INTRODUCTION
1.1 About NERC and its Reliability Standards
The North American Electric Reliability Corporation (NERC) is a not-for-profit
international regulatory authority whose mission is to assure the effective and efficient
reduction of risks to the reliability and security of the grid. NERC develops and enforces
Reliability Standards; annually assesses seasonal and long‐term reliability; monitors the
bulk power system through system awareness; and educates, trains, and certifies industry
personnel. NERC’s area of responsibility spans the continental United States, Canada,
and the northern portion of Baja California, Mexico. NERC is the electric reliability
organization (ERO) for North America, subject to oversight by the Federal Energy
Regulatory Commission (FERC) and governmental authorities in Canada. NERC's
jurisdiction includes users, owners, and operators of the bulk power system, which serves
more than 334 million people.
This Compliance Monitoring and Enforcement Program is to be used by the North
American Electric Reliability Corporation (NERC) and the Regional Entity to monitor,
assess, and enforce compliance with Reliability Standards within the Province of
Manitoba. Assessing of compliance with Reliability Standards is accomplished through
compliance monitoring and rigorous proactive Compliance Audits. NERC shall register
the organizations responsible for complying with Reliability Standards, in accordance
with applicable NERC Rules of Procedure. NERC shall notify organizations of their
inclusion on the NERC Compliance Registry and shall inform each Registered Entity, at
the time of such registration, of the Reliability Standards that are applicable to the
Registered Entity. NERC shall maintain on its web site a current listing of Reliability
Standards that are applicable to all Registered Entities. Each Registered Entity shall
inform the Regional Entity promptly of changes to its registration information.
The Transmission Loading Relief Procedure used by the Reliability Coordinators in
the Eastern Interconnection is described in NERC Reliability Standard IRO-006-EAST-
1. The purpose statement of NERC Reliability Standard IRO-006-5 states that, “To
ensure coordinated action between Interconnections when implementing
Interconnection-wide transmission loading relief procedures to prevent or manage
potential or actual SOL and IROL exceedances to maintain reliability of the bulk electric
1
system.” This coordinated action, for the Eastern Interconnection, is obtained through the
Interchange Distribution Calculator (IDC).
1.2 IDC Provider and 24x7 Technical Support
OATI provides 24x7 support of the IDC system. During normal business hours, the OATI
help desk will be available to answer calls and provide basic system support. During off-
hours, all calls to the help desk will be directed to the OATI answering service where
calls will be followed up and trouble tickets will be escalated to the appropriate line of
support. Please contact a NERC System Administrator for assistance in registration
matters.
1.3 Transmission Loading Relief Levels
Transmission Loading Relief (TLR) is a sequence of actions taken during operations
planning or during real-time operation to avoid or remedy security violations associated
with the transmission system. System planners and operators have developed unique
systematic procedures to prevent transmission loading problems and they vary across the
interconnected grid of each control area. Issues of security raised due to financial
transactions are resolved by formal TLR procedures with consistency and fairness. The
process starts when a security coordinator identifies a transmission facility within its
security area that is about to, or has exceeded the operating security limit. At this point
the security coordinator may invoke TLR. These procedures are briefly summarized
below.
LIMITATIONS: The transmission relief procedure depend on number of limitations:
a) Computation of off-line ATC doesn’t consider the effect of the actual transactions
in/out of the region. It is a non-simultaneous computation. b) The non-peak hour
operating conditions differ from that at peak hour. c) Numerical errors are present in off-
line ATC because it often neglects the influence of reactive power, uses linear models
and assumes constant distribution factors.
The Interchange Distribution Calculator (IDC) uses TLR levels to define the severity of
the loading on the transmission system as well as actions that will be taken by the IDC
to relieve the overloading. The listed system condition examples are intended to assist
the Reliability Coordinator in determining what level of TLR to call.
2
Table 1.1 Transmission loading relief levels
Level Examples of Possible System Conditions
TLR-1 At least one Transmission Facility is expected to approach or exceed its SOL
or IROL within 8 hours.
TLR-2 At least one Transmission Facility is approaching or is at its SOL or IROL.
Analysis shows that holding new and decreasing non-firm Interchange
Transactions and energy flows for the next hour can prevent exceeding this
SOL or IROL.
TLR-3a At least one Transmission Facility is expected to exceed its SOL or IROL
within the next hour.
Analysis shows that full or partial curtailment or reallocation1 of non-firm
Interchange Transactions and energy flows can prevent exceeding this SOL
and IROL.
TLR-3b At least one Transmission Facility is exceeding its SOL or IROL, or
At least one Transmission Facility is expected to exceed its SOL or IROL
within the current hour.
Analysis shows that full or partial curtailment or reallocation2 of non-firm
Interchange Transactions and energy flows can prevent exceeding this SOL
and IROL.
TLR-4 At least one Transmission Facility is expected to exceed its SOL or IROL.
Analysis shows that full curtailment of non-firm Interchange Transactions and
energy flows or reconfiguration of the transmission system can prevent
exceeding this SOL and IROL.
TLR-5a At least one Transmission Facility is expected to exceed its SOL or IROL
within the next hour.
Analysis shows that the following actions can prevent exceeding this SOL and
IROL:
Full curtailment of non-firm Interchange Transactions and energy flows, and
Reconfiguration of the transmission system, if possible, and
Full or partial curtailment or reallocation3 of firm Interchange Transactions
and energy flows.
TLR-5b At least one Transmission Facility is exceeding its SOL or IROL, or
At least one Transmission Facility is expected to exceed its SOL or IROL
within the current hour.
Analysis shows that the following actions can prevent exceeding this SOL and
IROL:
Full curtailment of non-firm Interchange Transactions and energy flows, and
Reconfiguration of the transmission system, if possible, and
Full or partial curtailment or reallocation4 of firm Interchange Transactions
and energy flows.
TLR-6 At least one Transmission Facility is exceeding its SOL or IROL, or
3
At least one Transmission Facility is expected to exceed its SOL or IROL
upon the removal from service of a generating unit or another transmission
facility.
TLR-0 No transmission facilities are expected to approach or exceed their SOL or
IROL within 8 hours and the Interconnection-wide transmission loading relief
procedure may be terminated.
CHAPTER 2
IDC FACTORS
4
If a tag indicates a TDF of 8.3% on flowgate X, this means that 8.3% of the transfer
amount on that tag flows on flowgate X.
Use the following formula to calculate the MW impact on a flowgate for a particular
Interchange Transaction:
MW impact = (Interchange transaction MW) x (TDF) (2.1)
5
Use the following formula to calculate the MW impact on a flowgate for a particular
generator.
MW impact = (Gen MW) x (GSF) (2.5)
6
In the Flowgate GLDF display the user selects a flowgate and is shown a list of
generators that contribute to flow as a byproduct of serving their own Balancing
Authority Area load (i.e., the GTL impact).
In the CA GLDF display, the user is shown a listing of flowgates that are impacted by
generators serving their own Balancing Authority Area load. From this list, the user
can drill down and view the generator contribution to flow.
The GLDF is calculated according to the following formula:
GLDF = GSF -LSF (2.8)
∆P𝑘
𝑙
LODFl,k = (2.9)
P𝑜
𝑘
Where: ∆P𝑙𝑘 -Change of power flow in the line l when the outage of line k.
P𝑘𝑜 -Real power flow in the line k before outage.
Line Outage Distribution Factor (LODF) represents the percentage of flow on a
contingent facility that will flow on the monitored elements, if the contingent facility
is outaged–Contingency Analysis.
Post-Contingency Flow on Monitored Element = Pre-Contingency Flow on
Monitored Element + (Pre-Contingency Flow on Contingent Element) * LODF
P𝑙 = P𝑙𝑜 + LODF𝑙,𝑘 P𝑘𝑜 (2.10)
The PTDF is equivalent of the GSF in terms of mathematical definition. The PTDF
represent the sensitivity of change power flow in line l when injected power to the bus
i is increased by 1 MW.
∆P
PTDF𝑙𝑘 = ∆P𝑙 (2.11)
𝑖
7
PTDF Flowgates are Flowgates that do not consider contingencies during curtailment
evaluation. With PTDF Flowgates the monitored branches alone are considered during
curtailment evaluation.
2.1.7 Outage Transfer Distribution Factor (OTDF)
The OTDF represents the sensitivity of change power flow in line l when the power
in line k is increased by 1 MW.
∆P
OTDF= ∆P 𝑙 (2.12)
𝑘
8
3.Title: Implementation of PTDFs and LODFs for Power System Security.
Authors: Chong Suk Song, Chang Hyun Park, Minhan Yoon & Gilsoo Jang.
Publications: Journal of International Council on Electrical Engineering, Vol. 1, No. 1,
pp. 49~53, 2011.
Inference: This paper describes an algorithm to formulate the PTDFs and LODFs, to
calculate the generation shifts so that the power flow on the transmission lines that violate
security limits due to single and multiple-line outage events are adjusted to its security
limits. Two cases have been dealt with to test for the effectiveness of the formulation and
the algorithm.
1) Case 1: The generation and loads are being increased by 5% to create a situation
where there are overloads in the overhead lines.
2) Case 2: A single-line outage is present in the system. This would result in the change
in power flow on adjacent lines leading to overloading of a few lines.
4.Title: Graphical contingency analysis.
Authors: Huang Z, Wong PC, Mackey P, Chen Y, Ma J, Schneider K, Greitzer FL.
Association: Association for the Advancement of Artificial Intelligence, PNNL, USA,
2008.
Inference: The Graphical Contingency Analysis (GCA) Tool is a visual analytic
software tool developed by Pacific Northwest National Laboratory (PNNL) researchers.
The GCA Tool provides quick visualization of potential problem areas to improve wide-
area situational awareness. The GCA Tool allow the user to rank order contingencies
from worst to best. The GCA Tool can provide effective decision making support to
operators.
5.Title: Contingency Analysis of Power System
Authors: Mrs. Veenavati Jagadishprasad, Prof. Manisha D. Khardenvis
Publications: IEEE Students Conference on Electrical, Electronics and Computer
Science, 1st to 2nd March 2012 Bhopal, Madhya Pradesh, India.
Inference: The authors presented on Contingency analysis of power system with modern
Energy Management Systems (EMS). Security is determined by the ability of the system
to withstand equipment failure. Contingency Analysis of a power system is a major
activity in power system planning and operation. In general, an outage of one
transmission line or transformer may lead to over loads in other branches and/or sudden
system voltage rise or drop. Contingency analysis is used to calculate violations. The
idea was implemented with an example on 6 bus power system which gives information
9
of violations & remedial action to remove violations. 1. Weak elements are those that
present overloads in the contingency conditions. 2.Standard approach is to perform a
single (N-1) contingency analysis simulation. 3. A ranking method will be demonstrated
to prioritize transmission planning. 4. CA is therefore a primary tool used for preparation
of the annual maintenance plan and the corresponding outage schedule for the power
system. The corrective actions effectively removed the limit violations in the system. The
results obtained through the proposed algorithm are found to be quite accurate and thus,
this work provides new tool for developing remedial control actions for higher order
contingencies. Contingency analysis study helps to strengthen the initial basic plan. It is
also helpful to develop system operators to improve their ability to resolve problem. This
tool helps especially the busy power system operators.