4 - Sewerage Reticulation
Trench Excavation
4.1 (i) Trench excavation of sewer pipe for depth exceeding
1.5 m but not exceeding 2.0 m including part backfill
on completion, compaction, removal of surplus,
shoring and/or sheet pile where necessary:-
(a) 225mm dia V.C. pipe 601 lin.m 20.00 12,026.00
(b) 300mm dia V.C. pipe R.O lin.m 20.00
4.2 Extra over item 4.1 for trench excavation in mettalled road. R.O lin.m 75.00
Rate to include cutting of mettalled pavement with diamond
cutter, reinstatement of mettalled road with 50mm thick sand
blanket, 300mm thick crusher run, 50mm thick binder
course and 60mm thick wearing coarse.
4.3 Ditto ~ for trench excavation under existing road side drains. R.O Lump Sum 2,000.00
Rate to include reinstatement of road side drain.
4.4 Ditto ~ for trench excavation under existing main drains. R.O Lump Sum 1,000.00
Rate to include reinstatement of pudu cut main drain.
Pipe Laying
Notes : -
All sewer with diameter less than 450mm shall be
vitrified clay pipe (VCP) with flexible joint and comply
with M.S 881 Part 1 1991, M.S. 1061;1986.
Foundation base of sewer must be compacted with
crushed run.
(b) 300mm dia V.C. pipe (Class A bedding) 429 lin.m 100.00 42,900.00
BQ 4 - 1
Bill No. 4 - Sewerage Reticulation
(a) below ground level to invert level not exceeding 2.0m 14 no 2,000.00 28,000.00
(b) ditto exceeding 2.0m but not exceeding 3.0m 11 no 2,800.00 30,800.00
(c) ditto exceeding 3.0m but not exceeding 4.0m 5 no 3,300.00 16,500.00
(d) ditto exceeding 4.0m but not exceeding 5.0m 4 no 3,301.00 13,204.00
4.9 Supply and fix Heavy Duty ductile iron manhole 34 no 440.00 14,960.00
covers and frames as specified
BQ 4 - 2
Bill No. 4 - Sewerage Reticulation
4.6 (a) Carry out test for straightness and obstruction on all 1 Lump Sum 2,000.00 2,000.00
sewer lines as specified in Clause 4.3(a) of Section 5 of
Specification
(b) Carry out water testing on all sewer lines as specified in 1 Lump Sum 2,000.00 2,000.00
Clause 4.3(b) of Section 5 of Specification
(c) Carry out air testing on all sewer lines as specified in N/A
Clause 4.3(c) of Section 5 of Specification
(d) Carry out C.C.T.V. Test and submission of test report for
sewer lines as directed by S.O. representative or IWK/JPP
Service Connection
(b) Supply and install Marker complete as shown on the Rate Only no 50.00
drawings
(c) To excavate, supply and construct last manhole within Rate Only no
housing lot at the depth of 1.35m as shown on the
drawings
d) To supply and install end cap and install marker to D.I pipe 1 L.s 165.00
for future connection to last manhole of P.S.No.4
IWK Inspection
4.9 Allow for liasing with IWK/JPP for interim inspection 1 Lump Sum 4,000.00 4,000.00
during construction and final inspection for
handing over