Sie sind auf Seite 1von 31

Lecture Notes

CHAPETR IV
PROCUREMENT AND CONTRACTUAL MANAGMENT
In this chapter the following section will be covered to some detail.
❖ Procurement and Contract ❖ Types of Construction

Management Process ❖ Stages in


❖ Procurement and Contract Construction
Delivery Systems
❖ Contract Documents
Contracts
❖ Term of Reference ( TOR)
Introduction

Construction Industry involves procurement and contract management systems in order to


ensure fair competition and distributions of obligations and rights among stakeholders.
Competition helps:

• The Project Owners' to acquire the five rights (Counterpart, Cost, Time, Quality and Quantity)
s/he is entitled to
• The Project Financiers' and Regulators' to value market principles and effective utilization of
finance such that lowest qualified bids takes the project , and
• The Project Providers' to get impartial and neutral Opportunity for business.

Obligations and Rights help to allocate appropriate risks among contractual parties and their
remedial rights. That is, their entitlements and provisions are clearly stated and agreed upon.

Project Owners shall consider its own particular institutional and technical SWOT (including
access to financing) before selecting which procurement and contract forms to adopt for its
projects. These include the design source, allocation of coordination responsibilities and the
pricing methods.

Each type of contracting affects, in its own way, the allocation of responsibility & the
demands on the Employer for coordination of the project. Through properly allocating these
responsibilities for the project to reflect the results and recommendations of the SWOT's,
Project Owners' can rationalize the contract price against its exposure to project risks. Project

34
Lecture Notes

Owners' are at liberty to use either its own in-house capacity or to allocate them to one or
more other parties (Private and / or Public).

Procurement and Contract management has a strong linkage and relationship with
Construction Process and Stakeholders Management. The delivery system chosen, the
procurement method adopted and the contract types decided upon determine the
construction process involved and the relationships and roles of stakeholders along the
process.
4.1. Procurement & Contract Management Process

Procurement and Contract Management involves three major processes: Contract Planning,
Procurement Management and Contract Management (Figure 4.1).

Contract Planning: Construction projects are components of a certain business or


development demands. That is, they are formulated if and only if such businesses or
development demands acknowledge their contribution and it is a must to involve them. This
requirement is dealt during the basic / strategic planning phase of the over all business. This
phase often pass through the identification, feasibility and financing stages of Programs or
Projects. Contract is a customary tool used to implement formulated programs or projects. As
a result, contract planning becomes part of this basic / strategic phase.

Delivery System Contract Formulation


Procurement Method Contract Administration
Contract Types Contract Closing
i
Procurement Contract
Management Management
Contract
Planning _/rd Procurement Preparation
Tendering
Tender Evaluation & Notice of Acceptance

Figure 4.1: Procurement and Contract Management Processes

_________________________________ 35 __________________________________
Lecture Notes

Contract planning includes decisions on proposed Delivery Systems, Procurement Methods


and Contract Types to be followed and used together with its provisions for alterations. This
is because such decisions are related to regulatory requirements such as:

■ Ethical (Neutrality, Formality, and Impartiality);


■ Economical: (Proof of Competition, Least Qualified and Evaluated Bidder);
■ Accountable: (Obligations and Rights);
■ HSE (Health, Safety and Environment); and
■ Transparent: (Accessibility and Notice of Advertisement).

Procurement and Contract Management processes shall be based upon the approved contract
planning provisions; that is, the contract delivery system, the procurement method and
contract types decided upon. The approved contract provisions can only be changed
following the change process stated in the contract planning document and if and only if:

■ the Environment and Context considered are not correctly analyzed or changed,
■ their application can remarkably affect the objective of the project, and
■ procurement management process justifies change of the Contract Types.

Once the validity of the contract provisions are checked once again and taken for granted or
other provisions are devised; Procurement Management followed by Contract Management
can be initiated, planned, implemented, monitored and closed.

Among the three important contract Planning Provisions, Procurement and Contract
Delivery system is dealt in section 4.2. Procurement Methods will be dealt in the course work
of Contract Specification and Quantity Survey. And Contract Types are covered to some
extent in section 4.3.

Procurement Management: is a process of selecting individuals or organizations to carry out


the intended services and / or works. Procurement Management is carried out based on the
provisions made during the contract planning phase of the Procurement and Contract
Process. It involves the preparation of procurement documents, their invitation and
submission of tender proposals, and Opening and Evaluation of tenders. On the bases of
results from tender evaluations, the procurement team will recommend the lowest responsive
bidder for Contract Management Phase.
________________________________36 ______________________________
Lecture Notes
The following issues are necessary for a successful Procurement Management phase:

> knowing and ensuring the implementation of procurement related National and International
laws, rules and regulations,
> adherence to the provisions made during the contract planning phase including their change
processes that is; with respect to: Delivery Systems, Procurement Methods and Contract
Types,
> establishment of a flexible procurement team, and
> adhering to the principles of Proof of competition, Impartiality, Neutrality, Accessibility and
Formality.

Contract Management: is a process of reaching contractual agreement for implementation, its


administration and finally concluding the contract. Similar to the procurement management
process, it shall be based on the provisions decided during the contract planning phase. It
involves negotiation based on tender evaluation recommendations and signing of contractual
agreement followed by its administration for contractual implementation, progress tracking,
and changes, claim and disputes administrations.

The following issues are necessary for a successful Contract Management phase:

> knowing and ensuring the implementation of contract related National and International laws,
rules and regulations,
> adherence to the provisions made during the contract planning phase including their change
processes, that is; wrt Delivery Systems, Procurement Methods and Contract Types,
> identifying, recognizing and involving all potential or key stakeholders to form a contract
team,
> understanding, mapping and monitoring all contract conditions agreed upon, and
> ability to administer changes, claims and disputes.

4.2. Procurement and Contract Delivery Systems

Procurement and Contract Delivery system is the way Project Owners together with Project
Regulators and Financiers determine the assignment of responsibilities to Project

37
Lecture Notes

Stakeholders along the Construction Process. Procurement and Contract Delivery system is
often determined during the Basic Planning phase of Construction Project.

Generally, there are six types of Procurement and Contract Delivery systems. These are:

> Force Account, > Construction/Facility Management


> Design Bid Build (DBB), Consultancy, &
> Design Build (DB) or Turnkey, > Alliances and Outsourcing.
> Finance / Build Operate System (BOT),

Such Procurement and Contract delivery systems are developed overtime and are shown in
Fig. 4.2 below. The development was based on problem solving for the previous type and the
Development of the Construction Industry technologically and management wise.

Force Account - Since development started

*+■ Design Bid Build (DBB) - 1950s / 1987

Desian Build (DB) / Turnkey - 1970s Onwards / Mid 1990s

Finance / Desian Build Operate - 1980s / .................

CM / Facility Management - Mid 1990s / 2000s

Alliances & Outsourcing - 2000s / 2000s


V y

Figure 4.2: The different Procurement and Contract Delivery Systems and their development overtime

4.2.1. Force Account

When the Project Owners engage themselves to undertake the project, it is called a force account
delivery system. Often such a system is promoted if the Project Owners believe that there is a
comparative advantage in Cost, Time and Quality issues. Besides, when there is a lack of capacity
from the private sector to undertake very large and technologically new projects, public companies
do undertake such projects using Force account delivery systems.

38
Lecture Notes

These days this type of delivery system is often used when projects are small and places are remote
such that reaching them is difficult and in general they are not attractive enough to call the
attention of Bidders. Besides when projects are spatially scattered and maintenance are to be done
for schools, colleges, health centres etc., such cases can be applied.

4.2.2. Design Bid Build (DBB)

This is the most practiced type of delivery system in the Construction Industry of Ethiopia since
the 1987. After project owners did prepare the Basic Planning that identifies construction
project programs, they call upon the participation of Design and / or Supervision Consultants
either by tender or by negotiated contracts. This consultant will carry out the design together
with the necessary tender documents which will be the bases for tendering to select
contractors. These process is called Design - Bid - Build and hence the name for such delivery
system.

In this type of delivery system, projects are divided into different packages interfacing to
each other. Though the design and supervision consultant will be the prime professional on

behalf of the owner and largely the administrator of the construction contract; the
employer takes the responsibility of coordinating the various project packages and their
respecting interfaces.

Besides, designers have not been required to guarantee results but rather methods. That
is, they are held accountable on the basis of their superior knowledge and sufficient
competency and ability to design with a reasonable degree of technical skills. As a
result, contracts and courts focused on professional duty of care, not results or project
goals. Contractors are also responsible to construct works with due care and diligence
and complete them in accordance with the contract, but they are not held responsible
for design deficiencies.

Since the 1980s, this traditional approach becomes less popular due to the following
factors:

_________________________________ 39 __________________________________
__________________________________________________________________________________________Lecture Notes

• Severe Adversarial relations between the design and contract administration consultant and the
contractor
• Fragmented contract for the project owner
• Project owner responsibility for risks associated with the design and contract administration
• Non - Impartiality of the Design and Contract Administration services
• The inability of design and contract administration consultants to cope up with new
construction technologies and constructability issues of their designs
• Severe adversarial relationships between Urban Planners and Architects on the one hand; and
Architects and Engineers on the other hand on building projects
• The indirect contractual obligation assigned for the Design and Contract Administration
consultants
• The incompatibility of consultancy fee to the desired activities they are required to provide, etc.

The following standard forms of DBB Conditions of Contract are known for use for such
delivery system:

■ FIDIC White Book for Consultancy Services (Design and Supervision) and Red Book for

Construction Works

■ Standard Conditions of Contract for Construction of Civil Works, 1994; MWUD

4.2.3. Design Build (DB) / Turnkey


Design Build or Turnkey Delivery system is a response to problems associated to the last two
types of delivery systems. These were promoting privatization and its business like approach to
enhance the Force Account System and reducing fragmentation, adversarial relations and
Project Owners' risk which are recurrent manifestations in the DBB delivery system.

Design Build or Turnkey by principle reduces numbers of procurement processes engaged in


the fragmented process and employ only one procurement process and a single contractor to
provide the entire Construction Implementation Process (Design and Construction
Implementations). In the 1970s, large firms began to offer both design and construction services
in order to provide project owners with a single source for project delivery. At the beginning,
this delivery system was limited to complex projects such as industrial, big plants and big
infrastructural constructions.
40
__________________________________________________________________________________________Lecture Notes

DB delivery system is common worldwide specifically for Private projects. This led lead
contracting firms to form a team or consortium of designers and specialty contractors who work
together to meet the entire demand. Such services are initiated after the Project Owner built
the project concept during the basic planning phase and brought to the DB Contracting Firms.
The project concept should clearly define the performance criteria such as output, input, waste
and any other performances the employer may desire. This makes an additional responsibility
to the contractor which is "fitness to purpose" according to the Orange Book of Fidic. Fitness to
purpose is beyond the professional duty of care and places liability on the contractor for any
failure of the design to perform the standards required.

Typical advantages of this system include:

• reducing fragmentation and adversarial relations between designers and constructors;


• minimizing Project owners' risk transferable due to Designers' faults;
• accountability and entire responsibility for both design and construction which entitle the
employer to receive completed project is onto a single contractor;
• employers' responsibility to co-ordinate interfaces between different project elements is avoided;
• single point responsibility minimizes the opportunity to claims by the contractor due to design
related issues;
• coordination between design and construction processes will also be enhanced (both in
communication for constructability as well as in fast tracking); and
• the client budget or financial requirement is defined early enough in the development process.

For this type of delivery systems, either joint ventures or firms with large design and
construction capabilities were able to participate.

The disadvantage of this delivery system is loss of control, cost of tender and cost of risks.

■ Since limited supervisory role by the employer representative is practiced; which is relatively
flexible and makes the employer distanced from the whole process, the employer has little
chance to understand what is developed and entertain variations in requirements implying loss
of control.
■ Contractors in order to provide reasonable offer, their tender cost is higher than in the case for
DBB delivery system. This is because they need to carryout acceptable design for project cost
41
__________________________________________________________________________________________Lecture Notes

offers. Though it was not practiced often, employers who shared costs related to tendering are
informed to get seriously considered offers. World Bank suggested a Two staged procurement
method based first on technical merit and followed by financial competition and not for more
than six bidders.
■ The increase in risk transferred onto the contractor will be counterbalanced by the increase in
contract prices which can be taken to include these costs of risks.

Projects carried out using DB delivery system are often called Turnkey Projects because a single
contractor is responsible to hand over the completed facility and let the Project owner to turn
the key and gets in. Often Turnkey projects use Lump-Sum contract type which will be
discussed in section 4.3. The following standard forms of DB Conditions of contract are known
for use for such delivery systems:

■ FIDIC Orange Book ICE Design & Construct Conditions of

■ ENAA Model Form International Contract

Contract EIC Contract


AIA Contract Form A191
4.2.4. Finance / Build Operate Transfer (BOT)

Build - Operate - Transfer is a form of procurement and contract delivery system that promotes
Public Private Partnership (PPP) in which a private company is contracted to finance, design,
construct, operate for a certain period (usually 10 years) and transfer. BOT contractors look to
project financiers for the realization of projects through equity contributions or credits. Such
provisions are different from budgetized finances such that they involve no or limited re -
course which means the project owner is not responsible for any liability other than force
majeure and agreed upon claim adjustments. This obliges that projects should first be viable for
revenue generation in order to payback its depts.

The Typical BOT contract is the process whereby a government grants a concession to a project
development company to develop and operate what would normally be a public sector project,
for a given period of time known as the concession period. BOT project involves a potentially
complex contractual structure. The Operation period between completion and transfer gives
the contractor an opportunity to verify the quality of the output of the services and works, and
42
Lecture Notes

train the employer personnel on how to manage the facility afterwards. In some BOT contracts,
defect liability period will be included in order to ensure the quality of the facility during
transfer. This is because, operators in an attempt to save costs, may decrease operating and
maintenance expenditures towards the end of the concession period.

This delivery system is advantageous because of three major factors:

■ it minimizes owners' scarcity of financial resources;


■ It devoid of considerable risks from the project owners and lesson regulatory activities; and
■ the facility is well operated and transferred with free of charge or minimum compensations to
project owners.

Such delivery system requires appropriate packaging of projects and their definition clearly. It
is advisable to start with small projects and tries to develop experience and expertise to make
such delivery system successful. Most BOT projects failed because of their built up and
engagement in very large projects which is an extremely risky business for contractors.
Consortium of contractors is used to carry out such projects. The increasing popularity of the
BOT project is largely due to a shortage of public funding and the opinion that the facility will
be more efficiently managed by a private entity.

The following standard forms of BOT Conditions of Contract are known for use for such
delivery systems:

■ FIDIC Yellow Book

4.2.5. Construction / Facility Management Consultancy

Construction Management Consultancy Delivery System is a response to problems associated


with DB and BOT where the Project Owner was not well represented for its benefit and the
problem of fragmentation between Planning and Implementation. As a result, construction
management consultancy firm is used to coordinate all activities from concept inception
through acceptance of the facility. Facility management consultancy adds operation of facility
during operation to Construction Management Consultancy.

35
Lecture Notes

Construction Management service in such delivery system include the management activities
related to a construction program carried out during the Basic Planning, Design & Construction
Implementation and its completion process that contributes for the successful completion of
projects. The main difference of this delivery system is that, while all the others involve only
during the implementation phase after major decisions was made during the Basic planning
phase of the construction process, it is involved in the whole construction processes.

Construction Management Consultancy service are particularly attractive to organizations that


involve in construction physical infrastructures such as MoE, MoH, Real Estate Organizations,
MoWRs, MoT&C, etc. Construction Management Consultants then represents Project Owners
to carry out the following services:

• Feasibility studies of Construction related services


• Plan and Monitor the Triple Constraints of Project Performances
• Lead and Organize regulatory systems of the Construction Industry
• Valuation, Quantity Surveying and Procurement and Contract Management Services

4.2.6. Partnering, Alliances, Outsourcing (Running and Specialized Delivery System)

The need for constructing quicker, cheaper and to a higher quality of physical infrastructure by
clients and at the same time with very minimized or no dispute questioned fragmentation of
packaging, costs related to wastes and overheads, single staged procurement systems, involving
in less competitive and comparative advantage for services and works and existing stakeholders
relationships. As a result,

■ running delivery system using Partnering and Alliances,


■ specialized delivery system using Outsourcing,
■ fast tracking, parallel and coordinated implementations using Concurrent Engineering and Just
in Time principles

which focuses most on management of relationships and value adding to ensure quicker,
cheaper and quality services and products with less disputes are recent developments. These
systems require to overcome cultural and behavioral barriers among interest groups and control
motivated performance based management. These types of delivery systems are often the bases

36
Lecture Notes

behind DB, BOT, FM\CM consultancy delivery systems but their at most and recent
developments.

4.3. Types of Construction Contracts

Contracts for the execution of civil engineering works are of following type:
(a) Lump sum contract
(b) Unit rate contract
(c) Lump sum and schedule contract
(d) Cost plus fixed fee contract
(e) Cost plus percentage of cost contract

A. Lump Sum Contract

In this type of contract, the contractor offers to do the whole work as shown in
drawings and described by specifications, for a total stipulated sum of money. Lump
sum contract are typically used for buildings. The qualities of the materials required
can be calculated with sufficient accuracy during the bidding process to allow
contractors to submit a single lump sum price for the work.

There are no individual rate quoted, thus it becomes difficult to make adjustments in
the contract value of any changes are to be made in the work later on.

A lump sum contract is more suitable for works for which contractors have prior
construction experience. The experience enables the contractors to submit a more
realistic bid. This type of contract is not suitable for difficult foundations, excavations
of uncertain charter, and projects susceptible to unpredictable hazard and variations.

B. Unit Price or Bill of Quantity

Also called a schedule contract, in this contractor undertakes the execution of work
on an item rate basis. The amount to be received by the contactor depends upon the
quantities of various items of work actually executed. The payment to the contractor
is made on the basis of detailed measurements of different items of work actually
done by him.

Unit-price contracts are used for work where it is not possible to calculate the exact
quantity of materials that will be required. Unit-price contracts are commonly used
for heavy/highway work.

37
Lecture Notes

The designer may calculate that 1,000 m3 of earth needs to be moved, but the owner
and contractors know that after the work has been completed, the contractor may not
move exactly 1,000 m3. The exact quantity will usually vary.

Contractors submit a price for each item on a unit-price contract. Unit prices are
multiplied by the engineer's estimated quantities and totaled. The low bidder is the
bidder with the low total of the all items. Items whose actual quantity varies from the
estimated quantity by more than 15 or 20%, either above or below the estimated
quantity, are sometimes subject to renegotiation of the unit price.

Bill of Quantity

The unit price contracts are usually presented in the Bill of Quantity. A Bill of
Quantity (BOQ) shows the items present for the construction work with the
associated specification and the estimated quantity with the Unit price for each of the
items.
Item Description Unit QTY Rate Amount
no
A-SUB STRUCTURE
1. EXCAVATION & EARTH WORK
1.01 Site clearing and removing of top 200mm thick
soil
m2
1.02
Bulk excavation in expansive soil to a depth not m3
exceeding 1500 mm.
1.03 Pit excavation for footings in expansive soil to a
depth not exceeding 1500 mm. m3

1.04 Ditto exceeding 1500 mm but not exceeding


3000 mm. m3
1.05
Back fill around foundation with brought
material from outside well rolled and compacted m3
in layers not exceeding 200 mm thick.

1.06
Fill under hardcore with brought material from
quarry waste and compact with layers not m3
exceeding 200 mm thick.
1.07
Cart away surplus materials from the site as per m3
the Engineer's instruction.
1.08 m2
250 mm thick basaltic stone hardcore well
rolled, consolidated and blinded with crushed
stone.
Total carried to
Summary ...................................................

_________________________________ 38 __________________________________
__________________________________________________________________________________________Lecture Notes

The item rate contract is most commonly used for all type of engineering works
financed by public or government bodies. This type of contract is suitable for works
which can be divided into various items and quantities, under each item, can be
estimated with accuracy.

C Lump sum and scheduled contract

This is similar to the lump sum contract but schedule of rates is also included in the
contract agreement. In this type of contact, the contractor offers to do a particular
work at a fixed sum within a specified time as per plans and detailed specifications.

The schedule of rates for various items is provided which regulates the extra amount
to be paid or deduced for any additions or deletions made during the progress of
work. Measurements of different items of original work are not required but extra
items are required to be measured for payment. The original work shall however be
checked and compared with the drawings and specifications.

The type of contract is more suitable for construction works for which contractors
have prior work experience and can consequently estimate the project cost more
realistically.

D. Cost plus

Cost plus (cost reimbursable) contracts are used in situations that make it difficult or
impossible for either the owner or the contractor to predict their costs during the
negotiation, bid, and award process.

Factors that may make the calculation of costs impossible include unpredictable and
extreme weather conditions such as would be encountered in the Antarctic, known
transportation requirements to remote locations, combat or war, or contracts where
the amount of effort that will be required depends on another contractor's work.

Cost plus contracts take many forms, the most common being cost plus fixed fee and
cost plus a percentage. Most owners prefer cost plus fixed fee because then the
amount of profit the contractor will earn cannot increase, thereby removing any
incentive for the contractor to be anything less than thrifty, or to produce poor-
quality work.

Cost plus percent contracts may be fair in situations that are very difficult, or when
the time to complete the work is not known with any certainty, but some incentives
to maintain productivity are needed.
39
Lecture Notes

D.1. Cost plus Fixed Fee Contact

Cost plus fixed fee contract is desirable when the scope and nature of the work can at
least be broadly defined. The amount of fee is determined as a lump sum from a
consideration of the scope of work, its approximate cost, nature of work, estimated
time of construction, manpower and equipment requirements etc.

In order to negotiate such a type of contract, it is essential that the scope and some
general details of the work are defined.
The contractor in this type of contract is selected on the basis of merit rather than the
fee alone. In case of cost plus percentage contract, the contractor has a tendency to
increase his profit by increasing the cost of work.

But this drawback is overcome in cost plus fixed fee contract because here the
contractor's fee is fixed and does not fluctuate with actual cost of work. Once this fee
is fixed, the contractor cannot increase the cost of work.

D.2. Cost plus Percentage of Cost Contract

In this type of contract, instead of awarding the work on lump sum or item rate basis,
it given on certain percentage over the actual cost construction. The actual cost
construction is reported by the contractor and is paid to him by the owner together
with a certain percentage as agreed earlier.

The contractor agrees to do the work in accordance with the drawings, specifications
and other conditions of contract. In this type of materials and labor are arranged
between the client and the contractor.

The tendency of the contractor to increase the cost of work to earn more profit by
way of percentage of enhanced actual cost is the major demerit of this contract type.

Special Contracts

There are certain special contracts which are used at different occasions. Some of
these contracts are listed below.
• Turn-key Contract
• Package Contract
• Negotiated Contract
• Running Contract

40
Lecture Notes

4.4. Stages in Construction

The following are the formal stages for a construction project:

4.4.1 Inception and feasibility


At this stage the owner puts his visions and wishes and with this as the starting point,
the various groups (professionals) try to conceptualize the project and prepare a
conceptual design.

Then cost/benefit analysis is carried out to ascertain feasibility. And also


Environmental impact assessment should be properly carried out.

Steps:
• Carry out preliminary technical and non-technical investigations
• Select the most feasible alternative

Selection and Evaluation of Consultants

Consultants are selected, basically, using one of the following methods:


♦♦♦ Public announcement
♦♦♦ Short listing
♦♦♦ Direct negotiation

For all the three procedures, the owner has to prepare the Terms of Reference (TOR)
for the consultancy service that is required to be performed and the evaluation
criteria or guide line set.

General Guideline for Evaluation


-The firm's general experience in the field of assignment.
-The qualification and competence of the personnel proposed for the assignment and
-The adequacy of the proposed work plan and approach in responding to the TOR.

Even though the relative importance of these categories may vary with the type of
project in this particular case more emphasis is given for the firm's general experience
in the field of assignment and the qualification and competence of the assigned
personnel.

41
Lecture Notes

4.4.2. Planning and Design stage

Planning is a function of devising the cause for future with a vision, formulated for
the future state of the organization or project. Planning leads to organizing and
staffing followed by directing, controlling and coordinating.

Steps:
• Finalize the selected alternative
• Carry out detailed technical investigations
• Prepare detailed designs
• Prepare working drawing and specifications
• Prepare final cost estimates(engineering estimate)
• Prepare construction schedule
• Get the project approved by regulatory bodies

4.4.3. Tendering stage

At this stage contractors are invited to offer their best technical and financial offers as
per the conditions and specifications depicted in the contract documents. Usually a
2% of bid bond is required so as not let him disappear.

4.4.3.1. Construction Tendering Procedures

The methods of tendering can be made in three different forms:

a. Open tendering: this is a method where the construction work will be


advertised, inviting all eligible constructors to compete for winning the job.
Advantages:

^ Allows all interested contractors to participates


^ Avoids bias
^ Ensures good competition
^ Prevents formation of rings by contractors

b. Short listing: in this case certain construction firms are invited to participate
in the tendering.

c. Negotiated contract: here a known contractor is identified and negotiation is


conducted with him.

42
Lecture Notes

4.4.3.2. Bid Evaluation / Evaluation of Tenders

The bids are evaluated based on:


• Compliance with the contractual terms and conditions,
• Correction of bid prices,
• Detailed analysis.

Generally, a good contractor for a project is an important factor contributing to its


successful completion and the client's professional advisers may look for the following
attributes when drawing up a list suitable contractors from whom to invite bids:

• Contractor's reputation in business:


A contractor's good past record of
performance in the construction business is considered; for example, the
number and monetary value of projects the contractor has completed
successfully and high standard of workmanship are the attributes of a
reputable construction company.

• Contractor's financial standing:


The knowledge of a contractor's current
financial standing or likely to for into liquidation and, hence, there is the need
for a bank guarantee or caution when dealing with that contractor in business.

• Contractor's potential resources: The contractor's potential resources embrace


his or her physical as well as human resources. For example, buildings, offices,
workshops, factories, fixed plant and machinery, the number and type of trade
operatives regularly employed and the quality of management personnel (at
the hand office and on site), their technical knowledge and experience.

• Contractor's normal conduct of business: Considerations under this heading


include the type of work package normally undertaken by the contractor's
own direct operatives and those that are normally placed as sublets: the
categories of clients(e.g. public, private) the contractor chooses to work for
and the type of projects in which the contractor specializes (e.g. new build,
maintenance or refurbishment).

• Contractor's attitude on contractual claims: Contractors who have a good


record of not being claim conscious or claim loving and who take legal action
only as a last resort is a sign of flexibility in resolution of construction disputes.
• Non-economic factors, contractors may be selected for reasons unrelated to
performance; for instance, a contractor may be appointed to faster business
relationship (subsidiary company) or to maintain or promote employment in a
locality.

_________________________________ 43 __________________________________
Lecture Notes

The first step in the evaluation of bids is the public opening and reading of offers in
the presence of all competitors. At this stage the names of tenderers offering bids are
read out as written and recorded, with a general check on establishing conformity
with instruction to tender, completeness of tenders, validity of tenders, and check on
the bid security. Next to this the client/consultant then starts the formal bid
evaluation process.

Over the years the bid evaluation process has been updated and refined to reflect the
changing trend of the construction industry. In general it can be considered to have
three components. Which are:

^ General Contractual and Administrative Evaluation,


^ Technical Evaluation,
^ Financial Evaluation.

4.4.4. Award of Contract

After the negotiations have been successful, the contract will be awarded to the
successful contractor.

Steps:
• Write a letter of acceptance
• Write the letter to proceed with the works
• Performance bond: 10% a guarantee that he will do the job as per agreed

There are different methods & types of construction contracts. The owner generally
makes the selection. The type selected depends on the kind of work being performed
and the conditions under which it is being performed.

4.4.5. Construction Stage

Here is where the actual execution of the works takes place as per scheduled.
Construction schedule comprises of:
• Performance schedule
• Equipment schedule
• Material delivery schedule
• Manpower schedule
• Financial schedule

4.4.6. Commissioning and Acceptance

_________________________________ 44 __________________________________
Lecture Notes

Commissioning is a process where by the contractor makes sure that all installed
mechanical or electrical parts are operational. During commissioning, therefore all
such parts are run in the presence of the client or his representative as per the
conditions agreed.

Acceptance:
Acceptance has to stages:
a. Provisional acceptance:
In this acceptance, the client accepts the completed works on provisional basis
for a period one year. During this period all payments except the retention
money are paid. The other option is to release the retention money and
require for a bank or insurance security.

b. Final acceptance:
At this stage the owner completely accepts the works executed and the
retention money is released to the contractor. But if the client found out some
construction default during this period, he can oblige the contractor to work
out that default or the client himself worked it out from the retention money.
The contractor is assumed to have completed his contractual obligation from
this time on.

4.5. Contract Documents

4.5.1 The make up of a CONTRACT

The makeup of a contract, whether the owner is a public agency or a private


corporation, is essentially the same. The form of the documents may change, but the
elements of the contracts are the same.

Legal Definition of Contract

According to the Civil code of Ethiopia, Art.1675:

A contract is an agreement whereby two or more persons as between themselves


create, vary or extinguish obligations of a proprietary nature.

Formation of Contracts: -

^ There must be a valid offer and acceptance.


^ There must be meeting of minds.

_________________________________ 45 __________________________________
Lecture Notes

^ Capacity of parties.
^ Written/ Oral form.

Objectives of Contracts (Art. 1711 - 1718): -

^ The object of the Contract must be sufficiently defined


^ The object of the Contract must b possible
^ The object of the Contract must be lawful

Concepts and Basic Terms of Contracts. -

Offer: - proposal to enter into a contract.


Acceptance: -
Performance of Contracts: -
Performance - fulfilling respective legal obligations
Extra - Contractual Liability: -

4.5.2. Construction Contract Documents

The main contract documents are Invitation to tender, Instruction to tender, Form of
tender, The Agreement, Condition of contract( General and Particular), Specification
(General and Particular), Bill of Quantities, Drawings, Addenda and Appendix to
Tender.

4.5.2.1. Invitation to Tender: -

An initiation letter to the contractor to participate in the tender with an


acknowledgment attached.

4.5.2.2. Instruction to Tenders: -

The contractor is given directive of what is required of tenders. It includes:


• Tendering procedures, bid bond, data, space, time
• Commercial requirements
• Information in what shall be submitted with the tender (alternative proposals
etc)
• Scope of work
• Tender basis
• Tender bond (possible)

46
Lecture Notes

4.5.2.3. Form of Tender

This is a document where the contractor:


• Confirms, that he has examined all the tender documents
• Confirms that he will perform the work
• Promises that the validity of the tender is open for a certain period
• Shows his understanding that the lowest bid or any after may be rejected
• States that part of the work may only be accepted
• Confirms that he will enter into an agreement if awarded

4.5.2.4. Agreement

The agreement is the document that represents and reflects the legal contract
between the owner and the contractor. Obviously there is also a contract between the
owner and the designer, and between the general contractor (GC) and the sub-
contractors, or between the contractors and the suppliers for those contracts.
• It is simply a letter that constitutes legal evidence that a contract exists, and
forms the basis for its enforcement.
4.5.2.5. Conditions of Contract

The condition of contract is a document that states the obligations and highs of the
parties and detail the conditions under which the contract is to be carried act.

It states to what extent should be the relation between the engineer, contractor and
client. It includes General and Supplementary or Special/Particular conditions of
contract.

4.5.2.5.1. General Conditions

A document called the General Conditions is an essential part of the contract. It


defines the responsibilities of the parties involved in the contract- the owner and the
general contractor. It describes the guidelines that will be used in the administration
of the contract
• It is often referred to as boilerplate, implying that the same documents are
standard to all contracts. Contractors must know exactly what is contained in
the boilerplate.
• Various standard forms of General Conditions have been development by
different organizations. These forms are familiar to all parties concerned, and
the wording is not only clearly understood, but has also been tested in the
courts.

47
Lecture Notes

4.5.2.5.2. Supplementary Conditions

The Supplementary Conditions are sometimes known as Special Provisions or Special


Conditions. The purpose of the Supplementary Conditions is to provide an extension
of the General Provisions of the contract to fit the specific project at hand.

They serve as amendments or augmentation to the General Conditions. Items


included in the Supplementary Conditions are entirely subject to the discretion of the
owner, and may include topics such as:
• The number of copies of contract documents to be received by the contractor
• Survey information to be provided by the owner
• Materials provided by the owner
• Changes in insurance requirements
• Phasing requirements
• Site visit
• Start date of the construction
• Requirements for security and temporary facilities
• Procedures for submittal and processing of shop drawings.
• Cost and schedule reporting requirements
• Traffic control and street cleaning requirements
• Responsibilities fir testing of materials
• Actions to be taken in the event of discovery of artifacts or items of historical
value

4.5.2.6. Specifications

Specification may also be known as Technical provisions. They are written


instruments to be used in conjunction with the drawings, so together the drawings
and the specifications fully describe and define the requirements of the contract, to
include the quality that is to be achieved.

They supplement the drawings and provide information that cannot be shown in
graphic form, or information that is too lengthy to be placed within the drawings.
They guide bidders in the preparation of cost proposals as well as field execution of
the work.

They also guide the contractor through the processes of ordering materials and
construction and installation of the facility.

48
Lecture Notes

4.5.2.7, Bill of quantity

Describe the expected amount of work (measured) in works; it sets out the units of
measurement, the units of work, the unit price and the total cost of the works.

4.5.2.7. Drawings

Drawings are the means by which the designer conveys the physical, quantitative,
and visual description of the project to the contractor. The drawings are a two-
dimensional representation of the physical structure that meets the objectives of the
owner. They are also known as plans or blueprints.

4.5.2.8. Addenda

Any change to the bid documents after they are released for bidding but before bids
are actually received requires the issuance of an addendum.
• This formal document changes the original bid documents and becomes a part
of the bid package.
• At the time of bid opening, bidders must in their bid documents, acknowledge
all addenda.
• Technically addenda may be issued to change the bid opening date, to modify
the original design, to delete or add items, or to correct errors.
• Addenda may not be issued within about five days of bid opening unless the
bid date is also extended accordingly.

_________________________________ 49 __________________________________
Lecture Notes

4.5.2.10. APPENDIX TO TENDER

APPENDIX TO THE CONSTRUCTION AGREEMENT

Clauses
Maximum amount 10 10 percent of the contract price

Minimum amount of third party insurance 23 Birr 35,000.00 per occurrence with party
insurance number of occurrences, unlimited.

Time of commencement 41 15 calendar days from signing of the


contract agreement

Time of completion 43 90 calendar days

Amount of liquidated damages 47 1/1000 of the contract price per day

Limit of liquidated damages 49 20 percent of the contract price

Defects liability period 59 365 calendar days

50
Lecture Notes

Percentage of retention money 60(4) Zero percent

Minimum amount of interim certificate 60 10 percent of the interim payment certificate


amount

Advance payment 60(8) 20 percent of the contract price

4.6. Preparation of Term of Reference (ToR)

Term of Reference is a document prepared by the procuring agency, either public or


private, for the procurement of goods, services and works. It indicates what is
expected from the procurement process and states the expected end result. Such a
document shall be prepared with much care and expertise.

Term of References can have different form. The following term of reference is
prepared for research project proposal preparation.

TERM OF REFERENCE FOR WRITING A PROJECT PROPOSAL

1. PURPOSE

A project proposal provides a description of the project and how it will be conducted
and thus serves as a planning tool of a project. The purpose of this document is to
provide a framework and to give guidance on the preparation and writing of the
project proposal thus ensuring that proper project planning is carried out and less
time is spent on writing a proposal for a project.

It entails the core structure and technical information that are necessary and crucial
when preparing a proposal. However, this document is not meant to be a blueprint
but it can rather be regarded as a semi-standardized guide. It should therefore be
adapted to suite a particular project needs when necessary.

2. SCOPE

The scope of the work with any additional information shall be provided.

51
Lecture Notes

3. STRUCTURE OF THE PROPOSAL

The core structure of the project proposal should at least reflect the following
elements:
* Background * Benefits, Beneficiaries and indicators
* Rationale for the study of the success of the study
* Aims and Objectives *Project Team and Project
* Project principles and approach Management Committee
* Key issues/themes to be considered in * Costs estimation the
study * Project activities and Milestones
* Methods of investigation

Project proposals compiled by outside research


consultants, should apart from the
core structure, include the following headings:
* Ethics * Track record of research consultants
* Infrastructure in the organization * Appendices

3.1 Background to the study


Information contained in this section is vital in the selection of the appropriate aims
and objectives of the study. The rationale behind the execution of the study can best
be understood from the issues that are stated in this section. Therefore, this section
should provide background information on the issue to be investigated including
information that identifies the problem.

Questions around the nature of the problem for investigation should begin to be
asked here. The information provided should be brief but concise and ensuring that
crucial issues ranging from the historical information to key project principles and
agreements as laid down are covered.

3.2 Rationale to the study


An execution of a particular study is manifested from the need to explore, learn,
evaluate, monitor and ultimately have a better understanding of specific issues. A
decision to embark on a study should therefore be prompted by these needs,
including the existing constraints and delays relating to the process and the running
of the project which would have been described in the background section. In this
section, known project related problems should be stated which will then serve as a
basis for the execution of a study. A paragraph should be sufficient to provide a good
motivation on why a particular study has to be undertaken.

52
Lecture Notes

3.3 Aims and Objectives


The aim and objectives can be considered to be integral parts of any study which
needs to be clearly stated in simple terms to make them easy to understand. The aim
which can be stated in one or two sentences basically concerns with what it is that
the study would like to achieve while the objectives of the study in this case refers to
series of specific issues that would be pursued in order for the study to accomplish its
aim.

3.4 Project principles and approach


The success of each project hinges along the presence of clear guiding principles and
also the adherence to these principles to ensure that set study objectives are met. In
this section, a project proposal compiler is required to spell out the study principles
and how he/she is going to approach it (study). The way in which the research
consultants approach their studies should therefore reflect and be based on more or
less the following guiding principles:
* A need to undertake a study in an open and transparent manner ensuring wider
consultation and a truly integrated framework for action.
* Study should be focused, i.e. it should focus on specific issues that relate to the
activities and objectives of the study.
* Ensure that an investigation is carried out in a cost effective way.
* Follow phased approach to enable the project management team to assess and
monitor the study progress at various phases.

3.5 Methods of investigation


This section of the project proposal concerns with how would the study be
conducted. The compiler of the project proposal must at this stage specify the group
of people to be interviewed, and decide on the necessity of drawing a sample,
appropriate measuring instrument to be used, the type of the interviewing technique
to be used and how would the data be analyzed.

3.5.1 Target groups and Sample


Target groups are people who will be requested to respond to question asked by the
study. Apart from specifying the target group, the principal question is to determine
whether or not it is feasible to interview every member of the target group. If then it
is not possible to interview everyone, a sample must therefore be drawn and a
decision taken on the type of sampling method to select an interviewee. Cost, time
and the human resources are amongst the elements which should be used to
determine whether or not it is possible to include all members of the target group.

Thus, the drawing of sample is necessary to reach conclusion regarding the group of
people under study at lowest cost, using less manpower, and within short period of

_________________________________ 53 __________________________________
Lecture Notes

time from the elements of the sample by means of statistical inference or


generalization.

3.5.2 Measuring instrument


What type of measuring instrument will be used to collect information? Amongst
many research instruments (e.g. performance test, attitude survey) that are used to
measure the performance or gather research data, questionnaire is most commonly
used instrument. In this section, if a questionnaire has been decided upon as a
measuring instrument, a project proposal compiler is required to outline the
procedure for the construction, pre-testing, and administering the questionnaire. The
following crucial factors have to be taken into consideration when developing a
questionnaire:
* numbering of questions and those that are related to one another should be grouped
together to give logical succession.
* Instructions should be included thus ensuring uniform completion of the
questionnaires.
* Sensitive questions should be placed at the last part of the questionnaire enhancing
the honesty and accuracy of information collected.

In this sub-section a decision will also need to be taken on the techniques that will be
used to administer the questionnaire. Will face-to-face individual, group discussion,
postal and telephonic interviews be used when administering the questionnaire?

3.5.3 Data analysis, interpretation and presentation of the project results


This sub-section deals with description of types of analysis that will be carried out as
well as procedures for processing and analyzing the data. Does the facility for data
analysis exist?
Apart from stating how the data will be interpreted the compiler must also outline
plans (including seminars, workshop, publications, meetings and presentations) for
disseminating the findings of the proposed research project to the relevant people.

3.6 Benefits and Beneficiaries


One of the important elements that should be included in the project proposal are
what do we want to get out of this study, and also who will ultimately benefit from
the project findings. This section therefore deals with how the findings will be used
and made accessible to the users.

3.7 Project team and Project management Committee


This section explains the composition of the project team and the project
management committee. Persons who will be involved in the execution of the project
forms a project team and must be listed and their roles and responsibilities be

_________________________________ 54 __________________________________
Lecture Notes

clarified. In the case of collaborative projects involving research consultants, their


time commitment, qualifications and experience must also be specified. In the case of
studies being undertaken by outside consultant's project management committee
should be established.

The role of the project management committee will amongst others be to:
* assist the project team in decisions regarding key issues to be investigated;
* facilitate communication between the client and the project team; and
* oversee the progress of the project.
Progress report should be submitted to the project management committee on regular
basis.

3.8 Cost Estimation


When drafting a budget a research consultant should include as much supporting
information as possible to clearly illustrate how the estimates were developed and this
will ensure that reasonable costs for each element of the project are estimated. Such
supporting information would include fixed cost element such as labour, and variable
cost elements such as the cost of traveling (air tickets, car rentals), stationeries, faxes
and telephone, printing and photocopying questionnaires, workshop/seminar
organizing, data processing and analysis.
Research consultants needed to include two detailed and different budget scenarios.

3.9 Project activities and Milestones


This section covers the detailed description of all the activities that will be carried out
in various phases of the project, the amount of time required to carry out these
activities, the date at which these activities will be completed, and the personnel
involved.

4 ADDITIONAL ELEMENTS OF PROJECT PROPOSAL

The project proposal elements that will be discussed in this section are applicable to
outside research consultants who will be requested to undertake a research study for
the procuring agency.

4.1 Ethics
This section entails the drafting of project protocols, and these will cover wide range
of ethical issues and concerns. Protocols would clarify issues such as copyright, as well
as anonymity of respondents.

55
Lecture Notes

4.2 Infrastructure in the organization


This section deals with the organizational capacity to handle the proposed study. It
entails a brief overview of the infrastructure, the historical information, the mission
and the specific objectives of the organization. Also state the strengths of the
organization.

4.3 Track record of the research consultants


The research consultant here needs to briefly state his/her experience, qualifications,
past achievements, including few publications related to the study.

4.4 Appendices
In this section project proposal compilers can attach any other supporting
documentation or essential references.

5 Concluding note
In order for your project proposal to look good it should:
* be clearly and concisely presented;
* cover most of the essential elements discussed above; and
* Not be too technical and full of jargon.

56

Das könnte Ihnen auch gefallen