PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.

JOB ACTIVITY
HIRARC NO: 005 DATE: 15 MARCH 2017
HOLLOW CORE SLAB INSTALLATION
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS

Movement Assign signalman to control


Major Injury
public vehicle 4 4 16 the trailer & traffic before 1 4 4
Death
at public road. entering site

Mobilization of  Assign signalman to


Workers,
the precast control the trailer &
1 material &
components workers.
machinery Major Injury 4 3 12 1 3 4
using lorry  To make sure machinery
movement on
path clear from
site
obstruction & compacted.
Improper
access for  Using ladder & apply
Major Injury
inspection at 3 3 9 safety rules when using it. 1 2 2
the lorry.

1|Page
PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.
JOB ACTIVITY
HIRARC NO: 005 DATE: 15 MARCH 2017
HOLLOW CORE SLAB INSTALLATION
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS
 Assign competent crane
operator with signalman.
 The crane ground surface will
be compacted and stable
area.
 Spreader bar will be use
during lifting for stability.
 Major  Clamp will be use to hoist the
slabs.
Falling Object Injury 4 4 16 2 3 6
 Crane and lifting gear will be
Loading &  Death inspected for safe to use.
Unloading the  Crane load chart will be
2 components & applied for the load &
slabs using unloading activity.
mobile crane  Lifting radius will be isolated
with warning tape to prevent
workers into the lifting area.

 Assign competent crane to


check the surface of the
Crane toppled crane.
Major Injury
due to uneven 4 3 12  The crane ground surface will 2 3 6
Death be compacted and park at
ground
stable area.

2|Page
PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.
JOB ACTIVITY
HIRARC NO: 005 DATE: 15 MARCH 2017
HOLLOW CORE SLAB INSTALLATION
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS
 Assign competent crane
operator with signalman.
 The signalman will apply
orange vest.
Movement of  Major
 Efficient communication
lifting Injury
4 5 20 between crane operator & 2 3 6
material.  Death signalman.
Loading &
 Tagline will be applied.
Unloading the
 Lifting radius will be isolated
2 components & with warning tape to prevent
slabs using workers into the lifting area.
mobile crane
 Workers to wear glove
when performing activity
Sharp edges Minor Injury 2 2 4 1 2 2

3|Page
PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.
JOB ACTIVITY
HIRARC NO: 005 DATE: 15 MARCH 2017
HOLLOW CORE SLAB INSTALLATION
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS

 Lifeline will install when


working at edges.
 Safety harness will be used
and anchored.
Major Injury,
Open edges 4 4 16  Ladder will be used as 1 4 4
death
access.
 Scaffolding will be used as
access or working
platform.

Wrong
Installation of Minor Injury  Apply correct posture for
3 posture
slabs Back pain 2 2 4 manual handling or 1 2 2
during
working.
installation

Minor Injury  Workers to wear glove


Sharp edges 2 2 4 1 2 2
when performing activity

 Apply safety goggles


Dust particles
when performing hacking
through eyes Minor Injury 2 1 2 1 2 2
activity.
when hacking

4|Page
PROJECT TITLE: XEPA NOVO - OSD BUILDING AND CAR PARK.
JOB ACTIVITY
HIRARC NO: 005 DATE: 15 MARCH 2017
HOLLOW CORE SLAB INSTALLATION
SCOPE: LEGAL REQUIREMENT: -
REVISION NO: 00
SUPER STRUCTURE WORK FMA BOWEC (SAFETY) Regulation 1986, Part XIII, Reg. 111 - 118.
RISK ASSESSMENT RISK ASSESSMENT
HAZARD IDENTIFICATION (BEFORE RECOMMENDED (AFTER RECOMMENDED
RECOMMENDED CONTROL
NO JOB SEQUENCE CONTROL MEASURES) CONTROL MEASURES)
MEASURES
POTENTIAL POTENTIAL Likelihood Severity Risk Rating Likelihood Severity Risk Rating
HAZARD RISK L S LxS L S LxS

 Sharp edges
of the
 Mandatory PPE, gloves will
Housekeeping material
4 Minor Injury 2 2 4 be applied for this activity 1 2 2
activity  Wrong body
 Correct body posture
posture

Prepared by: Review by (HSSE Department): Approved by (Project Manager):

…………………………………………………………… ……………………………………………….. …………………………………………………….


Name: TENGKU AHMAD WILDAN BIN TENGKU AZAN Name: MOHD RAMDHAN BIN MOHD SAID Name: YAP KOK YAW
Date : 15 MARCH 2017 Date : 15 MARCH 2017 Date : 15 MARCH 2017