Kick Off Meeting

Activity ID Status Combined Top Urgent


Date
Earthworks
Earth Works - Backfill Conducted Done
Earth Works - Excavation Conducted Done Combined
Civil / Skeleton (Concrete)
Concrete Ready-Mix Conducted 25-Dec-16
Steel Structure - PEB / Space Frame
Curtain Walls Conducted Done
Metal Cladding Conducted Done
Skylight/Space Frame Conducted Done
Structural Steel Conducted 9-Jul-17
Precast / Metal Cladding
Precast Concrete Panels Conducted 18-Jul-17
MEP
Fire Fighting Pipes Conducted 25-May-18
HVAC - Ducts Conducted 25-Jul-17
Plumbing - Pipes Conducted 17-May-17
Lift station Pumps Open TBC
Gasoline and Diesel Tank installation Open TBC
Fuel Station System installation Open TBC
FRP tank installation Open TBC
General Workshop Facility equipment Installation Open TBC
Welding /NDE Fuel Carbon Steel Pipes Conducted 30-Sep-18
Installation Compressed Air System Conducted 26-Aug-18
Refrigerant Pipes (AHU +Brazing ) Conducted 31-Jul-18
Finishes
Vinyl/Access Floor Conducted Done
Ceramic/Porcelain/Quarry Tiles Conducted 30-Oct-17 Combined
CMU Blocks Conducted 13-Aug-17
Gypsum Wall Lining Conducted 1-Oct-17
Marble/Granite/Stone Open TBC Combined
Plaster Conducted 16-Oct-17
Screed Conducted Done
Suspended Ceiling Conducted Done Repeated
Utility Networks (Infra)
Concrete Drain Pipes Open TBC
Fire Water RTR Pipes Conducted 21-Sep-17
Grounding PVC Cables Conducted Done
LV Cables Conducted Done
MV Cable Conducted 30-Aug-17
Potable Water PVC Pipes Conducted 17-May-17
PVC Ducts Conducted 17-May-17
Sanitory/Oily RTR Pipes Conducted 17-May-17
Treated PVC Pipes Conducted 17-May-17
Utility PVC Pipes Conducted 17-May-17
Hardscaping & Landscaping
Concrete Curb and interlocking Conducted Done Repeated
Grass Conducted 23-Jan-19
Plants Conducted 23-Jan-19 Combined
OHTL
Construction of Access road including backfilling and
compaction
Conducted 15-Feb-17
Pile foundation works and Uplift load test Conducted 19-Apr-17
Construction of duct banks Conducted 29-Jul-17
115 KV U/G cable and NMFOC Laying works Conducted 20-Aug-17
Assembly and errection of 115 KV OHTL Tower and
Gantries
Conducted 3-Oct-17
OHTL stringing works complete Conducted 12-Dec-17
Grounding installation works complete Conducted 27-Dec-17
CONCRETE POURING WORKS Conducted 25-Dec-16
10' RTR Line
Potable Water RTR Pipes Conducted 2-Jan-17
Roads / Carparks
Asphalt Base Course Conducted 25-Dec-16
Asphalt Wearing Course Conducted 25-Dec-16
Compacted AGBase Mtrl Conducted 25-Dec-16
Compacted Subbase Mtrl Conducted 25-Dec-16
Cutting Grading Area Conducted 25-Dec-16
Fill Materials Conducted 25-Dec-16
Marl Material Conducted 25-Dec-16
Prime Coat Conducted 25-Dec-16
Tack Coat Conducted 25-Dec-16 Combined
Fence & Gates
Chain Link Fence Conducted 15-Jul-17
Others
LV Panel Board Conducted 22-Jul-18
Over Head Crane Conducted 26-Jul-18
Hollow metal Door Conducted Done
Fire Stopper Application Conducted Done
Pad Mounted Transformer Installation and Testing. Conducted Done
THRUST BORING Conducted Done
Installation of Earthing System Conducted Done
ELEVATORS Conducted Done
Installation of Acoustical Ceiling Tiles Conducted Done Repeated
Car Parking & Tent Shade Conducted Done
Installation of Concrete Pre- Cast Manhole Conducted Done
Asphalt Road Marking / Painting – MMCE Conducted Done
Installation of Curb Stone & Inserts Conducted Done Repeated
Cladding Installation - Zamil Steel Co. Conducted Done
Dry Type Transformer Conducted 19-Aug-18
Switchgear Open TBC
ATS Open TBC
Fire proofing Conducted 26-Nov-18
ODOR Control System Open TBC
Celling Baffles Open TBC
Audio Visual System Open TBC
Cathodic protection Open TBC
Remarks