Plot plan Guidelines and Procedure

1. Terminal Name – Write in Site Mark-up Drawing.


2. Survey Control Point Name : Terminal Name
3. Take First Point in North Direction.
4. Create the Mark-up Drawing with features name and Tag No. in the Site
5. Start Survey point from Boundary and Fencing point.
6. Measurements take From Survey Machine.
Description Name Coding
1. Boundary Point BW
2. Fencing Point FNC
3. Main Gate Point MGT
4. Path Way Point (Foot Path) PW
5. Civil Base Point CB
6. Building Point BD
7. Building Roof Point BDR
8. Door Point DOR
9. Window Point WIN
10.Separator Diameter point SPD
11.SeparatorDimension Point (Length) SPL
12.Separator Nozzle Point SPN
13.Separator Flange Point SPFL
14.Separatorsupport Point SPSU
15.SeparatorElevation Point SPEL
16.Filter Diameter point FLD
17.FilterDimension Point (Length) FLL
18.FilterNozzle Point FLN
19.Filter Flange Point FLFL
20.Filter Elevation Point FLEL
21.Pig Launcher Diameter point PGLD
22.Pig LauncherDimension Point (Length) PGLL
23.Pig Launchersupport Point PGLSU
24.Pig Launcher Nozzle Point PGLN
25.Pig Launcher Elevation Point PGLEL
26.Pig Receiver Diameter point PGRD
27.Pig ReceiverDimension Point (Length) PGRL
28.Pig Receiver Nozzle Point PGRN
29.Pig Receiver support Point PGRSU
30. Scrubber Diameter point SCD
31.Scrubber Dimension Point (Length) SCL
32.Scrubber Nozzle Point SCN
33.Scrubber Flange Point SCRFL
34.Scrubber support Point SCSU
35.Cross Over CR
36.Material Handling MH
37.Fire Hydrant FRH
38.Mono Rail MR
39.Road RD
40.Control Room CNR
41.Skid Point SKD
42.Earth Pit Point EP
43.Drain Pit Point DP
44.Pipe Support Point PSU
45.Electrical Unit Point ELU
46.Flag Point FG
47.Pipe Inlet PLIN
48.Outlet Point PLOT
49.Pipe Line 10" Point PL10
50.Pipe Line 12" Point PL12
51.Pipe Line 14" Point PL14
52.Pipe Line 16" Point PL16
53.Quick Closer Point QC
54.PSV Point PSV
55.Control Valve Point CNV
56.Cage Ladder Point CGL
57.Terminal Shed Point TRSH
58.Security Room Point SR
59.Shed Area Point SH
60.Covered Shed Point CSH

7. Measurements take From Tape.


a) Skid Dimension
b) Equipment Base Plate Dimension
c) Pipe Support Dimension
d) Instrument Box Dimension
e) Boundary Thickness Dimension
f) Pit Dimension
g) Wall Thickness Dimension
h) Electrical unit Dimension
8. Show Grass Area, Concrete Area, Clay area in Mark-up Drawing
9. Cad Activity:
a) Rotate the Point in cad with reference to North Direction
b) Create Objects in cad by Using the Points and mention Dimensions.
10.Prepare Final Mark-up With Dimension in Red Pen.
11. Scan and Send the Final Mark-up and Cad Native File to Hyderabad