CE-62: Pavement Analysis and Design

1st Sem, 2018-2019


Name: _____________________________________________________ Score: _____________
Section: ___________________ Seat # : _____________
Quiz # 2: Earthwork
A. Indicate the Item number to the corresponding description:
1. Clearing and Grubbing
2. Overhaul
3. Structure Excavation
4. Subgrade Preparation
5. Embankment

B. Identify the correct answer. In the event that the item requires 2 answers, use “/” (slash) to separate
the answers.
1. This Item shall consist of roadway and drainage exaction and disposal of the material.
2. This Item shall include necessary diverting of live streams, bailing, pumping, draining,
sheeting, bracing, and the necessary construction of cribs and cofferdams.
3. Material which is acceptable in accordance with the contract and which can be
compacted.
4. Soil can be classified as unsuitable material if the natural water content exceeds ____%
and the natural density is equal to or lower than _________ kg/m³.
5. All materials below subgrade level in earth cuts shall be excavated to what depth,
unless otherwise specified.

Quiz # 3: Subbase and Base Course

A. Indicate the Item number to the corresponding description:


1. Aggregate Subbase Course
2. Crushed Aggregate Base Course
3. Aggregate Stockpile
4. Aggregate Base Course
5. Lime Stabilized Road Mix Base Course

B. Identify the correct answer. Use “/” (slash) to separate the answers.
1. The amount of asphaltic material to be added to the soil-aggregate shall be from ______
to _____ mass percent of the dry soil-aggregate.
2. The amount of cement to be added to the soil-aggregate shall be from ______ to _____
mass percent of the dry soil.
3. The amount of lime to be added to the soil-aggregate shall be from ______ to _____ mass
percent of the dry soil.
4. The permitted variation from design level of surface in aggregate subbase.
5. In some areas where the conventional base course materials are scarce or non-
available, the use of ____% weathered limestone blended with ____% crushed stones
or gravel shall be allowed.