Beruflich Dokumente
Kultur Dokumente
INSTITUTE OF TECHNOLOGY
NAME ID no
Acknowledgment
We would like to express our gratitude to all those who gave us the possibility to complete
final project. Especially we are deeply indebted to express our thanks to our advisor
Chalachew Abebe who gave us a complete and series comments and suggestion how to we
go. He also gave countless help and advices that encourage us to finalize this project
We would like to give exceptional thanks to our families whose patient love and help enabled
us to complete this work with no worry about financial.
Finally we can’t forget our friends and classmates for giving us encouragement, valuable
discussions throughout the work of this Project
Table of Content
Acronym................................................................................................................................... vi
Abstract ...................................................................................................................................vii
1 INTRODUCTION ............................................................................................................ 1
1.1 General ........................................................................................................................ 1
1.2 Objective of the project ............................................................................................... 1
1.2.1 Specific objectives .......................................................................................................... 1
1.2.2 General objectives ........................................................................................................... 2
1.3 Methodology ............................................................................................................... 2
1.4 Description of the Study Area ..................................................................................... 3
1.4.1 Site description................................................................................................................ 3
9 Reference ......................................................................................................................... 56
10 Appendices ................................................................................................................... 57
List of figures
Figure 2-1፡Run off hydrograph for full duration .................................................................................. 14
Figure 2-2፡ Stage discharge curve ........................................................................................................ 16
Figure 3-1፡Geological cross section at the weir axis ............................................................................ 19
Figure 3-2: ogee weir profile ................................................................................................................... 23
Figure 3-3: Haydraulic calculation .......................................................................................................... 24
Figure 3-4: type II stilling basin .............................................................................................................. 26
Figure 3-5 tail water and hydraulic jump curve........................................................................................ 27
Figure 3-6 pressure calculation at key points ........................................................................................... 37
Figure 4-1 Force acts on the weir............................................................................................................ 38
Figure 5-2 retaining wall......................................................................................................................... 44
Figure 6-1 main canal cross-section ......................................................................................................... 48
List of tables
Table 2-1፡Daily havest rainfall data consistency test ............................................................................. 3
Table 2-2: Estimation of time of concetration ............................................................................................ 8
Table 2-3 Design rainfall arrangements ..................................................................................................... 9
Table 2-4: Direct runoff computation ...................................................................................................... 12
Table 2-5: Computation of hydrograph for each increment of runoff ........................................................ 12
Table 2-6: Hydrograph components for each incremental runoff ............................................................... 12
Table 2-7: Tail water depth computation ................................................................................................. 15
Table 3-1: U/S profile of the ogee weir .................................................................................................... 21
Table 3-2: D/S Profile the ogee weir ........................................................................................................ 22
Table 3-3: U/S Face curve parameters ...................................................................................................... 22
Table 3-4: stillng basin design for type II basin ........................................................................................ 25
Table 3-5: stilling basin design variables .................................................................................................. 26
Table 3-6 Tail water depth and jump height depth .................................................................................. 27
Table 4-1 stability analyisis of weir .......................................................................................................... 39
Table 4-2 factor of safety against ............................................................................................................ 39
Table 5-1 divided wall height determination ............................................................................................ 42
Table 5-4 U/S retaing wall height determinations ..................................................................................... 45
Table 5-5 U/S retaing wall stability analyisis ............................................................................................ 45
Table 5-6 U/S factor of safety against of retaing wall................................................................................ 45
Table 5-7 D/S retaing wall height determination ...................................................................................... 46
Table 5-8 D/S retaing wall stability analyisis ............................................................................................ 46
Table 5-9 D/S factor of safety againsty of retaing wall .............................................................................. 46
Table 6-1: Quantity of work ................................................................................................................. 50
Table 9-1 antecedent rainfall conditions and curve no (for Ia=0.2S) ........................................................ 57
Table 9-3 unit weight of material ......................................................................................................... 58
Acronym
Abstract
Timble Small Scale Irrigation Project is found in Amhara region, Awi zone and 93KM far from
Bahir Dar. The project is done on TIMBEL River to irrigate 200ha of land. The weather
condition is Weyna Dega agro ecological zone.
This design report contains the back ground of the project, design of head work and other
structures and bill of quantity. In the back ground part objective, significance, working
methodology, location, catchment characteristic, and weather condition of site and water
sources of project are stated.
For safe and economical design of head work, we have developed the 50 year return period
from 35 years daily heaviest rain fall data records. This design rain fall has been estimated to
be 113.58mm generated from a storm of 3.608hr time of concentration and 1hr duration
based on the advanced pattern of storm, incremental rainfall, widely applicable in Ethiopia.
The design flood has been estimated to be 72.6m3/s occur at time of peak (5.66hr) analyzed
based on SCS-CN-method.
On the other hand in the headwork design part we attempt to encompass all prominent
features of the headwork (weir), under sluice, head regulator, stilling basin and retaining wall
are designed based on peak discharge. The weir is designed for the peak discharge with a
height of 1.62m and crest width of 38m (i.e. it is from bank to bank). To be structurally safe
the ogee type weir is selected. Next to these, main canal dimensions are designed based on
the base flow of the river. Canal dimensions are 0.7 depth and 0.8m width with trapezoidal
cross_ section. (at the outlet, it has to be masonry rectangular )
1 INTRODUCTION
1.1 General
Amhara region is endowed with different natural resources, agro-ecologies, biodiversities and huge
manpower. The economy of the region largely depends on subsistence agriculture, which is
traditional and rain fall dependant. The presence of erratic and variable nature of rainfall, farmland
scarcity, poor soil fertility, occurrences of plant and livestock diseases and crop pests, absence or low
use of modern inputs make the practice low productive and traditional type. Due to these increase the
water efficiency by constructing permanent structure like dam, diversion structure etc.
The existing insufficient or unreliable rainfall dependent traditional agriculture is not in a position to
feed the increasing population. In this rationale on top of the need of different intensification efforts,
it is a must to support the current food production with irrigation.
The region has great potential for surface and subsurface water resource. The Timbile River is one of
the surface resources at west Gojam zone in Amhara region. We design diversion structure (diversion
weir) on this river to expand the traditional diversion structure to modern irrigation by constructing
permanent structure. This permanent structure increase the water efficiency by constructing lined
canal on places of high seepage canal routes, quantity and quality of productivity and buildup the
living standard of the people around the area.
1.3 Methodology
In the designing of this final year project on diversion weir we will use the following procedures:
Data collecting from different sources and we get:
50,000 scale top map and a 35 year highest rain fall data
Geological and socio economic repot
Hydrological analysis
Consistency test
Estimation of peak discharge from the given rainfall data
Tail water depth computation
Weir designing
Selection of site and weir type
Weir height determination
Stability analysis
Design of divide wall , under sluice, head regulator and stilling basin
Design retaining wall and main canal.
Description of the Study Area
2 Hydrology Analysis
Descending Log
NO YEAR Rf Rank new Rf log(x)
order (Y)
1 1973 62.4 166 1 2.22 113.2 2.05
2 1974 56.4 113.2 2 2.05 96.6 1.98
3 1975 79.5 96.6 3 1.98 90.4 1.96
4 1976 48.1 90.4 4 1.96 89.2 1.95
5 1977 50.9 89.2 5 1.95 87 1.94
6 1978 63.3 87 6 1.94 79.6 1.90
G.C 2005 WRED Page 3
Timble Diversion Headwork Design
Descending Log
NO YEAR Rf Rank new Rf log(x)
order (Y)
7 1979 71.7 79.6 7 1.90 79.5 1.90
8 1980 53.3 79.5 8 1.90 75.2 1.88
9 1981 71.5 75.2 9 1.88 73.6 1.87
10 1982 113.2 73.6 10 1.87 72.1 1.86
11 1983 72.1 72.1 11 1.86 72.1 1.86
12 1984 66.2 72.1 12 1.86 71.7 1.86
13 1985 96.6 71.7 13 1.86 71.5 1.85
14 1986 42.6 71.5 14 1.85 70.3 1.85
15 1987 48.2 70.3 15 1.85 69.8 1.84
16 1988 64 69.8 16 1.84 68.7 1.84
17 1989 75.2 68.7 17 1.84 68.6 1.84
18 1990 69.8 68.6 18 1.84 67.2 1.83
19 1991 68.6 67.2 19 1.83 66.2 1.82
20 1992 79.6 66.2 20 1.82 64.1 1.81
21 1993 67.2 64.1 21 1.81 64 1.81
22 1994 89.2 64 22 1.81 63.3 1.80
23 1995 55.3 63.3 23 1.80 62.4 1.80
24 1996 51.6 62.4 24 1.80 58.4 1.77
25 1997 87 58.4 25 1.77 56.4 1.75
26 1998 53.6 56.4 26 1.75 55.3 1.74
27 1999 68.7 55.3 27 1.74 53.6 1.73
28 2000 166 53.6 28 1.73 53.3 1.73
29 2001 90.4 53.3 29 1.73 51.6 1.71
30 2002 64.1 51.6 30 1.71 51.4 1.71
31 2003 51.4 51.4 31 1.71 50.9 1.71
32 2004 73.6 50.9 32 1.71 48.2 1.68
33 2005 58.4 48.2 33 1.68 48.1 1.68
34 2006 70.3 48.1 34 1.68 42.60 1.63
35 2007 72.1 42.6 35 1.63
2306.10
Sum 2472.1 64.14 67.83
Mean 70.6314 1.83 15.34
Standard Deviation(dn-1) 22.442 0.12
Skewness coefficient(Cs) 1.08
No of data(N) 35
As shown from the above calculation the station Skewness is greater than 0.4, test for higher and lower
outliers are required. This is done to check whether the adopted data is within the limited range or
not.
Higher outlier Yh Y KnSy
Where: Y = mean of data in log unity
Kn = From table for sample size N
For data N=35, Y 1.833
, Kn 2.628 SY=0.116 (from Subramanian engineering hydrology
Table7.3 and Table7.4)
Yh Y KnSy
1.8332.628*0.116 2.136
ℎ𝑖𝑔𝑒𝑟 𝑜𝑢𝑡𝑙𝑖𝑒𝑟 = 10𝑌ℎ
ier (10)2.136 136.844mm
Higheroutl
The highest recorded value from Enjibara Town metrological station is (166mm) is greater than the
higher outlier (136.844mm). Therefore, the highest value from recorded data, i.e. (166mm) will be
excluded from the hydrological analysis
Yl YKnSy
1.8332.628
*0.1161.529
Loweroutli er10yh
(10)1.529 33.792mm
The Lowest recorded value is (42.6mm) which is greater than lower outlier (33.729mm). Hence no
lower outlier date will eliminated. Therefore, the recorded data is consistent for both outliers.
Conclusion: From the test result it is conclude that the daily heaviest rainfall data recorded from
1973to 2007 E.C year do not depart significantly from the trend of the data series, and hence the data
could be said consistent for flood frequency analysis.
Gumbell (1958) introduced the concept of extreme value distribution and develops a model for
production of hydrologic events such as floods peaks, max rain fail, max wind speed. etc. He defend a
flood as a largest flow in the year (365 day) and termed as the annual series of flood flows a series of
largest values of flood .i e flood flows which are the largest of all the flows occurring on each of the
365 days of a year. For our calculation we use the modified equation of Gumbell. In this case
magnitude 𝑋𝑇 (the Gumble value) hydrologic event may be represented as the mean of the variant
plus the product of the standard deviation & frequency factor. The empirical for this distribution is:
xT=X̅+σn−1 ∗Kt
∑(𝑥−𝑥̅ )^2
𝜎𝑛−1 = √ 𝑁−1
Kt = frequency factor
𝑌𝑇−𝑌𝑛
𝑘𝑡 = (Using modified Gumbell frequency analysis equation 𝑋𝑇 is calculated.
𝑆𝑛
𝑇 𝑇
𝑦𝑇 =-[ln (ln𝑇−1)] or 𝑦𝑝 = − [0.834 + 2.303 ∗ log (𝑙𝑜𝑔 𝑇−1)] = 3.902
T=return period, for weir and small dam the return period (T) = 50 year.
𝑆𝑛 =1.127 and 𝑌𝑛 =0.540 for N=34respectively (source: hydrology and soil conservation2nd edition,
relation between Gumbell’s reduced standard deviation & sample size, table 7.3&7.4, page 105)
3.902−0.540
𝐾𝑡 = =2.98
1.127
𝑋𝑇 = 67.826+2.98*15.336= 113.58mm
Maximum probable flood is a hypothetical flood at a selected location, whose magnitude is such that
there is no chance to exceed. It is estimated by combining the most hydrological and meteorological
conditions considered reasonably possible at the particular location under consideration.
As we have described earlier 34years daily heaviest Rainfall data obtained from Enjibara
Meteorological station is used for determination of maximum probable flood. Based on the available
data, the following methods are used to estimate the design flood from rain fall data.
𝐿𝑖 3
𝑇𝑐 = ∑ 0.948 ( ) ^0.585
𝐻𝑖
Where: Tc = time of concentration (hrs)
Li = length of flow (km)
Hi = elevation difference (m)
Table 2-2: Estimation of time of concetration
the vicinity and adaptation of standard curves is the only option. When we design this project We
have use the standard curve from IDD Manual and used to compute rainfall profile of the project area.
The runoff in mm is determined from the catchment input data and design rainfall. To conclude the
runoff, the rainfall profile is used to determine the actual areal rainfall depth for each time interval.
The incremental rainfall depth is determined by subtracting the required time interval rainfall depth
from the proceeding time interval depth. These incremental are tabulated 1, 2, 3, 4, 5 and 6 in
descending orders and arranged as 6, 4, 3, 1, 2, and 5. Based on the rearranged on the rearranged
order incremental rainfall was calculated. The rearranged incremental rainfall depth is shown in the
table below
Design
Rainfall Rainfall Arran Rearranged Asce
Time point incremental Cumulative
Profile Profile Rank ged p(mm) nding
(hr) Rainfall rainfall p, (mm)
(%) (mm) order incremental Order
(mm)
𝐹 𝑄
= 𝑃−𝐼 And F=P-𝐼𝑎 -Q
𝑆 𝑎
(𝑃−𝐼 )2
𝑎
Then Q=(𝑃−0.8𝑠)
Design flood is calculated SCS (The United States Soil Conservation Service). This method is
derived in 1986 that is primarily used for assessing the project storm aiming for the determination of
the design flood of rural catchments. It is widely adopted for design flood estimation. The approach
considers, watershed parameters, like Area, Curve number, and time of concentration. The curve
number's a function of soil type, vegetation, land use, cultivation practice and antecedent moisture
condition. Estimation of Hydrologic soil cover complex number is made based on the top map , field
trip to the Watershed and the result of detail study of other catchments with similar features and the
estimated wet antecedent moistures condition II (AmcII) is 81.84. But commonly for design flood
estimation antecedent moisture condition III (Amc III) is considered and for antecedent moisture
condition II of 81.84, the corresponding value of antecedent moisture condition III is shown below
the calculation.
Tp D TL D 0.6Tc
2 2
Where, TP፡ time to peak
Tc=3.608, D = Tc/6=0.6hr D will be 1hr since time of concentration is greater than 3hr
Tp =0.5D+0.6*3.608 =2.665
S 25400
hr; Tb
254
=2.67Tp=2.67*2.665=7.115hr CN
S 25400
254 22.087mm
92
Q
p0.2S2
p0.8S
S: maximum potential difference between rainfall and runoff (mm), starting at the time the
storm begins
The peak runoff rate derived from triangular hydrograph is expressed as,
qp 0.21AQ
TP
qp 0.21*15.58*1 1.228m3/s/mm
2.665
Table 2-4: Direct runoff computation
Time H1 H2 H3 H4 H5 H6 SUM
5.00 0.00 0.62 6.16 41.05 6.57 0.00 54.39
5.66 0.00 0.49 5.17 54.69 10.90 1.35 72.61
6 0.00 0.42 4.66 50.52 13.13 2.04 70.79
6.66 0.00 0.29 3.68 42.43 17.50 3.39 67.29
7 0.00 0.22 3.17 38.26 16.19 4.08 61.92
7.12 0.00 0.20 2.99 36.79 15.71 4.33 60.02
7.66 0.09 2.18 30.17 13.59 5.44 51.47
8 0.02 1.67 26.00 12.26 5.03 44.98
8.12 0.00 1.49 24.53 11.79 4.88 42.69
9.00 0.18 13.73 8.33 3.81 26.05
9.12 0.00 12.26 7.86 3.66 23.78
10.00 1.47 4.40 2.59 8.46
10.12 0.00 3.93 2.44 6.37
11.00 0.47 1.37 1.84
11.12 0.00 1.22 1.22
12.00 0.15 0.15
12.12 0.00 0.00
The peak discharge is determined as the maximum of horizontal sum of each incremental runoff
which is equals to 72.61m3/s.
80
70 H3
H4
60
H5
50 H6
Discharge (m3/sec)
H-TOTAL
40
30
20
10
0
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00
-10
Time (hr)
The water discharge is calculated by Manning’s open channel formula. Basic inputs for the analysis
and the detail procedure are described as follows.
V 1 R2/ 3 S ,
n
Where, R = Hydraulic radius = (Area/Perimeter) =A/P
S= average river bed slope
n=manning roughness coefficient
V=flow velocity
QV A
1 1767 0 0 0 0 0 0
2 1767.5 0.5 9.37 21.86 0.43 1.15 10.77
3 1768 1 21.76 27.98 0.78 1.71 37.17
4 1768.43 1.43 35.1972 34.9999 1.005637159 63.182601 72.61
5 1768.5 1.5 37.67 36.14 1.04 2.08 78.23
6 1769 2 57.8 44.98 1.29 2.39 138.03
7 1769.5 2.5 85.69 67.27 1.27 2.37 203.45
8 1770 3 124.72 89.56 1.39 2.52 314.22
Stage Curve
3.5
2.5
Depth (m)
0.5
0
0 50 100 150 200 250 300 350
Discharge (M^3/sec)
From the rating curve, the tail water depth (D/S HFL) corresponding to the flood discharge (i.e. Q
=72.61m3/sec) is found to at 1768.43m masl, which is 1.43m above the riverbed level.
When we select the weir type, we should have to consider the availability of construction materials,
simplicity of the structure/practicality , nature of foundation and the river bed material as well as weir
height. The peak discharge estimated is 72.61𝑚3 /sec. A weir type that can dissipate the energy of
water falling from height needs to have better energy dissipation efficiency, because the weir shape is
capable of resisting the impact from a jet (pressurized stream of fluid) of water. In addition to this the
river carries sizable boulders and cobbles towards the diversion site during flood season. In this
respect an ogee type weir is preferable.
The weir height is determined based on the maximum command area elevation which is required to
irrigate the maximum possible irrigable area and consists of head losses: (1) across the head
regulator, (2) due to slope of main canal (3) required to drive the full supply level in the main canal.
The analysis is shown as follow:
River bed level=1765.98m.a.s.l.
Maximum command area elevation= 1764.22m.a.s.l
Maximum flood elevation=1941.25m.a.s.l.
Distance from the head work site=2000m
Head loss at the turn out=0.05m
Head regulator loss=0.06m
Water depth required =0.5m
loss in the canal=2.67m
Free board=0.1
Total loss=head loss across head regulater + loss in the canal + head loss at the turn out
=0.06+2.67+0.05=2.78m
Full Ssupply Level=1767.5
Canal outlet level=1767.5-0.5=1767m.a.s.l
Weir crust level= 1764.22+0.5+0.1+2.78=1767.6m.a.s.l
weir height=1767.6-1765.98masl=1.62m
Accordingly the weir height was fixed to be 1.62m and the corresponding crest level was fixed to
be 1767.6m.a.s.l
So, considering the actual site conditions of the river banks stability and width of the river channel,
the crest length of the weir is considered a 38m
The overflow section of the weir is designed in order to pass 100% of the flood without considering
to accommodate through the under sluice portion. The usual ogee weir formula is used for the
evaluation of the discharge that could pass over the weir and it is expressed as:
Cd= Coefficient of Discharge =2.2 (from Irrigation and Hydraulic Structures, Arora, third
edition august 2001.)
L= Overflow length of a weir=38m
2/ 3 2/ 3
He Qd 72.61
Head over the weir crest, 0.9m
2.2L 2.238
River bed level = 1765.98m.a.s.l
Weir crest level, = 1767.6m.a.s.l
U/s TEL = crest level + He
= 1767.6+0.9m= 1768.51m.a.s.l
But High flood level before construction of the weir D/S HFL is =1767.41m (From
Rating curve)
Assume He =Hd
When p/H d > 1.33, then the velocity of approach has been found to have a negligible effect up on discharge
va =Q/ (L (Hd+P))
Va = (72.61/ (38*(0.9+1.62)))
Va =0.755m/s
Ha=VA^2/ (2g)
Ha=0.755^2/ (2*9.81)
Ha=0.029m
Hd =0.9m
p 1.621.33the velocity of approach can be neglected
Then; H 0.9
d
3.4.2 Afflux
The rise in the water level on the upstream compared to level in the downstream at the time of
passage of the design flood. Lesser waterway would result in larger afflux and vice versa.
The rise in the maximum flood level of the river upstream of the weir after construction is known as
afflux. The amount of afflux will determine the top levels of guide banks and marginal banks. By
providing a higher afflux, the waterway and, therefore, the length of the weir can be reduced, but it
will increase the cost of training works and the risk of failure by outflanking. At the same time, the
discharge intensity and the consequent scour shall go up, and hence, the sections of loose protections
upstream and downstream as well as the depths of pile lines at either ends shall have to be increased,
thereby making it costly. It is, therefore, always desirable to limit the afflux to a safe value of 1.0 to
1.2 meters, however, in steep reaches with rocky bed, a higher value of afflux may be permitted.
Afflux=u/s HFL-D/s HFL
1768.51masl-1767.41masl= 1.1m
The upstream profile extends up to the point x=-0.27Hd where Hd is the depth of flow at the design
discharge above the weir crest. Hd was determined to be 0.9m. Therefore the upstream profile
extends up to the point of coordinates (-0.21m, 0m). The upstream profile at an interval of 0.04m in
the x direction is presented in the following table.
Hence, from the construction point of view and stability, it is better to provide 1:1 d/s slope.
𝑋 1.85
𝑌 = 2∗𝐻𝑒 0.85 Where, He=Hd
𝑋 1.85
Y=X1.85/ (2*He0.85) = X1.85 /2*(0.9)0.85 𝑌 = 2∗0.90.85
𝑋 1.85
𝑌= 1.65
𝑑𝑦 𝑉 1
= =
𝑑𝑥 ℎ 1
𝑑𝑦 1.85𝑋1.85−1 1
= =
𝑑𝑥 1.65 1
1.65
𝑋 0.85 = 1.85 , 𝐹𝑜𝑟 𝑋0.99𝑚 𝑎𝑛𝑑 𝑌 = 0.59𝑚
Based on the above formula the coordinate of x for y=0 to y=1.62are tabulated as follows:
From the ogee weir profile the radius of the bucket is H/4 where H is weir height (i.e.=1.62/4=0.41m)
and the point at which the bucket starts is at H/8(i.e.=1.62/8=0.2m)
The bottom width of the ogee shape weir is calculated by taking of the value of y =1.62m then find
the value of x from downstream profile equation (i.e.Y=X1.85/ (2*He0.85)) then x will be 1.7m finally
bottom width will be 1.7+b=1.7+0.23=1.93m provideB=2m) see the figure below.
𝑦1 0.227
𝑦2 = (√1 + 8 ∗ 𝐹𝑟2 − 1) 𝑦2 = (√1 + 8 ∗ 5.1882 − 1) =1.65m
2 2
1. Basins for Froude numbers less than 1.7:- no special stilling basin is needed
2. Basins for Froude numbers between 1.7and 2.5:- pre-jump stage
3. Basins for Froude numbers between 2.5and 4.5(type I ) transition flow stage
4. Basins for Froude numbers greater than 4.5 and velocity less than 15m/s (type II) provide
basin with chute blocks, baffle blocks and end sills.
5. Basins for Froude numbers greater than 4.5 and velocity greater than 15m/s (type III) in this
case baffle block is not provided.
The incoming velocity at the downstream of the spillway is 7.89m/s, which is less than 15m /s and
the Froud number, is 5.28. Therefore, stilling basin type II is selected the length of the stilling basin,
the height h3 of the baffle block and the height h4 of end sill are obtained from table below.
Fr 5 5.2 6
L/y2 2.3 2.34 2.5
h3/y1 1.5 1.54 1.7
h4/y1 1.2 1.24 1.3
𝐿
= 2.34, 𝑊ℎ𝑒𝑟𝑒 𝑌2 𝑖𝑠 Post − jump depth
𝑌2
ℎ3
= 1.54, 𝑊ℎ𝑒𝑟𝑒 𝑌1 𝑖𝑠 Pre − jump depth
𝑌1
ℎ4
= 1.24, 𝑊ℎ𝑒𝑟𝑒 𝑌1 𝑖𝑠 Pre − jump depth
𝑌1
Iteration
of Y1
Eo =
H Q q P He
He+P y1 V1 Fr y2
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.50 10.77 0.28 1.62 0.26 1.88 0.04 7.03 11.19 0.62
1.00 37.17 0.98 1.62 0.58 2.20 0.13 7.49 6.62 1.16
1.43 72.61 1.91 1.62 0.91 2.53 0.24 7.96 5.19 1.65
1.00
0.80 Tail water depth
0.60 y2
0.40
0.20
0.00
0.00 20.00 40.00 60.00 80.00
discharge(m^3/s
The relation of the tail water and jump depths for different discharges determines the scouring effect
of the flow on the riverbed and bank. The results of this analysis as it is plotted in the figure above
shows that the tail water depth is lower than the jump depth throughout all the discharges. as the
TWRC is lower than HJC, the hydraulic jump forms at a certain section downstream of the toe. For the
formation of the jump, the horizontal apron may be depressed by excavating the river bed downstream of the
toe of the spillway to increase the tail water depth. The depth of depression may be equal to the difference b/n
the tail water depth and post jump depth.
Particl diamater=D50=1mm
2 2
1/ 3 1/ 3
Scour depth: R 1.35* q 1.35*1.91 1.72m
f 1.76
U/S HFL =1768.51m.a.s.l
Then, the upstream scour depth, d1, is determined using the following relation
d 1 = River Bed Level – U/S LSL
= 1765.89-176.93=-0.05 provide d1=1m
Then the downstream scour depth, d2 will be, is determined using the following relation
d 2 = River Bed Level – D/S LSL
=1765.99-1763.97=2.01provide 2m
=15*1.62=24.3
The length of the downstream pervious floor, Ld, is given by
𝐻𝑠 1.62
Ld = 2.21C√ 10 =2.21*15√ 10 =13.34 provide 14m
Intermediated piles of smaller length were ineffective except for local redistribution of
pressure.
GE H . 1
d2
2
1 1 b
2 d2
17.5 =8.75
2
1 18.75 =4.9
2
2
GE H . 1
d2
𝐻
Firstly ℎ= 𝐿𝑏
h= pressure head
1.62
ℎ= ∗ 22.5 = 1.3
28
4 ℎ
𝑡= ∗( )
3 𝐺−1
4 1.3
𝑡= ∗( ) = 1.24 𝑝𝑟𝑜𝑣𝑖𝑑𝑒 1.2𝑚
3 2.4 − 1
𝐻
ℎ= 𝑏
𝐿
Where b=12.5
H= 1.62m
L= 28m
h= pressure head
1.62
ℎ= ∗ 12.5 = 0.72
28
4 ℎ
𝑡= ∗( )
3 𝐺−1
4 0.72
𝑡= ∗( ) = 0.688𝑝𝑟𝑜𝑣𝑖𝑑𝑒 0.7𝑚
3 2.4 − 1
For the upstream apron, nominal thickness i.e 0.5 is provided because the poundage can stabilize its
uplift pressure and piles have nominal thickness i.e.0.5m due to the insignificance of its thickness.
B=17.5
D1=1
𝑏 17.5
𝛼= = = 17.5
𝑑1 1
1 + √1 + α2 1 + √1 + 117.52
λ = = = 9.26
2 2
φD 1 = 100 − φ D=100-14.93=85.07%
φE 1 = 100%
𝐷+𝑑 𝐷
𝐶 = 19 ( ) (√ ′ )
𝑏 𝑏
2+1 2
𝐶𝑚1 = 19 ( ) (√ ) = 1.13%(+𝑣𝑒)
17.5 16.7′
b=17.5
d2=2m
𝑏 17.5
𝛼= = = 8.75
𝑑2 2
1 + √1 + α2 1 + √1 + 8.752
λ = = = 4.9
2 2
G.C 2005 WRED Page 34
Timble Diversion Headwork Design
φC =0
𝐷+𝑑 𝐷
𝐶 = 19 ( ) (√ ′ )
𝑏 𝑏
1+2 1
𝐶𝑚2 = 19 ( ) (√ ) = 0.8%(−𝑣𝑒)
17.5 16.7
𝐻∗𝑞
𝐿2 + 𝐿3 = 18 ∗ 𝐶 √
10 ∗ 75
𝑄 72.61
𝑞= = = 1.91
𝐿 38
1.62 ∗ 1.91
𝐿2 + 𝐿3 = 18 ∗ 15√ = 14.66𝑚
14 ∗ 75
Therefore the downstream protection length L3=10.405-10=0.4m. Upstream protection is 1.5 times
the upstream pile depth (d1)
=1.5*1.2=1.8 m
𝑊𝑒𝑖𝑔ℎ𝑡(𝑊) = 𝛾𝑐 ∗ 𝐴𝑐
ℎ2
𝑃𝑤 = 𝛾𝑤 ∗
2
the weir is calculated for case i.e. water raise up to crest level of the weir.
Lever
arm
(about
code the
Dimension Load toe) Moment
Width Depth Vertical Horizontal R Positive Negative
Pw 1.62 1.62 0.00 13.12 0.54 0.00 7.09
W1 1.00 1.62 38.88 0.00 1.50 58.32 0.00
W2 1.00 1.62 19.44 0.00 1.33 25.92 0.00
Ps 12.96 1.62 0.00 4.22 0.54 0.00 2.28
U 2.00 1.62 16.20 0.00 1.33 21.60 0.00
Sum 16.58 6.48 74.52 17.35 5.25 105.84 9.37
Scour the silt deposited in front of the canal off take (regulator)
In addition to the supply of water to the intake and the removal of silt, this acts to remove the boulder
that comes to wards it.
Design consideration
To ensure proper scouring its capacity should be at least double the canal discharge.
The crest of the under sluice should be lower than the crest of the head regulator at least by
1m to 1.2m if special silt exclusion is not provided. (Source; Irrigation and water power
engineering Dr.B.C.PunmiaDr.Pande.B.B.LAL, 12th Etd. Newdelhi, laxmi, publication, 1992.
Gargpp 183 )
The sill level of this under sluice is fixed to be 0.77 m higher than the minimum river bed level.
Hence the sill level of the under sluice=1765.98+0.77=1766.75masl where the canal sill level is
1766.75masl
Considering this, the opening size of the gate is 1.2 m*1.2 m. Considering Orifice (opening or vent)
flow and pond level case, the discharge passing is computed using the following formula.
Q=Cd*A (2*g*h) ^0.5
The forces that exist in the divided wall are self-weight of the structure, silt and water pressures that
occur in the side of the weir. Thus, the worst case is considered, but for the under sluice side it is
stabilizing and we intentionally left it, and provide only for the upstream side only.
Descriptions values
U/S HFL 1768.51
U/S RBL 1765.98
Free bored (assume) 0.6
divided wall height 3.13
width 0.5
The recommendation is
L
= 20 to 35
t
whereL = length of the greater span=1.30m.
t = thickness of slab
Take L =
30 => t= L = 1.30/30 = 0.043m, Provide t= 0.2m
t 30
The reinforcement is provided in accordance with the minimum percentage of reinforcement. Hence,
G.C 2005 WRED Page 42
Timble Diversion Headwork Design
As= 0.15% of gross area of the section (Gross area= 0.2*1.30= 0.26m2)
As 0.15*0.26 0.00039
m2
100 =390mm2
S 1000
*as 2 𝜋∗122
Spacing as is assumed bar Φ12mm bars as =𝜋𝑑4 = = 113𝑚𝑚2
As 4
1000*113
S= 390 = 289.74mm
Provide Φ12 bars at 200 mm c/c spacing in both directions with minimum reinforcement cover of
25mm for slab and breast wall.
The common concern in design of retaining wall is that the masonry section of the retaining wall
must have sufficient self-weight to resist the thrust due to earth pressure occurs at the back without
overturning, sliding, tension and compressive stress developed within the body of the structure. The
Maximum design flood and the flood jump height govern the height of the retaining wall with some
free board provided to protect overtopping of flood and scouring of the banks.
Hence the level of divide wall and weir body foundation should be the same and is 1765.98m.asl
U/s wall height = U/s HFL – river bed level + free board, Adapt 0.6m free board
Provide 3.13m wall height and the top level of the divide wall
D/s wall height = (D/s HFL – river bed level) + free board
G.C 2005 WRED Page 43
Timble Diversion Headwork Design
Provide 2.03m wall heights at d/s end of the weir and the top level of the divide wall
= 1765.98masl + 2.03m=1768.01masl
Therefore, the proposed divide wall section is structurally stable. thus, bearing in mind the wall
height the load’s acting on the wall and the materials proposed for wall construction Provide
2m*2.1m*3.13m and 1.5m*1.7m*2.03m (top, bottom, and height) divide wall dimensions for U/s and
D/s respectively.
6 Main canal
The main canal runs almost along the contour line for a total length of 4000m and a capacity of
0.4m3/sec. It has two part depending up on the construction material and geological condition. In
which the first 2000m is a trapezoidal lined canal to avoid risks that comes from the river edge and to
minimize seepage lose, this increases efficiency of canal. The second part of the canal is unlined
canal of trapezoidal canal.
Area =(b+mY)*Y
wetted perimeter(P) =𝑏 + 2𝑌 ∗ √1 + 𝑚2
hydraulic radius(R) =A/p
canal depth (Y) = d+ free board
2 1
𝐴∗𝑅 3 ∗𝑆 2
Then the canal discharge (Q) = 𝑄= 𝑛
n= manning coefficient
Therefore from the above equation the dimension of the canal is calculates as follow
The full supply discharge of the canal =Duty*command area *correction factor (take 1.5)
1.38Lt/s/ha*200ha*1.5
Based on these a hydraulic economic efficient channel the one which can pass maximum
discharge with minimum perimeter is calculated using the formula
5
𝑄×𝑛 ((𝑏+𝑌)𝑌)3
1 = 2 …………….**
𝑆2 [𝑏+2𝑌×√1+𝑚2 ]3
Therefore the canal dimensions are width (b) = 0.8m and canal depth (d)
The gate for canal head regulator is to be vertical sheet metal of size 0.7 m x 0.7m for the closure of
the opening space providing some extra dimensions for the groove insertion.
The area of the canal head regulator =h*w=0.7*0.7=0.49m2
Driving head,hd=h/2=0.7/2=0.35m
For the orifice flow, Qd=Cd*A√2𝑔ℎ = 0.6 ∗ 0.49√2 ∗ 9.81 ∗ 0.35 = 0.77𝑚3 /𝑠,safe
7 BILL OF QUANTITY
Table 7-1: Quantity of work
2 Divide Wall
Excavation 1 m3 7.8
Lean concrete 1 m3 0.1
Masonry 1 m3 6.2
2
Masonry 1 m 1.2
3 Under Sluice
Excavation 1 m3 9.0
3
Lean concrete 1 m 0.2
Cyclopean Concrete 1 m3 7.0
4 Operation Slab and Breat wall
Reinforced Concrete m3 0.3
Reinforcement bar, φ12 10 kg 8.87
Reinforcement bar, φ12 13 kg 15.00
Form work 1 m2 0.66
5 Retaining wall
5.1 U/S Retaining wall
Excavation 1 m3 25.2
Masonry 1 m3 55.6
3
Masonry 1 m 1.4
5.2 D/S Retaining wall 1.4
Excavation 1 m3 12.6
Masonry 1 m3 27.8
3
Masonry 1 m 0.2
EIA is discipline associated with feasibility checkup of a project against the environmental, social &
economical aspects.
In a broad sense EIA is the systematic process to identify, predict and evaluate the potential impact of
proposed action and project relative to:-
Physical
Biological
Cultural and
To promote sustainable development by ensuring the development proposal and not undermine
critical resources and ecological functions or the well being, life style and livelihood of the
communities and the people who depend on them.
8.1.1 Screening
Screening is the process of EIA whether a project requires an EIA or not
International unions all major donor countries screens out whether a particular project needs to run
EIA or not. Different agencies and governments in the world have adopted different approaches.
Irrigation and agricultural related development projects are generally requiring a full EIA according
to agreed organizations.
8.1.2 Scoping
After screening & when decision has made for further environmental assessment of a project, the next
stage is to determine the scope of EIA study. Scoping helps the progress of EIA by identifying:-
1. Reduction of air quality due to Watering of the area from which dust is
generated.
Dust formation from construction
2. Loss of flora and fauna due to weir locate projects far away from sensitive areas
construction in the site carry out necessary rehabilitation measures when
phasing out a project
3. Disturbance of ecosystem because of avoid construction materials during breeding
extraction of sand, gravel & rock for seasons in both water and terrestrial ecosystems
construction material. avoid the use of dynamite(explosive)
4. Change of the living condition of Construct fish ladders so that the fishes jump
and migrate against the flow of the water freely.
fish when its migration route is
5. Land use conflict may occur when Compensation may need to be considered for
the area is occupied. those whose housing, land resources, welfare or
livelihood are directly affected by projects.
give employment opportunity
6. Transmission of disease between Sanitary or precaution measures can be
human and animals. accomplished through a comprehensive health
awareness campaign.
Avoid stagnating water and give consecutive
awareness to reduce the occurrence of malaria
and other related diseases.
Source:- Dr. Belayneh Ayele, 2005 E.C. EIA lecture note, published by BDU college of
Agricultural and Environmental science, Bahir dar.
In this project the ogee weir type is selected in order to dissipate the higher energy due to higher
discharge and boulders that comes from river flow. It is structurally safe but the design analysis and
construction of ogee type is difficult as compared to broad crested weir type.
In this design all parameters that suggested must be considered based on the given dimension and the
selected site. In order to get stable serviceability of the weir, canal, retaining wall and divide wall, the
construction material of the structure should be done based on the design manual and the appropriate
time.
10 Reference
1. Irrigation and Water Power Engineering Dr.B.C.Punmia Dr.Pande.B.B.LAL, 12th
Etd.Newdelhi, laxmi, publication, 1992.
6. IDD Manual
11 Appendices
Table 11-1 antecedent rainfall conditions and curve no (for Ia=0.2S)
10 0.40 2.22
20 0.45 1.85
30 0.50 1.67
40 0.55 1.50
50 0.62 1.40
60 0.67 1.30
70 0.73 1.21
80 0.79 1.14
90 0.87 1.07