Sie sind auf Seite 1von 18

DESCON ENGINEERING LIMITED MS//MECH/16

Revision 0
METHOD STATEMENT FOR Page 1 of 17
CROSS COUNTRY PIPELINE INTALLATION

METHOD STATEMENT
FOR
CROSS COUNTRY PIPELINE INTALLATION

0 Initial Issue April 23, 2002 A.Hameed Q.Mannan DSZ

Rev. Comments Date Prepared by Checked by Approved by Client


DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 2 of 17
CROSS COUNTRY PIPELINE INTALLATION

INDEX

1. PURPOSE

2. SCOPE

3. REFERENCES

4. DEFINITIONS

5. RESPONSIBILITIES

6. PROCEDURE

7. TOOLS AND EQUIPMENTS

8. SAFETY INSTRUCTIONS

9. ATTACHMENTS

1. PURPOSE
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 3 of 17
CROSS COUNTRY PIPELINE INTALLATION

The purpose of this generic method statement is to define the procedure


for installation of cross country pipeline.

2. SCOPE

Scope of this method statement covers the following activities.


 Material handling

 Survey

 Route and Demarcation

 Right of way

 Trenching

 Stringing

 Welding

 Inspection

 Holiday test

 Trench Inspection and Sand padding

 Lowering in

 Field Bending

 Crossings

 Cleaning

 Hydro testing

 De watering and drying

 Nitrogen purging and inerting

 Restoration of right of way


DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 4 of 17
CROSS COUNTRY PIPELINE INTALLATION

3. REFERENCES

3.1 PROJECT DRAWINGS

 Applicable Project Piping Isometrics.

 Project Piping Layout drawings.

 Others.

3.2 PROJECT SPECIFICATION

 Site Material Management

 Painting & Protective Coating for Field Joints

 Coating & Wrapping for Field Joints

 Approved WPS.

 Other related Specifications.

3.3 PROJECT QUALITY PLAN (PQP)

 Project Quality plan.

3.4 CODES AND STANDARDS

 Project Drawings

 Project Specifications

4. DEFINITIONS
CL Client
PM Project Manager
SM Site Manager
CM Construction Manager
DE Discipline Engineer
ROW Right Of Way
ITP Inspection and Test Plan
QC Quality Control
QCI Quality Control Inspector
PQP Project Quality Plan
PPE Personal Protection Equipment
HSE PLAN Health Safety & Environment Plan.
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 5 of 17
CROSS COUNTRY PIPELINE INTALLATION

5. RESPONSIBILITIES
 It is overall responsibility of PM/SM to organize resources to perform construction
activities as per project specification, in compliance with quality, schedule & safety
requirements.

 It is the responsibility of CM that construction activities are executed according to


the relevant project specifications, in compliance with quality, schedule & safety
requirements.

 DE will ensure that all the works are performed safely as per latest Approved For
Construction (AFC) drawings & specifications.

 The relevant DE and Supervisor will ensure that all the piping work is conducted
in accordance with this method statement and project specification.

 The QC Inspector will ensure that all work is executed according to PQP and that
requirements of quality dossier are full filled.

 Safety and Construction supervision will be carried out under responsibility of


Client.

6. PROCEDURES / METHODOLOGY.

6.1 RECEIPT, HANDLING & STORAGE

 The piping material/piping components received from client shall be offloaded in


the lay down yard.

 A suitable crane and Nylon slings shall be used for off loading of piping.

 The Nylon slings will be used for handling of the pipes to avoid / minimizes the
external coating damaged.

 During loading or unloading pipes shall not be dropped onto or off the transporting
vehicle.

 The material received shall be checked for quantity and quality items.

 The pipes shall be placed above ground by using sandbag packing.

 The pipe ends shall be covered to prevent foreign matter entry.

 The piping materials shall be segregated as per size to facilitate the location and
ease of handling.
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 6 of 17
CROSS COUNTRY PIPELINE INTALLATION

6.2 PIPELINE ROUTE AND DEMARCATION:

 Using survey drawings, alignment sheets for the Pipeline route, a


survey of the route shall be carried out to establish pipeline corridor,
working grades, levels and install survey markers / monuments. The
survey markers shall be established as per the project drawings or at
every 200m along the route on ground. The survey shall be used to
know the crossings, underground or close by services or any other
possible hold ups, that must be kept in mind during the job planning
stage.

 It is understood that Client shall obtain necessary right of way from the
concerned Agencies / Authorities and there shall be no reason of
dispute with the landowners, which can become cause of any delay.
However, Descon shall keep a liaison with these Agencies / Authorities
for smooth working on the project.

 Four to five survey teams shall be deployed for carrying out the survey.
It is planned to submit for Clients’ approval a ROW survey carried out in
first 10 days enabling the ROW crew to start work.

6.3 RIGHT OF WAY (ROW)

 It is understood that client has already obtained approval for Right of


Way. The area shall be handed over by client to carryout uninterrupted
work to match project schedule.

 Make the width of ROW from the survey stones and start cutting and
leveling of ROW as per sectional drawings.

 Any trees or existing structures obstructing the right of way shall be


removed after approval from client.

 Sand dooms shall be scraped out to make level and inclination of


pipeline laying.

 An exclusive team shall be made responsible for maintenance of ROW &


to keep it worthy of traffic.

 Generally natural ground shall be used as ROW after removal of


boulders, grubbing and grading.

 After satisfactory leveling and easy movement of machinery draw


centerline for pipeline trench.

6.4 TRENCHING:

 The center line of pipeline shall be marked as per relevant drawings.


DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 7 of 17
CROSS COUNTRY PIPELINE INTALLATION

 Particular care shall be taken to locate any buried installation, working.

 Hydraulic excavators, rock breakers and / or dozer with pull shall be


deployed to excavate the trench. Controlled blasting shall also be used
wherever required.

 Where the trench is know to cross other pipeline or under ground


system / services, the excavation at that point shall be done by manual.
The trench at these points shall be excavated so that the pipeline
crosses under the encountered obstacle. Care shall be taken so as not
to damage the crossed pipeline or under ground system.

 The dimensions of trench shall be generally maintained as per approved


drawings. It shall be made wide to avoid any damage to pipe coating
especially at the bends.

 The soil will be placed a minimum 0.4m from the edge of the ditch.

 The trench walls and bottom shall be made free of any sharp edges and
elements that may cause damage to pipe coating.

 Sufficient lead to piping shall be provided to avoid any obstruction to


their flow of works.

 The excavated materials suitable for back filling shall be placed along
side the trench at a sufficient distance, 1m away to avoid any
unnecessary load on trench walls and it does not obstruct pipeline
stringing and welding works.

 Before welding activity is started, 3KM lead for trenching shall be


achieved. Trenching work shall be executed using excavators. Major
Equipment Deployment Schedule depicts the equipment deployed on
this activity.

6.5 ROCK BLASTING

 In the area of rock excavation controlled blasting shall be done.


Necessary approvals from client shall be obtained prior to the blasting
work.

 Only well trained & experienced people shall be allowed to use


explosive for blasting works. The area to be blasted surveyed and
pneumatic drills shall be used to make holes in ground for loading
explosives.

 The holes shall be made in such a fashion to have minimum


unnecessary blasting of hard soil.

 The explosive shall be charged just before the start of blasting works.

 The area to be blasted shall be covered with an appropriate blanket


(chain or used tyres or equivalent) to arrest flying pieces.
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 8 of 17
CROSS COUNTRY PIPELINE INTALLATION

 Also please refer safety precautions for handling explosive given in


Section 12.0

6.6 HAULING & STRINGING OF MATERIAL

 Stringing may proceed after the ROW clearing and grading is complete
and will be in accordance with the specifications.

 Place wooden skids / dirt berms approximate 02 meter away and along
the side of the trench.

 After achieving one-KM trench, stringing activity shall be started using


the equipment as shown in the Major Equipment Deployment Schedule.

 The pipes shall be strung along side excavated trench and marked for
identification.

 The trailer bed and their side supports shall have a suitable protective
material to avoid chances of scratches, scars or brusis to the pipe
coating.

 The pipe will be off loaded in accordance with the stringing schedule.
This is to ensure that, pipes of the correct wall thickness are placed in
correct sequence of use.

 Where necessary the lines of string pipes will be interrupted to allow


passage of vehicles and animals.

6.7 WPS & WQT

 The WPS shall be prepared in accordance with API Standard 1104 latest
edition for field welding of pipeline / as per the project specifications
and shall be submitted for client’s approval. The tests shall be
conducted for the final acceptance of welding procedure, welding
consumables, welding current and other parameters. The incharge
quality control shall maintain a record of all WPS.

 Upon the acceptability of the WPS, welders’ qualification tests shall be


performed. This process shall be on going for some period on the
project till a desired number of welders are selected. Each welder shall
be issued an identification tag having following information:

A) Own Photograph
B) Welder’s name
C) Company name
D) Qualification symbol

 The identification tag shall be displayed during the welding process.


The welder number shall be progressive and shall not be repeated.

 A weld repair procedure shall also be established.


DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 9 of 17
CROSS COUNTRY PIPELINE INTALLATION

6.8 CLEANING & INSPECTION OF PIPES AND BEVELS

 The pipe ends shall be factories beveled to satisfy API 1104. The ends
shall be checked for their geometry, mechanically cleaned, reset on the
sandbags / wooden skids and shall be made ready for welding crew.
Cleaning shall be performed on the inside and outside of the pipe and
at least up to ten cm from the edge. In case any end is damaged
beyond the permissible limits set in the Project Specification/Applicable
Code it shall be brought to the notice of the Job Inspector and a suitable
remedial action shall be taken.

 The line shall be swabbed and cleaning means. Subsequently the pipe
ends shall be covered using polyethylene sheet and tape or any other
economical means.

 The crew shall have its own dedicated crane and necessary tools to
continue the job independently to provide lead to the welding crew.

 Pipe diameter and thickness will be verified at each pipe end and any
deviation shall be brought to the notice of field inspector for corrective
action if needed.

6.9 MAIN LINE WELDING

 Following codes and standards shall be used for welding and welding
related requirements:

API 1104 latest edition.


ANSI B31.4 latest edition.
ASME code-Section IX

 The pipe shall be visually checked from inside for any foreign material.
In case it carries any foreign material it shall be swabbed again before
engaging the two ends by external line up clamp.

 Bevel ends shall be checked for their cleanliness

 The two sections shall be aligned together using nylon belts and line-up
clamp. On achieving the proper gap as given in WPS the root bead will
be run by a pair of qualified welders as per parameters established
during the execution of the WPS.

 The lifting tackle shall be disengaged as soon as the root bead is


complete and the pipes are placed on supports. Care must be taken to
protect the coating on the pipes.

 Another pair of welders shall carry out hot pass and hot fill pass while
the third pair of welders shall complete filling / capping. Thorough
cleaning of the root pass shall be done before start of the subsequent
passes by using power brush and / or disc grinder. The hot pass shall be
applied quickly before the stinger bead gets cool. Minimum and
maximum interpass temperature shall be checked during welding.
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 10 of 17
CROSS COUNTRY PIPELINE INTALLATION

Particular attention to welding current and travel speed shall be given


to achieve a good weld.

 No arc strike shall be permitted outside the bevel area. Any accidental
arc strike shall be ground out and then subject to MPI or DPT test in
accordance with ASME SE-138 / 165 respectively.

 Any weld not completed on the day due to any reason shall be well
supported and protected against dew and dust.

 Each weld shall have a unique number. Welder shall write their
identification number with crayon on each weld. A record shall be
maintained to control the quality of the welders and also to work on the
modification / repair of any joint.

6.10 WELDING INSPECTION & RADIOGRAPHY

 The weld acceptance standard of API 1104 shall apply to the visual and
non-destructive inspections.

 The welding inspectors shall have visual check of the weld joints to
ensure procedure and specification compliance.

 Welds shall be radiographed as per approved Project Quality Plan


(PQP). A record of each radiographed joint shall be maintained with
reference to weld numbers, welders’ number and the radiography
results.

 Safety and protective measures shall be taken during radiography


operations as laid down in the Project Safety Manual.

6.11 INSTALLATION OF HEAT SHRINK SLEEVE

 The weld shall be cleaned and the sleeve shall be installed as per the
sleeve manufacturer’s recommendations and project specifications.
Holiday test shall be carried out after the installation is complete.

6.12 HOLIDAY TEST & REPAIR COATING

 As soon as the welding operation is completed on a stretch, Holiday test


shall be carried out using calibrated test equipment of proper capacity
and range as per ITP. The repair work on the holidays shall be carried
out as per approved procedure provided by the Coat and Wrap / Pipe
manufacturer.

6.13 TRENCH INSPECTION & SAND PADDING

 Before lower in the pipe the trench shall be inspected for its
dimensions, centerline and soil condition along its walls and at its
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 11 of 17
CROSS COUNTRY PIPELINE INTALLATION

bottom as per ITP. The bottom of the trench shall not have elements,
which can cause damage to the pipe and its coating. In case the soil
condition is such that such fragments cannot be avoided then sand
padding shall be provided to protect the pipe.

6.14 LOWER-IN & TIE-IN

 Lowering-in shall be accordance with the project specification.

 Standing water shall be pumped out from the trench wherever possible prior to
lowering the pipe into the ditch.

 A rigging study, to lower a line with 30 to 40 joints welded shall be


prepared.

 Lowering operation shall be done using the side booms of proper


capacity and nylon belts.

 During lowering operation Holiday test shall be performed on skid


marks and if needed repair work shall be carried out as per repair
procedure.

 Care shall be taken to ensure that the pipe is in the center of the trench
and that the coating or joint wraps are not damage.

6.15 TIE-INS

 All Tie-ins shall be undertaken by a dedicated crew (s) fully equipped for
this operation.

 Tie-in shall be carried out where sections of pipeline laid in the trench
join and at road, canal, railway crossings and other major crossings.

 For tie-ins the pipe shall be cut so as to permit a good alignment of two
strings and a good weld. The lap of pipe strings at tie-ins shall be at
least 1~2 meters. The weld seams of the adjoining pipes shall offset by
30% of the diameter or 76mm which ever is greater. If this is not
possible then a spool piece of not less than 1.2 meters in length shall
be inserted. The minimum pup length shall be one (1) meter. The tie-ins
shall be made at the minimum temperature of the day but not less than
10C0.

 Bell Holes shall be made in the trench to perform the weld. The bell hole
shall be of following minimum dimensions

Depth 60 cm below the lower part of the pipe

Length 70 cm in excess of the outside diameter of the pipe

Width 90 cm between the outside of the pipe and the bell hole wall on
either side of the pipe.
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 12 of 17
CROSS COUNTRY PIPELINE INTALLATION

6.16 FIELD PIPE BENDING

 Field pipe bending shall be done accordance with the project specification.

 Bend will be made along the longitudinal axis of the pipe, so that the weld is not
subject to elongation or stress.

 All field bends shall be free from buckling or flattening, particular care will be taken
to minimize the ovality.

 Any pipe showing defects shall be rejected and replaced.

 Field pipe bending shall be done by using hydraulic pipe bending


machine. The machine shall bend pipe with a bending radius more than
or equal to 40 time nominal diameter of pipe. Bend geometry shall be
prepared for each bend suiting to its location.

6.17 BEDDING

 The trench shall be back filled after client’s approval. A proper


documentation shall be prepared for the back filling operation.
 The trench shall be back filled initially up to 20cm as the approval is
received.

 After reaching the level of surrounding ground, the ground shall


lightly compacted and later the remaining excavated material shall
be crowned enough up to height above as per specifications over the
trench and shall be compacted lightly.

 Where the trenches have been dug through driveways, roads, dikes,
etc. the compaction shall be done using mechanical means by
adding small layers of materials.

 Project specifications shall be followed in carrying out the back filling.

6.18 CROSSINGS

Following points shall be considered for crossings.


 Project specification & drawing shall be followed. If specified casing pipe
shall be laid and the carrier pipe passed through it.

 The activity shall be planned in a way to ensure minimum disturbance


to the facility and to create as little as possible
hindrance/inconvenience to the general public. Where the activity has
to continue over the night warning signs shall be displayed to avoid risk
of any accident.

 The detours shall be adequate to meet the requirement of the traffic.

6.19 CLEANING
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 13 of 17
CROSS COUNTRY PIPELINE INTALLATION

 It is proposed that cleaning & testing of pipeline may be done in


sections after agreement with client.

 Temporary Pig Launcher & Receiver shall be welded to either end of the
pipeline section under test.

 Pipeline cleaning pigs equipped with polymer discs & wire brushes shall
be used for cleaning. During the cleaning process the following
information shall be noted.

 Cleaning pig run number

 Time launched

 Time received

 Average pigging pressure

 Amount of debris connected

 Once the debris collected in front of the pig shows decreasing trend &
subsequent cleaning pigging process does not bring much debris, the
clearing process shall be considered complete.

6.20 GAUGING

 The gauging of pipeline shall be carried out by propelling a Gauging pig


in the line using compressed air

 The Gauging pig shall be fitted with polymer discs & an aluminum
gauge plate. The diameter of plate shall be 95% of minimum ID of the
pipeline section.

 The pig shall be passed through the pipeline at controlled speed with
compressed air.

 A gauging acceptance report shall be prepared by checking the Gauge


Plate after a run.

6.21 HYDROTESTING

6.21.1 FLOODING:
 The flooding of pipeline shall be carried out by propelling two
pigs in the line using water

 If required the flooding water will have corrosion inhibitor added


to it.

 Prior to launching of first pig around 10 cum water shall be


DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 14 of 17
CROSS COUNTRY PIPELINE INTALLATION

pumped into the line to wash away any foreign materials.

 Similarly before launching the second pig around another 10 cum


of water shall be pumped in the pipeline.

 The two pigs shall be pumped forward using water at a speed


around 1.8m / sec.

 Once the first pig is received at the other end pumping shall
continue until the second pig is also received ensuring that the
line is completely full.

 The water pumping shall be stopped after maintaining a positive


pressure in the pipeline.

6.21.2 PRESSUREIZATION
 Temperature stabilization shall begin upon completion of flooding
works.

 Thermocouples shall be attached on external surface of the


pipeline after removal of coating.

 Thermocouples to measure soil temperature shall also be buried


close to pipeline.

 Temperature reading for pipeline & soil shall be taken at regular


intervals. Temperature stabilization shall be considered achieved
when the difference between the two is not above 1 oC.

 The line shall be pressurized to test pressure at a pre-agreed


rate. During this process the following readings shall be taken:

1. Fill water flow rate

2. Pipeline pressure recording

3. Pipeline temperature recording

4. Temperature of fill water

 A plot for pressure Vs volume shall be made & compared with a


theoretical plot. In case of a deviation beyond a specified limit
(approx. 0.2% of line volume) the pressurization will be stopped
to investigate cause.

 Two consecutive pressures lowering of approx. 0.5 bar &


measuring amount of water drained shall check the volume of air
in pipeline. This volume shall be compared with theoretical
volume. The ratio between the two should not exceed by a valve
given in specifications.
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 15 of 17
CROSS COUNTRY PIPELINE INTALLATION

 Upon achieving 100% test pressure the pump shall be


disconnected form the pipeline and temperature & pressure
charts removed for safe keeping.

 The pressure will be maintained for 24 hours. During this period


the following readings shall noted.

A) Pipeline pressure

B) Pipeline temperature

C) Soil temperature

D) Ambient temperature

 At the end of 24 hour hold period the pressure change valve as a


function of temperature shall be added to the pressure valve
reading noted the adjusted pressure valve, shall be compared
with initial valve. The test shall be considered acceptable if the
difference is within specified limits (usually 1bar)

 Upon acceptance of pressure test the line shall be depressurized


carefully.

6.21.3 BULK DEWATERING AND


 The pipeline de watering will be done form the lowest point.

 The drained water shall be disposed at a pre-agreed location.

 Pipeline pigs shall be propelled in the line using compressed air.

 Upon complete bulk de watering drying process shall start.

 The drying will be achieved by propelling several trains of foam


pigs.

 After the foam pigging dry air will be blown through the pipeline
to achieve desired valve of dew point.

6.22 NITROGEN PURGING AND INERTING

 A nitrogen tanker with an evaporator shall be used as source.

 Nitrogen gas shall be introduced from one end and air purged out form
the other end by controlled opening of a small valve.

 Purging shall continue until 02 pipeline volumes have been purged.

 On completion of purging the valve shall be closed and Nitrogen


pressure to be maintained in the line.

6.23 CATHODIC PROTECTION SYSTEM


 The qualified staff following the AFC drawings and project specification
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 16 of 17
CROSS COUNTRY PIPELINE INTALLATION

provided shall carry out the installation of CP System by client.

 A team from civil work shall be assigned to carry out all civil works
associated with this installation in a sequence determined by the CP
installation team.

 Testing of CP System shall be done to ensure achieving the desired


resistivity using the proper testing instruments having valid calibrated
certificates.

6.24 RESTORATION OF THE RIGHT OF WAY

 Restoration and clean up of the ROW will be in accordance with the project
specification

 All waste materials, wooden supports and foreign materials shall be removed and
shifted to a dump and or the appropriate storage location.

 Any excess earth shall be spread along the ROW by scraping and or harrowing to
the satisfaction of the client representative.

 Access roads, tracks, banks, water courses, fences etc, which have been partially
demolished during the work, shall be restored their original shape and condition.

 Special attention will be taken during restoration of the area of the road, canal and
railway crossing.

 Pipeline route and aerial markers shall be positioned as stated in the project
specification and drawings.

7. TOOLS & EQUIPMENTS


7.1 EXECUTION

 Hand Tools
 Cutting, Beveling & Grinding Machines
 Welding Machine
 Welding Machine (Diesel)
 Cranes
 Trailer
 Tractor with Trolley
 Pipe Layer (Side Boom)
 Excavator with Jack Hammer
 Loader
 Dozer
 Motor Grader
 Dump Truck
 Compressor
 Power Generator
 Blasting machine
 Painting spray machine
DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 17 of 17
CROSS COUNTRY PIPELINE INTALLATION

 Pipe Bending Machine


 Sewage Tanker
 Water Bouser
 Diesel Tanker

7.2 TESTING

 Holiday Detector
 DPT Unit
 RT Of Welds
 Pressure and Temperature Recorder
 Hygrometer
 Dry Film Micrometer
 Salt Detector
 Adhesive Test
 Profile Meter
 Reference Electrode (Half Cell)
 Digital Multimeter
 Insulation Resistance Tester (Meger)

7.3 SAFETY

 Safety helmet
 Safety Shoes
 Safety Goggles
 Gloves
 Welders Helmet
 Dust mask (if required)
 Fire Extinguishers
 Blasting hood.
 Long sleeve (if required)
 Cover all.

8. SAFETY INSTRUCTIONS

During execution of the job all measure shall be adopted to ensure safe
working.
 Client site management system (latest revision) will be implemented.

 All personnel involved will use necessary PPE as required.

 The workers will be made aware of safety requirements related to this activity
through daily, weekly and monthly toolbox and safety talks.

 Safety notice board will be installed.


DESCON ENGINEERING LIMITED MS//MECH/16
Revision 0
METHOD STATEMENT FOR Page 18 of 17
CROSS COUNTRY PIPELINE INTALLATION

 All equipment will be inspected by HSE (DESCON) prior to use.

 During transportation of pipes and other fittings, the material shell be properly
supported and tied on the Trailer.

 Ensure that pipes are properly wedged or blocked to avoid rolling.

 Correct rigging procedure should be observed.

 Access and good housekeeping should be maintained in all fabrication and


erection areas.

 Fire extinguisher should be available in all working areas.

 Proper storage, handling and use of gas cylinders will be observed.

 All cylinders shall be kept in trolleys and in an upright position.

 Welding sets should be checked and maintained regularly for wear and tear.

 Waste Management Procedure shall be strictly followed to keep the job


site neat and clean.

9. ATTACHMENTS
 Project Quality Plan.
 HSE Plan.

Das könnte Ihnen auch gefallen