ID Task Task Name Duration Start December 2018 Finish January 2019 February 2019 March 2019

Mode 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 02 05 08 11 14 17 20 23 26 29
0 1 Start 0 days Mon 01/10/18 Mon 01/10/18
2 Molding Longspan Cawang 124 days Mon 01/10/18 Fri 01/02/19
31 Pengecoran Box Girder Cawang 133 days Mon 08/10/18 Sun 17/02/19
285 Erection Longspan Cawang 125 days Wed 31/10/18 Mon 04/03/19
286 Persiapan Lahan 114 days Wed 31/10/18 Thu 21/02/19
287 Tutup U-turn BNN 0 days Tue 18/12/18 Tue 18/12/18 18/12
288 Bongkar DPT area P07-P08 & 14 days Wed 31/10/18 Tue 13/11/18
perataan lahan
289 SPK keluar 09/11 0 days Fri 09/11/18 Fri 09/11/18
290 Drawing submit OCG (response 1 day Wed 02/01/19 Wed 02/01/19
comment)
291 Presentasi ke OCG 0 days Tue 18/12/18 Tue 18/12/18 18/12
292 Crane 280 ton 1 (P07) 10 days Wed 05/12/18 Fri 14/12/18
297 Crane 280 ton 2 (P06) 10 days Sun 16/12/18 Tue 25/12/18
302 Assembly truss P05-P06 28 days Sun 16/12/18 Sun 13/01/19
303 Material on site 0 days Sun 16/12/18 Sun 16/12/1816/12
304 Fabrikasi truss P05 - P06 5 days Mon 17/12/18 Fri 21/12/18
305 Fabrikasi tower 10 days Mon 17/12/18 Wed 26/12/18
306 Fabrikasi sleeper 4 days Mon 17/12/18 Thu 20/12/18
307 Setting tower 7 days Sat 22/12/18 Fri 28/12/18
313 Assembly truss 2 days Fri 28/12/18 Sat 29/12/18
314 Setting Elevasi Truss (PLN) 1 day Sat 05/01/19 Sat 05/01/19
315 Assembly beam pembagi & rel 1(PLN)
day Sun 06/01/19 Sun 06/01/19
316 Setting rel (PLN) 1 day Mon 07/01/19 Mon 07/01/19
317 Mob trolley 1 day Tue 08/01/19 Tue 08/01/19
318 Setting trolley 1 day Wed 09/01/19 Wed 09/01/19
319 Pekerjaan Elektrikal & Mechanical
3 days Thu 10/01/19 Sat 12/01/19
320 Commisioning 1 day Sun 13/01/19 Sun 13/01/19
321 Assembly main truss P06 - P07 38 days Thu 20/12/18 Sun 27/01/19
(Dishub)
322 Pembayaran DP 0 days Mon 07/01/19 Mon 07/01/19 07/01
323 Mob main truss 2 days Tue 08/01/19 Wed 09/01/19
324 Assembly main truss utara 5 days Thu 10/01/19 Mon 14/01/19
325 Assembly main truss selatan 5 days Tue 15/01/19 Sat 19/01/19
326 Fabrikasi sleeper 4 days Sat 05/01/19 Tue 08/01/19
327 Fabrikasi tower P07 0 days Thu 20/12/18 Thu 20/12/18 20/12
328 Setting tower P07 1 day Wed 09/01/19 Wed 09/01/19
329 Erection main truss Utara & Selatan
4 days Fri 18/01/19 Mon 21/01/19
334 Setting elevasi 1 day Tue 22/01/19 Tue 22/01/19
335 Setting trolley 1 day Wed 23/01/19 Wed 23/01/19
336 Pekerjaan Elektrikal & Mechanical
3 days Thu 24/01/19 Sat 26/01/19
337 Commisioning 1 day Sun 27/01/19 Sun 27/01/19
338 Shoring P07 (Setting wet joint) 49 days Thu 03/01/19 Thu 21/02/19
Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: MOLDING UPDATE (Re
Milestone Inactive Summary Start-only Critical Progress
Date: Wed 09/01/19
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline

Page 1
ID Task Task Name Duration Start December 2018 Finish January 2019 February 2019 March 2019
Mode 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 02 05 08 11 14 17 20 23 26 29
344 Shoring P08 23 days Fri 11/01/19 Sat 02/02/19
349 P06 63 days Wed 19/12/18 Wed 20/02/19
350 Drawing TPT Sequence 0 days Wed 19/12/18 Wed 19/12/18 19/12
351 Load test Main Truss 1 day Mon 28/01/19 Mon 28/01/19
352 1L3 & 1R3 4 days Mon 28/01/19 Thu 31/01/19
353 1L4 & 1R4 2 days Fri 01/02/19 Sat 02/02/19
354 1L5 & 1R5 1 day Sun 03/02/19 Sun 03/02/19
355 1L6 & 1R6 4 days Mon 04/02/19 Thu 07/02/19
360 1L7 & 1R7 1 day Fri 08/02/19 Fri 08/02/19
361 1L8 & 1R8 1 day Sat 09/02/19 Sat 09/02/19
362 1L9 & 1R9 1 day Sun 10/02/19 Sun 10/02/19
363 1L10 & 1R10 1 day Mon 11/02/19 Mon 11/02/19
364 1L11 & 1R11 1 day Tue 12/02/19 Tue 12/02/19
365 1L12 & 1R12 1 day Wed 13/02/19 Wed 13/02/19
366 1L13 & 1R13 1 day Thu 14/02/19 Thu 14/02/19
367 1L16 1 day Sat 16/02/19 Sat 16/02/19
368 1L15 1 day Mon 18/02/19 Mon 18/02/19
369 1L14 1 day Wed 20/02/19 Wed 20/02/19
370 P07 18 days Fri 15/02/19 Mon 04/03/19
385 Closure 17 days Thu 21/02/19 Sat 09/03/19
386 P05 - P06 7 days Thu 21/02/19 Wed 27/02/19
387 P07 - P08 5 days Tue 05/03/19 Sat 09/03/19
388 P06 - P07 5 days Tue 05/03/19 Sat 09/03/19
389 FINISH 0 days Sat 09/03/19 Sat 09/03/19 09/03

Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: MOLDING UPDATE (Re
Milestone Inactive Summary Start-only Critical Progress
Date: Wed 09/01/19
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline

Page 2

Das könnte Ihnen auch gefallen