ACTIVITY ATTRIBUTES

Project Title: Warehouse Construction Date Prepared: November 6, 2017

ID: 1 Activity: Pre-Construction


Description of Work:
Includes sub-activities such as designing the warehouse and acquiring building, electrical and sanitary permits

Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag

None Finish-to-Start Foundation Finish-to-Start

Number and Type of Skill Requirements: Other Required Resources: Access to Certificate of Land Title, Tax
Resources Required: Declaration of Property-lot, Photocopy of Tax Receipts. Blueprint and
Person-Architect, construction design of the warehouse
Engineer

Type of Effort:

Location of Performance: Local, Municipal and other government offices and agencies

Imposed Dates or Other Constraints:

Page 1 of 1
Assumptions: No national holidays and no suspension of government work due to natural disasters, etc. during the processing of documents

ACTIVITY ATTRIBUTES

Project Title: Warehouse Construction Date Prepared: November 6, 2017

ID: 2 Activity: Foundation


Description of Work:
Includes sub-activities such as site clearing, excavation, foundation digging, and concrete pouring

Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag

Pre-Construction Finish-to-Start Framing/Structure Finish-to-Start

Number and Type of Skill Requirements: Other Required Resources:


Resources Required:
Person-Construction
Workers
Equipments such as
Excavators, Bulldozers,
Backhoe, Wheelbarrows,
Shovels, Concrete Mixer,
etc.
Materials such as Sand,
Gravel, Water, Cement,
Soil

Page 1 of 1
Type of Effort:

Location of Performance:

Imposed Dates or Other Constraints:

Assumptions:

ACTIVITY ATTRIBUTES

Project Title: Warehouse Construction Date Prepared: November 6, 2017

ID: 3 Activity: Framing/Structure


Description of Work:
Includes sub-activities such as construction of pillar footings, wall, door & window frames, roof system, electric system & pipeworks

Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag

Foundation Finish-to-Start External Cladding Finish-to-Start

Page 1 of 1
Number and Type of Skill Requirements: Other Required Resources:
Resources Required:

Type of Effort:

Location of Performance:

Imposed Dates or Other Constraints:

Assumptions:

ACTIVITY ATTRIBUTES

Project Title: Warehouse Construction Date Prepared: November 6, 2017

ID: 4 Activity: External Cladding


Description of Work:
Includes sub-activities such as installing roof cladding

Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag

Page 1 of 1
Framing/Structure Finish-to-Start Finishing Finish-to-Start

Number and Type of Skill Requirements: Other Required Resources:


Resources Required:

Type of Effort:

Location of Performance:

Imposed Dates or Other Constraints:

Assumptions:

ACTIVITY ATTRIBUTES

Project Title: Warehouse Construction Date Prepared: November 6, 2017

ID: 5 Activity: Finishing


Description of Work:
Includes sub-activities such as applying paint to the interior and exterior of the warehouse, installing and connecting electrical system and
pipeworks from inside the roof to outside electrical posts and underground drainage system, and preparing the site for use

Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag

Page 1 of 1
External Cladding Finish-to-Start None

Number and Type of Skill Requirements: Other Required Resources:


Resources Required:

Type of Effort:

Location of Performance:

Imposed Dates or Other Constraints:

Assumptions:

ACTIVITY ATTRIBUTES (Sample for Foundation)

Project Title: Warehouse Construction Date Prepared: November 6, 2017

ID: 2.2 Activity: Excavation


Description of Work:
Removing soil, rocks, etc using drills, explosives to create an open hole in the ground

Page 1 of 1
Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag

1.1 Warehouse Finish-to-Start 2.3 Foundation Digging, Finish-to-Start


Design, 1.2 2.4 Concrete Pouring,
Acquisition of 3.1 Pillar Footings, 3.2
Permits, 2.1 Site Wall Construction, 3.3
Clearing Door & Window
Frames, 3.4 Roof
System, 3.5 Electric
System & Pipework
Installation (Inside
Roof), 4.1 Plain Roof
Cladding, 5.1 Paint
Application, 5.2 Electric
System & Pipework
Installation (Outside
Roof), 5.3 Cleaning
Number and Type of Skill Requirements: Other Required Resources:
Resources Required:

Type of Effort:

Location of Performance:

Imposed Dates or Other Constraints:

Page 1 of 1
Assumptions:

ACTIVITY ATTRIBUTES (Sample for Framing/Structure)

Project Title: Warehouse Construction Date Prepared: November 6, 2017

ID: 3.4 Activity: Roof System


Description of Work:
Constructing and installing ventilation, insulation and interior structure

Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag

1.1 Warehouse Finish-to-Start 4.1 Plain Roof Cladding, Finish-to-Start


Design, 1.2 5.1 Paint Application
Acquisition of
Permits, 2.1 Site
Clearing, 2.2
Excavation, 2.3
Foundation
Digging, 2.4
Concrete Pouring,
3.1 Pillar Footings,
3.2 Wall
Construction

Page 1 of 1
Number and Type of Skill Requirements: Other Required Resources:
Resources Required:

Type of Effort:

Location of Performance:

Imposed Dates or Other Constraints:

Assumptions: