Sie sind auf Seite 1von 1

CONTRACT BETWEEN GTB Engineering TAM Geo- Engineering PLC & EMU

General Import PLC.


FOR THE CONSTRUCTION OF BOREHOLE(S)
IN Oromia Region Ethiopia

PROVISIONAL INSPECTION CERTIFICATE

1. This is to certify that the well/surface structure

Well no. : ___________ (according to the execution proposal)

Region: ____________________________________

Wereda: ____________________________________

Town: ____________________________________

Site: ____________________________________

Has been completed according to the Agreement on: _________________ (date)

2. The following minor defects and/or minor remaining works were found:

a) Minor defects : ________________________________________________________


________________________________________________________
________________________________________________________
________________________________________________________

b) Minor remaining works :


__________________________________________________________
____________________________________________________________________

c) Deadline for correction of defects and, if applicable, for completion of remaining works

On: ______________ (date)

3. Remarks:

Place: _________________________ Date: _______________

The Consultant: ______________________________

The Contractor: ______________________________

The Authority: ______________________________ (The Authority on ground)