NAME OF WORK
: ESTIMATE FOR STILLING TANK.
NAME OF SCHEME : KALAMONIJAN LIS.
NAME OF DIVISION : JCAD DIVISION (IRRIGATION), HOJAI
NAME OF SUB-DIVISION : HOJAI SUB-DIVISION (IRRIGATION), HOJAI
Item No.1 Earth work in excavation in foundation trenches including filling up the sides of trenches and remova
of spoils after the completion of works and ramming, dressing, dressing, shoring etc. complete a
directed including bailing out water where necessary (in ordinary soil)
Item No.2 C.C. work in prop 1: 3: 6 in foundation/abutment wall/wing wall/ pier etc. with hand broken stone aggregat
of size 13mm to 38 mm including curing bailing out water with necessary timber shuttering, wher
necessary as directed complete (Shuttering , scaffolding cost will be paid separately)
Item No.3 Supplying, fitting & laying of reinforcement bar in position to R.C.C. work including cutting, bending
cranking with two piles of 0.90mm (20BWG) annealed wire, hooking, tying etc.
Item No.4 Cement concrete work in prop 1:2:4 in foundation/abutment wall/wing wall pier & slab etc. with hand broke
stone aggregate of size 6mm to 20 mm including curing with necessary timber shuttering, scaffolding wher
necessary as directed. (Shuttering, scaffolding cost will be paid separately)
A) With shuttering & without dewatering
Footing 4 x 2.50 x 2.50 x 0.30 = 7.50 m3
Column 4 x 0.30 x 0.30 x 2.00 = 0.72 m3
Base Beam 2 x 4.70 x 0.30 x 0.70 = 1.97 m3
2 x 4.70 x 0.30 x 0.70 = 1.97 m3
Tank Slab 1 x 5.60 x 5.60 x 0.30 = 9.41 m3
Wall Of Tank 2 x 5.00 x 0.30 x 3.00 = 9.00 m3
2 x 5.60 x 0.30 x 3.00 = 10.08 m3
Total = 40.66 m3
Item No.5 Centering and shuttering including propping etc. where necessary and removal after the completion C.C
/R.C.C. work as directed complete. (Measurement to be taken on the face area timbered)
(A) for Wing wall , abutment wall
Footing 4x 4x 2.50 x 0.30 = 12.00 m2
Column 4x 4x 0.30 x 1.70 = 8.16 m2
Beam 1x 4x 1.40 x 5.00 = 28.00 m2
Tank Slab 1x 5.00 x 5.00 = 25.00 m2
Tank Wall 2x 5.00 x 3.00 = 30.00 m2
2x 5.60 x 3.00 = 33.60 m2
Total = 136.76 m2
Item No.6 12mm thick cement plastering work including clearing surface curing etc in prop 1:3 complete as directed
Total =
Say =
For 2 Nos
#NAME?
Executive Engineer,
JCAD Division(Irrigation)
Hojai:Nagaon.
sides of trenches and removal
sing, shoring etc. complete as
Rs. 5,955.00
Rs. 15,276.50
Rs. 279,553.91
Rs. 56,353.33
Rs. 26,983.24
erproofing coating Brushbond of
sunken slabs, chajjas, tunnels,
e with water prior to application
Rs. 27,744.85
Rs. 3,246.49
Rs. 763,792.14
Rs. 763,800.00
Rs. 1,527,600.00
Executive Engineer,
CAD Division(Irrigation)
Hojai:Nagaon.