PROJECTS DIVISON
A-1101 B
Primary Reformer
Catalyst Change Out
5. Site meeting/Discussion.
9. Establish stock of empty drums with liners and lids at reactor grade,
which will be supplied from the pre-bagging operation.
1. Kanooz mechanical team will install isolation and lock out Reformer
tube counter weight arrangement.
2. Ensure all Isolation/Blind points are correct & locked out , Document
the isolation / Blind list.
3. Set up Vacuum unit with Cyclone, drum roller, Steel Drums with plastic
drum liners. When running out the Vacuum Hose insure to run it out in
a way to minimize the risk of trip hazards, Barricade the work area to
ensure none essential personal area not in the work zone.
4. When removing the Reformer tube blind Flange cover take initial dip
measurement and record it
6. Ensure all personnel that are working in the Catalyst handling area
have full PPE requirements.
11. Video Inspection will be carried out to ensure all the Catalyst has been
removed.
8. Ensure all personnel working in the area around the catalyst handling
have full PPE requirements.
12. Box Up blind flange end cover, Ensure proper Tightening /Torque of all
reformer flanges
14. Client mechanical team will Unlock Reformer tube counter weight
arrangement
4.0 DEMOBILISATION
END OF SCHEDULE