Beruflich Dokumente
Kultur Dokumente
Presented by:
C.A. Prasad, Director, METEY Engineering and Consultancy pvt. ltd.
Pavan Patchigolla, Structural engineer, METEY Engineering and Consultancy pvt. Ltd.
Some failures
Failure of column in
shear.
Bhuj earthquake, 2001
Improper confinement of
longitudinal
reinforcement led to
shear failure of column
during earthquake.
Some failures
Failure of column.
Inelastic deformation of
column due to lack of
confinement.
Some failures
Bridge failure
The great hansin
earthquake, kobe, 1995.
Failure of building
turkey earthquake, 1999
Failure of building
Simav earthquake, 2011
Based on the above statement, an attempt is made to bring out the importance of ductility of the buildings
during earthquakes.
Design philosophies
• Strength design:
• Capacity design:
Certain locations for energy dissipation are chosen and are designed for
inelastic flexural strength and shear failure is inhibited by a suitable strength
differential Capacity design philosophy
Capacity design
• We accept high risks of damage to the structure than • It is observed that the lack of strength against the
for other extreme loads. actual earthquake forces will not always result in
failure provided that the structural strength is
• Codes suggest methodology to calculate the design
maintained without excessive degradation with
earthquake forces which are far lesser compared to the
increase of inelastic deformation.
actual forces happen at site
• This inelastic response has emerged as an important
• Designers usually design the structure for design
element or factor for seismic design.
strength of materials which are perhaps 15% - 20%
lesser than that of the elastic strength • Observations states that all inelastic modes of
deformation are not equally viable while some leads
• This philosophy expects the structure to survive an
to failure, some leads to perform well because of
earthquake by large inelastic deformation and energy
ductility
dissipation corresponding to material distress
Capacity design
• Inelastic deformation should never lead to the brittle Capacity design sequence is as follows:
• Required strengths of undesirable modes of inelastic 2. Beam shear design: (Shear demand as per IS 13920:2016)
• Provided shear strength differential must exceed the 4. Column transverse reinforcement design: (Shear demand
as per IS 13920:2016)
actual flexural strength to ensure that inelastic shear
5. Strength of elements at beam column joint
deformation cannot happen
6. Beam – Column joint design:
• Bond failure impending to brittle failure of elements
Codes suggest various formulae which when followed
needs to be avoided
inhibits the undesirable inelastic modes of deformation
(Shear and Bond).
The requirements of this section shall be met within unless a larger
amount of transverse reinforcement is required from shear strength
considerations.
≤ 0.2fck 6.1
R=5
≤ 0.08fck
and Ductile)
Width - Depth ratio -- Not available 6.1.1 ≤ 0.3
Minimum Width -- Not available 6.1.2 200 mm
25 % of Clear span (design of deep
Minimum Depth -- Design of deep beams are allowed 6.1.3
beams not allowed)
Flexural reinforcement
26.5.1.1 (a) 85/fy (in%) 6.2.1 0.24 * (fck)0.5/fy (in%)
(Min.)
Flexural reinforcement
26.5.1.1 (b) 4.00% 6.2.2 2.50%
(Max.)
Flexural reinforcement 6.2.3 and
-- Not available Yes, Available
(overriding clauses) 6.2.4
Development length + (10 Times Bar
Bond (Anchorage) 26.2.1 Development length only 6.2.5
dia.)
Lap splices (location) Shall not be provided with in joint
Splices shall be provided as far as
26.2.5 from the sections of maximum stress Within distance of 2d from face of
and be staggered the column
6.2.6.1
When bars are spliced at maximum
Within quarter length of beam
26.2.5.1 stressed points such as increasing lap
adjoining plastic hinge
and closer spacing of stirrups
Transverse reinforcement 26.5.3.2 Diameter shall not be less than 1/4th of Min dia. Is 8mm/10mm depending on
7.4.2 (a)
(Min. Link dia and spacing) (c,2) largest longitudinal bar dia. diameter of main bar
Max. spacing shall be limited to 300mm
Spacing shall not be less than the
7.4.2 (b, d) or half of the least lateral dimension of
following:
column
26.5.3.2 Least lateral dimension of compression Min spacing shall be less than 1/4th of
(c,2) 8.1 (b) (1)
members min. dimension of the column
16 times the smallest dia of long. Bar Min. spacing shall be less than 6 times
8.1 (b) (2)
300mm the diameter of smallest main bar
A plan has been taken up to demonstrate the cost difference between the ordinary and ductile
detailing
Case study
Building parameter Dimension
Maximum dimension of Building 58.8 m
Assumption
Earthquake analysis is done for zone -3 and assumption of ordinary
moment resisting frame.
Consumption charts
40
30
35
25
30
20 25
42
15 20
28 29 28 35
15
10
10
18
5 11
5
2 1 2 2 1
0 0
Foundations Columns Beams Slabs Staircases Miscellaneous Foundations Columns Beams Slabs Staircases Miscellaneous
Consumption charts
Cost consumption chart
2 1
Foundations
16 24
• Cost of Slabs, Staircases and
Columns foundations – Unaffected by clauses
• Cost of foundations – Effected by
Beams
Response reduction factor for OMRF
and SMRF (40%)
• Cost of beams and columns – 50 –
Slabs 60% of total cost of project
Staircases
35
Miscellaneous
22
Quantity comparison (Ordinary Vs Ductile)
Beam (Sample -1) Beam (Sample -2)
Detailing type Steel (in Kgs.) Detailing type Steel (in Kgs.)
Concrete (Cum) Concrete (Cum)
Longitudinal Transverse Longitudinal Transverse
Conclusion: Concrete consumption being the same, the steel requirement Conclusion: Concrete and steel matches as the flexural demand on the member
reduces by about 18% in ductile detailing is minimum
Quantity comparison (Ordinary Vs Ductile)
Column (Sample -1) Column (Sample -2)
Column (3.0 X 0.23 X 0.45 - OD); 3.0 X 0.3 X 0.45 - Column (3.0 X 0.23 X 0.6 - OD); 3.0 X 0.3 X 0.6 - DD)
DD)
Detailing type Steel (in Kgs.) Detailing type Steel (in Kgs.)
Concrete (Cum) Concrete (Cum)
Longitudinal Transverse Longitudinal Transverse
Conclusion: Concrete consumption of column is 30% more in ductile Conclusion: Concrete consumption of column is 30% more in ductile detailing,
detailing, the steel requirement reduces by about 40% in ductile detailing the steel requirement increases by about 30% in ductile detailing
Cost comparison (Ordinary Vs Ductile)
Ordinary Detailing (R=3) Ductile Detailing (R=5)
Comparison
Quantity Cost (in lakhs) Quantity Cost (in lakhs)
Footings
Concrete Cum 720 32.4 540 24.3
Steel MT 22 13.2 17 10.2
Shuttering Sqm 1067 2.13 907 1.81
Column
Concrete Cum 256 11.52 333 14.99
Steel MT 123 73.8 95 57
Shuttering Sqm 3294 6.59 4282 8.56
Beams
Concrete Cum 737 33.17 737 33.17
Steel MT 177 106.2 172 103.2
Shuttering Sqm 8030 16.06 8030 16.06
Slab
Concrete Cum 990 44.55 990 44.55
Steel MT 26 15.6 26 15.6
Shuttering Sqm 7920 15.84 7920 15.84
Staircases
Concrete Cum 23.64 1.06 23.64 1.06
Steel MT 2.3 1.38 2.3 1.38
Shuttering Sqm 130 0.26 130 0.26
373.76 347.98
Conclusions
• Inelastic shear deformation which leads to collapse shall be avoided by providing the suitable
strength differential
• Ductile design or capacity design is a necessity to be practiced to avoid any collapse of buildings.
• Ductile design and detailing costs more than the ordinary detailing which is a misnomer (if
earthquake analysis is made to the building).
• Overall cost of buildings followed with ductile detailing is about 7% lesser compared to ordinary
detailing (for case study taken up)