LIST OF REMAINING 1st & 2nd FIX ACTIVITIES IN BASEMENT FLOORS

Levels Pending Electrical Works Reason

Power cable pulling


Low current system wiring- finished Done
Fire Alarm conduits and wiring
Electrical BMS conduits and cabling
Exposed conduits

L06 Duct Installation, insulation & Dampers Insulation pending


Insulation of chilled water pipe and FCU valve assembly
FHC Civil is not ready
Installation of gate valve, strainer and check valve for PPR
Mechanical
Chilled water hydrotest Done
Fire water hydrotest Done

Power cable pulling


Low current system wiring- finished Done
Fire Alarm conduits and wiring
BMS conduits and cabling
Electrical
Exposed conduits
Installation of Cable Tray Ongoing

L07
Duct Installation, insulation & Dampers Insulation pending
Insulation of chilled water pipe and FCU valve assembly
FHC ongoing
Installation of gate valve, strainer and check valve for PPR
Mechanical
Chilled water hydrotest Done
Fire water hydrotest Done

Power cable pulling


Low current system wiring- finished Done
Fire Alarm conduits and wiring
BMS conduits and cabling
Electrical
Exposed conduits
Installation of Cable Tray Done

L08
Duct Installation, insulation & Dampers Done
Insulation of chilled water pipe and FCU valve assembly
FHC
Installation of water supply pipes 80%
Mechanical
Chilled water hydrotest Done
Fire water hydrotest Done
Installation of gate valve, strainer and check valve for PPR

Power cable pulling


Low current system wiring- finished Done
Fire Alarm conduits and wiring
BMS conduits and cabling
Electrical
Exposed conduits
Installation of Cable Tray Done

Duct Installation, insulation & Dampers Insulation ongoing


L09
Installation of fire water pipe Done
Installation of water supply pipes Done
Installation of Drainage Pipe Done
Installation of chilled water pipe Done
Mechanical
Insulation of chilled water pipe and FCU valve assembly
FHC Civil is not ready
Installation of gate valve, strainer and check valve for PPR