15. Expected yield of each tube ZONE I = Maximum 48 m3/hr at a drawdown of 1.20
well. mtr.
ZONE II = Maximum 41.56 m3/hr at a drawdown of 0.98
mtr.
16. Depth of ground water table. 7.93 m.
20. Distance of reference TW from Spatial/ arial distance of T/W of the proposed scheme from the
the proposed source. reference tube well is about 3 Km. (approx.)
21. Details of reference tube well. Enclosed datasheet of T.W. No-1 of Barakamalpur W/S Scheme of Singur
Block in the District Hooghly.
00 mm
22. Details DESCRIPTION LENGTH DIA MATERIAL
of tube well proposed. Depth of each
(Provision of depth of the tube 155 m. 300 mm x200 mm
tube well & size
well has been kept as 155 mtr. 1. Housing pipe 50.00 m. 300 mm PVC
as per block wise 2. Well pipe 72.00 m. 200 mm PVC
recommendation of depth by 3. Strainer 30.00 m. 200mm HDPE
CGWB. However actual 4. Blank pipe 3.00 m. 200 mm PVC
position of the strainer will be
ascertained during execution as
per trial boring and Electro
logging results at pinpointed
23. Open area of strainer. 10%
24. Chokage area assumed. 50%
25. Entrance Velocity. 1.25 cm / sec.
26. Velocity of rise. 0.38 m / sec
27. Layer chart & Yield test report of Enclosed in separate sheet.
reference tubewell.
28. Quality aspect of the source. Water analysis report of the reference tube well shows that the max m
concentration of Iron is within permissible limit. The presence of
Fluoride, Chloride & Nitrates in ground water are well within the
permissible limit. Water of the proposed tube well will be made
potable after disinfection by Chlorination.
29. Quantity aspect of the source. Adequate, as per information revealed from hydro- geological map
of CGWB & yield test report of the reference tube well.