Sie sind auf Seite 1von 4

Monthly preventive maintenance

Year (2018)
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Machin
Date of Type of
e name/ Engineering
Department doing the preventive Performed
No. Identifi department
name/Section preventive maintenan by
cation signature
maintenance ce
number
Injectable line
1 Injectable machine IN100 M

2 Injectable Laminar flow IN110 Q

3 Sterilizing Tunnel IN120 M

4 Vial Washing machine IN130 M

5 Injectable labeling IN140 M


machine

6 Injectable Conveyors + IN150 M


turn tables

7 Injectable preparation IN160 Q


tank 1000L(1)

8 Injectable preparation IN170 Q


tank 1000L(2)

9 Injectable preparation IN180 Q


tank 500L(1)

10 Injectable preparation IN190 Q


tank 500L(2)

11 Injectable preparation IN200 Q


tank 100L

12 Autoclave IN210 _____


Liquid line
13 Liquid Filling machine LIQ100 M
14 Liquid Capping LIQ110 M
machine
15 Liquid Check weightier LIQ120 _____
16 Liquid Induction sealer LIQ130 _____
17 Liquid Conveyors + LIQ140 M
turn tables
18 Liquid labeling machine LIQ150 M
19 Liquid preparation tank LIQ160 M
3000L(1)
20 Liquid preparation tank LIQ170 M
3000L(2)
21 Liquid preparation tank LIQ180 M
500L(1)
22 Liquid preparation tank LIQ190 M
500L(2)
23 Liquid preparation tank LIQ200 M
100L
Powder line
24 powder Filling machine PD100 A
25 powder Check weightier PD110 _____
26 powder Capping PD120 A
machine
27 powder Induction sealer PD130 Q
28 powder Conveyors + PD140 A
turn tables
29 powder labeling PD150 A
machine
30 v-mixer 500 PD160 M
31 v-mixer 100 PD170 M
32 Hammer mill PD180 M
Water treatment unit
33 Multi-Column Distill WT100 M
Water
Machine
34 Purified Water Plant WT110 M
35 Purified water WT120 M
distribution system
36 WFI distribution WT130 M
system
Air Handling Unit
37 POWDER AHU 1 AHU100 Q
(GF)
38 Injectable AHU 2 AHU110 Q
(B1)
39 Liquid AHU 3 (B1) AHU120 Q
40 Weighting AHU4 (B3) AHU130 Q
41 Store AHU 5 (B3) AHU140 Q
42 HVAC SYSTEM HVC100 Q
(diffusers)
Dust Collector
43 Powder dust collector DC100 _____
44 Dust collector (1) DC110 _____
45 Dust collector (2) DC120 _____
46 Dust collector (3) DC130 _____

Waste Water Treatment Unit


48 Waste Water WST100 _____
Treatment
Boilers
49 Steam Boiler 1 SB100 _____
50 Steam Boiler 2 SB110 _____
Compressors
51 Air compressor (1) CMP100 _____
52 Air compressor (2) CMP110 _____
53 Air dryer (1) CMP120 _____
54 Air dryer (2) CMP130 _____
Chillers
55 Industrial Chiller CH100 Q

56 Heat Pump Chiller CH110 Q

Generator
57 Diesel Power GEN100 Q
Generator
UPS
58 Uninterruptible power UPS100 _____
supply injectable line
59 Uninterruptible power UPS110 _____
supply laboratory
Elevators
60 1000KG ELEVATOR EL100 _____
1
61 1000KG ELEVATOR EL110 _____
2
62 500KG ELEVATOR 1 EL120 _____
Solar system
63 Solar system SO100 _____
Stacker
64 Stacker ST100 _____

Designed by :
Date: Approved by: Date:
Eng.mohammad sokker