Beruflich Dokumente
Kultur Dokumente
1
ELGrid
ENERGY GRID MANAGEMENT AND
OPTIMIZATION
R&D project
• Co-funded by ERDF
Business goals
Benefits
ELGrid components
SCADA (CIM)
Data access Optimizations
layer
METEO (WEB) METEO interface
Billing map
interface
AMR Billing
Database
Savings
Decrease of both technical and trade losses of electrical energy
Network Optimization
Savings
Active failure prevention
Safety
Savings
Increase of efficiency of existing energy infrastructure (splitting points
Network Optimization
management)
Delayed investments
Investment method
• Choice of optimal location for the scattered source
• In some cases can result in increased losses
Two locations
Goal:
• Investigate current situation in the grid
• Optimize electrical grid technical parameters
Steps:
• Electrical grid mapping
• Estimate maximum load of electrical grid elements
• Power flow calculation
• Optimization:
• Network configuration optimization
• voltage optimization
Calculations:
• maximum load of electrical grid elements estimation
• power flow
Optimization
• Network configuration optimization
• voltage optimization
Optimization goal
• minimize energy loss
Optimization constraints
• avoid transformers and lines overload
• maintain end-of-line voltages within regulatory limits
Prerequisites:
• Import an existing grid mapping form GIS system – 1 or 2 days for one GPZ
• Mapping corrections, including switches corrections – time depends on quality of
initial data – 1 day up to 1 week
• Data validation using flow software
Power Flow
Results Analysis Results:
Power Flow Correct electrical grid mapping
Calculations
Basic Topology
Validation
Validation of
Initial Data From
source Systems
Obtaining full medium and low voltage grid mapping can be very costly
and time-consuming
System can be useful even if full mapping was not obtained. It’s possible
to work having only the medium voltage electrical grid mapped.
• Each customer provided with low voltage power has to be
assigned to medium/low voltage substation
• Full functionality and calculations of the system is available for
medium voltage grid
Input data
• Area powered by chosen substation – geospatial information (GIS),
topology
• Electrical grid elements (lines, transformers, switches) data including
supplier data sheets
• Transformers tap settings initially set to zero
• Maximum load estimated as by ELGrid software
Results
• Transmitted power (lines transformers)
• Energy losses (lines, transformers)
• Node voltages
Customer/receiver Absolute voltage difference [kV] Relative voltage difference [%] Nominal voltage [kV]
Odbiorca[27385] 0,052 12,9 0,348
Odbiorca[27498] 0,049 12,3 0,351
Odbiorca [27631] 0,051 12,7 0,349
Odbiorca [27750] 0,049 12,2 0,351
Odbiorca [27774] 0,054 13,5 0,346
Odbiorca [27884] 0,053 13,2 0,347
• Optimal switch states for the analyzed area and given time
• List of suggested switch state changes
• Energy loss (kWh/year) before and after optimization
• Number and cost of suggested changes
• Number of new suggested switches and their location
• Cost of new elements and installation
• Reduction of losses, cost of changes and profit as a
difference between those values
• Payback time
Results:
• Number of transformer and tw transformer tap setting changes
• Suggested new tap settings for each transformer for each tariff period (morning
and afternoon on-peak and one off-peak period)
• Suggested set of four settings (three for primary voltage, one for intermediate
voltage) for each tw transformers for each tariff period (morning and afternoon
on-peak and one off-peak period)
• Energy loss (kWh/year and PLN/year) before and after optimization
Assumptions
• Miximum load estimated
• Transformers 110/SN energy losses taken into account
Optimization period
• 01-01-2010 – 28-02-2010
Multidimensional objective function
• energy loss minimization
• avoid transformers and lines overload
• maintain end-of-line voltages within regulatory limits
GPZ1 GPZ2
Number of consumers 32110 10432
GPZ1 GPZ2
Reactive power 12534 kVar 3090 kVar
(kVar)
Real power 31750 kW 12070 kW
(kW)
Apparent power 34130 kVA 12460 kVA
(kVA)
Real power loss 2067 kW 382,64 kW
(kW)
Real power loss to real power ratio 6,5% 3,2%
(%)
GPZ1 GPZ2
Number of end-users with voltage below 23 0
regulatory limits (10%)
Number of suggested transformers tap changes 345 100
Real power loss reduction (%) 7,5% 4,1%
(on-peak period)
Real power loss reduction (kWh) 156,107 kW 15,84 kW
(on-peak period)
Reactive power loss reduction (%) (on-peak 4,1% 2,2%
period)
Energy loss reduction (%) 7,2% 3,5%
Energy loss reduction (kWh) 260697,34kWh 25837,91kWh
over period: 1.01 – 28.02 2010
Results:
Optimization results (elements that should be changed are highlighted on
maps or can be listed as a table of records)
• Optimal transformers tap settings
• Optimal network - reconfiguration of network splitting points
Results:
• Energy and financial savings after optimization
• Energy (kWh/year) and financial($/year) losses comparison
before and after optimization
• CO2 emission reduction (credits for CO2 emission)
• Investment costs
• Return on investment
PPS 1 PPS 2
Energy loss reduction 782 78
[MWh]
Energy loss reduction 39 000,00 3 870,00
[Euro]
Estimated CO2 emission reduction [kg] 312 000 31 000
Estimated CO2 emission reduction [Euro] 2 200,00 220,00
Energy loss reduction (%) 7,2% 3,5%