Beruflich Dokumente
Kultur Dokumente
The history of Performance Audit under the SAI Pakistan is not very long. It dates back to late Seventies
that the department undertook the task of Performance Audit and arrangements were made to set up a
Performance Audit wing and bring out guidelines on Performance Audit. The SAI Pakistan published a set
of Performance Audit guidelines during 1981-1993 with the help of technical assistance from Royal
Government of the Netherlands.
The initial Guidelines and other literature on Performance Audit contained limitations and constraints being
first effort of Performance Audit under SAI Pakistan. These initial guidelines did not provide the sufficient
details to auditors regarding how to conduct Performance Audit as the main focus was on the concept of
discounted cash flows (DCF) analysis. The rapid changes in audit methodologies, Public administration, and
information technology coupled with enhanced emphasis on the accountability of public managers
necessitated the revision of the Performance Audit guidelines. This revision is basically a shift from
traditional method of internal control evaluation to the new concept of enterprise risk assessment for a
comprehensive value for money auditing.
SAI Pakistan continues to innovate and develop new products that meet emergent needs The Performance
Audit Manual in hand is an attempt by the SAI Pakistan to standardize planning, execution and reporting on
Performance Auditing in Pakistan, as per International best practices. This manual not only enumerates
guidelines on effective Performance Auditing but also provides a mechanism for quality assurance of the
Performance Audits. It's my considered opinion that introduction of this Performance Audit Manual in SAI
Pakistan will improve upon the effectiveness of Performance Auditing in Pakistan and will go a long way in
examining economy, efficiency and effectiveness of public sector operations. In fact this is another step
forward in our constant strive to put in place systems, procedures and equip our workforce with tools and
frameworks to transform us into a progressive SAI.
-sd-
Dated: February 14th,
2012 Islamabad
(Muhammad Akhter Buland Rana)
Auditor General of Pakistan
ii | P a g e
1. INTRODUCTION ..................................................................................................................................................................... 1
A. CONTEXT ........................................................................................................................................................................................ 1
B. EXISTING GUIDELINES ON PERFORMANCE AUDITING ........................................................................................................................... 1
C. OBJECTIVES OF THE MANUAL ........................................................................................................................................................... 2
D. ORGANIZATION OF THE MANUAL ....................................................................................................................................................... 3
E. AUDITOR GENERALS MANDATE FOR PERFORMANCE AUDIT ................................................................................................................. 3
F. TONE AT THE TOP ............................................................................................................................................................................ 3
6. AUDIT EXECUTION.............................................................................................................................................................. 35
3| Page
4|Page
ANNEXES...................................................................................................................................................................................... .90
v|Page
TABLE 5: AQMW ANNUAL PLAN FOR QUALITY ASSURANCE REVIEW FOR THE YEAR ENDING 30 JUNE ............................................................ 81
TABLE 21: QUARTERLY PLAN FOR THE PERIOD FROM ... TO... (INSERT DATES) ..............................................................................................114
6| P a g e
7| P a g e
8| P a g e
Box II FROM: INTOSAI HOWTO INCREASE THE USE AND IMPACT OF AUDIT REPORTS: A GUIDE FOR SUPREME AUDIT
INSTITUTIONS .... 33
ix | P a g e
10 | P a g e
1. Introduction
A. Context
1.1 The development of Performance Audit (PA) Manual is part of the broader objective of the Auditor
General of Pakistan (AGP) to build capacity in performance auditing. Capacity building is a
comprehensive term and in a generic sense it involves at least the following elements:
(a) Independence of the Supreme Audit Institution (SAI): It refers to the independence of the SAI from
the executive departments for budget and human resource needs. The independence is ensured by
the law that also gives the SAI authority to plan and execute audits.
(b) Authority: It refers to the authority of the SAI with respect to other stakeholders and executive
departments to obtain information and to oversee implementation of audit recommendations and
review internal control systems.
(c) Ability to hire and fire competent persons: It refers to the ability of the SAI to identify, recruit,
compensate and retain personnel of desired knowledge and skills for performing its functions
adequately.
Framework for knowledge management: It refers to the ability of the SAI to retain institutional
memory, creating new knowledge and transfer of knowledge to future generations etc."
(d) Guidance for auditors: It refers to the guidance of the SAI in the form of manuals, guidelines,
practice advisories, operating procedures and code of ethics for auditors at all levels.
1.2 It is in the context of the last of the above elements of capacity building effort that the AGP has decided
to issue a manual for performance auditing.
(a) The first set of Guides revolves around the concept of discounted cash flow (DCF) analysis. The
tools of the analysis include working out benefit/cost analysis, net present value, output budgeting,
sensitivity testing and internal rate of return. The comprehensive name for these tools is DCF
analysis. The Guides do not go beyond this concept. The Guides produced during the second phase
do use other methods of analysis as well. However, they do not approach the subject of
performance auditing in a systematic manner.
(b) The Guides do not tell the auditors how to conduct performance audit in sufficient detail. There is
little material in the Guides by way of standardized methodology for undertaking performance audits
in all situations.
1|Page
(c) Significant changes have taken place in public administration, auditing methodology and
information technology since the time the Guides were written. For example, the role of Government
has undergone major changes. Massive nationalization has given way to wholesale privatization.
The number and size of public sector enterprises has declined enormously. The Government is
dishing out grants to NGOs for various functions which it used to handle directly.
(d) Developments in public administration have changed the perceptions of the people about role of the
Government. For example, there is a lot of emphasis now on accountability of public managers and
politicians, transparency and freedom of information and good governance that is free from
corruption and nepotism.
(e) Side by side, major developments have taken place in the methodology of performance auditing. A
major development in auditing methodology is emphasis on risk assessment. The traditional method
of internal control evaluation as the focal point in audit planning has given way to enterprise risk
assessment.
(f) Developments in computerization have also influenced the methodology of performance auditing.
Internet has virtually revolutionized the flow of knowledge and information at no cost or at a minimal
cost. The time these Guides were written, most of knowledge was available in hard copies in form of
books, reports, papers and research notes and was also not available in Pakistan. With the easy
availability of Internet, information gathering has become lot more simple than what it used to be.
Communication through e-mail and its free availability and the possibility of transmitting documents
as attachments has also revolutionized the way the auditors used to work. The auditors can send
and receive large chunks of information to and from their colleagues and bosses at no cost almost
instantly. Supervision of audit and quality assurance has become extremely fast and effective
because of the availability of e-mails. Such facilities were not available when the Guides were
written. The authors had to think of various long-winded methods of teaching auditing techniques in
that environment.
(g) These developments have necessitated development of a compact and comprehensive manual for
performance auditors that not only encompasses the changes in public administration that have
taken place since the existing Guides were written but also incorporates state of the art
methodology in performance auditing.
(a) Develop a set of general instructions for planning, executing and reporting on performance audit by
adopting, adapting and integrating existing departmental instructions and guidance with
international practice.
(c) Define roles and responsibilities of various levels of staff with respect to performance auditing.
(d) Design tools of accountability of auditors and audit managers for quality assurance in performance
auditing.
1|Page
(a) audit all expenditure from the Consolidated Fund of the Federation and of each
Province, and to ascertain whether the moneys shown in the accounts as having been
disbursed were legally available for, and applicable to, the service or purpose to which they
have been applied or charged and whether the expenditure conforms to the authority which
governs it;
(b) audit all transactions of the Federation and of the Provinces, relating to Public Accounts;
(c) audit all trading, manufacturing, profit and loss accounts and balance sheets and other
subsidiary accounts kept by Order of the President or of the Governor of a Province in any
Federal or Provincial; and
(d) audit, subject to the provisions of this Ordinance, the accounts of any authority or body
established by the Federation or a Province, and in each case to report on the expenditure,
transactions or accounts so audited by him.
1.7 These provisions empower the AGP to undertake audit, which in its generic sense, also include
performance audit.
• Performance auditing would become one of the routine functions of the FAOs.
• The promotion and career prospects of auditors would be linked to good quality performance audit
reports.
• Independent quality assurance of the PA work done by the field auditors would ensure a merit-
based motivational policy.
• There would be a competition for more resources and greater recognition and support for high
quality performance audit work.
12 | P a g e
(a) All senior managers will undergo a certain minimum period of training and orientation in PA every
year.
(b) The performance of individual officers will reflect the work done on PA during the year.
(c) The incentive system of the Department will incorporate reward for outstanding work in PA.
Role of Deputy Auditor General of Audit Policy and Special Sectors (APSS) in PA
1.11 The Deputy Auditor General (APSS) will be the focal person for all policy-related matters on PA.
Performance Audit Wing (PAW) will function under the supervision of DAG (APSS).
13 | P a g e
2.2 Despite a general consensus on need for expanding the scope of audit, there is no universally agreed
definition of performance auditing. However, most of the definitions agree that the performance auditing
focuses on the economy, efficiency and effectiveness in the management of public resources. INTOSAI
has defined the performance auditing as follows1:
Performance auditing is concerned with the audit of economy, efficiency and effectiveness
and embraces:
(a) audit of the economy of administrative activities in accordance with sound
administrative principles and practices, and management policies;
(b) audit of the efficiency of utilization of human, financial and other resources, including
examination of information systems, performance measures and monitoring arrangements,
and procedures followed by audited entities for remedying identified deficiencies; and
(c) audit of the effectiveness of performance in relation to achievement of the
objectiveness of the audited entity, and audit of the actual impact of activities compared
with the intended impact.
1 International Organization of Supreme Audit Institutions. 2004. Implementation Guidelines for Performance
Auditing Vienna: INTOSAI.
5|Page
6|Page
Economy
• reduction in costs through better contracting, bulk buying, etc;
• reduction in costs through economies on usage of personnel or other resources;
• introduction of charges where none were previously imposed or revision of charges;
> rationalization of facilities;
Efficiency
• greater outputs from same inputs;
• remedying duplication of effort or lack of coordination;
Effectiveness
• better identification/justification of need;
• clarifying objectives and policies;
• introducing better sub-objectives and targets;
• better achievement of objectives by changing the nature of outputs or improved targeting;
Improved accountability
• improved visibility of procedures and outputs;
• improved accountability for expenditure to the legislature and to the public sector;
• improved forms of account, including commercial formats;
• improved external control and monitoring by departments;
• better and/or more accurate performance indicators;
• better comparison between similar agencies;
• greater information on sector performance; and
• clearer and more informative presentation of information.
7|Page
2.11
E. Approach of Performance Auditing
According to INTOSAIISSAI # 3000, performance auditing has two approaches:
• Results-oriented approach
• Problem-oriented approach
8|Page
2.19 Performance auditing follows a normative approach. It does not stop short at identifying instances of
waste, inefficiency and ineffectiveness. It goes a step further and makes recommendations for remedial
action.
2.20 Although performance auditing is fundamentally concerned with improving public service and
management of public resources, yet it has implications for accountability of the public managers. The
managers who could not produce results as planned have to account for their performance. In this
respect, performance auditing has a sharper bite than financial auditing.
2.21 Performance auditors do not question policies of the Government directly. However, they trace
performance of the projects or programs to policies, if the cause of poor performance lies in faulty
policies.
2.22 The canvas of performance auditing is quite vast and it borrows from different auditing traditions. In the
final analysis performance auditing requires an in-depth analysis and research in the subject of audit. It
requires multiple skills and analytical abilities. Basically, performance auditing is an intellectual
enterprise and auditors with higher education and knowledge and skills should undertake it.
9|Page
• Sector studies
• State-of-the-art studies
• The SAI should have a clearly defined mandate for performance audit.
• Performance audit should be formally planned.
• The criteria for performance audit should be made known to the auditee and if possible agreed
with them.
• Performance audits should be properly supervised.
• Performance audit report should be based on relevant, sufficient and competent evidence.
10 | P a g e
11|P a g e
Approach Finds errors and omissions, based on Measures performance, based on internal as
internal records and evidence well external evidence
Criteria Applies accounting standards, rules, Uses applicable rules, regulations, and
and regulations. Standard criteria for all generally accepted management
audits practices, and technical standards, etc.
Unique in each case
Reports Annual report, more or less Long form reports depending on nature of
standardized audit and reporting policies of the auditee
12 | P a g e
of policy implementation and do not question the policy itself. However, the performance
evaluation can question the policy as well2 3 4.
(b) Independence Supreme Audit Institutionsor other auditors who are independent of the
executive conduct performance audits independently. Performance evaluation may or maynot
be independent of the program management in ail cases.
(c) Reporting mechanismPerformance audit reports in the government are placed before the
parliament or governing boards of the public enterprises. The reports of performance
evaluation are usually submitted to the minister-incharge or the chief executive of the
enterprise.
(d) Criteria: Thereare differences in the criteria that performance auditing uses as compared to the
performance evaluation. The performance auditing uses good management practices as basic
criteria for auditing the performance and making recommendations. The performance
evaluation uses the technical operational standards as basiccriteria for evaluation and making
recommendations.
2.35 Performance auditing and performance evaluation do overlap at certain points. But as
disciplines, they require different types of expertise and serve distinct set of purposes.
2 McPhee, Ian. 2006.Evaluations and Performance Audit: Close Cousins or Distant Relatives?Canberra: Australian
National Audit Office. Pp.17.
3 Ibid.
4 Ibid.
13 | P a g e
Entry Interview ^
3. Audit Execution
Audit Execution
1—
k ---- ► Ongoing
Working Papers J dialogue
to
clarify/
resolve
^ _ Exit Interview
issues
4. Audit Reporting
i ------►
Draft Report |
Entity Response j
DAC Decisions j
5. FOIIOW-UD
K Tracking Implementation of
^ Recommendations
Follow-up Audit j
14 | P a g e
15 | P a g e
Chapter 3 Annual Plan for Performance Audit
21 | P a g e
3.11 PAW will consolidate the proposals and priorities received from FAOs and may discuss further with the
FAOs to have a clearer view. PAW may like to hold seminars with FAOs to firm up the views and smooth
out any overlaps and duplications.
3.12 For preparing the strategic plan PAW would undertake necessary research in basic trends in economy,
government, and social sector. It will review relevant publications and previous reports relating to
performance and regularity audits; listen to experience of regularity auditors; listen to or read
transcripts of parliamentary debates; attend relevant conferences and seminars; hold discussions with
colleagues, stakeholders and specialists; listen to radio and television broadcasts; and read
newspapers and journals. It would be a continuous process that ensures that the Department is always
in possession of updated information about what happens in the society that may require examination
by the AGP. Examples of PA themes could be energy crisis, security management, flood management,
earth quack impact management, e-government, etc.
3.13 PAW will prepare a draft strategic plan for review of DAG (APSS) who will keep in view the vision and
priorities of the AGP while finalizing the strategic plan. The DAG (APSS) may like to discuss further
about the priorities with other DAGs/ Additional AGP. The strategic plan will also specify themes, sub-
themes, if any, and objectives and scope of each theme and sub-theme.
3.14 PAW will prepare one working paper for each theme in the draft strategic plan. The working paper will
give at least the following information:
(a) Background of the subject
(b) Some basic facts, materiality and risk areas
(c) Executive departments involved
(d) Reasons for selecting the theme
(e) Potential risks if the theme is not selected
(f) Objectives, scope and approach of AGP's audit
3.15 Each working paper would have necessary supporting documents to indicate the basis on which the
theme has been selected.
3.16 DAG (APSS) will submit the draft strategic plan for approval to the AGP. The AGP may like to consult the
Public Accounts Committees of the National Assembly and Provincial Assemblies to assess priorities of
the public representatives for performance audits. The AGP may also consult other Committees of the
Legislature(s) for determining priority areas for the strategic plan.
3.17 The AGP will approve the strategic plan which will be circulated among all concerned by the DAG
(APSS).
3.18 After receipt of the approved strategic plan, the FAOs will translate the plan for the first year into audit
assignments in their respective Annual Audit Plans for approval by the AGP.
3.19 The format of the strategic plan for the first year in a 3-year plan is at Annex-B.
3.20 The plans for years 2 and 3 would only be in skeleton form. Next year, the plan for year 2 of the approved
strategic plan will become plan for the current year and shall be elaborated in the format given at Annex-
B. At the same time, another skeleton plan will be added which will then become plan for year-3. The set
of plan for the three years as revised on the beginning of the second year will also pass through the
same approval process as stated above. In this way, the plan for year-2 of the last strategic plan will
become current plan and another skeleton plan will be added which will become plan for year-3.
21 | P a g e
21 | P a g e
feel that input from a consultant would be potentially beneficial for the annual audit planning process.
Normally, such consultancy assignments should be between one to four weeks.
3.31 As a result of various activities stated above, the FAOs will prepare Risk Register and end up in
preparing a list of possible audit assignments. The Risk Register gives risk profile of each proposed
audit assignment in a summary form. For each assignment proposed as a result of risk assessment
exercise, the Risk Register indicates the following:
• Nature of risk
• Effectiveness of internal controls
• Probability of occurrence of risk
• Impact of risk
3.32 The Risk Register presents the risk profile of all proposed assignments. But it does not rank the
assignments in terms of riskiness.
3.33 The next step is to prioritize the audit assignment in order of riskiness. For this purpose, the Manual
provides a Scoring Tool. (See Fig F, Annex C). The scoring will be done in two steps. As a first step,
each assignment in the list will get a score in light of the Scoring Tool. In the second step, this list will
be sorted in descending order of the score of risks. The sorted list will arrange the assignments in order
of riskiness. Illustration in Annex C shows application of the Scoring Tool.
Audit mandate
3.35 It is of utmost importance that the subject selected for audit falls within the audit mandate of the AGP. It
would not be possible for the AGP to approve the audit plan if it is out of the scope of his or her
mandate.
Past audits
3.36 The assignments that have been recently audited would rank lower in preference to those that have been
audited in the distant past or that have not been audited in the past.
Riskiness
3.38 The FAOs will feed result of risk assessment exercise into the annual plan. For incorporating the result
of risk assessment, the FAOs will use the list of assignments sorted in order of riskiness. (Figure F,
Annex-C).
Social impact
3.39 Considering social impact of the program or project to be audited is of paramount importance. The AGP
is keen to see that the public funds are managed with due regard for the benefit of larger number of
people. The programs that are going to have an impact on the lives of larger number of people would
stand a higher chance for selection for the annual plan of the coming year.
21 | P a g e
Economic impact
3.40Investment of public funds should be done with due prudence and care. The economic return on public
investment should justify a project or a program. As a result, the AGP will prefer the audit of those
projects and programs which are likely to produce a higher return in present value terms.
Materiality
3.41A matter is material if its disclosure is likely to influence or be of importance to the report users.
Materiality and significance are synonymous for purposes of performance auditing. In performance audit
a matter is deemed material or significant if its disclosure is likely to be of interest to, or influence the
report user even if the financial implications are insignificant. Materiality, or significance in the case of
performance audits, is one of the main criteria considered at the annual planning stage as well as later in
the reporting process. It assists in selection of audit areas and in deciding what needs to be included in
audit reports. There are three main factors which influence the materiality decisions:
• Materiality by amount - the consideration of the financial value involved in the audit area;
• Materiality by nature - a matter may be material because it involves substantial impact to the
environment;
• Materiality by context - it might be necessary to draw attention to the topic or issues under
consideration.
3.42The FAOs will keep in view all these aspects of materiality while preparing annual plans for performance
audit.
Legislative/public interest
3.43The FAOs should consider the importance of proposed audit assignment in terms of legislative and
public interest. The legislature's interest is important because it will have a direct effect on the impact of
the audit office's work. If the audit office's recommendations are opposed by the audited entities and the
audit report does not generate much interest among the legislators, it may be difficult to secure
improvements in value for money or public accountability. Similarly, the FAOs should think if the
proposed audit assignment will attract attention of the public through media or other sources.
Auditability
3.44The FAOs should only select those areas for audit about which the AGP has the necessary capacity in
terms of resources, audit skills, mandate, etc. The FAO should assess:
• The availability of relevant audit skills or possibility of contracting the required expertise
21 | P a g e
Client request
3.45The FAOs should also consider an audit assignment as potential candidate for selection if auditee
management has made a request for its performance audit. The likelihood of getting cooperation from
the management increases in such case. However, the audit management should remain alert to the
possibility of getting involved in the internal strife and professional jealousies of the client entities.
Timeliness
3.47The FAOs should consider whether or not:
• This is the right time for the AGP to investigate a particular area.
• The audited entity needs more time to implement some of its major work plans or procedures before
progress; or
Media visibility
3.49Projects and programs that have got attention of the media should be considered for performance audit
on a priority. The FAOs should keep track of the media reports relevant to their field of audit.
• Strategic plan
21 | P a g e
• Program or project under one Principal Accounting Officer (PAO) or those under more
Planning Template
3.53 The FAOs will use the Audit Plan Template issued by the AGP for preparing the Annual Plan. The
Template has space for PAs as well.
3.57 Where a FAO does not have appropriate competence, it may approach the AGP for redefining or even
deferring the audit.
3.58 The DG of FAO should formulate audit teams, nominate auditors in-charge for each audit and broad time
table or timing of each audit, leaving detailed planning for each audit to a later stage.
21 | P a g e
Quarterly Plans
3.59 The DG in each FAO would prepare Quarterly Plans for PAs and get it approved from the respective
DAGs. The Quarterly Plans will distribute the workload among four quarters of the year and also identify
the audit teams responsible for each audit assignment. The DAGs will use these Quarterly Plans for
monitoring progress of the actual implementation of the Annual Plan.
3.60 The Template for Quarterly Report is at Annex-E.
22 | P a g e
4.1 INTOSAI Auditing Standards require that all audit assignments should be planned. This applies to PAs
as well. The primary responsibility for preparing plan for an audit assignment lies with the Auditor In-
charge. As soon as decision to take up an audit assignment is taken by the DG, the Auditor Incharge will
commence preparatory work for writing an audit plan. He or she would discuss the objectives, scope
and approach with the Audit Supervisor and DG. Besides, the Auditor In-charge, with the approval of DG
organize meetings, workshops, seminars or brain storming sessions, as necessary, for clarifying the
audit subject, its objective, scope and approach and its criteria. The Auditor In-charge should also surf
Internet for getting background information about the subject of audit.
4.2 Early in the planning phase of an audit the DG should consult PAW for any past similar audits, or other
technical material available in its repository of knowledge.
4.3 Planning process for an audit assignment has following steps:
(a) Preparation of a preliminary survey report
(b) Decision to proceed or abandon audit
(c) Preparation of an audit assignment plan
(d) Approval of audit assignment plan
a) background knowledge and information needed to understand the entity to be audited, to allow an
assessment of the problem and risk, possible sources of evidence, auditability, and the materiality or
significance of the area considered for audit;
b) the audit objective, questions or hypotheses, criteria, scope and period to be covered by the audit, and
methodology (including techniques to be used for gathering evidence and conducting the audit analysis);
c) an overall activity plan which includes staffing requirements, i.e. sufficient competencies (including the
independence of engagement staff), human resources, and possible external expertise required for the audit,
an indication of the sound knowledge of the auditors in the subject matter to be auditedl3;
d) the estimated cost of the audit, the key project timeframes and milestones, and the main control
points of the audit.
30 | P a g e
Cancel
► No
Proceed to examination
phase
Proceed to examination
phase
24 | P a g e
Familiarization
4.6 The first step in developing a PSR is to understand the objectives, and operations of the organization,
and expected outputs, outcomes and impact of the project or program to be audited. For purpose of
familiarization, the auditors should study the basic documents about the audit assignment.
4.7 The auditors should aim to collect at the least the following information for proper familiarization:
• Background information of program being audited (policy, objectives, role and functions,
30 | P a g e
The accounting information of the organization is recorded correctly, timely and in accordance
with generally accepted accounting principles.
The assets of the organization are safeguarded.
The business of the organization is carried out in the most economical, efficient and
effective manner.
The management complies with the policies of the government.
4.10 An adequate and reliable internal control system is one that has a built-in warning system to prevent or
detect frauds or errors in the operations of an organization. For a fair assessment of control mechanism
the auditors are expected to undertake at least the following examination:
• The auditors should see the extent to which the objectives of the organization have been clearly
stated and that the policies adopted to achieve these objectives are based on reliable
information.
• The auditors should see that the organization has system in the place for constantly reviewing
the policies in light of changing circumstances.
• The auditors should be specifically note that the organizations delivering social services may
not have measurable targets of performance. In such cases, the management should have
systems in place to review the performance regularly, albeit subjectively. In other cases
performance could be measured quantitatively. The auditors should see in these cases whether
the management has laid down measurable targets.
> The auditors should examine the extent to which an organization questions the basis of its preparation
of estimates. It should be seen whether all the expenditure is regularly justified against
objectives to be achieved. Absence of such a mechanism allows wasteful and redundant
expenditure to perpetuate over years.
30 | P a g e
any management concerns, and project outputs and outcomes. It is so important an activity for the PSR
that rest of the audit work revolves around these issues.
Template of PSR
4.19 Template for PSR is at Annex-F.
30 | P a g e
Audit Objectives
4.23 The Auditor In-charge should re-visit the PSR, if prepared, and see if the objectives can be adopted as
defined at the time of PSR or would they require some modification. In any case, this is the time to firm
up the audit objectives finally.
4.24 If the DG decides that the performance audit assignment should focus on certain areas of compliance
audit or study certain problem areas in detail, the audit objectives should specify these matters clearly.
Audit Scope
4.25 Audit scope refers to the extent of audit coverage in terms of time period, stage of the project of program
or organization, the locations and facilities to be included in audit coverage and any aspect which will not
be covered with reasons for exclusion. Audit scope determines the responsibility of the audit team in the
assignment.
Audit Approach
4.26 Audit approach refers to the method of work to be adopted by the auditors. The auditors generally review
documents. They also interview key resource persons. Besides, in certain audits, they may visit certain
locations, conduct some surveys, collect market information directly, and approach third parties for
additional information or for verification of client's assertion.
4.27 The performance audit approach can focus on the performance measurement system adopted by the
auditee management. The audit could assess if the system is satisfactory. It is also possible that the
performance audit examines the reasonableness of performance indicators being used by the
management. The questions asked would be: Are there key performance indicators that measure
economy, efficiency and effectiveness of the program or project? Do the key performance indicators
cover all areas of operations? Does the management have a robust system of collecting and analyzing
data on performance indicators? In some cases, the management may not have a
30 | P a g e
system of performance measurement. In such cases, the audit could focus on measuring performance
directly.
4.28 The planning document tries to imagine the steps to be taken in a broad sense, leaving drafting of
detailed audit procedures to audit program. The approach is only an expression of the planned direction
of the work.
Audit Criteria
4.30 One of the primary concerns of the auditors at this stage is to determine the audit criteria for each issue
of potential significance. There are no universally accepted criteria for auditing the performance.
Paragraph 2.28 of this Manual provides guidance on how to lay down audit criteria.
4.31 Laying down audit criteria is so vital an element of audit planning that it is almost impossible to carry out
a performance audit in their absence. The auditors should discuss the criteria with management before
adopting them. Sometimes, the management would dispute the criteria adopted by the auditors. In such
situations the matter is resolved by discussion. But if the auditee management is adamant on some
particular criteria about which the auditors feel unsure, the auditors should proceed with their criteria
and mention the controversy in their audit report.
Audit Team
4.32 The Auditor In-charge should discuss with the Audit Supervisor and DG about the audit team and the
extent of time in person-days each member of the team would spend on the audit assignment.
Time Budget
4.33 The Auditor In-charge should prepare a time budget for the audit assignment. While doing so, the time of
the support staff is not included in the total time estimate.
Scheduling of Audit
4.35 The Auditor In-charge should prepare a plan for carrying out the audit on the prescribed format given in
the Audit Assignment Plan (Annex-G).
30 | P a g e
30 | P a g e
A. Letter of Notification
5.1 As soon as decision to take up a performance audit is made, the DG should notify the plan of the Office
to conduct that audit. The notification letter to the auditee management should be issued on Template for
Letter of Notification at Annex-H.
21 | P a g e
5.8 The DG should draw the attention of the auditee management to the audit criteria to be used by the
auditors and seek their agreement. In case of disagreement, efforts should be made to arrive at mutually
agreed criteria without jeopardizing the independence of the audit.
5.9 The DG should particularly request the auditee management about any matters that they would like the
audit teams to examine.
22 | P a g e
5.11The audit team should maintain a productive relationship with the auditee throughout audit. The audit
Box ii from: INTOSAI How to increase the use and impact of audit reports: A Guide for
Supreme Audit Institutions Inform the auditee of what to expect during the audit
The relationship between the SAI and the auditee can be greatly improved if the SAI sets up
communication protocols. These protocols cover the following areas:
the responsibilities of the SAI and the auditee, with guidance on key stages of the
audit process and what documents will be shared between the SAI and the auditee
at each stage;
how the SAI will let the auditee know about upcoming audits, to allow enough time
for the auditee to prepare;
what initial meetings will take place to discuss the audit work with the auditee; who
will be the key contact persons for the SAI and the auditee during the audit, and how
contact persons will be told about developments during the audit; the information
that the SAI will provide to the auditee about the audit plan, timetable for the audit,
and audit methodology, including buildings and locations to be visited.
team should seek to create an understanding of its role and function among the auditee staff. The audit
team should be able to obtain information freely and frankly and conduct discussions in an atmosphere
of mutual respect and understanding. An atmosphere of trust and mutual respect is helpful for audit and
persuades the auditee to accept recommendations of the auditors.
23 | P a g e
24 | P a g e
46 | P a g e
Chapter 6 Audit Execution
6. Audit Execution
46 | P a g e
B. Audit Program
6.3 The audit execution phase starts with preparation of audit program. Unlike financial auditing, standard
ready-to-use audit programs do not exist for performance auditing. For each performance audit
assignment a tailor-made audit program has to be written.
6.4 The Auditor In-charge is responsible for developing the audit program. The Director will review the audit
program and submit it to DG for approval. The field work will start after approval of the audit program by
the DG.
6.5 The audit program is a written plan for execution of an audit assignment. It consists of audit procedures
to be followed during the audit execution phase. The audit program is a guide for systematic fieldwork. It
is, at the same time, an effective tool of supervision for ensuring that the auditors follow appropriate
procedures and the work is completed according to the planned schedule and in a manner that achieves
audit objectives.
Audit objective(s)
6.7 There are overall objectives for each audit assignment. The auditors conceptualize those objectives
quite early in the audit assignment and most often during the preliminary survey stage. But while
developing the audit program they should specify their objective of the examination for each issue. This
very objective will, to a large extent, determine the audit procedures and their sequence to be followed
during the audit execution phase.
Audit criteria
6.8 The audit program should state clearly the audit criteria for all each issue of potential significance. This
work they had already done at the stage of Assignment Audit Plan. It will be a copy and paste action here
but is done for keeping the audit criteria in sight while implementing the audit program.
Audit procedures
6.9 The audit program specifies the audit procedures to be carried out by the auditors to substantiate or
falsify each issue of potential significance. The auditors should frame procedures to find answers to
following questions:
• What are the audit objectives?
• What are the audit criteria?
• What are the facts?
• What are the deviations from the audit criteria?
• What are the causes of the deviation?
• What are the effects of the deviation?
• What could the auditee management do to remedy the situation?
6.10While trying to find answers for such questions the auditors list down steps that they must carry out.
These steps become the audit program.
Special instructions
6.11Special instructions in the audit program relate to following matters:
46 | P a g e
Sources of Information
6.16 The audit team should start fieldwork by following the audit program for each issue and gathering
necessary evidence. The main sources of audit evidence are as follows.
37 |P a g e
Performance Audit Manual Auditor General of Pakistan
Chapter 6 Audit Execution
Auditee files
6.17Review of auditee files and documents is the starting point for the auditors to commence the fieldwork. It
includes case files, financial statements, progress reports, monitoring reports and any assessments
made by the auditee or some other consultants before arrival of the performance auditors.
6.18In exceptional cases, the auditors should photocopy important documents and those conveying
significant or potentially controversial matters and record original file identity on the photocopy.
6.19The auditors should note that in real-life the files under review may not contain all documents. There
could be other locations for relevant papers. The audit team may not be aware of those locations. The
team should exercise judgment and inquisitiveness to speculate if further information could be lying
elsewhere. At the end, the team should seek to ensure that the evidence obtained is complete enough to
answer the audit questions.
Direct observation
6.22The age-old maxim 'seeing is believing' is true in case of performance auditing as well. The foremost
technique of collecting evidence is physically visiting a place or a facility and seeing directly what is
happening. Physical verification is the time-tested technique of auditors. It should be followed in
performance auditing as well.
Interviews
6.23The auditors should interview key auditee personnel for gathering information. In large projects such
interviews are conducted at three levels: top, middle and operational. The information from the top is
usually more authoritative but broad in nature. As the level moves downward more details are available.
But before accepting, in case the information obtained during the interview is likely to be part of the
performance audit report, the auditors should forward the interview notes to the interviewee for
confirmation. If the audit team receives the confirmation no further verification may be necessary and
the auditors can decide whether and how to use the information. Quite often, in practice, the
interviewees do not respond to such audit notes. The failure to respond to this note by the auditee staff
leaves a doubt as to whether they have agreed with the note or would not disagree with it later.
Therefore, these notes are used with care. Preferably, before relying on them, they are confirmed from
other sources.
46 | P a g e
6.24 When asking for opinions on different issues, as a good practice, the auditors should not give the
questions to the interviewee in advance. The same applies if for any reason the audit team needs to
interview several people within the same organization. On the other hand, if the purpose of the interview
is to collect specific facts about the audited entity, it is advisable to provide the questions in advance to
enable the interviewee collect relevant statistics and other documentation. Whichever the case, the
Auditor In-charge should prepare the interview questions in advance in the form of an interview guide.
6.25 When seeking opinion of an interviewee on any matter, the auditor should inform the respondent
about the purpose for which the information will be used. If the interviewee has an objection to the
disclosure of his or her identity for this information, the auditors should ensure anonymity. However, in
case the auditors need to refer to this information in the audit report, they should adopt other means to
getting this information in a transparent manner without compromising their commitment to the
interviewee about maintaining the anonymity. In no case should the auditors dishonor their commitment
with the interviewee for maintaining anonymity.
6.26 The typical interview is held in the context of a meeting. Sometimes telephone interviews provide an
alternative that can save both time and costs, especially if the questions are relatively simple and
standardized. A standardized interview can be done when information is collected with a questionnaire.
Questionnaires
6.27 The auditors should prepare questionnaires for soliciting information. Preferably this work should
be done before commencing the fieldwork. The auditors should keep following points in mind while
preparing the questionnaires:
6.28 A good questionnaire is not suggestive; it does not pre-empt the respondent from giving a genuine
reply, nor does it limit the scope of reply unnecessarily. The questionnaires requiring the respondent to
work hard are likely to get a poor response.
6.29 The format and design of a questionnaire depends on the purpose for which it is required. The
questionnaire could be for seeking documented information, for interviewing a person or conducting a
survey. In each case the format of the question would be different and according to the situation.
Use of consultants
6.31 The performance auditors should consider seeking help of consultants in certain areas, especially,
those that require technical knowledge. In such cases they should check the advice of the consultants
for its inherent validity, for sources of its data and for its practicality before they decide to adopt it in the
audit report.
46 | P a g e
Departmental manuals
6.32Departmental manuals of the auditee often contain valuable information. The manuals contain rules,
regulations and procedures. Some of the procedures emphasize economy and efficiency in operations.
The auditors should adopt them as their criteria. Any deviation from these procedures becomes basis for
audit findings.
Surveys
6.34Sometimes the auditors are interested in getting information that is not available in the auditee files. For
example, they may like to formulate an opinion about the quality of service provided by the auditee to a
certain segment of population. This can be ascertained from the concerned population only. This type of
information can be collected only through surveys. Surveys are expensive techniques. They should be
considered only when it is absolutely essential to undertake them. The surveys could be through mail
questionnaire, in-person interviews, telephonic interviews, e-mails, or circulars through departmental
channels. In any case, the designing of survey questionnaire requires specialized expertise to avoid bias
and to make the survey results amenable to analysis. Since surveys cannot be administered to the entire
population, they usually involve decision by the DG about the method of selection of sample and the size
of sample. The auditors may also require help of statisticians in this work.
6.35Internet search will inform the auditors about organization which can conduct surveys on behalf of the
auditors. These organizations charge a small fee for conducting the survey. If the auditors decide to
outsource the survey, they will require the permission of the DG . Besides, the organization conducting
the survey requires the questions to be in a certain format so that the computer can analyze the survey
responses. Also, such surveys are possible only when the respondents are literate in computers and
have an e-mail address. Surveys from general public can also be outsourced. However, the cost for such
surveys is often prohibitive for the audit office. The DG should consider all options before launching a
survey.
Case studies
6.36Case studies provide the opportunity to thoroughly explore a small number of cases in order to have an
in-depth knowledge of organizations, systems, processes and activities relevant for the audit problem. It
enables the auditors to concentrate on details and on understanding the organizational processes. The
cases can be examples of a situation that may be prevalent throughout a population. Generalizing from
case studies is a question of good arguments, not absolute proof or statistical certainties. It is essential
for the argumentation to use a clear and specified logic in the selection of cases, a logic that supports
the intended use of the information. It is wise to choose a case (or a few cases) that are the most or least
likely to have certain characteristics. Another option is to choose one or a few cases that are considered
to be representative of the whole population. Depending on the purpose, there are several possible ways
to select cases, e.g. the best cases, the worst cases, extreme cases, or typical cases for the whole
46 | P a g e
country or for a group of possible cases. The method of collecting information for cases remain the
same: review of documents, interviews, questionnaires, surveys, etc.
Literature searches
6.37 The auditors should surf Internet extensively for collecting relevant information and understanding the
best practices in the area of their audit. Besides Internet, they should also search libraries for clarifying
their concepts and ideas about the subject of audit.
Market research
6.38 It involves collection of data about environment in which an organization or project is operating. It also
means gathering data on similar projects or programs. The cost for this type of work is often quite high.
It also requires knowledge of such disciplines as economics, sociology, psychology, statistics and EDP
besides training in auditing and accounting. Sometimes the auditors hire consulting firms to do this
specialized work for them.
Databases
6.39 Many organizations have compiled databases, both manual and computerized. The Statistics Division
and Agriculture Census Organizations in the Federal Government and Board of Economic Enquiry in the
Punjab Government are examples of such organizations. These organizations maintain detailed
information on different aspects of the economy. There may be commercial databases that are run, for
example, by banks, (like Electronic Credit Information Bureau) which may be used to collect data. These
databases may enable the auditors use data that has already been collected and compiled. This will save
time and money. It might also be possible to order special computer compilations as required for the
audit.
6.40 The above is not an exhaustive list of the sources of evidence for performance auditing. Evidence
collection is an organic activity. The creativity of auditors may suggest certain unique sources of
information in some cases.
D. Categories of Evidence
6.41 The audit evidence usually falls into four categories:
Physical evidence obtained by direct observation. Examples are physical verification of cash,
site visits of projects, verification of inventory etc.
Testimonial evidence obtained from others through oral or written statements. Sometimes
auditors need this type of evidence from users of a service or target group of beneficiaries to
assess effectiveness of a program or a project.
Documentary evidence consists of - files, reports, manuals and instructions.
Analytical evidence built up by analysing the information obtained from other sources. Most
common example in performance auditing is the benefit-cost analysis.
E. Quality of Evidence
6.42 The evidence should be: (a) valid (b) relevant (c) sufficient (d) timely (e) economical and (f) objective.
46 | P a g e
Validity
6.43 Valid evidence means that there should be no doubt about accuracy of the evidence. Whatever
interpretation the auditors may like to place on it, the facts should be beyond any doubt. It applies not
only to facts collected from the auditee's records but also any analysis done by the auditors themselves.
6.44 The auditors should adopt a critical approach and professional skepticism toward the data presented by
the auditee. They should exercise independent judgment about relevance and validity of the data
obtained during the audit. They should try to see things from their perspectives and maintain an
objective distance from the data put forward by the auditee. At the same time, they must consider views
and arguments of the auditee and other stakeholders.
6.45 It is difficult to make a general statement about the criteria for valid evidence. However, there are some
general guidelines that can help the auditors in assuring themselves about validity of the evidence:
Direct evidence obtained by physical inspection or analysis of valid facts is more reliable than
indirect evidence.
Strong internal controls give a greater assurance on validity of outputs of the organisation than
weak controls.
Documentary evidence including photographs is more reliable than oral evidence.
Original documents are more reliable than photocopies.
Information obtained through independent external sources could be more reliable in a given
situation than internal information.
Information provided by the management is acceptable if it is written and signed by an appropriate
authority.
Evidence on one issue from more than one source gives added assurance.
Relevance
6.46 Relevant evidence means that the evidence should be related directly to the point at issue. It should not
be indirect or remote evidence. For example, in case of an educational program, the number of students
enrolled, number of students qualified and the number of repeaters would provide direct and relevant
evidence on quality of education. Examples of irrelevant evidence could be as follows. Trying to infer
about the performance of the school from the number of teachers or expenditure on the support staff or
number of books in the school library or number of computers in the lab. Another example of irrelevant
evidence could be accepting future plans of a school as basis for opinion. The future plans may be
highly interesting but hardly relevant to performance audit of the past years.
Sufficiency
6.47 Sufficient evidence means that the evidence should be persuasive. It should enable the auditors express
opinion without fear of contradiction. In other words, the evidence should be neither more nor less than
what the occasion demands. It should be just sufficient to prove the point. For example, in performance
audit of a road transport organization, comparison of the wear and tear of tyres at one transport depot
with another depots in the same region would be an example of sufficient evidence. In this case,
however, making comparisons with transport organizations of other countries would be going too far.
Such an attempt would be an example of more than sufficient evidence and would add to the cost of
audit with unpersuasive results.
6.48 Some of the guidelines for judging sufficiency of evidence are given below:
46 | P a g e
The auditors should rely on evidence that is persuasive rather than convincing. The auditors are
seldom convinced beyond all doubt with respect to all aspects of the data being examined.
There should be a rational relationship between the cost and the usefulness of evidence,
although difficulty and expense of gathering evidence should not be a valid reason for omitting
it.
In absence of reasonable assurance either the auditors should perform more tests or modify
their opinion.
Timeliness
6.49 Timeliness of evidence refers to need for availability of evidence in the time-frame of audit. The
evidence that delays the audit opinion beyond reporting deadline, however valid, relevant or sufficient,
would be unacceptable. There can be a trade off between the timeliness of evidence and its validity,
relevance and sufficiency. For example, in a primary school project, involving establishment of a few
thousand primary schools all over the country, an attempt to be sufficient and relevant in evidence could
delay the results of audit beyond acceptable limits. While planning such audits the auditors must foresee
what would be the acceptable magnitude of evidence to be collected to enable them to produce a timely
and persuasive report. They may have to review their resource position. A situation that does not allow
collection of a bare minimum of evidence for giving an opinion may lead to auditors' dilemma: should
they or should not do this audit? They may decide not to undertake such audits in the first instance.
Economy
6.50 Economical evidence means that the auditors should always weigh the cost of gathering evidence
and the benefit of increasing the credibility of their findings by certain degrees. They have to strike a
balance between the two. For example, in the above case, the auditors may be able to collect evidence
on the selected sample of schools in all provinces by increasing the number of auditors. But before
doing so they should assess whether it would increase the creditability of their findings significantly.
These are questions for auditors' professional judgement. No hard and fast rules can be laid down in
this regard.
Objectivity
6.51 Objective evidence means that the evidence should be free from bias. It should not be intended to
malign or favour any particular person or entity. Objectivity in audit evidence makes it distinct from
certain other types of evidence, like, the evidence given in a court of law on behalf of the prosecutor and
defendants.
46 | P a g e
46 | P a g e
6.59 The DG should present main audit findings and audit recommendations to the meeting and seek auditee
management's responses on each finding and recommendation.
6.60 The DG should also inform the auditee management that by such and such date the management can
send any further information or replies to the audit observations. Besides, the DG should inform the
auditee about further procedure for finalization of the report and request their cooperation at all stages.
6.61 The auditee will often want to know the final context in which the findings will be reported and the
conclusions that will be drawn. These can be discussed in the Exit Conference, but the DG should warn
the auditee that any conclusions are preliminary until all of the evidence has been reviewed by senior
officials of the FAO.
6.62 The DG and the audit team should carefully listen to the point of view of the auditee and assess its
validity before accepting it. If necessary the auditors can request for more documentation or evidence
for substantiating the auditee's point of view.
6.64 After approval of the DG, the Auditor In-charge will send the note of the proceedings of the Exit
Conference to the auditee management as well.
6.65 Since the auditee management comments on findings have to be reflected in the draft report, it is
important for the audit team to identify briefly as follows:
• Where there are differences in perception regarding audit findings between the management
and the audit team: The management's view on the issue should be reflected in the report along
with the auditors' explanation for not accepting that view.
• Where there is important disagreement by the management on the audit findings: The audit
team should reflect this in the report along with the reasoning given by the management for not
agreeing on the finding/s.
6.66 The audit team, under given circumstances might consider the possibility of offering the auditee another
chance to provide additional information that supports their position.
6.67 If the audit team allows additional time to the auditee it should require the auditee to meet the agreed
deadline. If the auditee offers further information the auditors will evaluate and analyze it. If it is relevant,
competent and reliable the Auditor In-charge may review the earlier audit conclusion. If the additional
information offered by the auditee does not meet the necessary requirements, the Auditor In-charge should
hold to the early conclusions.
6.68 Where agreement can't be reached, the auditor should obtain the auditee view in writing and reflect it in the
report.
46 | P a g e
6.69 The audit team should meet soon after the Exit Conference to review their work in light of the auditee
responses. Some of the audit findings may require revisions, others may have to be cancelled or withdrawn
but some may have to be deepened. The team should plan these actions and complete them quickly after the
Exit Conference but before packing up and declaring the field work closed.
46 | P a g e
7.1 INTOSAI Auditing Standards state that auditors should adequately document the audit evidence in
working papers, including the basis and extent of the planning, the work performed and the findings of
the audit.5
7.2 The audit working papers are files established by the auditors during planning, and executing of an
audit. The auditors may also decide to file various versions of the audit report in the working paper files,
if they do not maintain separate files for the audit report. The main purpose for establishing these files is
to gather and save the information of continuing importance during and after completion of the audit.
Besides, properly kept working paper files enable the audit supervisors satisfy themselves about the
work done and the audit checks applied by the audit team. The audit working papers permit the audit
management shuffle the auditors during the course of an audit as the work done by the outgoing
auditors is well documented.
7.3 The audit working papers provide a link between the work done by the auditors and the performance
audit report. They should be in sufficient detail and kept in an organized manner so that retrieval and
reference is easy.
7.4 Typically, performance audit working papers contain following information:
• Audit planning information such as all primary documents and studies in connection with familiarization
and preliminary survey report
• An assessment of internal controls of the auditee
• Audit criteria and audit procedures for each issue of potential significance
Preliminary survey report and audit assignment plan
• Details of the audit work carried out by each member of the audit team
• Evidence that the work of the audit team has been properly reviewed
• A summary of audit findings
• Various versions of draft and final audit reports
Permanent Files
7.6 The DG will assign audit entities or their units to officers who are eligible to become Auditors Incharge.
The Auditor In-charge will be the custodian of Permanent Files of entities or units assigned to him or her.
7.7 Permanent Files are permanent in nature and used in current and future audit assignments relating to a
particular organization. Typically, they contain the following information:
5INTOSAI, Code of Ethics and Auditing Standaf&p. 57 and also to ISSAI300 Field Standards in Government
Auditing, paragraph 5.5.
47 | P a g e
Execution section
• Audit program
• Working paper for the Entry Conference
• Minutes of the Entry Conference
• Correspondence with the auditee for seeking interviews, obtaining information, confirmations,
clarification, etc
• Sample size and selected samples
• Interview notes
• Field plan to execute the audit program and details of the actual work performed
• Summary of audit findings
• Working paper for the Exit Conference
• Minutes of the Exit Conference
• Actions taken after the Exit Conference
Reporting section
• Draft performance audit report: all successive versions
• Approval of the draft audit report by DG
• Auditee responses
• Further comments on the auditee responses
• Various versions of the final performance audit report
• Approval of the final report by the DG
• Matters of interest for further audits
47 | P a g e
7.18 The abbreviation for all documents will be done according to the title or subject of the document.
7.20 For Audit Execution, audit program should be the reference point and the page numbering will be as
follows:
47 | P a g e
7.21 For reporting section the pagination will be on the following pattern:
CF/DR/v.l/ 1, 2, 3, ... for Draft report version 1. Subsequent versions will have v.2, and v.3
after the second slash.
7.22 For final report the page numbering will be as follows:
CF/FR/v.l/ 1.2. 3
7.23 For auditee responses the page numbering will be as follows:
CF/Auditee Rep/1. 2.3....
7.24 All working paper files will have an index in the beginning.
47 | P a g e
Divide the working paper folder for background information in different sections as follows:
• Information pertaining to the sector or broad area of study
• Information to international perspectives
• Information relating to best practices on the subject
• Information relating to the audit entity
• Information relating the program or project to be audited
• Information pertaining to strategic plans, operational plans, performance indicators, progress reports
and monitoring reports relating to the assignment of audit
For documents
• What is the source of the document?
• What is the date of the document?
• What is the status of the document? (i.e. current, requires updating, ownership of the document, etc)
• What is the objective of the document and what are its main contents? Mention the main document if
any abridgement has been done or extracts have been taken from a larger document.
• Mention the geographical area and the period to which the information is applicable.
• Where and from whom further information is available?
For interviews
• The date, time and venue of interview
• Who were present in the interview?
• What is the name and designation of the focal person of the interview?
• Is there any documents or information that the interviewee promised to send later on?
• How to contact the interviewee next time, in particular if he or she is located a t a different station?
62 | P a g e
8.1 The auditors collect a lot of data during the fieldwork. For drawing audit conclusions, they need to
analyze the data. Before starting analysis of the data, the auditors should revisit the audit objectives and
segment of the audit program to which the data pertains. This would help them decide the analytical
technique required.
8.2 Generally, the financial auditing requires application of simple techniques such as ratio analysis and
some elementary statistical methods. However, in performance auditing some more sophisticated
techniques are used for arriving at credible and persuasive conclusions. The auditors can us a number of
data analysis techniques in performance auditing. The more commonly used techniques are described in
this chapter. But the discussion is only indicative. In practice, the auditors will have to decide whether
these techniques are sufficient for achieving the audit objectives or they would require still more
sophisticated techniques. In the latter case, they may require assistance of a statistician. However, the
DG should take the decision to seek the help of a statistician quite early during the planning stage as it
would also influence the parameters and mechanics of the data collected. The auditors would have to
collect data according to the design prepared by the statistician.
A. Benefit-cost Analysis
8.3 Detailed guidance on concepts and techniques of benefit-cost analysis and its application to various
sectors such as construction, education, health, road transports, railway transport, water supply project
and telecommunication projects, etc is available in the Performance Audit Guidelines (198493) 25
volumes published by the AGP. The following discussion is only for providing a quick link to the
techniques.
In the public sector and not-for-profit contexts, the time value of money recognizes that society
generally prefers to receive services now rather than later, so as to defer costs to future
generations. This preference, commonly referred to as the Social Time Preference, is the value
society attaches to present as opposed to future consumption, and some governments
recommend using it as the standard real discount rate. This allows discounting of future benefits
and costs, based on comparing utility across different points in time or different generations.
6 International Federation of Accountants. 2007. Project Appraisal Using Discounted Cash F/ow.New York
62 | P a g e
8.6 It means that the costs incurred or benefits received earlier in time have a higher social value as
compared to the value of these variables later in time. In case of financial analysis, only financial costs
and benefits are considered and in case of economic analysis, economic costs and benefits are also
included in the analysis. The reason is that in some public sector projects, it is difficult to determine the
financial costs and benefits or at least, the projects cannot be justified in financial terms. For example, in
a water supply scheme, it may not be possible to recover all costs of the scheme from the public on
humanitarian grounds. The project will not be justified in financial terms, as it will not earn a profit if the
rates of water to be recovered from the population are subsidized. In such cases, the economic value of
benefits is estimated and taken into consideration. Same is true for education and public health programs
and projects.
Discounting
8.7 For giving effect to the concept of time value of money, future costs and benefits for life cycle of the
project are taken into account. These values are then discounted at a certain rate of interest and their
present values are determined. In Pakistan the Planning Commission uses a rate of 10 percent for
discounting purposes. For sake of convenience and for purpose of compatibility with the analytical work
done at the time of project planning, the Department also uses 10 percent rate for discounting the data on
projects and programs. However, it is not mandatory. The AGP can decide to use some other rate. In that
event, the AGP will notify it.
8.8 Discounting is reverse of compounding. It means finding answer to the following question: \Nhat will be
the present value of money spent or received in a certain point of time in future? This is determined by
discounting the future series of costs and benefits to the present. It is determined by the following
formula:
Dn = ______ 1 _________ ,
(l+rf
where
Dn is the discounted value of the amount n, r is the rate of interest and t is the time.
8.9 For example, if we have to determine the present value of Rs 1000 received in year 5, and the rate of
interest is 10%, the discounted value would be [1/ [lOOOx (1.10) 5 ]= Rs 621' It means the present value of
Rs 1000 received in year 5 would be Rs 621 if the rate of interest were 10 percent. In practice, the auditors
can use Excel Sheet and apply the following formula for working out the discounted value:
8.10 For example, if the rate of discount is 10 percent, the amount to be discounted is Rs 7000, the
discounted value for the amount for the first 5 years would be as follows:
62 | P a g e
A single value representing the difference between the sum of the projected discounted cash
inflows and outflows attributable to a capital investment or other project, using a discount rate
that properly reflects the relevant risks of those cash flows.
8.12 A positive NPV means, the option under analysis would generate a positive return, assuming the rate of
discount is appropriate. When we determine the NPV for all investment options, it becomes possible to
rank them in terms of their net worth and determine which one would be more beneficial, in financial or
economic terms.
"Internal Rate of Return (IRR): The average annual percentage return expected for a project,
where the sum of the discounted cash inflows over the life of the project is equal to the sum of
the discounted cash outflows. Therefore, the IRR represents the discount rate that results in a
zero NPV of cash flows."
8.14 It is arrived at by hit and trial, discounting the costs and benefits at different rates of interest, until we
arrive at a zero NPV. Calculating IRR manually is quite cumbersome. Flowever, by using Excel program
on computer, it is now easy to determine IRR. It may mean, in case of financial analysis, for example, the
resources to be used for a project should not be borrowed at a rate higher than the FIRR, as it would then
produce a negative NPV and the project would not be financially justifiable. But using IRR as a measure
to choose a project is not considered a good option as
7 Ibid. Pp. 7.
8 Ibid. Pp.8
62 | P a g e
sometimes the IRR may lead to ranking of options differently than NPV, which is a more reliable measure
of analysis.
62 | P a g e
illustrations are simplified cases and show how NPV and IRR are calculated by using actual data as
compared to the planned data of the PCI. In actual practice, the auditors will come across various
complications in determining the capital cost, operational cost and quantification of benefits. For
handling these complex situations, the auditors should refer to Performance Audit Guidelines Vol. 1
(1984) published by the Department of the AGP.
B. Sensitivity Testing
8.20 While planning a project a number of factors are unknown and the risk of changes that may affect the
feasibility of the project remains high. One of the methods for facing such challenges is to estimate the
effect of possible changes in various assumptions of the project and see how each change will affect the
profitability or feasibility of the project. For example, if the estimate time for construction is 2 years, it is a
valid question at the planning stage to ask: What will happen to the NPV and IRR if the construction takes
3 years? Similarly, it is an important question to ask: Flow will a certain percentage increase in the
estimated capital or maintenance cost affect the overall profitability of the project? Such questions can
be answered by using sensitivity analysis. The technique aims at determining the effect of changes in
cost and benefit variables (in terms of cost and time) to NPV of the project. The technique is applied as
follows:
8.21 Taking the base-line data for appraisal of the project as in PC 1, financial or economic analysis is carried
out. It gives figures of estimated NPV and IRR. As a second step, NPV and IRR are calculated by
assuming changes in different variables, one at a time, keeping the other variables as constant. For
example, the questions often posed are as below:
(a) What will be the NPV of the project if the capital cost exceeds the estimated cost by 10
percent?
(b) What will be the NPV if the project takes a year longer than estimated for completion?
(c) What will be the NPV if the project output is reduced or increased by a certain percentage?
8.22 In each case, the NPV is worked out by changing the data for one assumption at a time, keeping rest of
the data as constant. The result, in terms of NPV and IRR, is tabulated in ascending or descending order
indicating the variable, which would affect the project most.
8.23 The sensitivity analysis is mostly used at the time of project planning. But it can also be used at the time
of performance audit, taking actual figures for whatever period they are available and extrapolating them
for the rest of the project's life on the same trend. In this way, it can be estimated what factors could
affect the performance of the project and to what extent in the future. The auditors can make
recommendations for appropriate action in case they foresee significant changes in the performance of
the project in the future. For example, in a power distribution project, using the actual data for five years
for a project with an expected life of 25 years, the sensitivity analysis might indicate that the NPV of the
project is most sensitive to a 20 percent increase in the electricity price. It might indicate that increase in
the price of electricity should remain below 20 percent for some time to come. The auditors can phrase
appropriate recommendation in their audit report on basis of sensitivity analysis.
C. Output Budgeting
8.24 In social sector projects determination of benefits is often a problematic issue. For example, it is very
difficult to determine in quantified terms the benefits of educating a student or treating a patient in a
hospital or supplying a gallon of water or cleaning a certain area of the street. In such
62 | P a g e
projects, the emphasis is in delivering services. The objective of performance audit in such projects is to
see if the cost of a unit of service or unit of output was the same as planned. For this purpose the
technique of output budgeting is used.
8.25 Output budgeting method uses the concept of time value of money and techniques of discounted cash
flows. The auditors take the output budgeting analysis done at the time of project appraisal and adopt it
as a benchmark. Using actual data for the period of operation of the project and supplementing it with the
estimated data for the residual life of the project, the auditors carry out their own output budgeting
analysis and determine the variance in the unit cost as compared to the planned unit cost on which the
project was appraised and justified.
8.26 The auditors discount the costs and the outputs at various points in time at a certain rate of interest. The
rate of interest is usually the same on which the project is justified by the project authorities at the time
of appraisal. The discounted total cost is divided by discounted total output (physical units). The quotient
gives the unit cost.
Illustration 8.3 at Annex-L shows how to use the technique in performance auditing.
Test a relationship
8.28 A program under audit may have assumed a relationship between two variables. For example, in a public
distribution system, entitlement for income support (Y) is linked to income level of the beneficiary (X).
People having an income level lower than a certain cut-off margin are eligible to receive the benefit. A
definite relationship between Y and X has been assumed in the design of the program. Performance
auditors may like to test whether the program management is adhering to the assumption while
administering the income support. They collect actual data on both variable: income level (X) and income
support (Y) and calculate correlation between the two. A high coefficient of correlation (more than 50%)
indicates that the assumption of program is valid and operational. A low coefficient (less than 50%)
indicates that the assumption of the program is not being adhered by the management while
administrating the assistance to the beneficiaries.
9 The auditors can access various statistical formulas in the Excel menu by clicking on the icon ’ and scrolling down to
statistical and clicking at 'Correlation?.
62 | P a g e
Make projections
8.32 Regression analysis provides a relationship between variables. Once the relationship has been
determined on basis of limited data collected during audit, it can be used to project the relationship on a
wider scale. It can also be used to make projections for the future based on an observed relationship
held in the past.
8.33 Illustration 8.4 at Annex-L to the Manual shows the method of calculating coefficient of correlation.
E. Ratio Analysis
8.34 Ratio analysis is one of the most commonly used methods of data analysis. It involves comparison of
two or more variables of data over a base value. The base value can be a time period or any other value.
For example, what is the ratio of staff time with number of complaints in providing a service? Or, what is
ratio of complaints in the current year as compared to the last year? The ratio analysis, though simple in
concept and use, can cause problems in practice. For example, the auditors can make gross errors in
using ratio analysis if they do not see the analysis in its proper context. If, for example, the data being
compared is insignificant with reference to the total population, the result may convey a wrong message.
For example, if in a total population of 7500 payments, only 10 payments were made by cheque and five
of them had errors, we cannot say that 50 percent of the cheques were incorrect. Though factually true, it
conveys a wrong message. Similarly, ratio analysis where the denominator is zero would convey a wrong
message. For example, if error in cheque writing in a base period was zero and it rises to 5 in the next
month, the ratio would be infinity, which is wrong.
Mean
8.36 Mean or arithmetic mean refers to simple average of values. For example, if a department has a fleet of 20
cars and the total consumption of fuel for one month is 5000 liters. The mean consumption per car will be
250 liters. The mean value may not be representative of the fuel used for all makes and models of the
cars. There could be cars which are using more than 500 liters and others less than 150 liters. The
average figure hides these differences. For the data containing one or two extremely large or very small
values the mean will not be a representative figure. The performance auditors should keep this fact in
mind while using the mean value.
62 | P a g e
Median
8.37 It is the mid-point value in a population. In the above example, the median figure for fuel consumption
could be 205 liters, which means that half of the cars are using 205 liters or more and the other half less
than 205 liters. For finding out median value, the cars and the fuel consumed by each car are listed in
ascending or descending order. The mid-point value in the list is the median value.
Mode
Mode is the value of the observation that appears most frequently. For example, if in the fleet of car
mentioned above, 13 cars consume 220 liters per month, the mode value will be 220 liters. Mode is not
affected by extremes of values and can be used, like median, as a measure of central tendency.
Average deviation
8.38 It is arithmetic means of the absolute values of the deviations from the arithmetic mean. For example, in
the above example, the mean consumption of fuel is 250 liters. Flowever, consumption by each car
differs from this number. If we find out the difference between the consumption of fuel of each car and
the mean value and then take an average of the deviations from the mean, we arrive at the average
deviation. While doing so we ignore the positive or negative signs of the difference. The average
deviation makes up the deficiency of the arithmetic mean as it takes into account the value of each unit in
the population and compares it with the average.
8.40 The calculation of variance and standard deviation is illustrated in the following table. For convenience of
performance auditors, the technical symbols have not been shown so that the concept becomes easy to
understand. A formal presentation of these concepts can be seen from any standard text on statistics for
undergraduate student.
8.41 Taking the above example further we find in case of fuel consumption of 20 cars, the mean value is 250
liters. The aggregate of deviations of consumption of fuel, variance and standard deviation are as
follows:
Table 3: Example of Variance and Standard Deviation
Deviation from Dev. From mean
Cars Fuel mean without +/-sign Dev. From mean squared
consumed
1 290 -40 40 1600
2 235 15 15 225
3 300 -50 50 2500
4 295 -45 45 2025
5 215 35 35 1225
6 290 -40 40 1600
7 325 -75 75 5625
8 190 60 60 3600
62 | P a g e
10 180 70 70 4900
11 225 25 25 625
12 270 -20 20 400
13 190 60 60 3600
14 270 -20 20 400
15 230 20 20 400
16 260 -10 10 100
17 240 10 10 100
18 220 30 30 900
19 230 20 20 400
20 245 5 5 25
Total 5000 0 700 32750
Mean 250
Average deviation 35
Varianc 1637.5
e
Standard deviation 40.5
Mean = 5000/20 =250 liters
1637.5
62 | P a g e
cost due to inflation. For example, suppose the planned cost data pertained to year 2007. The execution
started in year 2009. The auditors should apply the rate of inflation for years 2008 and 2009 to respective
costs incurred during these years and then deduct the 2007 data in the project plan from the aggregate of
2008 and 2009. The difference would be increase in cost due to inflation, assuming other factors are
constant.
8.45 For imported goods and material, the auditors should compare the estimated costs in the project plan
and invoices of the foreign exporters to compare any increase in the prices of imported goods, materials
and services as compared to the planned costs.
62 | P a g e
cost due to inflation. For example, suppose the planned cost data pertained to year 2007. The execution
started in year 2009. The auditors should apply the rate of inflation for years 2008 and 2009 to respective
costs incurred during these years and then deduct the 2007 data in the project plan from the aggregate of
2008 and 2009. The difference would be increase in cost due to inflation, assuming other factors are
constant.
8.45 For imported goods and material, the auditors should compare the estimated costs in the project plan
and invoices of the foreign exporters to compare any increase in the prices of imported goods, materials
and services as compared to the planned costs.
62 | P a g e
months to approve the project. However, the Planning Division can take inordinately longer time. Yet we
are not quite sure what should be the reasonable benchmark for approval from the Planning Division. In
most of the cases such issues will remain contentious and it would be difficult to arrive at a benchmark
that can be used to measure delay for each activity. Therefore, for each segment of work in the project
management, the auditors would require a careful analysis and discuss with the management what could
be reasonable and also exercise their own judgment about the same question. Only after such a careful
analysis, they may be able to conclude whether there was any delay in a particular activity and if that was
so whether that was beyond the control of the management.
8.52 The auditors should carefully assess if the management lost any time due to lack of sense of urgency.
There could be delays just because the management did not have proper plans in place or did not have a
mechanism to guide them for certain activities which could be started simultaneous and whether the
management waited for completion of certain activities when there was no need to that. These factors
require judgment. The management may not agree with the auditors' judgment and also may challenge
the technical knowledge of the auditors about certain activities. In such cases, the auditors may require
consultancy services of technical experts who could assess reasonableness of the time taken by the
management.
63 | P a g e
64 | P a g e
64 | P a g e
64 | P a g e
64 | P a g e
64 | P a g e
Accounts Committee in respect of a performance audit report follows similar steps as are undertaken for
financial audit and compliance audit reports. There are no special procedures to be followed while
preparing to present a performance audit report before the Public Accounts Committee.
64 | P a g e
Conditions Found
10.4 While following the audit program, the auditors document conditions found on the ground. If the
conditions on the ground meet the criteria, the auditors have a positive conclusion. They should mention
it in the audit report by acknowledging achievements of the auditee management.
10.5 The audit team should identify any gaps between the audit criteria and the conditions on the ground. The
gaps indicate qualified or negative conclusions which constitute potential material for the performance
audit report. However, the audit team must validate their findings for accuracy of the facts. In reaching a
decision on the observation, the auditors should also look at interrelated facts and other relevant
evidence to have confidence on their conclusions.
Analysis of Gaps
10.6 Once the facts are confirmed to be valid, the auditors should commence with analysis of the gaps
between the audit criteria and the conditions found. The analysis requires that the auditors probe into
causes for the gaps. There could be reasons which are beyond control of the auditee management. In
that event, the auditors must recognize this fact and mention it in their report. Similarly, if the gaps exist
because some of the internal controls are weak or missing, the auditors
74 | P a g e
711P a g e
analysis should lead the auditors to identify (a) controllable causes; and (b) uncontrollable causes. The
former category leads the auditors to suggest actions that can help improve performance or to hold persons
responsible for poor performance. The latter category will provide material for the AGP's report to the
parliament for long-term and strategic action plans.
So What?
10.7 The auditors often come across situations where they point out gaps between criteria and conditions and
also show that the management could do better. However, the auditee management may disagree with
the auditors. They might ask: if we have not met the audit criteria, so what? What has been the impact of
that on our operations? The onus to answer this question is on the auditors and they should be well
prepared for that. They must be able to show that the gap between criteria and conditions has significant
impact on the performance of the organization.
10.8 The auditors should try to provide evidence from operations of the auditee and examples of cases noted
during the field work and show how performance of the audited organization has been lower than
expected and how there was room for improvement. While doing that, the auditors should attempt to
quantify their conclusions as far as possible. In some cases extracts from auditee files, written replies to
audit queries and interview replies could be appropriate bases to show impact of not meeting the audit
criteria. Examples of the impact could be higher cost in procurement, longer than expected time in
completing certain tasks, poor quality of service, improper targeting of service delivery, weaker controls
creating opportunities for corruption and fraud, dissatisfaction of citizens expressed through media and
other means, bad governance and misuse of discretion, etc. The auditors should try to determine who is
affected by the issue (for example, other units in the organization, central agencies, third parties, etc).
10.9 The auditors should determine auditee management's awareness of the issue. If the management is
aware of the issue and the corrective action is under way, the issue may have less significance for
reporting purposes. Certainly it will change how the matter is reported.
10.10 The auditors should have confidence about their analysis on the basis of evidence they have
gathered and also from discussions with the auditee staff during the field work. The Director during
review of the field work and the DG during mock-run for Quality Assurance Review should challenge the
audit team about audit findings, audit analysis and impact of audit recommendations. The objective
should be to be on sure be to get confidence about audit findings and recommendations.
74 | P a g e
10.12 The litmus test of an appropriate recommendation is its acceptance by the auditee
expensive, pre-mature, unfair or unsuitable for any reason, it would never implement it. The
of the people at large. If the auditee management finds a recommendation unsuitable or unacceptable,
the FAO should review the recommendation at the highest level and if necessary at the AGP level. It is
only when the AGP considers that the recommendation must be made despite auditee resistance, that
the FAO should include it in the draft performance audit report. In all other cases of auditee resistance,
the FAO should either modify the recommendation or withdraw it.
10.13 An appropriate audit recommendation has following characteristics:
(a) The recommendation should flow logically and directly from the audit findings.
(b) The recommendation should be practical. Preferably, it should not require additional resources.
The cost of implementing the recommendation should not outweigh the benefits expected from it.
(c) The recommendation should not deal with actions that fall outside the domain of the auditee
management such as political or legislative action. However, in case the FAO considers that a
change in law is also necessary, the matter must be discussed at the level of AGP before
including it in the performance audit report.
(d) The recommendation should propose some action by the management which can be verified
once completed. A good idea not supported by expected action will not make a good audit
recommendation.
(e) The recommendation should state what should be changed and avoid telling how this should be
done. The exact method of bringing the change is domain of the auditee management and the
auditors should avoid getting into that.
(f) The recommendation should identify the person, entity or the level which should implement it.
The public sector organizations generally have a large number of persons and several
organizational levels. Until it is clearly mentioned who should take action, the recommendation
remains dormant. Everyone keeps waiting for someone else to take action. When the audit report
clearly mentions that such and such person or entity should take action, the accountability
requirements are also well-defined and it becomes possible to find out who has or has not taken
action on the recommendation. It further means the audit team should discuss the
recommendation with the prospective auditee staff that would be required to implement it. This
would inform the auditors any hidden resistance at the implementation level quite early and they
can fine-tune the language and content of the recommendation appropriately. It would increase
the rate of acceptability of audit recommendations.
(g) The recommendation should be formulated in a stand-alone style so that it is possible to
understand it even in absence of detailed audit report. It means the wording of the
recommendation should be such that it does not require reference to any specific part of the
audit report.
(h) The recommendation should, as far as possible, give a time-frame during which it should be
implemented. Open ended recommendations (for future only) do not cut much ice. The auditee
organizations find such recommendations easy to respond by saying: "Noted for compliance."
Quite often, such a response is without much substance. The auditors should
74 | P a g e
discuss the question of the time-frame with the auditee management during the field work and in
Exit Conference and embed it in the recommendation. It would be possible, later on, to monitor
implementation of the recommendation.
(i) The recommendation should be persuasive and show the advantage clearly if it is implemented.
the audit evidence from the audit observation. It should also be possible to trace the audit observation
from working papers and audit program.
10.17 The auditors should use the Template for Audit Observation for documenting the audit observations
(Annex-Q).
74 | P a g e
The performance audit report has two main stages: (a) draft performance audit report; and (b) final
culmination point. The culmination point for the draft report arrives when the DG is satisfied about format and
content of the audit report and presents it to AQWM for Quality Assurance Review. Once AQMW clears the
report for quality, the DG issues the draft report to the auditee management for comments and replies.
11.2 The culmination point of the final audit report arrives when the AGP approves the report for issuance
to the auditee and Public Accounts Committee through normal procedure. The AGP will approve the final
report after the concerned DAG has reviewed it and found it suitable for AGP's approval. The DAG of Audit will
ensure that the report complies with the overall strategy and policy of the AGP, has sound analysis and
appropriate recommendations, and responses and comments of the auditee management have been taken
care of in the text of the report. The DAG may require the DG to
11.3 The structure of draft and final performance reports follows the prescribed template. The main as are
necessitated by auditee responses or review of the AQMW during Quality Assurance Review. The
11.4 The draft and final performance audit reports should adhere to INTOSAI Auditing Standards. (ISSAI
400 and ISSAI 3000). Annex-A contains a summary of INTOSAI Auditing Standards on reporting.
and have varied interests. Most of them would like to read 'horror' stories. Others would be interested in
'catching-the-thief type of presentation in the name of public accountability. While the auditors
honest, objective and fair. The challenge for the auditors is to present high impact reports without
compromising on their professional commitment.
11.6 The audit team should ensure that the performance audit report adheres to the following best
practice. The report should:
• Have current and topical information.
• Be unbiased and fair and report the point of view of the management as well.
• Be written in plain language avoiding technical jargon as far as possible.
• Have graphics, charts, photos, headings, sub-headings with text boxes for significant points.
• Have actionable and practical recommendations.
11.7 The performance audit report should have the following style.
• It begins with achievements of the auditee before it goes on to the shortcomings.
• The chapters and paragraphs are logically connected.
75 | P a g e
Camera photos
Achievements/ deficiencies noted during physical
verification/visit
75 | P a g e
• Introduction
• Audit objectives
• Audit scope and methodology
• Audit findings and recommendations
• Conclusion
• Acknowledgement
• Annexes
75 | P a g e
11.20 The Director will ensure that the Auditor In-charge prepares further comments on responses received
from the auditee. These comments will take into account verification of the responses done by the office. The
further comments may consist of disagreement or conflict with the auditee responses. In that case, the DG
should ensure that the further comments have a valid basis and can be defended in the PAC. In case, the
Auditor In-charge agrees with the auditee management, he or she should modify the draft report but
specifically mention these changes in the accompanying note for attention of the Director/DG of Audit.
11.21 The Auditor In-charge may incorporate the oral comments of the auditee in the audit report in
following cases:
• Where the audit team has been working with the auditee staff closely and the latter are familiar
• with the audit observations while in the making;
• The auditors have discussed the recommendations with the auditee management informally;
• The audit team does not expect a major disagreement from the auditee on audit recommendations.
75 | P a g e
The objective of quality assurance is to give confidence to AGP that the quality control systems and practices
in FAOs are working effectively and that the performance audit reports are appropriate.
Quality assurance compares what is required of performance audit and what is actually being delivered.
Audit Standards of AGP (paragraph 2.1.27 and 2.1.28) relating to quality assurance apply to performance audit
as well. The audit standards state as follows:
2.1.27. The Department of AGP shall establish systems and procedures to:
Confirm that integral quality assurance processes have been operated satisfactorily.
12.1 The AGP issued Quality Management Framework for Public Sector Auditing (QMF) in September 2010
for implementing the above standards. The QMF was revised in August 2011. The DG in a FAO will have the
primarily responsibility for quality assurance in performance audit within the framework. The DG should put in
place essential controls at all stages of performance audit to ensure that quality of the performance audit
report meets International Standards for Supreme Audit Institutions (ISSAIs) as adopted by the AGP. The
Director will also perform all functions relating to performance audit as envisaged for Director Quality
Assurance in the QMF.
12.2 The process of quality assurance starts with annual planning for performance audit in a FAO. The FAO
should be able to select entities, projects and programs for performance audit independently, remaining within
the guidance provided in this Manual. The selection of audits should aim at adding value to public sector
management and accountability framework. Proceeding from annual plan to detailed plan for an assignment,
the Auditor In-charge should follow the guidance provided in this Manual and other relevant documents issued
by the AGP on the subject. While reviewing the audit plan for an assignment, the Director and DG should
ensure that the audit objectives and scope, methodology,
79|P a g e
approach, criteria and procedures are likely to produce high quality audit report. For this purpose, they should
ensure that the audit plan adheres to various instructions given in this Manual.
12.1 During audit execution the audit team should follow the audit program in its true spirit and document
all evidence in working papers properly. It should be possible to retrieve relevant evidence in each case
quickly. The Director should use various supervision tools prescribed in this Manual and ensure that audit
conclusions are robust and defensible.
12.2 The DG should check the draft audit report with reference to supporting evidence and hold a mock-run
for quality assurance before AQMW undertakes its Quality Assurance Review. The performance audit report
should meet standards of language, format, style and structure prescribed by the AGP. It may also have
comments on implementation of government policies. The final performance audit report should incorporate
replies of the auditee management with further comments by the FAO, if required. In brief, the instructions
given in this Manual for various stages of audit should be followed in true spirit to ensure a high quality
performance audit.
12.3 The first level of quality assurance process is internal to FAO. The DG and Director of Quality
Assurance (or Director of Performance Audit, if the Director of Quality Assurance is not available) make sure
that the performance audit assignment meets expected standards. The second level of quality assurance is
external to FAO. It is the responsibility of AQMW. The auditing procedures prescribed in chapters 1-11 of this
Manual deal with various internal controls that the DG should implement for ensuring quality. The present
chapter deals with quality assurance external to DG. It primarily deals with the role of AQMW and DAG
concerned in assuring quality on behalf of the AGP.
83 | P a g e
12.10 The Additional AGP will ensure the adequacy of the QCC level review and grading awarded to
performance audit reports, on a sample test basis. The Additional AGP shall sample performance audit reports
normally from each grade-category to confirm the reliability of grading allocated by the QCC of the respective
audit wing to its audit reports.
Table 5: AQMW Annual Plan for Quality Assurance Review for the Year ending 30 June ...
S. No. FAO Performance Audit Assignment Estimated date
for draft report Schedule of
by FAO QAR by AQMW
12.14 The DAG (AQMW) will approve the annual plan of AQMW relating to QARs. After approval of the plan,
head of AQMW will communicate the plan to all concerned immediately.
12.15 Any changes in the schedule of the QAR will have to be decided mutually by the DG head of AQMW.
Flowever, if it is likely to delay the submission of final performance audit report, the DG requesting the change
should first seek approval of the concerned DAG.
12.16 AQMW will prepare QAR Plan for each audit assignment on the format given at Annex-S
Execution of QAR
12.17 QAR is very much similar to an audit assignment. Normally, Director AQMW responsible for QAR or
Quality Management Specialist (QMS) of performance audit will undertake this activity with the
81 |P a g e
approval. Head of AQMW may assign one or more officers to work with the Director/QMS, who will then be a
team leader.
12.18 The team leader for QAR will inform the FAO about program and schedule of the review at least 2-3
weeks ahead of the schedule, allowing the FAO enough time to be in readiness.
12.19 The QAR team will work closely with the performance audit team, Auditor In-charge, the Director and
the DG.
12.20 The QAR team will hold an Entry Conference with the DG. The DG will ensure that members of the
audit team and Director should also attend the Entry Conference. The QAR team leader will discuss the scope
and methodology of the review and also discuss time table for the entire exercise.
12.21 The primary work of the QAR will consist of the following:
• Interviews with the audit team and other officers of the FAO
• Review of planning files relating to the audit assignment
• Review of working paper files
• Review of audit report files
12.22 The QAR team will use the QAR Tool for systematic review (Annex-T). As the last column of the Tool
indicates, the QAR team should prepare working papers for each review question, assign a number to each
working paper and cross refer it on the body of the Tool for subsequent reference and retrieval.
12.23 The QAR team should prepare working papers files very much similar to what the auditors prepare in
their routine work. The working paper files prepared by QAR team will be reviewed by head of AQMW after
completion of the QAR and before submission of the QAR report to DAG concerned and to the FAO.
12.24 The QAR team will hold an Exit Conference with the DG and discuss main findings and
recommendations.
83 | P a g e
12.31 The DAG will monitor receipt of reply to the Client Satisfaction Survey Form (Annex-V) and if
necessary remind the auditee for expediting it. On receipt of reply from the auditee management, the DAG may
like to discuss any matters arising from the reply with the DG.
83 | P a g e
A. Tracking Recommendations
13.1The final performance audit report contains recommendations to which the auditee management has
already shown agreement. The PAC considers final performance audit report and approves or upholds
all or some of the recommendations. The recommendations approved by the PAC must be implemented
by the auditee management. In principle there should be no reason for not implementing these
recommendations as the auditee management had already accepted them at the draft and final report
stages. The FAO should now track implementation of these recommendations. The accountability cycle
culminates with implementation of the audit recommendations by the auditee management.
13.2All FAOs should maintain record of implementation of the recommendations approved by the PAC. For
this purpose, each audit reports and each recommendation in the report should have a distinct numbers
that appear on body of the report. The auditors should request the auditee management to refer to the
serial number of recommendation in all communications relating to implementation.
13.3The FAOs should request, as a standard practice, evidence of implementation of the recommendation. In
certain cases, the evidence provided by the auditee management will be conclusive and would not
require any further follow-up action. In other cases, the FAO may require further verification of the
assertions made by the auditee management regarding implementation. In that case, the FAOs may
decide to conduct further verification by deputing auditor(s) to verify the implementation.
13.4Should the FAOs decide to conduct further verification of the recommendation, the Director/DG should
inform the auditee management of their plan to do so and agree with the auditee management a time
table for actual verification. As far as possible, the FAOs should avoid surprise or unannounced
verification.
13.5In some cases, the process of implementation may have been started by the auditee management and it
would take some time before the recommendation is fully implemented. In such cases, the FAOs should
request the auditee management for a time table for full implementation. Physical verification in such
cases should take wait till the auditee management informs that the recommendation has been
implemented.
13.6In some cases, it may be more economical and efficient if the visiting regularity audit team carries out
verification of the implementation. The DG of Audit should consider this option.
86 | P a g e
Rec.# Recommendation PAC Directive: Action to Due date Auditee response AGP further comments
be taken
Rec.# Recommendation PAC Directive: Action to Due date Auditee response AGP further comments
be taken
Rec.# Recommendation PAC Directive Due ate Auditee response AGP further comments
86 | P a g e
13.12 Methodology for planning, executing and reporting of follow-up audits is the same as for performance
audit assignments presented in this Manual. The only difference between a follow-up audit and an original
audit is that of the scope and coverage.
13.13 All FAOs should plan follow-up audits properly. Following question could be relevant at the time of
planning:
• Did the entity have enough time to address the issues raised originally? [It may be too soon that the
FAO is considering a follow-up audit.]
• Are the recommendations still relevant?
• Should the audit only address implementation of the recommendations, or should the issues
themselves be re-audited?
• Have the initial problems or issues identified evolved with time?
• From a risk perspective, what are the key issues for re-audit?
13.14 Generally, the FAOs should focus on issues or recommendations that were presented in previous
reports and that are of continuing interest to Parliament and/or that pose a significant risk. The FAOs
should take a fresh look on the audit issues and decide whether follow-up audit should remain restricted
to those issues or new issues may also be added. In case new issues have evolved and require focus, the
FAOs should re-define its objective and audit criteria as well. If the FAOs decide to add new issues,
redefine its objectives and develop new criteria, they must inform the auditee management about these
changes and consider any suggestions or feedback on the subject before finalizing the follow-up audit
plan.
13.15 Ideally, the original audit team should carry out the follow-up audit. However, this may not always be
possible. The need to involve members of the audit team that conducted the original audit may depend on
complexity of the issues to be re-audited. If the issues that will be re-audited are complex, the DG should
consider making efforts to include members from the original performance audit in the current audit team.
13.16 Under certain conditions, it may not be possible for any of the previous team members to participate in
the follow-up audit. In the event that the audit team is comprised primarily of new members, the DG/ Director
should organize a meeting with members of the previous audit team, if they are available, when the follow-
up audit is about to begin. This meeting can provide a comprehensive briefing/orientation for new team
members on the audit issues and the previous audit approach.
86 | P a g e
PA Planning Coordination: While planning for PAs to be undertaken during a year will remain an
executive function of all DGs of Audit under supervision of respective DAGs, the PAW will coordinate this
effort in following manners:
(a) Prepare strategic plan for PA, get it approved by the AGP through DAG (APSS)and coordinate
annual plans for PA for individual FAOs.
(b) Define horizontal audits to be conducted by more than one FAO and coordinate for deciding the
lead office for such audits.
Knowledge management on PA: The PAW will act as a repository of knowledge on PA. PAW will be the
lead Wing for managing Intranet of the AGP's Department that will include information on PA as well as
other routine functions of the Department. It will undertake such activities as follows:
87 | P a g e
Technical support The PAW will act as a living guide for work relating to PA in the Department. It will
provide guidance on performance audits planned by FAOs.
Advocacy: PAW will undertake activities to promote PA both within the Department as well in other
executive departments and offices. It will undertake such activities as follows:
Re-launch the publication of the quarterly journal Perform'd as a vehicle for dissemination of knowledge
relating to performance audit.
Proactively involve in delivering lectures and seminars for executive departments and public service
training institutes and academies.
Arrange orientation sessions for all stakeholders including members of the federal, provincial and
district legislative bodies.
Publish promotional literature on PA.
88 | P a g e
What should be maximum length of the auditee response to be included in the audit report?
If a summary of the response is to be included, will it require auditee's clearance?
When should, at the latest, the auditee send responses to be included in the report?
How to reflect disagreement with the auditee in the report?
When the auditee response will not be included in the audit report (e.g. when it is wrong and misleading.)
89 | P a g e
90 | P a g e
• Basic principles
• General standards
• Field standards
• Reporting standards
The purpose of auditing standards is to provide the criteria against which the quality of the audit results can
be evaluated.11 The INTOSAI Auditing Standards do not have mandatory application, but they reflect a 'best
practices' consensus among SAIs. Each SAI should determine whether the INTOSAI Auditing Standards are
compatible with the achievement of its mandate. National standards, taking into consideration the
constitutional, legal and other circumstances, under which the SAI operates, should be defined.
The basic principles are assumptions, principles and requirements, which help in developing auditing
standards and serve the auditors in forming their opinions and reports, particularly in cases where no
specific standards apply. Auditing standards should be consistent with the principles of auditing and
provide minimum guidance for the auditor to help determine the steps and procedures that should be
applied in the audit.
The general standards describe the qualifications and competence, the necessary independence and
objectivity, and the exercise of due care, which will be required of the auditor to carry out the tasks related to
the field and reporting standards in a competent, efficient and effective manner.
The field standards establish the criteria or overall framework for the purposeful, systematic and balanced
steps that the auditor has to follow. These steps represent the research that the auditor, as a seeker of audit
evidence, carries out to achieve a specific result. The standards establish the framework for planning,
conducting and managing audit work.
The reporting standards set the framework for the auditor to report the results of the audit, including
guidance on the form and content of the auditor's report.
91 | P a g e
A code of ethics is a comprehensive statement of the values and principles that should guide the daily work
of auditors. The independence, powers and responsibilities of the public sector auditor place high ethical
demands on SAIs and the staff they employ or engage for audit work. A code of ethics for auditors in the
public sector should consider the ethical requirements relating to civil servants in general and the particular
requirements relating to auditors.
Integrity
Integrity is the core value of a code of ethics. It requires auditors to observe both the form and the spirit
of auditing and ethical standards. Auditors have a duty to adhere to high standards of behavior (e.g.
honesty and candidness) in their work and in their relationships with the staff of audited entities. The
conduct of auditors should be above suspicion and reproach.
Independence
Independence from the audited entity and other outside interest groups is indispensable for auditors.
This implies that auditors should behave in a way that increases, or in no way diminishes, their
independence. Auditors should strive to be independent of audited entities and other interested groups,
but also to be objective in dealing with the issues and topics under review. It is essential that auditors be
independent and impartial, not only in fact but also in appearance.
Political neutrality
It is important to maintain both the actual and the perceived political neutrality of the SAI. Therefore, it is
important that auditors maintain their independence from political influence and discharge their audit
responsibilities in an impartial way. This is relevant for auditors since SAIs work closely with the
legislature, the executive and government entities required by law to consider the SAI's reports.
Conflict of interest
When auditors are permitted to provide advice or services other than audit to an audited entity, care
should be taken that these services do not lead to a conflict of interest. Auditors should protect their
independence and avoid any possible conflict of interest by refusing gifts or gratuities, which could
influence or be perceived as influencing their independence and integrity.
12 INTOSAICode of EthicjlLssued by the Auditing Standards Committee at the 151th Congress of INTOSAI in 1998
in Montevideo, Uruguay, ISSAI 30.
92 | P a g e
Professional secrecy
Auditors should not disclose information obtained in the auditing process to third parties, either orally
or in writing, except for the purposes of meeting the auditing body's statutory or other identified
responsibilities as part of the auditing body's normal procedures or in accordance with relevant laws.
Competence
Auditors have a duty to conduct themselves in a professional manner at all times and to apply high
professional standards in carrying out their work in order to perform their duties competently and with
impartiality. Auditors must not undertake work they are not competent to perform.
Professional development
Auditors should exercise due professional care in conducting and supervising the audit and in preparing
their reports. They should use methods and practices of the highest possible quality in their audits and
have a continuous obligation to update and improve the skills required for meeting their professional
responsibilities.
- is competent to perform the engagement and has the capabilities, including time and resources, to do so;
- has considered the integrity of the auditee and does not have information that would lead it to conclude
that the auditee lacks integrity.
d) Human resources
Each SAI shall establish policies and procedures designed to provide it with reasonable assurance that it
has sufficient personnel with the competence, capabilities and commitment to ethical principles necessary
to:
93 | P a g e
- perform engagements in accordance with professional standards and regulatory and legal requirements
and
- enable the SAI or engagement partners to issue reports that are appropriate in the circumstances.
e) Engagement performance
SAI shall establish policies and procedures designed to provide it with reasonable assurance that
engagements are performed in accordance with professional standards and regulatory and legal
requirements, and that the SAI or the engagement partner issue reports that are appropriate in the
circumstances.
fj Monitoring
SAI shall establish a monitoring process designed to provide it with reasonable assurance that the policies
and procedures relating to the system of quality control are relevant, adequate and operating effectively.
27. In a performance audit, the auditor reports on the economy and efficiency with which
resources are acquired and used, and the effectiveness with which objectives are met. Such
reports may vary considerably in scope and nature, for example covering whether resources
have been applied in a sound manner, commenting on the impact of policies and programmes
and recommending changes designed to result in improvements.
28. For all audit assignments any limitations to the audit, such as restrictive regulations, or
limitations concerning access to information or reporting requirements, should be disclosed to
users of the audit report. The report should also disclose the standards that were followed and
audit criteria applied in carrying out the performance audit.
29. The auditor is not normally expected to provide an overall opinion on the achievement of
economy, efficiency and effectiveness by an audited entity in the same way as the opinion on
financial statements27. Where the nature of the audit allows this to be done in relation to
specific areas of an entity's activities, the auditor is expected to provide a report which
describes the circumstances and context to arrive at a specific conclusion rather than a
standardized statement.
30. The audit report should include information about the audit objective, audit questions,
audit scope; audit criteria, methodology, sources of data, any limitations to the data used, and
audit findings. The findings should clearly conclude against the audit questions, or explain why
this was not possible. The audit findings should be put into perspective and congruence
should be ensured between the audit objective, audit questions, findings and conclusions. The
report should, where appropriate, include recommendations.
31. The report should be timely, complete, accurate, objective, convincing, constructive, and as clear
and concise as the subject-matter permits28. It should also be reader-friendly, well structured, and
contain unambiguous language. Overall, it should contribute to better knowledge and highlight
improvements needed29. The audit findings and conclusions should be based on evidence and
94 | P a g e
should be clearly distinguishable in the report30. All relevant viewpoints should be considered in the
report and the report should be balanced and fair31.
32. Recommendations, where provided, should be presented in a logical, knowledge-based and rational
fashion, and be based on competent and relevant audit findings32. They should be practicable, add
value and address the audit objective and questions.
They should be addressed to the entity(ies) having responsibility and competence for their
implementation.
33. Auditors should refer to all significant instances of non-compliance and significant instances of
abuse33 that were found during or in connection with the audit34. Where such instances are not
pertinent to the audit questions, it is envisaged that they would nevertheless be communicated to the
auditee preferably in writing at the appropriate level.
34. Unless prohibited by legislation or regulations, before publishing a performance audit report, the
SAI should always give the auditee(s) the opportunity to comment on the audit findings; conclusions,
and recommendations35. Where disagreements occur they should be analysed and factual errors
corrected. The examination of feedback received should be recorded in working papers so that any
changes to the draft audit report, or reasons for not making changes, are documented.
35. Distributing audit reports widely can support the credibility of the audit function. SAIs should
decide about the method of distribution in conformity with their respective mandates. The reports should
be distributed to the auditee, the Executive and/or the Legislature, and where relevant, made accessible
to the general public directly and through the media and to other interested stakeholders36, unless
prohibited by legislation or regulations."
26 ISSAI 400/4.
27 ISSAI 400/23
28 ISSAI 400/7(a).
29 ISSAI 3000/5.3.
30 ISSAI 400/7.
31 ISSAI 400/24.
32 ISSAI 3000/4.5.
33.ISSAI 1240/P6, "Abuse involves behavior that is deficient or improper when
compared with behavior that a prudent person would consider reasonable...".
34 ISSAI 400/7.
35 ISSAI 3000/4.5.
36 ISSAI 3000/5.4.
95 | P a g e
Standards and Guidelines for Performance Auditing based on INTOSAI's Auditing Standards and
Practical Experience, ISSAI 3000
ISSAI 3000 is based on generally accepted principles of performance auditing. The guideline sets out the
general framework for performance auditing, defines application of auditing principles for performance
auditing, provides standards and guidance for planning and conducting performance audits, and for
presenting the audit results. It also includes information on performance auditing in relation to information
technology and on conducting performance audits with an environmental perspective. Further, a framework
of system-oriented approaches in performance auditing is presented.
96 | P a g e
97 | P a g e
Introduction
Performance auditors need to carry out risk assessment at two stages: (a) while preparing annual plan
for deciding the audit assignments; (b) while preparing audit plan for an assignment for deciding audit
issues to be focused.
In broad terms, "risk" can be defined as anything that prevents an entity from meeting its goals and
objectives. An answer to the key question, "what can go wrong?" usually identifies risk in an entity,
function or process.
Control risk It refers to the risk that the internal control may not be working or are inadequate and do
not prevent the inherent risk take place. It is also known as residual risk.
Ultimate risk It refers to the probability and impact of the risk, should it take place. It means: Assuming
the internal controls are what they are, what is the probability that the identified risk will occur and if it
does occur what impact will it have on the operations and objectives of the organization?
Categories of Risk
An organization can face numerous types of risks. For sake of simplicity, the auditors can classify the
risks in following categories. Classifying the risks in these categories helps in organizing thoughts
relating to possible risks. It is more likely that the auditors will be able to enumerate all possible risk if
they think through these categories.
Strategy ris : Strategy risk encompasses those risks which can occur through lack of strategic thinking
that manifests in strategic planning; adverse or improperly implemented decisions; lack of
responsiveness to changes in the external environment; and exposure to economic or other
considerations.
Governance risk: Governance risk arises through inappropriate use of authority in decisionmaking.
Examples of governance risk are probability of corruption and misuse of authority; failure to establish
appropriate processes and structures for informing, directing, managing and monitoring the activities;
insufficiencies in senior management leadership; and the absence of an ethical culture.
Compliance risk: Compliance risk arises from violations of or the failure or inability to comply with
laws, rules, and regulations, prescribed practices, policies, procedures or ethical standards.
Financial risk: Financial risk arises from insufficient funding; inappropriate use of funds; inadequate
management of financial performance; or unreliable financial reporting or disclosure.
98 | P a g e
Operational risk: Operational risk arises from inadequate, inefficient or failed internal processes or
failure to conduct operations economically, efficiently or effectively.
Human resources risk: Human resource risk arises from the failure to develop and implement
appropriate human resources policies, procedures and practices.
Information risk: Information risk arises from the failure to establish and maintain appropriate information and
communications technology systems and infrastructure.
• An organization
• A ministry or a department
• A division within a ministry or a department
• A section or unit within a division
• A project or a program
• A specific focus area or process (e.g. recruitment of personnel, contract management, etc.)
Conducting risk assessment at an organizational level can also be used to prioritize risk areas and
develop an overall audit plan for the entity as a whole.
99 | P a g e
100 | P a g e
101 | P a g e
For preparing annual plan for performance audits to be conducted during the next financial year, a Federal
Government audit office carried out risk assessment. The Audit Office was responsible for audit of several
ministries, divisions, and department beside numerous public sector corporate bodies and funds. As a result of
the risk assessment the auditors identified 12 assignments (shown below). Since the Audit Office did not have
enough resources to conduct all of these audits, it decided to prioritize the assignments using the scoring tool
(Attachment-4). Following was the result of scoring. After scoring all assignments, the office sorted these
assignments in descending order to identify the most risky assignments.
Table 8: Risk Ranks of Audit Assignments (Unsorted)
Probability
S. No. Audit Area of Impact Rank
Occurrence
6 H H 9
Human resource management in Telecommunication Authority
9 H M 7
General services and supplies in Ministry of Supplies and
Procurement
11 H H 9
Management of expendable stores In Ministry of Supplies and
Procurement
12 H H 9
Management of information technology and communications
in Ministry of Information Technology
102 | P a g e
Notes
Columns 3 and 4 of this table have been taken from Risk Register. [Attachment -2]
Column 5 of this table has been developed in light of Scoring Tool. [Attachment-4]
103 | P a g e
Probability
S. No. Audit Area of Impact Rank
Occurrence
2 H H 9
Management of information technology and communications...
4 Recruitment of staff... M H
8
5 Financial management... M H
8
7 Procurement management... M H
8
Travel management... H M 7
8
Transport management... H M 7
10
Contract management... L L
1
11
Budgetary Control... L L
12 1
Conclusion
Depending upon the resources that the audit office has, it can decide to audit the most risky audit assignments
in the descending order. Suppose the office has resources to audit for 5 assignments, it will select the
104 | P a g e
105 | P a g e
Attachment-1
Interview objectives
The primary purpose of the discussion is to:
Discussion points
To facilitate this process you should be prepared to discuss the following matters.
(a) The fundamental goals and objectives of your area of responsibility (what are you and your people charged
with doing)?
(b) Key business processes in your functional area?
(c) Current initiatives in your area of responsibility (i.e., performance improvements actions, cost reduction
activities, responses to regulatory actions, process changes or system changes, etc.)?
(d) Factors that may prevent you from achieving your objectives, their potential financial or operational impact,
and their probability of occurrence?
(e) Key controls in your area (processes that mitigate key risks and make it more likely that you will achieve
key objectives)?
(f) Key performance measurements and other tools that are used to monitor performance within your
area of responsibility?
(g) Opportunities for performance improvement you are presently aware of and related constraints (i.e.,
necessary financial resources, available time, etc.)?
106 | P a g e
Attachment-2
Probability
Control of
Impact18
Existing Effectivene Occurrence
ss16 17
Audit Assignment Observed Risks Operational (High,
Identified (Strategy, and/or Financial Strong, Medium,
governance
Controls Moderate, High,
operational, Low)
Weak Moderate
compliance,
financial, HR, Low
information, etc)
(1) (2) (3) (4) (5) (6)
M H M
Procurement and
contracting
The risk that the
Procurement
organization is non- manual
compliant with central exists.
agency procurement
and contracting
Procurement
policies.
planning is
For example: obligatory.
Notes: 14 15 16
107 | P a g e
108 | P a g e
Attachment-4
Moderate There are some problems with the way in which the
controls are being applied. The controls do not
significantly alter the impact on the risk.
Strong Controls are appropriate and they are being applied as
intended.
109 | P a g e
Attachment-3
Figure F: Ranking Risks - Probability Impact Matrix
Table 11: Guide for Scoring
Control Effectiveness
Tool
High 9 7 5
Medium 8 6 4
Low 3 2 1
Impact
110 | P a g e
Attachment-5
Name Title
Note: Drawing on input from relevant auditee management, the above individuals were selected to
participate in the risk assessment conducted by the Audit Team.
111 IP age
YEAR __________
112| P age
TOTAL: 50
113 |P age
Reported time over run is over 100 percent of the original plan. 3
1
3 Reported time over run is between 50-100 percent of the original plan.
2
5 Reported time over run is between 25-50 percent of the original plan.
1
2
3
114| P age
assignment] YEAR
Table 21: Quarterly Plan for the Period From ... to... (Insert dates)
S. Audit Assignment Title Audit End of End of Draft Final
No. Team Planning Fieldwork Report Report
Date Date Date Date
(1) (2) (3) (4) (5) (6) (7)
Legen
c for initials of team members (Col. 3):
Date:
Approved by:
Notes
Col. 3 Use initials of the team members and give legend at the bottom of this Template.
Col. 6 Indicate planned ate of approval of draft report by DG.
Col. 7 Indicate planned date of approval of the final report by DG.
115 | P a g e
YEAR __________
1. Name of the project, and background information
[A summary of the history, nature and major factors affecting the project and, if it is the part of a program,
of the whole program to which it belongs. Mention the location(s) of the project or locations of the major
operation of the program. ]
2. Responsible authorities
[Mention the department, agency and the controlling ministry.]
3. Project details
116 |P age
Type of project
Objectives of the project [State the objectives and goals, targets of the project or program]
Beneficiaries [Population in general, identifiable
large groups of the population, or certain target groups.]
Time phasing Capital cost Sources of finance Type of financing Project stage
[State whether the project is in the implementation stage, or if it is implemented / operational
since... or (temporarily) abandoned.]
4. Data availability
[Availability of pertinent, sufficient and reliable data is most important for achieving the audit objectives
that would resultantly produce a reliable and controversy-free report. A list of available documents,
reports and other allied matters must be prepared.]
5. Risk assessment
[Risk assessment is an exercise that leads the auditors to conceive what can go wrong, what is the
probability it will go wrong and what will be the impact if it does go wrong. The objective is to identify
issues of potential significance.]
Project stage
Availability of data
Findings of some previous audit or special study Resources available in the audit office
Cost of audit and expected benefits or savings from the audit exercise State of internal controls
117 | P a g e
Or
G. Template for Audit Assignment Plan
9. Reasons forOFFICE
abandoning the
OF THE audit
DIRECTOR GENERAL
OF AUDIT (Insert Name)
Prepared by Date
Approved by Date
118 |P age
YEAR __________
Introduction
1. [Give a brief introduction of the audit assignment. Start with the audit entity, its organization and
operation and context in which the current project or program lies.]
2. [Give a description of capital value, size, geographical coverage, locations, services to be provided
or being provided, number of persons employed.]
3. [Give an introduction to the management of the project or program, controlling authorities,
authorities with delegated powers and accountability relationships.]
Audit Objectives
[Revisit the PSR which contains the audit objectives. Fine tune these objectives, if necessary, with the
approval of the DG]
Scope of Audit
1. [State period to be covered, locations to be covered, facilities to covered, etc.]
2. [Mention any exclusions, in particular those which would be normally expected to be included.]
3. [Explain reasons for excluding these areas.]
Approach of Audit
[Mention the method to be adopted by the auditors, in particular, if they have to visit other locations, or
conduct survey, or float questionnaires among the auditee staff, etc.]
Audit Issues
[Revisit the PSR of the assignment as approved by the DG. Assume that the issues remain the same.
However, before finalizing consult the DG once again, in particular if the Auditor In-charge realizes that a
change has become necessary.]
Audit Criteria
1. [Determine the audit criteria for each issue f potential significance.]
2. [Discuss the criteria internally within the FAO and also share it with the auditee management. Try to
get their agreement or adopt/ adapt the criteria to arrive at an agreed version. ]
Audit Team
[With the approval of the DG mention the names of the auditors for the audit assignment.]
Time Budget
[With the approval of the DG define the time budget for the audit. The budget should mention time required in
terms of number of person days of auditors for (a) planning (b) executing (c) reporting. The
119 | P age
time budget will not include the number of person days for support staff. Provide the information on format of
Table G.l below:]
Table 22: Time Budget for Performance Audit of...
Activity Team leader Auditor-1 Auditor-221
PSR preparation
Audit plan preparation
Audit execution
Schedule of Audit
[Give a plan for dates on which various activities will be carried out. Us the format of Table G.2 below]
Table 23: Schedule for Performance Audit of...
Activity Target Dates
End of Planning
End of Fieldwork
Prepared by:
Date:
120 | P a g e
YEAR ___________
To:
1. I wish to inform you that the Directorate General of Audit... plans to conduct the following performance
audit:
Audit Subject
Director Responsible
Auditor In-charge
Auditors
2. As part of our preparations, we would like to meet with you and/or your representatives to discuss
and obtain your views on various aspects of the audit, including its proposed objectives, scope,
procedures, and timetable, as well as how any related disruptions to your operations could be
minimized.
3. The Auditor-in-charge will contact your office to arrange a mutually convenient date and time for
the meeting.
4. Thank you in advance for your assistance and cooperation in ensuring the proper and efficient
conduct of this audit.
(Signature of DG)
121|P a g e
Audit issue: # 1
Audit objective:
Audit criteria:
1.2
1.3
And so on
Audit issue # 2
Audit objective:
Audit criteria:
Audit
procedures:
2.1
2.2
2.3
And so on
122 | P a g e
YEAR
Audit Findings and Recommendations Annotate Replies by the Auditee
Audit issue:
Audit findine:
Audit recommendation #: 1
Audit issue:
Audit findine:
Audit recommendation #: 2
And so on
123 | P a g e
WP#
K. Template for Working Paper OFFICE OF
THE DIRECTOR GENERAL OF AUDIT (Insert Name)
PERFORMANCE AUDIT Oinsert title of assignment ]
YEAR _________
Audit Issue:...
Audit procedure #... [Refer to Audit Program] Date...
S. No.# Work Done Done By
Note: The audit conclusions should be used to prepare audit observations. There should be a cross reference
of the working paper on each audit observation.
124 | P a g e
A Dam Construction Project had a planned capital cost of Rs 10 millions, all to be incurred in the first year.
The dam had an estimated life of 30 years. The operational costs of the project during years 2-30 were
estimated as Rs 1.00 million per year. It is estimated that the project benefits will start flowing from year 2
when they will be only Rs 0.5 million. They will grow by Rs 0.5 million till year 7. From year 7 to the end of the
project life the benefits will stabilize at the level of year 7. The discount rate for the project was 10 percent.
The PCI of the project calculated NPV as Rs 2.45 million and IRR as 12.33 percent.
When implemented the total project capital cost was Rs 12.45 million (year 1 =Rs 5; year 2 = Rs 7.45). It took
two years to complete and the actual benefits started flowing from year 3. However, the benefits were merely
Rs 0.45 million for years 3 and 4; from year 5 to9, the benefits increased by Rs 0.35 million. From year 10, the
dam attained full capacity and the actual benefits stabilized at the level of year 9. The expected life is 30 years
as planned. The operation and maintenance cost is Rs 1.2 million for the years 3-10, Rs 1.5 for year 11-20 and
Rs 2 million for year 21-30. The auditors worked out the cost benefit analysis of the project on the basis of
actual data which was as follows.
1 5 0 -5 -4.55 -4.81
2 7.45 0 -7.45 -6.16 -6.89
3 0.45 -0.75 -0.56 -0.67
1.20
4 1.20 0.90 -0.3 -0.20 -0.26
5 1.25 0.05 0.03 0.04
1.20
6 1.20 1.60 0.4 0.23 0.32
7 1.95 0.75 0.38 0.57
1.20
8 1.20 2.30 1.1 0.51 0.80
9 1.20 2.65 1.45 0.61 1.02
10 1.20 2.65 1.45 0.56 0.98
1.50 2.65 1.15 0.40 0.75
11
12 1.50 2.65 1.15 0.37 0.72
13 1.50 2.65 1.15 0.33 0.69
125 | P a g e
The project had NPV of Rs -5.82 million at 10 percent discount rate. The project went into losses at the
planned rate of discount. It had an IRR of merely 4 percent as compared to the planned IRR of 12.33 percent,
less than one third of what was planned.
126 | P a g e
Illustration 8.2
Note: The following illustration tries to show how economic benefits are quantified for conducting
economic benefit cost analysis. The illustration does not show the benefit cost analysis itself
because it is the same methodology as illustrated in the previous example.
A paved road project was planned at a capital cost of Rs 42 millions. The maintenance cost of the project from years 2
to the end of its life would be Rs 0.30 million per annum. The road would connect several small villages to the market.
The length of the road is 21 km and its expected life is 21 years. The financial benefits from the project are negligible
since the toll tax to be collected would be at a low rate to facilitate the poor population of the villages. The real benefits
of the project are estimated to be in terms of economic efficiency. The villagers have lower vehicle operating cost due
to reduction in distance, reduced vehicle maintenance costs due to lesser wear and tear of tyres and saving in terms
of travel time. The estimated benefits were quantified as follows:
Estimated benefits:
(a) Reduced vehicle operating cost calculated as below:
i. Total kilometers of distance saved = Average daily traffic x Reduction in distance x 365
ii. Total cost of oil saved = Total kilometers saved x Average consumption of oil per km x Average price
of a liter of oil
(c) Savings in terms of time, monetized at average daily wage of an unskilled worker (taking the most
conservative point of view) was calculated as follows:
Savings due to time saved =Average time saved in a trip from village to market x Number of persons traveling
everyday x 365 x daily wage rate
127 | P a g e
PC 1 calculated the net present value as Rs 23.71 million and IRR as 15.5 percent and economic internal rate
of return (EIRR) for the project. The rate of discount is 10 percent.
The auditors will get the data for actual costs and benefits and prepare estimates of benefits and costs on
that basis. Using the actual data they will follow the same methodology as illustrated in Illustration 8.1
above.
In a water supply scheme the planned and actual data were as follows.
Particulars Planned Actual
Capital cost Rs 30 million Rs 38 million
Construction period 1 year 2 years
Maintenance cost Rs 1 million per annum Rs 1.5 million per annum
Water supply 365 million gallons per annum 412 million gallons per day
The cost of a gallon of water as planned was Rs 0.01.
The auditors calculated the unit cost of water by using actual data. Their calculations were as follows:
Output Budgeting Illustration Actual data
Cost(R Water (Gal. Discounted cost at
s
Year M.) M.) lOpercent Discounted output at 10 percent
1 19 0 17.3 0
2 19 0 15.7 0
3 1.5 412 1.1 310
4 1.5 412 1.0 281
5 1.5 412 0.9 256
6 1.5 412 0.8 233
7 1.5 412 0.8 211
8 1.5 412 0.7 192
9 1.5 412 0.6 175
10 1.5 412 0.6 159
Conclusion:
The unit cost of water is Rs 0.02 (just double of what was planned).
128 | P a g e
During the audit of 'Rescue 4444', an emergency response organization, the auditors noted that maintenance
operation of vehicles, etc was rising steeply. It was Rs 15000 in January 2010 but by June 2011 it had
reached the limit of Rs 100,000. On enquiry they learnt that the management of 'Rescue 4444' had started a
crash program for reducing its response time to reach the place of emergency. The response time to
complaints was 40 minutes in January 2010 when the program was launched. The management aimed at
cutting this time to 5 minutes. For this purpose, they required a fleet of vehicles so that the maintenance
staff could rush to the troubled spot quickly. The management started adding to its fleet of service vehicles
until it reached 30 vehicles in June 2011 from 4 in January 2010. It planned to have another 10 vehicles that
would increase the monthly expenditure on maintenance and operations to Rs 110,000.
The auditors were skeptical about the effectiveness of the program. They hypothesized that there was a
weak relationship between the expenditure on vehicles and the response time as most of the vehicles
seemed to run errands for personal needs of the staff and officers. They also wanted to ensure that the
planned increase in monthly expenditure to Rs 110,000 was justified.
They carried out the coefficient of correlation exercise on Excel sheet and found as follows:
Jan-10 15000 40
Mar-10 30000 30
Jun-10 40000 25
Aug-10 60000 22
Dec-10 70000 20
Apr-11 90000 20
Jun-11 15
100000
Note:
For calculating Coefficient of correlation, in Excel program: Select Formulas, then Statistical and
then Correct and fill the dialogue box. On the Enter command, you will get the coefficient of
correlation.
129 | P a g e
Measuring response time for Rs 110,000, assuming the trend remains the same20:
By entering the data on the dialogue box for the same series of Y and X and the New Value of Rs
110,000 we get
Response time value as 12 minutes. It means if we increase the expenditure to Rs 110,000, the response
time
Should be 12 minutes, assuming the present trend of response time.
Finding the level of monthly expenditure to reduce the response time to 5 minutes:
By hit and trial the auditors found that a monthly expenditure of Rs 138000 would be necessary to reduce
the response time to 5 minutes.21
Response time for New Value of Rs 138000 (new value of X, Constant is True) = 5.104 Audit Conclusions
(1) The auditors found that there was strong correlation between expenditure on maintenance and operations
of vehicles and the reduction in response time. The program was effective. The hypothesis of the auditors was
untrue.
(2) If the management desires to reduce the response time further to 5 minutes and the present trend of
efficiency continues, it would require a monthly expenditure of Rs 138000. For achieving its target of Rs
110,000 and response time of 5 minutes, the management needs to increase the efficiency of its staff by
monitoring the actual movements of the vehicles and cutting on wasteful expenditures. The trend needs to be
changed.
20 The calculation uses Excel worksheet (Statistical formula for measuring “Trend”). The value for new „XD is put as Rs
110,000. The value of,.Constant^ required in the formula has been give a$,TrueD.
21 By changing the value of new „XD iteratively, until we arrived at the desired response time of 5 minutes.
130|P a g e
YEAR __________
Notes:
1. The Director will use this tool to assess if the audit plan prepared by the Auditor in-charge for a performance
audit assignment satisfies audit standards and complies with policies of the FAO.
2. Column (4) will refer to the source document or any other basis on which the opinion in column
(3) is based.
3. Column (5) will record any further observation(s) that the supervisor likes to record. Use additional pages, if
required.
s. Review Questions Y/N/NA Reference Remarks, if any
No to basis
(1) (2) (3) (4) (5)
1 Is the time taken by the Auditor In-charge to
prepare the audit plan reasonable since the
approval of the PSR24?
131 |P a g e
17
Do the issues of potential significant tie in with the
long term strategy of the SAI and policy of FAO?
18
Will the issues identified be of interest to users of
the audit report such as parliamentarians, executive
authorities, media and the general public?
19 Does the approach to audit identify the methods
for collecting audit evidence?
132 | P a g e
133 |P a g e
Notes:
1. The Director will use this Tool to review field work of the performance audit team.
2. Column (4) will refer to the basis on which opinion in column (3) has been recorded. Column (5) will
record any further observation(s) that the supervisor likes to record. Use additional pages, if
required.
3. The Director will use this Tool to review the work during the audit at least twice, though more
often will be desirable.
Date of Review:
S. No Review Question Y/N/NA Evidence for the Remarks if any
basis
(1) (2) (3) (4) (5)
4
Will the audit team be able to complete
the work as planned by due date?
5 Will the audit team require any extension
to complete the work? If so, what is the
reasonable estimate?
Does the audit team require any
6
additional human resources? If so,
25 Generally, two weeks will be reasonable.
134 | P a g e
135 |P a g e
verifications, if any?
18 Do the working paper files contain notes
of physical verifications done by the
auditors?
19
Did the audit team collect any evidence
from outside such as market research,
independent enquiries from third parties,
etc? If so, assess if the methodology
adopted was reasonable and defensible?
20 Review the questionnaires for written
replies and assess if the questions are: (a)
clear (b) non-suggestive (c) do not require
hard work by the respondent (d) relevant
to the audit objectives (e) brief.
136 |P a g e
137 |P a g e
Notes:
1. The Director shall complete this checklist while submitting the Draft Performance Audit
Report to DG for approval.
2. Column (4) will refer to explanatory notes which will be attached to the Checklist.
s# Review Questions Date Note#
Yes/No/NA
138 |P a g e
20 Overall Assessment
Date:
Date:
139 |P a g e
YEAR
Auditor In-charge ___________________________________ Assignment No ____
A. General Review
S. No Review Question Yes/No/NA
3 Has the Auditor In-charge taken off all irrelevant papers from the working
paper file?
4 Does the working paper file follow the same order as the Audit Program?
5 Have members of the audit team signed the working papers prepared by
each one?
B. Detailed Review:
(s):...
Result of the Review
Working Subject/Title of Working Comments, if any
Papers Paper
page
numbers
140 | P a g e
______________________________________________________________________________________________________________________ 141 | P a g e
Performance Audit Manual Auditor General of Pakistan
Annex-Q Template for Audit Observation
YEAR
Auditor In-charge ____________________________________ AssignmentNo ___________
Subject: [Mention main heading of the Audit Observation as it would be inserted in the Draft Audit
Report+...
Topical Sentence: [Summarize the main message of the observation as it would be inserted in the draft
audit report+...
Criteria
Conditions
[ Insert working papers reference in the text within brackets and in distinct color]
Causes [ Insert working papers reference in the text within brackets and in distinct color]
Effect [ Insert working papers reference in the text within brackets and in distinct color]
142 | P a g e
Recommendation(s)
Name and Signature of the Auditor Name and Signature of the Auditor In-charge
Date Date
Certified that I have reviewed the audit observation and related working papers. I am satisfied
that the audit evidence is sufficient, relevant and valid.
Date
Date
143 | P a g e
APSS Wing
Auditor-General's Office
April 2011
144 | P a g e
145 | P a g e
1. This Template and Guidance Notes are structured to cover most aspects of
performance/project/program audits. Thus, what is described may not be relevant to every individual
audit. Field Audit Offices (FAOs) will need to pick the Template elements that relate to specific audit
assignments they have undertaken. Similarly, FAOs may find additional aspects not covered in the
Template worthy to be included in their Audit Report. FAOs may cover those additional
areas/aspects in the Reports. Thus, the Template is "flexible" and not "restrictive".
2. The Template includes Guidelines in italics. These Guidelines indicate what should be covered
under each section/sub-section of the Audit Report. Further, the Guidelines suggest the structure of
sentences to be used in drafting. Standardized phrases have been given in some sections to help
you with writing. Blank space has been left in standardized text for you to fill in. You can modify
phrases if necessary.
3. The paragraph numbers in the template are only for purpose of illustration. In practice, this will
change according to each audit report.
4. Findings are to be given under sub-headings. Under each sub-heading, the Template indicates one
recommendation. In practice, an Audit Report may have more than one recommendation under one
sub-heading. The general principle should be that in cases where a recommendation can logically
respond to multiple findings, an Audit Report should not have two recommendations in such
situations.
5. First line of each paragraph will have a left indent of 0.5 spaces.
7. Except for headings and sub-headings, the normal text should use Times New Roman Font size 12.
146 | P a g e
147 | P a g e
148 | P a g e
[Insert Date] (Day/Month/Year e.g. 15th April 2011)[Times New Roman Bold 14]
149 | P a g e
150 | P a g e
[The objective of the preface is to introduce the report as a document. Preface may highlight information,
which requires immediate attention of the audited organization or the readers in general. Only in rare cases
the Preface should be of more than one page. No reference should be made in the preface about the results of
the audit.]
The Auditor-General conducts audits subject to Article 169 and 170 of the Constitution of the Islamic
Republic of Pakistan 1973, read with sections 8 and 12 of the Auditor- General's (Functions, Powers and
Terms and Conditions of Service) Ordinance 2001[add reference of any other relevant laws and regulations as
applicable to the subject of audit]. The audit of [activity22/project/programme, Ministry/Department of ]
.................................... was carried out accordingly.
The Directorate General [give your office name] conducted audit of the [activity/project/program] during
[indicate the period during which audit was carried out] for the period [indicate the period covered in this
audit] with a view to reporting significant findings to stakeholders. Audit examined the economy, efficiency,
and effectiveness aspects of the [activity/project/programme]. In addition, Audit also assessed, on test check
basis [amend if basis are different] whether the management complied with applicable laws, rules, and
regulations in managing the [activity/project/programme]. The Audit Report indicates specific actions that, if
taken, will help the management realize the objectives of the [activity/project/program]. Most of the
observations included in this report have been finalized in the light of discussions in the DAC meetings.
The Audit Report is submitted to the [insert Governor of Province or President as appropriate] in pursuance
of the Article 171 of the Constitution of the Islamic Republic of Pakistan 1973, [add reference of any other
relevant laws and regulations as applicable to your area of audit].
22Activity covers other than PSDP initiatives such as waste management operations, imports operations, large scale
procurements etc. This footnote is given for guidance only. The report will mention the activity covered in audit in the
preface.
151|P a g e
EXECUT
IVE
SUMMAR
Y
Page
No.
SECTIONS
1. INTRODUCTION
2. AUDIT OBJECTIVES
4.8 Environment
4.9 Sustainability
5. CONCLUSION
152 | P a g e
ACKNOWLEDGEMENT
153|P a g e
154 | P a g e
EXECUTIVE SUMMARY [Times New Roman Bold Size 14] [Insert Audit
Title[Times New Roman Bold Size 14]
[From here onward: Font Times New Roman, Size 12, formal text
Director General of Audit [insert name of the office] conducted an audit of [audit title] [in (month, > or from
(month) to (month, year)]. The main objectives of the audit were to [insert (only brief objec to be provided,
details to be given in Section2 Obectives].The audit was conducted in accordance with the INTOSAIAuditing
Standards.
[Start typing the summary from here onward. Mention main findings only. Close the summary with
recommendations. The summary should not .] exceed two pages
155 | P a g e
b. Following are specific areas that need to be covered in this section. Sub headings may be used for
structured description.
i. Rationale of the project /activity 23 and its linkage with MTDF and PSDP.
ii. Approval by competent forum, specific instructions given, if any. Significant decisions
i. e. by Prime Minister,ECNEC/ CDWP related to project/activity
Hi. Time lines/ period of the project/activity.
iv. Paragraph on description of project/activity.
v. Projecfactivity objectives and outputs as provide d in PCI/other policy documents and a
brief on achievement against these objectives and outputs.
vi. Cost of the project/activityand financing including donor support.
vii. Summary of the financial results yearwise ( resourceallocation PSDP or through other
means funds released, actual expenditure).
viii. Progressjin both quantitative and qualitative terms) as perPCI/other approved plans
ix. Details of revisions in project. How many times has PCI been revised; variation in
objectives, cost and scope vs originally approved PCI.
x. Major loan/ grant covenants (if applicable)
xi. Analysis of major findings in PC IV for completed projects/other reports on the activity
audited
c. The subheadings that are not relevant to the audit subject may be ignored.
1. [Start typing herejThe Director General of Audit [insert the name of office] conducted an audit
of [audit title] [in (month, year) from (month) to (month, year)]. [This is the first paragraph of
introduction.] [Add more paragraphs if necessary]
23
Activity covers other than PSDP initiatives such as waste management operations, imports operations, large scale
procurements etc.
156 |P a g e
Audit objectives should be specific and carefully determined before commencement of field audit activity.
Management’s input may also be obtained where appropriate to come out with responsive reports.
3. AUDIT SCOPE AND METHODOLOGY [Times New Roman Bold Size 14]
This section should also indicate any areas that were excluded from the audit scope and limitations of
audit coverage. On scope of audit, mention the period covered, geographical areas included or any other
information that defines the scope of auditors work. The section should also state the methodology used
such as file review, field survey, auditee interviews, focused group discussion, market research etc.]
3.1 [Start typing text here Add paragraphs sequentially] [New Times Roman, font size 12, normal text.]
Suggestive finding areasay be modified subject to the scope of audits and reporting requirements. Each
finding should discuss the condition, cause, criteria and impact. This should follow a specific
recommendation thabddresses the cause and condition noted in the findings
157 | P a g e
The subheadings that are not relevant to the audit subject may be ignored. Similarly, if you consider an
area not covered above as material for purpose of reporting in the Audit Report, you should take that into
account.
Recommendations: The [client] Administration should [insert recommended action addressing the
cause and conditions discussed above]
4.2 Financial Management ( 3 - 4 pages)
This sub- section helps in assessing financial management aspects of the activity/project/program
audited. Itmayinclude audit comments on:
i. Quality and timelines of submission and approval of Cash and Work Plan (VFM)
ii. Details of release requests and lead times from submission of release request to actual
release of funds (VFM)
Hi. Details of funds lapsed (Regularity)
iv. Reappropriations and surrenders (Regularity)
v. Periodicity of financial reports preparation and circulation (Regularity)
vi. Format of financial reportsiPSAS, FARAH etc. (Regularity)
vii. Submission of accounts to accounting offices (Regularity)
viii. Reconciliation with accounting offices (Regularity)
ix. Details of project’s bank accounts (Regularity)
x. Reconciliation of bank accounts (Regularity)
xi. Procedure for recording and details of third party payments (Regularity)
xii. Payments made in accordance with terms and conditions of the agreement. Cost
escalations not allowed on foreign exchange component. (Regularity)
xiii. Fixed exchange rate agreed in contract whereas payments made at rate prevailing on date
of payment.
xiv. Advance payments made against bank guarantee/ security and adjusted
in time. (Regularity)
xv. Advances to employees after proper approval and adjusted in time. (Regularity)
xvi. Data archiving and record management to ensure safe custody of record. (Regularity)
The subheadings that are not relevant to the audit subject may be ignored. Similarly, if you consider an
area not covered above as material for purpose of reporting in the Audit Report, you should take that into
account.
Recommendations: The [client] Administration should [insert recommended action addressing the
cause and conditions discussed above]
158 | P a g e
The sub-headings that are not relevant to the audit subject may be ignored. Similarly, if you consider an area
not covered above as material for purpose of reporting in the Audit Report, you should take that into account.
Recommendations: The [client] Administration should [insert recommended action addressing the
cause and conditions discussed above]
4.4 Construction and Works ( 2- 3 pages)
Audit report may include comments on construction and works related activities carried out by an entity/
project/program in following areas.
i. Site Selection; ideally before preparation of design and cost estimates. Sites
identified in PCI vs. actual site of construction. Any survey conducted for site
selection to ensure it is suitable for the purpose.(VFM)
ii. Acquisition of Land; method of acquisition either through govt, department or by project/
programme directly from owners. Any market survey conducted to assess the price/ rate of
land. Payment made for land acquisition vs. provision in PCI.(VFM, Regularity)
iii. Preparation of design and drawings. Who prepared the design, whether approved by relevant
authorities, compliance with approved standards. Procedure for hiring of consultant for
design.(VFM)
iv. Cost estimates prepared in accordance with design. What standards/ system was used for
cost estimation. Approval of cost estimates and comparison with PCI.(VFM)
v. Contract award; process followed, evaluation criteria, details of competition (how
many parties participated and bid price), basis of selection (technical and financial), approval of
selected bidder, drafting of proper contract to safeguard project's
interest. Cost comparison of contract price with cost estimates and PCI.(VFM,
Regularity)
vi. Construction: construction schedule prepared by contractor and approved by management,
monitoring of construction for timely completion, preparation of periodic status reports and
submission to management, physical progress actual vs planned, procedures to ensure
quality of work, results of physical inspection conducted by audit
159|P a g e
(if any), details of any scope changes, cost charged for additional work with
justification.(VFM)
vii. Operation: identification of issues which have or can delay an asset from becoming operative,
e.g. delay in installation of utility connections, delayed procurement of office equipment or
non provisioning of funds for office equipment in PCI.(VFM)
The sub-headings that are not relevant to the audit subject may be ignored. Similarly, if you consider an area
not covered above as material for purpose of reporting in the Audit Report, you should take that into account.
Recommendations: The [client] Administration should [insert recommended action addressing the
cause and conditions discussed above]
4.5 Asset Management ( 1 - 2 pages)
This sub-section will present assessment of internal controls and utilization of assets by an
entity/project/programme, including:
160 | P a g e
viii. Major issues highlighted in Aid Memoirs and monitoring reports and there current status
(VFM)
The sub-headings that are not relevant to the audit subject may be ignored. Similarly; if you consider an area
not covered above as material for purpose of reporting in the Audit Report, you should take that into account.
Recommendations: The [client] Administration should [insert recommended action addressing the
cause and conditions discussed above]
4.7 Compliance with grant/ loan covenants (1/2 page)
This sub-section covers a review of loan covenants applicable to an entity/project/programme. The review will
help see whether or not loan covenants were complied with and, if not, what were the implications thereof for
the entity/project/programme..
Recommendations: The [client] Administration should [insert recommended action addressing the
cause and conditions discussed above]
161 | P a g e
Activities/projects/programmes should also be rated for risks. The analysis made under sub-section 4.9
provides some guidance on risk assessment. Risk assessment becomes more critical in case of ongoing
activities/projects/programmes as it can point toward remedial steps that can eventually lead to an
activity/project/programme reaching intended objectives. FAOs are expected to use objective criteria for
rating.
i. Relevance: Whether project/activity audited was within overall MTDF framework and in-line
with government's sectoral policies.
ii. Efficacy: Achievement of physical outcomes, financial performance, likelihood of
achievement of project outcomes leading to achievement of project goals with reference to
originally concerned objectives.
iii. Efficiency: Cost overruns and time overruns in the project, timeliness in submission of cash
plans and release requests by project, timelines in funds availability to the project, timeliness
and competitiveness in procurement.
iv. Economy: Procurement of goods and services at competitive rates without compromising
quality. Specifications, BOQs, bidding process, timely delivery and quality etc.
v. Effectiveness: Using a range of performance measure and indicators to assess entity's
effectiveness. Whether desired results, objectives and targets have been successfully
achieved.
vi. Compliance with Rules: Seriousness of non compliance with applicable rules and
regulations. Major instances of non-compliance.
a. High
b. Substantial
c. Medium
d. Low
162 | P a g e
*Begin with a topical sentence 'Bold Font Size 12. No paragraph number on this sentence]
5.2 Lessons Identified: General conclusions, both positive and negative arising from the review.
This will include practices, processes and management practices contributing to the successful
implementation of an activity/project/programme or otherwise and can be lessons for similar
activities/projects/programmes.
163 | P a g e
32. We wish to express our appreciation to the Management and staff of [client] for the assistance and
cooperation extended to the auditors during this assignment.
164 | P a g e
ANNEX-1
(Yes/No) Date
165 | P a g e
1. Background
a. Title of performance audit being reviewed
2. Objective of QAR
5. QAR schedule
166 | P a g e
Purpose:
The purpose of this tool is to provide the Quality Specialist Managers assess the quality of the Performance Audit
completed by a Field Audit Office.
S. No. Element of QA Total Criteria for scoring Score Reference
Score obtained to WP
1. Audit Planning
2. Audit Execution
167 | P a g e
3. Audit Report
3.1 Did the auditors cover all audit 2 Fully =2 Partly =1 Not at
objectives? all =0
168 | P a g e
169 |P a g e
Su-total-4
10
Grand Total
100
170 | P a g e
Conclusion
[The Quality Management Specialist can work out the percentage of the score obtained with reference to
the total score.]
Comments of the DG
Serial no in the Comments of the DG
QATool
171 | P a g e
Title of Assignment:
Year:
Dates of QAR:
172 | P a g e
The Department of the Auditor General is assessing the overall quality of its audit process. A key element of
this assessment involves determining how our clients rate the quality and value added by the audits. As
such, I am requesting that you consult with your managers who dealt directly with the auditors, and
complete the survey below. I assure you that the information you provide will remain strictly confidential.
4.
173 | P a g e
Title: _____________________________
Thank you for taking the time to fill out this survey. Please send the completed survey form as soon as
possible in the enclosed envelope addressed to:
174 | P a g e
Analysis of Gaps, 70
Annual Plan for Performance Audit, 15
Approval of the Annual Plan, 21
ASOSAI, 7
Audit Approach, 28
Audit Assignment Plan, 25, 28, 29,49,118
Audit Completion Checklist, 67, 77,138
Audit criteria, 31, 36,47,115,121 Deciding Audit Assignments, 18 Decision Point, 27
Audit Criteria, 29, 70,118 Definition of Performance Auditing, 5 Departmental manuals, 40
Audit Execution Cycle, 35 Direct observation, 38 documentation, 47 Economic impact, 19,
Audit mandate, 18 111 Engagement performance, 94 Entry Conference, 31, 32,
Audit objective, 36,121,170 34,49, 82,138,169 Equipment for Performance Auditors, 88
Audit Objectives, 26, 28,118 ethical requirements, 92, 93 Exit Conference, 32,44, 45,46,49, 65,
Audit Observations, 70, 71, 74 67, 70, 74, 82, 122,139,169,174 Field Work, 37, 64, 65,134 Field
Audit procedures, 36,121 Work Plan, 37
Audit Program, 17, 36, 37, 49,121,123,140,142 Finalizing the Assignment Audit Plan, 30
Audit Scope, 28 Financial Impact Guide, 112
Auditee files, 38 Financial risk, 98
Auditee Response, 77 Following PA Themes, 17
Average deviation, 60, 61 Follow-up Audit, 86
Benefit-cost Analysis, 53 Follow-up Performance Audits, 85
Camera pictures and videos, 40 Format of the Performance Audit Report, 76
Capacity building, 1 Governance risk, 98
Case studies, 40 Horizontal Performance Audits, 17
Categories of Evidence, 41 Human Resource Plan, 21
Categories of Risk, 98 Human resources risk, 99
causal relationships, 59 impact for AGP, 20,112
Client Satisfaction Survey, 82, 83,175 Implementation of PAC Directives, 85
Client Satisfaction Survey Form, 82, 83 Implementation of the Manual, 87
Comparison with Financial Auditing, 12 Improved quality of service, 7
Comparison with Performance Evaluation, 12 Independence of the Supreme Audit Institution, 1
Compliance risk, 98 Information risk, 99
comprehensive manual, 2 Internal Clearance, 74, 77
Conducting Risk Assessment, 17 Internal Rate of Return, 55, 56
Confidential information, 32 Interviews, 38, 82
Conflict with the Auditee, 33 INTOSAI, 5, 8,10, 23, 47, 64, 75, 91, 92, 94, 96,156
contact person, 32 INTOSAIs code of ethics, 92
Control Effectiveness, 106,108 IRR, ix, 55, 56, 57, 62, 63,124,125,127
Correlation Analysis, 129 Issues of Potential Significance, 26, 29
Correlation and Regression Analysis, 58 Key Internal Controls, 25
Current Files, 47,48, 50, 51 knowledge management, 1
Data Analysis, 53 Knowledge management, 87
Databases, 41 Legislative/public interest, 19
175 | P a g e
176 | P a g e
177 | P a g e
178 | P a g e