBS, the HLURB Board affirmed
together in committing wrong or whose acts, if the decision of the Arbiter. The OP upheld the decision of
independent of each other, unite in causing a single injury. the HLURB Board, holding that PEPI and AFPRSBS should
Under Article 219429 of the Civil Code, joint tortfeasors are indeed be jointly and severally liable because PEPI and
solidarily liable for the resulting damage. In other words, AFPRSBS were referred to singly as the seller in the
joint tortfeasors are each liable as principals, to the same contract and there were no delineations whatsoever as
extent and in the same manner as if they had performed to their rights and obligations. AFPRSBS filed a petition
the wrongful act themselves."30 The Court’s for review before the CA. The appellate court merely
pronouncement in People v. Velasco 31 is instructive on affirmed the decision of the OP and echoed the view that
this matter, to wit:32 the two liable entities ought to be jointly and severally
liable as they came to the contracting table with the
Where several causes producing an injury are concurrent
intention to be bound jointly and severally. The CA
and each is an efficient cause without which the injury
concluded that the nature of the obligation of PEPI and
would not have happened, the injury may be attributed to
AFPRSBS under the subject contract was solidary
all or any of the causes and recovery may be had against
pursuant to Article 1207 of the Civil Code.
any or all of the responsible persons although under the
circumstances of the case, it may appear that one of them Issue: Whether or not petitioner AFPRSBS is jointly and
was more culpable, and that the duty owed by them to the severally liable with PEPI to Sanvictore
injured person was not same. No actor's negligence ceases
Ruling:
to be a proximate cause merely because it does not
exceed the negligence of other actors. Each wrongdoer is Yes. In Spouses Berot v. Siapno, the Court defined solidary
responsible for the entire result and is liable as though his obligation as one in which each of the debtors is liable for
acts were the sole cause of the injury. the entire obligation, and each of the creditors is entitled
to demand the satisfaction of the whole obligation from
There is no contribution between joint [tortfeasors]
any or all of the debtors. On the other hand, a joint
whose liability is solidary since both of them are liable for
obligation is one in which each debtor is liable only for a
the total damage.1âwphi1 Where the concurrent or
proportionate part of the debt, and the creditor is entitled
successive negligent acts or omissions of two or more
to demand only a proportionate part of the credit from
persons, although acting independently, are in
each debtor.
combination the direct and proximate cause of a single
injury to a third person, it is impossible to determine in The well-entrenched rule is that solidary obligations
what proportion each contributed to the injury and either cannot be inferred lightly. They must be positively and
of them is responsible for the whole injury. clearly expressed. Article 1207 of the Civil Code does not
presume solidary liability unless the obligation expressly
AFPRSBS vs. Sanvictores, G.R. 207586, 2016
so states or the law or the nature of the obligation
Facts requires solidarity.
Sometime in 1994, PEPI, formerly Antipolo Properties,
In the case at bar, there is no doubt that the nature of the
Inc., offered to Eduardo Sanvictores for sale on
obligation of PEPI and AFPRSBS under the subject contract
installment basis a parcel of land in Village East Executive
to sell was solidary. In the said contract, PEPI and AFPRSBS
Homes designated as Lot 5, Block 64, Phase II, situated in
were expressly referred to as the seller while Sanvictores
Tayuman, Pantok, Binangonan, Rizal. Sanvictores paid
was referred to as the buyer. The contract to sell did not
the required downpayment. A Contract to Sell was
state sellers but seller. This could only mean that PEPI and
executed by and between PEPI and AFP Retirement and
AFPRSBS were considered as one seller in the contract.
Separation Benefits System (AFPRSBS), as the seller, and
Sanvictores, as the buyer. In 1999, Sanvictores paid the There was no delineation as to their rights and obligations.
full purchase price. Despite full payment, PEPI and Also, the signatories were Espina, representing PEPI, and
AFPRSBS failed to execute the corresponding deed of Mena, representing AFPRSBS. The signatures of Espina
absolute sale on the subject property and deliver the and Mena were affixed again in the last portion of the
corresponding title thereto. In 2000, Sanvictores Deed of Restrictions under the word owner. AFPRSBS
demanded from PEPI the execution of the deed of sale repeatedly argues that the contract was not signed by any
of its authorized representative. Conveniently, however, it demand, whereby such other person suffers injury."
remained silent as to Mena. Verily, foreseeability is the fundamental test of
negligence. It is the omission to do something which a
It never denied that Mena was its representative. AFPRSBS
reasonable man, guided by those considerations which
is estopped from denying Mena’s authority to represent
ordinarily regulate the conduct of human affairs, would
it. It is quite obvious that AFPRSBS clothed Mena with
do, or the doing of something which a prudent and
apparent authority to act on its behalf in the execution of
reasonable man would not do.
the contract to sell.
Under Article 2180 of the New Civil Code, employers are
There is estoppel when the principal has clothed the agent
liable for the damages caused by their employees acting
with indicia of authority as to lead a reasonably prudent
within the scope of their assigned tasks. Once negligence
person to believe that the agent actually has such
on the part of the employee is established, a presumption
authority. A corporation may be held in estoppel from
instantly arises that the employer was remiss in the
denying as against innocent third persons the authority of
selection and/or supervision of the negligent employee.
its officers or agents who have been clothed by it with
To avoid liability for the quasi-delict committed by its
ostensible or apparent authority.
employee, it is incumbent upon the employer to rebut this
R Transport vs. YU, G.R. 174161 presumption by presenting adequate and convincing
proof that it exercised the care and diligence of a good
Facts: Loreta, after having alighted from a passenger bus, father of a family in the selection and supervision of its
was hit and run over by a bus driven by Gimena, who was employees.
then employed by petitioner R Transport Corporation.
Loreta was immediately rushed to the hospital where she Unfortunately, however, the records of this case are
was pronounced dead on arrival. As testified by the police bereft of any proof showing the exercise by petitioner of
officer on duty at the time of the incident and indicated in the required diligence. As aptly observed by the CA, no
the Autopsy Report, the deceased’s clothes were ripped evidence of whatever nature was ever presented
off from her body, her brain even spewed out from her depicting petitioner’s due diligence in the selection and
skull and spilled over the road. The bus driven by Gimena supervision of its driver, Gimena, despite several
bumped the deceased in a loading and unloading area of opportunities to do so. In fact, in its petition, apart from
a commercial center. denying the negligence of its employee and imputing the
same to the bus from which the victim alighted, petitioner
The husband of the deceased, respondent Luisito, filed a merely reiterates its argument that since it is not the
Complaint for damages before the RTC against petitioner registered owner of the bus which bumped the victim, it
R Transport, Gimena, and Metro Manila Transport cannot be held liable for the damage caused by the same.
Corporation (MMTC) for the death of his wife. Nowhere was it even remotely alleged that petitioner had
exercised the required diligence in the selection and
MMTC denied its liability reasoning that it is merely the
supervision of its employee. Because of this failure,
registered owner of the bus involved in the incident, the
petitioner cannot now avoid liability for the quasi-delict
actual owner, being petitioner R Transport. Since it was
committed by its negligent employee.
not actually operating the bus which killed respondent’s
wife, nor was it the employer of the driver thereof, MMTC Sps. Ibanez vs. James, G.R. 194272
alleged that the complaint against it should be dismissed.
For its part, petitioner R Transport alleged that Facts: Sometime in October 1996, spouses Amado and
respondent had no cause of action against it for it had Esther Ibañez (spouses Ibañez) borrowed from Francisco
exercised due diligence in the selection and supervision of E. Muñoz, Sr. (Francisco), Consuelo Estrada (Consuelo) and
its employees and drivers and that its buses are in good Ma. Consuelo E. Muñoz (Ma. Consuelo) the amount of
condition. Meanwhile, the driver Gimena was declared in ₱1,300,000, payable in three months, with interest at the
default for his failure to file an answer to the complaint. rate of 3% a month.

After trial on the merits, the trial court rendered judgment On October 14, 1996, the spouses Ibanez issued a
in favor of respondent Luisito ruling that petitioner R Promissory Note binding themselves jointly and severally.
Transport failed to prove that it exercised the diligence
As security, on October 1 7, 1996, the spouses Ibañez
required of a good father of a family in the selection and
executed a Deed of Real Estate Mortgage. The mortgage
supervision of its driver. The RTC ordered defendants R
contained the same terms as the promissory note. It
Transport and Metro Manila Transport Corporation
further stipulated that Ma. Consuelo and Consuelo shall
(MMTC) to be primarily and solidarily liable and defendant
have the right to immediately foreclose the mortgage
Gimena subsidiarily liable to plaintiff Luisito. The CA
upon the happening of the following events: (1) filing by
affirmed the Decision of the RTC with modification that
the mortgagor of any petition for insolvency or suspension
defendant Antonio Gimena is made solidarily liable for the
of payment; and/or (2) failure of the mortgagor to
damages caused to respondent.
perform or comply with any covenant, agreement, term or
ISSUE: Is the petitioner liable for the damages caused by condition of the mortgage.
its employee?
On September 23, 1997, alleging that the conditions of the
RULING: The petitioner is liable for the mortgage have been violated since November 17, 1996
damages caused by its employee. Negligence has and that all check payments were dishonored by the
been defined as "the failure to observe for the protection drawee, Ma. Consuelo and Consuelo applied for
of the interests of another person that degree of care, foreclosure of the real estate mortgage. Spouses Ibañez
precaution, and vigilance which the circumstances justly filed in the RTC of Manila a Complaint for injunction and
damages with prayers for writ of preliminary injunction Consuelo as the defendants they covenanted to pay.
and temporary restraining order. There is nothing in the Hatol, and the Amended
Compromise Agreement it is based on, which shows a
On June 11, 2002, the parties filed a Joint Motion for
declaration that the obligation created was solidary.
Approval of Amended Compromise Agreement which was
granted and adopted as “hatol”. However, the defendants In any case, solidary obligations cannot be inferred lightly.
failed to comply with the agreement and during the period They must be positively and clearly expressed. Articles
to do so Francisco died. His heirs then substituted him. 1207 and 1208 of the Civil Code provide:

Aggrieved by the Regional Trial Court order, the heirs of Art. 1207. The concurrence of two or more creditors or of
Francisco, identified as Maria C. Muñoz, Angelina M. two or more debtors in one and the same obligation does
Crocker and Maria Elena M. Webster and represented by not imply that each one of the former has a right to
James Harper, filed before the CA a Petition for demand, or that each one of the latter is bound to render,
Certiorari under Rule 65 of the Revised Rules of Court. entire compliance with the prestations. There is a solidary
They assailed the Orders dated August 11, 2006 and liability only when the obligation expressly so states, or
February 20, 2007 of the trial court and clarified that when the law or the nature of the obligation requires
contrary to the findings of the trial court, they are pushing solidarity.
for the execution of the Amended Compromise
Art. 1208. If from the law, or the nature or the wording of
Agreement. The heirs are of the view that since the
the obligations to which the preceding article refers the
spouses Ibañez have not complied with any of the
contrary does not appear, the credit or debt shall be
foregoing stipulations, the December 16, 1997 status quo
presumed to be divided into as many equal shares as there
order of the trial court should already be lifted. They
are creditors or debtors, the credits or debts being
likewise argue that the trial court gravely and seriously
considered distinct from one another, subject to the Rules
erred when it disregarded Francisco an
of Court governing the multiplicity of suits.
The CA ruled that the Amended Complaint and the Hatol
In this case, given that solidarity could not be inferred
identified Francisco, Ma. Consuelo and Consuelo as the
from the agreement, the presumption under the law
creditors and the parties who were supposed to receive
applies-the obligation is joint.
the proceeds of the Amended Compromise Agreement.
Since the Deed of Assignment was executed only in favor As defined in Article 1208, a joint obligation is one where
of Ma. Consuelo and Consuelo, the loan obligation of the there is a concurrence of several creditors, or of several
spouses Ibañez to Francisco remained unsettled. The heirs debtors, or of several debtors, or of several creditors and
of Francisco thus retain the right to invoke paragraph 2.5 debtors, by virtue of which each of the creditors has a right
of the Compromise Agreement which provides for the to demand, and each of the debtors is bound to render
lifting of the trial court’s status quo order. The CA compliance with his proportionate part of the prestation
disagreed that there was no valid substitution of parties which constitutes the object of the obligation. Each debtor
and noted from the records that the RTC was notified of answers only for a part of the whole liability and to each
Francisco’s death on June 29, 2006. obligee belongs only a part of the correlative rights as it is
only in solidary obligations that payment made to any one
Issues: Whether or not the obligation created in the
of the solidary creditors extinguishes the entire obligation.
amended compromise agreement and hatol is solidary
This means that Francisco, Ma. Consuelo and Consuelo are
thus payment made to Ma. Consuelo and Consuelo
each entitled to equal shares in the ₱3,000,000 agreed
discharged the obligation with respect to Francisco.
upon in the Amended Compromise Agreement and that
Rulings: No. The Supreme Court ruled in the negative. A payment to Consuelo and Ma. Consuelo will not have the
compromise agreement is a contract whereby the parties, effect of discharging the obligation with respect to
make reciprocal concessions to avoid a litigation or put an Francisco.
end to one already commenced. In a compromise, the
Government vs. CFI G.R. L-32162
parties adjust their difficulties in the manner they have
agreed upon, disregarding the possible gain in litigation Facts: In 1964, respondent-appellee V.D. Isip, Sons &
and keeping in mind that such gain is balanced by the Associates represented by Vicente David Isip entered into
danger of losing. It encompasses the objects stated, a contract with the City of Pasay represented by then
although it may include other objects by necessary Mayor Pablo Cuneta for the construction of a new Pasay
implication. It is binding on the contractual parties, being City Hall for the contract price of P4.9 million. Isip
expressly acknowledged as a juridical agreement between proceeded with the construction and accomplished the
them, and has the effect and authority of res judicata. amount of work equivalent to P1.7 million. Pasay paid only
the total amount of P1.1 million, leaving a balance of
Here, the spouses Ibañez agreed to pay Francisco, Ma.
P613,000. Pasay failed to remit the amount, so Isip filed a
Consuelo and Consuelo the total amount of ₱3,000,000,
case for specific performance with damages before CFI
with the initial payment of ₱2,000,000 to be sourced from
Manila. The parties arrived at a draft amicable agreement
the proceeds of a GSIS loan and secured by the spouses
wherein it was stated that Pasay will remit P613,000 to
Ibanez while the remaining balance of ₱l,000,000 to be
Isip and that Isip will start the construction work
paid one year from the date of the Amended Compromise
corresponding to the next stage. The Municipal Board
Agreement.
enacted an ordinance which approved the Compromise
As correctly identified by the CA, the Amended Agreement. CFI approved the compromise agreement and
Compromise Agreement clearly refers to the spouses subsequently issued a writ of execution. An application for
Ibañez as plaintiffs and Francisco, Consuelo and Ma. and notice of garnishment were made and effected upon
Pasay's funds with the PNB. Pasay filed a motion to quash deposited with the Philippine National Bank which
the writ of execution, alleging that the Sheriff has no eventually was delivered to the respondent-appellee.
power to levy or garnish on execution the general funds,
RS Tomas Inc, vs. Rizal Cement, G.R. 173155
specially the trust funds, of Pasay City. CFI denied the
motion and ordered the enforcement of garnishment. Facts: On December 28, 1990, respondent and petitioner
Hence, Pasay filed a petition for review before the SC. entered into a Contract[5] for the supply of labor,
materials, and technical supervision of the following
Issue: WON Respondent can ask for rescission and enforce
projects:
the compromise agreement.
1. J.O. #P-90-212 Wiring and installation of primary and
Ruling: The two purposes of a compromise agreement are
secondary lines system.
enunciated in Article 2028 of the New Civil Code, to wit:
2. J.O. #P-90-213 Supply and installation of primary
A. 2028. A compromise is a contract where by the
protection and disconnecting switch.
parties,by making reciprocal concessions, avoid a litigation
or put an end to one already commenced. 3. J.O. #P-90-214 Rewinding and conversion of one (1)
unit 3125 KVA, 34.5 KV/2.4 KV, 3 Transformer to 4000
The first purpose — "to avoid a litigation" — occurs when
KVA, 34.5 KV/480V, 3 Delta Primary, Wye with neutral
there is a threat of an impending litigation. At this point,
secondary.[6]
no case has yet reached the courts. The moment a case
has been filed in court then the second purpose — "to put Petitioner agreed to perform the above-mentioned job
an end to one already commenced" — applies. orders. Specifically, it undertook to supply the labor,
equipment, supervision, and materials as specified in the
In the herein case, We are concerned with the second
detailed scope of work.[7] For its part, respondent agreed
purpose. The latter purpose is given effect in Article 2037
to pay the total sum of P2,944,000.00 in consideration of
of the New Civil Code which reads:
the performance of the job orders. Petitioner undertook
Article 2037. A compromise has upon the parties the to complete the projects within one hundred twenty (120)
effect and authority of res judicata; but there shall be no days from the effectivity of the contract.[8] It was agreed
execution except in compliance with a judicial upon that petitioner would be liable to respondent for
compromise. liquidated damages in the amount of P29,440.00 per day
of delay in the completion of the projects which shall be
A compromise agreement not contrary to law, public
limited to 10% of the project cost.[9] To secure the full and
order, public policy, morals or good customs is a valid
faithful performance of all its obligations and
contract which is the law between the parties themselves
responsibilities under the contract, petitioner obtained
(Municipal Board of Cabanatuan City vs. Samahang
from Times Surety & Insurance Co. Inc. (Times Insurance)
Magsasaka, Inc., 62 SCRA 435). A judgment on a
a performance bond[10]in an amount equivalent to fifty
compromise is a final and executory (Samonte vs.
percent (50%) of the contract price or P1,458,618.18.
Samonte, 64 SCRA 524). It is immediately executory
Pursuant to the terms of the contract, respondent made
(Pamintuan vs. Muños et al., L-26331, 22 SCRA 1109
an initial payment of P1,458,618.18 on January 8, 1991.[11]
[March 15, 1968]) in the absence of a motion to set the
same aside on the ground of fraud, mistake or duress In a letter[12] dated March 9, 1991, petitioner requested
(Cadano vs. Cadano L-34998, 49 SCRA 33 [January 11, for an extension of seventy-five (75) days within which to
1973]). complete the projects because of the need to import some
of the materials needed. In the same letter, it also asked
In fact in the herein case before Us, execution has already
for a price adjustment of P255,000.00 to cover the higher
been issued. Considering this in the light of Article 2041 of
cost of materials.[13] In another letter[14] dated March 27,
the New Civil Code, to wit:
1991, petitioner requested for another 75 days extension
Art. 2041. If one of the parties fails or refuses to abide by for the completion of the transformer portion of the
the compromise, the other party may either enforce the projects for failure of its supplier to deliver the materials.
compromise or regard it as rescinded and insist upon his
On June 14, 1991,[15] petitioner manifested its desire to
original demand.,
complete the project as soon as possible to prevent
it is obvious that the respondent-appellee did not only further losses and maintain goodwill between the
succeed in enforcing the compromise but said plaintiff- companies. Petitioner requested for respondents
appellee likewise wants to rescind the said compromise. It assistance by facilitating the acquisition of materials and
is clear from the language of the law, specifically Article supplies needed to complete J.O. #P-90-212 and J.O. #P-
2041 of the New Civil Code that one of the parties to a 90-213 by directly paying the suppliers. It further sought
compromise has two options: 1) to enforce the that it be allowed to back out from J.O. #P-90-214 covering
compromise; or 2) to rescind the same and insist upon his the rewinding and conversion of the damaged
original demand. The respondent-appellee in the case transformer.
herein before Us wants to avail of both of these options.
In response[16] to petitioners requests, respondent,
This can not be done. The respondent-appellee cannot ask
through counsel, manifested its observation that
for rescission of the compromise agreement after it has
petitioners financial status showed that it could no longer
already enjoyed the first option of enforcing the
complete the projects as agreed upon. Respondent also
compromise by asking for a writ of execution resulting
informed petitioner that it was already in default having
thereby in the garnishment of the Pasay City funds
failed to complete the projects within 120 days from the
effectivity of the contract. Respondent further notified
petitioner that the former was terminating the contract. It needed more repairs than what it knew during the
also demanded for the refund of the amount already paid bidding.[51] In the same letter, however, petitioner
to petitioner, otherwise, the necessary action would be repeated its request that direct payment be made by
instituted. Respondent sent another demand letter[17] to respondent to petitioners suppliers.[52] More importantly,
Times Insurance for the payment of P1,472,000.00 petitioner admitted that it made a judgment error when it
pursuant to the performance bond it issued. quoted for only P440,770.00 for the contract relating to
J.O. #P-90-214 based on limited information.
On November 14, 1991,[18] respondent entered into two
contracts with Geostar Philippines, Inc. (Geostar) for the It can be inferred from the foregoing facts that there was
completion of the projects commenced but not not only a delay but a failure to complete the projects as
completed by petitioner for a total consideration stated in the contract; that petitioner could not complete
of P3,435,000.00. the projects because it did not have the materials needed;
and that it is in need of financial assistance.
On December 14, 1991, petitioner reiterated its desire to
complete J.O. #P-90-212 and J.O. #P-90-213 and to Assuming for the sake of argument that the subject
exclude J.O. #P-90-214,[19] but the same was denied by transformer was indeed in a damaged condition even
respondent in a letter[20] dated January 14, 1992. In the before the bidding which makes it impossible for
same letter, respondent pointed out that amicable petitioner to perform its obligations under the contract,
settlement is impossible. Hence, the Complaint for Sum of we also agree with the CA that petitioner failed to prove
Money[21]filed by respondent against petitioner and Times that respondent was guilty of bad faith, fraud, deceit or
Surety & Insurance Co., Inc. praying for the payment of the misrepresentation.
following: P493,695.00 representing the amount which
Bad faith does not simply connote bad judgment or
they owed respondent from the downpayment and
negligence; it imports a dishonest purpose or some moral
advances made by the latter vis--vis the work
obliquity and conscious doing of a wrong, a breach of a
accomplishment; P2,550,945.87 representing the amount
known duty through some motive or interest or ill will that
incurred in excess of the cost of the projects as agreed
partakes of the nature of fraud.[59] Fraud has been defined
upon; P294,000.00 as liquidated damages; plus interest
to include an inducement through insidious machination.
and attorneys fees.[22]
Insidious machination refers to a deceitful scheme or plot
Times Insurance did not file any pleading nor appeared in with an evil or devious purpose. Deceit exists where the
court. For its part, petitioner denied[23] liability and party, with intent to deceive, conceals or omits to state
claimed instead that it failed to complete the projects due material facts and, by reason of such omission or
to respondents fault. It explained that it relied in good concealment, the other party was induced to give consent
faith on respondents representation that the transformer that would not otherwise have been given.[60] These are
subject of the contract could still be rewound and allegations of fact that demand clear and convincing
converted but upon dismantling the core-coil assembly, it proof. They are serious accusations that can be so
discovered that the coils were already badly damaged and conveniently and casually invoked, and that is why they
the primary bushing broken. This discovery allegedly are never presumed.[61] In this case, the evidence
entailed price adjustment. Petitioner thus requested presented is insufficient to prove that respondent acted in
respondent for additional time within which to complete bad faith or fraudulently in dealing with petitioner.
the project and additional amount to finance the same.
Petitioner in fact admitted that its representatives were
Petitioner also insisted that the proximate cause of the
given the opportunity to inspect the subject transformer
delay is the misrepresentation of the respondent on the
before it offered its bid. If indeed the transformer was
extent of the defect of the transformer.
completely sealed, it should have demanded that the
Issue: whether or not the evidence presented by same be opened if it found it necessary before it offered
petitioner adequately established the true nature and its bid. As contractor, petitioner had been remiss in its
condition of the subject transformer. obligation to obtain as much information as possible on
the actual condition of the subject transformer or at least
Ruling: petitioner justified its inability to complete the
it should have provided a qualification in its bid so as to
projects within the stipulated period on the alleged
make clear its right to claim contract price and time
unavailability of the materials to be used to perform the
adjustment.[62] As aptly held by the CA, considering that
projects as stated in the job orders. Nowhere in said
petitioner is a company engaged in the electrical business
letters did petitioner claim that it could not finish the
and the contract it had entered into involved a sizable
projects, particularly the conversion of the transformer
amount of money, its failure to conduct an inspection of
unit because the defects were worse than the
the subject transformer is inexcusable.[63]
representation of respondent. In other words, there was
no allegation of fraud, bad faith, concealment or In sum, the evidence presented by the parties lead to the
misrepresentation on the part of respondent as to the following conclusions: (1) that the projects were not
true condition of the subject transformer. Even in its completed by petitioner; (2) that petitioner was given the
letter[49] dated May 25, 1991, petitioner only requested opportunity to inspect the subject transformer; (3) that
respondent that payment to the first progress billing be petitioner failed to thoroughly study the entirety of the
released as soon as possible and without deduction. It projects before it offered its bid; (4) that petitioner failed
further proposed that respondent make a direct payment to complete the projects because of the unavailability of
to petitioners suppliers. the required materials and that petitioner needed
financial assistance; (5) that the evidence presented by
It was only in its June 14, 1991 letter[50] when petitioner
petitioner were inadequate to prove that the subject
raised its observations that the subject transformer
transformer could no longer be repaired; and (6) that of Provident Savings Bank. In this case, there is no
there was no evidence to show that respondent was in indication or allegation that the BSP’s action was tainted
bad faith, acted fraudulently, or guilty of deceit and with arbitrariness or bad faith. It was made pursuant to
misrepresentation in dealing with petitioner. R.A. No. 7653. Respondent was also partly accountable for
the closure of its business. The legal effect is analogous to
In view of the foregoing disquisitions, we find that there
that created by contributory negligence in quasi-delict
was not only delay but non-completion of the projects
actions.
undertaken by petitioner without justifiable ground.
Undoubtedly, petitioner is guilty of breach of Therefore, the period during which the bank cannot do
contract. Breach of contract is defined as the failure business due to insolvency is not a fortuitous event.
without legal reason to comply with the terms of a
contract. It is also defined as the failure, without legal
excuse, to perform any promise which forms the whole or Respondent lessee invokes the doctrine of unforeseen
part of the contract.[64] In the present case, petitioner did event under Article 1267 of the Civil Code as an alternative
not complete the projects. This gives respondent the right justification for its premature termination of the contract.
to terminate the contract by serving petitioner a written
notice. Article 1267 provides that when the service has become
so difficult as to be manifestly beyond the contemplation
Spouses Jaime and Matilde Poon vs. Prime Savings Bank of the parties, the obligor may also be released therefrom,
represent by the Philippine Deposit Insurance in whole or in part. However, Article 1267 cannot be
Corporation as Statutory Liquidator G.R. No. 183794 June applied in all cases; otherwise, it would endanger the
13, 2016 security of contractual relations. Parties to a contract are
presumed to have assumed the risk of unfavorable
Facts: Petitioners owned a commercial building in Naga
developments.
City. On November 3, 2006, Matilde Poon and Respondent
executed a 10-year Contract of Lease over the building for It is only in exceptional changes of circumstance that
the latter’s use as its branch office in Naga City. They equity demands assistance for the debtor. The difficulty of
agreed to a fixed monthly rental of 60,000 pesos, with the performance should be such that the party seeking to
advanced payment of rentals for the first 100 months, in be released from the contractual obligation would be
the amount of 6,000,000, to be applied immediately. placed at a disadvantage by the unforeseen event.
Paragraph 24 of the Contract provides that should the
leased premises be closed, deserted, or vacated by lessee, Mere inconvenience, unexpected impediments, increased
the lessor shall have the right to terminate the lease expenses, or even pecuniary inability to fulfil an
without necessity of serving a court order and to engagement, will not relieve the obligor from an
immediately repossess the leased premises. The lessor undertaking that it has knowingly and freely contracted.
shall thereupon have the right to enter into a new contract The closure of respondent’s business was not an
with another party and all advanced rentals shall be unforeseen event. As the lease was long-term, it was not
forfeited in favor of the lessor. lost on the parties that such an eventuality might occur.

Three years later, BSP placed respondent under the HEIRS OF Liong vs. Castillo, G.R. 176425
receivership of Philippine Deposit Insurance Corporation.
FACTS:
The BSP eventually ordered respondent’s liquidation.
Respondent vacated the leased premises on May 12, Respondents in this case were petitioners in a civil case to
2000. PDIC then issued petitioners a demand later asking annul the title of PMPCI over respondents’ land.
for the return of the unused advance rentals amounting to Respondents entered into an AGREEMENT whereby in
3,480,000 pesos on the ground that the lease agreement exchange for the legal services of Atty. Zepeda and the
had become inoperative because of respondent’s closure, financial assistance of MANUEL UY EK LIONG, in the event
which constitutes force majeure. The petitioners refused of a favorable decision in the civil case, Atty Zepeda and
the PDIC’s demand and maintained that they were Manuel would be entitled to 40% of the realties and/or
entitled to retain the reminder of the advance rentals monetary benefits which may be adjudicated in favor of
following Paragraph 24 of their Contract. the respondents.

Issues: 1. Whether respondent may be released from its Respondents, on the same day entered into a Kasunduan,
contractual obligations on grounds of fortuitous event agreeing to sell the remaining 60% share in the land in
under Article 1174 of the Civil Code and unforeseen event favor of Manuel for the sum of 180k. Manuel would pay a
under Article 1267 of the Civil Code? 1K down payment upon execution of the Kasunduan. They
agreed that any party violating the Kasunduan would pay
Held: 1. The closure of respondent’s business was neither
the aggrieved party a penalty fixed in the sum of P50K,
a fortuitous nor an unforeseen event that rendered the
together with the attorney’s fees and litigation expenses
leased agreement functus officio.
incurred should a case be subsequently filed in court.
Respondent cites the case of Provident Savings Bank
The respondents won in the CIVIL CASE. The land was
wherein the closure of its business upon BSP’s order
divided in accordance with the Agreement but the
constituted a fortuitous event. However, the context of
respondents refused to comply with the KASUNDUAN,
that case is different form the case at bar.
despite Manuel’s offer to pay the remaining 179K balance,
The Court ruled in that case that the Monetary Board had claiming that the same was void ab initio for being
acted arbitrarily and in in bad faith in ordering the closure violative violative of Art 1491 of the NCC and the Canons
of Professional Responsibility. Article 1491 prohibits On February 23, 1996, petitioner filed an action for
lawyers from acquiring by purchase or assignment the ejectment before the Metropolitan Trial Court of
property /rights involved in the litigation in which they Malabon, Branch 55. He asked, inter alia, for the
intervene by virtue of their profession. Manuel instituted imposition of the contractually stipulated penalty
an action for Specific Performance and Damages against of P5,000 per day of delay in surrendering the possession
respondents. of the property to him. On September 3, 1996, the trial
court decided the case in favor of petitioner:
ISSUE: w/n the Kasunduan should be given effect
WHEREFORE, premises considered, the Court considers
HELD: The Kasunduan is valid. The prohibition applies only
the allegations of the complaint to be true and duly
during the pendency of the suit and generally does not
substantiated except as to the amount of damages and
cover contracts for contingent fees where the transfer
attorneys fees, which are reduced accordingly, a decision
takes effect only after the finality of a favorable judgment.
is hereby rendered in favor of the plaintiffs and against the
The Agreement and the Kasunduan are not independent
defendant, ordering the latter and all persons claiming
contracts, with parties, objects and causes different from
rights under it:
that of the other. Obligations arising from contracts have
the force of law between the contracting parties. When 1) To vacate the leased premises immediately and turn
the terms of the contract are clear and leave no doubt as over the same peacefully to the plaintiffs;
to the intention of the parties, the literal meaning of its
2) To pay plaintiff Antonio Lo the sum of P5,000.00 for
stipulation should govern.
every day of delay from the time defendant is supposed to
The Kasunduan contained a penal clause which provides have vacated the premises;
that a party who violates any of its provisions shall be
3) To pay the sum of P36,000.00 a month from January
liable to pay the aggrieved party a penalty fixed at P50K,
1996 until it finally vacates the premises as payment for
together with the attorney’s fees and litigation expenses
reasonable compensation for the use and occupancy
incurred by the latter should judicial resolution of the
thereof;
matter becomes necessary. The obligor would then be
bound to pay the stipulated indemnity without the 4) To pay the sum of P20,000.00 by way of reasonable
necessity of proof of the existence and the measure of attorneys fees; and
damages caused by the breach. The penalty clause
generally substitutes the indemnity for damages and the 5) To pay the costs of suit.[3]
payment of interests in case of noncompliance. The rule
On appeal to the Regional Trial Court of Malabon, Branch
is settled that a penal clause is not limited to actual and
74, the MTC decision was affirmed in toto on August 29,
compensatory damages.
1997.[4] Private respondents subsequent motion for
The RTC’s award of attorney’s fees in the sum of reconsideration of the RTC decision was denied on
P50,000.00 is, however, proper. Aside from the fact that November 26, 1997.
the penal clause included a liability for said award in the
From the adverse decision of the trial court, private
event of litigation over a breach of the Kasunduan,
respondent elevated the case to the Court of Appeals via a
petitioners were able to prove that they incurred said sum
petition for review.
in engaging the services of their lawyer to pursue their
rights and protect their interests. On May 26, 1999, the Court of Appeals rendered its
assailed decision affirming the decision of the trial court,
Lo vs. CA, 411 SCRA 523, 2003
with the modification that the penalty imposed upon
At the core of the present controversy are two parcels of private respondent for the delay in turning over the leased
land measuring a total of 2,147 square meters, with an property to petitioner was reduced from P 5,000
office building constructed thereon, located at Bo. to P 1000 per day.
Potrero, Malabon, Metro Manila and covered by TCT Nos.
Unsatisfied with the decision of the Court of Appeals,
M-13166 and M-13167.
petitioner filed the instant petition for review, raising the
Petitioner acquired the subject parcels of land in an sole issue of the alleged lack of authority of the Court of
auction sale on November 9, 1995 for P20,170,000 from Appeals to reduce the penalty awarded by the trial court,
the Land Bank of the Philippines (Land Bank). the same having been stipulated by the parties in their
Contract of Lease.
Private respondent National Onion Growers Cooperative
Marketing Association, Inc., an agricultural cooperative, The petition has no merit.
was the occupant of the disputed parcels of land under a
Generally, courts are not at liberty to ignore the freedom
subsisting contract of lease with Land Bank. The lease was
of the parties to agree on such terms and conditions as
valid until December 31, 1995.
they see fit as long as they are not contrary to law, morals,
Upon the expiration of the lease contract, petitioner good customs, public order or public policy. Nevertheless,
demanded that private respondent vacate the leased courts may equitably reduce a stipulated penalty in the
premises and surrender its possession to him. Private contract if it is iniquitous or unconscionable, or if the
respondent refused on the ground that it was, at the time, principal obligation has been partly or irregularly complied
contesting petitioners acquisition of the parcels of land in with.[5]
question in an action for annulment of sale, redemption
This power of the courts is explicitly sanctioned by Article
and damages.
1229 of the Civil Code which provides:
Article 1229. The judge shall equitably reduce the penalty drawn against insufficient funds (Exhs. H to H-7) except for
when the principal obligation has been partly or irregularly TCBTC 618821.
complied with by the debtor. Even if there has been no
Plaintiff made repeated written demands on defendants
performance, the penalty may also be reduced by the
to make good the checks they indorsed and to pay the
courts if it is iniquitous or unconscionable.
penalty charges it has imposed thereon, (Exhs. I, J, K, L, L-
The question of whether a penalty is reasonable or 1, M and N).
iniquitous is addressed to the sound discretion of the
Defendants failed to pay the value of the checks. Plaintiff
court and depends on several factors, including, but not
thus decided to undertake foreclosure of the real estate
limited to, the following: the type, extent and purpose of
mortgage.
the penalty, the nature of the obligation, the mode of
breach and its consequences, the supervening realities, Ruling: There is no dispute that the payment of penalty is
the standing and relationship of the parties.[6] sanctioned by the law, although the penalty may be
reduced by the courts if it is iniquitous or
In this case, the stipulated penalty was reduced by the
unconscionable.[5] Petitioner argues that while it
appellate court for being unconscionable and
recognizes the authority of the court to reduce the penalty
iniquitous. As provided in the Contract of Lease, private
if it is iniquitous or unconscionable, the
respondent was obligated to pay a monthly rent
court, however, does not have the authority to delete the
of P30,000. On the other hand, the stipulated penalty was
payment of the penalty charges altogether for this isin
pegged at P5,000 for each day of delay or P150,000 per
clear contravention of Article 1229 and the law of
month, an amount five times the monthly rent. This
contracts between the parties.
penalty was not only exorbitant but also unconscionable,
taking into account that private respondents delay in This contention is not well-taken.
surrendering the leased premises was because of a well-
founded belief that its right of preemption to purchase the The Court does not find any reversible error committed by
subject premises had been violated. Considering further the respondent court in ruling that the petitioner was no
that private respondent was an agricultural cooperative, longer entitled to recover any deficiency amount after the
collectively owned by farmers with limited resources, foreclosure sale on February 14, 1983. Per Statement of
ordering it to pay a penalty of P150,000 per month on top Account dated September 21, 1981, the obligation of the
of the monthly rent of P30,000 would seriously deplete its private respondent was computed to be P4,809,187.12
income and drive it to bankruptcy. In Rizal Commercial inclusive of interest and penalty charges. Since the private
Banking Corp. vs. Court of Appeals,[7] the Court tempered respondent failed to fulfill its obligation, petitioner then
the penalty charges after taking into account the debtors decided to foreclose the real estate mortgage on two
pitiful financial condition. properties of the private respondent. At the time of the
auction sale on February 14, 1983, the properties were
Accordingly, we rule that the Court of Appeals did not sold in the amount of P4,223,874.00 with the petitioner as
commit any reversible error in the exercise of its the highest bidder. Deducting this amount from the
discretion when it reduced the award of penalty damages outstanding obligation of P4,809,187.12 as stipulated in
from P5,000 to P1,000 for each day of delay. the Statement of Account, there would therefore be a
balance of only about P575,313.12.
WHEREFORE, petition is hereby DENIED.
Whether or not the alleged deficiency from the
State Investment House vs. CA, G.R. 112590
foreclosure sale was P575,313.12 or P2,601,147.62 as
Facts: On March 9, 1978, Lomuyon Timber Industries, Inc. claimed by petitioner was of no moment. The respondent
(hereafter, Lomuyon) agreed to sell to plaintiff its court disallowed the payment of the deficiency
receivables at a discount on a with recourse basis (Exh. altogether because it found that the principal obligation
A). It was agreed in that sale that should areceivable of the private respondent would not have ballooned to
remain unpaid, plaintiff, at its discretion, may impose a such a horrendous amount of P4.8M as of September 21,
penalty fee of 3% per month. To secure the payment of 1991 if not for the penalty charge of 3% per month or 36%
the receivables, the Malonjaos also executed in favor of per annum.
plaintiff, a real estate mortgage over their real property.
Surcharges and penalties agreed to be paid by the debtor
Pursuant to their agreement, on March 9, 10 and 15, 1978
in case of default partake of the nature of liquidated
and July 19, 1978, Lomuyon sold to plaintiff for a total
damages, covered by Section 4, Chapter 3, Title XVIII of the
consideration of P2,558,073.75 (Exhs. C, D, E and F),
Civil Code. Article 2227 thereof provides:
various receivables consisting of checks.
ART. 2227. Liquidated damages, whether intended as an
TCBTC (The Consolidated Bank and Trust Corporation)
indemnity or penalty, shall be equitably reduced if they
checks were all drawn by Amanda Malonjao to the order
are iniquitous and unconscionable.
of payee Lomuyon which in turn, indorsed the checks to
plaintiff. The MBTC (Metropolitan Bank and Trust In exercising this vested power to determine what is
Company) check was drawn by one Antonietta Malonjao- iniquitous and unconscionable, the Court must consider
Roque to the order of payee Amanda Malonjao who in the circumstances of each case. It should be stressed that
turn, indorsed said check to plaintiff. the Court will not make any sweeping ruling that
surcharges and penalties imposed by banks for non-
When plaintiff presented the checks for payment to the
payment of the loans extended by them are generally
drawee banks, the same were dishonored for having been
iniquitous and unconscionable. What may be iniquitous
and unconscionable in one case, may be totally just and
equitable in another. This provision of law will have to be ART. 2227. Liquidated damages, whether intended as an
applied to the established facts of any given case. Given indemnity or penalty, shall be equitably reduced if they
the circumstances under which GOYU found itself after are iniquitous and unconscionable.
the occurrence of the fire, the Court rules the surcharges
DBP vs. CA, G.R. 137557
rates ranging anywhere from 9% to 27%, plus the penalty
charges of 36%, to be definitely iniquitous and Facts: Development Bank of the Philippines is the owner
unconscionable. x x x of a parcel of land in Bulacan. On August 8, 1983, it sold
the land to respondent spouses Nilo and Esperanza De La
Likewise, in the case at bar, the two courts below found
Peña under a Deed of Conditional Sale for
the penalty charge of 3% a month or 36% per annum
₱207,000.00.4 The Deed of Conditional Sale stipulated:
iniquitous and unconscionable. Petitioner
computed the amount of P4,809,187.12 as the That the down payment shall be ₱41,400.00 and the
outstanding obligation of the petitioner as of September balance of P165,600.00 to be paid in six (6) years on the
21, 1981 after imposing the 3% penalty charge when semi-annual amortization plan at 18% interest per annum.
petitioner defaulted in their payments. This amount was The first amortization of ₱23,126.14 shall be due and
no longer questioned and wasparticularly taken into payable six (6) months from the date of execution of the
consideration when the mortgaged properties were Deed of Conditional Sale and all subsequent amortizations
foreclosed and sold at the auction sale in 1983, obtaining shall be due and payable every six (6) months thereafter;
a sum of about P4,223,874.00. These foreclosed
properties located in Makati[8] are undoubtedly valuable After the execution of the contract, the spouses De La
properties whose market value has greatly appreciated to Peña constructed a house on the said lot and began living
substantially satisfy the payment of the outstanding there. They also introduced other improvements therein
obligation. Notwithstanding the balance of P575,313.12, by planting fruit trees and building a small garage
petitioner has clearly recouped its investment and earned
After making the above payments, Esperanza De La Peña
more than enough profit in two years (1978-1981) by way
went to petitioner DBP and asked for the execution of a
of penalty charges. Although petitioner claims that the
Deed of Absolute Sale and for the issuance of the title to
penalty charge was well within the banking and business
the property.7 On January 5, 1989, however, respondent
practice, no proof was adduced thereof. To allow the
spouses De La Peña were informed by DBP through a letter
petitioner to recover the amount of P6,835,021.21 at the
that there was still a balance of ₱221,86.85.
time of the foreclosure sale in 1983, or P7,651,969.41 at
the time of the trial of the case in 1988 which amounts DBP demanded from respondent spouses the payment of
are almost three times more than the original investment this amount, which had increased to ₱225,855.86 as of
of about P2,558,073.75 is rather unwarranted. We quote June 30, 1989, otherwise, it would rescind the
with favor the respondent courts ratiocination: sale.9 Respondent spouses proposed a settlement of the
amount through semi-annual payments over a period of
The lower court did not err in its ruling under its statement
five years.10
that since plaintiff had already recovered fully the
receivables from the defendants, the court, considering As the parties failed to reach an agreement, respondent
that the plaintiff for the two properties foreclosed by it spouses filed a complaint against petitioner on January 30,
bidded the amount of P4,233,874.00, far and above the 1990 for specific performance and damages with
amount it had originally given to the defendants which injunction before the Regional Trial Court
was only over P2,000,000.00, it is rather most shocking
and unconscionable for plaintiff to still collect from the Issue: Whether or not the penalty is iniquitous or
defendants the alleged collectibles of P2,601,147.62 with unconscionable.
3% penalty charges. The plaintiff should have stopped Ruling: YES
imposing the 3% penalty charges and other burdens when
it had consolidated finally the two titles of the properties We find the interests to be excessive. It is noteworthy that
it had foreclosed (Decision, p. 8). After due consideration the interests paid by private respondents, which
and reflection on all the factual circumstances obtaining in amounted to P233,361.50,30 including therein the regular
the case at bar, it is Our opinion that the lower court interest, additional interest, penalty charges, and interest
properly exercised its discretion under Article 1229 of the on advances, is more than the principal obligation in the
Civil Code to reduce the penalty charges for being highly amount of P207,000.00, which private respondents owed.
and grossly unconscionable. x x x[9] Moreover, the additional interest of 18% alone amounted
to P106,853.45,31 which is almost half of what was already
While the Court recognizes the right of the parties to enter paid by private respondents.
into contracts and are expected ro comply with the terms
and obligations, this rule is not absolute. The Court Article 1229 of the Civil Code states that "Even if there has
allowed to temper interest rates when necessary. Article been no performance, the penalty may also be reduced by
1229 of the New Civil Code clearly provides: the courts if it is iniquitous or unconscionable." In Barons
Marketing Corp. v. Court of Appeals,32 the Court reduced
ART. 1229. The judge shall equitably reduce the penalty the 25% penalty charge to cover the attorney’s fees and
when the principal obligation has been partly or irregularly collection fees, which was in addition to the 12% annual
complied with by the debtor. Even if there has been no interest, to 10% for being manifestly exorbitant. Likewise,
performance, the penalty may also be reduced by the in Palmares v. Court of Appeals,33 the Court eliminated
courts if it is iniquitous or unconscionable. altogether the payment of the penalty charge of 3% per
Likewise, Article 2227 provides:
month for being excessive and unwarranted under the hence, contrary to morals (‘contra bonos mores’), if not
circumstances. against the law. The stipulation is void. The courts shall
reduce equitably liquidated damages, whether intended
Private respondents made regular payments to petitioner
as an indemnity or a penalty if they are iniquitous or
DBP in compliance with their principal obligation. They
unconscionable.
failed only to pay on the dates stipulated in the contract.
This indicates the absence of bad faith on the part of In the case at bench, petitioners stand on a worse
private respondents and their willingness to comply with situation. They are required to pay the stipulated interest
the terms of the contract. Moreover, of their principal rate of 6% per month or 72% per annum which is
obligation in the amount of ₱207,000.00, private definitely outrageous and inordinate. Surely, it is more
respondents have already paid ₱289,600.00 in favor of consonant with justice that the said interest rate be
petitioner. These circumstances convince us of the reduced equitably. An interest of 12% per annum is
necessity to equitably reduce the interest due to deemed fair and reasonable.
petitioner and we do so by reducing to 10% the additional
interest of 18% per annum computed on total
amortizations past due. The penalty charge of 8% per Ligutan vs. CA, G.R. 138667
annum is sufficient to cover whatever else damages
petitioner may have incurred due to private respondents’ Facts:
delay in paying the amortizations, such as attorney’s fees Petitioners Tolomeo Ligutan and Leonidas dela Llana obt
and litigation expenses. ained on 11 May 1981 a loan in the amount of
P120,000.00 from respondent Security Bank and Trust
DANILO SOLANGON AND URSULA SOLANGON vs JOSE Company. Petitioners executed a promissory note binding
AVELINO SALAZAR themselves, jointly and severally, to pay the sum
G.R.No. 125994, 29 June 2001 borrowed with an interest of 15.189% per annum upon
maturity and to pay a penalty of 5% every month on the
Facts:
outstanding principal and interest in case of default. In
On 1986, 1987, and 1990 the Solangons’ executed 3 real
addition, petitioners agreed to pay 10% of the total
estate mortgages in which they mortgaged a parcel of land
amount due by way of attorneys fees if the matter were
situated in Sta. Maria, Bulacan, in favor of the Salazar to
indorsed to a lawyer for collection or if a suit were
secure payment of a loan of P60, 000.00 payable within a
instituted to enforce payment. The obligation matured
period of four (4) months, with interest thereon at the rate
on 8 September 1981; the bank, however, granted an
of 6% per month, to secure payment of a loan of P136,
extension but only up until 29 December 1981.
512.00, payable within a period of one (1) year, with
interest thereon at the legal rate, and to secure payment Despite several demands from the bank, petitioners failed
of a loan in the amount of P230, 000.00 payable within a to settle the debt which, as of 20 May 1982, amounted to
period of four (4) months, with interest thereon at the P114,416.10. On 30 September 1982, the bank sent a final
legal rate. demand letter to petitioners informing them that they had
This action was initiated by the Solangons to prevent the five days within which to make full payment. Since
foreclosure of the mortgaged property. They alleged that petitioners still defaulted on their obligation, the bank
they obtained only one loan form the defendant-appellee, filed on 3 November 1982, with the Regional Trial Court
and that was for the amount of P60, 000.00, the payment of Makati, Branch 143, a complaint for recovery of the due
of which was secured by the first of the above-mentioned amount.
mortgages. The subsequent mortgages were merely
continuations of the first one, which is null and void After petitioners had filed a joint answer to the complaint,
because it provided for unconscionable rate of interest. the bank presented its evidence and, on 27 March 1985,
They have already paid the defendant-appellee P78, rested its case. Petitioners, instead of introducing their
000.00 and tendered P47, 000.00 more, but the latter has own evidence, had the hearing of the case reset on two
initiated foreclosure proceedings for their alleged failure consecutive occasions. In view of the absence of
to pay the loan P230, 000.00 plus interest. petitioners and their counsel on 28 August 1985, the third
hearing date, the bank moved, and the trial court
Issue: WON a loan obligation that is secured by a real resolved, to consider the case submitted for decision.
estate mortgage with an interest of 72% p.a. or 6% a
month unconscionable. Two years later, or on 23 October 1987, petitioners filed a
motion for reconsideration of the order of the trial court
Ruling: YES declaring them as having waived their right to present
evidence and prayed that they be allowed to prove their
While the Usury Law ceiling on interest rates was lifted by
case. The court a quo denied the motion in an order,
C.B. Circular No. 905, nothing in the said circular grants
dated 5 September 1988, and on 20 October 1989, it
lenders carte blanche authority to raise interest rates to
rendered its decision favouring respondent.
levels which will either enslave their borrowers or lead to
a hemorrhaging of their assets.5 In Medel v. Court of Issue: WON the 15.189% interest and the penalty of three
Appeals,6 this court had the occasion to rule on this (3%) percent per month or thirty-six (36%) percent per
question - whether or not the stipulated rate of interest annum imposed by private respondent bank on
at 5.5% per month on a loan amounting to P500,000.00 is petitioners loan obligation are still manifestly exorbitant,
usurious. While decreeing that the aforementioned iniquitous and unconscionable.
interest was not usurious, this Court held that the same
must be equitably reduced for Ruling: NO
being iniquitous, unconscionable and exorbitant and
A penalty clause, expressly recognized by law,[10] is an Petitioners next assail the award of 10% of the total
accessory undertaking to assume greater liability on the amount of indebtedness by way of attorney's fees for
part of an obligor in case of breach of an obligation. It being grossly excessive, exorbitant and
functions to strengthen the coercive force of the unconscionable vis-a-vis the time spent and the extent of
obligation[11] and to provide, in effect, for what could be services rendered by counsel for the bank and the nature
the liquidated damages resulting from such a breach. The of the case. Bearing in mind that the rate of attorneys fees
obligor would then be bound to pay the stipulated has been agreed to by the parties and intended to answer
indemnity without the necessity of proof on the existence not only for litigation expenses but also for collection
and on the measure of damages caused by the efforts as well, the Court, like the appellate court, deems
breach.[12] Although a court may not at liberty ignore the the award of 10% attorneys fees to be reasonable.
freedom of the parties to agree on such terms and
At any rate, the subsequent execution of the real estate
conditions as they see fit that contravene neither law nor
mortgage as security for the existing loan would not have
morals, good customs, public order or public policy, a
resulted in the extinguishment of the original contract of
stipulated penalty, nevertheless, may be equitably
loan because of novation. Petitioners acknowledge that
reduced by the courts if it is iniquitous or unconscionable
the real estate mortgage contract does not contain any
or if the principal obligation has been partly or irregularly
express stipulation by the parties intending it to supersede
complied with.[13]
the existing loan agreement between the petitioners and
The question of whether a penalty is reasonable or the bank.[21] Respondent bank has correctly postulated
iniquitous can be partly subjective and partly objective. Its that the mortgage is but an accessory contract to secure
resolution would depend on such factors as, but not the loan in the promissory note.
necessarily confined to, the type, extent and purpose of
Extinctive novation requires, first, a previous valid
the penalty, the nature of the obligation, the mode of
obligation; second, the agreement of all the parties to the
breach and its consequences, the supervening realities,
new contract; third, the extinguishment of the obligation;
the standing and relationship of the parties, and the like,
and fourth, the validity of the new one.[22] In order that an
the application of which, by and large, is addressed to the
obligation may be extinguished by another which
sound discretion of the court. In Rizal Commercial
substitutes the same, it is imperative that it be so declared
Banking Corp. vs. Court of Appeals,[14] just an example, the
in unequivocal terms, or that the old and the new
Court has tempered the penalty charges after taking into
obligation be on every point incompatible with each
account the debtors pitiful situation and its offer to settle
other.[23] An obligation to pay a sum of money is
the entire obligation with the creditor bank. The
not extinctively novated by a new instrument which
stipulated penalty might likewise be reduced when a
merely changes the terms of payment or adding
partial or irregular performance is made by the
compatible covenants or where the old contract is merely
debtor.[15] The stipulated penalty might even be deleted
supplemented by the new one.[24] When not expressed,
such as when there has been substantial performance in
incompatibility is required so as to ensure that the parties
good faith by the obligor,[16] when the penalty clause itself
have indeed intended such novation despite their failure
suffers from fatal infirmity, or when exceptional
to express it in categorical terms. The incompatibility, to
circumstances so exist as to warrant it.[17]
be sure, should take place in any of the essential elements
The Court of Appeals, exercising its good judgment in the of the obligation, i.e., (1) the juridical relation or tie, such
instant case, has reduced the penalty interest from 5% a as from a mere commodatum to lease of things, or
month to 3% a month which petitioner still from negotiorum gestio to agency, or from a mortgage
disputes. Given the circumstances, not to mention the to antichresis,[25] or from a sale to one of loan;[26] (2) the
repeated acts of breach by petitioners of their contractual object or principal conditions, such as a change of the
obligation, the Court sees no cogent ground to modify the nature of the prestation; or (3) the subjects, such as the
ruling of the appellate court.. substitution of a debtor[27] or the subrogation of the
creditor. Extinctive novation does not necessarily imply
Anent the stipulated interest of 15.189% per annum,
that the new agreement should be complete by itself;
petitioners, for the first time, question its reasonableness
certain terms and conditions may be carried, expressly or
and prays that the Court reduce the amount. This
by implication, over to the new obligation.
contention is a fresh issue that has not been raised and
ventilated before the courts below. In any event, the Lou vs. BPI. G.R. No. 225562, March 8, 2017
interest stipulation, on its face, does not appear as being
Facts
that excessive. The essence or rationale for the payment
of interest, quite often referred to as cost of money, is not A complaint for collection of sum of money was filed by
exactly the same as that of a surcharge or a penalty. A BPI against spouses Louh because they were unable to pay
penalty stipulation is not necessarily preclusive of interest, purchases made on their credit cards.
if there is an agreement to that effect, the two being
distinct concepts which may separately be They owed BPI the total amount of
demanded.[18] What may justify a court in not allowing the P533,836.27. Defendant William filed before the RTC a
creditor to impose full surcharges and penalties, despite Motion for Extension of Time to File an Answer or
an express stipulation therefor in a valid agreement, may Responsive Pleading. The RTC granted an extension of 15
not equally justify the non-payment or reduction of days or up to March 4, 2012, but the Spouses Louh still
interest. Indeed, the interest prescribed in loan financing failed to comply within the prescribed period.
arrangements is a fundamental part of the banking
BPI filed a motion to declare Spouses Louh in default.
business and the core of a bank's existence.[19]
Before the RTC can rule on BPI’s motion, Spouses Louh
filed an Answer more than three months after the been no perfom1ance, the penalty may also be reduced
prescribed period. by the courts if it is iniquitous or unconscionable.

RTC rendered a Decision and ordered the Spouses Louh xxxx


to solidarily pay BPI (1) P533,836.27 plus 12% finance and
x x x [T]he stipulated penalty charge of 31% per month or
12% late payment annual charges starting from August 7,
36% per annum, in addition to regular interests, is indeed
2010 until full payment, and (2) 25% of the amount due as
iniquitous and unconscionable. Thus, in Macalinao, the
attorney’s fees, plus P1,000.00 per court hearing and
Court reduced both the interest and penalty charges to
P8,064.00 as filing or docket fees; and (3) costs of
12% each, and the attorney’s fees to P10,000.00.
suit. However, the RTC found the 3.5% finance and 6%
late payment monthly charges imposed by BPI as In MCMP Construction Corp. v. Monark Equipment Corp.,
iniquitous and unconscionable. Hence, both charges the creditor cumulatively charged the debtor 60%
were reduced to 1% monthly. Anent the award of annually as interest, penalty and collection fees, and 25%
attorney’s fees equivalent to 25% of the amount due, RTC of the total amount due as attorney’s fees. The Court
found the same to be within the terms of the parties’ similarly found the rates as exorbitant and
agreement. unconscionable; hence, directed the reduction of the
annual interest to 12%, penalty and collection charges to
On appeal, Spouses Louh reiterated that the RTC wrongly
6%, and attorney’s fees to 5%. The Court explained that
declared them in default since by reason of William’s
attorney’s fees are in the nature of liquidated damages,
sickness, they were entitled to a relaxation of the rules.
which under Article 2227 of the New Civil Code, “shall be
Moreover, BPI had failed to offer preponderant evidence
equitably reduced if they are iniquitous or
relative to the actual amount of the Spouses Louh’s
unconscionable.”41
indebtedness
CA affirmed the RTC Decision in toto. In the case at bench, BPI imposed a cumulative annual
interest of 114%, plus 25% of the amount due as
Issue: Whether or not the 5% finance and 6% late payment
attorney’s fees. Inevitably, the RTC and the CA aptly
monthly charges imposed by BPI are iniquitous and
reduced the charges imposed by BPI upon the Spouses
unconscionable.
Louh. Note that incorporated in the amount of
Ruling: Yes. P533,836.27 demanded by BPI as the Spouses Louh’s
obligation as of August 7, 2010 were the higher rates of
In Macalinao, where BPI charged the credit cardholder of
finance and late payment charges, which the courts a
3.25% interest and 6% penalty per month, and 25% of the
quo had properly directed to be reduced.
total amount due as attorney’s fees, the Court
unequivocally declared that: In the SOA dated October 14, 2009, the principal amount
indicated was P113,756.83. In accordance
[T]his is not the first time that this Court has considered
with Macalinao, the finance and late payment charges to
the interest rate of 36% per annum as excessive and
be imposed on the principal amount of P113,756.83 are
unconscionable. We held in Chua vs. Timan:
reduced to 12% each per annum, reckoned from October
The stipulated interest rates of 7% and 5% per month 14, 2009, the date when the Spouses Louh became initially
imposed on respondents’ loans must be equitably remiss in the payment of their obligation to BPI, until full
reduced to 1% per month or 12% per annum. We need payment.
not unsettle the principle we had affirmed in a plethora
Anent BPI’s litigation expenses, the Court retains the RTC
of cases that stipulated interest rates of 3% per month
and CA’s disquisition awarding P8,064.00 as filing or
and higher are excessive, iniquitous, unconscionable and
docket fees, and costs of suit. However, the Court reduces
exorbitant. Such stipulations are void for being contrary
the attorney’s fees to five percent (5%) of the total
to morals, if not against the law.
amount due from the Spouses Louh pursuant
While C.B. Circular No. 905-82, which took effect on to MCMP43and Article 2227 of the New Civil Code.
January 1, 1983, effectively removed the ceiling on
interest rates for both secured and unsecured loans,
regardless of maturity, nothing in the said circular could
possibly be read as granting carte blanche authority to
lenders to raise interest rates to levels which would either
enslave their borrowers or lead to a hemorrhaging of their
assets. x x x

Since the stipulation on the interest rate is void, it is as if


there was no express contract thereon. Hence, courts may
reduce the interest rate as reason and equity demand.

The same is true with respect to the penalty charge. x x x


Pertinently, Article 1229 of the Civil Code states:

Art. 1229. The judge shall equitably reduce the penalty


when the principal obligation has been partly or
irregularly complied with by the debtor. Even if there has

Das könnte Ihnen auch gefallen