MINISTRY OF PUBLIC WORKS

DIRECTORATE GENERAL OF HIGHWAYS


TANJUNG PRIOK ACCSESS ROAD CONSTRUCTION PROJECT, PHASE 2
PACKAGE : SECTION N-S, YOS SUDARSO – SIMPANG JAMPEA, JBIC ODA LOAN IP-531

KATAHIRA & ENGINEERS INTERNATIONAL


In association with
JAPAN BRIDGE & STRUCTURE INSTITUTE. INC ,
CONSULTANT PT. VIRAMA KARYA (Persero), PT. INDEC
CONTRACTOR
INTERNUSA, PT. GUTEG HARINDO, PT. POLA
AGUNG CONSULTING, PT. BINA ASIH
CONSULTANTS

SUBMITTAL / TRANSMITTAL RECORD


Ref. No : SMHK-MS-010312.01
ATTN : Mr. Takashi Okumura
SUBJECT : Method Of Statement of Widening
Item No. Item / Subject Location
1 Sheet Piling -

CONTRACTOR’S REMARKS
ATTACHMENT : SAMPLE/RESULT SCHEDULE DRAWING/PLAN
METHODE STATEMENT REPORT OTHERS

FOR YOUR : APPROVAL INFORMATION AS REQUESTED


ACTION COMMENTS OTHERS

NOTE :

Submitted by Receive by

SMCC-HUTAMA JO
Date ……………………………… Date ………………………………
METHOD
STATEMENT
SHEET PILING
FEBRUARY, 2014
TABLE OF CONTENTS
1. GENERAL
2. METHOD STATEMENT
3. MATERIAL
4. EQUIPMENT AND RESOURCES
5. METHOD
6. QUALITY CONTROL PROCEDURE
7. HEALTH, SAFETY AND ENVIRONMENT
METHOD STATEMENT FOR SHEET PILING

1. GENERAL
The installation of sheet piles are the famous type of temporary works for the
construction of building or bridge during foundation works such as pilecap
structural. Steel sheet piles are long structural sections with a vertical interlocking
system that creates a continuous wall.
The walls are most often used to retain either soil or water. The ability of a sheet pile
section to perform is dependent upon its geometry and the soils it is driven into. The
pile transfers pressure from the high side of the wall to the soil in front of the wall.

There are permanent and temporary applications. Permanent sheet piles remain in
the ground and serve as permanent retaining structures. Temporary sheet piles are
designed to provide safe access for construction, and are then removed.

However in the construction works today with amount of contract sum too low due
to the tight competition during tender process and in order to secure profit margin
sometime we overseen and under estimate the ground condition without take
considered the temporary cost such as sheet piles.

Sheet pile design must account for earth, water, and adjacent structures. Sheet pile
design can be straightforward in simple cases, and quite complex in some other
conditions.
Many unknowns and factors that influence the behaviour of the sheet pile wall.
Typically, there are two systems in sheet pile wall that must be designed:

a. Cantilever Sheet Piles - the sheet pile wall that retains the earth and water ( etc.),
Design of cantilever sheet pile wall includes two parts:
- Design the embed length of sheet pile against rotational failure.
- Select the sheet pile section to resist moment and shear.
b. Achored Sheet Piles - the Support System (i.e. the internal or external bracing such as
rakers, struts, or tiebacks) that supports the sheet pile wall.
Commonly assumed failure mode of cantilever and anchored sheet piles are shown
below:
2. METHOD STATEMENT
This method statement describes the method and procedures involved in the
installation of sheet pile wall (refer to attached drawings) as temporary shoring
and facilitate the work relating to the construction of the proposed for fly over
access road Tanjung Priuk NS Direct Project.
The technical specification and other relevant information on machinery and
equipment used in this works are included.
3. MATERIALS
3.1 Sheet Pile
The sheet pile is a U Section and will be installed by means of a Vibro Hammer.
As the pile comes in 12m or shorter lengths, welding will be used to join the
sheet piles if a longer length is required. On the other hand, Oxy-acetylene will
be used to cut the sheet piles if these protrude out and causes a danger to the
trains passage. The sheet piles used will be the type of FSP Type III (British
Standard).
3.2 IWF Beams
Two I-Beams, will be used as a temporary guide for initial start of sheet pile
installation.
4. EQUIPMENT AND RESOURCES
a) Truck crane (minimum 20 M ton)
b) 3 – 7 tons Hydraulic vibro-hammer c/w power pack (depending on site
conditions)
c) Welding set
d) Back Hoe (if required)
5. METHOD
5.1 Work Access
These preparation works proceed both piling and staging activities.
1. The site shall be levelled to allow safe operation of heavy machinery.
2. Steel plates will be provided at locations where the ground is soft and
unable to support the machinery.
3. Fabrication and stocking of material such as sheet piles and other work
related material will be within the bridge ROW. Exact location will be
subject to site constraints.
4. Gas palettes and welding machines will located close to the place of work.
5.2 Work Flow
Before start installation of sheet piles, the location and grid line need to
prepare to control the straightness and verticality on the position. The sheet
piles will be installed between two guides of I-beam and a short temporary
sheet pile location as a guide to install the sheet pile. The temporary short
sheet pile to be use as initial guide, when start installation.
A vibro-hammer suspended with a crawler crane will vibrate the piles to the
required depth.
The following sequence will be used during sheet pile installation:
i) Surveyor locates centre of sheet pile wall.
ii) Appropriate reference line and offset point to the centre of piles to be set
out.
iii) Arrange the piles at each point with the use of a timber frame to ease and
maximise installation.
iv) Use vibro-hammer to install piles, a level may be used in checking the
verticality of the sheet pile wall. Two I-Beams will be used to guide and
correct the pile verticality and position.
v) Piling will continue until the desired depth is attained.
vi) Repeat step iii to vi for the next sheet pile and steps i to vi for every new
sheet pile wall.

Length of Sheet Pile

i) Sheet piles will be delivered in 12m or shorter lengths.


ii) Oxy-acetylene will be used to cut the piles to maintain the designed length.
iii) Once sheet pile walls are installed, waler and ground anchor works will
proceed.
iv) Construction of permanent retaining wall and bridge works shall than
proceed.
v) After completion of one half of bridge works and diversion of track,
dismantling of sheet pile walls will be carried out.
vi) The sheet pile wall will be dismantled in the following sequence:
- De-stressing of tendon
- Removal of anchor head
- Removal of Waler
- Extraction of sheet piles by vibro-hammer
- Stock piling and removal off site.

6. QUALITY CONTROL PROCEDURE


To accurate installation of sheet piles, all the measurement, level and position of
sheet piles will be determined before commencement of the work. If longer sheet
pile required proper welding, join will be used as specification required. Each of
sheet pile installation on interval time, the verticality will be monitored. The
installation will be going on until the length or set required.
7. HEALTH, SAFETY AND ENVIRONMENT
7.1 Working Hour
Line block will be applied during sheet piling works as the sheet pile wall will
be installed very near to the track and might pose a danger to trains as well as
to the track. All PT. WIJAYA KARYA (PERSERO) regulations regarding line blocks
will be adhered to.
7.2 Regulations
All site activities shall comply strictly with PT. WIJAYA KARYA (PERSERO)
regulations and requirements.
Before commencement of works, all relevant staff will be briefed and trained
to comply with PT. WIJAYA KARYA (PERSERO) regulations.
7.3 Inspections
A joint inspection of the track will be carried out with the consultants and PT.
WIJAYA KARYA (PERSERO) before work commenced. Existing track levels will
be monitored at every 5m by checking the settlement marker using survey
equipment within the bridge row before work start. The settlement will be
monitored continuously by visual inspection and survey during works, on
repair before line block removed and after 2 trains passed. If the track settles
more than 18mm), all work will be stopped and a track repair team will be
informed to repair the track immediately. Similar checking will be carried out
for lateral alignment by setting a reference line. If the alignment out by 18mm,
all work will be stopped and a track repair team will be informed to repair the
track immediately.
After installation of the sheet piles, the movement of the sheet piles will be
monitored regularly during and after the excavation works.
7.4 Health
All workers are to wear orange vest, safety helmet and safety shoes within PT.
WIJAYA KARYA (PERSERO) row. All safety issues will be governed by the Health
and Safety plan and adhered to strictly.
7.5 Environmental issues
The Environmental Plan will be adhered to strictly on site.