Beruflich Dokumente
Kultur Dokumente
INDEX
PART I GENERAL
PART I
GENERAL
INDEX
Page
1. GENERAL 5
1.1 Scope 5
1.2 Site Location 5
1.3 Climatic Conditions 6
1. GENERAL
1.1 Scope
This engineering standard covers the general requirements and conditions for
the design of the following items of Civil and Architectural Works for Metor
Expansion Project:
- Site conditions
- Earthwork, roads and paving
- Drainage system
- Concrete structures
- Steel structures
- Pipe Racks
- Architectural design
- Sanitary installations
These standards and criterion have been partially adapted for the project,
therefore, they might include items or specifications that will not be applied.
General geology:
From the view of texture, silty shales are predominant in the area with sandy
shales and shaly sandstones. According to the soil survey, three sectors can be
distinguished: sandstone strings, alluvial slopes and elongated hills or hills to the
south of the slopes.
- Temperature:
- Atmospheric pressure:
The averages of the means per month during 1970 - 1978 are the following:
PART II
SITE PREPARATION DESIGN CRITERIA
INDEX
Page
1. GENERAL 9
1.1 Scope 9
1.2 Language 9
1.3 Measurement Units 9
1.4 Standards 9
2. EARTHWORK 10
2.1 Retaining Walls 10
2.2 Remote Repressing System 11
2.3 Process Areas 11
2.4 Trenches 11
2.5 Control Room Building 11
3. ROADS 12
3.1 Transverse Slope (Pumping) 12
3.2 Road width 12
3.3 Stabilization width 12
3.4 Longitudinal Slope 12
3.5 Curves 13
3.5.1 Horizontal Curves 13
3.5.2 Vertical Curves 13
4. PAVING 13
4.1 Paving ground elevation 13
4.2 Joints 14
1. GENERAL
1.1 Scope
The objective of the following document is to describe the earthwork, road and
pavement works general design criteria, specifically for industrial plants
according to what is established in this document.
1.2 Language
All drawings title, building finish material in general drawings and notes will be
written in English.
1.4 Standards
The standards and references that will usually be used in the project are the
followings:
- Nationals:
- Internationals:
2. EARTHWORK
In general, the earthwork will be related to the general plant arrangement, the
required levels for the process and the natural drainage of the ground.
For the location and design of the retaining walls and dikes of a hydrocarbons
storage tanks patio, the following requirements should be followed:
The area around the tank should have a minimum slope of 1% towards the
retaining wall or drainage point.
The minimum distance from the tank’s base towards the wall or dike’s foot will be
15 meters.
The volumetric capacity of the retaining area will be bigger or equal to 150% of
the full tank capacity. If there are several tanks it will be equal to 150% of the
volume of the biggest tank plus the volume occupied by the rest of the tanks up
to the height of the wall.
When the pavement area and the drainage system guarantees a fast drain off,
the area slope could be of 0.5%.
In areas for spherical tanks, the minimum slope will be of 2.5% towards a sump
in an accessible and safe place. The area will be defined by a curb in its
perimeter of 0.60 m of maximum height.
The distance between the remote repressing and the nearest tank’s wall will be
of 30m.
The volume of the whole repressing system will be bigger or equal to 110% of
the capacity of the biggest tank that drains towards it.
The roads around the process areas should be elevated a minimum of 0.20 m
over its tallest point.
The area will have a minimum slope of 1% towards the sumps, in spill walls or
confined areas.
It will be defined with the process group, the design necessities and criterion to
confine zones within the process areas with curbs.
2.4 Trenches
The transverse dripping slope will be bigger or equal to 0.50%. Lengthwise, the
minimum slope will be of 0.30%.
The trench’s highest point should be 0.25m under the top of the sleepers. When
the trench’s width will be bigger than 8 meters, it is convenient to divide the slope
in two directions, locating the highest point in the trench center.
The minimum distance toward the edge of the roads will be of 2m.
The entrance of the services and the protection levels against floods will
determine the embankment height.
In areas that have not been indicated, the minimum recommended slope is of
0.50%, in areas where the drainage will be confined by ditches and/or curbs the
slope could be of 0.30%.
The cut and filling talus will depend upon what is recommended on the soil study
and usually they vary between 1.5H:1V to 3H:1V.
3. ROADS
The type of vehicle for which it will be designed will determine the road width. To
the width of the vehicle selected 0.50m of lateral spaces will be added to define
the causeway width. The total width of the road will be the sum of the number of
canals in each circulation way plus the lateral spaces, normalizing the width
values to 3, 3.30 or 3.60 by lane.
The minimum longitudinal slope will be of 0.30% for drainage purposes. The
maximum could go up to 8%, in short sections and in access and exit ramps.
Tank patio ramps could have 10% of maximum slope.
3.5 Curves
The minimum curvature ratio towards the border of the causeway will be of 6 m,
however, it should be according to the design vehicle.
Vertical curves will be designed for algebraic deference (A) of longitudinal slopes
bigger than 1%. The minimum longitude for the vertical curve is around 30m,
however, in intersections and small “A” value, the minimum longitude could be
reduced. The following expression will give and estimate of the minimum value
of the longitude of the curve in meters:
4. PAVING
The final finish of internal roads, dikes and tank yard, as well as the various Plant
areas shall comply with the following guidelines, in accordance with the soils
study recommendations:
The elevation above MSL (mean sea level) is ranging from 4 m to 11 m, which is
defined as “MSL + 4 m to 11 m”
The grading level shall define the ground level (GL) for each site, i.e.
4.2 Joints
Longitudinal Joints
They are built to control the longitudinal cracking, with a spacing of 2.50 to 4m
coinciding with the dividing lines of the traffic cross path. It is not recommended
to build longitudinal joints with separations bigger than 4m unless the local
experience indicates that the pavement with those conditions have satisfactorily
behaved.
The depth of the superior groove of these joints can not be less than a forth (1/4)
of the pavement depth. These joints normally have union bars that impede the
separation from its borders. For more than four cross paths it is convenient to
place a tongued and grooved longitudinal joint or free joints between them.
Transverse Joints
Whichever the joint construction procedure will be, the depth of the groove
should be at least equal to a fourth (1/4) of the pavement slab thickness.
The best guide, in respect to the transverse joint separation, is the local
experience towards the pavement behavior in service. If experience can not be
count upon, the following indications can be followed with reasonable security of
obtaining a satisfactory cracking control.
The necessity of placing in the transverse joints elements to transfer the loads
(pins), depends on the conditions of the sub-grade and the traffic that the
pavement will hold. The pins will not be necessary in residential roads or where
light traffic takes place, but they should be placed in roads where the daily traffic
is more than 60 or 90 heavy trucks per day, unless the pavement has a solid
treated cement base under it.
Expansion Joints
When the contraction joints have been adequately separated, the necessity for
expansion joints depends on the predominant temperature during the
construction and the gross aggregate characteristics used in the concrete
mixture.
Experimental and theoretical studies with regard to this matter indicate that with
the exception in placing them in front of existing structures and in irregular
intersections, the expansion joints will not be necessary, if:
c) The contraction joints are placed at intervals that control the transverse
cracking.
According to the process that the product will hold, the pavement surface and the
joints should be protected with specific additives depending on the case.
Besides, the dikes or walls confined storage areas and the trenches areas, the
dangerousness plant study will indicate the areas that should be delimited within
the process area to separate the contaminated and not contaminated drainage
system.
The delimitation could be done placing curbs in its perimeter to hold the flow of
spilled liquids. These should have a concave shape in order to return to the
surrounded area, the overflows occurred. The maximum height will be of 30 cm
over the floor level, excluding the curbs around the perimeter of spherical tanks
that could have 60 cm.
PART III
DRAINAGE DESIGN CRITERIA
INDEX
Page
1. GENERAL 19
1.1 Scope 19
1.2 Language 19
1.3 Measuring Units 19
1.4 Standards 19
6. PARTICULAR CONSIDERATIONS 22
6.1 Process Area 22
6.2 Tank Yards 22
6.3 Pipe Tracks 23
6.4 Trucks fillers and pumping station 23
6.5 Sumps (Catch basins) 23
8. SPECIAL STRUCTURES 26
8.1 Hydraulic seals 27
8.2 Manhole (for contaminated systems) 27
8.3 Ventilation 27
8.4 Oil Tramp 28
8.5 Separator 28
8.6 Manholes (for sanitary sewer and water systems) 28
8.7 Equipment drainage 28
1. GENERAL
1.1 Scope
The purpose of the present document is to describe the methodology and the
design criteria to be used in the drainage project of the Metor Expansion plant.
1.2 Language
All drawings title, building finish material in general drawings and notes will be
written in English.
1.4 Standards
- Rain water from areas not developed in the battery limit of the Plant.
- Rain water and firewater from offices and areas free of contamination.
- Steam boilers, water form air coolers, without the possibility of contamination.
Bolsters Manifolds
Pipe Tracks
Pipe Racks
Storage yard
Filling yards
- Acid flows, caustic or other discharges, will not indulge to drain to the system
of sanitary drainage or sewage waters.
It corresponds to the system that collects and transport the oil from purges or
others hydrocarbon machinery and equipment.
The rain water volume shall be obtained by the rational method, which is a function
of the rain volume, the area to be drained and the characteristics of the drained
area, and is expressed as follows:
Q = C x I x A (lt./s)
Where:
The rain water drainage system within the plant shall be designed for a 10-year
return period, and a concentration time equal to 10 min.
The rain volume values for the region shall be obtained from the attached volume-
frequency-duration curve.
The drainage systems shall operate by the atmospheric pressure. Hence, they
shall be designed to work by gravity, whereby 70% of the filled-up transversal
section shall be capable of transporting the maximum estimated design flow
volume, including future known requirements.
5.2 Firewater
The cumulative flow from the event of firewater will be indicated on the document
N° 3827 P200-00500 “SPECIFICATION FOR FIRE PROTECTION”. In the
process area it will be calculated by the following manner:
Lateral piping: the cumulative flow from the catch basins served.
Main process unit will be the cumulative flow from the laterals and sub-lateral.
Only the permanent type flow will be considered in the design. The sporadic flow
will be considered for the design only when it surpasses to the permanent one.
These waste waters may contain oil or residuals chemical products from the
process or from the laboratory test flows. Additionally, the flows from purges or
the maintenance of equipment have to be considered.
6. PARTICULAR CONSIDERATIONS
To reduce the cost of the final treatment of the contaminated wastewater, the
contaminating process areas will be confined with curbs. For this case, the
design of the flow will be the biggest of the following combinations:
In the unconfined areas the design flow will be the highest between the storm
runoff and 60% of the firewater.
The discharge flow of the tank yard must not be added to the maximum design
flow of the section where it will be connected, because its discharge will be
controlled by a gate valve. This valve must be located outside the tanks area and
it will be of easy access and operation.
Depending of the fluid that will be stored, the discharge must be controlled from
one or more valves taking the waste water to the line destined to conduct the
water to its final treatment.
b) The drainage system will have to be tested to guarantee that with the valve
completely open, the maximum level of the confined waters in the dikes
does not exceed in more than 30 cm. the height of the base support of the
tank after 48 hr. of continuous combat of fire.
h(m) accumulated plate = remanent flow (m3/hr) x 48 hr/ Yard area (m²)
The duration time of a combat of fire fixed by the standards is very long in
comparison with the 6 hr fixed for the storage of the flow for the combat fire.
Thus, the time check up will be 6 hr of duration and the time of the discharge of 8
hr to 12 hr.
It will be the biggest value between the rain water flow and the firewater.
The storage of the water in the area of the track will be permitted for 1/2 hr. in the
event of rain or fire. The permissible height during this storage must not be
higher than 0,15 m below the top of the sleepers.
The design flow will be the biggest value between rain water flow and 60 % of the
firewater.
The sumps that will collect the water confined in ditches or retained on areas will
be designed in accordance to the capacity of the outlet pipe.
In process areas, the maximum free air liquid displacement distance will be 15
m. So the maximum separation between sumps will be 30 m considering the
highest point 15 m from each other.
They will not be located less than 9 m away from access roads, control rooms,
hydrogen compressors and hydrators.
7.1 Channels
The channels sizing shall be carried out according to the Manning equation:
Q= 1 S1/2 A R2/3
n
Where:
The water velocity in the concrete channels shall not exceed 2 m/s.
7.2 Piping
The piping design, as well as the channels, shall be carried out, by means of the
Manning equation, and meet the following conditions:
Height Velocity
The minimum collector diameter shall be 0.20 m (8"), for regulated drainage
minimum diameter is 6”, for waste water for buildings minimum diameter is 6”
and for equipment drainage minimum diameter is 4”.
The flow regimen for the calculation shall be considered as permanent and
uniform. Concrete piping according to the INOS CL-C-65 shall be used. Steel
piping shall be carbon steel.
Material "n"
Closed concrete collectors
(flat inside)
Diameter ≥ 0.69 m 0.013
The level indicated on the drawings shall be used in the calculations and shall be
the piping or channel grade line level.
7.3 Location
Channels:
- Minimal lining: 0, 10 m
8. SPECIAL STRUCTURES
a) Where the principal piping of drainage arising from tank, process, integrated
stores and equipment areas be connected with the main pipe.
b) Between process units.
c) In the discharge of the catch basins.
d) Before entering to a separator.
8.3 Ventilation
a) Ventilation will be installed in the manhole with an immersion and also in the
catch basin located immediately upstream.
b) In the highest point of the catch basin the system is provided with seal.
c) They shall not be left under the pipe racks or others equipment
d) They shall be located at distances larger than 30 m from ovens, boilers or
other ignition sources.
It is a device designed to retain the floating oil. It should not be designed for the
segregation of oil in emulsion.
They will be placed in the outlet of compressor rooms, workshops, kitchens, and
fuel station supply.
8.5 Separator
Is a device designed for eliminating the oil in suspension. This design has to be
based on the velocity of the flow and the rate of the overflow. The most
commonly used device is the one recommended by the American Petroleum
Institute (API).
In super-critical regimen fallen have to be avoided inside the manhole and in the
sub-critical regimen should not be greater than 1 m.
The Official Journal (Gaceta Oficial) N° 5318 specifies that the maximum
separation between manhole will be 120 m for collectors < 0.30 m (12") and 150
m for collectors > 0.30 m (12”)
PART IV
REINFORCED CONCRETE STRUCTURES DESIGN CRITERIA
INDEX
Page
1. GENERAL 32
1.1 Scope 32
1.2 Language 32
1.3 Measuring Units 32
1.4 Standards 32
2. MATERIALS 33
2.1 General 33
2.2 Materials and standards 33
4. DESIGN 35
4.1 General 35
4.2 Loads 35
4.2.1 Dead Loads 35
4.2.1.1 Dead or permanent loads 35
4.2.1.2 Equipment dead loads 36
4.2.2 Live Loads 36
4.2.2.1 Uniform Loads for Buildings other than Warehouses 37
4.2.2.2 Operation floors in process structures 37
4.2.2.3 Operation floors in compressor buildings 37
4.2.2.4 Warehouses 37
4.2.2.5 Pump stations and equipment areas 37
4.2.2.6 Handrails 37
4.2.2.7 Cranes and material handling equipment 37
4.2.2.8 Overhead cross roads, platforms and ladders 38
4.2.3 Wind Loads 38
4.2.4 Seismic Loads 38
4.2.5 Impact Loads 39
4.2.5.1 Cranes 39
4.2.5.2 Exchangers pullout 40
4.2.5.3 Cases of other weights 40
1. GENERAL
1.1 Scope
1.2 Language
All drawings title, building finish material in general drawings and notes will be
written in English.
1.4 Standards
The concrete structure design shall meet following Venezuelan Standards and
documents:
- Acciones del Viento sobre las Construcciones (Wind effect over Buildings),
COVENIN-MINDUR 2003-89.
2. MATERIALS
2.1 General
The materials to be used shall meet the standards requirements such as listed in
point 2.2. The quality of the materials to be used shall be indicated in the
drawings.
As far as the materials other than the ones specified in the drawings, it will be
possible to use locally available materials, whenever these are suitable in quality
and quantity for the specific use for which they are required.
3.1 Concrete
The resistance to the minimum final compression after 28 days and lab-cured,
shall be as follows:
Reinforcement steel of 1" diameter bars or less shall be used whenever possible.
4. DESIGN
4.1 General
The structural design shall be executed according to the fracture theory method
for concrete structures, in accordance with the COVENIN-MINDUR 1753-87 and
ACI 318 standard.
4.2 Loads
The design loads for buildings and other structures shall follow the COVENIN-
MINDUR 2002-88, with the exception of what is specified herein.
The weight of all the structural components, including the fire protection coating,
which is a permanent part of the structure.
In metallic platforms, the supporting structure floor and the floor grid shall have
an estimated dead load value not less than 100 kg/m².
25 kg/m2 for building roofs, in order to cover the weight of lighting fixtures,
suspended roofs, air conditioning ducts, piping, etc.
50 kg/m2 for process structure floors, in order to cover the piping and
miscellaneous loads.
100 kg/m2 on the second level and upper floors in buildings where the partition
layout might be relocated.
150 kg/m2 in compressors operation floors, in order to cover the piping, control
panels, and miscellaneous loads.
The equipment dead load, excluding external piping, caused by the weight of
equipment such as vessels, fractionating towers, heat exchangers, stacks and
pumps, shall be defined as follows:
The dead load of the empty equipment in installation will be the equipment
weight, and it will not include the weight of all the internal or external parts,
which are not connected to the equipment before the installation.
The dead load of the equipment in operation shall be the weight of the
wholly assembled equipment including insulation and the fluid within it. It
shall exclude the piping and external structures connected to the
equipment, whenever these have been previously considered.
The dead load of the empty equipment will be the same as the equipment in
operation without the operation fluids.
The dead load in test will be calculated as the dead load of the equipment in
operation, defined in b, excluding the internal and external insulation, the
volume of liquid in operation, as well as any internals susceptible to damage
due to liquid test immersion. The equipment as well as the piping
associated with the test will be considered full of liquid test.
Use 450 kg/m2; if 25% or more of the bay area shall be covered with equipment,
the distributed uniform load shall be reduced according to the percentage
covered, and this shall be applied as uniform load over all the bay area together
with the equipment load.
4.2.2.4 Warehouses
Use 750 kg/m2; whenever the expected live loads in storage areas shall exceed
750 kg/m2, the engineer in charge of the calculations shall justify the applicable
value.
4.2.2.6 Handrails
A uniform load of 150 kg/m2 should be used. The ladder steps should be design
with a concentrated load at the center of the step of 130 kg.
Except for control buildings and Electrical Substation, buildings shall be classified
in accordance with COVENIN 2003-89 Groups “B”.
All other structures and equipment foundations shall be classified as Groups “B”,
with a wind Importance Factor I= 1.00.
Earthquake load for all other structures and foundations shall be determined in
accordance with UBC-97 Chapter 16.
- Seismic Zone: 3
- Soil profile: Sc (According to recommendation of Geotechnical
Study)
- Seismic Importance Factors I shall be: For equipments and structures in
Areas 1620, 1630, 1640 & WWT (UBC Category 4) = 1.0. For other
Hazardous Facilities & Cooling Tower (UBC Category 2) = 1.25.
Tanks shall be designed per API Standard 650.
The impact load shall be considered as a percentage of the moving load and
shall be applied according to the following information.
Whenever the equipment manufacturer shall specify higher loads than the ones
mentioned herein, the ones specified by the manufacturer shall be used.
4.2.5.1 Cranes
a) Vertical Load
b) Side Load
For mobile cranes supporting beams, a 20% of the sum of the lifted load
weight plus the car load (with the exception of other parts of the crane)
applied to the upper edge of the rails acting in both normal directions, will
be considered; the load will be distributed according to the supporting
structure rigidity.
c) Longitudinal load
The horizontal force will only be transmitted to the exchanger fixed support.
In the case that the equipment manufacturer specifies higher loads that the ones
previously mentioned these loads should be considered.
For support for light motor or transmission driven machines, use not less than
20% of the machine weight.
For reciprocating equipment or power driven units’ support, use not less than
50% of the machine weight.
The horizontal forces caused by friction shall be considered as the product of the
C friction coefficient multiplied by the corresponding vertical load.
The loads due to equipment or piping acting on fixed or sliding points shall be
considered in the structural design taking into account their real situation.
In those cases in which these loads shall be applied, the following structure
design requirements shall be considered:
In case that the explosion-proof control room design shall be specified, the
calculations shall be carried out considering a 17500 kg/m2 uniformly distributed
load acting over the reinforced concrete walls and a 7000 kg/m2 over the roof
slab. The intention is to safeguard the personnel and to maintain the installations
operable in such events.
The structures shall be designed to withstand the effects of individual loads and
load combinations to which they may be submitted during installation or when the
equipment is empty, during equipment and piping tests as well as during
operation. The loads to be considered in the structure design for each one of the
referred load conditions are given in Table I.
The following points shall be applied to design load combinations in any one of
the load conditions given in Table I.
The loads shall be combined to produce the most critical load conditions to the
structural member design. Those loads that might reasonably occur
simultaneously shall be combined. It is not necessary to carry out load
combinations for non-structural elements such as platforms, step ladders, etc.
The partial application of the following shall be considered: live and dead loads
which might occur during equipment installation, during equipment individual
parts tests or those which might result from the operation loads variations in
cyclic process equipment to calculate maximum stress in continuous bents or
beams.
Impact, maintenance and other short-term loads shall not be combined with wind
or seismic.
In the crane support structural element design, a single crane in operation shall
be considered, whenever there is no possibility of two simultaneous cranes.
In the case of supporting elements for tube bundle pullout, one at a time pullout
shall be considered.
TABLE I
LOAD CONDITIONS
- 1.4 CM + 1.4 EM or EV
- 0.75 (1.4 CM+ 1.4 EM or EV ± 1.7 W)
- 0.9CM+1.3W
- 0.75 (1.4 CM + 1.4 EM or EV) ± 1.0S
- 1.4 (CM + EO + T)
- 1.4 (CM + EO + T) + 1.7 CV
- 0.75 (1.4CM +1.4 EO + 1.4 T + 1.7 CV ± 1.7 W)
- 0.75 (1.4CM +1.4 EO + 1.4 T + 1.7 CV) ± S
- 0.9 CM +0.9 EO + 1.4 T ± 1.3 W
- 0.9 CM + 0.9 EO + 1.4 T± S
- 0.75 (1.4 CM + 1.4 EO + 1.4 T± 1.7 W)
- 0.75 (1.4 CM + 1.4 EO + 1.4 T) ±S
Nomenclature:
CM = Dead load
T = Temperature Load
CV = Live Load
FH = Pullout Load
EM = Equipment in Installation Load
EP = Equipment in Test Load
EO = Equipment in Operation Load
EV = Empty Equipment Load
W = Wind Load
S = Seismic Load
In general, the reinforcement steel shall have a protection layer of 50 mm. for all
super-structural members and foundations.
The designer shall clearly specify what foundations are cast directly against the
ground and leave 75 mm. concrete cover protection in these cases.
PART V
STEEL STRUCTURES DESIGN CRITERIA
INDEX
Page
1. GENERAL 49
1.1 Scope 49
1.2 Language 49
1.3 Measuring Units 49
1.4 Standards 49
2. MATERIALS 50
2.1 Steel Structures 50
2.2 Bolts 50
2.3 Welding 51
2.4 Floor Plates and Grating 51
2.5 Galvanizing 51
2.6 Fire Protection 52
3. ALLOWABLE STRESSES 52
4. DESIGN 52
4.1 General 52
4.2 Loads 53
4.2.1 Dead Loads 53
4.2.1.1 Dead or permanent loads 53
4.2.1.2 Equipment dead loads 54
4.2.2 Live Loads 54
4.2.3 Wind Loads 55
4.2.4 Seismic Loads 55
4.2.5 Impact Loads 58
4.2.5.1 Cranes 58
4.2.5.2 Other vertical load cases 59
4.2.5.3 Exchangers bundle pull-out 59
4.2.6 Friction Loads 59
4.2.7 Operation Loads 59
4.2.7.1 Thermal expansion loads 60
4.2.7.2 Pressure loads 60
4.2.7.3 Dynamic loads 60
4.3 Load Combinations 60
4.3.1 Empty Equipment or equipment in Process of Installation 63
4.3.2 Equipment in Test 63
1. GENERAL
1.1 Scope
The present criteria establish the requirements for the steel structures analysis
and design for the project Metor Expansion Plant.
1.2 Language
All drawings title, building finish material in general drawings and notes will be
written in English.
1.4 Standards
The steel structures design shall meet the following Venezuelan standards and
documents in their most recent issue:
2. MATERIALS
With the exception of the requirements of the present specification, all the
materials shall meet the AISC standards.
The structural shapes shall comply with the ASTM A36 or ASTM A572 Gr. 50
standards. The steel plates shall comply with the ASTM A36 standard. The
2
maximum allowable yield strength shall be fy=2530 kg/cm for the A36 material
2
and fy=3500 kg/cm for the A572 Gr. 50 material.
The steel piping for structural applications shall meet either one of the following
standards: ASTM A-53, types E or S, Grade B or API 5L, Grade B.
2.2 Bolts
High-strength bolts shall be used in the structure, according to the ASTM A-325,
Type I.
Common, low-strength Bolts shall be used in stairways, poles, and other non-
structural elements. These bolts shall meet the ASTM A-307 specifications.
2.3 Welding
The welding shall be carried out by means of manual arch, according to the A5.1
or A5.2 standards, or by submerged arch, according to AWS A5.17. The E70-XX
electrode shall be used.
- Checkered steel plates or grating shall be used in the floor system for
platforms, according to the designer requirements, and shall comply with
the following characteristics:
- The staircases and railing shall meet the COVENIN 2245 standard.
- The stair step shall be rectangular, grating (1" x 3/16") and the edge
will be non skid checkered plate.
2.5 Galvanizing
All the steel surfaces shall be hot dip galvanized according with ASTM A-123.
Galvanizing shall consider vat sizes of hot-dip galvanizing facilities. Galvanizing
process shall be performed at fabricator’s workshop, and cold galvanizing touch
up paint shall be applied at site during construction stage in those places where
the shop’s galvanized may result damaged due to transportation and/or erection
process.
3. ALLOWABLE STRESSES
The allowable stresses for steel structures shall be the ones specified by the
AISC standard.
The allowable stresses for members and their connection in those load
combinations with wind or earthquake may be increased up to 33%.
The maximum allowable traction stress for low-strength bolts (A-307) used as
anchor bolts, shall be based on the square root of the thread area, and shall be
2
1060 kg/cm for a test or operation load condition, without any additional
increase. As far as empty equipment, or equipment-in-installation conditions, the
2
maximum allowable traction stress for anchor bolts shall be 1270 kg/cm , without
any additional increase.
4. DESIGN
4.1 General
The steel structure design and details shall be carried out according to the
standards indicated in point N° 1.4, with the following specifications:
Those structure in which the bracing may interfere with piping equipment and
staff access, shall be designed according to AISC Type 1 (rigid frames)
construction.
Minor structures such as platforms, footbridges, stairways and safety cages, can
be supplied as part of the equipment and under the supplier's standards. If this
shall not be the case, they will be supplied according to the designer's
1145-01-90-C01-TEC-001 REV-0 05/03/2007 52 de 117 INE-DOCUMENTO
METOR EXPANSION PROJECT
requirements and in any case, they shall be designed using the corresponding
building safety standards.
4.2 Loads
- In steel platforms, the supporting structure and the floor grid weight, an
2
estimated dead load value not less than 100 kg/m shall be considered.
The equipment dead load, excluding external piping, caused by the weight of
equipment such as vessels, fractionating towers, heat exchangers, stacks and
pumps, shall be defined for each load condition as follows:
The dead load of the empty equipment will be the equipment load weight, and
it will exclude the weight of the internal or external parts which are not
connected to the equipment before the installation.
The dead load of the equipment in operation shall be the weight of the wholly
assembled equipment, including insulation and the fluid within it. It shall
exclude the piping and external structures connected to the equipment,
whenever these have been previously considered.
The dead load in test will be calculated as per the previous paragraph,
excluding external and internal insulation and the volume of liquid in operation,
as well as any internals susceptible to damage due to liquid test immersion.
The equipment as well as the piping associated with the test shall be
considered full of liquid test.
The following live loads shall be uniformly distributed, and the values are given in
Table I.
In the case of cranes and equipment for material handling, the load shall be the
capacity of these equipments.
Except for control buildings and Electrical Substation, buildings shall be classified
in accordance with COVENIN 2003-89 Groups “B”.
All other structures and equipment foundations shall be classified as Groups “B”,
with a wind Importance Factor I= 1.00.
Earthquake load for all other steel structures shall be determined in accordance
with UBC-97 Chapter 16.
- Seismic Zone: 3
- Soil profile: Sc (According to recommendation of Geotechnical
Study)
TABLE I
The impact load shall be considered as a percentage of the moving load, and it
shall be applied according to the following information.
In case that the equipment supplier shall specify loads which exceed the one
above exposed, these shall be considered in the design.
4.2.5.1 Cranes
In the crane supporting beams, the overloads shall be taken as the top loads
upon the wheels.
a) Vertical Load
b) Side Load
For mobile cranes supporting beams, a 20% of the sum of the lifted load
weight plus the car weight (with the exception of other parts of the crane),
applied to the upper edge of the rails, and acting in both directions normal
to the rail, will be considered; the load will be distributed according to the
supporting structure rigidity.
c) Longitudinal load
- For support for light motor or transmission-driven machines, use not less
than 20% of the machine weight.
- For reciprocating equipment or power driven units support, use not less
than 50% of the machine weight.
The horizontal force will only be transmitted to the exchanger fixed support.
The horizontal forces caused by friction shall be considered as the product of the
C friction coefficient multiplied by the corresponding vertical load.
In those cases in which these loads shall be applied, the following structure
design requirements shall be considered:
The following points shall be applied to design load combinations in any one of
the load conditions given in Table II.
- The loads shall be combined to produce the most critical load conditions to
the structural member and connection design. Those loads which might
reasonably occur simultaneously shall be combined. It is not necessary to
carry out load combinations for non-structural elements such as platforms,
step ladders, walkways, etc.
- The impact, maintenance and other short-term loads shall not be combined
with wind or seismic.
- For support elements for tube bundle pull-out, one at a time pull-out shall be
considered.
TABLE II
LOAD CONDITIONS
The engineer shall revise the following load combinations; not all possible
combinations are included. Therefore the engineer will decide which other
combinations are necessary to be analyzed.
- DL + EL
- DL + EL + LL
- 0.75 (DL + EL ± W)
- 0.75 (DL + EL ± 0,72 S)
- DL + OL + TL + FL
- DL + OL + TL + FL + LL
- 0.75 (DL + OL + TL + FL + LL ± 0,72 S)
- 0.75 (DL + OL + TL + FL + LL ± W)
- 0.75 (DL + OL + TL + FL ± 0,72 S)
- 0.75 (DL + OL + TL + FL ± W)
Where:
DL = Dead Load
LL = Live load
EL = Empty equipment load or load of equipment in installation
tL = Load of equipment in test
OL = Load of Equipment in operation
BL = Tube bundle pull-out force
TL = Thermal load
S = Seismic load
W = Wind load
FL = Friction load
4.4 Deflections
The following maximum values are recommended for the deflections due to
variable and wind loads:
- For the pipe rack structures, the following maximum deflection values due
to variable and wind loads are recommended:
The deflection shall be the sum of the one coming from the
longitudinal plus the transversal beam at
the intersection point L/200
The connections carried out in the workshop shall be welded, except when the
welding may be impractical or when the designer so indicates.
The structural connections shall be carried out with high-strength bolts, according
to the ASTM A-325 standard, and with a minimum 5/8" diameter.
PART VI
PIPERACKS DESIGN CRITERIA
INDEX
Page
1. SCOPE 70
4. MATERIAL TYPE 75
5. DESIGN LOADS 76
5.1 Operation Loads 76
5.1.1 Operating gravitational loads of pipes 76
5.1.2 Friction and anchor loads 77
5.2 Hydro Static Test Loads 77
5.3 Wind Loads 78
5.4 Seismic Loads 78
5.5 Load Combinations 78
6. METHODS OF ANALYSIS 79
7. DEFLECTIONS 80
1. SCOPE
This design practice outlines the design process of structuring and analyzing
steel or concrete pipe racks.
It is not covered here the detailing of the structural elements of the pipe rack nor
its foundations.
A pipe rack is, usually, one or more rows of columns, which are alone or joined
by beams. In the case that there is only one row, it is usually formed by “T” posts.
When there are two or more parallel rows, the columns of one row can be joined
to the other columns in the same row through beams perpendicular to the
direction of the pipes that they support forming transverse elevation frames.
These transverse elevation frames can be joined to each other by longitudinal
beams parallel to the direction of the pipes.
The principal function of the pipe racks is to support the pipes and its related
components; electrical and instrument cable trays. They may also support
aircoolers, maintenance platforms, equipment, etc.
It is a support of one column, which can have one or more supporting levels.
It is a connection that has sufficient rigidity to hold virtually unchanged the angle
between connected members.
2.7 Strut
They are beams which run longitudinally between column frames and which
function is to give vertical support to the pipes, which enter and exit the pipe rack,
cable trays, etc. Their secondary function is to behave as a strut forming part of
the longitudinal bracing system.
These are forces that act on the frame beams, originated by the pipes do to their
thermal expansion or contraction.
It is a support that restraints translation and/or rotation of the pipe in one or more
degrees of freedom.
2.11 Guide
2.12 Stop
It is a support that restraints the pipes movements in all six degrees of freedom.
2.14 Bent
Individual rigid or braced frame in the perpendicular direction to the main running
pipe direction. This frame is the key structural part of the pipe support system.
2.15 Bay
Sliding support at one end of a longitudinal beam, which allows a section of the
pipe rack to expand do to thermal loads with out been restrained by the
contiguous pipe rack section, where the beam is supported. This objective can
also be accomplished by suppressing the longitudinal beams between to
consecutive transverse bents.
In general, the selection of the structural configuration of the pipe rack should be
based in structural and economical criteria, which minimizes cost of the structure
and its foundations. This design guide aids in the selection of an economical
system.
criteria. It is common practice to design them with bent length (L) between 3.0
and 9.0 meters and a spaced from each other (S) between 6.0 and 10.0
meters.
The first pipe supporting level generally is located at an elevation between 5.0
and 6.0 meters above ground, with the exemption of the cross roads, where the
overhead clearance is controlled by the vehicles requirements for the plant in
question.
The vertical spacing between adjacent levels is, usually, around 2.0 meters.
The first level height could get to be relatively small when there is no space
requirement under the frames for equipment or its maintenance, and on the other
hand there is also no required height for the plants processes. In the case that
only one level is required and the elevation is smaller than approximately 1.2 to
1.5 meters, it is probably more convenient to support the pipes on sleepers.
It could occur that a client decides to take provisions for the future of one or more
levels of pipes. In this case, the analysis and design will be executed with the full
level configuration, but making the drawings for the current construction
requirements and leaving the necessary previsions for the future expansion. It is
always convenient, even if no future levels are required, to leave at least a 15 cm
extension at the top end of the column to help prevent the fall of a loose pipe.
Usually transverse frames (bents) are designed with rigid connections that are
able to resist moments in there plane, for which the columns are oriented so that
its flanges can form a moment connections with the beams (or beams if it is a
multilevel pipe rack) of the frame. They are also connected to the foundation with
a moment connection through a base plate and at least four anchor bolts. In this
case the longitudinal forces (perpendicular to the transverse frames), which could
not be resisted only by the columns, as independent cantilevers, can be
absorbed by a bracing system. This system can be of type cross “X” or knee “K”
connecting the transverse frames to each other with longitudinal beams, which
we will call connectors or struts when this is their only function. We will call them
longitudinal beams when at the same time, or when their only function is to
support vertical pipe loads that enter and exit the pipe rack, equipment,
platforms, etc., or serve as support for intermediate beams.
- When the longitudinal forces are absorbed by a bracing system, this one
should have at least one level of struts or longitudinal beams, for each row of
columns in the section. The system should also have at least one span of
braces in “X” or “K” for each row, placed preferably in the same relative
position (one in front of the other). For the maximum recommended length
(60.0 to 90.0 meters), a minimum of two spans of bracing is adequate, and
more could be required in order to minimize the axial forces that act on the
braces and on the foundations.
In the selection of the material type that is going to be used for the structure of
the pipe rack, besides the client requirements, the economical aspect must be
considered. This related not only to the material cost and its installation, but also
to execution times, availability according to the zone and plant location
circumstances, etc. In the case the structure is of steel, it is important to consider
if it must be fireproofed.
All of these aspects mentioned above are not static in time which means that an
evaluation needs to be performed in the detail design stage in order to compare
both concrete and steel solutions. Material of each Piperack/Structure shall be
decided with consideration of all kinds of options such as economic efficiency,
schedule, practicability, etc., at Detail Engineering Stage.
5. DESIGN LOADS
The operation loads must include the self-weight of the structural elements, pipes
and its contents, insulation, fireproofing, cable trays, equipment, platforms with its
overload, etc. Also friction and anchor loads form part of the operation loads.
The uniform load of pipes in operation (W), can be calculated with enough
approximation in the following manner:
(Units kg, m)
Where,
The load “W” in this way calculated should not be taken as less than 122*S.
Once obtained the definite loads from the piping group, loads should be revised
and if required perform the necessary modifications in the design.
Also to begin the design of the longitudinal beams (when these have to support
pipes), they can be estimated as a uniform load of 35% of the load of the
adjacent transverse beam.
In the pipe racks where intermediate beams are required without columns (they
are supported on longitudinal beams), the distribution of weights is not to be
done using tributary area. This is doing to the higher stiffness of the transverse
beams in the frames making them support more loads than the intermediate
beams.
The empty weight of the pipes can be estimated as 60% of the established by the
formulas in section 4.1.
Until a more accurate and definite information is obtained from the flexibility
analysis of the pipes, the following loads can be assumed:
Longitudinal:
The friction and/or anchor loads will be taken as a uniform load in every
transverse beam, equal to 10% of the operating weight of the total pipes
supported or 30% of the weight of the heavier pipe, which ever is greater. The
longitudinal connectors or struts will be designed taking these loads in to
consideration acting on every level on all frames in the structure in the same
direction.
Transverse:
The transverse anchor loads will be taken as 340 kg in each level of the frame or
5% of the total load applied in that level, which ever is greater. The load at each
level should be applied as a transverse concentrated load in all levels.
The beams that support pipes 24” diameter or greater, should be verified for the
load case of the pipe full of water, unless it has been informed that other type of
test will be performed, determined by the corresponding designer group.
For 30” diameter pipes and greater, verify with the other workgroup leaders the
possibility of decreasing the maximum number of pipes to be tested to less than
3 simultaneously, if this case is too demanding.
The transverse wind forces with the pipes empty may generate traction in
elements like columns, anchor bolts and foundations that can be determinant in
the design, so this condition should be checked.
Also the transverse wind forces with pipes in operating condition may control the
design, thus, it is necessary to include this case in the design process, unless it
is determined that the transverse seismic load is greater.
In the load combinations for the design of pipe racks the following should be
included:
Case II Test loads (pipes + equipment) + other permanent loads + live load
(on platforms, etc).
Case III Operating gravity loads (pipes + equipment) + other permanent loads
+ live loads + friction and anchor loads.
6. METHODS OF ANALYSIS
The simplification that can sometimes be done in the analysis of pipe racks is to
divide it in several plane structures as simple frames, generally moment resisting
in the transverse direction and braced in the longitudinal direction. Thus, allowing
to incorporate modifications in loading and geometry very easily (which is
frequently necessary, since the design process is usually started with preliminary
information). A three dimensional analysis would greatly increase the difficulty of
incorporating changes to the model.
The structural analysis of pipe racks, because these usually been formed by
orthogonal frames, can be simplified by reducing the structure in, generally, two
or more typical transverse frames and one or more longitudinal frames. These
are analyzed as two-dimensional structures (but are defined as three
dimensional in the computer program in order to be able to introduce out of plane
forces). The common orthogonal frame elements (columns) are loaded with the
forces from the analysis of the orthogonal frame to which they form part of, in the
corresponding load combination. Since, the longitudinal elevation includes one
column from every transverse beam, it is common practice to analyze this first
and later introduce the resulting loads in the transverse frame analysis. This is
greatly simplified when the longitudinal and transverse beams meet the columns
at the same elevation, and additionally the longitudinal frames are braced. This
configuration will result only in the addition to the transverse frame analysis the
axial loads from the longitudinal directions (no moments or shear forces are
developed from the longitudinal braced frame analysis).
7. DEFLECTIONS
The deflections of the structural elements in a pipe rack must be limited, since
the subsequent displacement of the pipes could cause large stresses and failure
of the associated equipment and its connections. These deflections if not large
enough to cause a failure they could at least cause incorrect functioning of the
plants system. Some frames in certain areas of the plant could have higher
restrictions in their deflections than others; depending on how susceptible is the
associated equipment in the area.
The most common limits used in allowable horizontal and vertical deflections,
that have controlled the design in many projects are the following:
Where,
Generally concrete beams are not slender enough to encounter the need to
use this advantage and on the other hand the spacing between pipes is
generally small enough to allow the steel beams to reach its maximum
allowable bending stress with out worrying about the un-braced length.
The “k” values used to determine the column slenderness are the ones
established in the ACI, AISC and COVENIN codes in their last editions. It
could serve as an aid in the interpretation of these codes the guides by
several authors, for example “Guide to Support Design” by C.V. Char 1979,
figure 7, k factors for frames and “T” posts.
PART VII
BUILDING ARCHITECTURE DESIGN CRITERIA
INDEX
Page
For the architectural design of buildings that form an industrial complex, the
following criteria should be evaluated and defined:
- Architectural criteria
For example: shape, function, volume, visuals, and group composition, among
others.
- Functional relations
- Visuals
Study of the best visuals toward the group or toward spaces of interest
between the buildings.
- Levels (Topography)
Study of the optimal implantation level for the buildings within the complex.
Study of the solar incidence in the building and its probable solutions and
alternatives.
It is necessary to foresee in all those buildings that have a high rate of human
occupancy, and adequate orientation, that considers the particular characteristics
of sun exposure of these latitudes.
A suggested orientation is North-East or North for all those sites that are going to
be used as offices, dinning rooms, etc. In case these orientations can not be
used, solar protection elements that are adequate and functional are
recommended.
The building should always offer the biggest facade length toward the favorable
orientation. This generates a smaller area exposed to the sun; the heat
absorption coefficient decreases and avoids the over-design of air conditioning
equipment.
All the buildings should comply with the codes established for the oil and
petrochemical industry and in special cases, specific standards established by
the client or technology that applies should be considered. At the same time,
is convenient to verify the building specifications and standards made by
MINDUR, COVENIN, and Municipals, which are adapted to the procedures,
materials, and local constructive technology.
The alternatives of using high resistance, high quality and low maintenance
material will be studied.
Each of the buildings has a specific typology, which should be reflected in its
component design, the treatment and combination of its constructive
materials.
Adequateness of some equipment within the buildings and its specific location
for maintenance purposes and services connections will be studied.
The electrical, mechanical and instrumental work groups will define the basic
requirements.
- Service requirements
Particular necessities like services and basic endowment for each building will
be verified for its functioning.
The phases that are usually followed in the architectural building design are the
following:
Conceptual Phase:
After the plot-plan definition and the final building location, the specific design for
each building will proceed starting with the design of the architectural “Base Plan”
level, with the interaction of all the work groups involved:
- Civil entrance:
The architectural work group, working in parallel with the other work groups
will define the elevations and final elevations of the building, with the general
details and other support documents, to complete the building design.
Among the most common building typologies in industrial complexes are the
following:
Generally they are reinforced concrete structures with concrete or clay blocks for
the closure, painted or wainscoted, with air conditioning systems, where the
electrical control cabinets of the different equipment and complex installations
are located.
These are buildings that have the instrumentation centers and industrial
complexes control.
The external closures shall be with concrete blocks with fine rustic wainscot and
painting.
The recommended free internal height from the false floor to the soffit should be
at least 3.10 meters in the control, computing and mechanical places, and from
2.45m to 2.50m in the other places.
The control buildings will have centralized air conditioning systems (of precision
in some cases) and internal special finishes that guarantee optimal acoustic,
lighting, cleaning and security systems, according to the special characteristics of
the equipment placed in them.
Some of its sites are: Control main room, Computer room, UPS room, Battery
room, Mechanical room, General sanitary installations, Rest rooms, Dinning
rooms and dressing rooms among others.
In general they are reinforced concrete structures with modular structural spans
according to the building specific function (offices) and with closures of concrete
and/or clay blocks of 20 cm of thickness and anodized aluminum and glass
windows.
The free height normally used between the finished floor and the soffit in these
locals is of 2.50 meters
It should be foreseen that these two works do not interfere between them and
can cohabit independently inside the same building.
They are concrete structures, with a centralized location regarding the working
places in the complexes. As in the administrative building they will have closures
of concrete and/or clay blocks of 20 cm in thickness and anodized aluminum and
glass windows.
It is convenient to define the capacities and the dinning room type to be designed
because in some cases the dinning rooms are conditioned for food preparation,
and more informal dinning rooms just for heating pre-done food, which do not
need special service installations (kitchen, refrigeration, etc.).
Some of its ambiance’s are: Showers areas, Lockers areas, Toilets. In its
design, it is convenient to differentiate between the wet (showers) and dry
(dressing rooms) areas inside the dressing rooms, for cleaning purposes.
They are usually mixed structures, of concrete (infrastructure) and/or steel, and
aluminum or cement fiber ceiling. The external closure is generally from
concrete or clay blocks, with ventilation spaces from 1.50m to guarantee
adequate internal ventilation.
1.3.7. Workshops
As the storage rooms they can be mixed structures. Sometimes a crane should
be located on top of the steel beams.
The free internal height is from 4 to 5 meters to the lower border of the crane.
Offices or workshop spaces should be left for specific instruments or electric
equipment. These spaces usually have air conditioning and free height of at least
3.10m. The workshop internal spaces should have a convenient ventilation and
lighting. Some spaces in the workshops are: Mechanical area, Instrumentation
area, Electrical area, Small piece storage room, and General deposit, among
others.
1.3.8. Laboratories
As the control room they are concrete structures with closures of concrete or clay
blocks, rustic wainscot and painting.
The minimum free height should be approximately 3 meters (in the laboratory
places) and 2.45m or 2.50m in the other ambiance.
Among the places in the laboratory we can name: Main laboratory, Sample room,
Scales’ room, Laboratory workers offices, Bathrooms, Sample storage room,
Sample drop-off room, Chemical deposit area, among others.
Generally they are concrete and/or steel structures with light ceilings in cement
fiber or aluminum. The closure will be with blocks or cement fiber sheets or light
aluminum. The adequate ventilation should be guaranteed.
As the booths, they are structures that its function is to cover minor equipment
like compressors, pumps, etc. Preferably the structure should be of steel shapes
and will not have a closure, unless it requires protection against the rain.
They are concrete structures, with closures of concrete or clay blocks and
finishes with fine rustic wainscot and painting. If they have a guarding function,
they will have security windows, air conditioning, bathrooms and deposits.
The interaction among work groups involved in the building projects start with the
conceptual phase, because the information from the other work groups toward
the architecture is a very important part of the adequate development of
alternatives and schemes, that afterwards will conduct the building detailed
design.
- Instrumentation:
- Electrical:
- Civil - Structural:
- Civil - Sanitary:
- Piping:
- Electrical:
- Civil-Structural:
Structural criterion definition for the floor levels, columns, slabs and beams.
Pre-fabricated elements definition in case they apply.
- Civil-Sanitary:
- Piping (Location)
- Civil-Structural:
- Civil-Sanitary:
1.5.1. Drawings
1.5.1.1. Levels
Lower level
They are usually done in 1:50 or 1:100 scale for better detail of the drawing.
All the rooms will be indicated in the plan, using the standard technology referred
to in the general finishes table, which could be in another drawing page or in the
same one. All the measures, internal and external elevations will be indicated
because they will be necessary for its construction.
The building elements that stand out will be indicated, as: stairs, doors, windows,
floor finishes, roof projections and important finishes
Upper Level
As in section 1.5.1.1, all the rooms, elevations and other important elements will
be shown.
It usually serves as a base plan for the luminary, diffusers/grating and others,
distribution. (It is very important to indicate its levels). The common scale for the
reflected soffit drawing is 1:50.
It usually serves for the location of the equipment, cabinets, distribution of air
conditioning through diffuser gratings, and control rooms and sub-stations
installations. The common scale for this drawing is 1:50.
It is used to define the roof slope and the grating and standpipe distribution for
the rain drainage (Civil/Sanitary work groups). The common scale for this
drawing is 1:50 (It is convenient to indicate the structural slab level and its
different borders/parapets).
1.5.1.2. Elevations
The architectural elevations show the characteristics and basic external finishes
of the building.
Some important elements locations are defined in them, as: windows, doors,
openings for equipment or cables access, floor height, and basic architectonic
finishes.
In the elevation drawings it is convenient to use all finishes and its symbols,
according to INELECTRA drawing standards; as well as to indicate all the
necessary notes for its complete understanding.
1.5.1.3. Sections
All the important elements of the section are used in them according to its
location in the architectural plan.
It is convenient to indicate all the sections internal elevations, slabs and beams
thickness, internal architectonic finishes, spaces characteristics and relevant
heights with respect to its structural components, as well as the cable entrances
and exits openings, ducts, electric trays, etc
All the internal finishes should be indicated with INELECTRA´s standard symbols
and elaborate a legend table inside the same drawing.
The detail drawings, which are commonly used in architectural projects, are the
following:
1.5.2. Documents
Descriptive Memories
A basic description of the project is given in them, explaining its most important
elements.
Specifications
Material Take-Off
The architectural material take-off will reflect the material quantities for each item
in the material bill and will be ordered according to Inelectra S.A. standard, like
its numeration and organization.
These materials for construction, in its greatest uses and common practices, with
the accomplishment of the project construction specifications and the building
characteristics table, will serve as a guide to accomplish standardized finishes,
with “heavy duty” (resistant) materials according to the building type and its use.
Some common external finishes used in industrial buildings are the following:
(It is convenient to verify the resistance to the sun loss of pigments, if the
wainscot to be used is “kenitex” or similar, and the colors should be specified,
like white, light gray, etc.)
- The final finish will be with asphalt paint aluminum color, and in the cases that
need to be walkable roofs, concrete prefabricated slabs will be placed directly
over the asphalt coat, or a “heavy duty” product for walkable terraces
according to the specifications. (Ex. Laykold, Ipa or similar heavy duty
materials).
- Doors: All the exterior doors should be made of steel, and/or template glass
according to the case. They will have enamel paint and the client or the
inspection will specify the color. The ironwork will be the heavy type for
resistant to corrosion and continued use.
- The main entrances in the maintenance and storage rooms are common to be
specified as rolling doors “Santa Maria´s” type with links of a chain and/or
sheets according to their ventilation and/or security requirements.
The thickness of the glass that they will hold will range between 4 and 8 mm.
According to the case. (Types: sliding, rocking, glass blade, fixed).
- Solar protection elements: they will be designed for the façades that need it
and that they will have direct or indirect sun according to their orientation.
These can be concrete or steel elements.
If the building exposition has West or East orientation the parasol should be
directly in front of the window in order to protect the internal ambiance from the
sun rays that fall horizontally on the façade. In case the orientation is North or
South, lateral parasols will be used on top of the windows, projected from 40
to 60 cm from the facade plan.
- Roof coverings: They will be mainly used in sheds, huts and booths. Fiber
cement sheet are recommended, generally accepted by the oil industry,
corrugated aluminum sheets type “Aceral”, “Acerolit” or “Coberib”, placed on
top of a steel structure formed by belts and truss. The asbestos-cement sheets
will be avoided in the roof.
They are rooms for human use and occupancy, for either administrative work or
for dinning, dressing or other common industrial rooms.
Floors: vinyl tiles, of ceramic, clay or granite poured on site, are the commonly
used materials for them.
Partition Walls: In aluminum structure, filled with Styrofoam and finished in panel,
or half way up glass, placed on top of a 1.00 m high railing where it is indicated.
Bathrooms: non-slipping ceramic on floors (20x20 cm) and ceramic tiles on walls
up to a 2.10 m high, mineral fiber soffit on roofs.
Baseboards: They will be made out of vinyl with 8 cm high, black or brown.
They are spaces to locate equipment that do not need special interior
conditioning. (Ex. Machinery room, mechanical room).
Walls: Flat or fine rustic wainscot and paint. (In the cases where painted blocks
are specified we will try for them to be as uniform as possible before painting).
Roofs: Flat wainscot. (If prefabricated beams are going to be used paint will be
applied directly over them, with a surface that has been previously uniformed).
They are spaces used to locate equipment with special characteristics, which
need a specific finish treatment.
(Ex. Battery room, control centers, motor control room, main and local electrical
sub-station).
Floors: In control rooms false modular floor will be used in 60x60 cm reticule and
the heights ranging between 45 and 60 cm (anti-dust paint in whole cable
basement).
In battery room: depending on the type of battery to be installed and to its content
(acid, base) epoxy paint will be used, chloride rubber or anti-acid tiles with anti-
acid mortar.
In Sub-stations: concrete floor with hardener will be used and/or granite poured
on site.
Walls: In control rooms and sub-stations: flat wainscot with rubber paint and
transparent polyurethane final finish (anti-dust surface). In battery room: epoxy
paint, chloride rubber or anti-acid ceramic tiles. (Depending of the type of battery
to be used).
Roofs: In control rooms: mineral fiber soffit. In battery rooms: chloride rubber or
epoxy paint. In sub-stations: rubber paint with transparent polyurethane finish.
PART VIII
SANITARY INSTALLATIONS DESIGN CRITERIA
INDEX
Page
1. GENERAL 103
1.1 Scope 103
1.2 Language 103
1.3 Measuring Units 103
1.4 Standards 103
3. DESIGN 105
3.1 Design Parameter 105
3.2 Supply Estimation 105
3.3 Flow units 105
3.4 Loss Pressure 105
1. GENERAL
1.1 Scope
The purpose of the present document is to describe the methodology and the
design criteria to be used for the sanitary installations in the Metor Expansion
plant project.
1.2 Language
All drawings title, building finish material in general drawings and notes will be
written in English.
1.4 Standards
This system takes advantage of the pressure that offers the service distribution
system by INOS, and it guarantees the constant static pressure service for
buildings not higher of three (3) stories.
The differences between the System described above and this one is that it does
not guarantee the constant supply or service pressure, so it requires a storage
reservoir for such purpose.
3. DESIGN
In the design for the supply of potable water system, the following factors will
have to be previously considered to proceed with the calculation of the
distribution system for the building: The water supply in lt./day for the building,
the addition of the flows units, by sanitary piece according to the design or
diagram of distribution, the determination of the probable flow for each bay and
the calculation of the pressure loss by friction will be determined according to
what the Official Journal of the Republic of Venezuela (Gaceta Oficial de la
República de Venezuela), Extraordinary issue N°. 4.044, September 8 1988,
Chapters VII to XXI, establishes.
The supply will be set according to the buildings destination use and will be
calculated according to the established by the Official Journal of the Republic of
Venezuela (Gaceta Oficial de la República de Venezuela), Extraordinary issue
N°. 4.044, September 8 1988, Chapter VII.
This method for calculating the potable water distribution system consists in
assigning to each sanitary piece a unit number pre-established in function of the
real flow. In base of the total number of units of a joint the probable supply of the
joint is determined considering the probability of the simultaneous use of the
pieces.
Once the probable flow is obtained, the diameters of the pipes will be assigned
based on a velocity that oscillates between 0,60 and 3 m/s for pressure pipe.
With the probable supply and the diameters assigned, the loss of pressure will be
calculated and will determine the residual pressures of each sanitary piece.
Checking the requirements with the pressures required for the convenient
function of each piece, the diameters will be increased or decreased until the
residual pressure obtained and it will guarantee the convenient functioning of the
system.
L V2
hf (m) = f ⋅ ⋅
D 2g
Where:
V = velocity in m/s.
L = piping longitude in m.
D = interior diameter in mm.
g = gravity acceleration 9.81 m/s².
f = friction factor.
hf = friction loss in m.
For the determination of the diameter the Hazen Williams formula will be used:
1756,574 ⋅ Q n
J ( m) = ,
C n ⋅ D 4,87
hf(m)=J x L
The distribution of the service supply will be by gravity using the Manning formula
according to the flow:
1
Q(l / s ) = ⋅ A ⋅ R 2 / 3 ⋅ So1 / 2
n
The roughness coefficient (n) varies according to the type of the pipe material
according to the following values:
Material "n"
PVC 0,012
Galvanized steel 0,012
Copper 0,012
It is recommended for gravity piping a velocity between 0,90 and 1,80 m/s.
- Choose the most unfavorable piece and add it to the value obtained from
the loss head, the residual pressure that is necessary to maintain, being
the minimal pressure of 7 m and a maximum of 14 m depending of the
sanitary piece type (valve or a tank).
Where:
Pump power
Q ⋅ Hb
P( pump ) =
75 ⋅ E
Q (lt./s) = N°. of Pieces to serve. x K (Only valid for the Peerles method).
Q = Flow (lt./s)
Depending of the case flow, the pumping will be calculated by the method of
probable flow (Hunter method) chapter XIII of the Official Journal of the Republic
of Venezuela (Gaceta Oficial de la República de Venezuela), Extraordinary issue
N°. 4.044, September 8, 1988 or by the Peerles pump division method.
Where:
Motor power:
PM (HP) = 1, 44 P (pump)
0,90 ⋅ ΔP
ΔV =
Min.Vol.Water + PMIN + ΔP
900 ⋅ Q(lt / s )
TankCapacity ( galon) =
N ⋅ ΔV
Where:
With the value of the capacity of the tank, the dimensions of the pressure of the
tank can be selected.
C.F .M ⋅ Pmax
Power( hp ) =
0,75 ⋅ 85
It is considered sewage water, those that have been used for domestic purpose
coming from the shower, washbasin, kitchen sinks, cleaning, etc, considering
that its volume is approximately equal to the potable water destined for the
edification.
8. SYSTEM TYPE
According to the Sanitary Standards a separate system will be considered for the
conduction of the sewage waters without including the conduction of the
rainwater.
A calculation sheet will be used for the sewage waters (discharge units) with the
purpose to control the discharge units that will be incorporated to the principal
branch of the system.
For the horizontal stack, it shall be considered the number of units that the pipe
will discharge through the Table N° 42 of the Official Journal of the Republic of
Venezuela (Gaceta Oficial de la República de Venezuela), Extraordinary issue
N°. 4.044, September 8, 1988, indicates these values.
It must be mentioned that the loosen gases from the sewage waters shall be
extracted to impede that these invade the vital atmospheres of the building, for
this reason the efficient and economic way to carry it out, is using a hydraulic
seal in each entrance of the system. This consists on the installation of a siphon
in each of sanitary pieces that needed one. This mechanism is a tube in form of
"U" where the water is stored in the bottom impeding the pass of the gases and
smells.
If the sewage water generated in the building is under the level of the street,
these will be conduced by gravity to a sewage water tank. These waters will be
pumped to a break head catch basin, integrating this flow of sewage waters to
the final system or device designed for such purpose. (see chapter XXX of the
Official Journal of the Republic of Venezuela (Gaceta Oficial de la República de
Venezuela), Extraordinary issue N°. 4.044, September 8, 1988).
Retention Time
The retention time is checked for the minimum volume of the catch basin, with
the maximal flow generated by the discharge units in the building and the volume
that is obtained for a maximum retention time of 30 minutes.
VTank = QAN x TR
Pump Height
Pump Power
Qb ⋅ H b
Pb( HP) =
45
1145-01-90-C01-TEC-001 REV-0 05/03/2007 111 de 117 INE-DOCUMENTO
METOR EXPANSION PROJECT
Motor Power
Qb⋅ H b
Pb( HP) =
45
PM (HP) = 1, 44 x Pb
The water seal of all sanitary pieces will have to be protected against siphonage.
We can accomplish this by the adequate use of ventilation branches,
guaranteeing atmospheric pressure all the time. The different types of ventilation
commonly used are: individual ventilation, ventilation as a whole, humid
ventilation or a combination of these. (See chapter XXVI of the Official Journal of
the Republic of Venezuela (Gaceta Oficial de la República de Venezuela),
Extraordinary issue N°. 4.044, September 8 1988, Table N° 44 and 45).
Each sanitary piece will be provided with a ventilation branch, but for different
reasons, of space or architectural design sometimes it is not possible to install a
branch for each siphon. However, those sanitary pieces that, for its form of
discharge are exposed to the autosiphonage, or that have a violent discharge
must be supplied with individual ventilation.
This case is when several pieces are connected directly or at a short distance to
a common horizontal collector, making use of this way to connect the ventilation
branch to the utmost of the collector. This method is preferably used when there
is a sanitary piece battery of the same type.
12.1 Scope
The disposition of the sewage waters effluents of the buildings will be made in
accordance with the availability of an existent infrastructure or with the
construction of a structure that is approved according to the characteristics of the
Project.
The system works in atmospheric pressure with a constant slope from branch to
branch, locating a manhole in each point where the slope or the direction of the
branch changes. This is done according to the "Normas e Instructivos para
Proyecto de Alcantarillado" INOS 1989.
This system is used when a sewage water disposition system does not exist or
when the waters are of industrial type and require special treatment
14.1 Scope
The water arising of the rainfalls will be collected and driven to the existent
drainage system. In the case that this mechanism does not exist the waters will
be drained freely toward the zones of the natural drainage (rivers) or to the
sumps in the street. Since most of the rainwater comes from the roofs, flat roofs
and patios is important to design the conduction mechanisms that has an
adequate final disposition system having to be capable of functioning for any
duration of the rainfall.
14.2 Design
R 2 / 3 ⋅ So1/ 2
V ( m / s) = ;
n
Q (lt./s) = V x A
Where,
Comparing this design capacity with the real flow that it is considered, we are
able to determine if the slopes and the diameters selected are enough and
adequate.
For the calculation of the real flow the following rational method formula will be
used:
Where, Q = C ⋅ I ⋅ A (lt / s )
360
The return period for the estimation of the design rain will depend on the return
period of the zone in the building area. It is recommended to use a 5-year return
period and 10 minutes of concentration time, if there is no data available.
In the case that there is an existing system for the disposition of the rain waters
they will be discharged in it, all waters arising from roofs, paved and unpaved
green areas that are located in the adjacencies of the buildings in the project. In
the case of being necessary to discharge to a stream of water, the disposal must
comply previously with what is stipulated in the environmental standards. If none
of the previously mentioned alternatives are possible, a particular system
drainage for rain water must be developed and will be ruled by the Normas e
Instructivos para el Proyecto de Alcantarillado INOS 1989.
ATTACHMENTS
ATTACHMENT “A”
ANCHOR BOLTS SIZING
C31GU031/6/14/01/mrp/SP 3 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
3. DISTANCIAS AL BORDE
C31GU031/6/14/01/mrp/SP 4 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
4. DETALLES TIPICOS
C31GU031/6/14/01/mrp/SP 5 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
DETALLES TIPICOS
C31GU031/6/14/01/mrp/SP 6 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
DETALLES TIPICOS
C31GU031/6/14/01/mrp/SP 7 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
DETALLES TIPICOS
C31GU031/6/14/01/mrp/SP 8 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
TABLA N°1
C31GU031/6/14/01/mrp/SP 9 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
6. NOTAS GENERALES
6.1 El espesor de las camisas de acero será el mínimo comercial y la tolerancia en diámetro
(Ext.) será + 0 y - 10 mm.
C31GU031/6/14/01/mrp/SP 10 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
En el peso de los pernos JN1 se incluye el peso de una arandela y una tuerca.
PESO ARANDELA PESO PESO TOTAL DE PERNOS (kg)
DIAMETRO L BARRA SIMPLE TUERCA JN1
pulg mm mm (kg/mm) (kg) (kg) P=75 P=110 P=150 P=200
3/8" 10 180 0.0006 0.0032 0.0115 0.172 0.194 0.218 0.249
1/2" 12 225 0.0009 0.0081 0.0169 0.291 0.322 0.358 0.402
5/8" 16 330 0.0016 0.0124 0.0329 0.685 0.740 0.803 0.882
3/4" 20 405 0.0025 0.0203 0.0633 1.267 1.354 1.452 1.576
7/8" 22 480 0.0030 0.0295 0.0766 1.762 1.867 1.986 2.135
1" 25 560 0.0039 0.0371 0.1080 2.592 2.727 2.881 3.074
1 1/4" 32 710 0.0063 0.0726 0.2850 5.314 5.535 5.787 6.103
1 1/2" 38 875 0.0089 0.1060 0.4950 9.059 9.370 9.726 10.172
1 3/4" 44 1015 0.0119 0.2269 0.7900 14.027 14.445 14.923 15.519
2" 50 1170 0.0154 0.2860 1.1900 20.666 21.205 21.822 22.592
2 1/4" 57 1360 0.0200 0.3762 1.4200 30.541 31.242 32.044 33.045
2 1/2" 64 1550 0.0253 0.4358 1.9500 43.423 44.306 45.317 46.579
3" 76 1780 0.0356 0.5874 4.2700 70.916 72.163 73.587 75.368
En el peso de los pernos JN2 se incluye el peso de una arandela y dos tuercas.
C31GU031/6/14/01/mrp/SP 11 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
En el peso de los pernos JA1 se incluye el peso de la camisa de acero, la placa cuadrada,
y el peso de una randela y de una tuerca en la proyección.
C31GU031/6/14/01/mrp/SP 12 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
En el peso de los pernos IN1 se incluye el peso de la tuerca, la placa cuadrada; y una
arandela y una tuerca en la proyección.
En el peso de los pernos IN2 se incluye el peso de una tuerca, la placa cuadrada; y de
una arandela y dos tuercas en la proyección.
C31GU031/6/14/01/mrp/SP 13 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
En el peso de los pernos IA2 se incluye el peso de la tuerca, la placa cuadrada, la camisa
de acero y una arandela y una arandela y una tuerca en la proyección.
En el peso de los pernos IA2 se incluye el peso de la tuerca, la placa cuadrada, la camisa
de acero; y una arandela y dos tuercas en la proyección.
PESO ARANDELA PESO PESO PESO PESO TOTAL DE PERNOS (kg)
DIAMETRO H BARRA SIMPLE TUERCA PLACA CAMISA IA2
pulg mm mm (kg/mm) (kg) (kg) (kg) (kg) P=75 P=110 P=150 P=200
1/2" 12 180 0.0009 0.0081 0.0169 0.4239 0.3062 1.015 1.046 1.082 1.126
5/8" 16 240 0.0016 0.0124 0.0329 0.7290 0.4155 1.753 1.808 1.871 1.950
3/4" 20 240 0.0025 0.0203 0.0633 0.7132 0.4155 2.116 2.202 2.301 2.424
7/8" 22 255 0.0030 0.0295 0.0766 1.1644 0.4155 2.824 2.928 3.048 3.197
1" 25 355 0.0039 0.0371 0.1080 1.4287 1.2892 4.736 4.871 5.025 5.218
1 1/4" 32 355 0.0063 0.0726 0.2850 2.2608 1.2892 7.192 7.413 7.666 7.982
1 1/2" 38 495 0.0089 0.1060 0.4950 4.0694 2.7843 13.519 13.831 14.187 14.632
1 3/4" 44 505 0.0119 0.2269 0.7900 5.5580 2.7843 17.862 18.280 18.757 19.354
2" 50 610 0.0154 0.2860 1.1900 8.7076 3.4030 26.525 27.064 27.681 28.452
2 1/4" 57 620 0.0200 0.3762 1.4200 14.7659 3.4030 36.727 37.428 38.229 39.231
2 1/2" 64 790 0.0253 0.4358 1.9500 18.2155 7.7063 54.052 54.936 55.946 57.208
3" 76 815 0.0356 0.5874 4.2700 29.5879 7.7063 82.386 83.632 85.056 86.837
C31GU031/6/14/01/mrp/SP 14 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
En el peso de los pernos HN1 se incluye el peso de la tuerca y placa cuadrada; y de una
arandela y una tuerca en la proyección.
C31GU031/6/14/01/mrp/SP 15 de 17 IN-0038MSW/13/Sep.99.R4C
inelectra INEDON
903-3050-C31-GUD-031
DEPARTAMENTO DE INGENIERIA CIVIL
Rev. 3
PERNOS DE ANCLAJE NORMALIZADOS DIMENSIONAMIENTO
C31GU031/6/14/01/mrp/SP 16 de 17 IN-0038MSW/13/Sep.99.R4C