General Notes shall be compacted to the same distribution of fill types over the whole fill
specification as adopted for the thickness.
Any site won materials must be validated subsequent compaction works. PLATE BEARING TESTS UNDERTAKEN ON A MAXIMUM 25x25m to confirm the absence of any The Contractor shall take all necessary GRID AT THREE LEVELS TEST 1, TEST 2 & TEST 3. contamination. Disposition of Fill steps to ensure that the fill is placed at the moisture content necessary to TESTS TO BE UNDERTAKEN UTILSING A 600dia PLATE LOADED Preparation of Site. Where construction is required upon fill achieve the specified level of compaction UPTO 300kN PER SQ.M. TEST TO BE UNDERTAKEN IN placed over sloping natural ground, and and shall, where necessary, add water to Drainage grips or trenches shall be where fill thickness is less than 5m, the ACCORDANCE WITH DIN 1813 TO DETERMIME VALUES OF Ev1 & or dry the fill, in order to obtain this value. excavated, as necessary, uphill of the adjacent ground shall be benched, with Ev2 A AND CALCULATE A VALUE OF Ev1/Ev2 WHICH SHOULD BE area to be filled to prevent the area being Where it is necessary to add water, this the maximum vertical height of each LIMITED TO 2.0. shall be done as a fine spray and in such flooded. Drainage shall be effected bench not exceeding 500mm and a way that there is time for the water to be without causing siltation or erosion and providing that the fill depth below any absorbed into the fill before being rolled water shall be disposed of in a manner to building does not vary by more than 2000 min PLATEAU BEYOND COLUMN CENTRELINE by the plant. be agreed with all parties. 15%. TO ENSURE FILL MATERIAL IS RESTRAINED SITE WON NATURAL NON-COHESIVE FILL FINISHED The area to be filled, whether an existing Cobbles, boulders, rock or waste Where, because of the current method of +142.200 FFL PROFILE fragments, the largest dimension of which MATERIAL FILL COMPACTED IN MAXIMUM excavation or otherwise undisturbed working, previously engineered fill placed is greater than two thirds of the 250mm THICK LAYERS UNDER 8No PASSES ground, shall be graded to falls, and during the current works has to be TEST 3 compacted layer thickness, shall not be sump pumping or other suitable benched as in Section 8.1 to allow new fill OF A VIBRATORY ROLLER WITH A MASS OF +141.750 incorporated into the fill. dewatering facilities shall be provided as to be placed adjacent to it, then the 3000kg PER LIN METRE OF ROLL necessary by the Contractor to keep the benches only require to be 0.5m high by No fill shall be placed and left base of the excavation dry at all times. 1.0m wide, even where these occur uncompacted at the end of the working +141.150 TEST 2 beneath the plots providing that the fill is day. Compacted fill shall be graded to Where the area to be filled comprises an the same material throughout the plot. falls to ensure free run-off of rainwater existing excavation, the excavation shall without ponding. be inspected and subsequently monitored Placing and Compacting Fill by the Contractor, to ensure that there is Compaction plant and compaction TEST 1 no danger of collapse during the works Clause 612 of MCJW Volume applies. method shall be selected having regard to with consequences for safety, for existing However, where there is conflict with the the proximity of existing trenches, buildings or for the construction adjoining. clauses below or notes on contract excavations, retaining walls or other drawings, Clauses from this specification structures and all work shall be performed All topsoil shall be stripped and, where and contract drawings shall take in such a way as to ensure that their required for further use, stockpiled in an precedence over Clause 612. existing stability is not impaired. area provided by the Contractor and agreed by the Engineer. Fill shall be placed and compacted in the EXISTING GROUND PROFILE REDUCED LEVEL EXCAVTION near-horizontal layers of the thickness If weather conditions are such that the specified moisture content and density All soft and compressible soils or existing required to achieve the specified end values cannot be achieved, the fill shall be removed and run to topsoil product or in accordance with the Contractor shall cease work until such dumps provided by the Contractor and approved method specification, and shall, time as the fill can be placed and agreed by the Engineer. The works shall as far as practicable, be brought up at a compacted to meet specification be accomplished in such a way that there uniform rate so that all parts of the site or requirements. is no undercutting of the sides of existing particular sections of the site reach excavations. finished (formation) level at the same If the result of control tests indicate that time. the fill is being placed and compacted in Existing foundations or ledges of hard such a way that the desired level of rock, roots of trees or former pipelines or The compaction plant selected, the compaction is not being achieved, the services at the base of the area to be number of passes made and the fill layer Contractor shall further compact or, if filled shall be excavated and replaced thickness and moisture content used shall necessary, shall excavate the affected with compacted general fill which shall be have regard either to the specified end work and replace with new fill, compacted compacted to the same specification as product and the means and manner of to meet the specification requirements. adopted for subsequent compaction control testing or the specified method works. and the means and manner of control If the results of control tests indicate that testing. antecedent weather conditions (such as Note: No tree roots greater than 5mm frost or heavy rain) have caused the diameter, no roots balls and no masses Where several different types of fill deterioration of finished work such that of fibrous roots shall remain at the base material (all meeting the requirements of the work no longer meets with the of the excavation. Section 2 of this specification) are to be specification, the Contractor shall, at his employed, they shall be deposited in such The base of the area to be filled shall be or her own cost, take such steps as are a way that all parts or particular sections proof rolled with a vibrating roller and all necessary to bring the fill to specification of the site receive roughly equal amounts soft materials replaced with compacted requirements. of a given material, in roughly the same fill. Where unsuitable material has been sequence, thus ensuring a uniform excavated, the underlying natural ground