SPORTS FACILITY COMPLEX

LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

MAIN BUILDING REMARKS MATERIAL STATUS

000 MAIN ENTRANCE

1 Concrete Ramp Done as of 18 Sept. 2011 Okay

2 Steel Hand Rails On-going Delivery


Civil & Architectural

3 Non-Slip Ceramic Floor Tiles Done Okay

4 Aluminum Trellis (Canopy) and its Supports 07 Dec. 2011 On-going Delivery

5 Wall Painting (Final Coating) Done Okay

6 Epoxy Floor Painting (for Ramp) 26 Nov. 2011 Already In The Site

7 Rubber Floor Mat 15 Dec. 2011

Fixing of Granites

8 Fire Alarm Horn with Strobe Light Done Okay


Elect'l.

9 Wall-Mounted Luminaire (1 x 70 Watts) - 3 pcs. Done as of 06 Oct. 2011 Okay

001 LOBBY / WAITING AREA

1 Double-Leaf Doors (Type A) - 2 pcs. Done as of 06 Oct. 2011 Okay

2 Doors Accessories Done as of 06 Oct. 2011 Okay


Civil & Architectural

3 Completion of Ceiling Works Done as of 06 Oct. 2011 Okay

4 Wall Painting (Final Coating) Done Okay

5 Skirting Done Okay

6 Signages For Follow-up to the Supplier

7 Removable Low Partition 26 Nov. 2011 Delivered

8 Furnitures 26 Nov. 2011 Delivered

9 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Okay


Mech'l.

10 Fire Hose Cabinet 14 Dec. 2011 Already In The Site

11 Fire Alarm Horn Done as of 10 Sept. 2011 Okay

12 Fire Alarm Control Panel Done as of 06 Oct. 2011 Okay

13 Smoke Detectors - 2 pcs. Done as of 10 Sept. 2011 Okay


Electrical

14 Recessed-Mounted Luminaire - 12 pcs. Done as of 06 Oct. 2011 Okay

15 Emergency Lighting Units - 3 pcs. Done as of 06 Oct. 2011 Okay

16 Exit Lighting Units - 2 pcs. Done as of 06 Oct. 2011 Okay

17 Switches, Outlets and Covers 30 Nov. 2011

18 Cable Tray Done Okay


Communication

19 UTP (for Wall Mounted Telephone) Done Okay

20 UTP (for WLAN) Done Okay

21 Face plates / Covers Done Okay

Page 1 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

002 OFFICE

1 Door Accessories 07 Dec. 2011 Door Glass Balance

2 Windows; (Type - W03) - 2 pcs. + (Type - W04) - 1 pc. Done as of 06 Oct. 2011 Okay

3 Carpet Floor Tiles Done Okay


Civil & Architectural

4 Completion of Ceiling Works Done Okay

5 Wall Painting (Final Coating) Done Okay

6 Skirting Done Okay

7 Counter Table 07 Dec. 2011 For Delivery

8 Door Signage For Follow-up to the Supplier

9 Furnitures Done Okay

Mech'l. 10 Flexible Connections (for HVAC Diffusers) Done as of 06 Oct. 2011 Okay

11 Smoke Detector Done as of 10 Sept. 2011 Okay


Electrical

12 Fluorescent Lighting Fixtures (4 x 18 Watts) - (7 + 1) pcs. Done as of 10 Sept. 2011 Okay

13 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

14 UTP (for Voice and Data) Done Okay


Comm.

15 Face plates / Covers Done Okay

003 TOILET

1 Heavy Metal Doors (Type B & DA) and accessories 26 Nov. 2011 Already In The Site
Civil & Architectural

2 Wall Tiles Done as of 06 Oct. 2011 Okay

3 Ceiling Works Done Okay

4 Door Signage For Follow-up to the Supplier

5 Toilet Fixtures and Accessories 30 Nov. 2011 Partially Delivered

6 Flexible Connections (for Exhausts) Done as of 08 Sept. 2011 Okay


Mech'l.

7 Exhausts Okay

8 Sanitary Fixtures (for Handicap - 2 nos.) Done

9 Fluorescent Lighting Fixtures (2 x 18 Watts) - 2 pcs. 30 Nov. 2011 Waiting for delivery
Electrical

10 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

11 Hand Dryer 30 Nov. 2011 For Delivery

004 OFFICE

1 Door Accessories (Vision Glass) 07 Dec. 2011 Already In The Site

2 Window (Type - W03) Done as of 08 Sept. 2011 Okay


Civil & Architectural

3 Carpet Floor Tiles Done Okay

4 Ceiling Works Done Okay

5 Wall Painting (Final Coating) Done Okay

6 Skirting Done Okay

7 Furnitures Done Okay

Mech'l. 8 Flexible Connections (for HVAC Diffusers) Done Okay

9 Smoke Detector 30 Nov. 2011 Already In The Site


Electrical

10 Fluorescent Lighting Fixtures (4 x 18 Watts) - (3 + 1) pcs. Done Okay

Page 2 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
Electrical

DHAHRAN, K.S.A.

11 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

Page 3 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

12 UTP (for Voice and Data) Done Okay


Comm.

13 Face plates / Covers Done Okay

005 HALL WAY


Architectural

1 Completion of Ceiling Works Done Okay


Civil &

2 Wall Painting (Final Coating) Done Okay

3 Skirting Done Okay

4 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Okay


Mechanical

5 Fire Extinguisher Already In The Site

6 Drinking Fountain 17 Nov. 2011 For Delivery

7 Smoke Detector Done as of 10 Sept. 2011 Okay


Electrical

8 Fluorescent Lighting Fixtures (4 x 18 Watts), Electronic Ballast - (2 + 1) pcs. Done as of 10 Sept. 2011 Okay

9 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

Comm. 10 Cable Tray Done Okay

006 MALE TOILET

1 Door Accessories (Vision) 07 Dec. 2011 Already In The Site


Civil & Architectural

2 Ceiling Works Done Okay

3 Completion of Wall Tiles Done as of 06 Oct. 2011 Okay

4 Phenolic Partitions Done as of 06 Oct. 2011 Okay

5 Signages For Follow-up to the Supplier

6 Toilet Fixtures and Accessories 26 Nov. 2011 Already In The Site

7 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Okay


Mech'l.

8 HVAC Diffusers Done as of 06 Oct. 2011 Okay

9 Fluorescent Lighting Fixtures (2 x 18 Watts) - 6 pcs. Done as of 06 Oct. 2011 Okay


Electrical

10 Fluorescent Lighting Fixtures (2 x 36 Watts) - (1 + 1) pcs. Done as of 06 Oct. 2011 Okay

11 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

12 Hand Dryer 30 Nov. 2011 For Delivery

007 HALL WAY


Architectural

1 Remaining Ceiling Works 26 Nov. 2011 Already In The Site


Civil &

2 Completion of Wall Tiles Done as of 06 Oct. 2011 Okay

3 Signages For Follow-up to the Supplier

4 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Okay


Mechanical

5 HVAC Diffusers Done Okay

6 Drinking Fountain 17 Nov. 2011 For Delivery

7 Chilled Water Piping and Accessories 02 Dec. 2011 On-going

8 Fire Alarm Horn 30 Nov. 2011 Already In The Site

9 Smoke Detector 30 Nov. 2011 Already In The Site


Electrical

10 Fluorescent Lighting Fixtures (4 x 18 Watts) - (2 + 1) pcs. Done Okay

11 Exit Lighting Units - 2 pcs. Done as of 06 Oct. 2011 Okay

Page 4 of 65
SPORTS FACILITY COMPLEX
Electrical
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

12 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

Page 5 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

008 MALE LOCKER

1 Ceiling Works Done Okay


Architectural

2 Completion of Wall Tiles Done as of 06 Oct. 2011 Okay


Civil &

3 Lockers Done Okay

4 Signages For Follow-up to the Supplier

5 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Okay


Mech'l.

6 HVAC Diffusers Done as of 06 Oct. 2011 Okay

7 Smoke Detector Done as of 06 Oct. 2011 Okay


Electrical

8 Fluorescent Lighting Fixtures (2 x 36 Watts) - (2 + 1) pcs. Done as of 06 Oct. 2011 Okay

9 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

009 MALE SHOWER / DRESSING

1 Door Accessories (Shower Rooms) Done as of 06 Oct. 2011 Okay


Civil & Architectural

2 Ceiling Works Done Okay

3 Completion of Floor Tiles Done as of 06 Oct. 2011 Okay

4 Completion of Wall Tiles Done Okay

5 Showers and Accessories 26 Nov. 2011 For Delivery

6 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Okay


Mech'l.

7 HVAC Diffusers Done as of 06 Oct. 2011 Okay

8 Fluorescent Lighting Fixtures (2 x 18 Watts) - 8 pcs. Done as of 06 Oct. 2011 Okay


Electrical

9 Fluorescent Lighting Fixtures (2 x 36 Watts) - (1 + 1) pcs. Done as of 06 Oct. 2011 Okay

10 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

010 HALL WAY


Architectural

1 Completion of Ceiling Works Done Okay


Civil &

2 Wall Painting (Final Coating) Done Okay

3 Skirting Done Okay

4 Flexible Connections (for HVAC Diffusers) Done as of 06 Oct. 2011 Okay


Mechanical

5 HVAC Diffusers Done as of 06 Oct. 2011 Okay

6 Fire Extinguisher Already In The Site

7 Smoke Detector Done as of 06 Oct. 2011 Okay


Electrical

8 Fluorescent Lighting Fixtures (4 x 18 Watts) - (2 + 1) pcs. Done Okay

9 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

011 FEMALE TOILET

1 Door Accessories Done as of 06 Oct. 2011 Okay


Civil & Architectural

2 Ceiling Works Done Okay

3 Completion of Wall Tiles Done Okay

4 Phenolic Partitions Done as of 06 Oct. 2011 Okay

5 Signages For Follow-up to the Supplier

Page 6 of 65
Civil & Architectural
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

6 Toilet Fixtures and Accessories 26 Nov. 2011 Already In The Site

Page 7 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

7 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Okay


Mech'l.

8 HVAC Diffusers Done as of 17 Sept. 2011 Okay

9 Fire Alarm Horn with Strobe Light Already In The Site

10 Exit Lighting Unit Done as of 06 Oct. 2011 Okay


Electrical

11 Fluorescent Lighting Fixtures (2 x 36 Watts) - (4 + 1) pcs. Done as of 06 Oct. 2011 Okay

12 Fluorescent Lighting Fixtures (2 x 18 Watts) - 5 pcs. Done as of 06 Oct. 2011 Okay

13 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

14 Hand Dryer 30 Nov. 2011 For Delivery

012 FEMALE LOCKER

1 Ceiling Works Done Okay


Architectural

2 Completion of Wall Tiles Done Okay


Civil &

3 Lockers Done Okay

4 Signages For Follow-up to the Supplier

5 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Okay


Mech'l.

6 HVAC Diffusers Done as of 17 Sept. 2011 Okay

7 Smoke Detector Done as of 06 Oct. 2011 Okay


Electrical

8 Fluorescent Lighting Fixtures (2 x 36 Watts) - (1 + 1) pcs. Done as of 06 Oct. 2011 Okay

9 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

013 FEMALE SHOWER / DRESSING

1 Door Accessories (Shower Rooms) Done as of 06 Oct. 2011 Okay


Civil & Architectural

2 Ceiling Works Done Okay

3 Completion of Floor Tiles Done as of 06 Oct. 2011 Okay

4 Completion of Wall Tiles Done Okay

5 Showers and Accessories 26 Nov. 2011 For Delivery

6 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Okay


Mech'l.

7 HVAC Diffusers Done as of 06 Oct. 2011 Okay

8 Fluorescent Lighting Fixtures (2 x 18 Watts) - 8 pcs. Done as of 06 Oct. 2011 Okay


Electrical

9 Fluorescent Lighting Fixtures (2 x 36 Watts) - 2 pcs. Done as of 06 Oct. 2011 Okay

10 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

Page 8 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

014 FITNESS AREA

1 Doors Accessories 07 Dec. 2011 Already In The Site

2 Completion of Ceiling Works Done as of 06 Oct. 2011 Okay

3 Wall Painting (Final Coating) Done Okay

4 Skirting Done Okay


Civil & Architectural

5 Carpet Floor Tiles Done Okay

6 Wood Flooring Done Okay

7 Athletic Flooring 26 Nov. 2011 By Supplier

8 Steel Hand Rails 30 Nov. 2011 For Delivery

9 Concrete Ramp 26 Nov. 2011 Already In The Site

10 Fitness Equipments Done Okay

11 Signages For Follow-up to the Supplier

12 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Okay

13 Drinking Fountain 17 Nov. 2011 For Delivery


Mechanical

14 Chilled Water Piping and Accessories Done Okay

15 Fire Extinguisher Already In The Site

16 Fire Hose Cabinet 14 Dec. 2011 For Delivery

17 Fire Alarm Horn with Strobe Light - 2 pcs. Already In The Site

18 Smoke Detector - 6 pcs. Done as of 10 Sept. 2011 Okay

19 Exit Lighting Units - 2 pcs. Done as of 06 Oct. 2011 Okay


Electrical

20 Outdoor Luminaire ( 1 x 26 Watts) Done as of 06 Oct. 2011 Okay

21 Fluorescent Lighting Fixtures (4 x 36 Watts) - (37 + 9) pcs. 1 pc. not installed Already In The Site

22 Switches, Outlets and Covers Nov. 2011 For Delivery

23 Disconnection Switches Nov. 2011 Already In The Site

24 Pull Box Done as of 18 Sept. 2011 Okay


Comm.

25 UTP (for Wall Mounted Telephone) Done Okay

26 Face plates / Covers Done Okay

015 MECHANICAL ROOM

1 Double-Leaf Door (Type F) Done as of 12 Sept. 2011 Okay

2 Door Accessories Done Okay


Civil & Architectural

3 Wall Painting (Final Coating) Done Okay

4 Skirting Done Okay

5 Ceiling Final Painting 26 Nov. 2011 Already In The Site

6 Epoxy Floor Painting 26 Nov. 2011 Already In The Site

7 Signages For Follow-up to the Supplier

8 HVAC Equipment Duct Connections 14 Dec. 2011 Already In The Site

9 Fire Extinguisher Already In The Site


Mechanical

10 Electric Water Heaters 14 Dec. 2011 Already In The Site

11 Air Handling Unit For Installation Already In The Site

12 Chilled Water Piping and Accessories Already In The Site

Page 9 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

13 Fire Alarm Horn 30 Nov. 2011 Already In The Site

14 Smoke Detector - 3 pcs. Done as of 17 Sept. 2011 Okay


Electrical

15 Exit Light Installation 30 Nov. 2011 Already In The Site

16 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (4 + 2) pcs. 2 pcs not yet installed Already In The Site

17 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

18 UTP (for Wall Mounted Telephone) Done Okay


Comm.

19 Pull Box Done as of 17 Sept. 2011 Okay

19 Face plates / Covers Done Okay

016 GYMNASIUM

1 Doors Accessories Done Okay

2 Completion of Wall Insulations and Gypsum Board (Upper Level) 26 Nov. 2011 Already In The Site

3 Wall Finishing 26 Nov. 2011 Already In The Site


Civil & Architectural

4 Wall Paintings 26 Nov. 2011 Already In The Site

5 Floor Finishing (Impact Absorbing Flooring) 15 Dec. 2011 By Supplier

6 Basketbal Goal 26 Dec. 2011 For Approval

7 Bleachers 26 Dec. 2011 For Delivery

8 Steel Hand Rails 30 Nov. 2011 For Delivery

9 Signages For Follow-up to the Supplier

10 HVAC and Diffusers On-going Already In The Site

11 Completion of Air Ducts On-going Already In The Site


Mechanical

12 Roof Exhaust Fans For Installation Already In The Site

13 Fire Extinguisher Already In The Site

14 Fire Hose Cabinet 14 Dec. 2011 Already In The Site

15 Fire Alarm Horn with Strobe Light - 4 pcs. 30 Nov. 2011 Already In The Site

16 Outdoor Luminaire ( 1 x 26 Watts) - 3 pcs. Done as of 06 Oct. 2011 Okay

17 Exit Lighting Units - 4 pcs. 30 Nov. 2011 Already In The Site


Electrical

18 Emergency Lighting Units - 12 pcs. 30 Nov. 2011 Already In The Site

19 High-Bay Industrial Lighting Fixtures (1 x 250 Watts) - 30 pcs. Done Okay

20 Contactor Switches 30 Nov. 2011 Already In The Site

21 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

22 UTP (for Wall Mounted Telephone) Done Okay


Comm.

23 Face plates / Covers Waiting for wall paints Already In The Site

017 ELECTRICAL ROOM

1 Doors Accessories Done as of 06 Oct. 2011 Okay

2 Wall Painting (Final Coating) Done Okay


Civil & Architectural

3 Skirting Done Okay

4 Floor Finishing Done Okay

5 Epoxy Floor Painting Done Okay

6 Concrete Ramp Done Okay

Page 10 of 65
Civil & Architectural
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

7 Signages For Follow-up to the Supplier

Page 11 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019
ME

8 Fire Extinguisher Already In The Site

9 Fire Alarm Horn 30 Nov. 2011 Already In The Site

10 Smoke Detector 30 Nov. 2011 Already In The Site

11 Outdoor Luminaire ( 1 x 26 Watts) Done as of 06 Oct. 2011 Okay


Electrical

12 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (5 + 1) pcs. Done as of 12 Sept. 2011 Okay

13 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

14 Main Distribution Board, Distribution Panel and Panels Done For Termination

15 RGS Conduits (to Panel Boards)

16 Wires and Cable Termination

17 UTP (for Wall Mounted Telephone) 21 Nov. 2011 For Delivery


Comm.

18 Face plates / Covers 21 Nov. 2011 For Delivery

018 TELECOM ROOM

1 Doors Accessories Done Already In The Site


Civil & Architectural

2 Wall Finishing 26 Nov. 2011 Already In The Site

3 Skirting 17 Nov. 2011 Already In The Site

4 Floor Finishing Done Okay

5 Anti-Static Vinyl Tiles Done Okay

6 Signages For Follow-up to the Supplier

Mech'l. 7 Flexible Connections (for HVAC Diffusers) 14 Dec. 2011 Already In The Site

8 Smoke Detector 30 Nov. 2011 Already In The Site


Electrical

9 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (1 + 1) pcs. Done Okay

10 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

11 UTP (for Wall Mounted Telephone) Done Okay


Comm.

12 Face plates / Covers Done Okay

018A AIR LOCK

1 Doors Accessories Done Okay

2 Wall Painting (Final Coating) 26 Nov. 2011 Already In The Site


Civil & Architectural

3 Skirting 26 Nov. 2011 Already In The Site

4 Floor Finishing 17 Nov.2011 Already In The Site

5 Anti-Static Vinyl Tiles 19 Nov. 2011 For Delivery

6 Concrete Ramp Done Okay

7 Signages For Follow-up to the Supplier

Mech'l. 8 Fire Extinguisher Already In The Site

9 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted Done Okay


Electrical

10 Outdoor Luminaire ( 1 x 26 Watts) Done as of 06 Oct. 2011 Okay

11 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

Comm. 12 Card Reader For Approval

Page 12 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

019 STORAGE

1 Heavy Metal Door (Type GA) Done as of 15 Sept. 2011 Okay

2 Door Accessories Done as of 06 Oct. 2011 Okay


Civil & Architectural

3 Wall Painting (Final Coating) Done Okay

4 Skirting Done Okay

5 Floor Adjustment (Near Door) Done as of 06 Oct. 2011 Okay

6 Epoxy Floor Painting Done Okay

7 Signages For Follow-up to the Supplier

Mech'l. 8 Fire Extinguisher Already In The Site

9 Smoke Detector - 2 pcs. Done Okay


Electrical

10 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (4 + 2) pcs. Done as of 12 Sept. 2011 Okay

11 Switches, Outlets and Covers Done Okay

Comm. 12 Cable Tray Done as of 06 Oct. 2011 Okay

020 HALL WAY

1 Door Accessories Done Okay


Civil & Architectural

2 Ceiling Works Done Okay

3 Wall Painting (Final Coating) Done Okay

4 Skirting Done Okay

5 Signages For Follow-up to the Supplier

6 Flexible Connections (for HVAC Diffusers) Done Okay


Mech'l.

7 Chilled Water Pipes On-going Already In The Site

8 Smoke Detector - 2 pcs. Done as of 06 Oct. 2011 Okay

9 Fire Alarm Horn Done as of 06 Oct. 2011 Okay


Electrical

10 Fluorescent Lighting Fixtures (4 x 18 Watts), Electronic Ballast - (4 + 2) pcs. Done as of 06 Oct. 2011 Okay

11 Exit Lighting Units - 2 pcs. Done as of 06 Oct. 2011 Okay

12 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

13 Cable Tray Done Okay


Comm.

14 UTP (for Wall Mounted Telephone) Done Okay

15 Face plates / Covers Done Okay

021 MECHANICAL ROOM

1 Double-Leaf Door (Type F) Done Okay

2 Door Accessories Done Okay


Civil & Architectural

3 Wall Painting (Final Coating) Done Okay

4 Skirting 26 Nov. 2011 Already In The Site

5 Floor Finishing 20 Nov. 2011 Already In The Site

6 Epoxy Floor Painting 26 Nov. 2011 Already In The Site

7 Concrete Ramp Done Okay

8 Signages For Follow-up to the Supplier

Page 13 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

9 Tanks For Installation Already In The Site

10 Pumps Fire Pump only for approval Others are for delivery
Mechanical

11 Air Handling Unit For Installation Already In The Site

12 Electric Water Heaters 14 Dec. 2011 Already In The Site

14 Fire Extinguisher Already In The Site

15 HVAC Equipment Duct Connections

16 Smoke Detector - 3 pcs. 30 Nov. 2011 Already In The Site

17 Fire Alarm Horn 30 Nov. 2011 Already In The Site

18 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (4 + 4) pcs. Done as of 06 Oct. 2011 Okay
Electrical

19 Exit Lighting Unit 30 Nov. 2011 Already In The Site

20 Outdoor Luminaire ( 1 x 26 Watts) Done Okay

21 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

22 Testing and Commissioning

20 UTP (for Wall Mounted Telephone) Done Okay


Comm.

21 Face plates / Covers Done Okay

022 CHILLER ROOM

1 Door Accessories Done Okay

2 Wall Painting (Final Coating) Done Okay


Civil & Architectural

3 Skirting 30 Nov. 2011 Already In The Site

4 Floor Finishing 20 Nov. 2011 Already In The Site

5 Epoxy Floor Painting 26 Nov. 2011 Already In The Site

6 Concrete Ramps Done Okay

7 Signages For Follow-up to the Supplier

8 Recirculation Pumps For Installation Already In The Site

9 Pool Water Heater Done Okay


Mechanical

10 Sand Filters For Installation Already In The Site

11 Sodium Hypochlorite Tank For Installation Already In The Site

12 Fire Extinguisher Already In The Site

13 Smoke Detector Already In The Site

14 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (4 + 1) pcs. Done as of 12 Sept. 2011 Already In The Site
Electrical

15 Exit Lighting Unit 30 Nov. 2011 Already In The Site

16 Outdoor Luminaire ( 1 x 26 Watts) Done Okay

17 Panel Boards To Be Changed For Delivery

18 Switches, Outlets and Covers For Relocation Already In The Site

023 SAUNA

1 Wooden Panel Door (Type K) and its Accessories Done Okay


Civil & Architectural

2 Door Accessories Done Okay

3 Wall Finishing Done Okay

4 Concrete Flooring Done Okay

Page 14 of 65
Civil & Architectural
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

5 Signages For Follow-up to the Supplier

Page 15 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

6 Lightings and Fixtures N/S


Electrical

7 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

8 Panel Board Done Okay

024 JACUZZI

1 Wall Painting (Final Coating) 26 Nov. 2011 Already In The Site


Architectural

2 Skirting Done Okay


Civil &

3 Concrete Flooring (Kool Deck) Done Okay

4 Door Signage For Follow-up to the Supplier

5 Lightings and Fixtures N/S


Electrical

6 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

7 Panel Board Done Okay

025 OPEN COURT

1 Door Accessories Done as of 06 Oct. 2011 Okay

2 Windows (Type - W01) - 2 pcs. Done as of 06 Oct. 2011 Okay

3 Wall Painting (Final Coating) Done as of 12 Sept. 2011 Okay

4 Skirting Done Okay


Civil & Architectural

5 Floor Finishing 15 Dec. 2011 Already In The Site

6 Door Signages For Follow-up to the Supplier

7 Granite Pavers 15 Dec. 2011 For Delivery

8 Bench 07 Dec. 2011 Already In The Site

9 Plant Boxes 07 Nov. 2011 Already In The Site

10 Gravels 07 Nov. 2011 For Delivery

11 Plants Done Okay

12 Fire Alarm Horn Done Okay


Electrical

13 Indoor Luminaire ( 1 x 70 Watts) - 10 pcs. Done as of 06 Oct. 2011 Okay

14 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

026 STORAGE

1 Double-Leaf Door (Type F) Done as of 10 Sept. 2011 Okay


Civil & Architectural

2 Door Accessories Done as of 06 Oct. 2011 Okay

3 Wall Painting (Final Coating) Done as of 06 Oct. 2011 Okay

4 Skirting 26 Nov. 2011 Already In The Site

5 Epoxy Floor Painting Done Okay

6 Door Signage For Follow-up to the Supplier

7 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Okay


Mech'l.

8 Fire Extinguisher Already In The Site

9 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - 3 pcs. Done as of 12 Sept. 2011 Okay
Elect'l.

10 Switches, Outlets and Covers Done Okay

Page 16 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

027 OFFICE

1 Door Accessories (Vision Glass) 30 Nov. 2011 Already In The Site


Civil & Architectural

2 Completion of Ceiling Works Done as of 06 Oct. 2011 Okay

3 Wall Painting (Final Coating) Done Okay

4 Skirting 20 Nov. 2011 Already In The Site

5 Floor Tiles Done as of 06 Oct. 2011 Okay

6 Door Signage For Follow-up to the Supplier

Mech'l. 7 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Okay

8 Fluorescent Lighting Fixtures (4 x 18 Watts) - (5 + 1) pcs. Done as of 12 Sept. 2011 Okay


Elect'l.

9 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

10 UTP (for Voice and Data) - 2 pcs. Done Okay


Comm.

11 Face plates / Covers Done Okay

028 HALL WAY

1 Door Accessories Done Okay


Architectural

2 Completion of Ceiling Works Done as of 06 Oct. 2011 Okay


Civil &

3 Wall Painting (Final Coating) Done Okay

4 Skirting Done Okay

Mech'l. 5 Flexible Connections (for HVAC Diffusers) Done as of 06 Oct. 2011 Okay

6 Smoke Detector Done as of 12 Sept. 2011 Okay


Electrical

7 Fluorescent Lighting Fixtures (4 x 18 Watts), Electronic Ballast - (2 + 1) pcs. Done as of 06 Oct. 2011 Okay

8 Exit Lighting Unit Done as of 06 Oct. 2011 Okay

9 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

Comm. 10 Cable Tray Done Okay

029 TOILET

1 Door Accessories (Vision Glass) 30 Nov. 2011 Already In The Site


Civil & Architectural

2 Ceiling Works Done Okay

3 Completion of Wall Tiles Done as of 06 Oct. 2011 Okay

4 Signages For Follow-up to the Supplier

5 Toilet Fixtures and Accessories 26 Nov. 2011 Already In The Site

Mech'l. 6 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Okay

7 Fire Alarm Horn with Strobe Light 30 Nov. 2011 Already In The Site

8 Fluorescent Lighting Fixtures (2 x 18 Watts) - 4 pcs. 30 Nov. 2011 Already In The Site
Electrical

9 Fluorescent Lighting Fixtures (2 x 36 Watts) - (3 + 1) pcs. 30 Nov. 2011 Already In The Site

10 Exit Lighting Unit Done Okay

11 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

12 Hand Dryer 30 Nov. 2011 For Delivery

Page 17 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

030 SHOWER / DRESSING ROOM

1 Door Accessories Done as of 06 Oct. 2011 Okay


Civil & Architectural

2 Ceiling Works Done Okay

3 Completion of Wall Tiles Done Okay

4 Signages For Follow-up to the Supplier

5 Showers and Accessories 26 Nov. 2011 For Delivery

Mech'l. 6 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Okay

7 Fluorescent Lighting Fixtures (2 x 18 Watts) - 8 pcs. Done Okay


Electrical

8 Fluorescent Lighting Fixtures (2 x 36 Watts) - (1 + 1) pcs. Done Okay

9 Switches, Outlets and Covers Done Okay

031 LOCKER

1 Ceiling Works Done Okay


Architectural

2 Completion of Wall Tiles Done as of 12 Sept. 2011 Okay


Civil &

3 Lockers Done Okay

4 Signages For Follow-up to the Supplier

5 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Okay


Mech'l.

6 Fire Extinguisher Already In The Site

7 Smoke Detector Done Okay


Electrical

8 Fluorescent Lighting Fixtures (2 x 36 Watts) - (3 + 1) pcs. Done Okay

9 Exit Lighting Unit Done Okay

10 Switches, Outlets and Covers Done Okay

032 OPEN COURT

1 Door Accessories Done Okay

2 Wall Painting (Final Coating) Done Okay

3 Skirting Done Okay


Civil & Architectural

4 Tile Works (for Open Showers) Done Okay

5 Non-Skid Cement Flooring (Kool Deck) 07 Dec. 2011 For Pick-up

6 Sun Shades (Canopy) 26 Dec. 2011 For Delivery

7 Furnitures Done Okay

8 Concrete Ramps Done Okay

9 Signages For Follow-up to the Supplier

10 Showers and Accessories 26 Nov. 2011 For Delivery

Mech'l. 11 Drinking Fountain 17 Nov. 2011 For Delivery

12 Fire Alarm Horn with Strobe Light - 2 pcs. Done Okay

13 Outdoor Landscape Luminaire (1 x 100 Watts) - 24 pcs. 3 pcs not yet installed Already In The Site
Electrical

14 Exit Lighting Unit Done Okay

15 Outdoor Luminaire ( 1 x 26 Watts) Done as of 06 Oct. 2011 Okay

16 Switches, Outlets and Covers Done Okay

Page 18 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

17 UTP (for Wall Mounted Telephone) N/A For Delivery


Comm.

18 Face plates / Covers N/A For Delivery

SP SWIMMING POOL

1 Tile Works (around the Swimming Pool) Done Okay


C&A

2 Steel Hand Rails Sub-Con

3 Underwater Lights (100 Watts) - 12 pcs. Done as of 06 Oct. 2011 Okay


Elect'l.

4 Underwater Lights (300 Watts) - 8 pcs. Done as of 06 Oct. 2011 Okay

ME MAIN EXIT

1 Double-Leaf Door (Type E) Done as of 10 Sept. 2011 Okay

2 Door Accessories Done Okay

3 Window (Type - W01) Done as of 06 Oct. 2011 Okay


Civil & Architectural

4 Concrete Ramp Done Okay

5 Steel Hand Rails Done Okay

6 Non-Slip Ceramic Floor Tiles 30 Nov. 2011 For Delivery

7 Wall Painting (Final Coating) Done Okay

8 Skirting Done Okay

9 Epoxy Floor Painting (for Ramp) 26 Nov. 2011 Already In The Site

10 Rubber Floor Mat 15 Dec. 2011 For Delivery

11 Outdoor Luminaire ( 1 x 26 Watts) Done For Delivery


Elect'l.

12 Switches, Outlets and Covers 30 Nov. 2011 For Delivery

EW EXTERNAL WALLS

1 Completion of Wall Painting (Final Coating) 26 Nov. 2011 Already In The Site
C&A

2 Wall Grooves (for Pre-Cast Wall Joints) 26 Nov. 2011 Already In The Site

3 Cage Ladders Done as of 06 Oct. 2011 Okay

Elect'l. 4 Flood Lights (1 x 250 Watts) - 23 pcs. Done as of 06 Oct. 2011 Okay

RW ROOF WORKS

1 Crushed Stone Aggregates 07 Dec. 2011 For Delivery


C&A

2 Flushing Done as of 06 Oct. 2011 Okay

3 Sun Shades (Canopy) - Trellis 26 Dec. 2011 Already In The Site

Page 19 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

EXTERNAL AREAS

1 Completion of Concrete Walkways 26 Nov. 2011 Already In The Site

2 Completion of Plant Boxes 30 Nov. 2011 Already In The Site

3 Completion of Curb Stones On-going Already In The Site

4 Bleachers 15 Dec. 2011 Already In The Site


Civil & Architectural

5 Handrails

6 Asphalts By Supplier

7 Parking Sheds 15 Dec. 2011 Already In The Site

8 Concrete Pavers Hardscape 30 Nov. 2011 Partially Delivered

9 Landscaping Done Okay

10 Pedestals UP-1000 and bollards

11 Traffic Signs and Pavement Markings 26 Dec. 2011 Already In The Site

12 Curb Stone Painting 15 Dec. 2011 Already In The Site

13 Liquid Chiller 20 Dec. 2011 Already In The Site

14 Chilled Water Valve Box 20 Dec. 2011 Already In The Site

15 Irrigation Valve Box 18 Dec. 2011 Already In The Site


Mechanical

16 Irrigation Pump 15 Dec. 2011 For Delivery

17 Irrigation Piping Works 19 Dec. 2011 Already In The Site

18 Fire Hydrants 15 Dec. 2011 Already In The Site

19 Connection to existing domestic line

20 Connection to existing sewer line

21 Transformer / RMU (Testing and Commissioning) Done For Termination

22 Light Poles On-going For Delivery

23 Grounding Termination Done Okay


Electrical

24 Lightings and Fixtures Done Okay

25 Laying of cables (for Chiller and Pump Room)

26 Laying of copper and fiber optic cables

27 Testing and Commissioning

FIRE PUMP ROOM


Architectural

1 PEB Building Frames and Panels 30 Nov. 2011 For Delivery


Civil &

2 Wall Cladding 15 Dec. 2011 For Delivery

3 Roll-up Door 20 Dec. 2011 For Delivery

4 Mechanical Piping For Delivery


Mech'l.

5 Pumps Feb. 2012 For Delivery

6 Conduiting and Wiring On-going Already In The Site


Electrical

7 Wiring Devices On-going Already In The Site

8 Lightings and Fixtures On-going Already In The Site

Page 20 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

26-Nov-11 30-Nov-11

26-Nov-11 08-Dec-11

01-Dec-11 03-Dec-11

18-Dec-11 18-Dec-11

12-Nov-11 22-Nov-11

26-Dec-11 27-Dec-11

01-Dec-11 06-Dec-11

29-Nov-11 14-Dec-11

28-Nov-11 30-Nov-11

Page 21 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

07-Dec-11 07-Dec-11

07-Dec-11 08-Dec-11

26-Dec-11 27-Dec-11

28-Nov-11 30-Nov-11

23-Nov-11 26-Nov-11

26-Dec-11 27-Dec-11

30-Nov-11 01-Dec-11

01-Dec-11 01-Dec-11

29-Nov-11 30-Nov-11

01-Dec-11 01-Dec-11

08-Dec-11 08-Dec-11

03-Dec-11 03-Dec-11

Page 22 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

01-Dec-11 01-Dec-11

Page 23 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

14-Dec-11 14-Dec-11

03-Dec-11 04-Dec-11

03-Dec-11 03-Dec-11

10-Dec-11 10-Dec-11

26-Dec-11 27-Dec-11

30-Nov-11 03-Dec-11

03-Dec-11 03-Dec-11

04-Dec-11 04-Dec-11

12-Dec-11 18-Dec-11

26-Dec-11 27-Dec-11

05-Dec-11 06-Dec-11

26-Nov-11 11-Dec-11

06-Dec-11 06-Dec-11

05-Dec-11 05-Dec-11

Page 24 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

04-Dec-11 04-Dec-11

Page 25 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

26-Dec-11 27-Dec-11

05-Dec-11 05-Dec-11

04-Dec-11 05-Dec-11

06-Dec-11 06-Dec-11

15-Dec-11 15-Dec-11

07-Dec-11 07-Dec-11

26-Dec-11 27-Dec-11

Page 26 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

06-Dec-11 07-Dec-11

Page 27 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

08-Dec-11 08-Dec-11

10-Dec-11 10-Dec-11

26-Dec-11 27-Dec-11

10-Dec-11 10-Dec-11

08-Dec-11 10-Dec-11

11-Dec-11 11-Dec-11

Page 28 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

11-Dec-11 11-Dec-11

29-Nov-11 05-Dec-11

08-Dec-11 10-Dec-11

06-Dec-11 07-Dec-11

26-Dec-11 27-Dec-11

07-Dec-11 08-Dec-11

20-Dec-11 20-Dec-11

04-Dec-11 19-Dec-11

12-Dec-11 12-Dec-11

13-Dec-11 15-Dec-11

06-Dec-11 10-Dec-11

11-Dec-11 13-Dec-11

26-Dec-11 27-Dec-11

12-Dec-11 22-Dec-11

10-Dec-11 15-Dec-11

04-Dec-11 19-Dec-11

Page 29 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

07-Dec-11 07-Dec-11

08-Dec-11 08-Dec-11

13-Dec-11 13-Dec-11

12-Nov-11 27-Nov-11

12-Nov-11 21-Nov-11

22-Nov-11 01-Dec-11

03-Dec-11 18-Dec-11

19-Dec-11 29-Dec-11

24-Dec-11 29-Dec-11

28-Nov-11 01-Dec-11

26-Dec-11 27-Dec-11

26-Nov-11 01-Dec-11

24-Dec-11 24-Dec-11

07-Dec-11 22-Dec-11

08-Dec-11 10-Dec-11

11-Dec-11 12-Dec-11

11-Dec-11 12-Dec-11

13-Dec-11 13-Dec-11

Page 30 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

26-Dec-11 27-Dec-11

Page 31 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

11-Dec-11 11-Dec-11

15-Dec-11 15-Dec-11

08-Dec-11 14-Dec-11

11-Dec-11 21-Dec-11

28-Nov-11 04-Dec-11

26-Dec-11 27-Dec-11

03-Dec-11 15-Dec-11

15-Dec-11 15-Dec-11

17-Dec-11 17-Dec-11

28-Nov-11 14-Dec-11

01-Dec-11 04-Dec-11

26-Dec-11 27-Dec-11

25-Dec-11 25-Dec-11

Page 32 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

26-Dec-11 27-Dec-11

26-Dec-11 26-Dec-11

26-Dec-11 27-Dec-11

05-Dec-11 07-Dec-11

05-Dec-11 07-Dec-11

05-Dec-11 07-Dec-11

26-Dec-11 27-Dec-11

Page 33 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

13-Dec-11 19-Dec-11

27-Dec-11 27-Dec-11

14-Dec-11 27-Dec-11

20-Dec-11 20-Dec-11

19-Dec-11 19-Dec-11

21-Dec-11 21-Dec-11

18-Dec-11 18-Dec-11

25-Dec-11 31-Dec-11

26-Dec-11 27-Dec-11

Page 34 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

26-Dec-11 27-Dec-11

Page 35 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

19-Dec-11 19-Dec-11

01-Dec-11 03-Dec-11

26-Dec-11 27-Dec-11

20-Dec-11 20-Dec-11

08-Dec-11 15-Dec-11

26-Dec-11 27-Dec-11

08-Dec-11 15-Dec-11

17-Dec-11 19-Dec-11

20-Dec-11 22-Dec-11

21-Dec-11 21-Dec-11

08-Dec-11 10-Dec-11

26-Dec-11 27-Dec-11

28-Dec-11 28-Dec-11

Page 36 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

12-Dec-11 12-Dec-11

11-Dec-11 12-Dec-11

26-Dec-11 27-Dec-11

22-Dec-11 22-Dec-11

24-Dec-11 24-Dec-11

13-Dec-11 13-Dec-11

26-Dec-11 27-Dec-11

11-Dec-11 17-Dec-11

20-Dec-11 20-Dec-11

21-Dec-11 22-Dec-11

21-Dec-11 22-Dec-11

24-Dec-11 24-Dec-11

25-Dec-11 25-Dec-11

Page 37 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

26-Dec-11 27-Dec-11

18-Dec-11 19-Dec-11

26-Dec-11 27-Dec-11

28-Dec-11 28-Dec-11

13-Dec-11 28-Dec-11

26-Dec-11 27-Dec-11

18-Dec-11 19-Dec-11

10-Dec-11 11-Dec-11

Page 38 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

22-Dec-11 28-Dec-11

08-Dec-11 14-Dec-11

15-Dec-11 17-Dec-11

18-Dec-11 18-Dec-11

25-Dec-11 25-Dec-11

12-Nov-11 27-Nov-11

12-Nov-11 27-Nov-11

22-Dec-11 28-Dec-11

23-Nov-11 27-Dec-11

Page 39 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
DHAHRAN, K.S.A. PRELIMINARY PUNCH LISTS AS OF 02/12/2019

15-Dec-11 28-Dec-11

12-Nov-11 24-Nov-11

18-Dec-11 24-Dec-11

19-Dec-11 29-Dec-11

13-Dec-11 28-Dec-11

10-Dec-11 17-Dec-11

01-Dec-11 07-Dec-11

08-Dec-11 24-Dec-11

08-Dec-11 14-Dec-11

28-Nov-11 08-Dec-11

24-Nov-11 26-Nov-11

17-Dec-11 20-Dec-11

13-Dec-11 17-Dec-11

01-Dec-11 17-Dec-11

25-Dec-11 28-Dec-11

26-Nov-11 01-Dec-11

03-Dec-11 08-Dec-11

21-Dec-11 25-Dec-11

10-Dec-11 25-Dec-11

10-Dec-11 25-Dec-11

10-Dec-11 25-Dec-11

10-Dec-11 25-Dec-11

10-Dec-11 25-Dec-11

Page 40 of 65
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

TARGET
MAIN BUILDING REMARKS COMPLETION MATERIAL STATUS
DATE

000 MAIN ENTRANCE

1 Concrete Ramp Done as of 18 Sept. 2011 Completed

2 Steel Hand Rails Completed


Civil & Architectural

3 Non-Slip Ceramic Floor Tiles Done Completed

4 Aluminum Trellis (Canopy) and its Supports For Painting 08 Dec. 2011 Already In The Site

5 Wall Painting (Final Coating) Done Completed

6 Epoxy Floor Painting (for Ramp) 15 Dec. 2011 Already In The Site

7 Rubber Floor Mat 18 Dec. 2011

Fixing of Granites Done Completed

8 Fire Alarm Horn with Strobe Light Done Completed


Elect'l.

9 Wall-Mounted Luminaire (1 x 70 Watts) - 3 pcs. Done as of 06 Oct. 2011 Completed

001 LOBBY / WAITING AREA

1 Double-Leaf Doors (Type A) - 2 pcs. Done as of 06 Oct. 2011 Completed

2 Doors Accessories Done as of 06 Oct. 2011 Completed


Civil & Architectural

3 Completion of Ceiling Works Done as of 06 Oct. 2011 Completed

4 Wall Painting (Final Coating) Done Completed

5 Skirting Done Completed

6 Signages 27 Dec. 2011 For Follow-up to the Supplier

7 Removable Low Partition 20 Dec. 2011 For Details

8 Furnitures 1 sofa already in the area Delivered

9 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Completed


Mech'l.

10 Fire Hose Cabinet Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

11 Fire Alarm Horn Done as of 10 Sept. 2011 Completed

12 Fire Alarm Control Panel Done as of 06 Oct. 2011 Completed

13 Smoke Detectors - 2 pcs. Done as of 10 Sept. 2011 Completed


Electrical

14 Recessed-Mounted Luminaire - 12 pcs. Done as of 06 Oct. 2011 Completed

15 Emergency Lighting Units - 3 pcs. Done as of 06 Oct. 2011 Completed

16 Exit Lighting Units - 2 pcs. Done as of 06 Oct. 2011 Completed

17 Switches, Outlets and Covers Done Completed

18 Cable Tray Done Completed


Communication

19 UTP (for Wall Mounted Telephone) Done Completed

20 UTP (for WLAN) Done Completed

21 Face plates / Covers Done Completed

002 OFFICE

1 Door Accessories Done Completed

2 Windows; (Type - W03) - 2 pcs. + (Type - W04) - 1 pc. Done as of 06 Oct. 2011 Completed

3 Carpet Floor Tiles Done Completed


Civil & Architectural

4 Completion of Ceiling Works Done Completed

5 Wall Painting (Final Coating) Done Completed

6 Skirting Done Completed

7 Counter Table 16 Dec. 2011 For Delivery

8 Door Signage 27 Dec. 2011 For Follow-up to the Supplier

9 Furnitures Done Completed

Mech'l. 10 Flexible Connections (for HVAC Diffusers) Done as of 06 Oct. 2011 Completed

11 Smoke Detector Done as of 10 Sept. 2011 Completed


Electrical

12 Fluorescent Lighting Fixtures (4 x 18 Watts) - (7 + 1) pcs. Done as of 10 Sept. 2011 Completed

13 Switches, Outlets and Covers Done Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

14 UTP (for Voice and Data) Done Completed


Comm.

15 Face plates / Covers Done Completed

003 TOILET

1 Heavy Metal Doors (Type B & DA) and accessories 1 door already installed 26 Nov. 2011 Already In The Site
Civil & Architectural

2 Wall Tiles Done as of 06 Oct. 2011 Completed

3 Ceiling Works Done Completed

4 Door Signage 27 Dec. 2011 For Follow-up to the Supplier

5 Toilet Fixtures and Accessories No mirrors, liquid soap dispenser, etc. Already In The Site

6 Flexible Connections (for Exhausts) Done as of 08 Sept. 2011 Completed


Mech'l.

7 Exhausts Done Completed

8 Sanitary Fixtures (for Handicap - 2 nos.) Completed

9 Fluorescent Lighting Fixtures (2 x 18 Watts) - 2 pcs. Done Completed


Electrical

10 Switches, Outlets and Covers Done Completed

11 Hand Dryer 13 Dec. 2011 Matl @ Site

004 OFFICE

1 Door Accessories (Vision Glass) Done Completed

2 Window (Type - W03) Done as of 08 Sept. 2011 Completed


Civil & Architectural

3 Carpet Floor Tiles Done Completed

4 Ceiling Works Done Completed

5 Wall Painting (Final Coating) Done Completed

6 Skirting Done Completed

7 Furnitures Done Completed

Mech'l. 8 Flexible Connections (for HVAC Diffusers) Done Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

9 Smoke Detector Done Completed


Electrical

10 Fluorescent Lighting Fixtures (4 x 18 Watts) - (3 + 1) pcs. Done Completed

11 Switches, Outlets and Covers Done Completed

12 UTP (for Voice and Data) Done Completed


Comm.

13 Face plates / Covers Done Completed

005 HALL WAY


Architectural

1 Completion of Ceiling Works Done Completed


Civil &

2 Wall Painting (Final Coating) Done Completed

3 Skirting Done Completed

4 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Completed


Mechanical

5 Fire Extinguisher 14 Dec. 2011 Already In The Site

6 Drinking Fountain Completed

7 Smoke Detector Done as of 10 Sept. 2011 Completed


Electrical

8 Fluorescent Lighting Fixtures (4 x 18 Watts), Electronic Ballast - (2 + 1) pcs. Done as of 10 Sept. 2011 Completed

9 Switches, Outlets and Covers Done Completed

Comm. 10 Cable Tray Done Completed

006 MALE TOILET

1 Door Accessories (Vision) Done Completed


Civil & Architectural

2 Ceiling Works Done Completed

3 Completion of Wall Tiles Done as of 06 Oct. 2011 Completed

4 Phenolic Partitions Done as of 06 Oct. 2011 Completed

5 Signages 27 Dec. 2011 For Follow-up to the Supplier

6 Toilet Fixtures and Accessories Mirrors not yet fixed 15 Dec. 2011 Already In The Site

7 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Completed


Mech'l.

8 HVAC Diffusers Done as of 06 Oct. 2011 Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

9 Fluorescent Lighting Fixtures (2 x 18 Watts) - 6 pcs. Done as of 06 Oct. 2011 Completed


Electrical

10 Fluorescent Lighting Fixtures (2 x 36 Watts) - (1 + 1) pcs. Done as of 06 Oct. 2011 Completed

11 Switches, Outlets and Covers Done Completed

12 Hand Dryer Matl @ site

007 HALL WAY


Architectural

1 Remaining Ceiling Works 18 Dec. 2011 Already In The Site


Civil &

2 Completion of Wall Tiles Done as of 06 Oct. 2011 Completed

3 Signages 27 Dec. 2011 For Follow-up to the Supplier

4 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Completed


Mechanical

5 HVAC Diffusers Done Completed

6 Drinking Fountain For Connection 06 Dec. 2011 For Delivery

7 Chilled Water Piping and Accessories 11 Dec. 2011 On-going

8 Fire Alarm Horn Done Completed

9 Smoke Detector 05 Dec. 2011 Already In The Site


Electrical

10 Fluorescent Lighting Fixtures (4 x 18 Watts) - (2 + 1) pcs. Done Completed

11 Exit Lighting Units - 2 pcs. Done as of 06 Oct. 2011 Completed

12 Switches, Outlets and Covers Done Completed

008 MALE LOCKER

1 Ceiling Works Done Completed


Architectural

2 Completion of Wall Tiles Done as of 06 Oct. 2011 Completed


Civil &

3 Lockers Done Completed

4 Signages 27 Dec. 2011 For Follow-up to the Supplier

5 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Completed


Mech'l.

6 HVAC Diffusers Done as of 06 Oct. 2011 Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

7 Smoke Detector Done as of 06 Oct. 2011 Completed


Electrical

8 Fluorescent Lighting Fixtures (2 x 36 Watts) - (2 + 1) pcs. Done as of 06 Oct. 2011 Completed

9 Switches, Outlets and Covers Done Completed

009 MALE SHOWER / DRESSING

1 Door Accessories (Shower Rooms) Done as of 06 Oct. 2011 Completed


Civil & Architectural

2 Ceiling Works Done Completed

3 Completion of Floor Tiles Done as of 06 Oct. 2011 Completed

4 Completion of Wall Tiles Done Completed

5 Showers and Accessories No shower curtain, soap holder, etc.

6 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Completed


Mech'l.

7 HVAC Diffusers Done as of 06 Oct. 2011 Completed

8 Fluorescent Lighting Fixtures (2 x 18 Watts) - 8 pcs. Done as of 06 Oct. 2011 Completed


Electrical

9 Fluorescent Lighting Fixtures (2 x 36 Watts) - (1 + 1) pcs. Done as of 06 Oct. 2011 Completed

10 Switches, Outlets and Covers Done Completed

010 HALL WAY


Architectural

1 Completion of Ceiling Works Done Completed


Civil &

2 Wall Painting (Final Coating) Done Completed

3 Skirting Done Completed

4 Flexible Connections (for HVAC Diffusers) Done as of 06 Oct. 2011 Completed


Mechanical

5 HVAC Diffusers Done as of 06 Oct. 2011 Completed

6 Fire Extinguisher 15 Dec. 2011 Already In The Site

7 Smoke Detector Done as of 06 Oct. 2011 Completed


Electrical

8 Fluorescent Lighting Fixtures (4 x 18 Watts) - (2 + 1) pcs. Done Completed

9 Switches, Outlets and Covers Done Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

011 FEMALE TOILET

1 Door Accessories Done as of 06 Oct. 2011 Completed


Civil & Architectural

2 Ceiling Works Done Completed

3 Completion of Wall Tiles Done Completed

4 Phenolic Partitions Done as of 06 Oct. 2011 Completed

5 Signages 27 Dec. 2011 For Follow-up to the Supplier

6 Toilet Fixtures and Accessories Mirrors not yet fixed 15 Dec. 2011 Already In The Site

7 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Completed


Mech'l.

8 HVAC Diffusers Done as of 17 Sept. 2011 Completed

9 Fire Alarm Horn with Strobe Light Done Completed

10 Exit Lighting Unit Done as of 06 Oct. 2011 Completed


Electrical

11 Fluorescent Lighting Fixtures (2 x 36 Watts) - (4 + 1) pcs. Done as of 06 Oct. 2011 Completed

12 Fluorescent Lighting Fixtures (2 x 18 Watts) - 5 pcs. Done as of 06 Oct. 2011 Completed

13 Switches, Outlets and Covers Done Completed

14 Hand Dryer Matl @ site

012 FEMALE LOCKER

1 Ceiling Works Done Completed


Architectural

2 Completion of Wall Tiles Done Completed


Civil &

3 Lockers Done Completed

4 Signages 27 Dec. 2011 For Follow-up to the Supplier

5 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Completed


Mech'l.

6 HVAC Diffusers Done as of 17 Sept. 2011 Completed

7 Smoke Detector Done as of 06 Oct. 2011 Completed


Electrical

8 Fluorescent Lighting Fixtures (2 x 36 Watts) - (1 + 1) pcs. Done as of 06 Oct. 2011 Completed

9 Switches, Outlets and Covers Done Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

013 FEMALE SHOWER / DRESSING

1 Door Accessories (Shower Rooms) Done as of 06 Oct. 2011 Completed


Civil & Architectural

2 Ceiling Works Done Completed

3 Completion of Floor Tiles Done as of 06 Oct. 2011 Completed

4 Completion of Wall Tiles Done Completed

5 Showers and Accessories No shower curtain, soap holder, etc.

6 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Completed


Mech'l.

7 HVAC Diffusers Done as of 06 Oct. 2011 Completed

8 Fluorescent Lighting Fixtures (2 x 18 Watts) - 8 pcs. Done as of 06 Oct. 2011 Completed


Electrical

9 Fluorescent Lighting Fixtures (2 x 36 Watts) - 2 pcs. Done as of 06 Oct. 2011 Completed

10 Switches, Outlets and Covers Done Completed

014 FITNESS AREA

1 Doors Accessories Done Completed

2 Completion of Ceiling Works Done as of 06 Oct. 2011 Completed

3 Wall Painting (Final Coating) Done Completed

4 Skirting Done Completed


Civil & Architectural

5 Carpet Floor Tiles Done Completed

6 Wood Flooring Done Completed

7 Athletic Flooring Done Completed

8 Steel Hand Rails Done Completed

9 Concrete Steps Done Completed

10 Fitness Equipments Done Completed

11 Signages 27 Dec. 2011 For Follow-up to the Supplier


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

12 Flexible Connections (for HVAC Diffusers) Done as of 08 Sept. 2011 Completed

13 Drinking Fountain Completed


Mechanical

14 Chilled Water Piping and Accessories Done Completed

15 Fire Extinguisher 20 Dec. 2011 Already In The Site

16 Fire Hose Cabinet Done Completed

17 Fire Alarm Horn with Strobe Light - 2 pcs. Done Completed

18 Smoke Detector - 6 pcs. Done as of 10 Sept. 2011 Completed

19 Exit Lighting Units - 2 pcs. Done as of 06 Oct. 2011 Completed


Electrical

20 Outdoor Luminaire ( 1 x 26 Watts) Done as of 06 Oct. 2011 Completed

21 Fluorescent Lighting Fixtures (4 x 36 Watts) - (37 + 9) pcs. Done Completed

22 Switches, Outlets and Covers Done Completed

23 Disconnection Switches Done Completed

24 Pull Box Done as of 18 Sept. 2011 Completed


Comm.

25 UTP (for Wall Mounted Telephone) Done Completed

26 Face plates / Covers Done Completed

015 MECHANICAL ROOM

1 Double-Leaf Door (Type F) Done as of 12 Sept. 2011 Completed

2 Door Accessories Done Completed


Civil & Architectural

3 Wall Painting (Final Coating) On-going

4 Skirting On-going

5 Ceiling Final Painting On-going

6 Epoxy Floor Painting 13 Dec. 2011 Already In The Site

7 Signages 27 Dec. 2011 For Follow-up to the Supplier


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

8 HVAC Equipment Duct Connections 22 Dec. 2011 Already In The Site

9 Fire Extinguisher 20 Dec. 2011 Already In The Site


Mechanical

10 Electric Water Heaters 15 Dec. 2011 Already In The Site

11 Air Handling Unit For Installation Already In The Site

12 Chilled Water Piping and Accessories 19 Dec. 2011 Already In The Site

13 Fire Alarm Horn Done Completed

14 Smoke Detector - 3 pcs. Done as of 17 Sept. 2011 Completed


Electrical

15 Exit Light Installation 08 Dec. 2011 Already In The Site

16 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (4 + 2) pcs. 2 pcs not yet installed Already In The Site

17 Switches, Outlets and Covers 13 Dec. 2011 For Delivery

18 UTP (for Wall Mounted Telephone) Done Completed


Comm.

19 Pull Box Done as of 17 Sept. 2011 Completed

19 Face plates / Covers Done Completed

016 GYMNASIUM

1 Doors Accessories Done Completed

2 Completion of Wall Insulations and Gypsum Board (Upper Level) Done Completed

3 Wall Finishing On-going 21 Dec. 2011 Already In The Site


Civil & Architectural

4 Wall Paintings On-going 25 Dec. 2011 Already In The Site

5 Floor Finishing (Impact Absorbing Flooring) Done Completed

6 Basketbal Goal 29 Dec. 2011 For Approval

7 Bleachers 29 Dec. 2011 For Delivery

8 Steel Hand Rails Done Completed

9 Signages 27 Dec. 2011 For Follow-up to the Supplier


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

10 HVAC and Diffusers Done Completed

11 Completion of Air Ducts Done Completed


Mechanical

12 Roof Exhaust Fans For Installation 01 Dec. 2011 Already In The Site

13 Fire Extinguisher 24 Dec. 2011 Already In The Site

14 Fire Hose Cabinet 22 Dec. 2011 Already In The Site

15 Fire Alarm Horn with Strobe Light - 4 pcs. 10 Dec. 2011 Already In The Site

16 Outdoor Luminaire ( 1 x 26 Watts) - 3 pcs. Done as of 06 Oct. 2011 Completed

17 Exit Lighting Units - 4 pcs. 12 Dec. 2011 Already In The Site


Electrical

18 Emergency Lighting Units - 12 pcs. 12 Dec. 2011 Already In The Site

19 High-Bay Industrial Lighting Fixtures (1 x 250 Watts) - 30 pcs. Done Completed

20 Contactor Switches For Installation Already In The Site

21 Switches, Outlets and Covers 13 Dec. 2011 For Delivery

22 UTP (for Wall Mounted Telephone) Done Completed


Comm.

23 Face plates / Covers Waiting for wall paints Already In The Site

017 ELECTRICAL ROOM

1 Doors Accessories Done as of 06 Oct. 2011 Completed

2 Wall Painting (Final Coating) 26 Dec. 2011


Civil & Architectural

3 Skirting 28 Dec. 2011

4 Floor Finishing 22 Dec. 2011

5 Epoxy Floor Painting 28 Dec. 2011

6 Concrete Ramp Done Completed

7 Signages 27 Dec. 2011 For Follow-up to the Supplier


ME

8 Fire Extinguisher Already In The Site


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

9 Fire Alarm Horn 11 Dec. 2011 Already In The Site

10 Smoke Detector Already In The Site

11 Outdoor Luminaire ( 1 x 26 Watts) Done as of 06 Oct. 2011 Completed


Electrical

12 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (5 + 1) pcs. Done as of 12 Sept. 2011 Completed

13 Switches, Outlets and Covers 15 Dec. 2011 For Delivery

14 Main Distribution Board, Distribution Panel and Panels Done For Termination

15 RGS Conduits (to Panel Boards) 14 Dec. 2011

16 Wires and Cable Termination 21 Dec. 2011

17 UTP (for Wall Mounted Telephone) For Delivery


Comm.

18 Face plates / Covers For Delivery

018 TELECOM ROOM

1 Doors Accessories Done Completed


Civil & Architectural

2 Wall Finishing Done Completed

3 Skirting Done Completed

4 Floor Finishing Done Completed

5 Anti-Static Vinyl Tiles Done Completed

6 Signages 27 Dec. 2011 For Follow-up to the Supplier

Mech'l. 7 Flexible Connections (for HVAC Diffusers) 15 Dec. 2011 Already In The Site

8 Smoke Detector Done Completed


Electrical

9 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (1 + 1) pcs. Done Completed

10 Switches, Outlets and Covers Done Completed

11 UTP (for Wall Mounted Telephone) Done Completed


Comm.

12 Face plates / Covers Done Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

018A AIR LOCK

1 Doors Accessories Done Completed

2 Wall Painting (Final Coating) 14 Dec. 2011 Already In The Site


Civil & Architectural

3 Skirting Already In The Site

4 Floor Finishing Already In The Site

5 Anti-Static Vinyl Tiles 04 Dec. 2011 For Delivery

6 Concrete Ramp Done Completed

7 Signages 27 Dec. 2011 For Follow-up to the Supplier

Mech'l. 8 Fire Extinguisher 25 Dec. 2011 Already In The Site

9 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted Done Completed


Electrical

10 Outdoor Luminaire ( 1 x 26 Watts) Done as of 06 Oct. 2011 Completed

11 Switches, Outlets and Covers For Delivery

Comm. 12 Card Reader For Approval

019 STORAGE

1 Heavy Metal Door (Type GA) Done Completed

2 Door Accessories Done Completed


Civil & Architectural

3 Wall Painting (Final Coating) Done Completed

4 Skirting Done Completed

5 Floor Adjustment (Near Door) Done as of 06 Oct. 2011 Completed

6 Epoxy Floor Painting Done Completed

7 Signages 27 Dec. 2011 For Follow-up to the Supplier

Mech'l. 8 Fire Extinguisher 26 Dec. 2011 Already In The Site

9 Smoke Detector - 2 pcs. Done Completed


Electrical

10 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (4 + 2) pcs. Done as of 12 Sept. 2011 Completed

11 Switches, Outlets and Covers Done Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

Comm. 12 Cable Tray Done as of 06 Oct. 2011 Completed

020 HALL WAY

1 Door Accessories Done Completed


Civil & Architectural

2 Ceiling Works Done Completed

3 Wall Painting (Final Coating) Done Completed

4 Skirting Done Completed

5 Signages 27 Dec. 2011 For Follow-up to the Supplier

6 Flexible Connections (for HVAC Diffusers) Done Completed


Mech'l.

7 Chilled Water Pipes On-going Already In The Site

8 Smoke Detector - 2 pcs. Done as of 06 Oct. 2011 Completed

9 Fire Alarm Horn Done as of 06 Oct. 2011 Completed


Electrical

10 Fluorescent Lighting Fixtures (4 x 18 Watts), Electronic Ballast - (4 + 2) pcs. Done as of 06 Oct. 2011 Completed

11 Exit Lighting Units - 2 pcs. Done as of 06 Oct. 2011 Completed

12 Switches, Outlets and Covers Done Completed

13 Cable Tray Done Completed


Comm.

14 UTP (for Wall Mounted Telephone) Done Completed

15 Face plates / Covers Done Completed

021 MECHANICAL ROOM

1 Double-Leaf Door (Type F) Done Completed

2 Door Accessories Done Completed


Civil & Architectural

3 Wall Painting (Final Coating) Done Completed

4 Skirting 07 Dec. 2011 Already In The Site

5 Floor Finishing 07 Dec. 2011 Already In The Site

6 Epoxy Floor Painting 07 Dec. 2011 Already In The Site

7 Concrete Ramp Done Completed


Civil & Archit
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

8 Signages 27 Dec. 2011 For Follow-up to the Supplier


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

9 Tanks For Installation Already In The Site

10 Pumps Fire Pump only for approval Others are for delivery
Mechanical

11 Air Handling Unit For Installation Already In The Site

12 Electric Water Heaters 19 Dec. 2011 Already In The Site

14 Fire Extinguisher 27 Dec. 2011 Already In The Site

15 HVAC Equipment Duct Connections 27 Dec. 2011

16 Smoke Detector - 3 pcs. 20 Dec. 2011 Already In The Site

17 Fire Alarm Horn 19 Dec. 2011 Already In The Site

18 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (4 + 4) pcs. Done as of 06 Oct. 2011 Completed
Electrical

19 Exit Lighting Unit 21 Dec. 2011 Already In The Site

20 Outdoor Luminaire ( 1 x 26 Watts) Done Completed

21 Switches, Outlets and Covers 18 Dec. 2011 For Delivery

22 Testing and Commissioning 31 Dec. 2011

20 UTP (for Wall Mounted Telephone) Done Completed


Comm.

21 Face plates / Covers Done Completed

022 CHILLER ROOM

1 Door Accessories Done (under new Change Order) Completed

2 Wall Painting (Final Coating) Done (under new Change Order) Completed
Civil & Architectural

3 Skirting Done (under new Change Order) Already In The Site

4 Floor Finishing Under new change order Already In The Site

5 Epoxy Floor Painting Under new change order Already In The Site

6 Concrete Ramps Done Completed

7 Signages 27 Dec. 2011 For Follow-up to the Supplier


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

8 Recirculation Pumps For Installation Already In The Site

9 Pool Water Heater Done Completed


Mechanical

10 Sand Filters For Installation Already In The Site

11 Sodium Hypochlorite Tank For Installation Already In The Site

12 Fire Extinguisher 27 Dec. 2011 Already In The Site

13 Smoke Detector Under new change order Already In The Site

14 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - (4 + 1) pcs. Done as of 12 Sept. 2011 Already In The Site
Electrical

15 Exit Lighting Unit Under new change order Already In The Site

16 Outdoor Luminaire ( 1 x 26 Watts) Done Completed

17 Panel Boards Under new change order For Delivery

18 Switches, Outlets and Covers Under new change order Already In The Site

023 SAUNA

1 Wooden Panel Door (Type K) and its Accessories Done Completed


Civil & Architectural

2 Door Accessories Done Completed

3 Wall Finishing Done Completed

4 Concrete Flooring Done Completed

5 Signages 27 Dec. 2011 For Follow-up to the Supplier

6 Switches, Outlets and Covers 19 Dec. 2011 For Delivery

7 Panel Board Done Completed

024 JACUZZI

1 Wall Painting (Final Coating) 03 Dec. 2011 Already In The Site


Architectural

2 Skirting Done Completed


Civil &

3 Concrete Flooring (Kool Deck) Done Completed

4 Door Signage 27 Dec. 2011 For Follow-up to the Supplier


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

5 Switches, Outlets and Covers 20 Dec. 2011 For Delivery

6 Panel Board Done Completed

025 OPEN COURT

1 Door Accessories Done as of 06 Oct. 2011 Completed

2 Windows (Type - W01) - 2 pcs. Done as of 06 Oct. 2011 Completed

3 Wall Painting (Final Coating) Done as of 12 Sept. 2011 Completed

4 Skirting Done Completed


Civil & Architectural

5 Floor Finishing 15 Dec. 2011 Already In The Site

6 Door Signages 27 Dec. 2011 For Follow-up to the Supplier

7 Granite Pavers On-going 15 Dec. 2011 For Delivery

8 Bench 19 Dec. 2011 Already In The Site

9 Plant Boxes 22 Dec. 2011 Already In The Site

10 Gravels For Delivery

11 Plants Done Completed

12 Fire Alarm Horn Done Completed


Electrical

13 Indoor Luminaire ( 1 x 70 Watts) - 10 pcs. Done as of 06 Oct. 2011 Completed

14 Switches, Outlets and Covers 21 Dec. 2011 For Delivery

026 STORAGE

1 Double-Leaf Door (Type F) Done as of 10 Sept. 2011 Completed


Civil & Architectural

2 Door Accessories Done as of 06 Oct. 2011 Completed

3 Wall Painting (Final Coating) Done as of 06 Oct. 2011 Completed

4 Skirting 10 Dec. 2011 Already In The Site

5 Epoxy Floor Painting Done Completed

6 Door Signage 27 Dec. 2011 For Follow-up to the Supplier


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

7 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Completed


Mech'l.

8 Fire Extinguisher 28 Dec. 2011 Already In The Site

9 Fluorescent Lighting Fixtures (2 x 36 Watts), Surface-Mounted - 3 pcs. Done as of 12 Sept. 2011 Completed
Elect'l.

10 Switches, Outlets and Covers Done Completed

027 OFFICE

1 Door Accessories (Vision Glass) Done Completed


Civil & Architectural

2 Completion of Ceiling Works Done as of 06 Oct. 2011 Completed

3 Wall Painting (Final Coating) Done Completed

4 Skirting Done Completed

5 Floor Tiles Done as of 06 Oct. 2011 Completed

6 Door Signage 27 Dec. 2011 For Follow-up to the Supplier

Mech'l. 7 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Completed

8 Fluorescent Lighting Fixtures (4 x 18 Watts) - (5 + 1) pcs. Done as of 12 Sept. 2011 Completed


Elect'l.

9 Switches, Outlets and Covers Done Completed

10 UTP (for Voice and Data) - 2 pcs. Done Completed


Comm.

11 Face plates / Covers Done Completed

028 HALL WAY

1 Door Accessories Done Completed


Architectural

2 Completion of Ceiling Works Done as of 06 Oct. 2011 Completed


Civil &

3 Wall Painting (Final Coating) Done Completed

4 Skirting Done Completed

Mech'l. 5 Flexible Connections (for HVAC Diffusers) Done as of 06 Oct. 2011 Completed
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

6 Smoke Detector Done as of 12 Sept. 2011 Completed


Electrical

7 Fluorescent Lighting Fixtures (4 x 18 Watts), Electronic Ballast - (2 + 1) pcs. Done as of 06 Oct. 2011 Completed

8 Exit Lighting Unit Done as of 06 Oct. 2011 Completed

9 Switches, Outlets and Covers Done Completed

Comm. 10 Cable Tray Done Completed

029 TOILET

1 Door Accessories (Vision Glass) Done Completed


Civil & Architectural

2 Ceiling Works Done Completed

3 Completion of Wall Tiles Done as of 06 Oct. 2011 Completed

4 Signages 27 Dec. 2011 For Follow-up to the Supplier

5 Toilet Fixtures and Accessories Mirrors not yet fixed 17 Dec. 2011 Already In The Site

Mech'l. 6 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Completed

7 Fire Alarm Horn with Strobe Light Done Completed

8 Fluorescent Lighting Fixtures (2 x 18 Watts) - 4 pcs. Done Completed


Electrical

9 Fluorescent Lighting Fixtures (2 x 36 Watts) - (3 + 1) pcs. Done Completed

10 Exit Lighting Unit Done Completed

11 Switches, Outlets and Covers Done Completed

12 Hand Dryer 25 Dec. 2011 For Delivery

030 SHOWER / DRESSING ROOM

1 Door Accessories Done as of 06 Oct. 2011 Completed


Civil & Architectural

2 Ceiling Works Done Completed

3 Completion of Wall Tiles Done Completed

4 Signages 27 Dec. 2011 For Follow-up to the Supplier

5 Showers and Accessories Done Completed

Mech'l. 6 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Completed
SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

7 Fluorescent Lighting Fixtures (2 x 18 Watts) - 8 pcs. Done Completed


Electrical

8 Fluorescent Lighting Fixtures (2 x 36 Watts) - (1 + 1) pcs. Done Completed

9 Switches, Outlets and Covers Done Completed

031 LOCKER

1 Ceiling Works Done Completed


Architectural

2 Completion of Wall Tiles Done as of 12 Sept. 2011 Completed


Civil &

3 Lockers Done Completed

4 Signages 27 Dec. 2011 For Follow-up to the Supplier

5 Flexible Connections (for HVAC Diffusers) Done as of 12 Sept. 2011 Completed


Mech'l.

6 Fire Extinguisher 28 Dec. 2011 Already In The Site

7 Smoke Detector Done Completed


Electrical

8 Fluorescent Lighting Fixtures (2 x 36 Watts) - (3 + 1) pcs. Done Completed

9 Exit Lighting Unit Done Completed

10 Switches, Outlets and Covers Done Completed

032 OPEN COURT

1 Door Accessories Done Completed

2 Wall Painting (Final Coating) Done Completed

3 Skirting Done Completed


Civil & Architectural

4 Tile Works (for Open Showers) Done Completed

5 Non-Skid Cement Flooring (Kool Deck) On-going 28 Dec. 2011 For Pick-up

6 Sun Shades (Canopy) On-going For Delivery

7 Furnitures Done Completed

8 Concrete Ramps Done Completed

9 Signages 27 Dec. 2011 For Follow-up to the Supplier

10 Showers and Accessories Done Completed


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

Mech'l. 11 Drinking Fountain For Connection 11 Dec. 2011 For Delivery

12 Fire Alarm Horn with Strobe Light - 2 pcs. Done Completed

13 Outdoor Landscape Luminaire (1 x 100 Watts) - 24 pcs. 3 pcs not yet installed Already In The Site
Electrical

14 Exit Lighting Unit Done Completed

15 Outdoor Luminaire ( 1 x 26 Watts) Done as of 06 Oct. 2011 Completed

16 Switches, Outlets and Covers Done Completed

SP SWIMMING POOL

1 Tile Works (around the Swimming Pool) Done Completed


C&A

2 Steel Hand Rails 28 Dec. 2011 Sub-Con

3 Underwater Lights (100 Watts) - 12 pcs. Done as of 06 Oct. 2011 Completed


Elect'l.

4 Underwater Lights (300 Watts) - 8 pcs. Done as of 06 Oct. 2011 Completed

ME MAIN EXIT

1 Double-Leaf Door (Type E) Done as of 10 Sept. 2011 Completed

2 Door Accessories Done Completed

3 Window (Type - W01) Done as of 06 Oct. 2011 Completed


Civil & Architectural

4 Concrete Ramp Done Completed

5 Steel Hand Rails Ramp area only remaining Already In The Site

6 Non-Slip Ceramic Floor Tiles Done Completed

7 Wall Painting (Final Coating) Done Completed

8 Skirting Done Completed

9 Epoxy Floor Painting (for Ramp) 17 Dec. 2011 Already In The Site

10 Rubber Floor Mat 18 Dec. 2011 For Delivery

11 Outdoor Luminaire ( 1 x 26 Watts) Done Completed


Elect'l.

12 Switches, Outlets and Covers 25 Dec. 2011 For Delivery


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

EW EXTERNAL WALLS

1 Completion of Wall Painting (Final Coating) On-going 27 Nov. 2011 Already In The Site
C&A

2 Wall Grooves (for Pre-Cast Wall Joints) On-going 27 Nov. 2011 Already In The Site

3 Cage Ladders Done as of 06 Oct. 2011 Completed

Elect'l. 4 Flood Lights (1 x 250 Watts) - 23 pcs. Done as of 06 Oct. 2011 Completed

RW ROOF WORKS

1 Crushed Stone Aggregates 28 Dec. 2011 For Delivery


C&A

2 Flushing Done as of 06 Oct. 2011 Completed

3 Sun Shades (Canopy) - Trellis On-going 27 Dec. 2011 Already In The Site

EXTERNAL AREAS

1 Completion of Concrete Walkways Done Completed

2 Completion of Plant Boxes Done Completed

3 Completion of Curb Stones On-going Already In The Site

4 Bleachers Done Completed


Civil & Architectural

5 Handrails 28 Dec. 2011 Already In The Site

6 Asphalts On-going By Supplier

7 Parking Sheds Done Completed

8 Concrete Pavers Hardscape Done Completed

9 Landscaping Done Completed

10 Pedestals UP-1000 and bollards Beside Fire Pump Room already installed 24 Dec. 2011

11 Traffic Signs and Pavement Markings 29 Dec. 2011 Already In The Site

12 Curb Stone Painting 28 Dec. 2011 Already In The Site


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

13 Liquid Chiller For installation Already In The Site

14 Chilled Water Valve Box 17 Dec. 2011 Already In The Site

15 Irrigation Valve Box 07 Dec. 2011 Already In The Site


Mechanical

16 Irrigation Pump For Delivery

17 Irrigation Piping Works 24 Dec. 2011 Already In The Site

18 Fire Hydrants 14 Dec. 2011 Already In The Site

19 Connection to existing domestic line 08 Dec. 2011

20 Connection to existing sewer line 26 Nov. 2011

21 Transformer / RMU (Testing and Commissioning) Done 20 Dec. 2011 For Termination

22 Light Poles On-going For Delivery

23 Grounding Termination Done Completed


Electrical

24 Lightings and Fixtures Done Completed

25 Laying of cables (for Chiller and Pump Room) 17 Dec. 2011 Already In The Site

26 Laying of copper and fiber optic cables 17 Dec. 2011 Already In The Site

27 Testing and Commissioning 28 Dec. 2011 Already In The Site

FIRE PUMP ROOM


Architectural

1 PEB Building Frames and Panels Done Completed


Civil &

2 Wall Cladding 08 Dec. 2011 For Delivery

3 Roll-up Door 25 Dec. 2011 For Delivery

4 Mechanical Piping 25 Dec. 2011 For Delivery


Mech'l.

5 Pumps 25 Dec. 2011 For Delivery

6 Conduiting and Wiring On-going 25 Dec. 2011 Already In The Site


Electrical

7 Wiring Devices On-going 25 Dec. 2011 Already In The Site

8 Lightings and Fixtures On-going 25 Dec. 2011 Already In The Site


SPORTS FACILITY COMPLEX
LIFTING / RESERVES
(ARAMCO)
PRELIMINARY PUNCH LISTS AS OF 02/12/2019
DHAHRAN, K.S.A.

GENERAL

1 Paint retouch on the following;

a Doors 29 Dec. 2011

b Walls (as applicable) 29 Dec. 2011

c Ceiling Slabs (as applicable) 29 Dec. 2011

2 Painting on parking areas 29 Dec. 2011

3 Tiles and grout retouch on the following;

a Walls (as applicable) 29 Dec. 2011

b Floors (as applicable) 29 Dec. 2011

4 Cleaning of the electrical outlets, switches and terminal covers On-going 29 Dec. 2011

5 Retouch on the acoustic ceiling strips (as applicable) 29 Dec. 2011

6 Replacement of damaged ceiling tiles (as applicable) 29 Dec. 2011