Beruflich Dokumente
Kultur Dokumente
BOILER
2. PRETREATMENT PLANT
4. DM WATER SYSTEM
7. AIR CONDITIONING
8. ASH HANDLING PLANT
Erection of Rubber expansion joints, NRVs and Butter fly Valves at discharge side of pump
Erection of Control Valve, Air release valves and P & I Instruments of pipe line.
Power and control cables to the motors of Raw water pumps and Butter fly valves from MCC.
PRETREATMENT PLANT:
Civil works on clarifiers, stilling chamber, sludge thickener, Sludge pit, Chemical House, Filter Water Pump
House, Pretreatment MCC Building are to be completed before taking up of the mechanical works.
Erection of Clarifier Bridge and floculaters paddles.
Erection of Travel drives floculaters drives.
Erection of Sludge Thickener Bridge.
Erection of Sludge Pumps.
Erection of Centrifuge.
Erection of alum, line and Poly electrolyte tanks and its agitators.
Erection of Raw Water Chlorination System.
Erection of flash mixture.
Erection of Clarifier in let sluice Valves.
Erection of CT makeup pumps, Filter Back wash pumps and Service water pumps in Filter water pump
house.
Erection of expansion joints, NRVs Butter fly valves of above pumps and piping from pump discharge to
terminal points.
Erections of spent filter back wash pump and its valves and piping.
Erections of filter back wash air blowers and its valves and piping.
Erection of pipe lines and valves in Rapid Gravity filters.
Erection of under slung crane in filter water pump house, electric hoist in chemical house and service
water pump bay.
Power and Control cabling to above pumps from pretreatment MCC.
AUXILIARY COOLING WATER SYSTEM:
Civil works for DM Water pump house, pipe rack from Budameru Bridge to DM Water Pump House are
to be completed.
Erection of DM transfer pump with its suction and discharge valves and NRVs at the exiting Stage-III
Erections of DM water pipe line (150NB SS pipe line) from Stage-III DM water pump House to Stage-IV
DM water tank.
Erection of DM Make up pumps, its suction, discharge valves, NRVs and its piping.
Erection of Boiler fill pumps, its suction, discharge valves, NRVs and its piping up to Boiler drain valve.
Power and control cabling to above pumps from BOP MCC.
Erection of LDO & HFO pipe lines from existing to fuel oil pump house to LDO & HFO tanks including
Civil works for Compressor house and foundations for air receives out side the building are to be
completed.
Erection of pipe line from compressor to Air receiver and Air receiver to Air drier and then to receiver.
Erection of water cooled air conditioning system in TG Building including supply of ducting supply air
diffuser, return air diffuser, volume control dampers, air handling units of various capacities, cooling
towers etc.,.
Erection of water cooled air conditioning system in ESP control room including supply of ducting
supply air diffuser, return air diffuser, volume control dampers, air handling units of various capacities,
Erection of Air cooled system in Switch yard control room including supply of ducting supply air
diffuser, return air diffuser, volume control dampers, air handling units of various capacities, etc.
Power and control cabling to chiller units, air handling units, fans etc.
ASH HANDLING PLANT:
Refracting cooling water system i.e. erection of pumps and its piping.
Ash extraction valves for completed ESP hoppers, Economiser and Air heater hopper are to be
erected.
Erection of 450NB pipe from raw water pipe line including butterfly valve to the fire water tanks.
Erection of fire hydrant pumps including its suction and discharge valves and piping.
Erection of spray pumps including its suction and discharge valves and piping.
Erection of diesel driven hydrant pump including its suction and discharge valves and piping.
Erection of jockey pumps including its suction and discharge valves and piping.
Erection of booster pumps including its suction and discharge valves and piping.
Erection of hydrant line header from fire water pump house to Boiler area.
Erection of Spray header line from fire water pump house to station transformer – 6.
Erections of deluge valves and spray system including nozzles and quarzoid bulbs for station
transformer – 6.
Erections of Hydrant system around Fuel Oil pump house and HFO & LFO tanks.
Erection of smoke detection system in Control Room LT & HT switch gear rooms and cable vaults.
ELECTRIAL WORKS IN BOP EQUIPMENT:
Laying of 11Kv cables from 11Kv switch board at TG building to transformers including its terminations at
both ends.
Laying of power cable for DC supply from Battery charger room at TG Building to DC DB in pretreatment
MCC building.
Laying of LT cables from MCC to various drive motors including its terminations at both ends.
Laying of control cables from local control stations and field switches to PLC I/O rack.
Erection of Lighting Transformers and LDBs including cabling in pretreatment MCC building.
Erection of Light fittings and conducting wiring from lighting panels to fittings in the building and at
equipments.
Erection Ash handling MCC, power cables to RCW pump supply, LT Bus ducts etc.,
Laying of 11Kv cables from 11Kv switch board at TG building to transformers including its terminations at
both ends.
Laying of power cable for DC supply from Battery charger room at TG Building to DC DB in pretreatment
MCC building.
Laying of LT cables from MCC to various drive motors including its terminations at both ends.
Erection of Lighting Transformers and LDBs including cabling in AHP MCC building.
Erection of Light fittings and conducting wiring from lighting panels to fittings in AHP MCC building and at
equipments.
Erection of LT MCC in SILO MCC building for power supply to Raw water pumps and its cables
terminations.