District 96 Long-Range

Facilities Plan

February 6, 2019
Part II
Presentation of Concept Design Ideas for
Blythe Park, Central Elementary and Hollywood Elementary
Schools
Brief Recap
● Facility Advisory Committee
● Strategic Plan Goals
● Community Survey
● Demographic Study on Enrollment
● Hired DLA Architect
● Focus Groups with Principals and District Leadership

January 16, 2019


Educational & Facility Needs
● Secured Front Entrance
● Account for all Existing Itinerants and Student Support Areas
● Appropriate Number of Classrooms (including possible Full-Day
Kindergarten)
● A Place to Eat and Conduct Large Group Projects = Multi-Purpose
Room
● Leverage New Property Acquisitions
● Alleviate Over-Crowding Across Schools
● Create Multi-Section Option for Blythe Park
● Allow for Relocation of Early Learners Program from Blythe Park
School to Ames School
● Separate Play and Parking
● Renovation and Reconfiguration of Library Media Center
Blythe Park Needs
● Secured Front Entrance
● Renovate Auditorium for Updated Performance and
Multi-Purpose Room
● Additional Classrooms
Blythe Park Design Option #1
● Includes:
○ Secured Front Entrance
Blythe Park: Option 1
Blythe Park: Option 1
Blythe Park Design Option #1
Concept Design Feature Description Option 1
Secured Front Entrance X
Accounts for all Existing Itinerants and Student Support Areas X
Appropriate Number of Classrooms (including possible Full-Day Kindergarten) *
A Place to Eat and Conduct Large Group Projects = Multi-Purpose Room *
Leverages New Property Acquisitions X
Alleviates Over-Crowding Across Schools X
Creates Multi-Section Option for Blythe Park

Allows For Movement of Early Learners Program from Blythe Park School to Ames School X
Separate play and parking NA
Renovation and Reconfiguration of Library Media Center

Total Square Footage Added 730


Total Square Footage Renovated 1,900
Estimated Construction Cost $860,000
Blythe Park Design Option #2
● Includes:
○ Secured Front Entrance
○ Additional Classrooms
■ Create a 1 ½ section school
■ Relocation of Early Learners to Ames
Blythe Park: Option 2
Blythe Park: Option 2
Blythe Park Design Option #2
Concept Design Feature Description Option 1 Option 2
Secured Front Entrance X X
Accounts for all Existing Itinerants and Student Support Areas X X
Appropriate Number of Classrooms (including possible Full-Day Kindergarten) * *
A Place to Eat and Conduct Large Group Projects = Multi-Purpose Room *
Leverages New Property Acquisitions X X
Alleviates Over-Crowding Across Schools X X
Creates Multi-Section Option for Blythe Park X
Allows For Movement of Early Learners Program from Blythe Park School to Ames School X X
Separate play and parking NA NA
Renovation and Reconfiguration of Library Media Center

Total Square Footage Added 730 1,800


Total Square Footage Renovated 1,900 3,200
Estimated Construction Cost $860,000 $1.8M
Blythe Park Design Option #3
● Includes:
○ Secured Front Entrance
○ Additional Classroom
■ Create a 2-section school
■ Relocation of Early Learners to Ames
○ Renovate Auditorium for Updated Performance and
Multi-Purpose Room for Lunch and Large Group
Learning Experiences
Blythe Park: Option 3
Blythe Park: Option 3
Blythe Park: Option 3
Blythe Park Design Option #3
Concept Design Feature Description Option 1 Option 2 Option 3
Secured Front Entrance X X X
Accounts for all Existing Itinerants and Student Support Areas X X X
Appropriate Number of Classrooms (including possible Full-Day Kindergarten) * * X
A Place to Eat and Conduct Large Group Projects = Multi-Purpose Room * X
Leverages New Property Acquisitions X X X
Alleviates Over-Crowding Across Schools X X X
Creates Multi-Section Option for Blythe Park X X
Allows For Movement of Early Learners Program from Blythe Park School to Ames School X X X
Separate play and parking NA NA NA
Renovation and Reconfiguration of Library Media Center

Total Square Footage Added 730 1,800 1,800


Total Square Footage Renovated 1,900 3,200 5,400
Estimated Construction Cost $860,000 $1.8M $2.2M
Committee Recommendation: Option 3
Blythe Park Design Option #3
Concept Design Feature Description Option 1 Option 2 Option 3
Secured Front Entrance X X X
Accounts for all Existing Itinerants and Student Support Areas X X X
Appropriate Number of Classrooms (including possible Full-Day Kindergarten) * * X
A Place to Eat and Conduct Large Group Projects = Multi-Purpose Room * X
Leverages New Property Acquisitions X X X
Alleviates Over-Crowding Across Schools X X X
Creates Multi-Section Option for Blythe Park X X
Allows For Movement of Early Learners Program from Blythe Park School to Ames School X X X
Separate play and parking NA NA NA
Renovation and Reconfiguration of Library Media Center

Total Square Footage Added 730 1,800 1,800


Total Square Footage Renovated 1,900 3,200 5,400
Estimated Construction Cost $860,000 $1.8M $2.2M
Central Needs
● Secured Front Entrance
● Accessibility with addition of elevator
● Multi-Purpose Room for Lunch and Large Group Learning
Experiences
● Account for all Existing Itinerants and Student Support Areas
● Relocation of the Nurse’s office
Central Design Option
● Includes:
○ Secured Front Entrance
○ Accessibility with addition of elevator
○ Multi-Purpose Room for Lunch and Large Group
Learning Experiences
○ Relocation of Nurse’s office
● Accounts for all Existing Itinerants and Student Support
Areas
Central: Option 1
Central: Option 1
Central: Option 1
Central: Option 1
Central: Option 1
Central: Option 1
Central Design Option
Concept Design Feature Description Option 1
Secured Front Entrance X
Accounts for all Existing Itinerants and Student Support Areas X
Appropriate Number of Classrooms (including possible Full-Day Kindergarten) X
A Place to Eat and Conduct Large Group Projects = Multi-Purpose Room X
Leverages New Property Acquisitions X
Alleviates Over-Crowding Across Schools X
Creates Multi-Section Option for Blythe Park X
Allows For Movement of Early Learners Program from Blythe Park School to Ames School X
Separate play and parking *
Renovation and Reconfiguration of Library Media Center

Total Square Footage Added 660


Total Square Footage Renovated 7,900
Estimated Construction Cost $3.5M
Hollywood Needs
● Secured Front Office
● Account for all Existing Itinerants and Student Support Areas
● Separation of Play and Parking
● Consideration of a Multi-Purpose Room for Lunch and Large
Group Learning Experiences
Hollywood Design Option #1
● Includes:
○ Secured Front Office
Hollywood: Option 1
Hollywood: Option 1
Hollywood Design Option 1
Concept Design Feature Description Option 1
Secured Front Entrance X
Accounts for all Existing Itinerants and Student Support Areas

Appropriate Number of Classrooms (including possible Full-Day Kindergarten) X


A Place to Eat and Conduct Large Group Projects = Multi-Purpose Room

Leverages New Property Acquisitions NA


Alleviates Over-Crowding Across Schools NA
Creates Multi-Section Option for Blythe Park NA
Allows For Movement of Early Learners Program from Blythe Park School to Ames School NA
Separate play and parking *
Renovation and Reconfiguration of Library Media Center

Total Square Footage Added 0


Total Square Footage Renovated 1,400
Estimated Construction Cost $460,000
Hollywood Design Option #2
● Includes:
○ Secured Front Office
○ New Multi-Purpose Room for Lunch and Large Group
Learning Experiences
○ Accounts for all Existing Itinerants and Student Support
Areas
○ Reconfigured Library
Hollywood: Option 2
Hollywood: Option 2
Hollywood Design Option 2
Concept Design Feature Description Option 1 Option 2
Secured Front Entrance X X
Accounts for all Existing Itinerants and Student Support Areas X
Appropriate Number of Classrooms (including possible Full-Day Kindergarten) X X
A Place to Eat and Conduct Large Group Projects = Multi-Purpose Room X
Leverages New Property Acquisitions NA NA
Alleviates Over-Crowding Across Schools NA NA
Creates Multi-Section Option for Blythe Park NA NA
Allows For Movement of Early Learners Program from Blythe Park School to Ames School NA NA
Separate play and parking * *
Renovation and Reconfiguration of Library Media Center X
Total Square Footage Added 0 2,500
Total Square Footage Renovated 1,400 2,000
Estimated Construction Cost $460,000 $2.2M
Committee Recommendation: Option 2
Hollywood Design Option 2
Concept Design Feature Description Option 1 Option 2
Secured Front Entrance X X
Accounts for all Existing Itinerants and Student Support Areas X
Appropriate Number of Classrooms (including possible Full-Day Kindergarten) X X
A Place to Eat and Conduct Large Group Projects = Multi-Purpose Room X
Leverages New Property Acquisitions NA NA
Alleviates Over-Crowding Across Schools NA NA
Creates Multi-Section Option for Blythe Park NA NA
Allows For Movement of Early Learners Program from Blythe Park School to Ames School NA NA
Separate play and parking * *
Renovation and Reconfiguration of Library Media Center X
Total Square Footage Added 0 2,500
Total Square Footage Renovated 1,400 2,000
Estimated Construction Cost $460,000 $2.2M
Community Feedback
Dates and format to be determined
Questions from the Board of Education