Sie sind auf Seite 1von 7

BEYOND THE CALCULATIONS: LIFE AFTER ARC FLASH

ANALYSIS
H. Wallace Tinsley III Michael Hodder Aidan M. Graham
Member, IEEE Member, IEEE Senior Member, IEEE
Eaton Electrical Eaton Electrical Eaton Electrical
130 Commonwealth Drive 4120B Sladeview Cres 13205 SE 30th St, Ste 101
Warrendale, PA 15086 Mississauga, ON L5L 5Z3 Bellevue, WA 98005

Abstract – Once an Arc Flash Analysis has been locations be lowered below 40 cal/cm2 in order for personnel to
performed for a facility, the quantification of the potential safety perform energized work on these locations.
incident energy has been completed. However, this is only Additional HRC thresholds are often desired in order to
the first step in establishing and implementing a complete minimize the cost of purchasing personal protective equipment
arc flash program. Labels must be applied to the equipment (PPE) for each employee. A summary of the NFPA 70E Hazard
and the information presented must be appropriately Risk Categories is shown in Table 1. Each HRC is associated
meaningful and instructive to qualified persons preparing with specific requirements for PPE.
to access the energized equipment. Arc Flash warning
Table 1: Hazard Risk Categories (HRC)
labels are only one type of arc flash documentation that
should be presented and available to facility personnel. A
Hazard Risk Incident Incident
comprehensive safety policy and corresponding training Category Energy From Energy
program should be developed and implemented to ensure (HRC)
2
(cal/cm )
2
To (cal/cm )
understanding and compliance with the procedures in
place to reduce the impact of a potential arc flash hazard. 0 >0 < 1.2
Lastly, a preventative maintenance program must be put 1 1.2 <4
into place to ensure that all electrical equipment, most 2 4 <8
importantly the protective devices, will react appropriately
during an arc flash event. 3 8 < 25
4 25 < 40
Index Terms – Arc Flash Analysis, Arc Flash Training, Arc
Flash Warning Labels, Maintenance Program When a facility decides to purchase clothing for HRC’s 1
through 4, the cost per employee is very high. In order to avoid
I. INTRODUCTION having to purchase clothing for each HRC, specific HRC
thresholds are often set. For example, one of the most common
Much has been written in recent years regarding the arc approaches is to limit the PPE to HRC’s 2 and 4. All employees
flash hazard and the importance of quantifying the incident requiring arc flash PPE are provided clothing that meets HRC 2
energy at all locations where work may be performed on and clothing that meets HRC 4. Using Table 1 as a reference,
energized equipment. This quantification is typically HRC 2 clothing would be required for all locations where the
2
accomplished by performing an arc flash hazard analysis calculated incident energy is less than 8 cal/cm . Likewise,
utilizing one of several calculation methods. However, the initial HRC 4 clothing would be required for all locations where the
arc flash analysis is only the first step in establishing and calculated incident energy is greater than or equal to 8 cal/cm2,
implementing a complete arc flash program. but less that 40 cal/cm2. Any locations with incident energy
2
levels above 40 cal/cm are deemed unsafe for energized work.
II. REVIEW OF STUDY RESULTS AND ENERGY Using the above-mentioned philosophy as a guideline, it is
REDUCTION APPROACH then common practice to attempt to set HRC thresholds for
each particular type of equipment within a facility. For
Upon completing the initial arc flash analysis, the next step example, in a 480 V distribution system it is often feasible to set
is to review the results of the study with the facility safety, the desired maximum threshold for all panelboards and motor-
maintenance and electrical staff. Prior to labeling the control centers (MCC) to HRC 2 and for all switchboards and
equipment, several items need to be addressed in order to switchgear to HRC 4.
“finalize” the arc flash analysis calculations. B. Incident Energy Reduction Approach
A. Determination of Hazard Risk Category (HRC) Thresholds Using the guidelines and HRC thresholds defined by the
It is the authors’ experience that the initial arc flash analysis facility personnel, the study engineer must then re-examine the
will usually reveal a number of work locations where the initial arc flash analysis and choose solutions to get each
2
calculated incident energy exceeds 40 cal/cm - the upper limit equipment location below the desired HRC threshold. This is
of HRC 4 set forth in the NFPA 70E Standard for Electrical accomplished using one of many incident energy reduction
Safety in the Workplace 2004 Edition. Due to arc blast pressure techniques. A summary of the most common techniques are
concerns, it is recommended that the incident energy at these listed below:

PRESENTED AT THE 2007 IEEE IAS PULP AND PAPER INDUSTRY CONFERENCE IN WILLIAMSBURG, VA: © IEEE 2007 - PERSONAL USE OF THIS MATERIAL IS PERMITTED.
• Changing Existing Work Procedures: One of the maintenance switch is that the reduced settings are
lowest cost and most straightforward methods to only in place during maintenance and can be
reduce the incident energy exposure is to change switched back to the settings of the coordination
existing work procedures. One example of this study at the completion of the work task. Additional
would be changing the work location when contacts can be added to the maintenance switch
performing power quality measurements using a to monitor its status.
portable meter. Historically, measurements have
been performed by direct connection of the voltage •Retrofit / Replacement of Equipment: Retrofit or
and current probes to the primary circuit, where replace protective devices with devices that clear
incident energy can be relatively high. By taking faster at the respective arcing fault currents. This is
measurements utilizing the potential transformer often accomplished by changing fuse types, such
and current transformer circuits, one can as going from an RK5 fuse to an RK1 fuse or by
dramatically reduce the potential incident energy changing trip unit functions, such as going from a
exposure. Another example of procedure change trip unit that utilizes only the long time and
is to use a laser light beam for bus dimension instantaneous functions (LI) to a trip unit that
measurement on energized switchgear (see Figure utilizes long time, short time and instantaneous
1 below). (LSI) functions.
The study engineer should always attempt to accomplish the
incident energy reduction using the least-cost method first
(typically changing working practices or modifying existing
protective device settings). If these do not provide adequate
reduction, then more costly solutions such as device retrofit or
replacement may be required.
C. Revise Arc Flash Analysis
After determining the most appropriate incident energy
reduction methods for each location where the energy level is
too high, the initial arc flash analysis should be revised to
incorporate all changes. This updated arc flash analysis should
be used as the guide in upgrading and/or replacing equipment,
testing and setting all overcurrent protective devices,
purchasing PPE and printing arc flash warning labels for all
equipment locations where energized work may be performed.

III. IMPLEMENTATION OF STUDY RESULTS


Figure 1: Alternate Method for Bus Dimension
Measurement A. Adjustment, Retrofit, Equipment Modification, Replacement
• Modifying Existing Settings: Modify the existing Upon completion of the revised arc flash analysis,
protective device settings to decrease the clearing appropriate action must be taken to implement the proposed
time at the associated arcing fault current. Care modifications to the power system. Until these modifications
must be taken when implementing this solution, as have been made, arc flash labels displaying the results of the
protective device coordination may be affected revised analysis should not be posted.
when reducing the clearing time of protective The proposed corrections and changes should be prioritized
devices. according to the financial and logistical impact to the facility.
The energy reduction techniques are often be grouped
• Increasing Working Distance: Increase the working according to the following categories.
distance (where feasible) at specific locations in
order to reduce the calculated incident energy. • Adjustment: The reduction techniques corresponding to
Care must be taken when implementing this the fewest financial and logistical concerns are those
solution, as the goal is to provide a solution that still system adjustments and procedural adjustments that
allows personnel to feasibly perform work at each may be made immediately. Such techniques should be
location. Increasing the working distance may implemented prior to the application of labels and, as
hinder a person’s ability to work on the equipment. appropriate, should be immediately included as a part of
arc flash hazard training for affected workers. Examples
• Adding Maintenance Switches: The addition of a of such reduction techniques may include portable
“maintenance switch” allows personnel to reduce meter usage and some device setting adjustments.
the clearing time of a protective device by either
reducing the existing settings (typically used on • Retrofit: Arc flash energy reduction is often achieved by
low-voltage circuit breakers) or by switching to a retrofitting and upgrading trip units to provide a more
second settings group (typically used on medium- accurate (lower tolerances), more rapid, and more
voltage multi-function relays). The benefit of a customizable tripping response. Implementation
involves the purchase and installation of the new trip
unit and typically allows for a direct replacement without IV. ARC FLASH LABELING
the need to modify the equipment or enclosure.
Installing arc flash warning labels is one of the most critical
• Equipment Modification: Some reduction techniques
steps after completion of the arc flash analysis and
may require additional equipment modification for
implementation of the study results. It can also be one of the
complete implementation. For example, bus work,
most frustrating due to the countless decisions that must be
enclosure doors, hinges, and latches may need to be
made prior to installing the first label.
upgraded or replaced. These modifications do not
Prior to a determination of label content, label placement,
typically require that the entire lineup of equipment be
and label quantity, the calculation basis for the labels should be
replaced. For example, if a fuse should be replaced by a
defined.
circuit breaker or vice versa, the existing equipment
Proper arc flash calculations take several short circuit
(enclosure, footprint, etc.) may be sufficient, but some
contribution scenarios and determine the worst-case energy for
internal cell modifications may be required. TM
each system location. IEEE Std. 1584-2002 requires the
• Replacement: In some cases, the existing system minimum and maximum short circuit contributions be
components are simply insufficient to allow for the considered. Additional scenarios (switching, loading, utility
application of the required arc flash energy reduction contribution, generator contribution) may also be required,
techniques. In this case, replacement of the existing depending on the distribution system.
system components would be required. While this comparison of contribution scenarios is required
The proposed changes may also be prioritized according for the calculations, this information may or may not be included
frequency of access to each piece of equipment. For example, on the arc flash labels.
when a reduction technique is suggested for an area of the When the incident energy values listed on the arc flash
distribution system that is rarely accessed and the financial or warning labels are the worst-case incident energy values
logistical ramifications discourage implementation, these considering multiple system configurations, the qualified person
recommendations may be postponed or rejected in favor of may suit up according to the label and not have to consider the
simply identifying that particular space as “Dangerous”. It should particular system configuration at the time of the work.
then be communicated that locations labeled as “Dangerous” Some power systems may have a scenario that exists for a
may not be accessed under any circumstances when the particular switching condition that occurs for only a brief period
equipment is energized. If, at a later date, implementation is of time, e.g. one hour each year. The rest of the time, the
feasible (or required), the reduction technique and a new label normal scenario applies. When labels correspond to this
should be applied. infrequent configuration and display a high energy level and the
normal configuration(s) produce less energy, workers are
B. Test and Set All Overcurrent Protective Devices required to wear a higher level of PPE than necessary.
One solution to this dilemma is to provide labels based on a
In haste to apply arc flash labels to equipment, a very specified condition (for example the “normal” operating
important step of the study implementation is often neglected. condition). Training must then be provided to ensure that when
While it is important to make modifications discussed above, it the power system is not in “normal” mode, the qualified worker
is equally important to test and set all of the overcurrent must refer to the report document for the scenario that applies.
protective devices to ensure agreement with the software model This requires a reporting of all scenarios in the final report.
of the system. The arc flash calculations are based on the Once calculation scenarios have been determined, the label
operation of the overcurrent protection as represented in the content can be chosen.
model. If the model does not reflect the reality of the distribution
system, the arc flash calculations are invalidated. A. Minimum Content Requirements
When a complete system analysis has been conducted and
the coordination of the overcurrent protection has been Arc flash labels are required by the NEC (NFPA 70) in
evaluated, the model should be the recognized standard to section 110.16. The stipulations of this section do not specify
dictate the adjustment of the protective devices and any devices the content of the label, only that labels should warn of a
found to be contrary to the study model should be corrected. potential arc flash hazard. Several proposals have suggested
For each distribution system and device type, the process that this section be revised to explicitly require certain
for setting and testing will vary. Care should be taken if information to be included, but, to date, each has been rejected
adjustments are attempted while the associated circuit is and the determination of label content is left to the individual
energized. Some overcurrent devices will operate and open the facilities.
associated circuit breaker when adjustments are made. For B. Labeling Issues Not Clearly Addressed in Standards
others, adjustments may be made while online (closed), but
injection testing will be required to confirm the actual response Locations < 240 V fed by 125 kVA or Less: IEEE Std
TM
of the device in accordance with the expected operation. 1584 -2002 states that “equipment below 240 V need not be
For proper implementation of the recommended device considered unless it involves at least one 125 kVA or larger low-
settings and to confirm the existing settings as shown in the impedance transformer in its immediate power supply.” [2]
software model, an outage should be scheduled and the Therefore, 208 V locations are not typically included in an arc
devices should all be adjusted and tested before the application flash analysis unless they are fed from a transformer larger than
of arc flash labels to the equipment. 125 kVA. However, most facility owners want labels on all
panelboards. Therefore, while detailed calculations may not be
performed for 208 V locations supplied by a transformer smaller
than 125 kVA, labels should still be provided for these locations device found to eliminate the arcing event. This device
and are typically labeled as hazard risk category zero. name may be displayed on the label to aid in the
Single-phase and DC Equipment: Generic warning labels placement of the label. The label should be placed at
may be placed on single-phase and direct-current (DC) the specified location or Bus Name that is protected by
equipment, but no published standards presently provide the the listed device name.
calculation methods for these circuits. One should not assume This device name may be particularly important to
that there is no hazard at these locations, but any quantification reference the location of a maintenance switch (See
of energy will be based on preliminary testing, personal Special Cases below) that should be engaged before
experience, and reasonable hypothesis. accessing the equipment.
Equipment not Routinely Accessed: As stated in NEC It is important to recognize that the listed protective
Section 110.16, the labels are applicable to those locations device name may not reference the device most
“likely to require examination, adjustment, servicing or immediately upstream. Qualified electrical personnel
maintenance will energized.” [3] In contrast, labels do not need should be trained to recognize that this device should
to be applied to equipment locations that are not routinely not be assumed capable of de-energizing the
accessed while energized. For example, in most cases, equipment location. In the calculation model, this
transformers, junction boxes, and conduit need not be labeled. device may correspond to one of several fault
contributing branches.
C. Selecting Meaningful Information for Labels.
• Incident Energy: The calculated incident energy may
With this flexibility to customize the labels, care should be
be displayed on the arc flash label (along with an
given to provide adequate, meaningful information to qualified
associated working distance), but the presentation
persons without overwhelming the reader.
should be carefully considered.
Generic arc flash warning labels meet the minimum
The Hazard Risk Category corresponds to a range
requirements, but do not provide quantification of the hazard. A
of calculated energies. For example, Hazard Risk
qualified person is required by OSHA to be able to determine
Category 2 corresponds to an energy range between 4
the hazards and the boundaries associated with the work to be
and 8 cal/cm2. As a guideline, NFPA 70E-2004
performed. The Arc Flash Hazard and the associated Flash
suggests that for a given Hazard Risk Category, the
Protection Boundary are included in this requirement. If the arc
corresponding minimum arc rating of the PPE be
flash warning label does not display this information, the
specified according to the upper limit of the associate
qualified person must either determine the hazard(s) and the
range of energies.
boundaries by an approved calculation method or they are
However, some flexibility is permitted and when the
required to reference some previous documentation containing
actual incident energy level is displayed, the qualified
these calculations for the location in question.
person may be allowed to select their PPE according
The information on the labels should be selected to reflect
to that level of energy. For example, if the displayed
the established safety policy and procedures of a given facility. 2
energy is 5.3 cal/cm , the qualified person may safely
The labels should not be designed to replace or inclusively
elect to wear PPE sufficient for 6 cal/cm2. If this actual
duplicate to contents of the safety policy.
energy is not displayed in favor of an energy range, the
• Location or Bus Name: When the arc flash labels go qualified person is given no choice but to don the PPE
beyond the required minimum warning label and corresponding to the upper limit of the Hazard Risk
display information corresponding to specific Category range.
calculations, the equipment location should be
displayed to insure proper placement of the labels. • Shock Hazard Information: Shock Hazard information
This location name should be identical to the bus has been shown on arc flash labels in many
names used in the associated Arc Flash Analysis applications. However, it is not required nor is it
report so that the applied labels directly reference the typically desired on an arc flash label for two reasons.
calculations. The first reason is that shock hazard and arc flash are
not directly related by the same variables. Arc flash is
• Hazard Risk Category: Each arc flash calculation based upon a calculated fault current and a specific
determines an incident energy and a corresponding device clearing time while shock hazard is based upon
Hazard Risk Category. These categories are used to the voltage at the work location. The second reason is
direct qualified persons to wear appropriate Personal that in order to detail both Arc Flash and Shock hazard
Protective Equipment (PPE). This category should be information, the font on each label must be reduced to
included on the label. a small size that makes the labels more difficult to
read. If shock hazard boundary labels are required, it
• Flash Protection Boundary: The Flash Protection
is recommended by the authors that this information be
Boundary defines the distance from the exposed,
provided on a separate label.
energized part within which a qualified person must
wear the appropriate PPE. This boundary should be • Working Distance: Incident energy calculations are
displayed on the label so that workers do not need to typically provided at the recommended working
perform this calculation each time energized access is distances listed in IEEE Std 1584TM-2002. It may be
required. useful to provide incident energy values at additional
working distances in the study report, but for labeling
• Protective Device Name: The results from most power
purposes it is common practice to provide the incident
system analysis software will display the name of the
energy values based on the “typical” [2] working
TM
distances listed in IEEE Std 1584 -2002. This Values from Arc Flash Study Calculated
distance can be changed from “typical” to specific Energy Working Distance x
equipment enclosure dimensions and location of Y = E (D )
exposed energized parts if required on a case-by-case (cal/cm^2) Distance (in) Factor
basis. Refer to Figure 2 below for an example of a 4 18 1.473 1182.9288
spreadsheet that calculates the hazard at a different
distance from the study’s calculated IE values. This
can be performed when four calculated values are Enter New
provided: Working 36
Distance
1. Energy calculated by analysis.
2. Working Distance used to by the analysis
calculation. New
3. Distance factor associated with the analysis New
Calculated
calculation. 1.44 Calculated 1
4. Revised working distance for the proposed Energy
HRC
job task. (cal/cm^2)

The energy equation (Equation 1) from IEEE Std. Figure 2: Hazard Calculations at Multiple Working
1584-2002 may be simplified as shown by Equation 2 Distances
which has only three terms comprised of the energy,
calculated by the analysis, the working distance and
the distance factor used by the analysis calculation System Distance x
and everything else combined as represented by the
Equipment Type
Voltage (kV) Factor
letter “Y” in Equation 2.
0.208-15 kV Open Air or Cable 2
Equation 1
0.208-1 kV MCC and panels 1.641
⎛ t ⎞⎛ 610 ⎞
x
E = C f ∗ En ∗ ⎜ ⎜
⎟⎜ x ⎟⎟ 0.208-1 kV Switchgear 1.473
⎝ 0.2 ⎠⎝ D ⎠ 1-15 kV Switchgear 0.973
where:
2 Table 2: Distance Exponents for Distribution Equipment
E is incident energy in cal/cm
D is the working distance
x s the distance exponent • Settings Implemented Box: It may be desired that the
label include a method to track whether or not the
(The remaining constants and variables are defined in recommended settings in the study report were
IEEE Std 1584TM-2002, but are not required for this implemented in the field. This could be a blank line for
discussion.) the person’s initials and the date the settings were
implemented or some other method to allow the worker
Equation 2 who is referencing the label to determine if the settings
were indeed implemented.

( )
E Dx = Y D. Customized Labels for Special Cases

Once Y is determined, the working distance (D) may • Protective Devices with Multiple Settings: When a
be changed to suit a given job task. The distance protective device is capable of operating under multiple
exponent (x) is dependent on the equipment in settings or settings groups, it may be desirable to post
question and does not change. Table 2 shows the a special label that provides the hazard information for
distance exponents associated with various equipment both setting configurations. For example, if a
types. With Y, D, and x, a new energy is easily “maintenance switch (MS)” is installed to provide faster
determined. fault clearing time at a particular location, the hazard
without the use of the MS will be greater than when the
MS is engaged. It is important to direct qualified
persons to the location where the MS is to be engaged
and to warn of the hazard that is present when the MS
is not in use. Similar labels may be desirable when
overcurrent relays with selectable setting groups or
other MS configurations are used.
Below are a number of topics that should be included in Arc
E. Quantity of Labels Flash Hazard training:
It is common practice to provide one arc flash warning label • Review of the Arc Flash Hazard report results and
per equipment location studied. This label has generally been implementation of these results. For example,
located at the main protective device or incoming power maintenance procedures need to be re-evaluated
compartment. This label should contain sufficient information to to align with the results of the Arc Flash study and
describe the entire equipment location. A qualified person is it’s recommendations
responsible to properly apply the information to their job task(s). • Review of limits of the study scope of work. For
However, it has occasionally been requested that a label be example, the study may not have included the
placed on each “equipment compartment” with a benefit that the entire facility and there may be locations in the
worker does not have to find the main protective device or system that were not labeled yet.
incoming power compartment to find the arc flash warning label. • Review of the single line diagram contained in the
The major downside to this method is that “over-labeling” the Arc Flash Hazard report and the link between the
equipment leads to much higher and often unnecessary costs. single line and the Arc Flash Hazard labels.
There is also a possibility of an assumption that all • Include references from NFPA 70E-2004 in the
compartments may have the same hazard level when in reality, training program. Perform training for interpretation
compartments may have different hazard levels. and compliance with NFPA 70E-2004.
• Carry out training in the use and care of the specific
F. Printing and Applying Labels
PPE that will be used at the site.
• Printing Materials: Careful attention should be paid to • Include hands on training for donning and wearing
the quality and durability of the labels selected for all applicable PPE. Photos of a person wearing the
application. For clean, contained environments, labels correct PPE for each hazard category also provides
printed by an ink jet or laser jet printer may suffice. a good training aid. An example of this is shown in
These labels, however, may fade, smear, and lose Figure 3.
adhesion if exposed to direct sunlight, rain, cleaning
solvents, spills, oils, etc. For these environments, high
adhesion vinyl labels should be printed with a thermal-
transfer printer. Depending on the printer selected,
lamination may be required to protect the labels from
exposure to excessive wear.
• Installation of Labels: The general recommendation for
installing arc flash labels is to position them as close
as possible to the main protective device or incoming
power supply, at a height from the floor that allows the
labels to be clearly visible to most personnel. It is
important for the label placement to be standardized
throughout the facility so that qualified persons are
trained to refer to a specified location on the equipment
and are not required to search for haphazardly placed
labels.

V. ESTABLISH SAFE WORK PRACTICES

After completing the steps shown in Sections II, III and IV


Figure 3: Photo Demonstrating Proper HRC 2 PPE
above, it is then necessary to review the existing safe work
practices or create new safe work practices. Switching
procedures may also need to be revised or changed. • The training should be consistent (shift to shift or
Training is a critical component that is required to achieve a plant to plant).
successful Arc Flash safety program. This includes re-certifying • Training regarding work procedures shall address
employees on an annual basis. For guidance on this topic, refer such issues as:
to NFPA 70E-2004 Article 110 General Requirements for o Lock out/Tag out
Electrical Safety-Related Work Practices. o Reading Arc Flash Warning Labels and
wearing proper PPE
A. Train All Qualified Employees o Use of safe working practices during the
There is a need for different training, depending on job execution of the task.
requirements. For example, qualified electricians will require o If temporary fast settings are used to lower
more extensive training compared to the amount of training incident energy, then for each work
required by operators who may only be performing specific location that is affected, a work procedure
tasks such as switching electrical equipment on or off. or safety policy should be written to
require these alternate settings to be VII. CONCLUSION
engaged prior to work.
o Any new procedures that are required for The Arc Flash Safety Program is not complete after the
Arc Flash reduction need to be calculations are done. There are many other steps to be taken
demonstrated and practiced. For example, which include:
new techniques may be required to - Reducing the arc flash hazard at locations above
achieve temporary fast fault clearing time. acceptable thresholds
B. Evaluate and Purchase Appropriate Personal Protective - Implementation of the recommendations or changes
Equipment (PPE) - Communication and training to affected employees
- Proper and meaningful labeling
Several items should be considered during the process of In addition, there is ongoing maintenance required to
evaluating and purchasing the appropriate PPE, based on the achieve a successful arc flash safety program.
calculated energy levels at a facility. These considerations
include, but are not limited to: VIII. ACKNOWLEDGEMENT

• “Standard” HRC levels – determined during the The authors thank W. S. Vilcheck for his sponsorship,
review of study results stage. For example, in advice, and encouragement.
many cases, a choice of HRC 2 for everyday work
wear will make sense. IX. REFERENCES
• Questions such as: What does each employee
require? How many sets of PPE does each [1] Electrical Safety Requirements for Employee Workplaces, NFPA 70E-
employee need? Do all employees get the same 2004 ©NFPA.
PPE? Do some employees only get HRC 2 while [2] IEEE Guide for Performing Arc-Flash Hazard Calculations, IEEE Std
others may need HRC 4 as well? Should HRC 4 1584TM-2002.
PPE be issued on an individual basis or should it [3] National Electrical Code, NFPA 70
be purchased in a few sizes and put in a central
location where it is most likely needed?
• Other items to consider when evaluating PPE X. BIOGRAPHIES
include:
o Cost Wally Tinsley received a BSEE in 2001 from Clemson
o Quality University in South Carolina. Mr. Tinsley is currently employed
o Comfort - lightweight, breathable, etc. as a Power Systems Senior Engineer by Eaton Electrical where
o Wear Life he is a study engineer with a stated emphasis on arc flash
o Laundering methods - home or industrial analysis. Mr. Tinsley is the chairman of his group’s arc flash
o Coveralls versus shirt and pants committee and is responsible for the standardization and
o Flash suits versus layering to achieve improvement of arc flash analysis methods at Eaton Electrical.
HRC 4
Michael Hodder received a BASc in Electrical Engineering
VI. MAINTENANCE PROGRAM from University of Waterloo in 1977. Mr. Hodder is currently
employed as an Advisory Engineer with Eaton Electrical
Services and Systems, a Division of Eaton Corporation. He
Developing and sustaining a thorough maintenance program
presently performs power system studies and is a technical
is a crucial step in ensuring that the investment in an arc flash
trainer for Power System and Electrical Safety seminars. Mr.
program does not go to waste. A comprehensive maintenance
Hodder was previously employed by the Industry Services
program includes, at a minimum, the following three phases:
Division of Westinghouse Canada Inc. where he was
1. Work Procedures: Maintaining and/or updating work responsible for power system studies, testing, commissioning,
procedures to comply with the Arc Flash standards and startup and maintenance of power system installations. Mr.
report recommendations Hodder is a member of IEEE and a registered Professional
Engineer in Ontario. He is the author of several technical
2. Equipment Maintenance: Routine testing and cleaning of publications.
electrical equipment is essential in ensuring that all
equipment, most importantly the overcurrent protective Aidan M. Graham received the BSEE in 1998 and MSEE in
devices, will react appropriately during an arc flash 1999 from the University of Nevada, Reno. Mr. Graham is
event. currently employed as the Western Zone Team Leader for the
Power Systems Engineering Group at Eaton Electrical Services
3. Arc Flash Study: Updating and re-running the arc flash and Systems, a division of the Eaton Corporation. His core
analysis due to changes to the power distribution system responsibility is the management of all power system
is crucial to maintaining accurate arc flash calculations engineering business in the Western US. Mr. Graham is a
and arc flash warning labels. These system changes Senior Member of the IEEE and is a Registered Professional
can include modification to the utility distribution system Engineer in the State of Washington and Oregon. He is author
or equipment changes internal to the customer facility. of several technical publications.

Das könnte Ihnen auch gefallen