Sie sind auf Seite 1von 3

TECHNICAL DATA

PERTAINING TO SOURCE FOR CLEARANCE BY STATE LEVEL


SCHEME SANCTIONING COMMITTEE
1. Name of the proposed scheme. Shantipur piped Water Supply Scheme.
2. Location. i. Block -- Sahid Matangini.
ii. District - Purba Medinipur .
3. Number of Mouzas proposed Zone (I)4 (Four) nos.
to be covered. Zone (II) 3 (Three) nos.
4. No of Zone. 2 (Two) nos.
5. Status of Block with special It is not identified either as Arsenic or as Fluoride affected Block.
reference to Arsenic & Fluoride.
6. Name of Mouzas with JL. No. SI. Name of mouza JI No.
No.
1.
Barageche 01
2.
Shantipur (PART) 03
ZONE(I) 3.
Guluria 04
4.
Kakdihi (PART) 05
5.
ZONE(II) Hakala 02
6.
Shantipur(PART) 03
7.
Kakdihi(PART) 05
7. Popula tion as per 2011 census. Name of Mouza Total SC ST Area
ZONE (I) Barageche 4981 171 18 206.76
Shantipur (PART) 4873 0 0 106.66
Guluria 1667 115 34 43.56
Kakdihi (PART) 969 0 0 178.61
TOTAL = 12490 286 52 535.59
ZONE(II) Hakala 2487 0 0 85.68
Shantipur(PART) 4873 290 17 106.66

Kakdihi(PART) 3875 150 0 38.39

Total = 11235 440 17 230.73


8. Population Density. ZONE I = 35.11 Nos. /Hectare based on 2011 Population.

ZONE II = 73.30 Nos. /Hectare based on 2011 Population

9. Design population as in 2044 ZONE I = 18805 Nos


ZONE II = 16915 Nos
10. Ultimate water demand in ZONE I = 1537 KLD
2044@ 70 lpcd Considering
institutional demand @ 5 % and
wastage @ 10%
ZONE II = 1330 KLD

11. Hourly demand considering ZONE I = 96 Cum /hr


16 hour of pumping per day.
ZONE II = 83.12 Cum /hr

12. Proposed source of water. Ground water

13. Method of collection. Big dia Tube Well

14. Total number of tube wells ZONE I = 2 (two) nos. (working)


required.
ZONE II = 2 (two) nos. (working)

15. Expected yield of each tube ZONE I = Maximum 48 m3/hr at a drawdown of 1.20
well. mtr.
ZONE II = Maximum 41.56 m3/hr at a drawdown of 0.98
mtr.
16. Depth of ground water table. 7.93 m.

17. Seasonal fluctuation of ground 7 mtr. (assumed)


water table.
18. Aquifer location of reference 88.39 mtr. to 131.06 mtr.
tubewell.
19. Discharge of reference ZONE I = 52210 LPH
tubewell.
ZONE II = 42676 LPH

20. Distance of reference TW from Spatial/ arial distance of T/W of the proposed scheme from the
the proposed source. reference tube well is about 3 Km. (approx.)

21. Details of reference tube well. Enclosed datasheet of T.W. No-1 of Barakamalpur W/S Scheme of Singur
Block in the District Hooghly.

DESCRIPTION LENGTH DIA MATERIAL


Depth of each tube
131.26 m. 300mm x 200 mm
well & size
1. Housing pipe 36.75 m. 300 mm MS ERW
2. Well & Blank pipe 64.01 m. 200 mm MS ERW
3. Strainer 30.50 m. 1 HDPE

00 mm
22. Details DESCRIPTION LENGTH DIA MATERIAL
of tube well proposed. Depth of each
(Provision of depth of the tube 155 m. 300 mm x200 mm
tube well & size
well has been kept as 155 mtr. 1. Housing pipe 50.00 m. 300 mm PVC
as per block wise 2. Well pipe 72.00 m. 200 mm PVC
recommendation of depth by 3. Strainer 30.00 m. 200mm HDPE
CGWB. However actual 4. Blank pipe 3.00 m. 200 mm PVC
position of the strainer will be
ascertained during execution as
per trial boring and Electro
logging results at pinpointed
23. Open area of strainer. 10%
24. Chokage area assumed. 50%
25. Entrance Velocity. 1.25 cm / sec.
26. Velocity of rise. 0.38 m / sec
27. Layer chart & Yield test report of Enclosed in separate sheet.
reference tubewell.
28. Quality aspect of the source. Water analysis report of the reference tube well shows that the max m
concentration of Iron is within permissible limit. The presence of
Fluoride, Chloride & Nitrates in ground water are well within the
permissible limit. Water of the proposed tube well will be made
potable after disinfection by Chlorination.

29. Quantity aspect of the source. Adequate, as per information revealed from hydro- geological map
of CGWB & yield test report of the reference tube well.

30. Proposed treatment. Disinfection by Chlorination is proposed.


31. Hours of pumping. 16 (sixteen) hours
32. Hours of supply. 8 (eight) hours
33. Availability of Electricity. Available nearby.
34. Index Map. Enclosed.

ASSISTANT ENGINEER EXECUTUIVE ENGINEER-III SUPERINTENDING ENGINEER


INVESTIGATION UNIT INVESTIGATION UNIT PLANNING CIRCLE-II
P.H. ENGINEERING DTE. P.H. ENGINEERING DTE. P.H. ENGINEERING DTE.