Sie sind auf Seite 1von 4

Proposed Budget for the installation of Training Equipments at DBI

S/NO description Condition QTY Unit Cost


1 3 Phase 200A Gear Switch Local Fabrication 1 85,000.00
2 240A Rectifier systems Used 2 450,000.00
3 200A 6-Way LV Panel Local Fabrication 1 260,000.00
4 200A DC Bus Bar Local Fabrication 1 130,000.00
5 20 Way DCDB Local Fabrication 2 85,000.00
6 Battery Bank 12
7 Installation of Power Equipments 1 200,000.00
8 Power Plan Designed 1 75,000.00
9 Cables 1
10 Miscelenous 1 25,000.00
ents at DBI
Amount
85,000.00
900,000.00
260,000.00
130,000.00
170,000.00

200,000.00
75,000.00
-
25,000.00
1,845,000.00
Proposed Budget for the installation of Training Equipments at DBI
S/NO description Condition QTY Unit Cost
1 3 Phase 200A Gear Switch (250A Break Local Fabrication 2 32,000.00
2 240A Rectifier systems Used 1 450,000.00
3 240A Rectifier systems with ATS Used 1 550,000.00
4 200A 8-Way LV Panel Local Fabrication 1 300,000.00
5 200A DC Bus Bar Local Fabrication 1 200,000.00
6 20 Way DCDB Local Fabrication 2 75,000.00
7
8 200,000.00
9 75,000.00
10
11
12 200,000.00
13 75,000.00
14
15
16 200,000.00
17 75,000.00
18
19 Battery Bank 12
20 Installation of Power Equipments 1 200,000.00
21 Power Plan Designed 1 75,000.00
22 Cables 1
10 Miscelenous 1 25,000.00
ents at DBI
Amount
64,000.00
450,000.00
550,000.00
300,000.00
200,000.00
150,000.00

-
-
-

-
-
-

-
-
-

200,000.00
75,000.00
-
25,000.00
2,014,000.00

Das könnte Ihnen auch gefallen