Sie sind auf Seite 1von 172

Controls Upgrades to Generator & Medium-Voltage Switchgear

Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02


SECTION 260115 - PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD
SWITCHGEAR

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall provide the equipment manufacturers recommended preventative


maintenance as well as protective relay testing and calibration for the 12.47 kV campus main
switchgear in accordance with the equipment manufacturers instruction manuals and industry
standards.

1.3 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

B. Section 261327- 15 kV Metal-Clad Switchgear Control Modifications

1.4 COORDINATION

A. It is the intent of the specified herein shall be coordinated with all other Division 26 work in order
to reduce the number and duration of power outages to the facility to the greatest extent possible.

B. Execute the work specified herein to occur during the facility power outage for the
implementation of the 15 kV controls modifications specified in Section 261327- 15 kV Metal-
Clad Switchgear Control Modifications.

1.5 SUBMITTALS

A. Qualification data for preventative maintenance services provider organization.

B. Qualification data, including training certification data, for field services technicians certifying
adequate training and experience for the specific type equipment involved on this project.

c. List of test equipment to be used in the performance of the preventative maintenance services,
including manufacturer and model number for each item.

D. Calibration certificate for each piece of test equipment, including torque wrenches, to be used in the
performance of the preventative maintenance services.

E. Copies of standard forms used for testing and recording field data for the 15 kV switchgear,
vacuum circuit breakers, station batteries and battery charger.

1.6 APPLICABLE STANDARDS

A. The work specified herein shall be governed by the latest applicable ANSI, NEMA and NFPA
standards, including but not limited to:

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 1


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
1. ANSI/IEEE C37.04 IEEE Standard Rating Structure for AC High-Voltage Circuit
Breakers Rated on a Symmetrical Current Basis
2. ANSl/IEEE C37.06 Switchgear - AC High-Voltage Circuit Breakers Rated on a
Symmetrical Current Basis - Preferred Ratings and Related
Required Capabilities
3. ANSl/IEEE C37.09 IEEE Standard Test Procedure for AC High-Voltage Circuit
Breakers Rated on a Symmetrical Current Basis
4. ANSl/IEEE C37.010 IEEE Application Guide for AC High-Voltage Circuit Breakers
Rated on a Symmetrical Current Basis
5. ANSl/IEEE C37 .011 IEEE Application Guide for Transient Recovery Voltage for AC
High-Voltage Circuit Breakers Rated on a Symmetrical Current
Basis
6. ANSl/IEEE C37.012 IEEE Application Guide for Capacitance Current Switching for
AC High-Voltage Circuit Breakers Rated on a Symmetrical
Current Basis
7. ANSl/IEEE C37.11 IEEE Application Guide for Electrical Control of AC High-
Voltage Circuit Breakers Rated on a Symmetrical Current Basis
8. ANSl/IEEE C37.20.2 IEEE Standard for Metal-Clad and Station-Type Cubicle
Switchgear
9. ANSl/IEEE C37.55 Metal-Clad Switchgear Assemblies - Conformance Testing
Procedures
10. ANSIIIEEE C37.90 Standard for Relays and Relay Systems Associated with Electric
Power Apparatus
11. ANSl/IEEE C39.1 Requirements for Electrical Analog Indicating Instruments
12. ANSl/IEEE C57.13 IEEE Standard Requirements for Instrument Transformers
13. ANSl/IEEE 450 Recommended Practice for Maintenance, Testing and
Replacement of Large Lead Storage Batteries for Generating
Stations and Substations
14. ANSIINETA MTS Standard for Maintenance Testing Specifications for
Electrical Power Equipment and Systems (Latest Edition)
15. NEMACCl Electrical Power Connectors for Substations
16. NEMASG-2 High Voltage Fuses
17. NEMASG-4 Alternating-Current High-Voltage Circuit Breakers
18. NEMASG-5 Power Switchgear Assemblies
19. NEMA250 Enclosures for Electrical Equipment
20. NFPA 70 National Electrical Code, 2017 Edition
21. NFPA 70B Recommended Practice for Electrical Equipment
Maintenance, 20 16 Edition
22. NFPA 70E Standard for Electrical Safety in the Workplace, 2018 Edition
23. OSHA 29 CFR 1910- S Occupational Safety and Health Standards - Subpart S -
Electrical
24. UL 1008A Transfer Switch Equipment, Over 1000 Volts

1.7 NECESSARY EQUIPMENT FOR 15kV SWITCHGEAR SERVICE

A. Provide, the following items as applicable for performance of the preventative maintenance
services specified herein:

1. Personnel protective equipment in accordance with NFPA 70E


2. Project folder/note book for documentation of test results and findings
3. Standard medium-voltage switchgear accessories and maintenance tools
4. Standard medium-voltage vacuum breaker accessories and maintenance tools

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
5. Insulation resistance test set- 1000 VDC minimum
6. Low resistance digital ohmmeter- 100 amp
7. Specimen grounding jumpers and ground mats
8. Torque wrenches, pound-inches and pound-feet
9. Phase rotation meter
10. RMS digital multimeter
11. Phase angle meter
12. Secondary injection test set
13. AC/DC power supply
14. Variable current source
15. Current transformer test set
16. AC HiPotentional test set- 60 Hz
17. Hygro-thermometer
18. Hydrometer
19. Temperature correction chart for battery maintenance
20. Shopvac
21. Lock-out/Tag-out

1.8 ACCEPTABLE PROVIDERS

A. The preventative maintenance services for 15 kV metal-clad switchgear, vacuum circuit breakers
and associated equipment and accessories shall be provided by one of the following:

1. ABB, EPIS
745 Charleston Oaks Dr.
St. Louis, MO 63021
(314) 223-0113
Kirk Voiding
2. Eaton Engineering Services and Systems
62 Soccer Park Rd.
Fenton, MO 63026
(636) 717-3426
Matt Wilhelm
3. Electric Power Systems
21 Millpark Ct.
Maryland Heights, MO 63043
(314) 218-2745
James Vaughn
4. Schneider Electric Services
801 Corporate Center Dr.
O'Fallon, MO 63368
(636) 439-8585
Andrew Watson

B. The preventative maintenance services for the 15 kV metal-clad switchgear station batteries and
battery charger shall be provided by one of the following:

1. Electrorep Energy Products, Inc


2121 Schuetz Rd.
St. Louis, MO 63146
(314) 606-5225
Stacey Hart

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
2. Engineered Power Systems
48 Progress Parkway
Maryland Heights, MO 63043
(314) 637-9634
Ken Kostecki
3. ALCAD
(203) 985-2538
Jason McShessrey

PART 2 - PRODUCTS

Not Used

PART 3- EXECUTION

3.1 ACTIVITIES PRIOR TO PREVENTATIVE MAINTENANCE SERVICE AND TESTING

A. Procure and Review:

1. Equipment drawings, schematics and wiring diagrams associated with equipment/device


being tested (Owner has on file)
2. Instruction bulletins/books (Owner has on file)
3. Revised power system study provided under Section 261327 - 15 kV Metal-Clad
Switchgear Control Modifications
4. Test data and field service forms
5. Safe working procedures and MSDS forms that apply to the equipment/device being tested
6. Site safety rules and emergency procedures
7. Site electrical one-line diagram (Project Drawing E-601)
8. Site 12.47 kV equipment schedules (Project Drawing E-603)

B. Preparation and Safety (NOTE: The following recommendations are not intended to take
precedence over the Contractor's safety procedures or industry standards. The Contractor shall
be responsible for the safety of all personnel on-site and for any damage to Owner's equipment
caused by Contractor's action, inaction, willful act and/or negligence.)

1. Perform switching of existing S&C pad-mounted switchgear as necessaty to isolate the 15


kV metal-clad switchgear to be serviced and to connect temporary generators as specified
in Section 260500- Common Work Results for Electrical. Contractor shall be responsible
for the switching all equipment and circuit breakers. The Owner does not have personnel
on site to operate 12.47 kV switches or circuit breakers.
2. Open the 2000A site emergency generator output circuit breaker inside the generator
enclosure.
3. Apply lock-out/tag-out to all open switches and circuit breakers.
4. Contact Ameren Missouri for disconnection of both incoming utility feeders to the 15 kV
metal-clad switchgear and apply safety grounds on both main breaker sections of the
switchgear. NOTE: Ameren Missouri may choose to apply their own safety grounds.

C. Verify:

1. The equipment nameplate ratings are consistent with the equipment drawings provided.
2. Suitability of tools and test equipment for use on the equipment to be tested.

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 4


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
3. Test data and field service forms are available with the following data to be recorded prior
to the start of testing:

a. Customer and project information


b. Equipment designation from site one-line diagram and equipment schedules
c. Serial number of equipment, if applicable
d. Field data
e. Equipment ratings; e.g., voltage, current, control voltage, shott circuit current rating,
interrupting rating, etc.
f. Vacuum circuit breaker counter readings as found prior to the start of testing
g. As found conditions of equipment prior to the start of testing
h. Temperature, humidity and general weather conditions at the time of testing
i. Date and time of testing
j. Test equipment data
k. Field service technicians name and company information
1. As found circuit breaker and protective relay settings prior to testing

3.2 INSPECTION AND TEST PROCEDURES

A. As a minimum, perform the following inspection, testing and preventative maintenance activities
for all equipment. Report serious deficiencies immediately to the responsible contact at the
Facility.

1. Examine 15 kV metal-clad switchgear line-up including all circuit breakers and accessories
for:

a. Loose or obviously damaged components


b. Proper identification
c. Proper application of the circuit breakers with the cells
d. Compliance to switchgear drawings
e. Doors, panels, and sections for alignment, dents, scratches, fit and missing hardware
f. Maintenance accessories for servicing and operating all devices

2. Inspect switchgear for:

a. Inspect all grounding connections for cleanliness and alignment


b. Main bonding jumper for proper size and termination per NEC 250
c. Insulators for evidence of physical damage or contaminated surfaces
d. Surge arrester and surge capacitor size, type, installation and connection to verify
compliance with the switchgear drawings, Ameren Missouri Specification CE-10
(included in Attachment A to Section 261327 - 15kV Metal-Clad Switchgear
Control Modifications), and NEC 280
e. Breaker cells, primary and secondary disconnects for physical condition, cleanliness
and lubrication.
f. Alignment and penetration of instrument transformer withdrawal disconnects,
current carrying, and grounding components
g. Control power transformers
h. Wiring for damaged insulation, broken leads, tightness of connections, proper
crimping, and overall general condition
i. Structure, grounding, cables and bus assembly
j. Proper operation of switchgear walk-in enclosure lighting fixtures, emergency lights,
convenience receptacles and air conditioning system

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115 - 5


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02

i. Verify the grounding electrode conductor is properly sized in accordance


with NEC 250 and is properly terminated
ii. Verify the proper grounding of instruments, panels, and connections per
NEC250
iii. Verify that conductors are properly identified
iv. Verify cable termination tightness to manufacturer's published values by
calibrated torque wrench
v. Verify integrity ofinsulation on bus bars and cable to bus connections
vi. Verify tightness of accessible bolted electrical connections by calibrated
torque wrench in accordance with manufacturer's published values.
vii. Verify correct barrier and shutter installation and operation
viii. Verify that filters are in place and/or vents are clear from obstructions

k. Control and instrumentation:

i. Verify that all PT (VT) and CT ratios properly correspond to drawings and
that polarity is conect
ii. Verify that shorting screws and bars are removed from CT's and terminal
blocks as required
iii. Verify the primary and secondary fuse ratings or circuit breakers match the
switchgear drawings
iv. Verify meter scaling and type match the switchgear drawings
v. Verify that circuit breaker and meter addresses are set for microprocessor-
communication packages
vi. Verify that accessible moving components are adequately lubricated per the
equipment manufacturer's recommendations

1. Key Interlock Systems

i. Verify key number and exchange codes


ii. Verify proper sequencing to comply with switchgear drawing notes
iii. Attempt to close locked-open devices
iv. Attempt to open locked-closed devices
v. Make key exchange with devices operated in off-normal positions
vi. Disposition of duplicate keys found shall be per the Owner's safety policy

m. With breaker open, inspect:

i. Primary leads, insulators, and disconnects


ii. Ground contact, secondary disconnect, close and trip interlocks, levering
latch, MOC and TOC operators, and all other interlocks

n. Verify manual operation of breaker

i. Charge closing spring using maintenance tool (manual charge handle), then
reomove handle
ii. Verify Charged/Discharged status indicators function properly
iii. Close breaker manually and verify Closed and Discharge indicator
iv. Charge breaker again and verify that the breaker stays closed
v. Trip breaker manually and verify Open indicator

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 6


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
vi. Repeat several times to confirm mechanism operates consistently and
reliably
vii. Charge closing spring and close manually

o. With breaker closed:

i. Inspect contact erosion indicator mark on vacuum interrupter moving stem


ii. Inspect contact wipe ("T" Slot)
iii. Measure contact resistance using a 100 amp DC source and compare with
previous results if information is available
iv. Perform "CLOSED" portions of AC high potential test (vacuum integrity
test)
v. Open breaker

p. With breaker open:

i. Perform the "OPEN". portion of AC high potential test


ii. Perform vacuum integrity test according to the instruction book and at the
OEM recommended voltage level. Do not exceed maximum voltage level
stipulated for this test. Provide adequate barriers and protection
against x-radiation during this test.
NOTE: Some DC high potential test sets are half-wave rectified and may
produce peak voltages in excess of the breaker manufacturer's
recommended maximum. It may also give erroneous indication of loss of
vacuum of the interrupter.

q. Perform control wiring AC high potential test at 1,125V RMS. Do not perform this
test on wiring connected to solid state components.
r. Rack the breaker into the cell ("Test Position" if applicable) using the standard
breaker maintenance accessories and check for binding or hesitation and the
movement of the breaker position indicator
s. Verify the proper operation of all breakers/cell accessories, shutters, auxiliary
switches, cell MOC and TOC switches, key interlocks, and cell status indicators
t. Verify the proper operation of all breaker/cell interlocks:

i. Maintenance interlock
ii. Levering interlock
iii. Positive interlock
iv. Negative interlock
v. Positive closing interlock
vi. Extension rail interlock
vii. Breaker/cell rating code interlock
viii. All other devices

B. As a minimum, provide the following electrical testing on the switchgear:

1. Insulation system:

a. Perform insulation-resistance tests on each bus section, phase-to-phase and phase-


to-ground. Values shall be in accordance with manufacturer's published data.
b. Perform insulation-resistance tests at 500 VDC on all control wiring. Do not
perform this test on wiring connected to solid-state components.

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115 - 7


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

2. Control and Instrumentation:

a. Perform the following tests on control power transformers:

i. Insulation-resistance tests. Perform measurements from winding-to-


winding and each winding-to-ground. Test voltages shall be as specified by
the equipment manufacturer.
ii. Verify correct secondary voltage by energizing primary winding with
system voltage. Measure secondary voltage with the secondary winding
connected.
iii. Perform secondary wiring integrity test. Confirm potential at all devices.
iv. Verify correct function of control transfer relays located in switchgear.
v. Verify operation of switchgear anti-condensation space heaters.

b. Perform the following tests on potential transformers:

i. Perform insulation-resistance tests. Perform measurements from winding-


to-winding and each winding-to-ground. Test voltages shall be as specified
by the equipment manufacturer.
ii. Verify correct secondary voltage by energizing primary winding with
system voltage. Measure secondary voltage with the secondary winding
connected.
iii. Perform secondary wiring integrity test. Confirm potential at all devices.

c. Perform the following tests on current transformers:

i. Ratio
ii. Saturation

3. Protection devices:

a. Verify settings for all protective relays per the revised power system study provided
under Section 261327- 15 kV Metal-Clad Switchgear Control Modifications.
b. Adjust settings to agree with the Settings Table in the report as required.
c. Determine accuracy of protective relays in accordance with the manufacturer's
instructions and industry standards.

4. Metering:

a. Verify operation and proper set-up of all metering devices.


b. Determine accuracy of meters in accordance with the manufacturer's instructions
and industry standards.

C. As a minimum, provide the following system function testing on all power circuit breakers and
cells:

1. Check for the correct value of control power for close and trip functions prior to racking
breaker into cell.
2. Verify the electrical operation of the breaker (in the test position or with auxiliary cable)

a. Perform close, trip, and anti-pump tests

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 8


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

3. Verify operation of the breaker from all local and remote-control switches or terminal
blocks.

a. Close and Open the breaker from each controllable device in the circuit
b. Verify proper operation of circuit breaker position indicator on breaker control
switches
c. Confirm which tests must be performed with the breaker in the "Test Position".

4. Verify that each protective relay and lock-out (86) device trips the breaker as designed.

D. Perform the following after completion of testing.

1. Before re-energizing the equipment:

a. Record the "as left" operations counter value on all circuit breakers
b. Remove metal shavings and thoroughly clean and vacuum the equipment. Use only
cleaning products recommended by the equipment manufacturer. No petroleum-
based cleaners of any kind shall be used.
c. Remove and account for all test equipment, jumper wires, and tools used during
testing
d. Remove and account for all safety grounds and tools
e. Replace all barriers and covers, close all doors, and secure all latches. Do not use
power actuated tools to install threaded fasteners to avoid cross threading or stripping
of the threads from overtightening and ensure all fasteners are installed.

2. Ensure all test forms and field data sheets are properly completed with all data entered
correctly. Note all corrective actions taken, deficiencies found and recommendations, as
well as any general comments.
3. Apply a test sticker that includes name of testing firm date and initials of technician on
each protective relay, circuit breaker and switchgear vertical section door.
4. Review and organize all test results into a report with cover that includes the project
information and a table of contents.

E. As a minimum, preform the following inspections and testing on the switchgear flooded lead-acid
batteries:

1. Visual and mechanical inspection

a. Verify the battery ventilation system is operable


b. Inspect physical and mechanical condition
c. Inspect battery racks, mounting, battery spill containment system, anchorage,
clearances, alignment, and grounding
d. Prior to cleaning or adding electrolyte, perform as-found tests
e. Verify electrolyte level. Measure electrolyte specific gravity and temperature levels
and record.
f. Verify presence of flame arresters
g. Neutralize acid on exterior surfaces and rinse with de-mineralized water
h. Clean corroded/oxidized terminals and apply an oxide inhibitor.
i. Inspect bolted electrical connections for high resistance using one or more of the
following methods:

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 9


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
i. Using a low-resistance ohmmeter
ii. Verify tightness of accessible bolted connections by calibrated torque-
wrench in accordance with the battery manufacturer's published data.
iii. Perform thermographic survey under load

2. As-Left electrical tests

a. Perform resistance measurements through all bolted connections with a low-


resistance ohmmeter.
b. Measure voltage of each cell and total battery voltage with charger energized and in
float operation.
c. Measure intercell connection resistances.
d. Perform ohmic measurement tests.
e. Perform a load test in accordance with battery manufacturer's specifications or
ANSI/IEEE 450 - Recommended Practice for Maintenance, Testing and
Replacement of Large Lead Storage Batteries for Generating Stations and
Substations.

3. Test values- Visual and Mechanical

a. Electrolyte level and specific gravity should be within normal limits.


b. Compare bolted connection resistance values to values of similar connections.
Investigate values which deviate from those of similar bolted connections by more
than 50 percent of the lowest value.
c. Bolt-torque levels should be in accordance with the battery manufacturer's published
data.

4. Test values- Electrical

a. Compare bolted connection resistance values to values of similar connections.


Investigate values which deviate from those of similar bolted connections by more
than 50 percent of the lowest value.
b. Cell voltages should be within 0.05 volt of each other or in accordance with the
battery manufacturer's published data.
c. Compare bolted connection resistance values to values of similar connections.
Investigate values which deviate from those of similar bolted connections by more
than 50 percent of the lowest value.
d. Cell internal ohmic (resistance, impedance, conductance) values should not vary by
more than 25 percent between identical cells that are in a fully charged state.
e. Results ofload tests should be in accordance with manufacturer's published data or
ANSI/IEEE 450.

F. As a minimum, preform the following inspections and testing on the switchgear battery charging
system:

1. Visual and mechanical inspection

a. Inspect for physical and mechanical condition


b. Inspect anchorage, alignment, and grounding
c. Prior to cleaning the unit, perform as-found tests
d. Clean the unit

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 10


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
j. Inspect bolted electrical connections for high resistance using one or more of the
following methods:

i. Using a low-resistance ohmmeter


ii. Verify tightness of accessible bolted connections by calibrated torque-
wrench in accordance with the battery manufacturer's published data
iii. Perform thermographic survey under load

k. Inspect filter and tank capacitors


l. Verify operation of cooling fans. Clean filters if provided.
m. Verify location and condition of temperature compensation sensor

2. As-Left electrical tests

a. Perform resistance measurements through all bolted connections with a low-


resistance ohmmeter.
b. Measure and record float voltage and equalize voltage levels. Adjust to battery
manufacturer's recommended settings.
c. Verify high-voltage shutdown settings
d. Verify current limit
e. Verify calibration of meters
f. Verify charger temperature compensation is working conectly
g. Verify operation of alarms, both local and remote
h. Measure and record input and output voltage and current
i. Measure and record AC ripple current and/or voltage imposed on battery
j. Perform full load testing of charger

3. Test values- Visual and Mechanical

a. Compare bolted connection resistance values to values of similar connections.


Investigate values which deviate from those of similar bolted connections by more
than 50 percent of the lowest value.
b. Bolt-torque levels should be in accordance with the manufacturer's published data.

4. Test values -Electrical

a. Compare bolted connection resistance values to values of similar connections.


Investigate values which deviate from those of similar bolted connections by more
than 50 percent of the lowest value.
b. Float and equalize voltage settings should be in accordance with the battery
manufacturer's published data.
c. Current limit should be within manufacturer's recommended maximum value.
d. Results of alarm operation should be in accordance with manufacturer's published
data and system design.
e. Input and output voltage should be in accordance with manufacturer's published
data.
f. AC ripple cunent and/or voltage imposed on the battery should be in accordance
with manufacturer's published data.
g. Charger should be capable of manufacturer's specified full load.

5. Perform the following after completion of battery system and charger testing:

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 11


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
a. Ensure all test forms and field data sheets are properly completed with all data
entered correctly. Note all corrective actions taken, deficiencies found and
recommendations, as well as any general comments.
b. Apply a test sticker that includes name of testing firm date and initials of technician
on each battery rack and the battery system charger.
c. Review and organize all test results into a report with cover that includes the project
information and a table of contents

END OF SECTION 260115

PREVENTATIVE MAINTENANCE FOR 15kV METAL-CLAD SWITCHGEAR 260115- 12


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
SECTION 260500- COMMON WORK RESULTS FOR ELECTRICAL

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The requirements of this section are applicable to all work performed under Division 26 -
Electrical.

1.3 RELATED SECTIONS

A. Section 033000- Cast In Place Concrete

1.4 COORDINATION

A. It is the intent of the Electrical Division of these Specifications that all electrical work specified
herein be coordinated as required with the work of all other Divisions of the Specifications and
Drawings so that all installations shall operate as designed.

B. Provide a complete operational electrical system. Route conduit and install equipment to avoid
conflicts with other trades and to enhance maintainability of system.

C. All construction work shall be carried on in a manner so as not to interfere with operation of the
Owner's facilities.

D. The Owner intends to make continued use of existing facilities. Utilities and services to existing
facilities shall not be interrupted without the Owner's approval as to the time and duration. The
Owner will continue to occupy the existing facilities throughout the construction operations, and
the Contractor shall so organize his work as to cause a minimum of interference with the normal
routine activities of the facilities. All interruptions shall be scheduled at the convenience of the
Owner.

E. The Contractor shall coordinate his work so there shall be no prolonged interruptions of existing
equipment and all interruptions of utilities must be scheduled with the Owner. In no case shall
any utilities be left disconnected at the end of a work day or over the weekend.

F. Any interruptions of any utilities either intentionally or accidentally shall not relieve the
Contractor responsible from repairing and restoring the utility to normal service. Repairs and
restoration shall be made before the workmen responsible for the repair and restoration leave the
job on the day such interruptions occur.

G. The Contractor's area for construction shall be as shown on the Drawings.

H. The Contractor shall maintain access to the Owner's facilities during construction by keeping
clear the drives in the construction area. Any blockage of the drives shall be scheduled with the
Owner.

COMMON WORK RESULTS FOR ELECTRICAL 260500- 1


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml40 1-02
I. This project will involve several contractors in addition to this Contractor. There may also be
contractors not associated with this project working in the vicinity.

J. This Contractor shall cooperate fully with the other contractors in the conduct of the work. Such
cooperation with regard to work schedules, area of work, etc., is to be a normal part of this type
of project and no extra compensation will be allowed for it.

1.5 DEFINITIONS

A. Concealed: Where the word "concealed" is used in conjunction with raceways, equipment, and the
like, the word shall be understood to mean hidden from sight as in chases, ftmed spaces, or above
suspended ceilings.

B. Exposed: Where the word "exposed" is used, the word shall be understood to mean open to view.

C. Provide: Where the word "provide" is used, in the Specifications or on the Drawings, it shall
mean "furnish and install" unless otherwise noted or specified.

D. Related Work: The sections referenced under RELATED SECTIONS shall be understood to
include provisions which directly affect the work being specified in the section where RELATED
SECTIONS occurs.

E. The Work: Where the words "the Work" are used together, they shall be understood to mean the
work under contract that is governed by these Specifications and the Drawings.

1.6 SUBMITTALS

A. The Contractor shall submit to the Engineer for approval, prior to fabrication and in accordance with
the procedures outlined in Section 013300- Submittals, all submittals as required by each Section in
this Division of these Specifications.

B. Each submittal shall be properly identified as to the specific equipment to which it relates.
Identification on the submittal shall be by reference to equipment identification numbers as shown
on the Drawings and, if applicable, by reference to the appropriate Article of the Specifications
in which the equipment is specified.

C. Shop drawings, brochures, or manufacturer's product data sheets showing more than one size or
model shall be marked to indicate the size or model proposed for the particular application.

D. All submittals shall be certified by the Contractor as being conect for the proposed work.

E. Submittals in the form of shop drawings shall include complete data on the equipment to be
provided, including physical dimensions and other infonnation required for installation,
performance capabilities and limitations, and schedules indicating locations when more than one
type of an item is to be used.

F. Prior to submittal, shop drawings shall be coordinated with the work of all other trades.

G. Any and all submittals that do not comply with all of the above requirements will be rejected and
returned without review.

H. Provide operating instructions and maintenance manuals in accordance with Section 013300 -
Submittals, Section 007213 - General Conditions and 007300- Supplementary Conditions.

COMMON WORK RESULTS FOR ELECTRICAL 260500-2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
1.7 RECORD (AS-BUILT) DRAWINGS

A. The Contractor shall update a complete set of the construction drawings, shop drawings and
schedules of all work daily by marking changes, and at the completion of their work (prior to
submission of request for final payment) note all changes and turn the set over to the Owner's
Representative in accordance with Section 007213- General Conditions. The updates shall show
all addenda, all field changes that were made to adapt to field conditions, changes resulting from
contract changes or supplemental instmctions, and all locations or structures. All concealed items
both inside and outside shall be accurately located and referenced to permanent features such as
interior or exterior wall faces and dimensions shall be given in a neat and legible manner in a
contrasting colored pencil or ink. If approved by the Engineer, an electronic file format may be
provided.

B. No deviations from the Contract Drawings or approved shop drawings shall be made without
prior approval from the Engineer or Owner's Representative.

1.8 REFERENCE STANDARDS

A. Included as a basic part of these Specifications are the applicable regulations of the standards
listed below. Portions of all of certain recognized industry or association standards referred
to herein as being a requirement of these Specifications shall be considered as binding as though
reproduced in full herein. Unless otherwise stated, the reference standard shall be the latest
edition of the standard which is cutTent as of the date of issuance of the Contract Documents.
Where conflicts exist from one code to another, the more stringent requirement shall apply.

B. Referenced Codes and Standards constitute minimum requirements and strict compliance is
required therewith unless supplemented and/or modified by more stringent requirements in these
Specifications.

C. Reference may be made to standards either by full name or by letter designation as follows:

1. ACI American Concrete Institute


2. AHDGA American Hot Dip Galvanizers Association, Inc.
3. AISC American Institute of Steel Construction
4. ANSI American National Standards Institute
5. ASA American Standards Association
6. ASTM American Society for Testing & Materials
7. AWS American Welding Society
8. BOCA Building Officials and Code Administrators International, Inc.
9. CSA Canadian Standards Association
10. EEl Edison Electric Institute
11. EIA Electronics Industries Association
12. ETL Electrical Testing Laboratories, Inc.
13. FMRC Factory Mutual Research Corp
14. lACS International Annealed Copper Standard
15. IBC International Building Code
16. IBEW International Brotherhood of Electrical Workers
17. ICC International Code Council
18. ICEA Insulated Cable Engineers Association
19. IEC International Electrotechnical Commission
20. IEEE Institute of Electrical and Electronics Engineer
21. IFC International Fire Code

COMMON WORK RESULTS FOR ELECTRICAL 260500- 3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
22. ISA The Instrumentation, Systems, and Automation Society
23. JIC Joint Industrial Council
24. NBFU National Board ofFire Underwriters
25. NEC National Electrical Code (NFPA 70)
26. NECA National Electrical Contractors Association
27. NEMA National Electrical Manufacturers Association
28. NETA InterNational Electrical Testing Association
29. NFPA National Fire Protection Association
30. NIST National Institute of Standards and Technology
(formerly National Bureau of Standards, NBS)
31. OSHA Occupational Safety and Health Administration
32. UL Underwriters' Laboratories, Inc.

1.9 REGULATORY LAWS, ORDINANCES, CODES AND STANDARDS

A. The governing federal, state, and local laws, codes and standards in effect at the project site
constitute the minimum requirements for all electrical work, and strict compliance therewith is
required unless supplemented and/or modified by more stringent requirements of the Contract
Documents.

B. All work under this Contract shall be performed in full compliance with the 2017 edition of the
National Electrical Code (NEC) NFPA-70.

c. The Contractor shall keep a copy of the 2017 NEC on the project site for his reference at all times.

D. Requirements in reference specifications and standards are a minimum for equipment, material,
and work. In instances where capacities, size, or other features of equipment, devices, or materials
exceed these minimums, meet specified or scheduled capacities.

E. Resolve code interpretations discovered in Contract Documents with Engineer prior to Contract
award. After Contract award, make corrections or additions necessary for compliance with
applicable codes.

1.10 CONTRACT DRAWINGS

A. Included under Section 000115 - List of Drawings of these Specifications are the Drawings which
indicate in general the character, arrangement, and construction of equipment and materials called
for in these Specifications.

B. Drawings are generally diagrammatic and are intended to encompass a system that will not interfere
with the structural and architectural design of the building. Coordinate work to avoid interferences
between conduit, equipment, architectural, and structural work.

c. Coordinate with architectural and structural features, trim and millwork details, and install equipment
in cabinets or other special areas as directed by Engineer.

D. Drawings are based on equipment specified. Make adjustments, modifications, or changes


required, due to use of other equipment.

COMMON WORK RESULTS FOR ELECTRICAL 260500-4


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml40l-02
1.11 WORKMANSHIP

A. All work shall be done under the supervision of the Contractor who shall provide competent
foremen to lay out all work. All work shall be laid out with due regard for proper working
clearances about electrical equipment in accordance with NEC Article 110 and the space
requirements of other contractors. The Contractor shall immediately report to the Owner's
Representative any conflict or difficulties with regard to the installation.

B. The Contractor shall be completely responsible for all work installed by him and shall employ
only competent and experienced personnel of proper trades to perform the work.

C. All work shall be installed so as to be accessible for operation, maintenance, adjustment,


replacement, and repair with particular attention given to locating controls and other items
requiring periodic lubrication, cleaning, adjusting, or servicing of any kind.

D. Control stations, conduit drops, electrical enclosures, etc. shall be located so as not to interfere
with access required for the necessary service and operation of equipment and shall meet the
working clearance requirements of Article 110 of the National Electrical Code.

PART 2 -PRODUCTS

2.1 MATERIALS AND EQUIPMENT

A. Only NEW, clean and perfect equipment, apparatus, materials, and supplies of latest design and
manufacture shall be incorporated in the work in order to assure an electrical system of high
quality.

B. All materials shall be new, shall be installed according to manufacturer's specifications or as


directed by the Engineer, and shall be listed and labeled by Underwriters' Laboratories, Inc. (UL)
or other nationally recognized testing laboratory.

c. All materials and equipment furnished under these Specifications shall be standard products of
the various manufacturers except where special construction or performance features are called
for. Where more than one of the specific items is required, all shall be of the same type and by
the same manufacturer.

D. The product of a manufacturer shall be acceptable only when that product complies with or is
modified as necessary to comply with all specified and indicated requirements in the Contract
Documents.

E. Materials and equipment not herein specified or indicated as to manufacturer but necessary for
complete functioning systems shall be provided from sources conforming to the quality levels
and functional requirements for corresponding materials and equipment set forth herein.

2.2 MANUFACTURER'S EQUIPMENT NAMEPLATES

A. All equipment shall have factory applied permanent nameplates indicating the manufacturer's
name, model and serial numbers, and any other data necessary to conform to specified
requirements.

COMMON WORK RESULTS FOR ELECTRICAL 260500- 5


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml40l-02
2.3 PAINTING AND FINISHES

A. All purchased equipment shall have a factory applied standard finish of the manufacturer's
standard color unless otherwise specified.

B. Finishes which are marred during shipping, handling, or installation shall be touched up by the
Contractor to match the original finish.

2.4 EQUIPMENT TAGGING

A. All equipment and materials shipped under these Specifications shall be properly tagged with the
name of the item, name of the project and project address, and shall bear the Contractor's name.

PART 3 - EXECUTION

3.1 SCOPE OF THE WORK

A. The Contractor shall provide all labor, materials, equipment, tools, supervision, and services
required for the complete installation of all electrical work as shown on the Drawings and
described in these Specifications.

B. The work under Divisions 26 of the Specifications includes, but is not limited to, the following
items:

1. Demolition of existing power and branch circuit conductors, cables, raceways, boxes, and
equipment
2. Demolition of existing control conductors, cables, raceways, boxes, and devices
3. Disconnection, handling, relocation and/or reconnection of existing equipment and electric
power and rerouting of existing power and control circuits as required and as shown on the
Drawings
4. Removal and disposal off site of the existing equipment and materials to be removed
5. All feeder and branch circuit wiring and raceways
6. All control conductors, cables, raceways, boxes and devices
7. Grounding and bonding
8. Junction and pull boxes
9. Fuses and circuit breakers
10. Detailed design and implementation of automatic transfer control system modifications to
the existing Siemens main campus 12.47kV switchgear
11. Resistive load bank
12. Repairs to the fuel tank instrumentation on the site emergency generator
13. Annunciation of 12.47kV campus main switchgear status and alarm signals at remote
building
14. Preventative maintenance on existing 12.47kV campus main switchgear including batteries
and battery charger

3.2 SHIPMENT AND DELIVERY

A. The Contractor shall be responsible for the furnishing and safe delivery of all materials and
equipment required for the project and for the safekeeping of all material and equipment until
final acceptance by the Owner's Representative.

COMMON WORK RESULTS FOR ELECTRICAL 260500-6


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
B. The Contractor shall be responsible for protecting all electrical equipment intended exclusively
to function indoors. Such equipment must be stored indoors and protected against exposure to or
accumulation of dust, moisture, freezing, flooding, corrosion or other form of damage. The
Contractor shall clean and restore damaged finishes as required to place the installation in a "like
new" condition before acceptance by the Owner.

3.3 SAFETY MEASURES

A. The Contractor shall arrange his work in such a manner that a minimum of interference will be
experienced with the operations of the Owner or with traffic, both pedestrian and vehicular, either
in the vicinity of or on the project site.

B. The blocking of thoroughfares shall be kept to a minimum and shall be coordinated with the
Owner's Representative and authorities have jurisdiction.

c. The Contractor shall comply with the U.S. Department of Labor-Occupational Safety and Health
Administration (OSHA) - Occupational Safety and Health Standards, all local and state public
safety regulations and provide such safety measures as signs, signals, road blocks, safety lights,
railings, guards, temporary walkways, crossings and similar safety equipment as may be required
for the adequate protection of the public, the Owner's personnel, workmen engaged on the project,
and property.

3.4 WORK VERIFICATION AND FIELD MEASUREMENTS

A. The Contractor shall verify the voltage, phase, full-load current and exact location of all electrical
equipment before rough-in.

B. The Contractor shall note that the configuration and dimensions of actual equipment may vaty
from that shown on the Drawings depending on the equipment supplied. The Contractor shall be
responsible for making the necessary modifications to connecting conduit, bases, etc. required by
the equipment supplied.

c. All dimensions and clearances affecting the installation of work shall be verified at the project
site in relation to established datum, to existing items and conditions, and to the work of other
trades.

D. The Contractor shall assume responsibility for proper installation of materials in the space
available.

E. The location of all equipment and systems shall be coordinated to preclude interferences with
other construction.

F. Should interferences occur which will necessitate deviations from layout or dimensions shown
on the Drawings, the Owner's Representative and/or Engineer shall be notified, and any changes
shall be approved before proceeding with the Work.

G. Where crowded locations exist and where there is a possibility of conflict between the trades, the
Contractor shall make composite drawings showing the exact locations of the items in question
(pipes, ducts, conduits, equipment, etc.). Drawings shall be based on actual measurements, after
consultation and agreement between the trades, and shall be approved by the Engineer before
installation ofthe Work.

COMMON WORK RESULTS FOR ELECTRICAL 260500-7


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
H. The Contractor shall provide all necessary offsets, raises or drops in conduits and fixtures as
required by existing conditions at no additional cost to the Owner.

I. The location of all items shall be obtained fi·om the Drawings. The Owner's Representative
and/or the Engineer shall be allowed to relocate any item within a 10-foot radius from the scaled
location on the plans without additional cost to the Owner, provided this is done prior to or during
rough-in and before finish installation.

3.5 ELECTRICAL WORK DEMOLITION AND RELOCATION OF EXISTING


EQUIPMENT

A. See Section 260505- Selective Demolition for Electrical in these Specifications.

3.6 MOUNTING HEIGHTS

A. Unless otherwise indicated elsewhere in these Specifications or Drawings, mounting heights of


wiring devices and equipment shall be in accordance with the following schedule.

B. The following item mounting heights shall be above finish floor/work platform to the horizontal
centerline of the item.

Item Mounting Height

1. Control Stations, selector switches 4 feet 0 inches


and push button controls

C. The following item mounting heights shall be above finish floor/work platform to the 1QQ of the item.

Item Mounting Height


1. Control panels

a. 36" high or less 5 feet 6 inches


b. 40" to 60" high 6 feet 0 inches

3.7 FASTENING TO BUILDING STRUCTURES

A. The methods of attaching or fastening equipment, equipment supports, raceways, or hangers to


building structures shall be subject to approval by the Owner's Representative at all times.

B. Support of electrical equipment and raceways shall be provided in accordance with Section
260529- Hangers and Supports for Electrical Equipment.

3.8 CUTTING, PATCHING AND REPAIRING

A. The Contractor shall be responsible for all cutting required for and resulting from the installation
of his work, except where noted otherwise. The Contractor shall patch and repair the holes and
restore the surface finish.

B. The Contractor shall place sleeves for conduits that must pass through foundations, walls, and
slabs ahead of concrete pouring. Failing in this, the Contractor shall do the necessary cutting and
sealing thereafter in an approved manner.

COMMON WORK RESULTS FOR ELECTRICAL 260500- 8


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M 1401-02
C. Under no circumstances shall any structural members, load bearing walls, building columns or
footings be cut without first obtaining written permission from the Engineer.

D. Cutting shall be in accordance with the following.

1. Concrete and Masonry: All openings for conduit shall be core drilled. Square or rectangular
openings shall be saw cut.

E. Patching shall be in accordance with the following.

1. Non-fire Rated Concrete and Masonry: Patch the opening with Sika Top 122 Plus (Sika
Corp.) non-shrink grout or approved equal, finished smooth with adjacent surface.
2. Fire-rated Construction: In accordance with Section 260533.13 - Conduit for Electrical
Systems.

3.9 ELECTRICAL TESTS

A. The Contractor shall, after the installation is completed, visually inspect all items to ascertain that
each item is not damaged and is in proper working condition, and shall test all circuits and
demonstrate to the satisfaction of the Owner's Representative and/or Engineer, the following:

1. That all power and control circuits are continuous and free from short circuits and unspecified
grounds.
2. That the resistance to ground of all ungrounded circuits operating below 600 volts is 50
megohms or greater at a test voltage of 1000 VDC.
3. That all circuits are properly connected to the correct phase and in accordance with the
Drawings and applicable wiring diagrams. Circuits shall be numbered as shown on the
Drawings and connected to equalize the loading on all phases.
4. That all circuits and equipment are operable. Demonstration shall include the proper
functioning and operation of each unit to the Owner's satisfaction, and the continuous
operation of all power circuits for not less than 24 hours.
5. That all equipment requiring calibration and adjustment has been properly calibrated and
adjusted in accordance with its intended function and the manufacturer's recommendations.
6. That all equipment and systems function properly.
7. That the phasing sequence and synchronization is the same throughout the entire electrical
system. The Contractor shall be responsible for the conect phase rotation on all motors and
devices. Any item that is damaged as a result of improper rotation or phasing shall be replaced
by the Contractor at no additional cost to the Owner.

B. All tests shall be made after notification to and in the presence ofthe Construction Representative
and/or Engineer and the authorities having jurisdiction, if required.

C. The cost of labor, materials, instruments and supplies of any kind required for testing shall be
borne by the Contractor.

D. Before starting up any system, each piece of equipment comprising a part of the system shall be
checked for proper lubrication, drive rotation, continuity of controls, and any other condition
which could cause damage to equipment or endanger personnel.

E. Test runs shall be made over the full design load range where possible, or simulated to the
satisfaction of the Construction Representative for other conditions. During test runs all

COMMON WORK RESULTS FOR ELECTRICAL 260500-9


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
necessary adjustments shall be made, controls checked for proper operation, motors checked for
possible overload, and the entire system checked by the Contractor for any abnormal condition.

F. During the test runs and prior to acceptance of any system, the Owner's designated operating
personnel shall be instructed in the operation and maintenance of the system.

G. Material and equipment damaged or shown to be defective during tests, unable to perform at
design or rated capacity, or not in accordance with the Specifications shall be repaired or replaced
by the Contractor to the full satisfaction of the Owner's Representative at no cost to the Owner.

3.10 STARTUP

A. All systems shall be completely assembled, tested, adjusted and demonstrated to be ready for
operation to the satisfaction of the Construction Representative.

B. The Contractor shall provide qualified personnel to perform start up assistance and final
acceptance testing of all equipment after it has been completely installed and is ready to be
energized, prior to applying voltage.

c. When the Contractor, Designer and Construction Representative agree that the new CMSWGR
automatic control system is ready for final acceptance testing, Contractor shall arrange for UL
Field Services and Ameren Missouri to come to the site for acceptance testing. Temporary
generators as noted in Article 3.11 below shall be provided to power the facility during the
multiple facility power outages that will occur as part of this acceptance testing. Any additional
charges incurred from UL Field Services or Ameren Missouri due to the equipment not
performing as required will be borne by the Contractor.

D. The Contractor shall be responsible for the operation and maintenance, including all costs thereof,
for systems or equipment temporarily placed in operation for testing and adjusting purposes, or
for the convenience or necessity of the Contractor prior to final acceptance by the Owner.

E. The Contractor shall instruct the Owner's operating personnel in the operation and maintenance
of the electrical equipment during energization but prior to acceptance by the Owner.

3.11 TEMPORARY POWER

A. The Bellefontaine Habilitation Center is a 24/7 live-in care facility for developmentally disabled
individuals and as such, requires that electrical power be maintained during the execution of the
work specified in the plans and these specifications.

B. The Work will require interruptions of the primary incoming 12.47 kV power to the facility. The
facility has a standby emergency diesel-engine generator that provides backup power for the
entire facility. However, the generator is connected to the same 12.47 kV campus main
switchgear (CMSWGR) as the two incoming utility feeders so no power will be available to the
facility when work is taking place that requires that the 12.47 kV CMSWGR be de-energized.

c. During all times when the 12.47 kV CMSWGR must be de-energized for more than 3 consecutive
hours for any reason during execution of the Work, temporary gasoline or diesel-engine
generators must be provided on campus as follows:

1. CMSWGR lighting, convenience receptacles, battery charger and site emergency generator
enclosure lighting, convenience receptacles, and battery charger - 208Y/120V, 3-phase

COMMON WORK RESULTS FOR ELECTRICAL 260500- 10


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
generator to be provided by Contractor. Connect to line side of 150A main circuit breaker
in Panelboard LPSG inside CMSWGR walk-in enclosure after disconnecting secondary
leads from the switchgear control power transformer. Size generator as required to serve
the connected load, approximately 8 to 10 kW, field verify.
2. Street Lighting - 25kW, 480Y/277V, 3-phase generator to be provided by Contractor.
Connect to secondary leads after disconnecting at transformer T-1. NOTE: This generator
is only required when a facility power outage occurs during times when the street lighting
would normally be in operation.
3. Warehouse/Food Distribution, Unit 1/Maintenance, Garage - 200 kW, 208Y/120V, 3-
phase generator to be provided by Contractor. Connect to secondary side of transformer
T-15 and back feed medium-voltage loop #2.
4. Remainder of the facility - 300kW, 208Y/120V, 3-phase generator to be provided by
Contractor. Connect to secondary side of transformer T-DP/GH and back feed medium-
voltage loop #3.
5. Apartments- 100 kW, 120/240V, 1-phase trailer mounted generator provided by Owner.
Connect to secondary leads after disconnecting at transformer T -11.

D. The Contractor shall be responsible for furnishing the four (4) generators noted above along
with cables and all other items required to connect all five (5) generators noted above.

E. The Contractor shall be responsible for furnishing all fuel for all generators.

F. Use of temporary generators to power the facility shall be limited to normal working hours,
Monday through Friday, excluding holidays observed by the State of Missouri. If an after-hours
power outage is deemed by the Contractor to be unavoidable he must petition the Construction
Representative for approval a minimum of 72 hours in advance.

G. The Contractor shall have a person knowledgeable in the operation of the temporary generators
on site at all times when one or more temporary generators are in operation.

END OF SECTION 260500

COMMON WORK RESULTS FOR ELECTRICAL 260500- 11


THIS PAGE INTENTIONALLY LEFT BLANK
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
SECTION 260505- SELECTIVE DEMOLITION FOR ELECTRICAL

PART 1- GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. This Section includes demolition and removal of selected portions of facility required for new
construction.

1.3 DESCRIPTION OF WORK

A. Furnish all materials, labor, equipment and services necessary to perform all electrical demolition
work.

B. Work included in this Section includes all demolition work as shown on the Electrical Drawings
and as specified herein and as required to complete the Work.

1.4 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

1.5 DEFINITIONS

A. Demolish: Completely remove and legally dispose of off-site.

B. Existing to Remain: Existing items of construction that are not to be permanently removed and
that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

c. Recycle: Recovery of demolition waste for subsequent processing in preparation for reuse.

D. Remove: Detach items from existing construction and legally dispose of them off-site unless
indicated to be removed and salvaged or removed and reinstalled.

E. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall
where indicated.

F. Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver
to Owner. Include fasteners or brackets needed for reattachment elsewhere.

1.6 SUBMITTALS

A. Schedule of Selective Electrical Demolition Activities: Indicate detailed sequence of selective


electrical demolition and removal work, with starting and ending dates for each activity and
interruption of electric power services.

B. Inventory: Submit a list of items to be removed and salvaged and deliver to Owner prior to start
of demolition.

SELECTIVE DEMOLITION FOR ELECTRICAL 260505- 1


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml40l-02
C. Predemolition Photographs or Video: Show existing conditions of adjoining constmction and
site improvements, including finish surfaces that might be misconstrued as damage caused by
selective electrical demolition operations. Submit before the Work begins.

D. Disposal Records: If hazardous wastes are removed by Contractor, submit the following:

1. Hazardous Waste Transporter license


2. Permit or license for hazardous waste treatment or disposal facilities
3. Completed Uniform Hazardous Waste Manifest for all shipments
4. Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept
hazardous wastes.

1.7 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with governing EPA notification regulations before


beginning selective demolition. Comply with hauling and disposal regulations of authorities
having jurisdiction.

B. Standards: Comply with ANSI A10.6 and NFPA 241, latest editions.

C. Prior to beginning demolition, arrange a conference with the Construction Representative to


review electrical demolition scope, procedures, schedule and items to be salvaged for the Owner.

1.8 PROJECT CONDITIONS

A. Owner will occupy the facility during construction. Localized areas to be demolished will be
vacated during demolition work. Conduct selective electrical demolition so Owner's operations
will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far
as practical.

C. Notify Construction Representative of discrepancies between existing conditions and Drawings


before proceeding with selective demolition.

D. Hazardous Materials: Hazardous materials are present in the interior of the building to be
selectively demolished.

1. If materials suspected of containing hazardous materials are encountered, do not disturb:


immediately notify Engineer and Construction Representative.
2. Hazardous material remediation will be completed as a portion of this contract. This work
is anticipated to be sequenced with the proposed phasing of construction activities.

E. On-site storage or sale of removed items or materials is not permitted.

F. Utility Service: Maintain electrical service to building during selective electrical demolition
operations.

1. Disconnect electrical power only to the items of equipment or the panelboard that is
identified for removal under the selective electrical demolition operations.

SELECTIVE DEMOLITION FOR ELECTRICAL 260505-2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
1.9 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged
during selective demolition, by methods and with materials so as not to void existing warranties.

1.10 MATERIALS OWNERSHIP

A. Except for items or materials to be reused, salvaged, reinstalled or otherwise indicated to remain
the Owner's property, demolished materials shall become the Contractor's property and shall be
removed from the site with further disposition at the Contractor's option but in compliance with
ordinances and regulations related to the materials being disposed.

1.11 COORDINATION

A. Arrange demolition schedule so as not to interfere with Owner's on-site operations and the
operations of adjacent occupied buildings.

B. Review and finalize selective electrical demolition schedule and verify availability of materials,
demolition personnel, equipment, and facilities needed to make progress and avoid delays.

C. Review requirements of General Demolition Contractor and work performed by other trades that
rely on demolition of electrical circuitry or equipment to allow for structural demolition or
removal of equipment.

D. Review areas where existing electrical circuitry and/or equipment is to remain in place and
requires protection. ·

PART 2 -PRODUCTS (NOT USED)

PART 3 -EXECUTION

3.1 EXAMINATION & RECORDING OF CONDITIONS

A. Verify that utilities have been disconnected and capped before statting selective electrical
demolition operations.

B. Survey existing conditions and coordinate and identify the extent of the electrical demolition work
required. Record existing conditions using preconstruction photographs.

c. Inventory and record the condition of items to be removed and reinstalled and items to be removed
and salvaged. Use photographs to document conditions.

D. When unanticipated site, mechanical, electrical, or structural elements that conflict with intended
function or design are encountered, investigate and measure the nature and extent of conflict.
Promptly submit a written report to Construction Representative and Engineer.

E. Perform surveys as the work progresses to detect hazards resulting from the execution of the
work.

3.2 COORDINATION

A. No electrical demolition work shall be performed without prior approval of the Construction
Representative.

SELECTIVE DEMOLITION FOR ELECTRICAL 260505- 3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
B. Electrical demolition work shall be carried on in a manner so as not to interfere with operation ofthe
Owner's facilities.

C. Any electrical demolition work which interferes with Owner's operation shall be scheduled with the
Construction Representative and be subject to the Owner's approval.

D. Maintain existing services required to avert disruption to the Owner's on-going operations and
protect them against damage during the performance of the work.

E. Do not interrupt existing electrical service to occupied facilities except when authorized in writing
by the Construction Representative.

F. Provide temporary electrical service during interruptions to existing electrical systems, as acceptable
to the Construction Representative.

G. Unless noted otherwise, provide not less than two weeks notice to the Owner if shutdown of electrical
service is required during the execution of the work.

H. The Contractor shall not remove any material beyond the limits indicated on the Drawings unless
given permission to do so by the Construction Representative. Any such material removed shall be
replaced by the Contractor at his expense. If the items removed are damaged and/or cannot be
satisfactorily reinstalled, new matetial of like construction shall be furnished and installed by the
Contractor at his expense.

I. All damages to buildings and utilities to remain in place shall be promptly repaired at no cost to the
Owner. Repairs and restoration of accidental utility interruptions shall be made before the workmen
responsible for the repair and restoration leave the job on the day such interruptions occur.

3.3 PREPARATION

A. Site Access and Temporary Controls: Conduct selective electrical demolition and debris-removal
operations to ensure minimum interference with roads, streets, walks, walkways, and other
adjacent occupied and used facilities.

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent
injury to people and damage to adjacent buildings and facilities to remain.

C. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required
to preserve stability and prevent movement, settlement, or collapse of construction and finishes
to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being
demolished.

D. Existing building openings may be used to remove material. No new openings may be made
without approval of the Construction Representative.

3.4 PROTECTION

A. Comply with governing laws, codes, and regulations governing fire protection and environmental
protection during electrical demolition operations.

B. Provide dust control and ventilation as required in areas of electrical demolition.

SELECTIVE DEMOLITION FOR ELECTRICAL 260505-4


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
c. Execute electrical demolition work, so as to insure adjacent areas against damage which might occur
from falling debris or other causes; do not interfere with the use of, operations in, or around adjacent
areas; maintain free and safe passage of persons around the areas of electrical demolition.

D. Provide temporary handrail, barricades, floor plates, etc. as required to provide protection for open
elevated platforms, holes, etc. created by the electrical demolition work.

E. Premises shall be maintained and protected from all unsafe or hazardous conditions at all times.

F. Protect existing surfaces, active utility services, and equipment which are to remain in place.

G. Protect lighting fixtures, exit signs, fire alarm devices, wireless routers, and cellular phone boosters
that are to remain in place from damage during demolition and construction operations. Exposed
fixtures and devices shall have a plastic bag or other suitable covering affixed over the item to protect
from dust and paint splatters.

3.5 DUST CONTROL

A. Contractor shall use temporary enclosures and other suitable methods as necessary to limit the
amount of dust and dirt carrying over to other parts of the Owner's property.

B. Adequacy of the dust control methods shall be subject to the approval of the Construction
Representative.

c. Areas of major electrical demolition inside the Owner's property shall be enclosed by means of
temporary walls constructed of wood framing with plywood or 6 mil polyethylene sheets.

D. Temporary enclosures shall be removed by the Contractor upon completion of the electrical
demolition work unless otherwise directed by the Construction Representative.

3.6 ELECTRICAL DEMOLITION- GENERAL

A. Remove all work indicated on the Drawings and as required to complete the new work indicated.

B. During electrical demolition operations, keep areas adjacent to electrical demolition work free of dust
and debris.

c. During electrical demolition operations, if suspected hazardous materials or conditions are


uncovered, stop work in that area, and inform the Construction Representative.

D. At concealed spaces, such as hollow walls, ducts, and pipe interiors, verify condition and contents of
hidden space before starting electrical demolition operations.

E. Neatly cut openings and holes plumb, square and true to dimensions, required.

F. Use cutting methods least likely to damage construction to remain or adjoining construction.

G. To minimize disturbance of adjacent surfaces, use hand or small power tools designed for sawing or
grinding, not hammering and chopping. Temporarily cover openings to remain.

H. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing
finished surfaces.

I. Do not use cutting torches until work area is cleared of flammable materials.
SELECTIVE DEMOLITION FOR ELECTRICAL 260505-5
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
J. Maintain portable fire-suppression devices during flame-cutting operations.

K. Contractor shall take care when using a torch to cut steel welded or bolted to structural members so
as to cut flush with but not damage the structural members.

L. All hanger and support material for demolished piping and conduit shall be removed back to the
primary structural support member. Grind connection to primary member smooth and touch up with
paint to match adjacent surface.

M. All elevated equipment and materials to be demolished shall be carefully lowered (not dropped) by
means of temporary riggings. Contractor shall not overload any elements of existing structure during
the rigging operation.

N. Locate selective electrical demolition equipment and remove debris and materials so as not to impose
excessive loads on supporting walls, floors, or framing.

0. Dispose of demolished items and materials promptly.

3.7 ELECTRICAL DEMOLITION

A. Protect existing electrical equipment and installations indicated to remain. If damaged or disturbed
in the course of the Work, remove damaged portions and install new products of equal capacity,
quality and functionality.

B. The Contractor shall use caution in the demolition of electrical systems and shall inform himself of
the status (active, inactive) of all electrical systems to be demolished prior to proceeding.

C. Prior to breaking or cutting conduit within the demolition area, the Contractor shall ascertain that the
system has been identified or shown on the Drawings to be wrecked under this Contract. Contact
the Construction Representative for clarification prior to demolishing or wrecking questionable
items.

D. The Contractor shall remove, cap and/or relocate equipment, outlets, lighting fixtures, conduit, wire,
etc., as specified or as shown on the Drawings and as may become necessary because of existing
field conditions at no additional cost to Owner.

E. All existing lighting fixtures, switches, receptacles, outlets, etc., shall be removed as required to
complete the work and blank covers provided over the outlets, unless othetwise noted.

F. Properly dispose of all lighting fixture lamps and ballasts in accordance with all applicable Federal,
State, and local laws and regulations.

G. All concealed conduit for circuits which are partially or completely abandoned may remain in place.
Remove all wiring for concealed circuits that are to be completely abandoned and cut and remove
concealed conduit 2 inches below the surface of adjacent construction. Cap conduits and patch
surface to match existing finish and fire rating. Exposed conduit for abandoned circuits shall be
removed, unless otherwise noted.

H. Exposed conduit containing circuits which are to be retained shall remain in place, unless otherwise
indicated or required.

I. Wiring for existing circuits which must be rerouted, or which are partially abandoned, shall be
reconnected to service the outlets/loads remaining on the circuit.

SELECTIVE DEMOLITION FOR ELECTRICAL 260505- 6


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
J. All wiring for a circuit which is to be removed or abandoned shall be removed back to the panel
which supplied the circuit.

K. Completely remove all hangers and suppmts to building structure. Grind off stubs without damaging
parent material (steel, concrete, etc.) and touch up paint as required.

L. All abandoned or remaining empty conduit with open ends resulting from demolition work shall be
promptly capped, plugged, or sealed.

M. All open conduit knockouts, holes or unused hubs in electrical boxes and enclosures shall be properly
plugged with suitable blanking devices that maintain the NEMA rating of the box or enclosure.

3.8 CONCRETE AND MASONRY DEMOLITION

A. Demolish concrete and masonry in small sections.

B. Cut concrete and masonry at junctures with construction to remain, using power driven masonry saw
or hand tools. Do not use power-driven impact tools.

3.9 PATCHING

A. All holes or openings in floors, walls or ceilings resulting from electrical demolition shall be
properly sealed with material similar to the adjacent surface/finish. Patch holes in concrete floors
and ceilings where conduits are removed using non-shrink epoxy grout or concrete material to
match existing surfaces and construction. Patch holes in walls and partitions where conduits are
removed to match existing construction and finish.

B. All rough edges of openings created by electrical demolition shall be promptly patched to create a
finished surface.

c. Openings in concrete shall be patched with cement mortar.

D. Openings in masonry shall be patched by toothing in masonry units to match existing.

E. Maintain the fire rating of all floors, walls, partitions and ceilings when patching.

3.10 REMOVED AND SALVAGED ITEMS

A. Carefully remove and clean salvaged items.

B. Pack or crate items after cleaning. IdentifY contents of containers.

c. Store items in a secure area until delivery to Owner.

D. Transport items to Owner's storage area as directed by Construction Representative.

E. Protect items from damage during transport and storage.

3.11 REMOVED AND REINSTALLED ITEMS

A. Carefully remove items to be reinstalled.

B. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match
new equipment.
SELECTIVE DEMOLITION FOR ELECTRICAL 260505-7
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
c. Pack or crate items after cleaning and repairing. IdentifY contents of containers.

D. Protect items from damage during transport and storage.

E. Reinstall items in locations indicated.

F. Comply with installation requirements for new materials and equipment.

G. Provide connections, supports, and miscellaneous materials necessary to make item functional for
use indicated.

H. If the items removed are damaged and/or cannot be satisfactorily reinstalled, new material of like
construction shall be furnished and installed by the Contractor at his expense.

3.12 EXISTING ITEMS TO REMAIN

A. Existing Items to Remain: Protect construction indicated to remain against damage and soiling
during selective electrical demolition.

B. When permitted by Construction Representative, items may be removed to a suitable, protected


storage location during selective electrical demolition and reinstalled in their original locations
after selective electrical demolition operations are complete.

3.13 DISPOSAL

A. All debris resulting from electrical demolition operations shall become the property of the Contractor
and shall be removed daily from the Owner's property unless otherwise permitted by the Construction
Representative.

B. Storage of removed materials on site will not be permitted.

c. Sale of removed materials on-site will not permitted.

D. Transport demolished materials off Owner's propetiy and dispose of legally in accordance with
Federal, State, and local laws and regulations.

E. Upon completion of work, remove tools, materials, apparatus, and rubbish. Leave area clean,
neat, and orderly.

3.14 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective electrical
demolition operations.

B. Return adjacent areas to condition existing before selective electrical demolition operations
began.

3.15 HAZARDOUS MATERIALS

A. The Owner, to the best of his knowledge, has identified hazardous materials such as friable asbestos
or lead in the work areas.

B. Should the Contractor discover additional material requiring removal which is suspected to contain
hazardous materials, do not disturb.

SELECTIVE DEMOLITION FOR ELECTRICAL 260505- 8


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
C. Contact and consult with the Construction Representative prior to proceeding. The Construction
Representative shall direct the Contractor how to proceed.

END OF SECTION 260505

SELECTIVE DEMOLITION FOR ELECTRICAL 260505- 9


THIS PAGE lNTENTIONALLY LEFT BLANK
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

SECTION260519- LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND


CABLES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall furnish and install all conductors, wiring, and cables as specified herein and
as shown on the Drawings.

1.3 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

B. Section 260526 - Grounding and Bonding for Electrical Systems

c. Section 260533.13- Conduit for Electrical Systems

D. Section 260533.16- Boxes for Electrical Systems

E. Section 260553 - Identification for Electrical Systems

F. Section 260583- Wiring Connections

1.4 SUBMITTALS

A. Manufacturer's product data sheets shall be submitted for each of the following items:

1. 600-volt building wire


2. 600-volt multiconductor control cable
3. 600-volt shielded instrumentation cable
4. CAT 5e copper Ethernet cable

B. Submit test report indicating results for copper wire and cable continuity and resistance testing.

PART 2 -PRODUCTS

2.1 GENERAL

A. All cable and wire shall have copper conductors; aluminum shall not be substituted nor permitted.

B. All conductors shall be new, shall be approved and listed by Underwriters' Laboratories, Inc., (UL),
shall bear UL identification, and shall have been manufactured within six months from date of the
Contract. If requested by the Engineer, the Contractor shall supply authenticated data from the wire
manufacturer stating the manufacturing date of the wire.

C. All wire sizes are expressed in American Wire Gauge (A WG) or in circular mils. Unless otherwise
indicated, all conductors shall have 90°C rated insulation (wet or dry). The current rating of all
conductor sizes shall be calculated using the correction factors and ambient temperature adjustment
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519- 1
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
factors in NEC Article 310-15(B) but under no circumstance shall exceed the values listed in the
60°C temperature column of the tables for circuits 100 amps and below or the 75°C temperature
column for circuits over 100 amps.

D. Conductors for all branch circuits and feeders shall be color coded in accordance with the National
Electrical Code (NEC) and conectly phased throughout the electrical system.

2.2 600-VOLT BUILDING WIRE

A. All conductors for lighting and power systems, including equipment grounding conductors and single
conductor control wiring shall be copper, 600-volt, single conductor building wire.

1. Conductor: ASTM B3, annealed copper. Conductor sizes 12 and 10 AWG shall be solid,
8 AWG and larger and 14 AWG single conductor control wiring shall be stranded per
ASTM B8. Minimum conductor size shall be 12 AWG except for single conductor control
wiring which shall be 14 A WG.
2. Insulation: 600-volt, heat and moisture resistant, Gasoline and Oil Resistant I and II,
polyvinyl chloride (PVC) per UL Standard 83; thickness per UL Standard 83.
3. Jacket: A tough nylon jacket shall be applied directly over the insulation per UL Standard
83.
4. Temperature Rating, Continuous Use: 90°C wet or dry locations.
5. UL Listed: Type THHN-THWN-2.
6. Testing: All cables shall be tested in accordance with the applicable requirements of UL
Standard 83.
7. Certification: All cables shall be certified to be in conformance with all applicable
requirements of UL Standard 83.
8. Identification: Surface printing on the cable shall show manufacturer's name, conductor
size and metal, voltage rating, UL symbol, insulation type and color per NEC Article 310-
110- Conductor Identification and Section 260553- Identification for Electrical Systems.
9. Manufacturer: Alanwire, Cerrowire, General Cable Company, Southwire Company or
approved equal.

B. Leads to special equipment shall be as recommended or supplied by the fixture or equipment


manufacturer and as shown on the Drawings or as required by applicable codes.

2.3 600-VOLT MULTI-CONDUCTOR CONTROL CABLE

A. All low voltage control cable shall be copper, 600-volt, unshielded, multi-conductor control cable
conforming to ICEA S-73-532/NEMA WC57.

1. Conductors: ASTM B3 and B8; Class B stranded, bare annealed copper confonning to
ICEA S-73-532/NEMA WC57. Size 18 AWG or 16 AWG as indicated on the Drawings.
Where no size is indicated use size 16 AWG.
2. Insulation: 600-volt, flame-retardant, polyvinyl chloride (PVC) with clear polyamide (nylon)
per ICEA S-73-532/NEMA WC57; minimum thickness: 15 mils PVC and 4 mils nylon per
ICEA S-73-532/NEMA WC57 Table 3-1. Color coding shall be ICEA Method 1, E-2.
Where wire colors white and/or green are required, color coding shall be ICEA Method 1,
E-1.
3. Jacket: Lead-free, flame-retardant, sunlight resistant polyvinyl chloride (PVC) per ICEA
S-73-532/NEMA WC57 Section 4, Paragraph 4.2 with thickness per ICEA S-73-
532/NEMA WC57, Table 4-1 as follows:

a. 16 AWG, 2 to 12 conductors: 45 mils

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519- 2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
b. 18 A WG, 2 to 12 conductors: 45 mils

4. Temperature Rating: Cable shall be suitable for continuous use at 90°C dry, 75°C wet (ICEA
S-73-532/NEMA WC57, Section 3, Paragraph 3.4.6)
5. UL Listed: Type TC-ER Power and Control Tray Cable per UL 1277
6. Testing: All cables shall be tested in accordance with the applicable requirements ofiCEA
S-73-532/NEMA WC57 and IEEE 383.
7. Certification: All cables shall be certified to be in conformance with all applicable
requirements ofiCEA S-73-532/NEMA WC57 and IEEE 383.
8. Flame Test Certification: Passes IEEE-383 ribbon burner flame test
9. Identification: Surface printing on the cable shall show the manufacturer's name, number
and size of conductors, voltage rating, UL information, insulation type, jacket type, and
numbered footage markers.
10. Manufacturer: General Cable Type VNTC, or approved equal by Belden, Dekoron or
Okonite

2.4 600-VOLT SHIELDED INSTRUMENTATION CABLE

A. Shielded instrumentation cable, with shielded twisted pairs; 600-volt rated conforming to ICEA S-
73-532/NEMA WC57.

1. Conductors: ASTM B3 AND B8; bare, annealed copper, Class B stranded confonning to
ICEA S-73-532/NEMA WC57, size 18 AWG or 16 AWG as indicated on the Drawings.
Where no size is indicated use size 16 A WG.
2. Insulation: 600-volt, flame-retardant, polyvinyl chloride (PVC) with clear polyamide (nylon)
per ICEA S-73-532/NEMA WC57; minimum thickness: 15 mils PVC and 4 mils nylon per
ICEA S-73-532/NEMA WC57 Table 3-1. Color coding shall be by Method 1 per ICEA S-
73-532/WC57 Appendix E using color-pigmented compounds. One (1) black and one (1)
white conductor. When multiple pairs are used, group identification shall be by printed
numbers on one conductor of each pair in consecutive order.
3. Pair Shield: Aluminized polymer or aluminized polyester tape with a tinned stranded copper
drain wire. Shields to be isolated from all other assemblies.
4. Cable Shield: Aluminized polymer or aluminized polyester tape with a tinned stranded copper
drain wire
5. Jacket: Lead-free, flame-retardant, sunlight resistant polyvinyl chloride (PVC) per ICEA S-
73-532/NEMA WC57 Section 4, Paragraph 4.2 with thickness per ICEA S-73-532/NEMA
WC57, Table 4-1
6. Identification: Sutface printing on the cable shall show the manufacturer's name, insulation
type, jacket type, number of pairs, size of conductors, voltage rating, and numbered footage
markers.
7. Temperature: Cable shall be suitable for continuous use at 90°C dty, 75°C wet (ICEA S-73-
532/NEMA WC57, Section 3, Paragraph 3.4.6)
8. Testing: All cables shall be tested in accordance with the applicable requirements ofiCEA S-
73-532/NEMA WC57 and IEEE 383.
9. Certification: All cables shall be certified to be in conformance with all applicable
requirements ofiCEA S-73-532/NEMA WC57 and IEEE 383.
10. Manufacturer: General Cable Company Type VNTC or approved equal by Belden, Dekoron
or Okonite

2.5 CAT 5e COPPER ETHERNET CABLE

A. 300-volt, CAT 5e (200MHz), 4-pair, UIUTP - Unshielded, indoor/outdoor, premise horizontal


Ethernet cable conforming to NECIUL Specification CMR, CMX.

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519- 3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
B. Conductors: Solid bare copper size 24 A WG

C. Insulation: 300-volt, polyolefin (PO); minimum thickness: 0.023". Color coding shall be:

1. Pair 1: White/blue strip and blue


2. Pair 2: Whjte/orange strip and orange
3. Pair 3: White/green strip and green
4. Pair 4: White/brown strip and brown

D. Jacket: Lead-free, flame-retardant, sunlight resistant polyvinyl chloride (PVC)

E. Temperature Range: -20°C to +75°C- installation, -40°C to +75°C- operating, UL temp rating
90°C

F. Electrical Characteristics:

1. Nominal Mutual Capacitance: 15 pF/ft


2. Maximum Capacitance Unbalanced: 330pF/100m
3. Nominal Velocity ofPropagation: 68%@ 100MHz
4. Maximum Delay: 537.60ns/100m@ 100MHz
5. Maximum Delay Skew: 45ns/100m@ 100MHz
6. Maximum Conductor DC Resistance: 9.38 nllOOm@ 20°C
7. Maximum DC Resistance Unbalanced: 3%@ 20°C

G. UL Listed: Type CMR, CMX

H. Testing: All cables shall be tested in accordance with CSA Flame Test FT4

I. Manufacturer: Belden 1594A or approved equal

2.6 600-VOLT CONNECTIONS AND TERMINATIONS

A. Provide connections and terminations for 600-volt wire and cable in accordance with Section 260583
-Wiring Connections.

2.7 CABLE PULLING LUBRICANT

A. Cable pulling lubricant shall be compatible with all cable jackets. The lubricant shall be UL
Listed. The lubricant shall contain no greases, silicones, or polyalkylene glycol oils or waxes.

B. A 200-gram sample of the lubricant, when placed in a one-foot, split metal conduit and fully dried
for 24 hours at 105°C, shall not spread a flame more than three inches beyond a point of ignition
at a continued heat flux of 40 KW/M 2 • Total time of test shall be one-half hour.

C. Cable pulling lubricant shall meet the following minimum specifications:

1. Lubricity at 200 lbs/ft Normal Pressure:

a. PVC or XLP jacketed cable/PVC conduit


Coefficient of dynamic friction ........................ ::::; 0.15
b. PVC or XLP jacketed cable/HDPE duct
Coefficient of dynamic friction ........................ ::::; 0.15

2. Percent Non-Volitle Solids ....................................... ::::; 5.5%


LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519-4
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
3. Temperature Use Range ................................ 20°F to ll0°F
4. pH ............................................................. ~ 6.5,::::; 9.0
5. Flammability ............................................. No Flash Point
6. Polyethylene Stress Cracking ...................None/ASTM Dl693
7. Temperature Stability:

a. < 10% change in Brookfield viscosity from 40°F to 100°F


No separation after ·five fi·eeze/thaw cycles or 24-hour exposure at 120°F

D. Cable pulling lubricant shall be:

1. POLYWATER® J
2. 3MWL
3. Approved equal by Ideal

PART 3 - EXECUTION

3.1 GENERAL

A. Store all conductors and cable indoors, protected from moisture.

B. Provide homerun conductors of continuous length without joint or splice fi·om overcurrent protective
device to first load termination point.

C. Provide power feeder conductors of continuous length without joint or splice for their entire length.

D. Conductors shall be continuous from source to destination without splices or taps in conduit runs,
except where indicated on the Drawings to compensate for voltage drop or where required to
prevent excessive pulling tension or sidewall pressure on wire or cable. Submit all proposed
splice locations to the Engineer for approval prior to pulling wire and cable. Where permitted,
splices shall be mechanically strong and have an insulation value equal to the wire or cable being
spliced. All splices and taps shall be contained within NEC sized junction boxes meeting the
requirements of Section 260533.16- Boxes for Electrical Systems.

E. All conductors and cables shall be in a raceway (conduit, duct, etc.) approved by the Engineer, unless
otherwise indicated.

F. Install conductors and cable with adequate bending radius in accordance with the National Electrical
Code and the conductor and cable manufacturer's recommendations:

1. Greater than six (6) times the conductor and cable outside diameter for 600-volt and below
wire and cable.

G. Swab the inside of conduit and raceways to insure they are dry and clean before conductors or cables
are pulled. Care shall be exercised in pulling to avoid damage to the conductors or cables. Pull all
conductors into a conduit at the same time. An approved type of wire pulling lubricant, UL Listed
for the application, shall be used.

H. All conductors and cables shall be installed directly from reels or coils. Conductors and cables shall
not be pulled along the ground or subjected to treatment that may cause abrasion or other damage to
conductor and cable insulation.

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519- 5


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
I. Use pulling means; including fish tape, cable, rope, and basket weave wire/cable grips that do not
damage the conductor, cable or raceway.

J. All conductors and cables shall be installed as recommended by the manufacturer. The
manufacturer's recommended ma'timum pulling tension and minimum bending radius shall be
adhered to during installation. Utilize the necessary guides, pulleys, sleeves, and pulling aids to
prevent abrasion and damage to the conductors or cables during installation. Monitor pulling tensions
and associated sidewall pressures to prevent damage to conductors and cables.

K. Provide individual dedicated full size neutral for each and every branch circuit.

L. Neatly train and lace wiring inside boxes, panelboards, and switchgear. Provide supplemental
structural members and materials as required to support wire and cable without transmitting strain to
connection points. Wire and cable shall be supported at 2-foot intervals as a minimum.

M. Group and tie single conductors of a circuit together at a minimum of 2-foot intervals in boxes,
panelboards, and switchgear.

N. Remove and discard conductors and cables cut too short or installed in wrong raceway. Do not install
conductors or cables which have been removed from a raceway.

0. Do not install conductors or cables in conduit which contains wiring already in place.

P. Do not exceed NEC limits on conduit fill.

Q. Conductors terminating in outlet or device boxes shall have at least 8 inches of free conductor left
inside the box.

R. Conductors for power shall not be smaller than size 12 AWG except wire supplied with equipment
by the equipment manufacturer. Conductors for control wiring shall not be smaller than size 14
A WG unless otherwise indicated.

s. Leads to special equipment shall be as recommended or supplied by the equipment manufacturer and
as shown on the Drawings or as required by the applicable codes.

3.2 WIRING SEGREGATION

A. Isolate and segregate power wiring circuits from control and instrumentation wiring circuits in
conduit runs, boxes, panels, and equipment.

B. Isolate and segregate "normal" power circuits from "emergency" power circuits in conduit runs,
boxes, panels, and equipment.

c. Isolate and segregate lighting and convenience receptacle wiring circuits from power, control, and
instrumentation wiring in conduit and boxes.

D. Isolate control wiring circuits from instrumentation wiring circuits in conduit runs and boxes.

E. In boxes, provide isolation and segregation by rigid conduit chase through box interior or continuous
metal dividers of same material as the box.

3.3 ETHERNET CABLE INSTALLATION

A. Conceal cables in finished spaces in buildings inside walls and above accessible ceilings.
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519- 6
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
B. Comply with ANSVTIA-568.C.l.

C. Terminate all conductors. No cable shall contain unterminated elements. Make terminations only
at cable connection points at equipment. Pairs shall not be untwisted more than 0.5 inches when
terminating.

D. Cable placement shall conform to industry standards with regard to anchoring, cable support and
separation from other facilities.

1. Secure and support cables at intervals not exceeding 30 inches and not more than 6 inches
from cabinets, boxes, fittings, outlets, racks, frames and terminals.
2. Install lacing bars to restrain cables, to prevent straining connections, and to prevent
bending cables to smaller radii than minimums recommended by manufacturer.
3. Bundle, lace, and train conductors to terminal points without exceeding manufacturer's
limitations on bending radii. Use lacing bars and distribution spools.
4. Cables shall not sag or droop but shall be installed so as to maintain a flat plane with
smooth transitions from one level or direction to another.

E. Where cable is installed above suspended ceilings without cable tray or conduit, suppmi cables
by J-hook, cable hook, or cable hanger system spaced a maximum of 5 feet apart. Plastic cable
ties or bridle rings shall not be used.

1. Cables shall not be attached to lift out ceiling grid supports or laid directly on the ceiling
grid.
2. Cables shall not be attached to or supported from fire sprinkler heads or delivery systems
or any environmental sensor located in the ceiling air space.

F. Install cable without damaging conductors or cable jacket.

1. Do not install bruised, kinked, scored, deformed, or abraded cable.


2. Remove and discard cable if damaged during installation and replace with new cable.

G. Cables shall not be spliced. Do not splice cable between termination, tap, or junction points.

H. Bring cable to a minimum of 60'F before de-reeling. Heat lamps shall not be used for warming
cable.

I. Provide additional slack at both ends of cables to accommodate future cabling system changes.

1. Do not store slack in bundled loops. Slack shall be stored in fixture-S configuration in an
extended loop. Store slack above lay-in ceiling where possible.
2. In communications equipment room, install 10-foot long service loop on each end of cable.
3. Leave 18-inch slack on each cable at each equipment panel.

J. Do not bend cable in handling or installation to smaller radii than minimums recommended by
manufacturer.

K. Install exposed cable parallel and perpendicular to surfaces or exposed structural members and
follow surface contours where possible.

L. Contractor shall be responsible for verifying the actual footages and distances identified on the
Drawings.

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519- 7


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
M. Install components as indicated and according to the manufacturer's written instructions. Use
techniques, practices and methods that are consistent with the requirements of the Category rating
of the components.

N. Provide minimum separation of cables from EMI sources in accordance with the cable
manufactmer' s recommendations.

0. Test and verity cable installation after terminating at both ends in accordance with industry
standards and the manufacturer's recommendations for the Category rating of the components.

P. CAT 5e Ethernet Cable Installation: Install using techniques, practices, and methods that are
consistent with Category 5e rating of components and that ensure Category 5e performance of
completed and linked signal paths, end to end.

1. Comply with ANSI/TIA-568-C.2.


2. Do not untwist cables more than 0.5 inches from the point of termination to maintain cable
geometry.

Q. Optical-Fiber Cable Installation:

1. Comply with ANSI/TIA-568.C.3.

3.4 WIRING CONNECTIONS AND TERMINATIONS

A. Provide connections and terminations for 600-volt wire and cable in accordance with Section 260583
-Wiring Connections.

3.5 FIELD QUALITY CONTROL

A. General:

1. Testing shall be perfonned in the presence of Construction Representative. Contractor


must provide 48 hours' notice prior to conducting tests.
2. Prepare a test report upon completion of testing activities. Report format shall include the
following information:

a. Summary of test results


b. Test equipment summary (model number, accuracy, calibration date)
c. Test personnel names and sign-offs
d. Completed data sheets
e. Test log and observations
f. Certificate of Compliance

B. Inspect wire and cable for physical damage and proper connection.

C. Torque test conductor connections and terminations to manufacturer's recommended values.

D. Perform continuity tests.

E. Perform and record results of megger tests for each phase and neutral conductor for each feeder.
Include actual recorded megaohm value for each conductor of each feeder in the feeder conductor
insulation test report.

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519- 8


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
F. Provide testing for connections and terminations for 600-volt wire and cable in accordance with
Section 260583 -Wiring Connections in conjunction with the testing specified herein.

END OF SECTION 260519

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519- 9


THIS PAGE INTENTIONALLY LEFT BLANK
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
SECTION 260526- GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall furnish, install and test the grounding systems as specified herein and as shown
on the Drawings.

1.3 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

B. Section 260519 -Low-Voltage Electrical Power Conductors and Cables

C. Section 260533.13- Conduit for Electrical Systems

D. Section 260533.16- Boxes for Electrical Systems

E. Section 260583 -Wiring Connections

1.4 SUBMITTALS

A. Manufacturer's product data sheets shall be submitted for the following items:

1. Grounding conductors
2. Exothermic welds
3. Grounding clamps
4. Grounding connectors
5. Grounding rods

B. Grounding rod resistance test repmt.

PART 2 -PRODUCTS

2.1 GROUNDING CONDUCTORS

A. All grounding conductors shall be insulated, stranded copper, and unless otherwise indicated, shall
meet the same specifications, in accordance with Section 260519- Low-Voltage Electrical Power
Conductors and Cables, as the accompanying circuit conductors.

B. Aluminum shall not be substituted for copper in grounding conductors.

2.2 EXOTHERMIC WELDS

A. Grounding wire connections to building steel or grounding rods shall be welded using an
exothermic process, unless otherwise indicated. Approved exothermic processes shall be either:

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526- 1


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
1. Cadweld
Manufactured by Erico Products, Inc.; Cleveland, Ohio
2. Thermoweld
Manufactured by Continental Industries, Inc.; Tulsa, Oklahoma

B. Where welded electrical connections are referred to elsewhere in the Drawings or Specifications
as being "cadwelded," it shall be understood that the process shall be exothermic by means of one
of the above two manufactured methods

2.3 GROUNDING CONNECTORS

A. Grounding conductor connections to equipment frames, equipment enclosures, and equipment


ground lugs shall be made using corrosion resistant compression, bolted, or split-bolt connections.
Bolts for equipment ground lugs shall be copper alloy terminal with a twin clamping element.
Bolts for equipment enclosures shall be silicon bronze with lock washers. Use products by
Burndy Corp., 0-Z/Gedney, or approved equal.

2.4 GROUNDING RODS

A. Grounding rods shall be 3/4-inch diameter, 10 feet long (unless indicated otherwise on the
Drawings), high strength solid steel rod with a bonded copper jacket, and UL listed.

B. Grounding rods shall be manufactured by Copperweld Steel Company, ITT Weaver; Thomas &
Betts; Blackburn; Joslyn Mfg. and Supply Co.; or approved equal

PART 3- EXECUTION

3.1 GENERAL

A. The entire electrical system and all electrical equipment shall be grounded in strict accordance with
Article 250 of the National Electrical Code and as shown on the Drawings.

B. The grounding system shall be continuous throughout the electrical system.

C. Insulated grounding conductors shall be identified with green colored insulation or marking tape in
accordance with Section 260553- Identification for Electrical Systems and NEC Article 250-119.

D. Grounding conductors shall be continuous with no splices.

E. Protect grounding conductors against unraveling, caging, and abrasion by several wrappings of
plastic tape on all ends, where cable leaves concrete, and at necessary intermediate points.

F. Install individual grounding conductors so as not to be entirely encircled or closely encircled by


magnetic material.

G. Suitably protect grounding conductors against damage during construction. Replace or suitably
repair at the discretion of the Engineer or Construction Representative if cable is damaged by anyone
before final acceptance.

H. When a conduit, which is fabricated of magnetic materials (e.g., steel conduit), contains only
grounding conductors, the grounding conductors shall be bonded to the conduit at both ends of the
conduit run, using grounding bushings with a bonding jumper installed between each grounding
conductor and the bushing.

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526-2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
I. All neutral conductors shall be continuous throughout the electrical system and shall be grounded
only where indicated on the Drawings or as specified herein.

J. All metallic conduits shall be properly grounded.

K. All flexible conduits shall contain a properly connected green insulated copper grounding conductor,
sized in accordance with National Electrical Code, Article 250, unless otherwise indicated.

L. Flexible conduits 1-1/2" size and larger shall have an insulated stranded copper grounding conductor
sized per the NEC installed external to the conduit and bonded to grounding type conduit connectors
on each end of the conduit. The grounding conductor shall be secured to the conduit using nylon
cable ties at 12" intervals. Cut off excess cable tie. Do not leave sharp edges.

M. A properly sized green insulated copper equipment grounding conductor shall be installed in each
and every conduit.

N. All flexible cords shall contain an insulated grounding conductor, color coded green, which shall be
properly connected at each termination.

0. All electrical enclosures, panels, boxes, equipment frames, conduits, equipment frames and other
non-current-carrying metallic objects shall be grounded and bonded as required by the NEC.

P. Connections: All grounding conductor connections shall be made in accordance with the
manufacturer's written instructions. Chemically degrease and dry completely before welding. Make
up bolted connections clean and tight. All connections shall be low resistance with a resistance drop
of less than 1 ohm. Do not cover connections until they have been inspected by the Engineer or
Construction Representative.

Q. Grounding conductors and bonding jumper connection devices or fittings that depend on solder shall
not be used.

R. Bond all metal conduits to the ground bus bar conductor of the control panel, terminal box,
panelboard, switchboard or frame of the equipment to which they are connected by terminating each
conduit with a threaded steel insulated grounding bushing or insulated tln·oat, grounding type conduit
hub having a solderless lug with a bonding jumper sized in accordance with NEC Table 250-66
attached to the ground bus conductor or equipment frame. Where the enclosure does not contain a
ground bus bar, bond to the enclosure using a mechanical lug. Scrape away paint at grounding lug
attachment location.

S. All control panel, panelboard, and switchboard ground bus conductors, power transformer cases, all
transformer neutrals, and all rotating electrical equipment shall be solidly and directly grounded to
the nearest approved grounding point, or as shown on the Drawings, using a conductor sized in
accordance with the NEC Table 250-66 or as indicated on the Drawings.

T. Power system neutrals shall be grounded only at the transformer where each system neutral is derived
in accordance with NEC Article 250.

U. Equipment grounds shall be made where indicated on the Drawings. Total resistance to ground shall
not exceed five (5) ohms.

3.2 RACEWAY SYSTEM GROUNDING

A. Ground/bond metallic conduits at all termination points.


GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526-3
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
B. Where extending metallic conduit into floor or grade mounted equipment from below, provide an
insulated grounding bushing on the end of the conduit and bond to the equipment ground bus or
frame using a NEC sized bonding jumper.

3.3 GROUNDING RODS

A. Driven grounding rods shall be installed in areas wherever required and where shown on the
Drawings.

B. Unless otherwise indicated, grounding rods located outdoors shall be installed vertically with the
top of the grounding rod 3 feet below finish grade.

C. Grounding conductor connections to grounding rods shall be exothermically welded.

3.4 GROUNDING ROD TESTING

A. The Contractor shall test the resistance to ground at all ground rod locations using an AVO Biddle
DET 2/2 Ground Tester, Catalog No. 250202 or approved equal using the "Slope Method." The
total resistance to ground shall not exceed five (5) ohms. If it does, the Contractor shall install
additional ground rods and re-test until the resistance is below five (5) ohms. Provide written
report of test results including date and time of testing, test equipment used, test equipment
calibration date, and names of individuals performing the test.

END OF SECTION 260526

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526-4


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
SECTION 260529 ~HANGERS AND SUPPORTS FOR ELECTRICAL EQUIPMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall furnish and install all supports and fastening devices for mounting and
anchoring all raceways and electrical equipment as specified herein and as shown on the Drawings.

1.3 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

B. Section 260533.13 -Conduit for Electrical Systems

c. Section 260533.16- Boxes for Electrical Systems

D. Section 263236- Resistive Load Banks

1.4 SUBMITTALS

A. Manufacturer's product data sheets shall be submitted for the following items:

1. Expansion anchors
2. U-channel steel supports including associated hardware and accessories

PART 2 -PRODUCTS

2.1 GENERAL

A. Weld Rod: Use E70 electrodes for shielded metal arc welding.

B. Provide materials, sizes, and types of supports, anchors, and fasteners to carry the loads of
conduit, boxes, and equipment. Include weight of wire and cable when selecting products for
conduit, equipment and box supports.

2.2 ANCHORS AND FASTENERS

A. Provide anchors and fasteners as required to install all conduit, boxes, electrical enclosures, and
equipment.

B. Expansion Anchors: Utilize expansion anchors for attachment of electrical equipment, boxes and
raceways to concrete and solid masonry surfaces.

1. Expansion anchors shall be Type 304 stainless steel or galvanized steel, stud type expansion
anchor with a single-piece, three-section wedge, Hilti K wik Bolt III or approved equal
installed per the manufacturer's written recommendations. The anchors shall meet the
description in Federal Specification FF-S-325, Group II, Type 4, Class 1, for concrete
expansion anchors. All bolts shall have length identification.
HANGERS AND SUPPORTS FOR ELECTRICAL EQUIPMENT 260529- 1
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
C. Provide adequate corrosion resistance for all fastening systems.

D. Bolts and Nuts: ANSI regular series, semi-finished, hexagon

1. Indoors: Cadmium plated steel


2. Outdoors: Type 304 stainless steel

E. Flat Washers:

1. Indoors: Cadmium plated steel


2. Outdoors: Type 304 stainless steel

F. Lock Washers: ANSI medium, spring type

1. Indoors: Cadmium plated steel


2. Outdoors: Type 304 stainless steel

G. Beam Clamps: Steel beam and angle clamps by B-Line or Thompson

1. Indoors: Cadmium, zinc plated or hot-dipped galvanized


2. Outdoors: Type 304 stainless steel

2.3 STRUCTURAL SUPPORT SYSTEMS

A. Steel Supports: Brackets, frames and hangers shall be fabricated from standard cold rolled
structural steel shapes or prefabricated structural systems, as manufactured by B-Line Systems,
Inc., Unistrut Corporation, KindorfElectrical Products Co., or approved equal.

1. Steel supports and accessories used indoors shall be made from steel meeting the minimum
mechanical propetties of ASTM A1011 SS Grade 33, then electro-plated with zinc per
ASTM B633. Fittings shall be manufactured from steel meeting the minimum
requirements of ASTM A907 SS, Grade 33. All fittings and hardware shall be zinc plated
in accordance with ASTM B633 (SC3 for fittings, SC1 for threaded hardware).
2. Steel supp01ts and accessories used outdoors or in indoor wet areas shall be hot-dipped
galvanized steel after fabrication per ASTM A123 with a minimum coating thickness of
2.5 mils or Type 304 stainless steel.

B. Hanger Supports: Threaded rods

1. Indoors: Electro-galvanized steel


2. Outdoors: Type 304 stainless steel

PART 3- EXECUTION

3.1 GENERAL

A. The methods of attaching or fastening equipment or equipment supports or hangers to the building
structure shall be subject to the approval of the Construction Representative.

B. Do not drill or cut any structural steel members.

C. Do not cut any structural concrete members.

HANGERS AND SUPPORTS FOR ELECTRICAL EQUIPMENT 260529-2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
D. Welding on any structure shall require prior written approval from the Construction Representative
for each type of application except where specifically shown on the Drawings. Weld in accordance
withAWS.

E. Do not use piping, ductwork, raceways, or equipment as structural members for support.

F. Equipment or raceways shall not be attached to or supported from the roof deck, from removable or
knockout panels, or temporary walls or partitions unless specifically indicated on the Drawings.

G. A minimum of four (4) anchor points shall be provided for electrical equipment enclosures and
dimensioned boxes.

H. Outdoor supports shall be installed to provide a minimum of 11/16" air space between wall mounted
electrical equipment enclosures and mounting surface.

3.2 ANCHORS AND FASTENERS


A. Unless noted otherwise on the Drawings, ·expansion anchor embedment shall be as follows:

1. Bolt Diameter, in. Embedment, in.

1/4 2
3/8 2-112
1/2 3-1/2
5/8 4
3/4 4-3/4

B. Utilize welded fasteners or beam clamps for attachment of electrical equipment and raceways to
structural steel surfaces in accordance with the requirements of the Engineer or Construction
Representative. Weld in accordance with A WS.

c. Utilize toggle bolts, hollow wall fasteners or through-wall bolt fasteners for attachment of
electrical equipment, boxes and raceways to hollow masonry surfaces.

D. Utilize machine screws for attachment of electrical equipment, boxes and raceways to metal
surfaces.

E. Nails shall not be used as a means of fastening.

F. Do not use spring steel clips.

G. Do not use powder-actuated anchors.

3.3 STRUCTURAL SUPPORT SYSTEMS


A. Weld in accordance with A WS.

B. Any galvanizing damaged by welding or erection shall be repaired with cold galvanizing per ASTM
A 780. Surface preparation shall include power disk sanding the abraded or welded area to bright
metal.

C. Do not use chain.

D. Do not use perforated strap or wire.

HANGERS AND SUPPORTS FOR ELECTRICAL EQUIP:tvfENT 260529- 3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
END OF SECTION 260529

HANGERS AND SUPPORTS FOR ELECTRICAL EQUIPMENT 260529-4


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

SECTION 260533.13- CONDUIT FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall furnish and install all raceways and fittings as specified herein and as shown on
the Drawings.

1.3 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

B. Section 260519- Low-Voltage Electrical Power Conductors and Cables

c. Section 260526- Grounding and Bonding for Electrical Systems

D. Section 260529- Hangers and Supports for Electrical Equipment

E. Section 260533.16- Boxes for Electrical Systems

F. Section 260553- Identification for Electrical Systems

1.4 SUBMITTALS

A. Manufacturer's product data sheets shall be submitted for the following items:

1. Each type of conduit (galvanized rigid steel, rigid aluminum, electrical metallic tubing,
liquidtight flexible metallic, rigid non-metallic)
2. Conduit hubs
3. Conduit bodies
4. Conduit mounting clamps
5. Fire-stopping materials
6. Intumescent silicone sealant
7. Protective coating for direct buried metal conduit
8. Underground conduit warning tape
9. Conduit/duct plugs

PART 2 -PRODUCTS

2.1 CONDillT

A. All conduit shall be new and shall be approved and listed by Underwriters' Laboratories, Inc. (UL)
and shall bear the UL label of approval.

B. All conduit shall be one of the following:

1. Galvanized rigid steel conduit, "Heavywall" (GRC), shall be Schedule 40 steel conduit,
hot dipped galvanized on both the outside and the inside. Conduit as obtained from the
CONDUIT FOR ELECTRICAL SYSTEMS 260533.13 - I
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

manufacturer shall have been cut and threaded before galvanizing, thereby insuring the
galvanizing of these areas. Conduit shall conform to the latest editions ANSI Standard
C80.1 and UL Standard No.6 and shall meet the requirements ofNEC Article 344.

a. · Minimum conduit size shall be 3/4-inch.


b. Running threads are not permitted.
c. GRC shall be used outdoors above grade down to 18" below grade.

2. Rigid aluminum conduit (RAC), heavywall, copper-free threaded aluminum in accordance


with ANSI C80.5 and shall meet the requirements ofNEC Article 344.

a. Minimum conduit size shall be 1-1/2-inch.


b. Running threads are not permitted.
c. Rigid aluminum conduit may be substituted for GRC in sizes 1-1/2" and larger.

3. Electrical metallic tubing (EMT) shall be thin wall steel conduit, hot dipped galvanized on
both the outside and the inside. EMT shall conform to ANSI Standard C80.3 and U.L.
Standard 797 and shall meet the requirements ofNEC Atiicle 358.

a. Minimum conduit size shall be 3/4-inch.


b. All connectors and couplings shall be zinc plated steel. Die cast zinc type are not
acceptable.

I) Size 2-1/2" and smaller compression type


2) Size 3" and larger set-screw type

c. Connectors up to and including size 1-1/2" shall be insulated throat type. All
connectors shall be terminated with a bonding type locknut. Threaded steel insulated
grounding bushings having solderless lugs shall be used where required.
d. EMT shall be used indoors in dry locations.

4. Liquidtight flexible metal conduit (LFMC) shall be square locked galvanized steel flexible
tubing having an extruded liquidtight thermoplastic or polyvinyl chloride (PVC) jacket,
making the conduit moisture proof, oil proof, and sunlight resistant LFMC shall conform to
U.L. Standard 360 and shall meet the requirements ofNEC Article 350. Liquidtight flexible
metal conduit shall be used at all locations where a flexible conduit connection is required.

a. Minimum conduit size shall be 1/2-inch.


b. Conduit and fittings shall be rated for 90°C conductors or cable and for use in direct
sunlight.
c. Liquidtight flexible metal conduit shall contain a continuous copper ground built
into the core in sizes 1/2-inch through 1-1/4-inch, and all sizes shall be approved and
listed by Underwriters' Laboratories, Inc. (UL). Liquidtight flexible metal conduit
shall be rated for a minimum temperature range of -20°C (-4°F) to +60°C (+ 140°F),
and shall be as manufactured by the following:

1) Anamet, Inc., Type UA


2) Electri-Flex Company, Type LA Liquatite
3) Southwire/Alflex, Type UL Ultratite

d. All connectors and couplings for liquidtight flexible metal conduit shall be malleable
iron with hot-dipped galvanized or steel with zinc plated finish, compression ring,
positive ground, positive grip, liquid tight, rain-tight and oil tight.

CONDUIT FOR ELECTRICAL SYSTEMS 260533.13 - 2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

e. All connectors and fittings shall be UL Listed as suitable for grounding in sizes 1/2-
inch through 1-1/4-inch.
f. All connectors shall be insulated throat type. All connectors shall be terminated with a
bonding type locknut. Threaded steel insulated grounding bushings having solderless
lugs shall be used where required.
g. All connectors in sizes 1-1/2-inch and larger shall have a grounding lug on the gland
nut for connection of an external grounding conductor in accordance with Section
260526 - Grounding and Bonding for Electrical Systems.
h. Neither flexible metal conduit ("greenfield") nor liquidtight flexible nonmetallic
conduit shall be substituted for liquidtight flexible metal conduit.
i. Unless otherwise indicated, liquidtight flexible metal conduit shall only be used for the
final connection to:

1) Vibrating type equipment, such as motors, HVAC equipment, and transformers


(flexible connection not to exceed 3 feet).
2) As permitted elsewhere in these Specifications or Drawings.

5. Rigid non-metallic conduit shall be heavy wall Schedule 40 (NEMA EPC-40 PVC, Type
II-III) polyvinyl chloride (PVC) electrical plastic conduit and shall meet the requirements
of NEC Atiicle 352. Rigid non-metallic conduit shall be as manufactured by Carlon
Electrical Products; Condux International, Inc.; Can-Tex Industries; Certainteed Products
Corp.; or approved equal.

a. Minimum conduit size shall be l-inch.


b. Rigid non-metallic conduit (PVC) shall only be used below grade.
c. Adhesive for PVC conduit shall be as recommended by the manufacturer of the PVC
conduit

2.2 CONDUIT HUBS

A. Conduit hubs shall be insulated throat, liquid-tight "copper-free" aluminum for aluminum conduit
and zinc plated steel or malleable iron for rigid galvanized steel conduit, grounding type with
ground lug/screw on the lock nut.

B. Conduit hubs shall be Myers Type STAG or STG Scru-Tite or approved equal.

2.3 CONDUIT BODIES

A. Conduit bodies shall be provided as required or where indicated on the Drawings and shall be hot-
dipped galvanized malleable iron with galvanized steel gasketed covers or cast, "copper-free"
aluminum having threaded hubs and stainless steel or "copper-free" aluminum, neoprene gasketed
covers fastened with stainless steel screws, rain-tight, suitable for wet locations, Crouse-Hinds,
Appleton or 0-Z Gedney Form 35, Form 8, Mark 9, or Mogul. Die-cast aluminum types are not
acceptable.

B. Conduit body cover screws shall thread directly into the conduit body. Conduit body covers with
wedge-clamp type covers are not acceptable.

C. Conduit body hub configuration shall be as required based on conduit routing for the cover to be
readily accessible for easy removal.

D. Conduit bodies enclosing size 6 AWG or smaller conductors shall have a cross-sectional area not
less than twice the cross-sectional area of the largest conduit to which the conduit body is attached.

CONDUIT FOR ELECTRICAL SYSTEMS 260533.13- 3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

E. Only those conduit bodies that are durably and legibly marked by the manufacturer with their cubic
inch capacity shall be permitted to contain splices, taps, or devices. The maximum number of
conductors shall be computed in accordance with NEC Article 314-16(C).

F. LB Conduit Body for Fiber Optic Cable: Die-cast aluminum LB type conduit body with gray
powder coat paint finish and gasketed cover with stainless-steel screws. ANSI/TIA/EIA 568,
NECA/FOA 301-2009 and BICSI TDMM, 13th Edition compliant for minimum bending radii for
fiber optic cable. SmartLB by Madison Electric Products or Engineer approved equal.

2.4 CONDUIT MOUNTING CLAMPS

A. Conduit mounting clamps for securing conduits inside buildings shall be galvanized steel one-hole,
two-hole or H-Type (mini's). Conduit mounting clamps used outdoors shall be Type 304 stainless
steel.

B. Conduit mounting clamps for securing rigid metal conduits to concrete or masonry surfaces inside
buildings shall be one piece "copper-free" aluminum or zinc plated malleable iron one hole type,
Crouse-Hinds Cat. No. 5XX or approved equal with Crouse-Hinds Cat. No. CBX or approved equal
"copper-free" aluminum or zinc plated malleable iron clamp backs/spacers.

C. Conduit mounting clamps for mounting conduits to channel supports shall be electro-plated zinc,
hot-dipped galvanized steel after fabrication per ASTM Al23 with minimum coating thickness of
2.5 mils, or Type 304 stainless steel to match channel support material, B-Line B2000 Series or
approved equal.

2.5 FIRE-STOPPING MATERIALS

A. The following fire-resistant penetration sealing materials are approved:

1. 3M Caulk CP 25
2. 3M Wrap/Strip FS-195
3. Damming materials- 3M Composite Sheet CS-195
4. SpecSeal Series 100 sealant
5. Rector Seal Corporation, Metacaulk 835 fire stopping sealant
6. Dow Corning 3-6548 silicone RTV foam
7. General Electric GE RTV850 or GE RTV6428
8. Chase Technology Corporation CTC PR-855 fire-resistant silicone foam

2.6 INTUMESCENT SILICONE SEALANT

A. Intumescent silicone sealant shall meet UL Water Leakage Test- Class 1 requirements and shall
be re-enterable and repairable; 3M Fire Barrier Water Tight Silicone Sealant 3000WT or Engineer
approved equal.

B. Fire barrier packing material for use with 3M UL listed 3000WT intumescent silicone sealant
shall be 3M Fire Barrier Packing Material PM4 or Engineer approved equal.

2. 7 CONDUIT PULL STRING

A. Conduit pull string shall be Greenlee or equal with a minimum of 240 lbs. tensile strength, and
shall be rot and mildew resistant. Pull string shall have permanently printed sequential
measurements at one-foot increments.

CONDUIT FOR ELECTRICAL SYSTEMS 260533.13 - 4


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

2.8 PROTECTIVE COATING FOR DIRECT BURIED METAL CONDUIT

A. Protective coating for direct buried metallic conduit shall be Kop-Coat, Inc. Bitumastic No. 50 or
two coats of 3M Scotchrap pipe primer over wrapped in accordance with the manufacturer's
written instructions with 3M No. 51, 20 mil thick tape.

2.9 UNDERGROUND CONDUIT WARNING TAPE

A. Warning tape shall be fabricated from polyethylene film, and shall be 6 inches wide and not less
than 3.5 mils thick.

B. Warning tape for all directly buried electrical conduit shall be high visibility red in color and
imprinted at frequent intervals with black letters having the following wording:

CAUTION BURlED ELECTRIC LINE BELOW

C. Warning tape for all directly buried fiber optic conduit shall be high visibility orange in color and
imprinted at frequent intervals with black letters having the following wording:

CAUTION BURlED FIBER OPTIC LINE BELOW

D. Warning tapes shall be Terra-Tape "Extra Stretch" manufactured by Reef Industries, Inc., or
approved equal, by EMED Co., Inc., Seton, W. H. Brady Co., or Allen Systems, Inc.

2.10 CONDUIT/DUCT PLUGS

A. Plugs for sealing empty duct bank conduits shall be compressible natural rubber with stainless
steel plate on both sides with stainless steel bolt and stainless-steel wing nut or hex nut for
compressing the rubber plug between the two stainless steel plates to secure it inside the conduit
or duct or all plastic/rubber with no metal parts.

B. Conduit/duct plugs shall beT-Cone Plug by ETCO Specialty Products or Blank Duct Plug by
Calam or approved equal by Osbourne Associates, Inc.

PART 3- EXECUTION

3.1 INSTALLATION

A. CONDUIT

1. Verify routing and termination locations of conduit runs prior to rough-in.


2. Conduit routing shown on Drawings is approximate. Route as required to complete wiring.
3. Design, layout, and detail conduit runs to permit installation.
4. Coordinate conduit routing with the Construction Representative to avoid equipment
operational and maintenance interferences and to permit easy removal of all conduit body
and box covers.
5. Conduit or fittings having any type of defects shall not be used in the work.
6. Exposed conduit shall be run perpendicular or parallel to building walls. Where more than
one conduit in a bank of exposed conduit changes direction, all bends shall be concentric.
7. Conduits shall be continuous from outlet to outlet, from outlet to junction or pull boxes,
from source panel to equipment, and shall be terminated to all boxes and enclosures in such
a manner that the conduit system is mechanically and electrically continuous throughout
the system.

CONDUIT FOR ELECTRICAL SYSTEMS 260533.13 - 5


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

8. The Contractor shall furnish and install NEC sized pull boxes or conduit bodies wherever
necessary in order that a run of conduit between conductor/cable pulling points does not
contain more than the equivalent of four quarter (90 degree) bends (360 degrees total).
9. Conduit bends shall not be less than the standard radius, unless otherwise indicated.
10. A minimum clearance of nine inches (9") shall be maintained between all conduits and
pipes carrying steam, hot liquids, or hot gases, except at points of cross over, in which case
the clearance may be reduced to six inches (6"). Any exceptions to this shall be presented
to the Engineer for approval on an individual case by case basis.
11. Maintain adequate clearance qetween conduit and piping, allowing for the maintenance of
insulation and outer protective covering on piping.
12. Couplings for conduits in a group shall be staggered at least six (6) inches.
13. Conduit shall not be routed along floors.
14. Conduits shall be concealed in finished spaces and exposed in unfinished spaces.
15. In unfinished spaces, arrange conduit to maintain minimum 7'-6" headroom above floors,
unless otherwise approved by the Construction Representative.
16. All rigid metal conduit, threaded joints and couplings shall be made up wrench tight with
at least five full threads engaged. The use of running threads at conduit couplings and
terminations is prohibited. All cut ends of conduits shall be reamed to remove rough edges
and shall be free of burrs and sharp edges. An approved aluminum lubricant shall be used
with rigid aluminum conduit.
17. Coat all field cut threads, scars, or wrench abrasions in rigid galvanized steel conduit with
an approved organic zinc rich primer equivalent to Koppers' "Organic Zinc."
18. Conduit shall be supported on approved types of steel brackets, channels, ceiling trapeze,
pipe straps or hangers secured by means of toggle bolts, hollow wall fasteners or through
wall bolt fasteners on hollow masonry or clay tile blocks; or expansion anchors in concrete
or brick; or machine screws on metal surfaces; or wood screws on wood construction. Nails
or powder-actuated anchors shall not be used as a means of fastening. Perforated flat steel
straps or wire shall not be used for supporting conduit. All conduit shall be properly
supported in accordance with Section 260529 - Hangers and Supports for Electrical
Equipment in order to deter any possible vibration, noise or chatter.
19. Conduit shall be supported from building structures. Do not use piping, ductwork, other
raceways or equipment for supporting conduits. Suppoti all conduit runs at a minimum of
every 10 feet and within 3 feet of all terminations.
20. Where possible, group conduits on U-channel conduit racks.
21. Utilize U-channel suppotis and associated fittings and hardware for conduit suppoti in
accordance with Section 260529- Hangers and Supports for Electrical Equipment.
22. Terminate rigid metal conduits at all NEMA Type 1 junction and pull boxes and equipment
enclosures inside buildings with a minimum of two (2) locknuts, one inside and one outside
the enclosure, and a steel or malleable iron insulated throat, grounding bushing having a
solderless lug and a copper bonding jumper, sized in accordance with NEC Atiicle 250, to
connect the conduit to the equipment grounding bus bar located inside the enclosure.
Provide a grounding lug where the enclosure does not contain an equipment grounding bus
bar.
23. Provide insulated throat, liquid tight, grounding type conduit hubs to terminate rigid metal
conduits at all NEMA Type 3, 3R, 4, 4X, 12 and 13 enclosures without integral cast
threaded hubs. Provide a copper bonding jumper, sized in accordance with NEC Article
250, to connect the conduit hub locknut to the equipment grounding bus bar located inside
the enclosure. Provide a grounding lug where the enclosure does not contain an equipment
grounding bus bar.
24. Grounding and bonding of conduit shall be in accordance with Section 260526- Grounding
and Bonding for Electrical Systems.
25. Identify all conduit runs; both new conduit and existing that is reused, in accordance with
Section 260553 -Identification for Electrical Systems.
CONDUIT FOR ELECTRICAL SYSTEMS 260533.13 - 6
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02

26. Prior to installing any cables in any existing conduit that is to be reused, demonstrate to the
Construction Representative that the conduit is clear of obstructions by pulling a mandrel
1/2-inch smaller than the nominal size of the conduit through the entire length of the
conduit.

B. CONDUIT BODIES

1. Conduit bodies shall be sized for the conductor fill of the conduits to which it is connected.
Use Mogul type conduit bodies if/as required.
2. Conduit body sizing shall be based on the maximum number of conductors permitted
accordance with NEC Article 314-16(C).
3. Conduit bodies enclosing size 6 AWG or smaller conductors shall have a cross-sectional area
not less than twice the cross-sectional area of the largest conduit to which the conduit body is
attached.
4. Utilize SmartLB telecommunication type LB conduit body with fiber optic conduits.
5. Conduit bodies shall be supported in a rigid and secure manner.

C. CONDUIT MOUNTING CLAMPS

1. Conduit shall not be mounted in direct contact with any concrete or masonry wall or ceiling.
Utilize U-channel supports or clamp backs/spacers to hold conduits a minimum of 3/16
inch away from concrete or masonry surfaces. Clamp backs/spacers shall be stackable to
allow the conduit to be spaced further away from the mounting surface as required.

D. CONDUIT OPENINGS

1. Provide conduit openings in floors, walls, and ceilings as required to install conduit runs.
Openings shall be kept to a minimum, as small as possible, and installed in a neat manner.
All damage to existing surrounding surfaces when installing openings shall be repaired to
original condition.
2. Locations of all openings shall be approved by the Construction Representative before
beginning work.
3. Core drill all openings in existing concrete or masonry surfaces using a dustless method.
4. After installation of conduit, openings in concrete or masonry shall be formed, grouted,
and caulked to provide a moisture and fire barrier that is equivalent to the fire rating of the
wall or floor.
5. All openings through which a conduit passes in walls and floors shall be properly sealed
after the conduit is installed to prevent transmission or leakage of liquids, dust, fire, smoke,
or sound. Openings in non-fire rated concrete or masonry construction through which
conduit passes shall be sealed, after the conduit is installed, with material similar to that
which surrounds the opening. Openings in fire-rated construction through which conduit
passes shall be sealed, after the conduit is installed, with an APPROVED fire-resistant
penetration seal. All fire-resistant penetration seals shall be installed in accordance with
the manufacturer's instructions.
6. Exterior metal wall panel openings shall be cut or punched. After installation of conduit,
the opening shall be flashed and caulked to provide a weather-tight seal. Fire barrier caulk
shall be used if the exterior wall is designated as a fire wall.

E. UNDERGROUND CONDUIT

1. Unless otherwise indicated, all underground conduit located outside building areas shall have
a minimum slope of 1/2% toward the drainage point, or as shown on the Drawings, and shall
be a minimum of three feet (3'-0") below finish grade to the top of the conduit.

CONDUIT FOR ELECTRICAL SYSTEMS 260533.13 - 7


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

2. Trenching, excavation, and backfilling for all underground conduit shall be accomplished
as hereinafter specified or shown on the Drawings.
3. Trench widths shall be kept to a minimum and bottoms shall be graded to a uniform slope.
The bottom of the trench shall be kept free of water. If required to protect the excavation
or personnel, shoring and sheeting of a design and materials suitable to maintain the trench
in a safe and workable condition shall be provided. Adequate barricades shall be installed
around excavations to protect workmen and the public during the construction. Provide
temporary supports for all underground utilities crossing an excavation.
4. Conduit in trenches shall be supported throughout the entire length on solid earth.
5. All metallic conduit directly buried in earth shall be completely coated with two 15- to 18-
mil thick coats of an approved bitumastic coal tar protective coating or two coats of 3M
Scotchrap pipe primer overwrapped in accordance with the manufacturer's written
instructions with 3M No. 51 tape before the conduit trench is backfilled. Rigid metal
conduit shall extend 18-inches below grade before converting to Schedule 40 PVC conduit.
6. Backfill for trenches containing direct buried conduit shall be in accordance with Section
310000- Earthwork. Any settlement shall be corrected by refilling and retamping. No
puddling will be permitted.
7. Underground conduits shall be at least 12 inches away from gas, water or other pipe lines.
8. Conduits shall have long swept elbows.

a. Size 2" and below- 24" minimum radius


b. Size 2-1/2" and above- 36" minimum radius

9. Couplings for conduits in a common trench shall be staggered at least 6 inches. All joints
shall have watertight seals.
10. All PVC conduit couplings, connectors and fittings shall be properly glued to the conduit,
pushing the conduit all the way in to the stop on the coupling, and using the adhesive
recommended by the manufacturer of the PVC conduit.

F. UNDERGROUND CONDUIT WARNING TAPE

1. Unless otherwise indicated, the location of all directly buried conduits shall be marked by
burying one a warning tape below grade in the backfill. The warning tape shall be placed
18 inches above the top of the conduit(s) and shall be parallel along the full length of the
run. Where the top of the conduit(s) is less than three feet (3'-0") below finish grade the
warning tape shall be placed 12 inches above the top of the conduit(s).
2. Contractor shall exercise care to ensure that the warning tape is properly located.

G. CONDUIT/DUCT PLUGS

1. Install conduit/duct plug in all spare (empty) conduits/ducts as indicated on the Drawings
to prevent vermin from entering electrical equipment through the conduit.
2. Size plugs based on the trade size of the conduit/duct to be sealed.
3. Tie-off pull tape/string to eye on duct plug before inserting into conduit/duct to be sealed.
4. Install plugs in accordance with the manufacturer's directions. Plugs shall be inserted in
the conduit or duct such that they fit flush with the end of the raceway. Tighten down the
nut to create a water-tight seal but do not over-tighten.

END OF SECTION 260533.13

CONDUIT FOR ELECTRICAL SYSTEMS 260533.13 - 8


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
SECTION 260533.16- BOXES FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall furnish and install all electrical boxes as specified herein and as shown on
the Drawings.

1.3 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

B. Section 260519 - Low-Voltage Electrical Power Conductors and Cables

c. Section 260526 - Grounding and Bonding for Electrical Systems

D. Section 260529- Hangers and Supports for Electrical Equipment

E. Section 260533.13- Conduit for Electrical Systems

F. Section 260553- Identification for Electrical Systems

1.4 SUBMITTALS

A. Manufacturer's product data sheets shall be submitted for the following items:

1. Outlet and non-dimensioned junction and pull boxes and device boxes
2. Dimensioned junction and pull boxes

PART 2 -PRODUCTS

2.1 GENERAL

A. All electrical boxes, including extension rings, plaster rings, covers and other accessories, shall be
UL Listed and Labeled.

B. All outlet, device and nondimensionedjunction and pull boxes shall be sized in accordance with the
allowable wiring fill permitted by the National Electrical Code (NEC).

C. Junction boxes and pull boxes shall be sized as per the NEC or as shown on the Drawings.

D. Outlet boxes shall be of the size and type to accommodate the structural conditions, the size and
number of raceways, conductors or cables entering, and the wiring device with which the box is
intended to be used. Install blank plates on all outlet boxes where apparatus is installed which does
not, in itself, provide a cover for the box.

E. Unless othetwise indicated, all junction or pull box covers shall be fastened with cadmium plated or
galvanized steel screws or bolts for indoor applications and stainless-steel screws or bolts for outdoor
BOXES FOR ELECTRICAL SYSTEMS 260533.16- 1
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
applications. The removable cover shall be fabricated from the same material as the box, and the
cover shall be on the largest accessible side of the box unless otherwise indicated. The cover of the
box shall be designed for quick removal.

F. Boxes shall be as manufactured by Appleton Electric Company, Eaton Crouse-Hinds, Steel City,
Raco, Killark Electric Manufacturing Company, 0-Z/Gedney Company, Hoffinan Engineering
Company, Wiegmann or approved equal.

2.2 BOXES FOR NONHAZARDOUS AREAS

A. Nondimensioned junction and pull boxes and device boxes located indoors shall be hot-dipped
galvanized drawn steel, 4-inch square, 4-11116-inch square or octagon, 1-1/2 inch minimum depth,
NEMA Type I with plaster ring, if/as required. Sectional boxes are not acceptable.

B. Nondimensioned junction boxes located outdoors shall be cast, cadmium or zinc plated malleable
iron or "copper-free" aluminum, having threaded hubs and neoprene gasketed covers fastened
with four ( 4) stainless steel screws, NEMA Type 4, Crouse-Hinds Type GRFX, or GS, or approved
equal, or Crouse-Hinds, Appleton Electric or Killark 2-1/8 inch deep Type FD, or approved equal.

C. Dimensioned junction and pull boxes located indoors shall be painted steel, galvanized steel or code
gauge sheet aluminum, NEMA Type I having removable neoprene gasketed covers fastened with
cadmium plated or galvanized steel screws, and continuously welded seams (ground smooth) with no
holes or knockouts.

D. Dimensioned junction and pull boxes located outdoors, above grade shall be Type 304 stainless steel,
NEMA Type 4X having hinged, neoprene gasketed covers fastened with 304 stainless steel screws,
and continuously welded seams (ground smooth) with no holes or knockouts.

E. Pull and junction boxes shall be sized in accordance with NEC Article 314-16 or 314-28 as a
minimum. Larger boxes may be provided.

F. Provide hinged cover enclosures for any box larger than 12 inches in any dimension.

G. Provide grounded metallic barriers in dimensioned junction and pull boxes as required to isolate
power circuits from other types of circuits. Barriers shall be designed so as not to separate the phases
of a power circuit. Barriers shall be constructed of the same material as the box in which they are
installed.

H. Inner Back Panels: Provide white painted steel, galvanized steel, code gauge sheet aluminum or
Type 304 stainless steel inner back panel, to match box construction, inside all boxes in which
terminal blocks or control devices are located.

PART 3 - EXECUTION

3.1 INSTALLATION

A. BOXES, GENERAL

1. Locate and install boxes to allow access. Coordinate with other trades to ensure boxes are
not made inaccessible by equipment, duct work or piping installation.
2. Locate and install to maintain headroom and to present a neat appearance.

BOXES FOR ELECTRICAL SYSTEMS 260533.16- 2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
3. Special care shall be taken to set all boxes square and true with the building finish. As far
as possible, all boxes shall be secured to the building structure or steel, using adjustable
supports where necessary.
4. Outlet boxes in unfinished areas shall be surface (exposed) mounted to columns or walls,
unless otherwise indicated.
5. All boxes shall be rigidly mounted.
6. Securely fasten boxes to building structure, independent of the conduit, except for splice
boxes that are connected to two metal conduits, both supported within 12 inches of the box.
7. All conduits entering sheet metal junction or pull boxes shall be through holes properly cut
with a punch and die. Cast boxes shall be provided with threaded conduit bosses or hubs
of proper size and externally located cast feet for mounting.
8. All open conduit knockouts, holes or hubs not used shall be properly plugged with suitable
blanking devices of the same material as the box that maintain the NEMA rating of the
box. Utilize stainless steel blanking devices for stainless steel boxes. Utilize NEMA 12
rated hole seals devices to seal all open holes in the top of all panel boards, switchboards,
switchgear and dimensioned junction and pull boxes located indoors.
9. Junction and pull boxes shall be furnished and installed where indicated on the Drawings,
required by code, and wherever else such a box may be deemed necessary to facilitate the
pulling or splicing of wires or cables. In general, junction or pull boxes shall be installed
to limit conduit runs to 125 feet and conduit bends to a maximum total of360 degrees. The
Contractor shall furnish and install properly sized pull boxes wherever necessary in order
that a run of conduit between outlet and outlet, between fitting and fitting, or between outlet
and fitting shall not contain more than the equivalent of four quarter (90 degree) bends
(360 degrees total). Additional pull boxes may be needed to facilitate wire pulling. All
boxes shall be installed in locations that will be accessible after completion of the
construction.
10. Dimensioned pull and junction boxes shall be sized in accordance with NEC Article 314-28
unless a larger size box is indicated on the Drawings.
11. Location of junction and pull boxes shall be approved before installation. Where
necessary, conduits may be rerouted with the approval of the Construction Representative.
12. Rigid metal conduits terminating in all NEMA Type 3, 3R, 4, 4X, 12 or 13 boxes and
enclosures, without integral cast threaded hubs shall be terminated in insulated throat,
grounding type, liquid tight, rigid conduit hubs. Conduit hubs shall be provided in
accordance with Section 260533.13 -Conduit for Electrical Systems.
13. Provide a grounding type conduit bushing with solderless lug and copper bonding jumper
sized in accordance with NEC Article 250 for all conduits terminating in NEMA Type 1
boxes and enclosures in accordance with Section 260526 - Grounding and Bonding for
Electrical Systems.

3.2 CIRCUIT IDENTIFICATION

A. Junction, pull, outlet, and device boxes shall be identified in accordance with the requirements of
Section 260553 - Identification for Electrical Systems.

B. Cover plates for all junction and pull boxes shall be marked on the inside surface of the cover
plate in finished areas or on the outside surface of the cover in unfinished areas in accordance
with Section 260553 -Identification for Electrical Systems.

C. All conductors in a junction or pull box shall be identified in accordance with Section 260553 -
Identification for Electrical Systems.

END OF SECTION 260533.16

BOXES FOR ELECTRICAL SYSTEMS 260533.16- 3


THIS PAGE INTENTIONALLY LEFT BLANK
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

SECTION 260553- IDENTIFICATION FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall furnish and install electrical identification for electrical equipment,
conductors, cables, and boxes as specified herein and as shown on the Drawings.

1.3 RELATED SECTIONS

A. Section 260500 - Common Work Results for Electrical

B. Section 260519 - Low-Voltage Electrical Power Conductors & Cables

c. Section 260533.13- Conduit for Electrical Systems

D. Section 260533.16- Boxes for Electrical Systems

E. Section 262726- Wiring Devices

F. Section 263236- Resistive Load Banks

1.4 SUBMITTALS

A. Submit electrical identification data as follows:

1. Nameplate type product data


2. Nameplate engraving schedule
3. Wire and cable identification label product data
4. Conduit marker product data

PART 2- PRODUCTS

2.1 NAMEPLATES

A. Nameplates shall be three-layer laminated plastic with engraved black characters on a white
background or engraved white characters on a red background as indicated on the Drawings.

B. Nameplates that will be located outdoors must be constructed from material that is waterproof and
UV resistant.

C. Nameplate engraving shall be as follows:

1. Lettering font shall be Gothic.

2. Nameplate character sizes shall be:

a. 1/2-inch high- Switchgear, utility meter enclosure and resistive load-bank

IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553- 1


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
b. 3/8-inch high - Control panels, terminal boxes, dimensioned junction boxes and
dimensioned pull boxes.
c. 1/8-ingh high- Local control stations

3. Lettering shall be centered on nameplate.


4. Nameplates shall have a m<L'<imum of forty (40) characters per line with a maximum of four
(4) lines.
5. Wording on nameplate shall include the equipment designation as indicated on the Drawings.
6. In addition, control panels and terminal boxes shall also have an engraved nameplate indicating
the source panel it is served from and the service voltage and number of phases/wires such as:
"208Y/120V-3PH-4W".
7. Engraving designations shall be approved by the Engineer.

D. Special nameplates shall be as indicated on the Drawings.

2.2 CONDUIT MARKERS

A. Conduit markers shall be vinyl "peel and stick" type with black characters on an orange
background:

1. Conduits 1-1/4" and smaller .................................................. 112" characters


2. Conduits 1-112" and larger ......................................................... 1" characters

B. Markers shall identify voltage and functional use ofthe conduit, such as "120/208 VOLT", "120
VOLT", "CONTROL", "FIBER OPTIC", etc.

2.3 WIRE LABELS AND CABLE MARKERS

A. Wire labels for No. 4/0 AWG and smaller wires shall be vinyl film, self-laminating, adhesive
wraparound type; W. H. Brady Co. B-292, Thomas & Betts WSL Series or approved equal.

B. Cable markers for cables and wire labels for all conductors 250 KCM and larger shall be polyester
film, non-adhesive, plate type designed for cable tie banding parallel to the cable/conductor.

c. Wire and cable identification numbers shall be printer generated or typewritten on the labels and
markers.

D. Character size for cable identification numbers shall be a minimum of 118-inch high.

E. Markers labels, number generation method, and attachment methods shall be subject to the approval
of the Engineer.

2.4 COLOR CODE TAPE

A. Each conductor, except control and signal conductors, shall be color coded with 3M No. 35 tape,
3/4" width, or colored insulation.

1. Color coding for 600-volt conductors shall be:

120/240V 1 Phase 120/208V 3 Phase 277 /480V 3 Phase


Phase A Black Phase A Black Phase A Brown
PhaseB Red Phase BRed Phase B Orange
Neutral White Phase C Blue Phase C Yellow

IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553-2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
Equipment Ground Green Neutral White Neutral Gray
Equipment Ground Green Equipment Ground Green

2. Color coding for 12,470-volt cables shall be:

12,470V 3 Phase
Phase A Red
Phase B Yell ow
Phase C Blue
Equipment Ground Green

B. Wiring to contacts powered from an external source shall be yellow.

C. Conductors for direct current (DC) circuits shall be color coded red for positive(+) conductor and
black for negative(-) conductor.

2.5 PANELBOARD CIRCUIT DIRECTORIES

A. Each panelboard shall have a framed circuit directory card with a clear plastic covering mounted on
the inside ofthe door.

B. The directory card shall provide a space at least 1/4-inch high by 3 inches long, or the equivalent, for
each circuit.

C. The directory card shall be typed to identify the load fed by each circuit for compliance with NEC
408.4.

PART 3 -EXECUTION

3.1 GENERAL

A. Degrease and clean surfaces to receive nameplates, markers, labels and color code tape.

3.2 NAMEPLATES

A. Nameplates shall be provided for each switchgear circuit breaker, panelboard, control panel, terminal
box, dimensioned pull box, dimensioned junction box, and local control station.

B. Nameplates shall be secured with an approved adhesive such as Goodyear "Pliobond" glue or
stainless steel machine screws in tapped holes. Self-tapping screws or sheet metal screws shall not
be used.

3.3 CONDUIT MARKERS

A. Attach a conduit identification marker to each conduit at all termination points and at 20' intervals
along the entire length of the conduit.

B. Secure markers parallel to conduit in a readily visible location.

3.4 WIRE LABELS AND CABLE MARKERS

A. Branch circuits, control and signal wires and cables shall be identified.

IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553-3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
1. Attach a wire identification label to each conductor of a circuit cable group at each termination
point.
2. Attach a cable identification marker to each circuit cable group at all termination entry points.

B. Wire labels and cable markers shall identify each conductor and cable with the circuit number.
Identify with branch circuit or feeder number for power circuits and with control wire or cable
number as indicated on schematic and interconnection diagrams and equipment shop drawings
for control wiring.

C. Cable markers for cables and wire labels for all conductors 250 KCM and larger shall be secured
with heavy duty plastic cable ties. Cut excess tie material off flush with tie clasp. Do not leave sharp
edges.

3.5 COLOR CODE TAPE

A. Code all wire and cable not available color coded from manufacturer by application of electrical
plastic tape in colors specified. Apply tape in uniform manner circling wire or cable. Half-lap tape
for length of cable as required by Local Authorities or NEC but not less than five (5) full wraps.

3.6 JUNCTION, PULL, OUTLET AND DEVICE BOX IDENTIFICATION

A. Cover plates for all non-dimensioned junction and pull boxes shall be marked on the outside surface
of the cover plate with the voltage, panel and circuit number of the branch circuit(s) contained inside
the box. Marking shall be with printer generated "peel and stick" labels.

B. Nameplates shall be provided on the external surface of the cover of all dimensioned junction and
pull boxes which shall identify the source voltage of the circuits inside the box as well as the location
of the AC power source(s) for these circuits.

C. Cover plates for all receptacles shall be marked on the outside sutface of the cover plate with panel
and circuit number of the branch circuit serving the device. Marking shall be with printer generated
"peel and stick" labels.

3.7 P ANELBOARD CIRCUIT DIRECTORIES

A. Provide new "updated" directoty cards for existing panelboards in which circuits have been
rearranged, added or deleted.

B. The directory card shall be typewritten or printer generated to identify the load served by each circuit.

C. Trace out unidentified circuits in existing panels and indicate load served on new circuit directory
for compliance with NEC 408.4.

END OF SECTION 260553

IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553-4


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02

SECTION 260583- WIRING CONNECTIONS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall furnish and install all wiring connectors and terminations for 600-volt
building wire, 600-volt multi-conductor control cable, and 600-volt shielded instmmentation
cable as specified herein and as shown on the Drawings.

1.3 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

B. Section 260519 -Low-Voltage Electrical Conductors and Cables

c. Section 260526 - Grounding and Bonding for Electrical Systems

D. Section 260533.16- Boxes for Electrical Systems

E. Section 263236- Resistive Load Banks

1.4 SUBMITTALS

A. Manufacturer's product data sheets shall be submitted for each of the following items:

1. 600-volt connectors
2. 600-volt terminations
3. CAT 5e copper Ethernet connectors
4. Optical-fiber connectors

PART 2 - PRODUCTS

2.1 600-VOLT CONNECTIONS AND TERMINATIONS

A. Pressure Type Terminal and Splice Connectors: Solderless, color coded, nylon insulated, pressure
type, UL Listed 105°C, 600-volt, sized for the cable to be terminated or spliced, tin-plated copper,
with crimping tool coded to the connectors with stops to prevent over-crimping and means to prevent
under-crimping; 3M Scotchlok or approved equal.

B. Spring Type Splice Connectors: Solderless, color coded, flame retardant polypropylene and
thermoplastic elastomer or flame retardant nylon, spin-on wings, spring steel inner spring with
corrosion resistant coating, UL Listed 105°C, 600-volt, sized for splicing two or more conductors
up to size #6 AWG; 3M Performance Plus or approved equal.

C. Control Wiring Connections and Termination: Control wiring connectors shall be vinyl or nylon
pre-insulated spade lugs to match stud or screw size with insulation grip sleeve flared to prevent
turned-back strands and crimping tool to crimp wire barrel and insulation sleeve.

WIRING CONNECTIONS 260583- 1


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
1. Where attachment is to a terminal block screw or stud, install using pre-insulated spade type
connectors.

D. Conductor to conductor splices shall be made using wire nuts or wing nuts only wrapped with a
minimum of three (3) half-lapped layers of jacketing tape specified. No crimp type connectors shall
be used for these types of splices.

E. Power Connections and Terminations:

1. Size 12 A WG through 2/0 A WG connectors shall be non-insulated, one-hole rectangular


tongue, for copper conductors, UL Listed 90°C, 600-volt.

2. Size 3/0 A WG and larger conductors shall be non-insulated, two-hole rectangular tongue with
long barrel length to permit two (2) crimps for copper conductors, UL Listed 90°C, 600-volt.

3. Butt splices shall only be made where specifically indicated on the Drawings or where pre-
approved by the Engineer.

a. Size 12 A WG through 2/0 A WG connectors, for splicing like sized conductors, shall
be non-insulated, standard length barrel, for copper conductors, UL Listed 90°C,
600-volt, compression type.
b. Size 3/0 A WG and larger connectors, for splicing like sized conductors, shall be
non-insulated, long barrel length to permit two (2) crimps on each conductor, for
copper conductors, UL Listed 90°C, 600-volt.
c. Size 12 AWG through 3/0 AWG connectors, for splicing different sized conductors,
shall be Thomas & Betts C-Tap compression connections or approved equal.
Overwrap connectors with a minimum of three (3) half-lapped layers of Thomas &
Betts Shrink-Kon TBFT201-36 self-fusing insulation tape.

F. Power Termination Insulation:

1. Insulating Putty: 3M Scotchfil electrical insulating putty or approved equal by Thomas &
Betts
2. Insulating Tape: 3M Scotch 23 or Thomas & Betts Shrink-Kon TBF201-36 self-fusing
insulating tape
3. Jacketing Tape: 3M Scotch 33+ jacketing tape
4. Provide pre-engineered insulating kits by 3M or Thomas & Betts where appropriate.

G. CAT 5e Copper Ethernet Cable Connectors: RJ-45, 8-pin compression type with locking tab
meeting the requirements of ANSI/TIA-568-C.2, field installable connector compatible with the
cable onto which installed.

H. Optical-Fiber Cable Connectors: Type SC, multi-mode optical-fiber mechanical crimp type
connector meeting the requirements of ANSI/TIA-568-C.3, field installable, compatible with the
Coming MM62.5 multimode optical-fiber cable onto which installed.

1. Connectors shall provide a strain relief mechanism for installation on a single-fiber cable
that contains strength elements. The fiber within the body of the connector shall be isolated
mechanically from cable tension, bending and twisting.
2. Connectors shall have a locking feature to the coupler and assure non-optical disconnect.
3. Connectors shall incorporate pre-radiused zirconia ceramic ferrules to ensure consistent
end face geometry and high-performance connector mating.

WIRING CONNECTIONS 260583-2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
PART 3 -EXECUTION

3.1 GENERAL

A. Conductors shall be continuous from source to destination without splices or taps in conduit runs,
except where indicated on the Drawings to compensate for voltage drop or where required to
prevent excessive pulling tension or sidewall pressure on wire or cable. Submit all proposed
splice locations to the Engineer for approval prior to pulling wire and cable. Where permitted,
splices shall be mechanically strong and have an insulation value equal to the wire or cable being
spliced. All splices and taps shall be contained within NEC sized junction boxes meeting the
requirements of Section 260533.16- Boxes for Electrical Systems.

3.2 CONTROL WIRING CONNECTIONS AND TERMINATIONS

A. Thoroughly clean wires before installing connectors.

B. Tape back spare conductors with 3M Scotch 33+ jacketing tape.

c. Where control cable terminations are split across terminal blocks or are otherwise separated by
more than 12 inches distance, identify each conductor group with the circuit number as specified
in Section 260553- Identification for Electrical Systems.

D. Conductor to conductor splices shall be made using wire nuts or wing nuts. No crimp type connectors
shall be used for these types of splices.

1. Apply a minimum of three (3) half-lapped layers of jacketing tape over each and every
spring type (wire nut) splice connection.

3.3 600-VOLT CONNECTIONS AND TERMINATIONS

A. Cut conductors to proper length such that the barrel or inner metal spring of the connector makes
full contact with the bare conductor and not the insulation and the plastic skirt of the connector
full covers the bare conductor.

1. Conductor to conductor splices for size 10 A WG or smaller conductors shall be made using
wire nuts or wing nuts. No crimp type connectors shall be used for these types of splices.
2. Apply a minimum of three (3) half-lapped layers of jacketing tape over each and every
spring type (wire nut) splice connection.

B. Power Connections and Terminations:

1. Cover all exposed live parts such as connectors, bolts, nuts, and bus bar with insulating
material to equal or exceed insulation of the connected cable.
2. At equipment with cable leads such as motors, install compression type terminal connectors
on equipment leads and power circuit leads, bolt together, and insulate with pre-engineered
motor terminal kits or as specified herein.
3. At equipment with integral set screw or clamp type connectors such as terminal blocks and
molded case circuit breakers, strip conductor insulation as required to clear contact.
surfaces, and torque connector in accordance with manufacturer's recommendations.

WIRING CONNECTIONS 260583-3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
3.4 600-VOLT POWER TERMINATION INSULATION

A. Insulate with pre-engineered kits where appropriate, or with a minimum of three (3) half-lapped
layers of insulating tape covered with three (3) half-lapped layers of jacketing tape. Where major
surface irregularities exist, fill voids with insulating putty prior to application of insulating tape.

B. Provide electrical insulating putty to fill major irregularities and voids in termination prior to
taping.

C. Apply self-fusing insulating tape directly to the conductors or over the electrical insulation putty.

D. Apply jacketing tape over the insulating tape to provide an outer covering for the cable
termination.

3.5 CAT 5e COPPER ETHERNET CABLE TERMINATIONS

A. Utilize the connector manufacturer's recommended installation tool(s) for cutting, stripping and
crimping cable and inserting into the connector.

3.6 OPTICAL-FIBER CABLE TERMINATIONS

A. Optical-Fiber Connector and Adapter Cleaning:

1. Prior to and during installation of fiber optic connectors, perform appropriate cleaning to
ensure that any contaminant particulates larger than 0.06 micron in size are removed.
2. Do not use canned air products when cleaning fiber optic connector surfaces.
3. A fiberscope shall be used to view and inspect the connector end face.
4. Utilize dry cleaning or wet cleaning methods per the written instructions of the connector
manufacturer.

B. Follow the connector manufacturer's written instructions for field termination of optical-fiber
cable and utilize the manufacturer's recommended consumable kit and tool kit for the adapter.

C. Polarity, where required, shall be maintained to prohibit the reversal of transmit and receive
signals. The transmit fiber shall be the fiber with markings on the sheath; the receive fiber has
no markings on the sheath. Provide contrasting colors and labels to aid in polarity identification.

3.7 FIELD QUALITY CONTROL

A. General:

1. Testing shall be performed in the presence of Construction Representative. Contractor


must provide 48 hours' notice prior to conducting tests.
2. Prepare a test report upon completion of testing activities. Report format shall include the
following information:

a. Summary of test results


b. Test equipment summary (model number, accuracy, calibration date)
c. Test personnel names and sign-offs
d. Completed data sheets
e. Test log and observations
f. Certificate of Compliance

B. Torque test conductor connections and terminations to manufacturer's recommended values.


WIRING CONNECTIONS 260583-4
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
C. Provide testing for 600-volt wire and cable in accordance with Section 260519 - Low-Voltage
Electrical Power Conductors and Cables in conjunction with the testing specified herein.

END OF SECTION 260583

WIRING CONNECTIONS 260583- 5


THIS PAGE INTENTIONALLY LEFT BLANK
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02

SECTION 261327- 15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract including General and Supplementary Conditions,
Bid Form, and other Division 01 Specification Sections apply to this Section.

1.2 HISTORY

A. The existing Siemens GM 15kV metal-clad dual source with automatic transfer switchgear was
commissioned in 2006 and functioned in accordance with ANSI, UL and Ameren Missouri
standards until it was modified by Siemens in 2010 to incorporate the addition of a standby
generator connection.

B. This 2010 modification incorporated Siemens SIPROTEC 7SJ64 relays with a fiber optic
communications link. These relays are not approved by Ameren Missouri. In addition, this
modification did not include any hardwired interlocks to prevent closing the generator breaker
when either of the two utility main breakers or closed thus either allowing the generator to be
motored by the utility or allowing the generator to be parallel connected to the utility without any
synchronism verification. This modification has proven to be inconsistent in operation, unreliable
and unsafe and must be corrected to comply with ANSI, UL, and Ameren Missouri standards and
"good engineering practice" for this type of system.

1.3 SCOPE

A. The Contractor shall furnish and install all equipment, materials, wiring and programming to upgrade
the automatic transfer system (ATS) controls for the existing 12.47 kV main campus metal-clad
switchgear for preferred - reserve utility supply with emergency generator backup, including field
startup, testing and commissioning for UL field evaluation certification and Ameren Missouri
acceptance as shown on the Drawings and as specified herein.

B. The Contractor shall provide all other equipment and services as required by this Specification.

1.4 RELATED SECTIONS

A. Section 260115- Preventative Maintenance for 15kV Metal-Clad Switchgear

B. Section 260500- Common Work Results for Electrical

C. Section 260505 - Selective Demolition for Electrical

D. Section 260519- Low-Voltage Electrical Conductors and Cables

E. Section 260553 -Identification for Electrical Systems

1.5 SUBMITTALS

A. The approved submittal drawings from the original Siemens 15kV metal-clad dual source with
automatic transfer switchgear, prior to the addition of the standby generator connection, will be
provided for the Contractor's reference.

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 1


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
B. The as-built version of the Siemens switchgear drawings from the project that installed the standby
generator are included in the bid documents as Drawings RE-001 through RE-045 and the AutoCAD
drawing files will be provided for each of these drawings for the Contractor's use in preparing the
revisions to these drawings required to document the modifications necessary to correctly implement
the standby generator connection with open-transition automatic transfer to backup the two utility
feeders and to make any corrections necessary to bring the switchgear automatic transfer controls into
compliance with Ameren Missouri and UL LLC requirements.

C. The Contractor shall prepare and submit to the Engineer for approval, PRIOR TO FABRICATION,
shop drawings and descriptive literature that indicate all modifications to the existing switchgear to
implement the changes indicated on the Ameren Missouri drawing markups, included as Drawings
RE-O 12A, RE-O 16A, and RE-O 17A, and bring the switchgear into compliance with UL 1008A -
Transfer Switch Equipment, Over 1000 Volts, Ameren Missouri Specification CE-10, included in
Attachment A at the end ofthis specification section, Ameren Missouri Document CO for Category 1
- Open Transition included in Attachment B at the end of this specification and all other applicable
ANSI, NEMA, ULand NFPA standards.

D. Update all existing switchgear drawings affected by the controls modifications; including but not
limited to:

1. Physical Drawings: Provide drawings showing the physical.construction and layout of all
hardware modifications to the existing switchgear, including but not limited to protective
relays, control relays, and terminal blocks.
2. One-Line Drawing: The one-line drawing shall include the main circuit breakers, revenue
metering CTs and PTs feeder circuit breakers, and the related information regarding the
"downstream" system that aids in defining the type of connection required. The one-line shall
be up-to-date and consistent with the additional information listed below.
3. Three-Line Drawing: The three-line drawing shall include proposed connections of all current
and/or potential transformers to the protective relays and revenue metering, in addition to the
primary bus connections.
4. Breaker Control Schematics

a. Provide detailed schematics of the main breaker trip and close control circuits.
These schematics shall show all protective relay functions as well as any control
functions including automatic transfer logic.
b. Provide trip and close control circuit schematics for all feeder breakers.

5. Automatic Control Schematics: Provide schematics that document the automatic transfer
control scheme. (Note: This control may or may not be completely covered on the breaker
control schematics.)
6. Protective Relaying Control Schematics: Provide schematics that document the protective
relaying scheme. (Note: This may or may not be completely covered on the breaker
schematics.)
7. Wiring diagrams
8. Interconnection diagrams
9. Circuit breaker element drawings
10. Bill ofMaterials: Provide a complete Bill of Materials of all items, listing items by quantity,
description and manufacturer's catalog number that includes relay style numbers and/or
ranges, current transformer ratio, etc.
11. Nameplate drawing
12. Descriptive literature for:

a. Potential transfmmers for generator voltage sensing including outline drawing

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
b. ATS controls components including protective relays and control relays
c. Installation details
d. Instruction Manuals

E. The Instruction Manuals shall describe installation, operation, and maintenance and shall be
complete with all wiring and schematic diagrams.

F. The Contractor shall prepare and submit to the Engineer for approval before beginning fabrication, a
complete schematic electrical diagram of all control circuitry for each breaker, all instrumentation and
the automatic transfer system; also, an electrical internal wiring diagram of the breaker, and an
· interconnecting electrical wiring diagram between each breaker and all extemal components.

G. If the Contractor recommends changes to the settings of any of the existing protective relays in the
switchgear, Contractor shall submit to the Engineer for review, all protective relay calculations and
recommended settings for each breaker. The Contractor shall have these calculations and settings
signed and sealed by a registered professional engineer in the State of Missouri. A copy of the SKM
file for the existing facility power system study will be provided for the Contractors use.

H. In addition to the number of copies of these submittals required by these specifications, provide five
(5) complete sets that will be forwarded to Ameren Missouri for review and approval prior to
fabrication of the equipment. Allow thirty (30) work days for the Ameren Missouri review.

I. After incorporation of any comments provided by Ameren Missouri, submit complete drawing
package to UL LLC for completion of the field evaluation desk review. Submit a copy of the UL
LLC desk review comments to the Engineer for review before incorporating into the switchgear
modification drawings.

J. Product data sheets for all components required for annunciation of 12.47kV campus main
switchgear status and alarm signals at remote building:

1. Ethernet peer-to-peer discrete I/0 mirrors


2. 1OOBase TX to 1OOBase FX media converter
3. Unmanaged Ethemet switch
4. 24VDC power supplies
5. Alann annunciator

K. Submit shop drawings for remote switchgear alann annunciation panel that include dimensioned
outline drawings showing front door mounted devices and internally mounted devices, wiring
diagram and complete bill of materials (BOM). Submit product data sheets for all items listed in
theBOM.

1.6 GENERAL

A. The switchgear automatic transfer control system shall be completely field acceptance tested and
approved by UL LLC and Ameren Missouri representatives.

B. All equipment and components shall be of new construction.

C. If the Contractor recommends changes to the settings of any of the existing protective relays in the
switchgear, the Contractor shall provide all calculations and recommended settings for each protective
relay, signed and sealed by a registered professional engineer in the State of Missouri, and submit these
to the Engineer for review. Engineer will forward to Ameren Missouri for review. After approval by

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
Ameren Missouri, the Contractor shall set and test each relay in accordance with the relay
manufacturer's instmctions and applicable industry standards, at the project site.

1.7 APPLICABLE STANDARDS

A. The switchgear covered by these Specifications is governed by the latest applicable ANSI, NEMA
and NFPA standards, including but not limited to:

1. ANSI/IEEE C37.04 IEEE Standard Rating Stmcture for AC High-Voltage Circuit


Breakers Rated on a Symmetrical Current Basis
2. ANSI/IEEE C37.06 Switchgear - AC High-Voltage Circuit Breakers Rated on a
Symmetrical Current Basis - Preferred Ratings and Related
Required Capabilities
3. ANSI/IEEE C37.09 IEEE Standard Test Procedure for AC High-Voltage Circuit
Breakers Rated on a Symmetrical Current Basis
4. ANSI/IEEE C37.010 IEEE Application Guide for AC High-Voltage Circuit Breakers
Rated on a Symmetrical Cunent Basis
5. ANSI/IEEE C37.011 IEEE Application Guide for Transient Recovery Voltage for A C
High-Voltage Circuit Breakers Rated on a Symmetrical Current
Basis
6. ANSI/IEEE C37.012 IEEE Application Guide for Capacitance Current Switching for,
AC High-Voltage Circuit Breakers Rated on a Symmetrical
Cunent Basis
7. ANSI/IEEE C37.11 IEEE Application Guide for Electrical Control of AC High-
Voltage Circuit Breakers Rated on a Symmetrical Cunent Basis
8. ANSI/IEEE C37.20.2 IEEE Standard for Metal-Clad and Station-Type Cubicle
Switchgear
9. ANSI/IEEE C37.55 Metal-Clad Switchgear Assemblies - Conformance Testing
Procedures
10. ANSI/IEEE C37.90 Standard for Relays and Relay Systems Associated with Electric
Power Apparatus
11. ANSI/IEEE C39.1 Requirements for Electrical Analog Indicating Instmments
12. ANSI/IEEE C57.13 IEEE Standard Requirements for Instmment Transformers
13. NEMACC1 Electrical Power Connectors for Substations
14. NEMASG-2 High Voltage Fuses
15. NEMASG-4 Alternating-Current High-Voltage Circuit Breakers
16. NEMASG-5 Power Switchgear Assemblies
17. NEMA250 Enclosures for Electrical Equipment
18. NFPA 70 National Electrical Code®, 2017 Edition
19. IBC International Building Code (Latest Edition)
20. UL 1008A Transfer Switch Equipment, Over 1000 Volts

1.8 WARRANTY

A. All equipment furnished under this Section of the Specifications shall be guaranteed against
defective parts and workmanship for a period of one ( 1) year from the date of final acceptance of
the installation by the Owner or eighteen (18) months after delivery, whichever comes first. Any
failures or deficiencies shall be corrected by the Contractor or the equipment supplier during the
warranty period at no cost to the Owner.

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-4


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml40l-02
1.9 ACCEPTABLE PROVIDERS

A. The switchgear automatic control system modification design, documentation, panel fabrication
and field installation shall be provided by:

1. Custom Controls
3913 West State Hwy. 86
Lampe, MO 65681
(417) 779-4819
Bob Davis
2. Electric Controls Company
2735 Mercantile Dr.
St. Louis, MO 63144
(314) 290-2919
Mark Price
3. EPS Engineering & Design
1338 E Kingsley St # B
Springfield, MO 65804
( 417) 483-6140
Tom Michalek

PART 2 -PRODUCTS

2.1 DELIVERY AND HANDLING

A. Deliver and handle equipment in accordance with recommended practices listed in manufacturer's
installation and maintenance manuals.

B. Protect equipment from damage during shipment with shipping skids and weatherproof wrapping as
required.

C. Inspect and report concealed damage to carrier within specified time.

D. All equipment shall be UL Listed and Labeled.

2.2 VOLTAGE SENSING RELAY

A. Provide Basler BE 1-47N negative sequence voltage relay, to match existing voltage sensing relays
on the two utility main circuit breakers in the switchgear, to provide 3-phase voltage sensing for
the 12.47 kV generator breaker in the campus main switchgear.

B. The BE1-47N shall include the following features/options:

1. Size S1, semi-flush, draw-out case


2. Sensing input voltage range as required for the application
3. Two (2) output relays; 47N and 27/59
4. Negative sequence timing as required for the application
5. 48 VDC/125 VDC power supply set to 48 VDC
6. Two internally operated, magnetically latched, manually resettable targets; 47N and 27/59
7. Undervoltage and overvoltage sensing with characteristics (as required for the application)
8. Two (2) auxiliary output contacts; 47N and 27/59

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-5


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
2.3 POTENTIAL TRANSFORMER

A. Provide a three-phase potential (voltage) transformer (PT) to sense the 480V, 3-phase
generator output voltage and provide a 120V, single-phase voltage input to the Basler BE1-
47N negative sequence voltage relay in the generator breaker cubicle.

B. Potential transformer shall have metering accuracy per ANSI Standards.

C. Potential transformer shall have both primary and secondary overcurrent and shmt circuit protection.
Overcurrent and short circuit protection shall be provided by cunent limiting fuses having an
interrupting rating equal to or greater than the ma'Cimum shott-circuit current available at that point
from an infinite bus.

D. Potential transformer shall be Flex-Core Model 2VT460 or Engineer approved equal by ABB or
GE-ITI.

2.4 AUTOMATIC TRANSFER SCHEME

A. The existing Siemens medium voltage switchgear serves as an automatic transfer system (ATS) for
two utility power sources and a standby generator. One utility source is from Ameren Missouri
feeder "LAT #25385" (preferred) and the other utility source is from Ameren Missouri feeder
"LAT #25384" (reserve). The standby generator that backs up both utility sources is a
1280kW/1600kVA, 480V, 3-phase diesel-engine generator that connects through a 1500 kVA step-
up transformer to a 12.47kV "generator" breaker in the main switchgear.

B. Under normal conditions, the load is connected to the "prefened" utility source. When this utility
source is lost, the "preferred" circuit breaker shall open after a time delay and the "reserve" circuit
breaker shall close. Upon restoration of the "preferred" source, the "preferred" circuit breaker shall
close after a time delay and the "reserve" circuit breaker shall open. Either source can be selected as
"preferred." When both utility sources are lost, both the "preferred" and the "reserve" breakers shall
be opened, the generator shall be commanded to statt and, after stable generator output voltage is
detected for 2 seconds, the generator breaker shall close. When either utility source is restored for a
period of fifteen (15) consecutive minutes, the generator breaker shall open, the utility source breaker
that has stable voltage shall close, and the generator shall go into cool down mode. If the utility source
is lost while the generator is still running in cool down mode, the utility breaker shall open, and the
generator breaker shall close to pick up the load without delay. Total transfer time from loss of both
the incoming utility sources until the facility is powered from the standby generator shall be 10 seconds
in accordance with NFPA 110 requirements.

C. The automatic transfer system shall be equipped with proper relays and controls, including
undervoltage indication on each incoming line, designed and connected so that they will operate in the
following manner:

1. Either of the two lines may be selected as the "Preferred" line by means of a three (3)
position selector switch labeled: #1 Preferred, Manual, and #2 Preferred. The "Manual"
position is to be in the middle. Selector switch must be lockable in all positions. Selector
switch shall be Electroswitch Series 24 or approved equal.
2. The selection of the preferred feeder shall be accomplished without rewiring the control.
3. The control shall be symmetrical between the two lines. Reference to either line should apply
conversely to the other.
4. A lockout relay shall be provided to trip and lockout the two incoming line breakers in case of
a bus fault. Lockout controls must be in the trip and close circuits of the preferred main breaker

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-6


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
and the reserve main breaker. This lockout relay must be reset by hand before either breaker
can be closed. Lockout relays shall be Electroswitch LOR-1 or approved equal.
5. Equipment shall transfer on loss of one, two or three phases.
6. Breaker control switches shall be wired into automatic transfer scheme so that if a breaker is
opened, or it does not have a red target on it, the automatic transfer scheme will be disabled.
7. Hardwired interlocks shall prevent closing the generator breaker when either or both utility
breakers are closed and from closing either or both utility breakers when the generator
breaker is closed.

D. Automatic Mode: When the selector switch is in either of the preferred positions, the respective
line shall then be the preferred line and the system shall be set up so that it will operate as indicated
in the following table. The below operating table shall be engraved in black characters on white
laminated plastic and installed on the front of the switchgear in place of the existing operating table
that was installed prior to the installation of the campus standby generator.

1. The voltage condition "Hot" is defined as normal, balanced, three-phase voltage. The
voltage condition "Dead" is defined as any condition where one, two or three phases have
an undervoltage condition.
2. Table: C = Closed, 0 = Open

ORIGINAL CONDITIONS
Line # 1 Preferred - Line #2 Reserve
Breaker
Position Voltage
Line Line Line Line
Case #1 #2 #1 #2 Change Requirement
1 c 0 Hot Hot Line #1 Dead Line # 1 opens after time delay and Line #2
closes (open transition)
2 c 0 Hot Hot Line #2 Dead No change
3 c 0 Hot Hot Both Dead Line #1 opens, backup generator starts, and
Simultaneously generator breaker closes (open transition)
4 c 0 Hot Dead Line #1 Dead Line # 1 opens, backup generator stmts, and
generator breaker closes (open transition)
5 c 0 Hot Dead Line #2Hot No change
6 0 c Dead Hot Line #1 Hot Line #1 closes after time delay and Line #2
opens (closed transition)
7 0 c Dead Hot Line #2 Dead Line #2 opens, backup generator starts, and
generator breaker closes (open transition)
8 0 0 Dead Dead Line #1 Hot The backup generator is disconnected and Line
# 1 is closed (open transition)
9 0 0 Dead Dead Line#2 Hot The backup generator is disconnected and Line
#2 is closed (open transition)
10 0 0 Dead Dead Both Hot The backup generator is disconnected and Line
Simultaneously # 1 is closed (open transition)
11 c 0 Hot Hot Switch from Line Line #2 closes after time delay and Line # 1
# 1 Preferred to opens (closed transition)

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-7


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

ORIGINAL CONDITIONS
Line # 1 Preferred - Line #2 Reserve
Breaker
Position Voltage
Line Line Line Line
Case #1 #2 #1 #2 Change Requirement
Line #2 Preferred
12 c c Hot Hot Switch from Line #2 opens immediately and Line # 1 remains
manual to Line closed
# 1 preferred

3. The control switch handle on each breaker shall have control over its associated breaker for
opening operations only. The control switch handle shall have no control over its associated
breaker for manual closing operations. Each control switch shall have suitable contacts
ananged so that tripping by either incoming line control switch handle will disable automatic
closing of both line breakers until the breaker's control switch is turned to the "closed" position
(red target).

E. Manual Mode: When the selector switch is moved from either preferred position to the manual
position, each circuit breaker shall come under the control of its respective control switch handle
and shall be operated in the following manner:

1. Each of the circuit breakers shall remain in the same position (either open or closed) until
its respective control switch handle is operated to change its position.
2. The control switch handle on each breaker shall have complete control over its associated
breaker, permitting paralleling of supplies for closed transition switching, as well as testing
operations.
3. When the selector switch is moved from line one preferred position through the manual
position to line two preferred position, the line two breaker shall automatically close after
which the first breaker shall automatically open (closed transition).
4. When the switch is in the manual position all automatic operations shall be disabled.

F. Transfer Between Utility Source Feeders and Campus Generator: Provide an independent
hardwired breaker auxiliary contact scheme to prevent and/or break up a condition in which the
generator is in parallel with the Ameren Missouri system. Comply with all requirements of Ameren
Document CO for Categoty 1 - Open Transition included in Attachment B at the end of this
specification.

1. Provide manual bypass; i.e., auto disable, feature for use in the event of a malfunction in
the automatic transfer between sources in either direction. The manual bypass function
shall be open transition in nature and mechanically interlocked to prevent the closing of
both the generator source and either one of the two utility sources at the same time.
2. The automatic transfer control system shall be "supervised" by the status of the generator
and both utility source main circuit breakers so that if a breaker is manually tripped,
automatic control will be disabled.

2.5 CONTROL WIRING

A. All new control wiring within the switchgear shall be Type SIS, flexible 41-strand minimum,
copper, 90°C dry, 600-volt single conductor wire, minimum size 14 A WG, except where larger size

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-8


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
wire is required. All wire shall be flame-retardant meeting Underwriters' Laboratories, Inc. VW -1
vertical flame test.

B. Interconnecting wiring from exterior components to the switchgear, as well as interconnecting wiring
within the switchgear, between vertical sections, shall terminate at the terminal blocks.

C. Terminal blocks shall be provided for the connection of all interconnection wiring leaving the
switchgear and going to all remote devices.

D. All new terminal blocks shall include a minimum often percent (10%) spare terminal points.

E. All terminal blocks shall contain a white or very light gray center mounted removable marking strip.

F. Conductors shall be identified at each termination by marking with a number to correspond with the
diagrams. Identification tags shall be made of oil-resistant material.

G. All wiring between the swing-out interior door and the interior of each vertical section shall be bundled
and properly laced, with sufficient slack to permit full opening of the door without damaging the wire
bundle. All wires between the door and the panel interior shall terminate at the terminal strip inside
the section enclosure.

2.6 CONTROLPANEL-GENERAL

A. All new control equipment, control relays, miscellaneous devices and hardware that will not fit
within the very limited control wiring areas within the exiting switchgear shall be mounted in a
factory wired control panel fabricated in a UL 508A certified industrial control panel shop
(Category Code NITW). The completed control panel shall be UL 508A listed and labeled. The
control panel short circuit current rating (SCCR) shall be adequate for the installation, 10 kA
minimum.

B. Control Panel Construction: Control panel shall be minimum 14-gauge steel, wall mount NEMA
12 cabinet with maximum dimensions of36" wide x 48" high x 12" deep finished with baked enamel
inside (white) and outside (ANSI 49 or 61 gray).

C. Provide inner back panel for mounting control components and terminal blocks finished in white
backed enamel.

D. Control panel enclosure shall be of sufficient width and depth to accommodate all controls and
instrumentation.

E. Seams shall be continuously welded and ground smooth with no holes or knockouts.

F. Control panel enclosure shall be front opening. Door shall be full height with full length continuous
hinge with stainless steel hinge pin and three-point latching mechanism operated by an oil-tight, key-
locking handle.

G. Latch rods shall have rollers for easier door closing.

H. Outside corners shall have a 1/4-inch radius.

I. Provide oil-resistant door gasket attached with oil-resistant adhesive and held in place with steel
retaining strips.

J. Provide cabinet grounding stud.


15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 9
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M140 1-02
K. Fasteners required for mounting devices shall not be visible on the outside of the enclosure. The
arrangement of any controls that are to be mounted in the door face shall be subject to the Engineer's
approval as part of the shop drawing submittal process.

L. All internal components shall be fastened to the inner back panel. Intemal component fasteners shall
not be visible on the outside of the enclosure. Drilling for mounting of equipment shall not be done
until a check of dimensions with equipment to be installed has been made. Tapped holes shall be
used. Self-tapping or sheet-metal screws are not allowed.

M. All cutouts shall be punched, or machine cut. Cutout dimensions shall be verified. Any dimensional
variations resulting in changes in panel layout shall be reported to the Engineer for resolution before
proceeding with fabrication.

N. A nameplate shall be furnished for each item on the control panel describing the function of the item.
Nameplates shall be white laminated plastic with black engraved characters, minimum 3/16" high.
Permanent nameplates or tags shall also be provided to label all devices located inside the control
panel.

0. If the control panel requires 120 VAC, single-phase, 60Hz supply power, provide a single-point
of connection for the 120 VAC power supply terminating in a circuit breaker or fused disconnect
with a minimum short circuit interrupting rating that is adequate for the installation, 10 kAIC
minimum.

P. If the control panel requires 48 VDC, provide a single-point of connection for the 48 VDC power
supply terminating in a circuit breaker or fused disconnect with a minimum shmi circuit
interrupting rating of 10,000 amps RMS symmetrical.

Q. All power and control wiring shall be stranded copper, 600-volt single conductor, moisture and heat
resistant, Type SIS panel wire, rated for 90°C. For power conductors, the minimum size shall be 12
A WG. For control conductors, the minimum size shall be 14 A WG. All wiring and component
installation shall be in accordance with the latest issue of the National Electrical Code. All
components shall have Underwriters Laboratories, Inc. approval.

R. All field and panel interconnection wiring shall be landed on terminal blocks in the control panel.
Interconnecting wiring from extemal devices to the panel, as well as interconnecting wiring within
the panel, shall terminate at the terminal blocks. No wire splices shall be allowed in the panel.
Terminal blocks shall have no more than two (2) wires connected per termination point. Factory
jumpers may be used where required. Jumpering of live voltages using non-insulated comb type
jumpers will not be acceptable. Isolated comb jumpers, insulated wire jumpers or jumper bars shall
be used.

S. Each wire end shall be permanently marked with the source and destination of the wire. The wire
markers shall be self-laminated vinyl, computer printable, Thomas and Betts Series WES, or
approved equal.

T. Each terminal on the terminal block shall be permanently marked with the complete terminal
number and shall be installed so as to be readable from left to right and top to bottom. Terminals
shall be numbered with a permanent, nonconductive strip on each block according to the detailed
wiring drawings to be provided by the equipment supplier. Wire numbers shall not be used to
identify terminals on terminal blocks.

U. Terminal blocks shall be grouped according to function and voltage level.

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 10


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
V. Terminal blocks shall be installed a minimum of six inches above the panel bottom, and flush with
the wiring duct front face.

W. Not less than two inches shall be provided between terminal blocks and wiring duct or equipment
for ease in wiring and wire number legibility.

X. Terminal block groups shall be permanently identified with an engraved laminated plastic
nameplate as specified on the control panel drawings.

Y. All wires going to external devices shall be terminated at terminal blocks. No more than two
wires shall be connected to the same terminal. Each wire shall be a continuous run. Splices will
not be permitted.

Z. All grounding conductors shall be identified with green insulation or green tape at termination
points.

AA. Plastic wiring duct shall be used to enclose panel wiring. Duct shall be Panduit Corporation Type
E or approved equal. The wire duct color shall be the same throughout the panel. The duct shall
be securely fastened to the panel with screws and washers or rivets. Ducts shall be a maximum
of 50 percent full. The 50-percent maximum fill provides capacity for future expansion.

BB. Wiring shall be routed by duct wherever possible. Wire shall be neatly arranged within and
exiting from duct. A small loop of wire shall be left in the wiring duct when connecting to
terminal strips. Wire identifications shall not extend into the wire duct. AC wiring and DC wiring
shall not be mixed in the same duct.

CC. Wiring duct shall be provided from the entry point of external cables/conductors to the
termination point of the cables/conductors. The AC wiring and DC wiring leading from the
devices and terminal blocks to the field shall be formed to exit separately in dedicated areas of
the panel.

DD. Field side of terminal blocks shall be free of wiring. An empty run of wiring duct shall be
provided for field wiring.

EE. Bundling of wires, except within covered wireway, shall be accomplished with Thomas and Betts
"Ty-Raps" or approved equal. The Contractor shall use the manufacturer's installation tool to
prevent sharp edges after the "Ty-Raps" have been cut. All wiring to door mounted devices shall
be suitably looped, protected with spiral wrap, and secured with "Ty-Rap" mechanically installed
mounted bases, Catalog No. TC5828 or approved equal.

FF. All wiring across hinges or to movable panels shall have Class C stranding.

GG. All components shall be arranged for easy access for future modification and maintenance. Panels
shall have a minimum of 2-inch space between outer edge of mounted components and side of
panel. Panels shall have a minimum of 2-1/2-inch space between all mounted components and
wireway. No wire splices shall be allowed in panels. All devices in enclosures, including those
that are door mounted, must be readily accessible.

HH. All electrical nodes and switches, indicating lights, relays, or other control devices are to be wired
to terminal blocks.

II. The control panel shall be quality checked and tested before shipment from the factory.

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 11


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
1. All tags and nameplates shall be checked for correct color, size, letter size, spelling and
location.
2. Continuity and point-to-point tests of all wiring shall be performed.

JJ. Provide control relays, timing relays, terminal blocks and other components, that are equal to the
components listed in the bill of materials for the original switchgear. See resource (RE series)
drawings. To the greatest extent possible, utilize the same manufacturer and model control
components as listed in the original switchgear bill of materials.

2.7 CONTROLSTATIONS

A. Control stations shall be cast aluminum, NEMA Type 4X (corrosion resistant/watertight)


with ANSI 49 or ANSI 61 gray finish. Control stations shall include push button units,
selector switch units, pilot light units, E-stop push buttons and/or other units as shown on
the Drawings. Manufacturer's legend plates shall be installed as identified on the Drawings.
Miniature type control devices shall not be used, unless otherwise indicated.

B. Each control station shall have an interconnection point-to-point wiring diagram mounted
inside the enclosure.

C. Approved control station manufacturers shall be:

l. Allen-Bradley
2. Eaton
3. General Electric
4. Siemens
5. Square D Company

2.8 PILOT LIGHTS

A. Pilot light units shall be NEMA Type 4/4X/13 (watertight/corrosion resistant/oiltight), fiberglass
reinforced thermoplastic polyester, 30 or 30.5 mm round, panel mounted, 120VAC or 48VDC,
push-to-test, full voltage, high-intensity LED type. Lamps shall be replaceable by removal of the
color cap.

B. Color of pilot lights shall be as indicated on the Drawings and as required by these Specifications.
C. Provide the device manufacturer's standard engraved collar legend nameplate to identify the function
of each pilot light as indicated on the Drawings.

D. Pilot lights shall be Allen-Bradley SOOT or approved equal by Eaton, General Electric, Siemens or
Square D.

2.9 PUSH BUTTONS

A. Push button units shall be NEMA Type 4/13 (watertight/oiltight), 30 or 30.5 mm round metal, panel
mounted. Push buttons shall have a fully guarded (flush) spring loaded (momentary) type
operator. Operator color shall be as specified herein.

B. Provide the device manufacturer's standard engraved collar legend nameplate to identify the function
of each push button as indicated on the Drawings.

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 12


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
C. Push buttons shall be Allen-Bradley SOOT or approved equal by Eaton, General Electric, Siemens or
Square D.

2.10 EMERGENCY STOP PUSH BUTTONS

A. Generator emergency stop (E-Stop) push buttons shall be NEMA Type 4/4X/13
(watettight/corrosion resistant/oiltight), fiberglass reinforced thermoplastic polyester, 30 or 30.5
mm round, panel mounted. E-Stop push buttons shall have 63 mm red plastic operator, 2-position
push-pull/twist release, non-illuminated type.

B. Provide the device manufacturer's standard engraved collar legend nameplate with "EMERGENCY
STOP" in red letters.

C. E-Stop push buttons shall be Allen-Bradley SOOT or approved equal by Eaton, General Electric,
Siemens or Square D.

2.11 SELECTOR SWITCHES

A. Selector switches shall be NEMA Type 4/13 (watettight/oiltight), 30 or 30.5 mm round metal, two-
position, maintained contact, panel mounted with the Standard Operator, unless otherwise indicated.

B. Provide the device manufacturer's standard engraved collar legend nameplate to identify the function
of each selector switch as indicated on the Drawings.

C. Selector switches shall be Allen-Bradley SOOT or approved equal by Eaton, General Electric,
Siemens or Square D.

D. Selector switches shall be NEMA Type 4/13, watertight/oiltight, round metal, 30.5 mm, panel
mounted, Allen-Bradley Bulletin SOOT or approved equal. Selector switches shall have black
"standard" operator.

1. Two (2), two-position maintained contact selector switches shall be provided for automatic
transfer system testing to interrupt control power to the prefened and reserve BE1-47N
voltage sensing relays.
2. Switches shall have color legend plate labeled "NORMAL" in the left-hand position and
"TEST" in the right-hand position.
3. Provide white laminated plastic nameplates with 3/16" engraved black characters:
"PREFERRED FDR TEST SW" and "RESERVE FDR TEST SW" for identification of
these two test switches.

2.12 SWITCHGEAR STATUS AND ALARM REMOTE ANNUNCIATION

A. Ethernet Peer-to-Peer Discrete 1/0 Mirrors: Direct input-to-output signal communication over
copper, optical-fiber, or wireless Ethernet IP with the following features:

1. High speed peer-to-peer I/0 within 20 ms


2. One physical alarm port for connectivity status
3. Quick and easy utility and web-based settings
4. Local alarm channel
5. Remote alarm message
6. Suppotts Modbus/TCP for remote monitoring
7. S digital input channels, S digital output channels

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 13


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
B. Discrete I/0 mirrors shall meet the following specifications:

1. LAN

a. Ethernet: 1 x 10/100 Mbps, RJ45


b. Protection: 1.5 kV magnetic isolation
c. Protocols: Modbus/TCP, TCP/IP, UDP, DHCP, Bootp, HTTP, SNTP

2. Digital Input

a. Channels: 8, source type


b. Sensor Type: NPN, Dry contact
c. I/0 Mode: Digital Input
d. Dry Contact

i. Logic 0: short to GRD


ii. Logic 1: open

e. Wet Contact

i. Logic 0: 0 to 3 VDC
ii. Logic 1: 10 to 30 VDC (DI COM to DI)

f. Common Type: 8 points per COM


g. Isolation: 3K VDC or 2K Vrms
h. Digital Filtering Time Interval: Software selectable
i. Over-Voltage Protection: 36 VDC

3. Digital Output

a. Channels: 8, sink type, 36 VDC, 200 mA


b. I/0 Mode: Digital Output
c. Over-voltage Protection: 45 VDC
d. Over-current Protection: 600 rnA
e. Over-temperature Protection: 16o·c
f. Output Current Rating: Max. 200 mA per channel
g. Isolation: 3k VDC or 2k Vrms

4. Alarm Port Output

a. Channels: 1, sink type


b. Output Current Rating: Max. 200 rnA per channel

5. Power Requirements

a. Power Input: 24 VDC nominal, 12 to 48 VDC


b. DO Power: 24 VDC nominal, up to 45 VDC

6. Physical Characteristics

a. Housing: Ventilated ABS plastic or aluminum


b. Installation: DIN-rail mounting
c. Wiring: I/0 cable max. 14 A WG

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 14


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
7. Environmental Limits

a. Operating Temperature: -10 to 60'C ( 14 to 140'F)


b. Storage Temperature: -40 to 85'C (-40 to 185'F)
c. Ambient Relative Humidity: 5 to 95% (non-condensing)

8. Standards and Certifications

a. Safety: UL 508
b. EMI: FCC Part 15, Subpart B, Class A, EN 55022 Class A
c. EMS: IEC 61000-4, IEC 61000-6
d. Shock: IEC 60068-2-27
e. Freefall: IEC 60068-2-32
f. Vibration: IEC 60068-2-6

9. Warranty Period: 5 years

C. Discrete I/0 mirrors shall be Moxa Model ioMirror E321 0 or Engineer approved equal by Cisco,
Hirschmann, N-tron or Phoenix.

D. 1OOBase TX to 1OOBase FX Media Converters: Copper to optical-fiber Ethernet media converters


shall include the following features:

1. Multi-mode with SC fiber connector


2. Link Fault Pass-Through (LFP)
3. DIP switches to select FDX/HDX/10/100/Auto/Force

E. Industrial media convetiers shall meet the following specifications:

1. Technology Standards

a. IEEE 802.3 for 1OBaseT


b. IEEE 802.3u for 100BaseT(X) and lOOBaseFX
c. IEEE 802.3x for Flow Control

2. Interface

a. RJ45 Ports: 10/100Base T(X)


b. Fiber Ports: 100BaseFX (SC connectors)
c. LED Indicators: Power, 10/lOOM (TP Poti), lOOM (fiber port), FDX/CPL (fiber
port)
d. DIP Switches: TP poti's 10/lOOM, Half/Full modes, Force/Auto modes; fiber poti's
Half/Full modes, Link Fault Pass-Through (LFP)

3. Optical Fiber (lOOBaseFX)

a. Fiber Cable Type: Multi-Mode


b. Wavelength:

i. Typical: 1300 nm
ii. TX Range: 1260 to 1360 nm
iii. RX Range: 1100 to 1600 nm

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 15


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
c. Optical Power

i. TX Range: -10 to -20 dBm


ii. RX Range: -3 to -32 dBm
iii. Link Budget: 12 dB
iv. Dispersion Penalty: 3 dB

4. Power Requirements

a. Input Voltage: 12 to 48 VDC


b. Input Current: 265 rnA @ 12 VDC
c. Overload Current Protection: 1.1 A
d. Connection: Removable 3-contact terminal block
e. Reverse Polarity Protection: Present

5. Physical Characteristics

a. Housing: Metal, IP30 protection


b. Installation: DIN-rail mounting

6. Environmental Limits

a. Operating Temperature: -10 to 60'C (14 to 140'F)


b. Storage Temperature: -40 to 75'C (-40 to 167'F)
c. Ambient Relative Humidity: 5 to 95% (non-condensing)

7. Standards and Certifications

a. Safety: UL 60950-1
b. EMC: EN 55032/24
c. EMI: CISPR 32, FCC Part 15B Class A
d. EMS: EN 61000-4-2 (ESD): Contact: 6 kV; Air: 8 kV
EN 61000-4-3 (RS): 80 MHz to 1 GHz: 1 VIM
EN 61000-4-4 (EFT): Power: 1 kV; Signal: 1 kV
EN 61000-4-5 (Surge): Power: 1 kV; Signal: 1 kV
EN 61000-4-6 (CS): 150kHz to 80 MHz: 3 V/m
EN 61000-4-8 (PFMF)
EN 61000-4-11
e. Shock: IEC 60068-2-27
f. Freefall: IEC 60068-2-32
g. Vibration: IEC 60068-2-6

8. MTBF (mean time between failures) per MIL-HDBK-217F: > 600,000 hrs
9. Warranty Period: 5 years

F. 100Base TX to 100Base FX media converters shall be Moxa Model IMC-21A-M-SC or Engineer


approved equal by Cisco, Hirschmann, N-tron or Phoenix.

G. Unmanaged Ethernet Switch: 8-port with the following features:

1. Relay output warning for power failure and port break alarm
2. Broadcast storm protection

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 16


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
H. Unmanaged Ethernet switch shall meet the following specifications:

1. Technology

a. Standards

i. IEEE 802.3 for I OBaseT


ii. IEEE 802.3u for 100BaseT(X) and 100BaseFX
iii. IEEE 802.3x for Flow Control

b. Processing Type: Store and Forward

2. Switch Properties

a. MAC Table Size: 2K


b. Packet Buffer Size: 768 Kbit

3. Interface

a. RJ45 Ports: 10/100Base T(X) auto negotiation speed, Full/half duplex mode, and
auto MDI/MDI-X connection
b. Fiber Ports: 100BaseFX ports (SC connectors)
c. DIP Switches:

i. Port break alarm mask


ii. Enable/disable broadcast storm protection (EDS-316)

d. Alarm Contact: 1 relay output with current carrying capacity of 1 A @ 24 VDC

4. Optical Fiber (100BaseFX)

a. Fiber Cable Type: Multi-Mode


b. Wavelength:

iv. Typical: 1300 nm


v. TX Range: 1260 to 1360 nm
vi. RX Range: 1100 to 1600 nm

c. Optical Power

v. TX Range: -10 to -20 dBm


vi. RX Range: -3 to -32 dBm
vii. Link Budget: 12 dB
viii. Dispersion Penalty: 3 dB

5. Power Requirements

a. Input Voltage: 12/24/48 VDC, redundant dual inputs


b. Operating Voltage: 9.6 to 60 VDC
c. Input Current: 0.15 A@ 24 VDC
d. Overload Current Protection: 3 A
e. Connection: Removable 6-pin terminal block
f. Reverse Polarity Protection: Supported

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 17


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
6. Physical Characteristics

a. Housing: Metal, IP30 protection


b. Installation: DIN-rail mounting

7. Environmental Limits

a. Operating Temperature: -40 to 75'C (-40 to 167'F)


b. Storage Temperature: -40 to 85'C (-40 to 185'F)
c. Ambient Relative Humidity: 5 to 95% (non-condensing)

8. Standards and Certifications

a. Safety: UL 508, UL 60950-1, EN 60950-1


b. Hazardous Location: UL/cUL Class 1 Division 2 Groups A/B/C/D, ATEX Zone 2
Ex nA nC IIC T4 Gc
c. EMC: EN 55032/24
d. EMI: CISPR 32, FCC Part 15B Class A
e. EMS: IEC 61000-4-2 (ESD): Contact: 6 kV; Air: 8 kV
IEC 61000-4-3 (RS): 80 MHz to 1 GHz: 20 V/M
IEC 61000-4-4 (EFT): Power: 2 kV; Signal: 1 kV
IEC 61000-4-5 (Surge): Power: 2 kV; Signal: 2 kV
IEC 61000-4-6 (CS): 10 V
EN 61000-4-8
f. Marine: IEC 60945
g. Shock: IEC 60068-2-27
h. Freefall: IEC 60068-2-32
i. Vibration: IEC 60068-2-6

9. MTBF (mean time between failures) per MIL-HDBK-217F, GB 25'C: > 250,000 hrs
10. Warranty Period: 5 years

I. Unmanaged Ethernet switch shall be Moxa Model EDS-308-MM-SC or Engineer approved equal
by Cisco, Hirschmann, N-tron or Phoenix.

J. 24VDC Power Supplies: Power supplies shall meet the following specifications:

1. Input Voltage: 100-240 VAC +/- 10%


2. Input Frequency: 50-60Hz+/- 6%
3. Minimum Efficiency: 88%
4. Output Power: 30 to 40 W
5. Output Voltage: 24 VDC
6. Voltage Adjustment Range: 24 - 28 VDC
7. Output Current: 1.3 to 1. 7A
8. Output Rlpple: < 150mVp-p
9. Typical Hold-up Time at Full Load: 31 ms@ 120VAC
10. Electronic overload, no-load and short-circuit protection with automatic recovery
11. Output Over-Voltage Protection: 36 VDC Typical (Output shuts down, cycle input power
to recover)
12. Physical Characteristics

a. Housing: IP20 protection, minimum


b. Installation: DIN-rail mounting

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-18


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
c. Wiring: I/0 cable max. 14 A WG (minimum)

13. Environmental Limits

a. Operating Temperature: -10 to 7o·c (14 to 158.F)


b. Storage Temperature: -40 to 85·c (-40 to 185"F)
c. Ambient Relative Humidity: 20 to 90% (non-condensing)

14. Standards and Certifications

a. Safety: UL 508, UL 60950-1, IEC 60950-1


b. EMC: EN 61000-4-2 (ESD): Contact: 8 kV; Air: 8 kV
EN 61000-4-3 (RF): 80 MHz to 2.7 GHz: 10 VIM
EN 61000-4-4 (EFT): Input Lines: 4 kV; Output Lines: 2 kV
EN 61000-4-5 (Surge): Input Lines: 2 kV; Output Lines: 2 kV
EN 61000-4-6 (CS): 0.15-80 MHz: 10 V
c. Shock: 30g 6ms, 20g llms; 3 bumps/direction, 18 bumps in total per IEC 60068-
2-27
d. Vibration: 2-17.8 Hz: +/-1.6mm; 17.8-500 Hz: 2g; 2 hrs/axis per IEC 60068-2-6

15. MTBF (mean time between failures): > 170,000 hrs at 24VDC, 1.3A and 4o·c
16. WatTanty Period: 3 years

K. 24VDC power supplies shall be PULS Model ML30.241, Moxa Model MDR-40-24 or Engineer
approved equal.

L. Alarm Annunciator: Panel mounted alarm annunciator shall include the following features:

1. Display: 8 red LED channel indicators plus one green LED power indicator
2. Alarm Messages: Custom printed adhesive clear labels; 1.25" x 0.25", 8 messages
3. Programming Methods: Rear 4-position switch for sequence selection and horn operation.
Three (3) front panel push buttons for NO/NC input selection, sequence option, and
operation. Programable for all common ISA sequences.
4. Audible Alarm: 85 dB internal horn
5. All programmed settings shall be stored in non-volatile memory for a minimum often years
if power is lost.
6. 1/8 DIN, high impact plastic, NEMA 4X/IP 65 front, UL 94V-O semi-flush panel mount
with mounting brackets included

M. Alarm annunciator shall meet the following specifications:

1. Input Power: 85-265 VAC, 50/60 Hz or 12-36 VDC, 6 W max (as required for the
application)
2. Input Protection: Required external fuse: UL Recognized, 5 A max, slow blow fuse
3. Isolated Power Supply: 24 VDC +/- 10%@ 200 rnA max (only with 85-265 VAC input)
4. Isolation: 4 kV input/output-to-power line
5. Overvoltage Category: Installation Overvoltage Category II
6. Shared First-Out Systems: 1 ms unit-to-unit delay with maximum of 200 units in shared
first-out system
7. Inputs

a. Input Types: NO or NC switches with no external excitation required

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327- 19


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
b. Open Collector Transistor (NPN): Open circuit voltage approx. 3.3 VDC. Logic
Levels: LOW= 0 to 0.9 VDC, HIGH= 2.4 to 28 VDC
c. Update Rate: 41 ms following alarm state; 1 ms for alarm state clear
d. Sequences: Input follower, ISA Sequences A, F1A, F2A, F3A, M, F1M, and F3M
per ISA Standard ISA-18.1-1979 R2004
e. Sequence Options: A, Fl, F2A, F3A, M, F1M, F2M, and input follower with
selectable options -1 (silence push button), -4 (no lock-in) and -6 (no horn).

8. Relays

a. Type: 2SPDT (Form C)


b. Rating: 3 A at 30 VDC or 3 A at 250 V AC resistive load; 1/14 hp at 125/250 VAC
for inductive loads
c. Relay Operation: Relay 1: Alarm state until alarm is acknowledged
Relay 2: Alarm state if any channel indicating alarm condition
d. Fail-Safe Operation: Programmable independent for each relay

9. Environmental Limits

a. Operating Temperature: -40 to 65·c (-40 to 149.F)


b. Storage Temperature: -40 to 85·c (-40 to 185.F)
c. Ambient Relative Humidity: 0 to 90% (non-condensing)

10. Standards and Certifications: UL 508 Listed and Labeled


11. Wiring Connections: Removable screw terminal blocks for 22 to 12 AWG conductors
12. Warranty Period: 3 years parts & labor

N. Annunciator shall be Precision Digital Vigilante II Model PD158 or Engineer approved equal by
Cole-Palmer or Murphy.

0. Remote Switchgear Alarm Annunciator Panel: Wall mounted, hinged door panel to house all
components required for the remote annunciation of status and alarm conditions on the 12.47 kV
campus main switchgear as specified herein and as shown on Drawing E-602. Annunciator panel
shall meet the following requirements:

1. All equipment, miscellaneous devices and hardware shall be mounted in a factory wired
control panel fabricated in a UL 508A certified industrial control panel shop (Category
Code NITW). The completed control panel shall be UL 508A listed and labeled. The
control panel short circuit current rating (SCCR) shall be a minimum of 10,000 amps RMS
symmetrical.
2. Annunciator panel enclosure shall be NEMA 1 carbon steel with a lockable hinged door
with and with carbon steel inner back panel. Enclosure shall be painted tan or beige and
inner back panel shall be white.
3. Seams shall be continuously welded and ground smooth with no holes or knockouts.
4. Door shall be full height with continuous hinge.
5. Panel shall be of sufficient height, width and depth to accommodate all devices mounted
on or inside the panel.
6. All internal components shall be fastened to the inner back panel. Internal component
fasteners shall not be visible on the outside of the panel. Drilling for mounting of
equipment shall not be done until a check of dimensions with equipment to be installed has
been made. Tapped holes shall be used. Self-tapping or sheet-metal screws are not
allowed.
7. All cutouts shall be punched or machine cut. Cutout dimensions shall be verified.

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-20


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
8. A nameplate shall be furnished for each item on the panel describing the function of the
item. Nameplates shall be white laminated plastic with engraved black characters,
minimum 3/16" high. Permanent nameplates or tags shall also be provided inside the panel
to label all devices.
9. The control panel shall have a single-point of connection for a 120 VAC single-phase, 60
Hz power supply terminating in a circuit breaker with a minimum short circuit interrupting
rating of 10,000 amps RMS symmetrical. Circuit breakers shall be Allen-Bradley 1489-
Ml C or approved equal.
I 0. All power and single conductor control wiring shall be stranded copper, 600-volt single
conductor, moisture and heat resistant, Type SIS panel wire or Type THHN-THWN-2 in
accordance with the UL listing requirements. For AC power conductors, the minimum size
shall be 12 A WG. For control conductors, the minimum size shall be 14 AWG.
11. All wiring and component installation shall be in accordance with the latest issue of the
National Electrical Code. All components shall have Underwriters Laboratories, Inc.
approval.
12. Provide terminal blocks inside the control panel for 24VDC power distribution. Terminal
blocks shall be 1492-WKD6 or approved equal. Terminals shall be numbered with a
permanent, nonconductive strip on each block according to the detailed wiring drawings to
be provided by the Contractor. Terminal blocks shall be DIN rail mounted to inner back
panel. Terminal blocks shall have no more than two (2) wires connected per termination
point. Factmy jumpers may be used where required.
13. Each wire end at terminal block and device terminations shall be permanently marked with
a full wire number. The wire markers shall be self-laminated vinyl, computer printable,
Thomas and Betts Series WES, with clear shrink tubing over labels.
14. Plastic wiring duct shall be used to enclose panel wiring. Duct shall be Panduit Corporation
Type E or equal. The duct shall be securely fastened to the panel with screws and washers
or rivets.
15. Wiring shall be routed by duct wherever possible. Wire shall be neatly arranged within
and existing from duct. A small loop of wire shall be left in the wiring duct when
connecting to terminal strips. Wire identifications shall not extend into the wire duct. AC
wiring or DC wiring shall not be mixed in the same duct.
16. Bundling of wires, except within covered wireway, shall be accomplished with Thomas
and Betts "Ty-Raps" or approved equal. The Contractor shall use the manufacturer's
installation tool to prevent sharp edges after the "Ty-Raps" have been .cut. All wiring to
door-mounted devices shall be suitably looped, protected with spiral wrap, and secured
with "Ty-Rap" mechanically installed mounted bases, Catalog No. TC5828.
17. All wiring across hinges or to movable panels shall have Class C stranding.
18. No wire splices shall be allowed inside the panel.
19. The control panel shall be quality checked and tested before shipment from the factory.

a. All tags and nameplates shall be checked for correct color, size, letter size, spelling
and location.
b. Continuity and point-to-point tests of all wiring shall be performed.

20. Annunciator panel shall include labeling in accordance with NEC 409.110 including the
SCCR.

PART 3 -EXECUTION

3.1 SWITCHGEAR CONTROLS MODIFICATION SEQUENCE

A. The anticipated sequence of events for the switchgear automatic controls modifications is as
follows.

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-21


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
1. The approved submittal drawings from the original Siemens 15kV metal-clad dual source
with automatic transfer switchgear, prior to the addition of the standby generator connection
will be provided to the Contractor.
2. The AutoCAD drawing files will be provided to the Contractor for each of the reference
("RE") drawings that are included in the Contract Documents for the Contractor's use in
preparing the revisions to these drawings required to document the modifications necessmy to
correctly implement the standby generator connection with open-transition automatic transfer
to backup the two utility feeders and to make any corrections necessary to bring the switchgear
automatic transfer controls into compliance with Ameren Missouri and UL LLC requirements.
3. Field verification of existing control wiring configuration of the equipment on-site with
respect to the "RE" series drawings that are included in the Contract Documents.
4. Update the AutoCAD drawing files for the "RE" series drawings to correct to as-built
condition and to document the modifications necessary to correctly implement the standby
generator connection with open-transition automatic transfer to backup the two utility feeders
and to make any corrections necessary to bring the switchgear automatic transfer controls into
compliance with Ameren Missouri and UL LLC requirements.
5. Submit updated "RE" series drawings, along with all other required submittal documents
specified herein, for UL review by Engineer, Ameren Missouri and UL LLC.
6. Incorporate all comments from submittal review process and submit revised documents for
review by Engineer, Ameren Missouri and UL LLC.
7. Incorporate all final comments and procure equipment and material necessary for the
switchgear modifications.
8. Fabricate new switchgear automatic transfer controls panel, if one is required for this
project, in UL 508 certified panel shop.
9. Deliver all equipment and materials to the project site.
10. Complete field modifications to existing switchgear and generator control panel.
11. Complete on-site testing of all controls to ensure conformance to all requirements and
satisfactory performance in all modes of operation and then schedule on-site review and
acceptance testing by UL LLC and Ameren Missouri.
12. Complete all acceptance testing specified by UL LLC and Ameren Missouri to receive
field evaluation certification of the equipment and Ameren Missouri approval.
13. Provide O&M manuals, warranty certificates, UL Field Evaluation cettification documents
and letter of acceptance from Ameren Missouri.
14. Provide Owner training on the switchgear automatic transfer controls.

3.2 EXISTING PROTECTIVE RELAYS

A. All existing Basler protective relays in the 12.47 kV campus main switchgear shall in service and
are to be tested and calibrated in accordance with Section 260115- Preventative Maintenance for
15 kV Metal-Clad Switchgear.

3.3 FIELD WIRING

A. All field wiring to/from control panels and equipment shall be in conduit in accordance with Section
260533.13- Conduit for Electrical Systems and wiring shall be in accordance with Section 260519
-Low-Voltage Electrical Power Conductors and Cables.

3.4 FIELD SERVICE ASSISTANCE

A. The Contractor shall provide a field service engineer from the switchgear controls system upgrade
provider to verify the installation of all equipment and interconnection wiring and to perform final
acceptance testing of the 12.47 kV campus main switchgear modifications.

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-22


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02
B. All items shall be visually inspected to ascertain that each item is not damaged and is in proper working
condition.

C. All protective relays shall be properly set in accordance with instructions from the Contractor's Relay
Engineer (subject to Ameren Missouri approval), and all protective relays shall be calibrated and tested
to insure correct and proper operation.

D. Commissioning Tests: Ameren Missouri will perform acceptability testing and inspection of the
primary switchgear to verify that all Ameren Missouri requirements have been met. Prior to testing a
set of as built drawings shall be provided to Ameren Missouri.

1. Ameren Missouri acceptability test may consist of, but will not be limited to:

a. Loss of 3 phase potential to one supply circuit


b. Loss of single phase potential to one supply circuit
c. Loss of potential to all supply circuits
d. Lockout operation
e. Phase checks
f. Interlock verification
g. Control switch operations
h. Transfer operation checks

2. Ameren Missouri inspection may consist of, but will not be limited to:

a. Locking provisions
b. Operating controls

E. UL Field Evaluation Tests: UL LLC will perform acceptability testing and inspection of the primary
switchgear to verify compliance with all applicable UL standards, including UL 1008A - Transfer
Switch Equipment, Over 1000 Volts. Prior to testing a set of as built drawings shall be provided to
ULLLC.

1. UL field evaluation testing will be completed in at the same time as the Ameren Missouri
commissioning testing.
2. UL field evaluation testing will include witnessing the commissioning testing in all modes
of operation, both normal and abnormal.

F. All discrepancies shall be immediately corrected by the Contractor, either by repairing or


replacement, to the satisfaction of Ameren Missouri and UL LLC at no additional cost to the Owner.
Final payment of the Contract shall be withheld until this has been accomplished.

G. Any changes made during startup and commissioning of the equipment shall be included on the "as-
built" record drawings to be submitted within two weeks of the successful completion of startup and
testing.

H. Provide on-site training to instruct the Owner's personnel in the proper operation and routine
maintenance of the switchgear automatic transfer controls. Review operation and maintenance
manuals, parts manuals and emergency service procedures. This shall be done after completion of the
acceptance testing. Training session shall be video recorded by the Contractor and an electronic copy
of the video file shall be provided to the Owner.

END OF SECTION 261327

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327-23


THIS PAGE INTENTIONALLY LEFT BLANK
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

SECTION 261327- 15kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS

ATTACHMENT A

Ameren Missouri Specification CE-1 0

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327 ATTACHMENT A-1


THIS PAGE INTENTIONALLY LEFT BLANK
SPECIFICATIONS & REQUIREMENTS FOR MULTIPLE & SINGLE LINE PRIMARY
METERED SERVICES

SECTION SUBJECT SHEET

1.0 PURPOSE AND SCOPE .................................................................................................. 3


2.0 DEFINITIONS AND ABBREVIATIONS ...................................................................... 3
3.0 PRIMARY SWITCHGEAR REQUIREMENTS .......................................................... 3
3.1 SITE PLAN ......................................................................................................................... 3

3.2 MAIN DISCONiVECT ........................................................................................................... 4

3.3 SfVITCHGEARDOORS ......................................................................................................... 4

3.4 INCOJviiNG CABLE COJvfPART1\1ENT ..................................................................................... 5


3.5 CONTROL VOLTAGE ........................................................................................................... 7

3. 6 ST¥ITCHGEAR RATINGS....................................................................................................... 7
4.0 METERING REQUIREMENTS .................................................................................... 7
4.1 GEJVERAL .......................................................................................................................... 7

4.2 PRIMARY METERING PT AND CT INSTALLATION ................................................................. 8

4. 3 P RI1viARY METERING WIRING ............................................................................................. 8


4. 4 METER LOCATION AND LOOP ............................................................................................ 9
4. 5 CONTROL POWER lYfETERING .... ......................................................................................... 9
4. 6 P RI1viARY METER LocATION............................................................................................... 9
4. 7 METERING POTENTIAL TRANSFORMERS (P. T. 's) .............................................................. 10
4.8 METERING CURRENT TRANSFORMERS (C.T. 's) ................................................................. 10
5.0 RELAY/FUSE COORDINATION ............................................................................... 11
5.1 GENERAL ........................................................................................................................ 11

5.2 OVERCURRENT PROTECTION ........................................................................................... 11

6.0 MANUAL TRANSFER SCHEMES ............................................................................. 14


6.1 GENERAL ........................ :............................................................................................... 14

6. 2 KIRK KEY INTERLOCK ..................................................................................................... 14

SPECIFICATIONS & REQUIREMENTS Standard Revision


SUBMITTED FOR MULTIPLE & SINGLE PRIMARY
CE-10 1
METERED SERVICE
Lead SME: Date: 12/14
A.Su Sheet
meren 1 of 41
Electrical Distribution Design Standard
6. 3 ELECTRICAL LVTERLOCK.................................................................................................. 14

7.0 AUTOMATIC TRANSFER SCHEMES ...................................................................... 15


7.I GENERAL ........................................................................................................................ I5

7.2 PROGRAlvfl'viABLELOGIC CONTROLLERS (PLC's) .............................................................. I6

8.0 COMMISSIONING TESTS .......................................................................................... 17


9,0 DRAWING SUBMITTALS,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,oooooooooooooooooooooooooooool8

9.I ONE-LINE DRATVING ....................................................................................................... I8

9.2 THREE-LINEDRAWiiVG .................................................................................................... I8

9. 3 CONTROL SCHElvfATICS ................................................................................................... I8

9.4 PROTECTIVE RELAYING CONTROL SCHEMATICS ............................................................... I9

9.5 PHYSICAL DRAWINGS (ALL VIEWS-PLAN, FRONT & SIDE ELEVATIONS) ............................. I9

9. 6 BILL OF MATERIALS ........................................................................................................ I9

10.0 REFERENCE MATERIALS ......................................................................................... 19


11.0 ATTACHMENTS ............................... ,........................................................................... 19
II.2 PREFERRED-RESERVESUPPLY-ATTACHlvfENT I .............................................................. 22

II.3 TWO-FEEDER, SPLIT-BUSSUPPLY-ATTACHlv!ENT2 ........................................................ 28

II. 4 TWO-FEEDER PREFERRED, ONE-FEEDER RESERVE SUPPLY- ATTACHMENT 3 .................. 34

12.0 ACKNOWLEDGMENTS ............... ,............................................................................... 41


I2.I REVISION 0 (05/06) ......................................................................................................... 4I

I2.2 REVISION I (IOII4) ......................................................................................................... 4I

SPECIFICATIONS & REQUIREMENTS Standard Revision


SUBMITTED FOR MULTIPLE & SINGLE PRIMARY
CE-10 1
METERED SERVICE
Lead SME: Date: 12/14
A.Su Sheet
meren 2 of41
Electrical Distribution Design Standard
1.0 PURPOSE AND SCOPE
The following document describes Ameren's requirements for the installation of Switchgear and
Metering on its electrical distribution system (i.e., 4.16kV, 12.47kV, 13.2kV, 34.5kV, and
69kV). While these system voltages are noted they may not be all inclusive through out all of
Ameren.

It is recommended that approval be obtained from Ameren before a purchase is made. Without
full approval, expensive modifications may have to be made in order to receive service.
Switchgear that does not meet the following requirements and is not approved by Ameren will
not be energized or placed in service.

Ameren requires a total of five completed sets of drawings for the review and approval of
projects. The typical review time needed by Ameren personnel is one calendar month, however
this may vary based on workload. Insufficient submittals, insufficient details, not meeting the
specification, and submittals not being project specific may also impact the required review time.

2.0 DEFINITIONS AND ABBREVIATIONS


3.0 PRIMARY SWITCHGEAR REQUIREMENTS
3.1 Site Plan
Amm·en personnel require a ten-foot deep clearance in front of the main incoming cable
compartment door for purposes of grounding the incoming cables with an eight-foot hot stick.

A six-foot deep clearance is also required in front of the main line cubicle doors that provide
access to the main circuit breaker or switch.

The switchgear shall be physically located such that there are two means of egress from the front
and rear.

For interior switchgear locations, cable pulling eyes will be required. They shall be centered to
facilitate pulling in utility primary service cables to each cabinet. The pulling eye location and
elevation shall be coordinated with Ameren prior to installation.

Ameren requires 24/7/365 access to the switchgear.

If a ladder is required for any purpose one must be provided by the customer along with space
and provisions to securely store the ladder.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 3 of41
3.2 Main Disconnect
The main disconnect shall be electrically located on the "line side" of the metering compartment.
(i.e. Metering is Cold Sequence)

Each incoming line shall have its own gang operated visible disconnecting means. For example,
a rackable breaker, or a gang operated load break switch.

Each incoming line shall have its own fault current interrupting device. For example, a fuse or a
breaker with overcurrent relays.

Either a circuit breaker or a fused switch combination is acceptable as a main disconnect device.
If a circuit breaker is used, it must have a draw out I racking mechanism.

Circuit breakers rated 34kV and above shall be provided with a remote draw out I racking
mechanism.

Manually operated air insulated switchgear rated 34kV and above are not allowed.

3.3 Switchgear Doors


All incoming cable compartment doors shall be hinged with a three point latch. The doors shall
have pad-locking provisions. Opening the doors shall not require the removal of bolts of any
kind.

Non-sheltered aisle type switchgear shall have exterior doors on the incoming main disconnect I
breaker cubicles that are hinged with a three point latch. The doors shall have pad-locking
provisions. Gaining access to such cubicles shall not require the removal of bolts of any kind.

The main disconnect I breaker shall be capable of being opened and/or racked out with the
control panel door closed and latched. Having the main disconnect I breaker opened and racked
out shall not impede the closing of any control panel doors.

All PT drawers, control power transformer drawers, and control power transformer fuse truck
drawers shall be capable of being opened and racked off. Having the drawers in the extracted
position shall not impede the closing of any control panel doors. The door of the cubicle housing
the equipment shall be able to be fully closed while the equipment is in the fully rolled out or
racked out position.

Switchgear utilizing high-hat access doors shall be hinged to open directly opposite the pulling
eyes. The doors shall be removable and padlockable with provisions for a company seal. The

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 4 of 41
doors' swing shall be such that the door swing of one door shall not interfere with the access to
an adjacent door (opposite door swing).

3.4 Incoming Cable Compartment


All incoming cable compartments must have adequate cable-training space. There shall be a
minimum 36" vertical clearance between point of cable entry and point of cable termination.

The conduit entrance into all incoming cable compartments shall be physically aligned with the
connections to the associated bus work.

There shall not be any obstructions inside the incoming cable compartments that could adversely
affect the installation, termination or landing of the medium voltage cables.

The incoming cable compartments shall not house ground fault sensing current transformers
(GFCT) through which the incoming cables extend. GFCT's are not allowed in the incoming
cable compartments.

Thy incoming cable compartment shall include a cable support bar (non-conductive material),
located approximately half way between the cabinet floor and the main bus utility cable
termination lugs (Y-plane) and approximately the same distance from the rear door as the main
bus utility cable termination lug (X-plane).

Grounding Facilities

All incoming cable compartments shall have a 5/8" diameter x 4" long grounding stud rigidly
attached to each phase of the incoming line/bus. The grounding studs shall be suitable for the
attachment of a C-clamp style grounding clamp. Ameren does not use ball type grounding
clamps. For example, an AB-Chance model T600-2364 or similar type stud would be
acceptable. The AB-Chance model C600-2102 is not acceptable.

The ground studs in each cable compartment shall be oriented pointing upward in a vettical
orientation or in a horizontal orientation. The studs shall not point outward from the bus.

The ground studs in the incoming cable compartment sections shall be located such that they can
be reached from ground level.

Ground studs shall be located such that no connections are made above or near energized
components. Any modifications necessary, including protective barriers, to ensure that this
requirement is met will be at the customer's expense.

All incoming cable compartments shall have a minimum 17" long grounding stirrup or bail
suitable for Iandin three groundin clam s, i.e. one er hase. The roundin stirru /bail shall
SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision
Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 5 of 41
Electrical Distribution Desi n Standard
be situated such that three grounding clamps can be installed with sufficient space to allow the
cubicle door to be latched shut.

Lightning Arresters

Lightning arrestors connected to the incoming cable shall have connections that are removable
with a hot stick. This is typically accomplished by connecting the lightning arrestors to a ground
stud using flexible conductor and a hot line clamp. The grounding studs may be the same ones
as specified above.

Switchgear that is fed by Ameren circuits that are entirely underground do not require lightning
arrestors. Ameren prefers that these installations are installed without lightning arrestors to
expedite fault locating.

Potential and Control Power Transformers

No unmetered current-consuming device shall be connected on the line side of the primary
metering current transformers except those that are necessary for the operation of circuit
breakers.

No control power transformer greater than 15 kVA shall be installed on the line side of the
primary metering current transformers without Ameren approval.

All voltage or control power transformers connected to the line side of the main disconnect I
breaker shall be installed at a height not to exceed 6' to the bottom of the drawer or trunnion.

All PT drawers, control power transformer drawers, and control power transformer fuse truck
drawers connected to the line side of the main disconnect I breaker shall have static grounds that
will discharge and ground the equipment in the rolled out position.

All PT drawers, control power transformer drawers, and control power transformer fuse truck
drawers connected to the line side of the main disconnect I breaker shall permit isolation of
primary and secondary voltages without de-energizing service.

All PT drawers, control power transformer drawers, and control power transformer fuse truck
drawers connected to the line side of the main disconnect I breaker shall have a primary voltage
connector that is on a separate insulator mounted on the carriage with final connection by
flexible lead to PT's primary terminal. (i.e. the primary stab shall not be connected to the PT,
CPT, or Fuse holder)

Control power transformer drawers and control power transformer fuse truck drawers shall be
interlocked such that the drawer cannot be extracted while carrying load.
SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision
Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 6 of 41
Electrical Distribution Desi n Standard
3.5 Control Voltage
It has been Ameren's experience that customer owned batteries tend to be poorly maintained
creating a liability for the customer and Ameren. For this reason, Ameren recommends capacitor
trip units for the main and tie breakers.

m All capacitor trip units shall be approved by Ameren.


111
Each lockout relay and breaker trip coil shall have its own dedicated capacitor trip unit.
111
48V DC or 125V DC control voltage is permissible but not recommended.

When DC control voltage is used, the trip and close circuits shall be individually fused on each
breaker.

Battery maintenance is the customer's responsibility. Ameren reserves the right to check the
customer's batteries that power the switchgear's main overcurrent protection equipment. Lack
of DC power will prevent the breakers from performing their overcurrent protection. This is a
National Electric Code Violation and will be reported to the Authority Having Jurisdiction. The
inability of the batteries to perform their intended function will result in the de-energization of
the switchgear until repairs are made.

111 Breaker closing shall be AC controlled.

3.6 Switchgear Ratings


The customer must verify circuit breaker and switchgear fault-interrupting and fault-withstand
capability. Upon request, Ameren will provide minimum fault-interrupting and fault-withstand
capability, along with initial fault current levels.

The guideline for circuit breakers and switchgear in the Metropolitan St. Louis area is 30kA at
5kV with k=l (250 MVA) for 4 kV and 20kA at 15kV with k=l (500 MVA) for 12 kV.

In the Illinois areas this information will be provided by the respective division engineer

The switchgear shall meet the appropriate ANSI BIL ratings.

4.0 METERING REQUIREMENTS


4.1 General
The primary metering shall be cold sequence metering.

The primary metering compartment shall be a minimum of 36 inches wide.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 7 of41
The primary metering compartment shall have front and rear hinged doors. The doors shall have
three point latches with padlocking and sealing provisions. Opening the doors shall not require
the removal of bolts of any kind.

No customer equipment shall be allowed in or accessible from the metering compartment.

Compartment batTiers shall be provided such that access from adjacent customer compartments
is completely restricted.

Customer Equipment is not allowed in the metering PT or CT circuits.

4.2 Primary Metering PT and CT Installation


Ameren provided PTs and CTs shall be shipped to switchgear vendor for installation at the
factory.

Customer shall furnish the metering PT and CT shipping address to Ameren after the customer
notifies Ameren of the successful bidder.

4.3 Primary Metering Wiring


Factory wiring ofPTs and CTs shall include wiring from secondary terminals to a terminal strip
located inside the compartment front door.

CT Terminal strips for the metering circuits shall be "non-shorting" type.

Wiring shall be #12 A WG stranded copper, extra flexible switchboard hinge wire, 600 volt type
SIS insulation.

Each wire shall be identified and marked.

Metering CT's secondary terminals shall be wired ungrounded to the terminal strip.

Common CT non-polarity return shall not be acceptable.

Metering PTs secondary wiring shall extend from a sliding rigid contact at drawer to terminal
strip.

A Common ungrounded neutral voltage wire shall be utilized.

A single # 10 A W G stranded copper wire shall be extended from switchgear ground bus to
terminal strip.

A single #10 AWG stranded copper wire shall be connect the switchgear ground bus to the PT
drawer neutral. This is often a point of confusion for the switchgear vendor. Please note that
SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision
Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 8 of41
Electrical Distribution Desi n Standard
this wire must go from the ground bus directly to the metering PT neutral connection. It is in
addition to any PT drawer secondary stabs.

Terminal strip access shall be protected from primary components by protective barriers.

Note: For Ameren Illinois, Ameren employees shall install and wire the secondary side of the
CT's and PT's to the electric meter.

4.4 Meter Location and Loop


The installation contractor shall install continuous meter bundles provided by Ameren without
splices or termination. The meter bundles can be picked up by the customer's installation
contractor at the Dorsett Meter shop. In the Ameren Illinois areas, all primary metering is
installed by Ameren employees

The installation contractor shall install one Ameren provided meter enclosure for each set of
instrument transformers.

The metering wire loop shall be in conduit for the entire run from the metering compartment.
Liquidtite conduit in the switchgear cable tray is acceptable. The metering wire loop shall not be
placed in the cable tray without conduit protection.

4.5 Control Power Metering


If control power transformers are connected on the line side of the primary metering current
transformers and they also supply power to ancillary switchgear devices such as heaters, house
receptacles, etc., an Ameren-approved 200 A single phase three-wire clamp jaw meter socket
with a manually operated lever bypass, shall be installed in an approved location for purposes of
revenue metering.

The meter location should be approved by the metering supervisor before installation.

4. 6 Primary Meter Location


The primary meter location should be approved by the metering supervisor before installation.

Ameren shall approve meter enclosure location. It shall be within 50 ft of switchgear metering
compartment.

On indoor switchgear installations, the preferred location is for the meter(s) to be located on an
exterior wall that is readily accessible to Ameren personnel. An alternate location would be
outside of the switchgear equipment room.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 9 of41
Electrical Distribution Desi n Standard
On outdoor switchgear installations, the preferred location is for the meter(s) to be located on a
separate support structure outside of the substation. The location should be readily accessible to
Ameren personnel. An alternate location would be on the outside wall or end wall of the
switchgear.

4. 7 Metering Potential Transformers (P. T. 's)


3 phase to neutral (single fuse) or 2 phase to phase (dual fuse) types shall be provided and
shipped by Ameren.

Metering PT fuses will be provided by Ameren, but not shipped to factory.

Ameren owned and provided PTs shall be factory mounted on a draw-out carriage that will
provide complete accessibility for installation and removal ofPTs.

The following Draw-out Carriage requirements shall be met:

Permit isolation of primary and secondary voltages without de-energizing service.

Primary voltage connector shall be on a separate insulator mounted on the carriage with final
connection by flexible lead to PT' s primary terminal.

Shall have static ground to discharge PT in rolled out position.

On phase to neutral PTs, the primary neutral connection shall be connected to switchgear ground
using the carriage sliding contacts.

Secondary voltage shall be connected using sliding contacts.

4.8 Metering Current Transformers (C.T. 's)


Ameren owned, and provided metering CTs shall be factory mounted.

Mounting shall facilitate future replacement (CTs shall be mounted at a height and location such
that special means-such as ladders-shall not be required for future replacement).

Secondary terminals shall face access door.

Secondary terminals shall not be grounded.

Power cables shall not be connected directly to CTs.

Power cables shall be on separately supported bus work with bus bar connection to CTs.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12114
Electrical Distribution Desi n Standard 10 of 41
When two element metering is specified, fabricator shall provide and install removable bus bar
in center phase.

CT polarity shall be checked when installing on bus and must always face incoming bus.

5.0 RELAY/FUSE COORDINATION


5.1 General
Ameren shall review and approve all relays and relay settings on the main circuit breaker and
any tie or reserve circuit breakers.

Ameren will verify the customer has correctly set and calibrated the relays to the agreed upon
settings. Ameren reserves the right to witness the calibration of all relays by the customer's
relay tester, and/or verify the settings using Ameren test equipment. In some cases, Ameren may
request certified test reports for each of the main and/or tie relays.

Final relay acceptance by Ameren shall be based on the proposed schematics, relay style
numbers and settings. The customer shall submit proposed interfacing relay settings and style
numbers to Ameren for review. These relay guidelines may not apply to all situations.

Operating controls must be clearly marked and easy to identify and operate.

Please note that Ameren Missouri's phase rotation is CBA. Make sure that all47N relays and
customer metering are wired appropriately.

In Ameren Illinois, the phase rotation is provided by the respective division engineer.

5.2 Overcurrent Protection

Ameren shall review and approve all fuse sizes and types where they are used for main
protection.

The maximum fusing limits for the Metropolitan St. Louis area is listed below. Limits in other
service areas can be provided by Ameren on request. These are only guidelines and each
proposed installation must be checked for coordination with Ameren upstream relaying. A
circuit breaker may be required for larger loads.

Where fuses are used, customers shall keep a minimum of three spare fuses on the premises,
preferably inside the switchgear. Where electronic fuses are employed, spare control modules
shall be kept on the premises.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 11 of 41
MAXIMUM FUSING LIMITS FOR ST. LOUIS METRO AREA
4 kV 12 kV 13.8 kV 34kV
Max Fuse 300A 250A 250A 200A
Max S&C Electronic Fuse 600A 500A 500A

In the Illinois areas this is provided by the local engineering at the respective division locations.

Overcurrent Relays

All relays shall be draw-out type with built-in test provisions. All overcurrent relays shall be
self-powered single phase relays. There shall be a minimum of three phase relays and one
neutral relay per incoming line. This provides N+ 1 relay redundancy for phase faults.

Ameren will allow multi-phase microprocessor relays if they are backed up by a set of single
phase self-powered single phase relays, as described above, or a second redundant
microprocessor relay is installed on each incoming line breaker. Each microprocessor relay shall
be installed with separate external test switches (ABB Flexitest).

Relays powered from AC station service are not allowed.

Examples of acceptable relays are:

Device 50/51

ABBCO
ABB MICR0-51/FT (MICR0-51 without the "FT" is not acceptable)
Basler BE1-50/51B
GEIAC
GEDIACA5B

Device 32

ABBCW
Basler BE1-32R

Device 59N

ABBSV

Device 59NX auxiliary

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 12 of 41
Electrical Distribution Desi n Standard
ABB TD-5

Device 67

Basler BE 1-67

Overcurrent Lockout Relays

All fault-sensing relays on the incoming line breakers and tie breakers shall trip a lockout relay.

The lockout relay shall trip and block closing of its associated main.

The lockout relays are required to trip on non-clearing faults.

The lockout relays shall prevent the closing of the reserve main breaker/switch or tie
breaker/switch into a fault.

The lockout relays shall provide this functionality in automatic and manual transfer modes of
operation. This shall apply with or without main incoming fuse protection.

Loss of Voltage Lockout Relays

Ameren does not recommend loss of voltage lockout relays, as they can lead to operating errors
and unnecessary outages.

Transformer Top Oil Lockout Relays

In the cases where the primary switchgear is served directly from an Ameren-owned substation
transformer, Ameren requires the installation of a transformer top oil over temperature lockout
relay. The transformer top oil lockout relay shall trip and block closing of its associated main
breaker.

Ameren will provide one set of dry contacts from the substation transformer top oil temperature
relay to trip the lockout relay. This lockout relay shall be solely dedicated for operation by the
transformer top oil temperature relay.

The transformer top oil lockout relay shall operate in either automatic or manual transfer modes.

When capacitor trip units are used, each lockout relay and breaker trip coil shall have its own
dedicated capacitor trip unit.

The transformer top oil lockout relay shall not block closing of a tie breaker or a reserve main
breaker.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 13 of 41
Electrical Distribution Desi n Standard
In switchgear that has automatic transfer capability, the top oil lockout relay shall initiate a
transfer to the alternate source when in automatic mode.

The transformer top oil lockout relay shall turn on an AC powered audible horn I buzzer to alert
personnel that the lockout relay has tripped.

6.0 MANUAL TRANSFER SCHEMES


6.1 General
Manual transfer switchgear shall have a mechanical or electrical interlocking scheme to prevent
the paralleling of incoming supplies by the customer. The scheme shall force the customer to
perform open transition switching between the incoming supplies.

Under Ameren's supervision, spare kirk keys may be utilized or the electrical interlocks may be
disabled by a 43 switch to perform closed transition switching between incoming supplies in
order to perform switching without causing an outage to the customer. Ameren will not allow a
scheme that does not allow for closed transition switching under Ameren's supervision.

Turning a control switch on a main or tie breaker/switch to the trip position shall directly trip the
breaker. This shall not be dependent on the position of any other control switches or interlocks.
In Ameren Illinois all transfer schemes are reviewed on an individual basis.

6.2 Kirk Key Interlock


If the interlock scheme is a kirk-key arrangement a spare key is required. All spare kirk-keys
shall be kept under Ameren's exclusive control. Typically Ameren will provide a lock box for
installation on the switchgear. The spare kirk keys will be stored in the lock box and secured
with an Ameren padlock. Ameren will utilize the spare kirk keys to perform closed transition
switching between incoming supplies without causing a customer outage.

6.3 Electrical Interlock


The customer shall provide a hard wired key lockable 43 switch. The switch shall be lockable in
the Normal position. The key shall be removable in the Normal and Parallel positions.
Typically Ameren will provide a lock box for installation on the switchgear. The 43 switch keys
will be stored in the lock box and secured with an Ameren padlock.

When the 43 switch is in the Normal position, the electrical interlock scheme shall be hard wired
to prevent the paralleling of the incoming supplies. It shall force open transition switching
between the incoming supplies.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 14 of 41
When the 43 switch is in the Parallel position, the electrical interlock scheme shall allow the
paralleling of the incoming supplies. Each control switch shall have complete control over the
trip and close operations of its associated breaker/switch. Ameren will not allow a scheme that
does not allow for closed transition switching under Ameren's supervision.

Under Ameren's supervision, the 43 switch may unlocked and placed in Parallel to perform
closed transition switching between incoming supplies in order to switch between supplies
without causing a customer outage.

It is the customer's responsibility to provide for single phasing protection. The protection should
protect the customer for the loss of any one, two, or three phases. Ameren recommends using a
negative sequence voltage relay and under voltage relays for this functionality (27 I 47N). In
addition, the relaying should prevent transferring to a reserve feeder that is single phasing.

7.0 AUTOMATIC TRANSFER SCHEMES


7.1 General
A 43 AIM (Automatic/Manual) selector switch shall be installed that will disable the automatic
scheme and allow manual operation. Ameren prefers that just one Auto/Manual control switch
be used to control the automatic scheme for the main incoming lines and bus ties.

The 43 AIM switch shall have a handle that can be key-locked in either the automatic or manual
position. The key shall be removable in the automatic and manual position.

The customer shall not possess any of the 43 AIM key or any copies. The keys will be secured
in a lock box mounted near the 43 AIM switch. Only Ameren will have access to the keys.

The 43 AIM switch shall be mounted on the door of either the main breaker/switch cubicle or the
tie breaker/switch cubicle.

The 43 AIM switch shall be a two-position switch labeled "Auto" and "Manual" for all
arrangements except the Preferred-Reserve arrangement, in which case the switch will be a
three-position switch labeled "Preferred 1", "Manual" and "Preferred 2".

The main breaker/switch and tie breaker/switch control switches shall be wired into the
automatic transfer scheme so that if a main or tie breaker/switch does not have a red target on the
control switch, the automatic transfer scheme will be disabled.

The main breaker/switch and tie breaker/switch close circuit shall have a control switch normal
after close contact in the automatic control string to prevent automatic operation when its

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 15 of 41
associated control switch has a green target. This shall be accomplished by wiring a control
switch normal after close contact in series with the automatic close control path.

When the 43 AIM switch is in the "manual" position all automatic operations shall be disabled.
The control switch shall directly trip and close the breaker/switch. Ameren will not allow a
scheme that does not allow for closed transition switching under Ameren's supervision.

When the 43 AIM switch is in the "manual" position the main and tie breaker/switch control
switch shall have complete control over their associated breaker/switch. They shall not be
interlocked in any way, with the exception of the lockout relays.

Turning a control switch on a main or tie breaker/switch to the trip position shall trip the
associated breaker/switch and block automatic operation. This shall not be dependent on the
position of any other control switches or interlocks.

It is the customer's responsibility to provide for single phasing protection. The protection should
protect the customer for the loss of any one, two, or three phases. Ameren recommends using a
negative sequence voltage relay and under voltage relays for this functionality (27 I 47N). This
condition should initiate a transfer to a reserve supply. In addition, the relaying should prevent
transferring to a reserve feeder that is single phasing.

Please refer to the appropriate attachment for additional automatic transfer requirements,
depending on the configuration ofthe installation:

111 Single Supply- Attachment 1


111 Preferred-Reserve Supply- Attachment 2
111 Two-Feeder, Split-Bus Supply- Attachment 3
111 Two-Feeder Preferred, One Feeder Reserve Supply- Attachment 4

7.2 Programmable Logic Controllers (PLC's)


Amm·en will allow the use ofPLCs for automatic transfer control logic with the following
requirements:

All of the automatic transfer requirements listed above apply to PLC installations.

In automatic mode the circuit breaker close and trip circuits shall be directly controlled by hard-
wired auxiliary contacts of the associated breaker. i.e. hard wired auxiliary contacts from the
main and tie breaker/switch will break up condition that parallels two incoming lines. Software
contacts are not acceptable.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 16 of 41
Electrical Distribution Desi n Standard
In manual mode, the control switch contacts for tripping and closing shall be wired directly into
the trip and close circuits of the main and tie circuit breakers. Software contacts are not
acceptable.

A hard-wired breaker auxiliary contact scheme be incorporated that will prevent a long-term
paralleling condition of the incoming supply circuits. Software contacts are not acceptable. If a
time delay in this backup scheme is required, the time delay shall be minimal. The time delay
range and setting must be reviewed and approved by Ameren. The timer shall be a discrete timer
that is not part of the PLC. PLC timer functions are not allowed in this circuit. If a time delay
longer than 1 second is required, contact Ameren for additional relaying requirements.

In the course of its normal operations, Ameren will occasionally have reason to place the
switchgear in manual mode in order to perform switching. Typically this will involve a transfer
of load from one incoming supply to another via temporary parallel operation. Ameren prefers
to restore the initial/normal conditions with the closed transitioning of supplies under automatic
operation. Ameren will place the 43 AIM switch in automatic, and then bring up a red target on
the open main or tie breaker/switch. This shall initiate a closed transition return to normal.
Please explain in detail how this interface will be done.

The PLC shall not lose power at any time as a direct result of automatic transfer switching
operations. This will be confirmed during Ameren's functional test of the switchgear. If an UPS
is used to maintain power to the PLC, it is the customer's responsibility to maintain the batteries
and perform periodic testing. Ameren's experience with these installations has been problematic.

Customer PLCs used for transfer between Ameren and customer generation must be backed up
by an independent hardwired breaker auxiliary contact scheme. The independent hardwired
breaker auxiliary contact scheme prevents and/or breaks up a condition in which the customer
generation is in parallel with the Ameren system. Additional requirements for customer
generation are covered in a separate Ameren specification which the customer must request if
planning to install generation.

8.0 COMMISSIONING TESTS


Ameren will perform a full functional test and inspection of all primary switchgear to verify that
all Ameren requirements have been met prior to switchgear being energized and placed in
service.

Prior to testing the customer shall provide a set of as built drawings to the appropriate Ameren
representative performing the test.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 17 of 41
A switching truth table and/or written operating guide is required to confirm the proper
automatic transfer operation.

The functional test shall consist of a verification of adherence to this document. It will include,
but not be limited to the following checks:

ill Loss of three phase potential to each supply circuit independently


ill Loss of a single phase potential to each supply circuit independently
ill Loss of potential to all supply circuits simultaneously
ill Lockout operation
ill Phase checks
ill Interlock verification
ill Control switch operations
ill Transfer operation checks
ill Grounding provisions
ill Meter location and installation
ill Switchgear construction
ill Locking provisions
ill Operating controls

9.0 DRAWING SUBMITTALS


9.1 One-Line Drawing
The one-line drawing shall include the main circuit breaker, revenue metering CTs and PTs, and
the related information. regarding the customer's "downstream" system that aids in defining the
type of connection required. The one-line shall be up to date and consistent with the additional
information listed below.

9.2 Three-Line Drawing


The three-line drawing shall include proposed connections of all current and/or potential
transformers to the protective relays and revenue metering, in addition to the primary bus
connections. This is especially important where differential, directional overcurrent, or
directional power relays are utilized.

9.3 Control Schematics


Detailed schematics ofthe main breaker/switch trip and close control circuits are required.
These schematics shall show all protective relay functions as well as any control functions
including automatic transfer logic. The customer shall also provide trip and close control circuit
schematics for any feeder breakers/switches or bus tie breakers/switches.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 18 of 41
9.4 Protective Relaying Control Schematics
Schematics that would be necessary to analyze and document the protective relaying scheme
used are required. (Note: This may or may not be completely covered on the breaker control
schematics.)

9.5 Physical Drawings (All Views-Plan, Front & Side Elevations)


Drawings showing the physical construction and layout of the switchgear, details of metering
compartment, cable compartment with ground studs, and control power transformer locations are
required.

9.6 Bill of Materials


A Bill of Materials that includes relay style numbers and/or ranges, current transformer ratio,
lightning arrester catalog numbers, etc.

10.0 REFERENCE MATERIALS


• ANSI/IEEE Device Numbers and Acronyms

11.0 ATTACHMENTS
11-1 Single Supply Using Main Breaker

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 19 of 41
Electrical Distribution Desi n Standard
Attachment 1

Supply Source

SINGLE LINE SUPPLY


MAIN CIRCUIT BREAKER

Figure 1

11-2 Single Supply Using Fused Switches

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 20 of 41
Attachmont 1
);(-~,..,.
~::f.liFH~l

$ ~:f::;:!:n ( ~~~~:!:
9 ~~:~to~: 1> Supply Source
~ ~~~:~!i~~n ~~·ltrn;"~tf
0 ~;:;'l~~;tl

SINGLE LINE SUPPLY


MAIN LOAD BREAK SWITCH-FUSE COMSINA110N

Figurlill2

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 21 of 41
11.2 Preferred-Reserve Supply -Attachment 1
The automatic transfer facilities shall be equipped with proper relays and controls, including
undervoltage and loss of phase indication on each incoming line, designed and connected so that
they will operate in the following manner:

A lockable three-position selector switch shall be provided. Either of the two lines may be
selected as the "Preferred" line by means of a three (3) position selector switch labeled: #1
Preferred, Manual, and #2 Preferred. The "Manual" position is to be in the middle. Selector
switch must be lockable and the key removable in all positions.

The selection of the preferred feeder shall be accomplished without rewiring the control.

The control shall be symmetrical between the two lines. Reference to either line should apply
conversely to the other.

In the case of a bus fault, the overcunent relays shall trip a lockout relay. The lockout relay shall
trip its associated main and prevent closing of the preferred and reserve mains.

The lockout relay must be reset by hand before either breaker can be closed.

Equipment shall transfer on loss of one, two, or three phases.

Automatic Mode

When the selector switch is in either of the preferred positions, the respective line will then be
the preferred line and the system will be set up so that it will operate as indicated in the
following table.

The voltage condition "Hot" is defined as normal, balanced, three-phase voltage. The voltage
condition "Dead" is defined as any condition where one, two or three phases have an
undervoltage condition.

The control switch handle on each breaker/switch will have control over its associated breaker
for opening operations. Each control switch will have suitable contacts arranged so that tripping
by either incoming line control switch handle will disable automatic closing of both line breakers
until the breaker's control switch is turned to the "closed" position (red target).

For automatic operation, both incoming mains shall have red targets on their control switches
and the automatic mode selector switch shall be in either the Preferred 1 or Preferred 2 position.

In automatic mode, the control switch shall allow closing of an incoming line breaker/switch
only when both incoming line breakers/switches open.
SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision
Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE
~ Sheet
12/14 'Ameren 22 of 41
Electrical Distribution Desi n Standard
Manual Mode

When the selector switch is moved from either preferred position to the manual position, each
circuit breaker comes under the control of its respective control switch handle and will be
operated in the following manner:

Each of the circuit breakers will remain in the same position (either open or closed) until its
respective control switch handle is operated to change its position.

The control switch handle on each breaker will have complete control over its associated
breaker, permitting paralleling of supplies for closed transition switching, as well as testing
operations.

When the selector switch is moved from line one preferred position through the manual position
to line two preferred position, the line two breaker will automatically close after which the first
breaker will automatically open (closed transition).

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 23 of 41
Electrical Distribution Desi n Standard
11-3 Attachment 1

ORIGINAL CONDITIONS
Line # 1 Preferred - Line #2 Reserve
Breaker
Position Voltage
Line Line Line Line
Case #1 #2 #1 #2 Change Requirement
1 c 0 Hot Hot Line #1 Line # 1 opens after time delay and Line
Dead #2 closes (open transition)
2 c 0 Hot Hot Line #2 No change
Dead
3 c 0 Hot Hot Both Dead No change
Simultaneously
4 c 0 Hot Dead Line #1 No change
Dead
5 c 0 Hot Dead Line #2 No change
Hot
6 0 c Dead Hot Line #1 Line # 1 closes after time delay and Line
Hot #2 opens (closed transition)
7 0 c Dead Hot Line #2 No change
Dead
8 c 0 Dead Dead Line #1 No change
Hot
9 c 0 Dead Dead Line #2 Line # 1 opens after time delay and Line
Hot #2 closes (open transition)
10 c 0 Dead Dead Both Hot No change
Simultaneously
11 0 c Dead Dead Line #1 Line #2 opens after time delay and Line
Hot # 1 closes (open transition)
12 0 c Dead Dead Line #2 No change
Hot
13 0 c Dead Dead Both Hot Line #1 closes after time delay and Line
Simultaneously #2 opens (closed transition)
C=Closed O=Open

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 24 of 41
Electrical Distribution Desi n Standard
11-4 Preferred-Reserve Supply Main Circuit Breaker Automatic Transfer

Att<lchment·J

PREFERRED RESERVE
LINE LINE

PREFERRED-RESERVE SUPPLY
MAIN CIRCUIT BREAI<ER
AUTOMATIC TRANSFER

Figure '1

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 25 of 41
11-5 Prefened-Reserve Supply Main Load Break Switch- Fuse Combinations
Automatic or Manual Transfer

A tt<lchm ent ·J

PREFERRED RESERVE
LINE LINE

NOTE:
1.1nte:rlook for Man!Jal Transfer Scheme
2.No interlock for Automatic Transfer
IHTERL OCK

PREFERRED-RESERVE SUPPLY
MAIN LOAD BREAK SWITCH -FUSE COMBINATIONS
AUTOMATIC OR MANUAL TRANSFER

Figure 2

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12114
Electrical Distribution Desi n Standard 26 of 41
11-6 Breaker Schematic

M2

I il
MAN
:ill.
Ml L
11
M2 I I 43
M2

52CS-Mt Tronsfer
I g ~~:t1-U

1~j
c M1

I I
Logic T

Ddl. 52CS·M1 g
M" - M2
NAC

J
52CS-M1

NAG
!!_Q. -
Breaker M1
52CS-M2
NAC

:~
M2

cc TC

4~ I I
M2I M1I I
_L 43
43 11
MAN
11
Ml T M2 I I M1

Transfer
Login
Transfor

L~Lo ~
W"'-~1
c
TransfDr
Log!G I g
M1
52CS·M2
r

~MZ.
g\
Ml ,
52CS-Ml
NAG
52CS-M2
I -
g
M2

NAG Breaker M2 NAG


L
rui
Mt

ll§_
M2

TC

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 27 of 41
11.3 Two-Feeder, Split-Bus Supply -Attachment 2
The automatic transfer facilities shall be equipped with proper relays and controls, including
undervoltage and loss of phase indication on each incoming line, designed and connected so that
they will operate in the following manner:

A lockable two-position automatic/manual selector switch shall be provided. The selector switch
must be lockable and the key removable in all positions.

The control shall be symmetrical between the two lines. Reference to either line should apply
conversely to the other.

In the case of a bus fault, the overcurrent relays shall trip a lockout relay. The lockout relay shall
trip its associated main and prevent closing of the tie breaker/switch.

The lockout relay must be reset by hand before either breaker can be closed.

Equipment shall transfer on loss of one, two, or three phases.

Automatic Mode

When the selector switch is in the automatic position, the system will be set up so that it will
operate as indicated in the following table.

The voltage condition "Hot" is defined as normal, balanced, three-phase voltage. The voltage
condition "Dead" is defined as any condition where one, two or three phases have an
undervoltage condition.

The control switch handle on each breaker/switch will have control over its associated breaker
for opening operations. Each control switch will have suitable contacts arranged so that tripping
by either incoming line control switch handle will disable automatic closing of both line breakers
until the breaker's control switch is turned to the "closed" position (red target).

For automatic operation, both incoming mains and tie shall have red targets on their control
switches and the automatic mode selector switch shall be in the automatic position.

In automatic mode, the control switch on a main breaker/switch shall allow closing of a main
breaker only when the tie breaker is open.

In automatic mode, the control switch on the tie breaker/switch shall allow closing of the tie
breaker only when one or both mains are open.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 28 of 41
Electrical Distribution Desi n Standard
Each control switch will have suitable contacts arranged so that tripping by either incoming line
control switch handle will disable automatic closing of that line breaker and the tie breaker until
that breaker's control switch is turned to the "closed" position (red target).

The tie breaker/switch control switch will have suitable contacts arranged so that tripping by the
control switch handle will disable automatic closing of the tie breaker until the tie breaker's
control switch is turned to the "closed" position (red target).

In no case should a line breaker be tripped on loss of voltage unless an adjacent line has normal
voltage and automatic transfer can be made.

For automatic operation, both incoming mains and the tie shall have red targets on their control
switches and the automatic mode selector switch shall be in the automatic position.

Manual Mode

When the selector switch is placed in the manual position, each circuit breaker comes under the
control of its respective control switch handle and will operate in the following manner:

Each of the circuit breakers will remain in the same position (either open or closed) until its
respective control switch handle is operated to change its position.

The control switch handle on each breaker will have complete control over its associated
breaker, permitting paralleling of supplies for closed transition switching, as well as testing
operations

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 29 of 41
Electrical Distribution Desi n Standard
11-7 Attachment 2

ORIGINAL CONDITIONS
(Line # 1 Preferred - Line #2 Preferred)
Breaker Position Voltage
Line Bus Line Line Line
Case #1 Tie #2 #1 #2 Change Requirement
1 c 0 c Hot Hot Line #1 Line # 1 breaker opens after time
Dead delay and bus tie closes (open
transition)
2 c 0 c Hot Hot Both Dead No change
Simultaneously
3 c 0 c Dead Dead Both Hot No change
Simultaneously
4 c 0 c Dead Dead Line #1 Line #2 breaker opens after time
Hot delay and bus tie closes (open
transition)
5 0 c c Dead Hot Line #1 Line # 1 breaker closes after time
Hot delay and bus tie opens (closed
transition)
6 0 c c Dead Hot Line #2 No change
Dead
7 0 c c Dead Dead Line #1 Line #2 breaker opens after time
Hot delay and Line # 1 breaker closes
(open transition)
8 0 c c Dead Dead Line #2 No change
Hot
9 0 c c Dead Dead Both Hot Line # 1 breaker closes after time
Simultaneously delay and bus tie opens (closed
transition)
C=Closed O=Open

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 30 of 41
11-8 Two Feeder, Split-Bus Supply Main Load Breaker Switch- Fuse Combination
Manual Transfer

A tt il chIll e 11 t 2

PREFERRED PREFERRED
LINE #'I LINE #2

___]_----< M

TW 0 FEEDER, SPLIT-BUS SUPPLY


MAIN L 0 AD B R E A K SWITCH - F U S E C 0 M B IN AT 10 N S
MANUAL TRANSFER

F i tJ tHe ·J

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 31 of 41
11-9 Two Feeder, Split-Bus Supply Main Circuit Breaker Automatic Transfer

Attachment 2

PREFERRED PREFERRED
LINE#l LINE#2

T W 0 FE E DE R • S P LIT -B U S S U P P L Y
M A IN C IR C U IT B REA K E R
AUTOMATIC TRANSFER

Figure 2

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 32 of 41
11-10 Breaker Illustration

~----~ 8:l ~-~


·:g;··
M1 M2
TIE

1~

43AIM
I
AUTO
Transfer
I I
MAN
43AIM
AUTO I
Logic
52CS
NAC -
52CS
c
Transfer
Lonlc
52CS
I 52CS
T

Breaker M1 NAC
(M2 similar}

l 43NM
I 43AjM
AUTO
§2_ lTransfer

I 5:C~:I
c I
M1

52
Logic

52CS - 52CS
TIE NAC - T
52
M1
I g
M2
52CS
NAC ·
Tie Breaker

M1

~t
TC
~

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 33 of 41
Electrical Distribution Desi n Standard
11.4 Two-Feeder Preferred, One-Feeder Reserve Supply -Attachment 3
The automatic transfer facilities shall be equipped with proper relays and controls, including
undervoltage and loss of phase indication on each incoming line, designed and connected so that
they will operate in the following manner:

A lockable two-position automatic/manual selector switch shall be provided between each


preferred feeder circuit breaker and the tie circuit breaker to the common reserve feeder. The
selector switches must be lockable and the key removable in all positions.

In the case of a bus fault, the overcurrentrelays shall trip a lockout relay. The lockout relay shall
trip its associated main and prevent closing of the tie breaker/switch.

The lockout relay must be reset by hand before either breaker can be closed.

Equipment shall transfer on loss of one, two, or three phases.

Automatic Mode

When the selector switch is in the automatic position, the system will be set up so that it will
operate as indicated in the following table.

Either preferred line breaker will be considered as the Line # 1 breaker, the associated reserve tie
breaker will be considered as the Line #3 breaker.

The voltage condition "Hot" is defined as normal, balanced, three-phase voltage. The voltage
condition "Dead" is defined as any condition where one, two, or three phases have an
undervoltage condition.

The breakers must be electrically interlocked through the use of hard wired breaker auxiliary
contacts to prevent closing both reserve breakers simultaneously.

The control switch handle on each breaker/switch will have control over its associated breaker
for opening operations. Each control switch will have suitable contacts arranged so that tripping
by either incoming line control switch handle will disable automatic closing of the incoming line
breaker and the tie breaker until the breaker's control switch is turned to the "closed" position
(red target).

For automatic operation, the incoming mains and its associated tie shall have red targets on their
control switches and their automatic mode selector switch shall be in the automatic position.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12114 meren 34 of 41
Electrical Distribution Desi n Standard
In automatic mode, the control switch on a main breaker/switch shall allow closing of a main
breaker/switch only when its associated tie breaker/switch is open.

In automatic mode, the control switch on the tie breaker/switch shall allow closing of the tie
breaker/switch only when its associated main is open and both tie breaker/switches are open.

Each control switch will have suitable contacts arranged so that tripping by either the incoming
line control switch handle or its associated tie control switch will disable automatic closing of
that line breaker and the tie breaker until that breaker's control switch is turned to the "closed"
position (red target).

For automatic operation, the incoming main and its associated tie shall have red targets on their
control switches and the automatic mode selector switch shall in the automatic position.

The tie breaker/switch control switch will have suitable contacts arranged so that tripping by the
control switch handle will disable automatic closing of the tie breaker until the tie breaker's
control switch is turned to the "closed" position (red target).

In no case should a line breaker be tripped on loss of voltage unless an adjacent line has normal
voltage and automatic transfer can be made.

Manual Mode

When the selector switch is placed in the manual position, each circuit breaker comes under the
control of its respective control switch handle and will operate in the following manner:

Each of the circuit breakers will remain in the same position (either open or closed) until its
respective control switch handle is operated to change its position.

The control switch handle on each breaker will have complete control over its associated
breaker, permitting paralleling of two supplies for closed transition switching, as well as testing
operations. At no time should it be possible to parallel all three supplies.

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 35 of 41
Electrical Distribution Desi n Standard
11-11 Attachment 3

ORIGINAL CONDITIONS
(Line #1 Preferred and #2 Preferred- Line #3 Reserve)
Breaker Position Voltage
Line Line Line Line
Case #1 or #2 #3 #1 or #2 #3 Change Requirement
1 c 0 Hot Hot Line 1 or 2 Dead Line 1 or 2 breaker opens after
time delay and Line 3 breaker
closes (open transition)
2 c 0 Hot Hot Line 3 Dead No Change
3 c 0 Hot Hot Both Dead Simultaneously No Change
4 c 0 Dead Dead Both Hot Simultaneously No Change
5 c 0 Dead Dead Line 1 or 2 Hot No Change
6 c 0 Dead Dead Line 3 Hot Line 1 breaker opens after time
delay and Line 3 breaker closes
(open transition)
7 c 0 Hot Dead Line 1 or 2 Dead No Change
8 c 0 Hot Dead Line 3 Hot No Change
9 0 c Dead Hot Line 1 or 2 Hot Line 1 or 2 breaker closes after
time delay and Line 3 breaker
opens (closed transition)
10 0 c Dead Hot Line 3 Dead No Change
11 0 c Dead Dead Line 1 or 2 Hot Line 3 breaker opens after time
delay and Line 1 or 2 breaker
closes (open transition)
12 0 c Dead Dead Line 3 Hot No Change
13 0 c Dead Dead Both Hot Simultaneously Line 1 or 2 breaker closes after time
delay and Line 3 breaker opens
(closed transition)
C=Closed O=Open

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1

Sheet
12/14
Electrical Distribution Desi n Standard 36 of 41
11-12 Two Feeder Preferred, One Feeder Reserved Supply Main Circuit Breaker
Automatic Transfer

A tt ::~ c h m e n t 3

I •''"";"
l'U< ~f'h''-'
( 1<~<h

f
RESERVE
LINE #3

PREFERRED PREFERRED
LINE #'I LINE #2

fV1

TWO FEEDER PREFERRED. ONE FEEDER RESERVED SUPPLY


MAIN CIRCUIT BREAKER
AUTOMATIC TRANSFER

Figure ·r

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1

Sheet
12/14
Electrical Distribution Desi n Standard 37 of 41
11-13 Two Feeder Preferred, One Feeder Reserved Supply Main Load Break Switch-
Fuse Combination Manual Transfer

RESERVE
LINE ~ ~

PREFERRED
LINE #1

TWO FEEDER PREFERRED, ONE FEEDER RESERVED SUPPLY


MAIN LOAD BREAK SWITCH- FUSE COMBINATION
MANUAL TRANSFER

Figure 3

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 38 of 41
11-14 Two Feeder Preferred, One Feeder Reserved Supply Main Circuit Breaker
Automatic Transfer

Athchm ent 3

RESERVE
LINE #3

PREFERRED PREFERRED
LINE #1 LINE #2

TWO FEEDER PREFERRED, ONE FEEDER RESERVED SUPPLY


MAIN CIRCUIT BREAI~ER
AUTOMATIC TRANSFER

Figure 2

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 39 of 41
Electrical Distribution Desi n Standard
11-15 Breaker Illustration

P2

~--------------------~:w

:tUl
I
43·1
AUTO
Tmnsfer
r·.
AUTO

Transfer .
Logic I I "C'·"
T

Logic I 52CS-R1
NAC
§£9.,!?:£1
NAG
Breaker P1
{P2 Similad

52TOC/" m Truck Oparated Conlflct


Closed when breoker is rocked on bus

-~~~r
5ZTc)C
P1

mQ£
52;~ r Logi~
§£-
R1
52TOC
1 I- 52C~-R1
R2 R1

Breaker R1
(R2 Similar)
~
Ni\C I
~
Ni\C

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14
Electrical Distribution Desi n Standard 40 of 41
12.0 ACKNOWLEDGMENTS
12.1 Revision 0 (05/06)
Contributing SME ......................................................................................................... Rob Duncan

12.2 Revision 1 (10114)


Approving Sponsor (IL) ................................................................................................ Rick Welton

Approving Sponsor (MO) ............................................................................................ Steve Brophy

Delegate (IL) ................................................................................................................. Rod Hilburn

Delegate (MO) .............................................................................................................. Rob Duncan

Lead SME ....................................................................................................................... Andy Sugg

Contributing SME ............................................................................................................ Bob Zuege

Contributing SME ....................................................................................................... John Shewski

Contributing SME ............................................................................................................. Bob Dodd

Contributing SME ............................................................................................... Rob Rauschenbach

Contributing SME ........................................................................................................... Wendy Wu

SPECIFICATIONS AND REQUIREMENTS FOR Standard Revision


Date MULTIPLE & SINGLE PRIMARY METERED
CE-10 1
SERVICE

Sheet
12/14 meren 41 of 41
Electrical Distribution Desi n Standard
THIS PAGE INTENTIONALLY LEFT BLANK
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

SECTION 261327- 15kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS

ATTACHMENT B

Ameren Missouri Document CO for Category 1 - Open Transition

15 kV METAL-CLAD SWITCHGEAR CONTROL MODIFICATIONS 261327 ATTACHMENTB -1


THIS PAGE INTENTIONALLY LEFT BLANK
Date: January 23, 2012

Document
-co
Use for:

Connection of Electric Generation


that will operate with an
Open Transition (Category 1) between the Ameren System and
the Generator
or operate with a
Synchronized Closed Transition (Category 2) between the
Ameren System and the Generator of Less than 100
Milliseconds

• •. ·Following is the cover letter, connection request form, and technical


requirements for generators. that operate in either an open transition
· with Ameren or a synchronized closed transition with Ameren for a
duration of less than 100 milliseconds.

• Note that no connection agreement is required.

. • · There is. no generator size limitation for this type of connection.

• Press F 11 to enter information into the gray boxes.

1
THIS PAGE INTENTIONALLY LEFT BLANK
~-- -------~~-~~----~~ -~--~--~ --

Joe Bates
Bates Electric
2006 Sierra Parkway, Arnold, Mo. 63010 ~ .

f.
Re: Generator installation
~

Dear Joe: i

Thank you for contacting Ameren regarding your plans to connect backup generation I
located at 10695 Bellefontaine rd.. The attached documents reflect the process for II
connecting generation that falls under one of two categories: ,,

)> A Category 1 generator only operates when there is an open transition between I
the Ameren electric system and the generator. I.
I
I
~- A Category 2 generator operates with a synchronized closed transition between
the Ameren electric system and the generator for no' more than 100 milliseconds.

Generally, Ameren requires. that customers interconnecting their electric generator to the I
electtic distribution system fund an interconnection study performed by Ameren and then
. enter into an interconnection agreement regarding the design, operation and testing of the
interconnection facilities. However, Ameren will not require generators falling under
one of the two categories above to fund. such a study or enter into an interconnection
agreement, provided the equipment owner ("Customer") abides by the conditionS and
requirements outlined in the following two documents; both attached hereto:

)> Generator Connection Request Form (Section E) -Outlines the requirements


regarding the use, testing and documentation of the generator installation; and

>·· Specifications and Requirements for the Connection of Electric Generation-


Outlines the operating requirements of the generator installation and associated
transfer switch equipment.

In addition, Amere:n. will not impose its standby service tariff on the Customer if the
generator unit is installed for emergency operation and the time duration of the closed
transition is less than 100 milliseconds.

The Customer must submit the documentation required as soon as available. Upon
receiving this information from the Customer, Ameren will review and provide any
applicable comments to the Customer. Comments from Ameren may require
modifications and resubmission of the documentation.

1
I
[
In order to formally begin the connection process, the Customer must submit the
completed Generator Connection Request Form attached hereto.

We are available to meet either at the generator site or at one of our central or division
offices to discuss your project prior to beginning the application and approval process.
This will allow us to become more familiar with your generation plans and allow you to
present any questions or concerns you may have.

Please direct all inquiries to:


Brad Youngberg
Ameren Corporation
MC655
6440 N. Hanley rd.
Berkeley, Mo. 63134

Or you can contact me at 314 992-8609 if you have any questions.

We look forward to working with you on this project.

Sincerely,

Brad Youngberg

2
Generator Connection Request Form
for the
Connection of Electric Generation
that will operate with an
Open Transition (Category 1) between the Ameren System and
the Generator
or operate with a ·
Synchronized Closed Transition (Category 2) between the
Ameren System and the Generator of Less than 0.1 Seconds

A. Customer Information
Name: Bellfontaine Habilitation Center
Mailing Address: 10695 Bellefontaine Rd.
City: Bellefontaine Neighbors State: _;M=O~- Zip Code: 63137
Service/Street Address (if different from above): _;:::.;Sam=e'-"as=ab"""o'-'-v-"'-e_ _ _ _ _ __
City: · State: Zip Code: _ _ __
Daytime Phone: 314-340-6235 Fax: 314-340-6298 E-Mail: Charles.Moody@oa.mo.gov
Emergency Contact Phone: 573-552-2795
Company Account No. (from Utility Bill): 64 700-00731

B. Cu~tomer's Generator & Transfer Switch System Information

Manufacturer Nameplate AC Power Rating: 1250 kW and Voltage: 480 V.


System Type: (describe) Diesel backup generator
s·ervice/Street Address: 10695 Bellefontaine Rd.
Transfer Switch Equipment Manufacturer: -'S=i=em=ehs~-----------
Transfer Switch Equipment Model No.: _ _ _ _ _ _ _ _ _ _ __
Are System Plans & Specifications Attached? Yes_K_ No
Location of Lockable Visible Open/Main Disconnect Device (describe): Disconnects
located within the switchgear and generator enclosure
Existing Electrical Service Capacity: unver Amperes Voltage: 12.7k Volts
Service Character: Single Phase__ Three Phase .1L_

1
C. Installation Information/Hardware and Installation Compliance

Person or Company Installing: _,B=at~e::!..s~E~Ie~ctr~i~c,_,I~n~c...___ _ _ _ _ _ _ _ _ _ _ __

Contractor's License No. (if applicable): _;E=-=..:11=3"""9_ _ _ _ _ _ _ _ _ _ _ _ __ !


l
I'
i
Approximate Installation Date: ~O=ct~2~0~1~1_ _ _ _ _ _ _ _ _ _ _ _ _ _ __
!
Mailing Address: _;B=ox........._lO=O"'---------------------- l
I
City: Imperial State: _,M=O~- Zip Code: 63052 I,
!
Daytime Phone: 636-464-3939 Fax: 636-464-9895 E-Mail: ibates@bates-electric.com
I
Person or Agency Who Will Inspect/Certify Installation: ~S-=ta,.,te"""'o""'f'"""M=is""'so><.:un~·~-----
r
r
I
D. Type of Connection !
Customer is proposing to connect generation that falls under the following category: I
i!'

_x_ Category 1 - Open Transition


.· __ Category 2- Synchronized Closed Transition of Less than 0.1 Seconds .

E. Conditions and Required Testing

For Category 1 and 2 generators:

1. Where the associated Ameren service is less than 600V, install a main service
disconnect capable of being padlocked in the open position. Also submit a
drawing indicating the nature and physical location of this equipment or
device. This equipment shall meet Ameren's Specifications and
Requirements for the Connection of Electric Generation attached;

2. Where the associated Ameren service is greater than 600V, install padlockable
equipment capable of establishing a "visible disconnect" between the Ameren

2
system and the generator. A visible disconnect is a switching device that
enables one to physically see an open air gap that is created by either the
disconnect device itself or by its being drawn out from a "seated" or "racked
in" position. Also submit a drawing indicating the nature and physical
location of this equipment or device. This equipment shall meet Ameren's
Specifications and Requirements for the Connection of Electric Generation ::
attached; I.
i

3. Provide signage in the immediate vicinity of Ameren's revenue meter


indicating that a generator exists on the premises and that a lockable main
service disconnect or lockable visible open disconnect is available. Similarly,
i
provide signage at the disconnect device itself for identification purposes;
I
4. Agree not to operate the generator in parallel with Ameren's electric system I·
for purposes of peak shaving, serving normal loads, or testing the capability of
. the generator to carry electric load. Prolonged operation of the generator in t
parallel with the utility electric system when it is de-energized creates a safety
hazard for utility employees, to the point of being potentially fatal.

For Category 2 generators only:

5. If the generator is equipped with "Fast Transfer Capability," i.e. relaying and F
controls that limit the duration of synchronized closed transition between the
generator and Ameren's electric system to less than 100 milliseconds during
startup and shutdown of the unit, the generator must demonstrate, through
equipment supplier information, that the equipment is designed to achieve the
fast transfer in less than 100 milliseconds; ,

6. Demonstrate that the transfer switch complies with all of Ameren's


··Specifications and Requirements for the Connection of Electric Generation,
including the provision for a transfer failure scheme, which will cause the
opening of one of the sources within two (2.0) seconds of the start of the
paralleling condition;

7. Demonstrate that the equipment can achieve the fast transfer by providing an
on-site start-up and commissioning test procedure for the fast transfer
capability of the hardware. Ameren and the customer shall agree on this
procedure as well as on the date and time of the testing. The test procedure
shall:

A. Provide sufficient notice to Ameren of the fast transfer testing in order


to allow Ameren the opportunity to both attend (if desired) and take
any operational or safety precautions deemed necessary (contact
Name of Ameren Contact at Phone Number );

3
B. Test the fast transfer capability per manufacturer's recommendations
and verify that the closed transition transfer takes place within 100
·milliseconds;

C. Test the transfer failure scheme and verify that one of the sources
opens subsequent to an extended paralleling condition of greater than
two (2.0) seconds;

D. Require immediate notification to Ameren of any periods during


testing when the fast transfer equipment is out of service or fails to
achieve transfer in 100 milliseconds, or when the transfer failure
scheme fails to operate properly; and

E. Arrange for the appropriate follow-up testing (and notification to


Ameren) in the case where any part of the original commissioning
procedure couldn't be satisfied.

F. Signature ·

I hereby certify that, to the best of my knowledge, all the information provided on this
Generator Connection Request Form is true and correct. After the installation and
testing of the generator and upon proper submission or resubmission of the
documentation required by Ameren, I agree to operate the generator in compli~ce
with the conditions stated above.

CustomerSignature: ~~ tf ~
Prillted Name: • ~ rn ue ( ~ Ht /:e tf, ? £,
c

Date: I /2 3/t 1 2_
~

4
Specifications and Requirements
for the
Connection of Electric Generation
that will operate with an
Open Transition (Category 1) between the Ameren System and
the Generator
or operate with a
Synchronized Closed Transition (Category 2) between the I·
Ameren System and the Generator of Less than 100
Milliseconds
II
1:
Approval shall be obtained from Ameren Corporation for all generation installations.
!:
This document relates to the connection of generation that will synchronize with the ,.
Ameren electric system for less than 100 milliseconds. If you are proposing a
synchronization time greater than 100 milliseconds, this procedure does not apply. I
Radial Ameren distribution systems are assumed. I
I
1. Definitions .................................................................... e •••••••••••••••••••· •.••••••••••••• 2

2. Requirements for Generation Installations ..................................................... 2

3. Requirements Specific to Open Transition Transfer (Category 1) ................ 4

4. Requirements Specific to Closed Transition Transfer (Category 2) .............. 5

5. Programmable Logic Controllers (PLC) ........................................................ 6

6. Drawing Requirements for Generator Installations ....................................... 8

I
1. Definitions

1.1 Automatic Transfer- The switching between an Ameren-provided electrical


source and customer-provided generation without the need for human operator
intervention.

1.2 Manual (Non-Automatic) Transfer- The switching between an Ameren-


provided electrical supply and customer-provided generation by human operator
intervention.

1.3 Open Transition - The transfer of an electrical load from one power source to
another through the use of a double throw switch or interlocks which prevent
the closing of the second source before the first source opens.
I

1.4 Closed Transition - The transfer of an electrical load from one power source to
l
another by closing the second source before opening the first. I
II
15 Parallel Operation- The closing of the electrical source from customer-
provided generation without opening the Ameren-provided electrical source. r
1.6 Visible Open Disconnect -A switching device that enables one to physically !:
see an open air gap that is created by either the disconnect device itself or by its f
being drawn out from a "seated" or "racked in" position. Molded case circuit
breakers, solid state switching devices, static transfer switches and switch status
indicators (e.g. lights, operating handle positions, etc.) do not qualify as visible
open disconnects.

· 2. Requirements for all Generation Installations

2.1. Transfer equipment shall be designed and installed to prevent inadvertent


continuous interconnection and operation of the normal and emergency power
sources. This equipment can take many forms depending on the voltage of the
associated Ameren service and whether the installation is designed for open or
closed transition transfer (ref. Sections 3 and 4 below).

·2.2. The transfer switch shall be UL listed and the entire transfer equipment
installation shall be approved by the proper inspection authorities having
jurisdiction and satisfy all applicable building and electrical codes.

2.2.1. If the transfer switch is also being used as the main service disconnect,
the transfer switch shall be UL listed specifically for this purpose per the
specifications in UL Standard 1008 (Transfer Switch Equipment). UL
1008 specifies that such a transfer switch shall be marked "Suitable
[only] for use as service equipment" and shall carry a pressure-sensitive
label marked "Service Disconnect."

2
2.2.2. It is not an Ameren requirement that the transfer equipment be capable
of switching or disconnecting the grounded circuit conductor (neutral),
though there are circumstances in which Ameren will require that an
exception to this be made. Such a determination will be made during
Ameren's review of the customer's plan.

2.3. Per National Electric Code (NBC) requirements, service entrance conductors
and generation supply conductors shall not occupy a common raceway other
than in the transfer equipment.

2.4. If the Ameren service being backed up by the generator is less than 600V, then
the associated main service disconnect device shall be padlockable in the open
position for the safety and protection of Ameren personnel.

2.4.1. A sign shall be permanently installed at the associated revenue metering


location that states, "Backup Generation Present - Lockable Main
Service Disconnect Available for Isolation." The sign shall have
minimum dimensions of5"x 7", be permanently secured with bolts, and
shall be both waterproof and ultraviolet resistant.

2.4.2. A sign shall also be permanently installed at the main service disconnect
device itself stating, "Lockable Main Service Disconnect for Isolation
from Generator" for purposes of identification by Ameren field .
personnel. It shall be similar in size, make and color to the sign at the
revenue meter so that an association can be easily made. All other NEC
and building code requirements around electric facility-related signage
shall be followed. ·

2.4.3. For pre-existing main service disconnects only: If the Ameren service
being backed up is a self-contained metered service (i.e. no metering
.CT' s) and the pre-existirig main service disconnectis unable to be
padlocked in the open position, the self-contained meter, being a "visible
.open disconnect" device (ref. Section 1.6) shall satisfy this requirement.

2.5. If the Ameren service being backed up by the generator is greater than 600V,
then at least one "visible open disconnect" device (ref. Section 1.6) shall be
required for the safety and protection of Ameren personnel.

2.5.1. Each visible open disconnect device shall isolate one or more of the
customer's generating units from the rest of the system. All generating
units shall be associated with at least one of these devices.

2.5.2. The visible open disconnect device shall be accessible to Ameren


personnel at all times. While the device does not have to be under .
Ameren's exclusive control, it shall have provisions for being padlocked

3
in the open position or in the "drawn out" position by Ameren personnel
should the need for temporary electrical isolation present itself.

2.5.3. A sign shall be permanently installed at the associated revenue metering


location that states, "Backup Generation Present- Lockable Visible
Open Disconnect Available for Isolation." The sign shall have
minimum dimensions of 5"x 7", be permanently secured with bolts, and
shall be both waterproof and ultraviolet resistant.

2.5.4. A sign shall also be permanently installed at the visible open disconnect
device itself stating, "Lockable Visible Open Disconnect for Isolation
from Generator" for purposes of identification by Ameren field
personnel. It shall be similar in size, make and color to the sign at the
revenue meter so that an association can be easily made. All other NEC
and building code requirements around electricfacility~related signage
shall be followed. ·

3. Requirements Specific to Open Transition Transfer (Category 1)

3.1. An open transition between the Ameren system and customer generator(s) can
be achieved with any of the following:

3.1.1. An integral transfer switch with mechanical interlocking provisions (e.g.


a double throw configuration, mechanical locking bar, etc.) to prevent
the closing ofboth sources at the same time;

3.1.2. A pair of Kirk key~interlocked disconnect switches or circuit breakers;


or

3.1.3. A pair of circuit breakers with electrical interlocking provisions to


prevent the closing of both sources at the same time, provided that the
interlocking scheme is backed up with hard-wired protection directly
from the breaker auxiliary contacts.

3.2. If the open transition between the Ameren system and customer generator(s) is
being achieved via automatic transfer means, then the following shall apply:

3.2.1. Voltage-sensing capability or other means for detecting the loss and
recovery of the Ameren source shall be required.

3.2.2. A manual "bypass'' (i.e. auto disable) feature is not required, but it is
highly recommended for use in the event of a malfunction in the
automatic transfer between sources in either direction. If this provision
exists, it shall be open transition in nature and mechanically interlocked
(e.g. a double throw configuration, mech~callocking bar, etc.) to

I•
prevent the closing of both sources at the same time. Ifthe bypass
switch is separate from the transfer switch, it shall also be mechanically
interlocked against its being switched to one source while the transfer
switch is switched to the other.

3.2.3. The automatic transfer controller shall be "supervised" by the status of


the transfer switch (and that ofthe bypass switch if it exists) so that if
either switch is manually tripped, automatic control will be disabled.

4. Requirements Specific to Closed Transition Transfer (Category 2)

4.1. A closed transition between the Ameren system and customer generator(s) can
be achieved either with an integral automatic transfer switch set or with two or
more circuit breakers or motor-operated solid blade disconnects.

4.2. Synchronizing capability shall be required in order for the Ameren-provided


source and the customer-provided generation to be safely tied together. All
synchronized transfer times shall be held to less than 100 milliseconds in
duration.

4.3. A transfer failure scheme shall be required that activates when the period of
synchronized closed transition exceeds a set time delay that is no longer than
two (2.0) seconds.

4.3.1. Upon activation, the transfer failure scheme will open one ofthe two
sources being paralleled and lock out the control circuit from any further .
transfer operation.

4.3.2. For cases with a maximum time delay relay range greater than two (2.0)
seconds, Ameren will also require Device 32 (directional power) and
Device 67 (directional overcurrent) relays. These relays shall be of a
.draw-out·type with built-in test devices. Otherwise, external test devices
(such as the ABB FT-1) are required for the isolation of trip contacts and
PT/CT inputs as well as the injection of secondary voltages and currents
during testi£g. .

4.3.3. Ifthe transfer switch has the capability of providing a hard-wired signal
that could trip a device that is separate from the transfer switch
equipment in order to interrupt a paralleling event exceeding 100
milliseconds, the customer shall see to it that this feature is utilized. The
control scheme shall trip the device and then block it from closing. The
time qelay on the trip signal shall not exceed two (2.0) seconds.

4.3.4. If the Ameren service being backed up by the generator is greater than
600V, an additional independent hard-wired breaker auxiliary contact ·

5
scheme may be required to break up extended paralleling of the two
sources. Ameren prefers this type of backup scheme and will only
accept another scheme pending a detailed evaluation.

4.3.5. There shall be no intended or built-in provision for the customer to


disable the transfer failure scheme.

4.4. An undervoltage protection provision shall be required which prevents a closed


transition transfer in the event that the Ameren source is not present.

4.5. In the event of a malfunction in the automatic transfer between sources in either
direction, the transfer switch shall be able to be manually switched to the
desired source.

4.6. A manual "bypass" (i.e. auto disable) feature is not required, but it is highly
recommended for use in the event of a malfunction in the automatic transfer
between sources in either direction. If this provision exists, it shall be open
transition in nature and mechanically interlocked (e.g. a double throw
configuration, mechanical locking bar, etc.) to prevent the closing of both
sources at the same time. If the bypass switch is separate from the transfer
switch, it shall also be mechanically interlocked against its being switched to
one source while the transfer switch is switched to the other .

. . 4.7. The automatic transfer controller shall be "supervised" by the status of the
transfer switch (and that of the bypass switch if it exists) so that if either switch
is manually tripped, automatic control will be disabled.

5. Programmable Logic Controllers (PLC)

5.1. For purposes of establishing the requirements herein, Ameren defines a


programmable logic controller (PLC) as any solid-state microprocessor-based
controller that needs to be programmed by the user with the logic necessary for
it to supervise and execute the control :funcdons for which it is being utilized.
This is separate from a factory-programmed controller whose logic restricts the
system to a single "proprietary" mode of operation, the parameters of which
need merely to be configured by the user. It is understood that the PLC can
exist as a stand.;alone unit or as a permanent component of an integral automatic
transfer switch.

5.2. Ameren will allow the use ofPLCs for automatic transfer control between an
Ameren-provided supply and customer-provided generation with the following
requirements:

5.2.1. A backup control scheme shall be provided to prevent the extended


paralleling operation of the generator with the Ameren system. The

6
backup control shall be completely independent of the PLC. Software
contacts or backup logic are not acceptable.

5.2.2. The backup control shall trip open a device that is separate from the
transfer equipment and block it from closing in the event of extended
parallel operation with the Ameren system.

5.2.3. The PLC and backup control logic shall be enabled when the transfer
scheme is placed in automatic operation and disabled when the transfer
scheme is placed in manual operation.

5.2.4. The automatic transfer switch shall be "supervised'' by the status of the
disconnect switch, circuit breaker or bypass switch controls so that if
any of these switches is manually tripped, the PLC control will disable
automatic transfer. II
5.2.5. The PLC shall not lose power at any time as a direct result of automatic I
[.
transfer switching operations. This shall be confirmed during Ameren's !
functional test of the automatic transfer equipment. I'
I
5.3. There are two preferred methods ofPLC backup control:
I
~
!
5.3.1. The first method is through the use of the hard-wired auxiliary contacts
of the associated breakers. The time delay shall be minimal and
typically no longer than two (2.0) seconds· in duration. The time delay
range and setting shall be reviewed by Ameren.
I
5.3.2. For those cases where the maximum time delay range exceeds two (2.0)
· seconds, Ameren will also require Device 32 (directional power) and
Device 67 (directional overcurrent) relays. These relays shall be of a
f
draw~out type with built-in test devices. Otherwise, external test devices
(such as the ABB FT-1) are required for the isolation of trip contacts and
PT/CT inputs as well as the injection of secondary voltages and currents
· during testing. The maximum time delay shall be absolutely no longer
than thirty (30) seconds in duration.

5.3.3. A second method for PLC backup control (provided a hard-wired


auxiliary contact scheme is not possible) is to install Device 32
(directional power), Device 67 (directional overcurrent) and Device 59N
(neutral overvoltage) relays that are approved by Ameren. The
operation of all these relays shall trip and lock out the generator breaker
or another disconnecting device that isolates the customer generator
from the Ameren source. The Device 59N requires the installation of
grounded wye to open delta potential devices on the delta high side of
the distribution or substation transformer supplying the customer.

-----------· .. --~--~··.
6. Drawing Requirements for Generator Installations

6.1. For generator installations utilizing integral transfer switches enclosed in a


single compartment, the following documentation is required in triplicate:

6.1.1. A one-line diagram is required showing the electrical location ofthe


Ameren source as well as that of the generator, the transfer switch, and if
applicable, the visible open disconnect device inside the customer
facility.

6.1.2. Details on the signage at both the revenue meter and the lockable main
service disconnect or visible open disconnect, including size, wording
and physical location, shall be required.

6.1.3. A manufacturer's cut sheet, operations manual and other specifications


II
are required for the particular transfer switch being installed. Among I
the more critical information therein are the manufacturer's model
number, transfer scheme type (open or closed transition), locking
provisions, interlock details, and if applicable, the time range of closed
I
transition, and details on the auto/manual and manual bypass switches. Il
I
6.1.4 .. Drawings on both the closed transition transfer and transfer failure !
'
schemes are required, which include the time delay setting and
maximum range.

6.2. For generator installations utilizing circuit breakers or disconnect switches


mounted in separate compartments, the following documentation is required in
triplicate:

·6.2.1. A one-line diagram is required showing the electrical location of the


Ameren source as well as that of the generator and associated transfer
switch in the customer facility.

at
6.2.2. Details on the signage both the revenue meter and the lockable main
service disconnect or visible open disconnect, including size, wording
and physical location, shall be required.

6.2.3. Detai.led control·schematics of the main breaker and generator breaker


trip and close control circuits are required. These schematics shall show
all protective relay functions and provide the information necessary to
analyze and document the logic associated with the generator transfer
scheme, transfer failure scheme, interlock controls and any other ·
pertinent control functions.

8
6.2.4. Drawings on both the closed transition transfer and transfer failure
schemes are required, which include the time delay setting and
maximum range.

l
"~
~
i

I
I
l!
l
I
I!
I
i

9
r

THIS PAGE INTENTIONALLY LEFT BLANK
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

SECTION 262726- WIRING DEVICES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall furnish and install all receptacle cover plates as specified herein and as shown
on the Drawings.

1.3 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

1.4 SUBMITTALS

A. Manufacturer's product data sheets shall be submitted for each of the following:

1. While-in-use weatherproof duplex GFCI receptacle cover

PART 2 -PRODUCTS

2.1 WHILE-IN-USE WEATHERPROOF COVER FOR DUPLEX GFCI RECEPTACLE

A. Weatherproof cover for duplex GFCI type receptacle located outdoors shall be UL Listed for wet
location (raintight) use with utilization equipment attachment plug inserted into the receptacle~

B. Cover door shall be spring loaded, self-closing type and the cover shall be designed for installation
on a vertically mounted Type FS/FD box housing a duplex GFCI receptacle.

c. Cover shall be provided with weatherproof gasket and shall have one stainless steel attachment screw
in each corner.

D. Cover shall be cast aluminum with powder coated gray finish.

E. Cover shall be NEMA 3R rated and shall meet or exceed the extra duty rating ofUL 514D and
shall comply with NEC 406.9(B).

F. While-in-use weatherproof cover for duplex GFCI receptacle shall be Hubbell WP26E or
approved equal by Appleton Electric, Eaton Crouse-Hinds, Killark, or 0-Z/Gedney.

PART 3- EXECUTION

3.1 INSTALLATION

A. Attach new weatherproof cover to existing exterior GFCI receptacle box in accordance with the
cover plate manufacturers written instructions.

WIRING DEVICES 262726- 1


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02

3.2 CIRCUIT IDENTIFICATION

A. Cover plates for all receptacles shall be marked on the outside surface of the cover plate with a printer
generated peel and stick label in accordance with Section 260553 - Identification for Electrical
Systems with the source panelboard designation and circuit number.

END OF SECTION 262726

WIRING DEVICES 262726-2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02

SECTION 262813 -FUSES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. The Contractor shall furnish and install all fuses as specified herein and as shown on the Drawings.

1.3 RELATED SECTIONS

A. Section 260500- Common Work Results for Electrical

1.4 SUBMITTALS

A. Manufacturer's product data sheets shall be submitted for the following items:

1. Each type offuse

1.5 EXTRA MATERIALS

A. The Contractor shall provide and turn over to the Owner 10% spare fuses (minimum of 3) for each
size and type of fuse used on this project, including control fuses and lighting fixture fuses.

PART 2 -PRODUCTS

2.1 250-VOLT AND 600-VOLT FUSES

A. Fuses and their applications shall meet all the requirements ofNEMA, the National Electrical Code
(NFPA 70) and OSHA Part 1910 SubpartS. Fuse sizes and types shall be as shown on the Drawings
and in schedules. Fuses shall be properly coordinated and shall be verified by the Contractor for the
final load served. All fuses shall be Underwriters' Laboratories (UL) approved and shall have
standard NEC dimensions.

B. Fuses used on circuits up to 250 volts shall be dual element, time delay, current limiting and
shall have a minimum short circuit interrupting capacity of 300,000 RMS symmetrical
amperes, UL Class RKl, LPN-RK, 250V for sizes up to 600 amperes.

C. Fuses used on circuits above 250 volts up to 600 volts shall be 600V, dual element, time delay,
current limiting and shall have a minimum short circuit interrupting capacity of 300,000 RMS
symmetrical amperes, UL Class RK 1 or Class J (as indicated on the Drawings) for sizes up to 600
amperes.

D. All fuses shall have blown fuse indication feature.

E. Fuses shall be as manufactured by the Cooper Bussmann Manufacturing Division of Eaton or


approved equal by Mersen or Littlefuse.

FUSES 262813 - 1
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
F. Control circuit fuses (less than 5 amps) and associated fuse holders shall be as shown on the
Drawings.

PART 3- EXECUTION

3.1 INSTALLATION

A. Equipment shall not be shipped and/or delivered to the job site with the fuses installed in place.

B. Install fuses in fuse clips with fuse indicator facing out such that it is visible for inspection without
removing the fuse from the fuse clips.

END OF SECTION 262813

FUSES 262813- 2
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri M1401-02

SECTION 263236- RESISTIVE LOAD BANKS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SCOPE

A. This specification contains the minimum requirements for the design, manufacture and testing of
a UL listed, air-cooled, outdoor weatherproof resistive load bank.

B. The load bank is required for periodic exercising and testing of the (standby) emergency power
source. The load bank shall be permanently mounted in a weatherproof enclosure, forced air
cooled with remotely mounted control panel.

1.3 RELATED SECTIONS

A. Division 3 - Concrete

B. Section 260500- Common Work Results for Electrical

c. Section 260519 -Low-Voltage Electrical Power Conductors & Cables

D. Section 260526 - Grounding and Bonding for Electrical Systems

E. Section 260529 -Hangers and Support for Electrical Systems

F. Section 260533.13- Conduit for Electrical Systems

G. Section 260553 - Identification for Electrical Systems

H. Section 260583 -Wiring Connections

I. Section 262813- Fuses

1.4 SUBMITTALS

A. The manufacturer shall submit for review technical data including features, performance,
electrical characteristics, physical characteristics, ratings, accessories, and finishes.

B. Shop drawings shall include dimensional plans, front and side elevations and mounting details
sufficient to properly install the load bank. Load bus configuration and load connections
termination area shall be clearly identified.

C. Electrical schematic drawings shall be provided to detail the operation of the load bank and the
provided safety circuits. Over-current protection and control devices shall be identified and their
ratings marked. A system interconnection drawing shall be included for control wiring related to
the load ban.

D. Provide recommended spare parts list, including pricing.

RESISTIVE LOAD BANKS 263236- 1


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
1.5 STANDARDS

A. The equipment covered by this specification shall be designed with the latest applicable NEMA,

B. NEC, and ANSI standards.

C. The load bank shall be listed to UL Standard 508A.

PART 2 - PRODUCTS

2.1 RATINGS

A. The total capacity of the load bank shall be rated 1000 KW at 480 Volts, 3-Phase, 3-Wire, 60
Hertz, 1,200 Amps per Phase at unity Power Factor and 50 KW minimum load step resolution.

B. The load bank shall be designed for continuous duty cycle operation with no limitations. The load
bank shall operate in an ambient temperature of -28°C to 49°C (-20°F to 120°F).

2.2 MATERIAL AND CONSTRUCTION

A. The load bank shall be outdoor weatherproof constmction, suitable for installation on a concrete
pad or stmctural base. All exterior fasteners shall be stainless steel. The load bank shall include
forklift channels in the base for lifting.

B. The load bank shall be constmcted of heavy gauge aluminized steel per ASTM A463. Aluminized
steel provides superior corrosion protection and extended service life, with a better tolerance to
high heat exposure compared to the more common Galvanized steel.

C. The main input load bus, load step relays, fuses and blower/control relays shall be located within
the load bank enclosure. A thermostatically controlled heater shall be located within the control
section to provide protection to the control devices from the effects of moisture and condensation.

D. Airflow throughout the load bank shall be vertical. Ambient intake cooling air shall be drawn in
at the base of the unit and heated air exhausted out the top. Intake openings shall be designed to
prevent objects greater than 0.50" diameter from entering the unit.

E. The load bank exhaust hood(s) shall be angled and include interior baffle plates to direct falling
rain from the interior of the load bank. The exhaust hood(s) shall be constructed of non-corrosive
aluminized steel or aluminum.

F. The load bank enclosure shall have a baked polyester powder coated finish with a film thickness
of2.8 +/- 0.4 Mils per coat.

G. Load elements shall be contained in multiple resistor cases or trays. Each can be removed in its
entirety as a unit for inspection or service.

2.3 RESISTIVE LOAD ELEMENTS

A. Load elements shall be Avtron Helidyne™, helically wound chromium alloy rated to operate at
approximately Yz of maximum continuous rating of wire. Elements must be fully supported across
the entire length within the air stream by segmented ceramic insulators on stainless steel rods.
Element supports shall be designed to prevent a short circuit to adjacent elements or to ground.

RESISTIVE LOAD BANKS 263236-2


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
B. The change in resistance due to temperature shall be minimized by maintaining conservative watt
densities.

C. The overall tolerance of the load bank shall be -0% to +5% KW at rated voltage. A -5%, +5%
rating allows the load bank to deliver less than rated KW and shall not be used. The load bank
must deliver full rated KW at rated voltage.

2.4 COOLING

A. The load bank shall be cooled by integral TEFC or TEAO motor(s) which is direct coupled to the
cooling fan blade. The fan motor must be electrically protected against overload using a motor
overload device and short circuit protected using three (3) current limiting fuses with an
interrupting rating of200kAIC.

B. The fan blade is to be an airfoil design constructed from aluminum or non-corroding material.

C. An integral control power transformer shall be provided to supply 120V, 1 phase, 60 Hz to the
load banks control and motor starter circuitry. Transformer primary and secondary control circuits
shall be fuse protected.

2.5 PROTECTIVE DEVICES

A. A differential pressure switch(s) shall be provided to detect air loss (one for each stack). The
switch(s) shall be electrically interlocked with the load application controls to prevent load from
being applied if cooling air is not present.

B. An over-temperature switch shall be provided to sense the load bank exhaust in each vertical
heater case assembly. The switch shall be electrically interlocked with the load application
controls to remove load from being applied in the event of an over temperature condition.

C. To provide for major fault protection, branch fuses shall be provided on all three phases of
switched load steps above 50KW. Branch fuses shall be current limiting type with an interrupting
rating of 200kAIC.

D. The exterior of the load bank shall have appropriate warning/caution statements on access panels.

2.6 CONTROL PANEL

A. The control panel shall be a remote 19" rack mounted panel housed in a NEMA 4 type wall mount
enclosure. The control panel shall contain the following manual controls:

1. Power ON/OFF switch


2. Blower START/STOP pushbuttons.
3. Master load ON/OFF switch.
4. Load step switches for ON/OFF application of individual load steps.

Control panel visual indicators shall be as follows:

5. Power ON indication light.


6. Blower ON light.
7. Blower/Air FAILURE light.
8. OVERTEMPERATURE light.

RESISTIVE LOAD BANKS 263236-3


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
B. A standard remote load dump circuit shall be provided as part of the load bank control circuit.
Provisions shall be provided to remove the load bank off-line from the operation of a remote
normally closed set of auxiliary contacts from a transfer switch or other device. In the event of
the remote contact opening, all load is removed.

C. An Automatic Load Step Controller shall be provided for maintaining a minimum load on the
generator set. The controller shall monitor the connected downstream loads and will automatically
add or subtract load steps in response to building load changes as to maintain a minimum load
level on the generator set. The controller includes an initial time-delay circuit, and automatic time
delayed load step application circuit. A remote contact closure is required for activation and
transfer of control. A separate current transformer shall be supplied loose for mounting and
sensing of downstream loads. The current transformer shall have a ratio of 2000:5A and shall be
sized as required to fit around the 480V bushing on the 480V to 12.47kV generator step-up
transformer.

D. The load bank shall have a digital monitoring system with real-time data logging software. The
monitoring system shall provide a 3-line extra-bright LED display of Voltage, Current, Frequency
and Power Measurements. System shall utilize communicator EXT type software which provides
PC based real-time monitoring and also automated data acquisition from an optical IrDA port. An
IrDA/USB adapter shall be provided for plug and play convenience.

2.7 DOCUMENTATION

A. Installation and operation manuals shall be provided with the equipment and shall include
complete details for the installation, commissioning, operation, and maintenance of the load bank.

B. The manuals shall include the electrical schematic and interconnect drawings for the power and
control wiring for the load bank and all control devices.

c. A complete parts list with part numbers, device identification, and rating shall be included in the
manuals. The original manufacturers name and part number shall be included in the parts listing.

D. Two (2) sets of manuals shall be provided with the load bank.

2.8 ACCEPTABLE MANUFACTURERS

A. The load bank shall be as manufactured by:

1. ASCO A vtron Loadbank, Inc.


6255 Halle Drive
Cleveland, Ohio 44125
Phone:216-573-7600
Email: LBsales@Emerson.com I Website: www.avtronloadbank.com
2. Loadtec Load Technology, Inc.
525 Commerce Circle
Mesquite, NV 89027-1900
Phone: 800-562-3832
Email: sales@loadtec.com I Website: www.loadtec.com
3. Simplex, Inc.
5300 Moon Road
Springfield, Illinois 62711-6228
Phone: 800-637-8603
Email: johnh@simplexdirect.com I Website: www.simplexdirect.com
RESISTIVE LOAD BANKS 263236-4
Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
2.9 QUALITY CONTROL

A. The load bank shall be fully tested using a test specification written by the supplier. Tests shall
include electrical functional testing, verifying conformance to assembly drawings and
specifications. Each load step shall be cold resistance checked to verify proper calibration of
resistive load steps and proper ohmic value.

B. Tests using high potential equipment shall be performed to ensure isolation of the load circuits
from the control circuits and to determine isolation of the load circuits from the load bank frame.
Tests of all safety circuits shall be performed to verify conformance to the specification

c. All electrical circuits shall have a high potential insulation resistance test performed at twice rated
voltage plus 1000 VAC to assure insulation integrity.

D. All quality control test equipment shall be regularly maintained and calibrated to traceable
national standards.

E. The Company's Quality System shall be IS09001 Certified.

2.10 QUALIFICATIONS OF MANUFACTURER

A. The load bank shall be manufactured by a firm regularly engaged in the manufacture of load
banks and who can demonstrate at least twenty-five (25) years' experience with at least twenty-
five (25) installations of load banks similar or equal to the ones specified herein.

B. The manufacturer shall have a written Quality Control procedure available for review by the
purchaser, which will document all phases of operations, engineering, and manufacturing.

c. Manufacturer must have a field service organization with service personnel having a minimum
of an Associate Degree in Electrical Engineering.

PART 3 -EXECUTION

3.1 INSTALLATION

A. Equipment shall be installed in accordance with the manufacturer's written instructions.

B. All power and control conduits shall enter/exit the bottom of the equipment enclosure at the
location indicated on the equipment drawing.

c. Provide reinforced concrete pad for installation of the equipment as indicated on the Project
Drawings.

D. Set equipment on pad in its final location. Do not slide equipment on concrete pad to avoid
damaging the factory corrosion protection finish on the bottom of the unit.

E. Orient the heat exhaust hood in the direction indicated on the Project Drawings.

F. Mount automatic load bank control panel to wall inside the 12.47kV campus main switchgear
enclosure as indicated on the Project Drawings.

RESISTIVE LOAD BANKS 263236- 5


Controls Upgrades to Generator & Medium-Voltage Switchgear
Bellefontaine Habilitation Center, St. Louis, Missouri Ml401-02
G. Connect power and control cables to load bank and automatic control panel as indicated on the
equipment drawings and torque all terminations in accordance with the equipment manufacturers
recommendations.

H. Touch up all blemishes in factor finish on the equipment using the method recommended by the
equipment manufacturer and using touch-up paint provided by the equipment manufacturer.

3.2 STARTUP AND COMMISSIONING

A. Provide startup and commissioning of the equipment by a factory authorized and factory trained
field startup technician.

B. Test functional operation of the load bank in both automatic and manual modes of operation from
minimum to full rated load of the load bank.

c. Repair and retest until equipment is fully functional as designed.

D. Provide field startup report for Owner's records indicating the date and time and name of the
technician who performed the equipment startup and commissioning services.

3.3 DEMONSTRATION AND OWNER TRAINING

A. Factory authorized and trained field service technician shall instruct the Owner's maintenance
personnel on the operation of the load bank in both manual and automatic modes and on
preventative maintenance and serving of all Owner serviceable components.

END OF SECTION 263236

RESISTIVE LOAD BANKS 263236-6

Das könnte Ihnen auch gefallen