SAUDI TELECOM COMPANY

Solution Document for


GBFD-119401 Extended Dynamic Allocation EDA

GBFD-119402 MS High Multislot Classes


(Note: The selectable part of the title can be update/patch installation/rectification
according to the actual implementation scenario. )

Prepared by: Muhammad Waqas Date:


29-12-2015
Mirza/m84030231

Reviewed by: Date:

Approved by: Date:


Implementation Solution for Change

Contents

1 Live network information ................................................................................................. 4

1.1 Live network topology .......................................................................................... 4

1.2 Business volume ................................................................................................... 4

1.3 Main existing problems ......................................................................................... 7

1.4 Remote access information ................................................................................... 7

2 Purpose and Requirements ................................................................................................ 7

2.1 Customer requirement and acceptance standards .................................................. 7

2.2 Change scenario .................................................................................................... 8

2.3 Change scope & scale ........................................................................................... 8

2.4 Change time and operation time window .............................................................. 8

3 Description of Change and Change Influence................................................................... 9

3.1 NE version number or patch number before and after change .............................. 9

3.2 Surrounding NEs and version number involved by the change ............................ 9

3.3 Change relevance .................................................................................................. 9

3.4 Description of changed software ........................................................................... 9

3.5 Description of changed hardware .......................................................................... 9

4 Change Preparations ......................................................................................................... 9

4.1 Composition of Change Team and Responsibility of Team Members ................. 9

Change Team of XX Company ................................................................................................. 9

Huawei On-site Change Team ............................................................................................... 10

Huawei Support & Guarantee Team ...................................................................................... 10

4.2 Check of Equipment Running ............................................................................. 10

4.3 Change Risks and Countermeasures ................................................................... 11

4.4 Check Before Change ......................................................................................... 11

5 Operation Steps for Change ............................................................................................ 12

5.1 Change Steps ....................................................................................................... 12

Technical support website: Technical support hotline: Page 2 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

5.1.1 Overall Description ............................................................................................. 12

5.1.2 Operation Steps for Change .......................................................................... 14

5.2 Test and Verification ........................................................................................... 14

5.3 Solution for Changeback In the Case of Failure ................................................. 15

5.3.1 Definition of Change Failure ............................................................................. 15

5.3.2 Overall Description of Changeback ................................................................. 15

5.3.3 Information Collection Before Changeback .................................................... 16

5.3.4 Changeback Steps ............................................................................................. 16

5.3.5 Equipment Status Check ................................................................................... 16

5.3.6 Tests After Changeback .................................................................................... 17

5.3.7 Changeback Risk Analysis ............................................................................... 17

5.4 Change of Spare Parts and Emergency Workstation........................................... 18

6 Work After Change ......................................................................................................... 18

6.1 Observation ......................................................................................................... 18

6.2 Provision of Materials ......................................................................................... 18

6.3 Provision of Software.......................................................................................... 18

6.4 Training ............................................................................................................... 19

6.5 Matters Needing Attention .................................................................................. 19

Technical support website: Technical support hotline: Page 3 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

1 Live network information

1.1 Live network topology for STC network is shown below

STC 2G wireless
network topology

1.2 Business volume

Traffic Volume

1.3

Eastern Region BSC: DH2GB08:

SDCCH/TCH Traffic(Erl)
45000 200.00
40000 180.00
Data Volume(GB)

35000 160.00
Traffic(Erl)

30000 140.00
25000 120.00
100.00
20000 80.00
15000 60.00
10000 40.00
5000 20.00
0 0.00
2015/4/11
2015/4/12
2015/4/13
2015/4/14
2015/4/15
2015/4/16
2015/4/17
2015/4/18
2015/4/19
2015/4/20
2015/4/21
2015/4/22
2015/4/23
2015/4/24
2015/4/25

Data Volume(GB) SDCCH Traffic (ErL) TCH Traffic (Erl)

Technical support website: Technical support hotline: Page 4 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

Central Region BSC: QH2GB01:

SDCCH/TCH Traffic(Erl)
45000 600.00
40000
500.00

Data Volume(GB)
35000
Traffic(Erl)

30000 400.00
25000
300.00
20000
15000 200.00
10000
100.00
5000
0 0.00
2015/4/11
2015/4/12
2015/4/13
2015/4/14
2015/4/15
2015/4/16
2015/4/17
2015/4/18
2015/4/19
2015/4/20
2015/4/21
2015/4/22
2015/4/23
2015/4/24
2015/4/25
Data Volume(GB) SDCCH Traffic (ErL) TCH Traffic (Erl)

South Region BSC: GSA8H2:

SDCCH/TCH Traffic(Erl)
16000 170.00
14000 165.00
Data Volume(GB)

12000 160.00
Traffic(Erl)

10000 155.00
8000 150.00
6000 145.00
4000 140.00
2000 135.00
0 130.00
2015/4/11
2015/4/12
2015/4/13
2015/4/14
2015/4/15
2015/4/16
2015/4/17
2015/4/18
2015/4/19
2015/4/20
2015/4/21
2015/4/22
2015/4/23
2015/4/24
2015/4/25

Data Volume(GB) SDCCH Traffic (ErL) TCH Traffic (Erl)

Technical support website: Technical support hotline: Page 5 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

West Region BSC GST4H1:

SDCCH/TCH Traffic(Erl)
18000 160.00
16000 155.00

Data Volume(GB)
14000
Traffic(Erl)

12000 150.00
10000 145.00
8000 140.00
6000 135.00
4000
2000 130.00
0 125.00
2015/4/11
2015/4/12
2015/4/13
2015/4/14
2015/4/15
2015/4/16
2015/4/17
2015/4/18
2015/4/19
2015/4/20
2015/4/21
2015/4/22
2015/4/23
2015/4/24
2015/4/25
Data Volume(GB) SDCCH Traffic (ErL) TCH Traffic (Erl)

There are 2 M2000 servers covering 60 BSCs & about 6000


BTS on customer network.

M2000 Name M2000 Server IP BSC Managed Qty.


4G1-2 172.20.76.39 2
4G3 172.20.153.6 10

BSC Type
AH2GB09 BSC6910
AH2GB10 BSC6910
AH2GB11 BSC6910
AH2GB12 BSC6910
AH2GB06 BSC6910
AH2GB07 BSC6910
AH2GB08 BSC6910
SH2GB03 BSC6910

Technical support website: Technical support hotline: Page 6 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

SH2GB04 BSC6910
NH2GB01 BSC6910
NH2GB02 BSC6910
NH2GB03 BSC6910

- Huawei Performance Team Contact Information:


- Huawei Mobile Network Performance
- STC Network – NMC Mobile Department
- Radio Tel: +966 1 4529851
- CS&PS Core Tel: +966 1 4529081
- Email: hperformance@stc.com.sa

1.4 Main existing problems

 This feature is Part of the delivery process to be communicated with customer and
upon approval will proceed for the FNI.

1.5 Remote access information

 Not available in STC network environment

2 Purpose and Requirements

To do Rollout for the subjected features on 2G NW with customer approval


as well Roll out based on requirement.

2.1 Customer requirement and acceptance standards

 After midnight as per customer regulation >> 00:00~08:00 AM

 Outage window from 00:02~00:05AM allowed by customer

 Outage window Huawei engineer will apply 02:30 to 03:00

 Activity Date 7th January 2016

Technical support website: Technical support hotline: Page 7 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

2.2 Change scenario

 Network tuning will have the following benefit to the network.


EDA

 EDA helps assign more timeslots in the uplink to the MS, improving the uplink
throughput.

Benefits

 This feature improves the uplink rate and helps transmit large amount of data in the
uplink. In this way, the user satisfaction is improved.

High Speed Multislot

 High multislot classes ensure that a maximum of five timeslots in the uplink or
downlink are assigned to a single MS, improving the uplink or downlink throughput
of a single MS.

Benefits

 The BSS supports the MS with a high multislot class of 30 to 34. A maximum of five
timeslots on the downlink can be assigned to an MS. If an MS is of the high multislot
class 34, a maximum of five timeslots in the uplink can be assigned to the MS.
Therefore, compared with four timeslots in the uplink or downlink, the throughput
is increased by 25%.

2.3 Change scope & scale

 Feature would be implemented on above 12 BSCs.

 For FNI BSC AH2GB06 has been selected.

2.4 Change time and operation time window

 Activity Timings 00:00~08:00 AM

 Outage timings 02:30 to 03:00

 Outage duration 1hour

Technical support website: Technical support hotline: Page 8 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

3 Description of Change and Change Influence

3.1 NE version number or patch number before and after change

 No version changes during the operation.

3.2 Surrounding NEs and version number involved by the change

 N/A

3.3 Change relevance

N/A

3.4 Description of changed software

N/A

3.5 Description of changed hardware

N\A

4 Change Preparations

4.1 Composition of Change Team and Responsibility of Team


Members

Change Team of XX Company

Name Responsibility Telephone No.


MaGuigeng Chief commander 00966550514902

Muhammad Waqas Owner for BTS product 00966506012504


change

Coordination with other


NEs
Muhammad Waqas 00966506012504
Test owner

Technical support website: Technical support hotline: Page 9 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

Muhammad Waqas Charging verification 00966506012504


owner
Network management 0114521295
MTAC
test owner
Muhammad Waqas Communication on 00966506012504
handling customer
complaints

Huawei On-site Change Team

Name Responsibility Telephone No.


MaGuigeng Chief commander 00966550514902

Muhammad Waqas Owner for BTS product 00966506012504


change

Huawei Support & Guarantee Team

Name Responsibility Telephone No.


Supporting overall 00966506012504
Muhammad Waqas
coordination as the
technical expert
+86-18668485288/0571-1866848
Product support contact
GTAC 5288(VoIP)
person

4.2 Check of Equipment Running

 The owner of reporting the KPIs & performance reports are the Huawei

performance team.

 To achieve successful operation we are following the below points once

operation completed.

 The performance KPIs must be checked every one hour after the MDT done
until 6:00 AM (MDT Activity Timings)
Technical support website: Technical support hotline: Page 10 of 19
http://support.huawei.com Fax:
Implementation Solution for Change

 Need to check for any concurrent activity at the time of MDT conflicting with
our planned activity.

4.3 Change Risks and Countermeasures

No. Risk Description Possibility Impact Countermeasure


(High/Middle/ (High/Middle
Low) /Low)
Low Low  Back up alarms,
log, MML ,
CFGMML and
1 Data backup
CFGBCP, DBfile,
device panel,OPT
logs etc.
2 Impact on NEs Low Low No impact
Low Low Control the process and

Risk in change rollback before 6:00 AM


3
duration if some issue can’t be

solved.
4

4.4 Check Before Change

No. Preparations Before Owner Completion Date


Change
1 Solution for changeback in Muhammad Waqas Last two hours of maintenance
the case of failure
time window
2 Test solution Muhammad Waqas Within maintenance time window.
3 Confirming change risks and Muhammad Waqas Within maintenance time window.
emergency measures
4 Readiness of mobile phone DT Team Within maintenance time window.
test card

Technical support website: Technical support hotline: Page 11 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

5 Readiness of change test DT Team Within maintenance time window.


personnel
6 Readiness of relevant PS & CS Team
equipment maintenance Within maintenance time window.
personnel
7 Readiness of support & Mohammed zubair Within maintenance time window
guarantee team
8 Readiness of remote log-in Not available Not available
environment
9 Readiness of emergency FM Team Within maintenance time window.
spare parts
10 Readiness of boards, tools, FM Team & Change
and instruments Within maintenance time window.
Owner
11

5 Operation Steps for Change

5.1 Change Steps

Please find attached below the Activation Script

Activation Script for EDA.txt Activation Script for MultiClass.txt

5.1.1 Overall Description

Activating smooth voice call handover:

Using the LMT

On the BSC LMT, run the

If the Extended Dynamic Allocation (EDA) (per 64Kbps) license is used:

 SET BSCPSSOFTPARA: SUPPORTEDA=SUPPORT;

Technical support website: Technical support hotline: Page 12 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

Activating MS High Multislot Class:

Using LMT:

 SET BSCPSSOFTPARA: SUPPORTDL5TS=SUPPORT;

Activation Observation

1. If the Extended Dynamic Allocation (EDA) (per 64Kbps) license is used:

 On the BSC LMT, initiate PTP message tracing over the Gb interface. Use an MS to
dial a number.

Expected result: In the traced ACTIVE PDP CONTEXT ACCEPT message, the
value of "gprs-extended-dynamic-allocation-capability" or
"egprs-extended-dynamic-allocation" is 1.

1. Obseving MS High Multislot Class.

 Initiate PS message tracing over the Um interface by referring to BSC6900 GSM


LMT User Guide or BSC6910 GSM LMT User Guide.
 Use an MS to download data in the test cell.
 Double-click the traced Packet Downlink Assignment message to query the value of
the "timeslot-allocation" IE
Expected result: In the binary bitmap for the "timeslot-allocation" IE, the number of 1s reaches
the maximum number of downlink timeslots supported by the high multislot capability of the
MS.

Deactivation:

Deactivation Script for EDA.txt Deactivating MultiClass.txt

Using the LMT

On the BSC LMT, run the

If the Extended Dynamic Allocation (EDA) (per 64Kbps) license is used:

 SET BSCPSSOFTPARA: SUPPORTEDA= NOTSUPPORT;


Technical support website: Technical support hotline: Page 13 of 19
http://support.huawei.com Fax:
Implementation Solution for Change

Deactiviting MultiClass using LMT:

 SET BSCPSSOFTPARA: SUPPORTDL5TS=NOTSUPPORT;

5.1.2 Operation Steps for Change

No. Change Step Operation Implementation Time


Person
1 CFG FILE , Alarms, BTS Key Muhammad 23:00~
Data backup
point MML command results Waqas 00:00
2 Muhammad
Operation Confirm with MNOC team to 00:00~
start start the operation Waqas 00:30

3 Muhammad 00:30
Execute the Execute the commands ~02:00
commands following the scripts Waqas

5.2 Test and Verification

1. If the Extended Dynamic Allocation (EDA) (per 64Kbps) license is used:

 LST BSCPSSOFTPARA:;

Verify is BSCPSSOFTPARA is set to support or not

2. If the Extended Dynamic Allocation (EDA) (per TRX) license is used:

 LST BSCPSSOFTPARA:;

 LST GCELLGPRS: IDTYPE=BYNAME, CELLNAME="CellName";

Verify if BSCPSSOFTPARA is set to not-support or not

Verify if EDA is Support in GCELLGPRS or not

No. Operation Item Operation Method Owner Time


1 Implementer
Check Software and Checking the software and
2:00
hardware status hardware status

Technical support website: Technical support hotline: Page 14 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

2 Check whether have any Implementer


reported alarms after the
Check Active Alarms 2:30
operation that related to the
operation
3
Performance KPIs counters
Check Performance KPIs Performance team 2:30~03:00
check on site and BSC level
4

Check service Check the handover Implementer 03:00~04:00

5 To call MNOC team to close


the related MDT after
Call MNOC MNOC team 6:00
confirmation of successful
operation

5.3 Solution for Changeback In the Case of Failure

5.3.1 Definition of Change Failure

 Implementer will recognize the change failure which cannot be


resolved before 5:00 AM
 The dial test shows that calls cannot be made successfully
 A lot of users fail to make or receive calls.
 One-way audio in a large area
 Frequent breakdown and for the Rollback will take project TD
approval.
 Project TD: Maguigeng/00707419
 The rollback timing start from “04:00 to 06:00”

Overall Description of Changeback

Technical support website: Technical support hotline: Page 15 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

Roll Back Using the LMT

Deactivation Script for EDA.txt Deactivating MultiClass.txt

 SET BSCPSSOFTPARA: SUPPORTEDA=NOTSUPPORT;

 SET BSCPSSOFTPARA: SUPPORTDL5TS=NOTSUPPORT;

5.3.2 Information Collection Before Change back

5.3.3 Changeback Steps

Step Time Required


KPIs performance checking 30 mins
Configuring the rollback sciprt 10 mins
Performing the rollback 5 mins
Verifying the rollback 5 mins
Verifying the KPIs 2 hours

No. change Step Operation Implemention Person Time


CFG File, MML, BTS
1 Data Backup Muhammad waqas 1:00
Alarm
Confirm with MNOC
2 Operation Start team to start the Muhammad waqas 1:30
operation
Execute Execute the change
3 Muhammad waqas 2:30~03:00
commands script

5.3.4 Equipment Status Check

1. change owner to Check whether the services are normal.


2. change owner to check the Related KPIs and alarms are normal.
3.DT team to check for the DT results after the Roll back.

Technical support website: Technical support hotline: Page 16 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

5.3.5 Tests After Changeback

 With the support of DT Team need to check the basic services, short calls,
longs call,Sms, DL/UP GPRS/EGPRS and intra and inter handovers.
No. Operation Item Operation Method Owner Time
1 Implementer
Check Software and Checking the software and
2:00
hardware status hardware status
2 Check whether have any Implementer
reported alarms after the
Check Active Alarms 2:30
operation that related to the
operation
3
Performance KPIs counters
Check Performance KPIs Performance team 2:30~03:00
check on site and BSC level
4

Check service Check the handover Implementer 03:00~04:00

5 To call MNOC team to close


the related MDT after
Call MNOC MNOC team 6:00
confirmation of successful
operation

5.3.6 Changeback Risk Analysis

 Its mandatory to collect all the related logs before the start of activity and
check/compare after the Roll back.
 However no risk is involved during the changeback.
Posibilty Impact
No. Risk Description Countermeasure
High/Medium/Low High/Medium/Low
Backup alarms
logs, CFGMML,
CFGBCP, DB
1 Data Backup Low Low
File, Device
Pannel, OPT
Logs
2 Impact on NE Low Low No Impact

Technical support website: Technical support hotline: Page 17 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

Control the
process and roll
Risk in change back before
3 Low Low
duration 6AM if some
issue cannot be
solved

5.4 Change of Spare Parts and Emergency Workstation

N/A

6 Work After Change

6.1 Observation

Sno Operation Item Operation Method Owner Time

Auditing the operation result &


Backup analyze the related Mohammad
1 Day time
daytime performance KPIs & to trouble zubair
shoot for any abnormal issues

6.2 Provision of Materials

 To backup the alarms from both sides, BSC & BTS alarms” from M2000”
 To backup the BSC CFGMML and CFGBCP
 To backup the license and license related information.
 To backup all other relevant alarms.
 To check the sites status on M2000 & BSC/BTS side, whether some sites are having any
outage.
 DT logs result.

6.3 Provision of Software

N/A

Technical support website: Technical support hotline: Page 18 of 19


http://support.huawei.com Fax:
Implementation Solution for Change

6.4 Training

 Training will be arranged upon customer needs & requirements

6.5 Matters Needing Attention

Sbs Team is using dedicated account for all activities in stc network.

Technical support website: Technical support hotline: Page 19 of 19