Beruflich Dokumente
Kultur Dokumente
PROJECT MANUAL
MASTER
NEW BUILD
MARRIOTT INTERNATIONAL
Design & Construction Services
Table of Contents
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Project Description
2. Definitions
3. Quality Assurance
4. Contractor Use of Premises
5. Bidding Classification
6. Contracts
7. Owner Furnished Products
8. Owner Provided Work
9. Sample Room
10. Allowances
1.02 PROJECT DESCRIPTION
A. Work of this Contract comprises the general construction required for [a new] TownePlace
Suites by Marriott hotel, in city and state as indicated on the Project Manual cover.
B. The Work includes, but is not limited to site, structural, architectural, plumbing, mechanical,
and electrical systems. It also includes installation of furniture, fixtures and equipment
(FF&E).
C. The work of this Project is shown on the Drawings and described in the various Sections of
the Specification.
D. The Drawings and Specifications are complementary and what is required by any one shall be
as binding as if required by all.
E. The Project consists of the following:
1. New construction of a [4]- story [wood frame] hotel consisting of [ 102 ] Guest Suites with
support functions.
2. All new site improvements including parking, walks, landscaping, on-site utility services
and tie-ins.
3. [Indoor] pool
1.03 DEFINITIONS
A. Furnish: Purchase and deliver to project site, ready for installation.
B. Install: Unpack, assemble, set in final position, fasten in place, make final connections, clean,
adjust, and leave ready for use.
C. Provide: Furnish and install.
D. Receive: Accepting a delivery.
E. Final Connections: Complete plumbing, mechanical, and electrical connections as required
and recommended by manufacturer for optimum operation of equipment.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Revision Log
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Contract Modification Procedures:
a. Submittals
b. Documentation of Change in Contract Sum and Contract Time
2. Contract Modification Pricing Guidelines
3. Requests for Information and Supplemental Instructions
4. Change of Contract Procedures
5. Allowances
6. Construction Change Directive
7. Change of Contract:
a. Stipulated price change order
b. Unit price change order
c. Time and material change order
d. Execution of Change of Contract written orders
8. Correlation of Contractor Submittals
B. Related Sections:
1. Agreement: Monetary values of established unit prices and percentage allowances for
Contractor's overhead and profit.
2. Section 01 33 00 (01330) - Submittals and Substitutions: Construction Progress
Schedules and miscellaneous submittals.
3. Section 01 60 00 (01600) - Material and Equipment: Product options and substitutions.
4. Section 01 77 00 (01770) - Contract Closeout: Project Record Documents.
4.02 SUBMITTALS
A. Submit name of the individual authorized to receive change documents, and be responsible
for informing others in Contractor's employ and Subcontractors of changes to the Work.
B. Change of Contract Forms: Furnished by Owner
4.03 DOCUMENTATION OF CHANGE IN CONTRACT SUM AND CONTRACT TIME
A. Maintain detailed records of work performed on a time and material basis. Provide full
information required for evaluation of proposed changes, and to substantiate costs of changes
in the Work.
B. Document each quotation for a change in cost or time with sufficient data to allow evaluation
of the quotation.
C. On request, provide additional data to support computations:
1. Quantities of products, labor, and equipment.
PART 5 PRODUCTS
Not Used
PART 6 EXECUTION
Not Used
To From
INFORMATION - RFI Co. Co.
Requested by:
Architect's Supplemental
Instructions:
Attachments:
Reply By:
The Work shall be carried out in accordance with these supplemental instructions issued in accordance with the Contract Documents without change in Contract
Sum or Contract Time. Prior to proceeding with these instructions, indicate acceptance of these instructions below Work as consistent with the Contract
Documents and return a copy to the Architect.
By: By:
Architect Date Contractor Date
END OF SECTION
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 8 ▪
REVISED: 01/01/13 FILE: Division 01 General Conditions
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Coordination
2. Administrative Procedures
3. Meetings:
a. Pre-construction Meetings
b. Progress Meetings
c. Preinstallation Meetings
4. Coordination Drawings
5. General Installation Provisions
6. Cleaning and Protection
B. Related Sections:
1. Section 01 71 23 (01720) - Field Engineering
2. Section 01 73 29 (01730) - Cutting and Patching
7.02 COORDINATION:
A. Coordinate construction activities included in various Sections of these Specifications to
assure efficient and orderly installation of each component. Coordinate construction
operations included under different Sections that depend on each other for proper installation,
connection, and operation.
B. Where installation of one component depends on installation of other components before or
after its own installation, schedule activities in the sequence required to obtain the best
results.
C. Coordinate installation of different components to assure maximum accessibility for
maintenance, service and repair.
D. Verify utility requirements and characteristics of operating equipment are compatible with
building utilities. Coordinate work of various sections having interdependent responsibilities for
installing, connecting to, and placing in service, such equipment.
E. Coordinate space requirements and installation of mechanical and electrical work which are
indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit,
as closely as practicable; place runs parallel with line of building. Utilize spaces efficiently to
maximize accessibility for other installations, for maintenance, and for repairs.
F. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the
construction. Coordinate locations of fixtures and outlets with finish elements.
G. Coordinate completion and clean up of Work of separate sections in preparation for
Substantial Completion and for portions of Work designated for Owner's partial occupancy.
H. After Owner occupancy of premises, coordinate access to site for correction of defective Work
and Work not in accordance with Contract Documents, to minimize disruption of Owner's
activities.
PART 8 PRODUCTS
Not Used
PART 9 EXECUTION
9.01 INSPECTION OF CONDITIONS:
A. The installer of each component shall inspect the substrate and conditions under which work
is performed. Do not proceed until unsatisfactory conditions have been corrected.
B. Verification of Conditions:
1. Verify that existing conditions, surfaces, and substrates are acceptable for subsequent
Work.
2. Verify that field measurements, are as required to receive subsequent Work.
3. Verify that existing substrate is capable of structural attachment of new Work being
applied or attached.
4. Examine and verify specific conditions described in individual specification sections.
END OF SECTION
Revision Log
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Wherever possible throughout the Contract Documents, the minimum acceptable quality
of workmanship and materials has been defined either by manufacturer's name and
catalog number or reference to recognized industry standards.
2. To ensure that the specified products are furnished and installed in accordance with the
design intent, procedures have been established for advance submittal of design data for
its review and approval or rejection by the [Architect]
3. This Section specifies administrative and procedural requirements for submittals required
for performance of the work, including:
a. Contractor's Progress Schedule
b. Shop Drawings, Product Data, and Samples
c. Letters of Conformance
d. Certificates
e. Manufacturer Installation Instructions
4. Substitution Procedures
5. Manuals
6. Miscellaneous Submittals
B. Related Documents:
1. Letter of Conformance Form
2. Contractor’s Substitution Request Form
C. Related Sections:
1. Contractual Requirements for Submittals: General Conditions
a. Two (2) copies of all Submittals, plus number of copies to be returned to Contractor,
shall be submitted unless otherwise specified.
b. Provide additional copies as required for use in Project Record Documents.
2. Section 01 77 00 (01770) - Contract Closeout
3. Individual Submittals Required: Pertinent Sections of these Specifications.
10.02 SUBMITTALS
A. Coordination: Coordinate preparation and processing of Submittals with performance of
construction activities. Transmit each Submittal sufficiently in advance of performance of
related construction activities to avoid delay.
1. Coordinate each Submittal with fabrication, purchasing, testing, delivery, other Submittals
and related activities that require sequential activity.
PART 11 PRODUCTS
11.01 SUBSTITUTIONS
A. Source Limitations: To the greatest extent possible for each unit of work, provide products,
materials, or equipment of a singular generic kind from a single source.
PART 12 EXECUTION
12.01 COORDINATION OF SUBMITTALS
A. General: Prior to submittal for Architect's review, use all means necessary to fully coordinate
all material, including the following:
1. Secure all necessary approvals from public agencies and others. Signify by stamp or
other means that all required approvals have been obtained.
2. Clearly indicate all deviations from the Contract Documents.
B. The General Contractor shall submit a prioritized tabulation by date of Submittals required
during the first 90 days of construction. List those Submittals required to maintain orderly
progress of the work, and those required early because of long lead time for manufacture or
fabrication.
1. These dates may be shown on Construction Project Schedule at Contractor's option.
12.02 TIMING OF SUBMITTALS
A. General
1. Make all Submittals enough in advance of scheduled dates for installation to provide all
required time for reviews for securing necessary approvals, for possible revision and
Resubmittals, and for placing orders and securing delivery.
CONTRACTOR:
The following product(s) has been selected for use in the above referenced project from the list of
specified items.
Statement of Conformance:
This Letter of Conformance is provided as a Submittal for Information in accordance with Section
01 33 00 - Submittals and Substitutions. The undersigned hereby declares that the Product identified
above by manufacturer's name and model number is (one of) the product(s) specified and is suitable
for the intended use as defined within the Contract Documents and will be provided and placed in
operational condition in accordance with the manufacturer's published instructions and the Contract
Documents.
SUBCONTRACTOR/SUPPLIER:
Phone Number: ( )
(Contact name of subcontractor/supplier offering above product)
CONTRACTOR:
TO: [Architect]
Phone: Fax:
SPECIFIED ITEM:
Section: Page: Paragraph: Description:
Drawing Number(s): Detail Number(s):
The undersigned request consideration of the following:
PROPOSED SUBSTITUTION:
The undersigned certifies that the following paragraphs, unless modified by attachments, are correct:
1. Proposed substitution has been fully checked and coordinated with the Contract Documents.
2. The proposed substitution does not affect dimensions shown on Drawings.
3. The proposed substitution does not require revisions to mechanical or electrical work.
4. The undersigned will pay for changes to the building design, including architectural and engineering design, detailing,
and construction costs caused by the requested substitution.
5. The proposed substitution will have no adverse affect on other trades, the construction schedule, or specified warranty
requirements.
6. Maintenance and service parts will be locally available for the proposed substitution.
7. The proposed substitution will have no adverse effect on LEED credits established through the CFRST LEED Volume
Program. (Applies to CFRST LEED Volume Program Projects ONLY)
The undersigned further states that the function, appearance, and quality of the proposed substitution are equivalent or superior
to the specified item.
Attachments: The attached data is furnished herewith for evaluation of the proposed substitution.
Catalog Drawings Samples Reports Tests Other:
Submitted by:
For use by the Architect: Accepted Accepted as Noted Rejected: Submit Specified Item
BY:
(Authorized Signature)
Date: Remarks:
PART 13 GENERAL
13.01 SUMMARY
A. Section Includes:
1. These Special Requirements contain changes and additions to the General Conditions
and other Contract Documents. Where any Article or paragraph is modified or voided by
these Special Requirements, the unaltered provisions shall remain in effect. In any case
of conflict, these Special Requirements shall prevail.
B. Related Documents:
1. Drawings and Articles of the Contract, including General and Supplementary Conditions
and Division 01 Specification Sections, apply to work of this Section.
2. All Contractors shall be governed by all applicable Sections of these Documents with
reference to their respective areas of work. It shall be the responsibility of the General
Contractor to apprise its Subcontractors and suppliers of these requirements.
a. The Contractor and each Subcontractor shall review all Sections of the
Specifications and all Drawings and are responsible for all work pertaining to their
trade regardless of Drawing or Section of Specifications it is written in.
13.02 GENERAL
A. The Contractor and each Subcontractor affirmatively represents that they are skilled and
experienced in the performance of work as required by this project and in the use and
interpretation of Drawings and Specifications such as those included in the Contract
Documents; that they have carefully reviewed the Drawings and Specifications of this project;
and that their Contract is based solely on these Documents, not relying in any way on any
explanation or interpretations - oral or written - from any other source. The Contractor agrees
that it shall be conclusively presumed that the Contractor has exercised his aforementioned
skill and experience and found the Drawings and Specifications sufficient and free from
ambiguities, errors, or omissions for the purpose of determining its Contract for the
performance of the work in conformity with the Drawings, Specifications, and all other Contract
Documents.
1. The Contractor and each Subcontractor further represents that they have visited the site
and correlated their observations of existing conditions with the requirements of the
Contract Documents.
B. Each Contractor shall provide sufficient and adequate labor, materials and construction
equipment necessary to properly correlate all phases of the work to the end that the approved
Progress Schedule can be adhered to and the Substantial Completion Date met.
C. Each Contractor is responsible for all necessary development of the work to fulfill the intent of
the Contract Documents for a complete and/or functioning system whether totally defined by
the Drawings and Specifications or not.
D. In no case shall any Contractor proceed with work in uncertainty.
13.03 COMMUNICATIONS
A. The Contractor shall forward all communications to the Owner through the [Owner’s
Representative].
B. Request for Information (RFI) and Supplemental Instructions
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 48 ▪
REVISED: 01/01/13 FILE: Division 01 General Conditions
PART 14 PRODUCTS
Not Used
PART 15 EXECUTION
Not Used
END OF SECTION
Revision Log
PART 16 GENERAL
16.01 SUMMARY
A. Section Includes:
1. Reference Standards
16.02 QUALITY ASSURANCE
A. Conflicting Requirements: Where compliance with two or more standards is specified and the
standards establish different or conflicting requirements for minimum quantities or quality
levels, comply with the most stringent requirement. Refer uncertainties and requirements that
are different, but apparently equal, to the Architect for a decision before proceeding.
1. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified
shall be the minimum provided or performed. The actual installation may comply exactly
with the minimum quantity or quality specified, or it may exceed the minimum with
reasonable limits. To comply with these requirements, indicated numeric values are
minimum or maximum, as appropriate, for the context of the requirements. Refer
uncertainties to the [Architect] for a decision before proceeding.
16.03 INDUSTRY STANDARDS
A. Reference Standards
1. Conform with the provisions or standards referenced in the sections of the Specifications
with the same force and effect as if the Standards referenced were bound or copied
directly into the section, except that:
a. Conform with more stringent provisions when contained elsewhere in the Contract
Documents; and
b. Conform with the more stringent provision when two or more Standards are
referenced; and
c. Conform with the more stringent provision when the Standard referenced and the
governing regulations differ unless the governing regulation require conformance to
the less stringent provision without exception.
2. Submit for clarification and conform to the decision of the Architect when the Standard
referenced:
a. Presents options which have not specifically been selected in the Contract
Documents; or
b. Contain provisions which conflict with other provisions in the Contract Documents; or
c. It is uncertain or not clear which of differing provisions is the more stringent.
3. Conform to the provisions of the most recent issue of the Standard referenced as of the
date of the Contract Documents.
B. Abbreviations and Acronyms of Organizations
1. Abbreviations and Names: Trade association names and titles of general standards are
frequently abbreviated. Where abbreviations and acronyms are used in the
Specifications or other Contract Documents, they mean the recognized name of the trade
association, standards-producing organization, authorities having jurisdiction, or other
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 52 ▪
REVISED: 01/01/13 FILE: Division 01 General Conditions
AMCA Air Movement and Control Association International, Inc. (847) 394-0150
30 W. University Dr. www.amca.org
Arlington Heights, IL 60004-1893
NEMA The Association of and Medical Imaging Equipment Manufacturers (703) 841-3200
1300 N 17th St., Suite 1752 www.nema.org
Rosslyn, VA 22209
NTMA The National Terrazzo & Mosaic Association, Inc. (800) 323-9736
201 North Maple, Suite 208 www.ntma.com
Purcellville, VA 20132
PART 17 PRODUCTS
Not Used
PART 18 EXECUTION
Not Used
END OF SECTION
PART 19 GENERAL
19.01 SUMMARY
A. Section Includes:
1. References
2. Quality Assurance
a. Testing Laboratory Qualifications
b. Control of Installation
3. Tolerances
4. Inspection and Testing Laboratory Services
5. Manufacturers' Field Services and Reports
B. Related Sections:
1. Information Available to Bidders: Soil investigation data.
2. General Conditions: Inspections, testing, and approvals required by public authorities.
3. Section 01 33 00 (01330) - Submittals and Substitutions: Submission of manufacturers'
instructions and certificates.
4. Section 01 60 00 (01600) - Material and Equipment: Requirements for material and
product quality.
5. Section 01 77 00 (01770) - Contract Closeout: Project Record Documents.
6. Individual Specification Sections: Inspections and tests required, and standards for
testing.
19.02 REFERENCES
A. For products or workmanship specified by association, trade, or other consensus standards,
comply with requirements of the standard, except when more rigid requirements are specified
or are required by applicable codes.
PART 20 PRODUCTS
Not Used
PART 21 EXECUTION
Not Used
END OF SECTION
Revision Log
PART 22 GENERAL
22.01 SUMMARY
A. Section Includes:
1. This Section specifies temporary services and facilities, including utilities, construction
and support facilities, security and protection. Provide facilities ready for use. Maintain,
expand and modify as needed. Remove when no longer needed, or when replaced by
permanent facilities.
2. Work of this Section shall include, but not necessarily be limited to, the following:
a. Project/Site Conditions
b. Use Charges
c. Field Office and Storage Sheds
d. Temporary Sanitary Facilities
e. Temporary Fire Extinguishers
f. Temporary Water
g. Temporary Electric Power Service and Interior Lighting
h. Temporary Telephone Service and Facsimile Service
i. Temporary Storm and Sanitary Sewer
j. Temporary Heating, Cooling, and Ventilation
k. Temporary Paving
l. Temporary Enclosures
m. Project Identification
n. Temporary Exterior Lighting
o. Progress Cleaning and Waste Removal
p. Surface and Underground Water Control
q. Protection of Installed Work
1) Environmental Protection
2) Dust Control
3) Barriers, Barricades, Warning Signs, and Lights
r. Removal of Construction Facilities and Temporary Controls
B. Related Sections:
1. Section 01 35 00.01 (01000) - Special Requirements
2. Section 01 11 00 (01110) - Summary of Work
3. Section 01 56 16 – Temporary Dust Protection
4. Section 01 74 00 (01740) - Cleaning and Waste Management
PART 23 PRODUCTS
23.01 MATERIALS
A. General: Provide new materials; if acceptable to the [Owner’s Representative], undamaged
previously used materials in serviceable condition may be used. Provide materials suitable for
the use intended.
B. Lumber and Plywood: Comply with requirements in Section 06 10 00 - Rough Carpentry.
PART 24 EXECUTION
24.01 INSTALLATION
A. Use qualified personnel for installation of temporary facilities. Locate facilities where they
serve the project adequately and result in minimum interference with performance of the work.
Relocate and modify facilities as required.
B. Provide each facility ready for use when needed to avoid delay. Maintain and modify as
required. Do not remove until facilities are not longer needed, or are replaced by authorized
24.02 TEMPORARY UTILITY INSTALLATION
A. General: Engage the appropriate local utility company to install temporary service. Where the
company provides only part of the service, provide the remainder with matching, compatible
materials and equipment; comply with the company's recommendations.
1. Obtain easements to bring temporary utilities to the site, where the Owner's easements
cannot be used for that purpose.
B. Water Service:
1. Install water service connected to nearest system, and distribution piping of sizes and
pressures adequate for construction until permanent water service is in use.
2. Sterilization: Sterilize temporary water piping prior to use.
3. The Contractor shall remove temporary water service at the completion of the Project.
C. Temporary Electric Power Service: Provide weatherproof, grounded electric power service
and distribution system of sufficient size, capacity, and power characteristics during
construction period. Include meters, transformers, overload protected disconnects, automatic
ground-fault interrupters and main distribution switch gear.
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 76 ▪
REVISED: 01/01/13 FILE: Division 01 General Conditions
END OF SECTION
Revision Log
PART 25 GENERAL
25.01 SUMMARY
A. Section Includes:
1. The Contractor shall provide and maintain at the site one project sign.
2. No other signs or advertisements will be allowed to be displayed on the premises.
25.02 QUALITY ASSURANCE
A. Design sign and structure to withstand 50 mph wind velocity.
B. Sign Painter: Engaged as professional sign painter for not less than three years.
C. Finishes, Painting: Adequate to withstand weathering, fading, and chipping for duration of
construction.
PART 26 PRODUCTS
26.01 MATERIALS
A. Structure and Framing: New wood, 4' x 4' x 8' treated posts, structurally adequate.
B. Sign Mounting Board: 4' x 8', exterior grade, GPX yellow or green plywood with medium
density overlay, minimum 3/4 inch thick.
C. Rough Hardware: Galvanized, aluminum or brass.
D. Paint and Primers: Exterior quality, two coats. Color to be White.
E. Vinyl sign to be provided by Owner and installed by Contractor.
PART 27 EXECUTION
27.01 CONSTRUCTION
A. Install project identification sign within 30 days after date fixed by Owner-Contractor Contract.
B. Erect at designated location as directed by [Architect] [Owner’s Representative].
C. Erect supports and framing with uprights 36 inches below surface, braced and framed to resist
wind loadings.
D. Install sign surface plumb and level, with butt joints. Anchor securely.
E. Paint sight-exposed surfaces of sign, supports, and framing.
27.02 MAINTENANCE
A. Maintain signs and supports clean. Repair deterioration and damages.
END OF SECTION
Revision Log
PART 28 GENERAL
28.01 SUMMARY
A. Section Includes:
1. Products
2. Transportation and Handling
3. Storage and Protection
4. General Product Requirements
B. Related Sections:
1. Section 01 33 00 (01330) - Submittals and Substitutions
2. Section 01 45 00 (01450) - Quality Control: Product quality monitoring.
28.02 QUALITY ASSURANCE
A. Do not use materials and equipment removed from existing premises, except as specifically
permitted by the Contract Documents.
B. Provide interchangeable components of the same manufacturer, for components being
replaced.
28.03 PRODUCT DELIVERY AND HANDLING
A. Transport and handle products in accordance with manufacturer's instructions.
B. Promptly inspect shipments to ensure that Products comply with requirements, quantities are
correct, and Products are undamaged.
C. Provide equipment and personnel to handle Products by methods to prevent soiling,
disfigurement, or damage.
28.04 STORAGE AND PROTECTION
A. Store and protect Products in accordance with manufacturers' instructions, with seals and
labels intact and legible.
B. Store sensitive Products in weather tight, climate controlled enclosures.
C. For exterior storage of fabricated Products, place on sloped supports, above ground.
D. Provide bonded off-site storage and protection when site does not permit on-site storage or
protection.
E. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to
avoid condensation or potential degradation of Product.
F. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing
with foreign matter.
G. Provide equipment and personnel to store Products by methods to prevent soiling,
disfigurement, or damage.
H. Arrange storage of Products to permit access for inspection. Periodically inspect to verify
Products are undamaged and are maintained in acceptable condition.
PART 30 EXECUTION
Not Used
END OF SECTION
Revision Log
PART 31 GENERAL
31.01 SUMMARY
A. Section Includes:
1. Quality Assurance
2. Submittals
3. Project Record Documents
4. Survey Requirements
5. Examination
6. Survey Reference Points
B. Related Sections:
1. General Conditions: Basic site engineering requirements.
2. Section 01 31 32 (00320) - Geotechnical Data: Owner's topographic survey.
3. Section 01 77 00 (01770) - Contract Closeout: Project Record Documents.
31.02 QUALITY ASSURANCE
A. Employ a Land Surveyor or Engineer registered in the State where project is located and
acceptable to the Owner [and Architect], to perform survey work of this section.
B. Submit evidence of Surveyor's or Engineer’s Errors and Omissions insurance coverage in the
form of an Insurance Certificate.
31.03 SUBMITTALS
A. Submit a copy of registered site drawing and a certificate signed by the Land Surveyor or
Engineer, that the elevations and locations of the Work are in conformance with Contract
Documents.
B. On request, submit documentation verifying accuracy of survey work.
31.04 PROJECT RECORD DOCUMENTS
A. Maintain a complete and accurate log of control and survey work as it progresses.
B. On completion of foundation walls and major site improvements, prepare a certified survey
illustrating dimensions, locations, angles, and elevations of construction and site work.
31.05 SURVEY REQUIREMENTS
A. Provide field engineering services. Utilize recognized engineering survey practices.
B. Establish a minimum of two permanent bench marks on site, referenced to established control
points. Record locations, with horizontal and vertical data, on project record documents.
C. Submit Project Record Documents under provisions of Section 01 78 39.
D. Establish elevations, lines and levels. Locate and lay out by instrumentation and similar
appropriate means.
E. Periodically verify layouts by same means
END OF SECTION
Revision Log
PART 34 GENERAL
34.01 SUMMARY
A. Section Includes:
1. Administrative and Procedural Requirements for Cutting and Patching
B. Related Documents:
1. Refer to other Sections of these Specifications, including Divisions 22 (15) through 28
(16), for specific requirements and limitations applicable to cutting and patching individual
parts of the work.
34.02 DEFINITIONS
A. Cutting: Removal of in-place construction necessary to permit installation or performance of
other Work.
B. Patching: Fitting and repair work required to restore surfaces to original conditions after
installation of other Work.
34.03 SUBMITTALS
A. CUTTING AND PATCHING PROPOSAL:
1. Where approval of procedures is required before proceeding, submit a proposal
describing procedures in advance of the time cutting and patching will be performed.
Include the following information, as applicable:
a. Describe the extent of cutting and patching required and how it is to be performed.
Indicate why it cannot be avoided.
b. Describe anticipated results, include changes to structural elements and operating
components and changes in the building's appearance and other visual elements.
c. List products to be used and entities that will perform work.
d. Indicate dates when cutting and patching is to be performed.
e. List utilities that will be disturbed, including those that will be relocated and those
that will be temporarily out-of service. Indicate how long service will be disrupted.
f. Approval by the [Architect] to proceed does not waive the [Architect] right to later
require complete removal and replacement of work found to be unsatisfactory.
34.04 STRUCTURAL WORK:
A. Do not cut and patch structural elements in a manner that would reduce the load-carrying
capacity or load deflection ratio. Obtain approval of the cutting and patching proposal before
cutting and patching structural elements.
34.05 OPERATIONAL AND SAFETY LIMITATIONS:
A. Do not cut and patch operating elements or safety components in a manner that would reduce
their capacity to perform as intended, or would increase maintenance, or decrease operational
life or safety. Obtain approval of the cutting and patching proposal before cutting and patching
operating elements or safety related systems.
PRODUCTS
34.07 MATERIALS:
A. Use materials identical to existing materials. If identical materials are not available or cannot
be used where exposed surfaces are involved, use materials that match existing adjacent
surfaces to the fullest extent possible. Use materials whose performance will equal or surpass
that of existing materials.
PART 35 EXECUTION
35.01 EXAMINATION:
A. Before cutting, examine surfaces to be cut and patched and conditions under which cutting
and patching is to be performed. Take corrective action before proceeding if unsafe or
unsatisfactory conditions are encountered.
35.02 PREPARATION:
A. Provide temporary support of work to be cut.
35.03 CLEANING:
A. Thoroughly clean areas and spaces where cutting and patching is performed or used as
access. Remove paint, mortar, oils, putty and similar items. Thoroughly clean piping, conduit,
and similar features before painting or finishing is applied. Restore damaged pipe covering to
its original condition.
35.04 PROTECTION:
A. Protect existing construction during cutting and patching to prevent damage. Provide
protection from adverse weather conditions for portions that might be exposed during cutting
and patching operations.
B. Avoid interference with use of adjoining areas or interruption of free passage to adjoining
areas.
C. Take all precautions to avoid cutting existing pipe, conduit, or ductwork serving the building,
but scheduled to be removed, or relocated until provisions have been made to bypass them.
D. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems
are required to be removed, relocated, or abandoned, bypass such services/systems, when
possible, before cutting to minimize interruption to occupied areas.
35.05 PERFORMANCE:
A. Employ skilled workmen to perform cutting and patching. Proceed with cutting and patching at
the earliest feasible time and complete without delay.
B. Cut existing construction to provide for the installation of other components or the
performance of other construction activities and the subsequent fitting and patching required
to restore surfaces to their original condition.
35.06 CUTTING:
A. All cutting of areas shall be by Contractor requiring cutting, except where noted otherwise in
the Specifications and/or Drawings.
END OF SECTION
Revision Log
PART 36 GENERAL
36.01 SUMMARY
A. Section Includes:
1. Throughout all phases and items of the construction period, maintain the building and site
in a standard of cleanliness as described in this Section including:
a. Cleaning Materials and Equipment
b. Progress Cleaning
PART 37 PRODUCTS
37.01 CLEANING MATERIALS AND EQUIPMENT:
A. Provide all required personnel, equipment, and materials needed to maintain the specified
standard of cleanliness.
37.02 COMPATIBILITY:
A. Use only the cleaning materials and equipment which are compatible with the surface being
cleaned, as recommended by the manufacturer of the material or as approved by the Owner’s
Representative.
PART 38 EXECUTION
38.01 PROGRESS CLEANING
A. General:
1. Retain all stored items in an orderly arrangement allowing maximum access, not
impeding traffic, and providing the required protection of materials.
2. Do not allow the accumulation of scrap, debris, waste material, and other items not
required for the construction of this work.
3. Twice weekly, and more often if necessary, the Contractor shall completely remove all
scrap, debris, and waste material from the job site, and shall place into container
furnished by the Contractor.
4. Provide adequate storage for all items awaiting removal from the job site, observing all
requirements for fire protection.
B. Project Site; The Contractor shall:
1. Daily, and more often if necessary, inspect the project site and pick up all scrap, debris,
and waste material. Remove all such items to the place designated for their storage.
2. Weekly, and more often if necessary, sweep all interior places clean. "Clean", for the
purpose of this subparagraph, shall be interpreted as meaning free from dust and other
material capable of being removed by reasonable diligence using a hand-held broom.
3. As required preparatory to installation of succeeding materials, clean the structures or
pertinent portions thereof to the degree of cleanliness recommended by the manufacturer
of the succeeding material, using all equipment and materials required to achieve the
required cleanliness.
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 91 ▪
FILE: Division 01 General Conditions REVISED: 01/01/13
Revision Log
SECTION 01 74 19 (01524) - CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
PART 39 GENERAL
39.01 SUMMARY
A. Section Includes:
1. Administrative and Procedural Requirements for the Following:
a. Salvaging Nonhazardous Construction Waste.
b. Recycling Nonhazardous Construction Waste.
c. Disposing of Nonhazardous Construction Waste.
d. Development and Implementation of a Construction Waste Management (CWM)
Plan.
B. Related Sections:
1. Section 01 33 00 – Submittals and Substitution Procedures
2. Section 01 50 00 – Temporary Facilities and Controls
3. Section 01 74 00 (01740) – Cleaning and Waste Management: For additional cleaning
requirements.
4. Section 01 81 13 (01352) - Sustainable Design Requirements: For additional LEED
requirements.
5. Section 01 81 19 – Indoor Air Quality Requirements
6. Section 31 10 00 - Site Clearing: For disposition of waste resulting from site clearing and
removal of above- and below-grade improvements.
7. Divisions 02 - 23: Individual Sections that involve finish materials that are located inside
the vapor retarder as well as auxiliary finishing materials installed within the vapor
retarder. This includes, but is not limited to, adhesives, sealants, paints, primers, carpets
and composite wood products.
39.02 DEFINITIONS
A. Construction Waste: Building and site improvement materials and other solid waste resulting
from construction, remodeling, renovation, or repair operations. Construction waste includes
packaging.
B. Demolition Waste: Building and site improvement materials resulting from demolition or
selective demolition operations.
C. Disposal: Removal off-site of demolition and construction waste and subsequent sale,
recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having
jurisdiction.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in
preparation for reuse.
PART 40 PRODUCTS
40.01 WASTE CONTAINERS
A. Durable, covered, secured, reusable container for each category or waste.
B. Signs for each container: At least 6 feet by 3 feet, exterior grade panel, painted, message in
large letters identifying waste category and waste hauling/disbursement subcontractor.
PART 41 EXECUTION
41.01 PLAN IMPLEMENTATION
A. General: Implement waste management plan as approved by the [Owner’s Representative]
[and] [Architect]. Provide handling, containers, storage, signage, transportation, and other
items as required to implement waste management plan during the entire duration of the
Contract.
1. Minimize the creation of construction and demolition waste on the job site. When
designing the Construction Waste Management Plan, the Contractor may use more than
one of these practices (simultaneously or phased in) as work progresses. In general, the
steps include:
a. Prevent waste in the first place:
1) Order materials precut to required size.
2) Order exact quantity required.
3) Use detailed take-offs to identify location and uses in structure to reduce risk of
unplanned and potentially wasteful cuts.
4) Verify that field measurements are as indicated on construction and/or shop
drawings before confirming product orders or proceeding with work.
5) Protect products from damage during storage, installation and in-place.
TOTAL IN WEIGHT OR $
PERCENTAGE OF WASTE
DIVERTED
(TOTAL WASTE DIVIDED
BY TOTAL DIVERTED
END OF SECTION 01 74 19 (01524)
Revision Log
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 102 ▪
REVISED: 01/01/13 FILE: Division 01 General Conditions
PART 42 GENERAL
42.01 SUMMARY
A. Section Includes:
1. Closeout Procedures
2. Inspection Procedures
B. Related Sections:
1. Section 01 33 00 (01330) – Submittal and Substitution Procedures
2. Section 01 74 00 (01740) - Cleaning and Waste Management
3. Section 01 78 13 (01780) – Bonds and Warranties
4. Section 01 78 39 (01785) - Project Record Documents
5. Section 01 78 43 (01790) - Spare Parts and Materials
6. Section 01 79 00 (01820) - Training
7. Section 01 78 23 (01830) - Operating and Maintenance Data
42.02 DEFINITIONS
A. Closeout is hereby defined to include general requirements near end of Contract Time, in
preparation for final acceptance, final payment, normal termination of contract, occupancy by
Owner, and similar actions evidencing completion of the work. Specific requirements for
individual units of work are specified in sections of Divisions 2 (02) through 16 (33). Time of
closeout is directly related to "Substantial Completion", and shall be a single time period for
the entire work.
42.03 PREREQUISITES TO SUBSTANTIAL COMPLETION
A. General: Prior to requesting inspection for Substantial Completion (for either entire work or
portions thereof), complete the following and list known exceptions in request:
1. Include supporting documentation for completion as indicated in these Contract
Documents.
2. Submit statement showing accounting of changes to Contract Sum.
3. The Contractor shall prepare, submit and complete a punch list in accordance with
General Conditions.
4. Submit specific warranties, workmanship/maintenance bonds, maintenance agreements,
final certifications, and similar documents.
5. Obtain and submit releases enabling Owner's full and unrestricted use of the work and
access to services and utilities, including (where required) occupancy permits, operating
certificates, waivers of lien, and similar releases.
6. Submit record drawings, maintenance manuals, and similar final record information.
7. Deliver tools, spare parts, extra stocks of materials, and similar physical items to Owner.
8. Complete start-up testing of systems, and instructions of Owner's operating/maintenance
personnel. Discontinue (or change over) and remove from project site temporary
facilities and services, along with construction tools and facilities, mock-ups, and similar
elements.
PART 43 PRODUCTS
Not Used
PART 44 EXECUTION
44.01 CLEANING
A. General: Special cleaning for specific units of work is specified in sections of Divisions 02
through 33. General cleaning during progress of work is specified in General Conditions and
as temporary services in Section 01 74 00. Provide final cleaning of the work, at time
indicated, consisting of cleaning each surface or unit of work to normal "clean" condition
expected for a first-class building cleaning and maintenance program. Comply with
manufacturer's instructions for cleaning operations.
1. Where extra materials of value remain after completion of associated work have become
Owner's property, dispose of these to Owner's best advantage as directed.
END OF SECTION
Revision Log
PART 45 GENERAL
45.01 SUMMARY
A. Section Includes:
1. This Section specifies general administrative and procedural requirements for warranties,
guarantees, and bonds required by the Contract Documents, including manufacturers
standard warranties on products and special warranties. Warranties required by the
Specifications, Divisions 02 through 33, shall not deprive the Owner of other rights the
Owner may have under other provisions of the Contract Documents and shall be in
addition to other warranties made by the Contractor under the Contract Documents.
2. Disclaimers and Limitations: Manufacturer's disclaimers and limitations on product
warranties do not relieve the Contractor of the warranty on the Work that incorporates the
products, nor does it relieve suppliers, manufacturers, and Subcontractors required to
countersign special warranties with the Contractor.
B. Related Sections:
Note: Reference below is to the Marriott General Conditions for Corporate Projects. Modify
subparagraph if a different document is utilized.
1. Additional requirements as specified in General Conditions.
2. General closeout requirements are included in Section 01 77 00 (01770) Contract
Closeout.
3. Warranties, including requirements for certifications for the work and products and
installation that are specified to be warranted, are stated in the individual Specification
Sections of Divisions 02 through 33.
4. Specific certification requirements and other commitments and agreements for continuing
services to the Owner are specified elsewhere in the Contract Documents.
45.02 DEFINITIONS
A. Categories of Specific Warranties: Warranties on the work are in several categories, including
those of General Conditions, and including (but not necessarily limited to) the following
specific categories related to individual units of work specified in sections of Divisions 02
through 33 of these Specifications.
1. Special Project Warranty (Guarantee): A warranty specifically written and signed by
Contractor for a defined portion of the Work and, where required, countersigned by
Subcontractor, installer, manufacturer, or other entity engaged by Contractor.
2. Specified Product Warranty: A warranty which is required by Contract Documents, to be
provided for a manufactured product incorporated into the Work, regardless of whether
manufacturer has published a similar warranty without regard for specific incorporation of
product into the Work, or has written and executed a special project warranty as a direct
result of Contract Documents requirements.
3. Coincidental Product Warranty: A warranty which is not specifically required by Contract
Documents (other than as specified in this Section), but which is available on a product
incorporated into the work by virtue of the fact that manufacturer of product has published
warranty in connection with purchases and uses of product without regard for specific
applications, except as otherwise limited by terms of warranty.
PART 46 PRODUCTS
Not Used
PART 47 EXECUTION
Not Used
END OF SECTION
Revision Log
SECTION 01 78 23 (01830) - OPERATION AND MAINTENANCE DATA
PART 48 GENERAL
48.01 SUMMARY
A. Section Includes:
1. This Section specifies the administrative requirements, procedural obligations, terms and
conditions and general requirements related to the preparation and submittal of
instruction manuals covering the materials installed, care, preservation and maintenance
of products, finishes, equipment and systems.
B. Related Sections:
1. Special operating and maintenance data requirements for specific equipment or building
operating systems are included in the appropriate Specifications Sections of Divisions 02
through 33.
2. Preparation of Shop Drawings and Product Data are included in Specification Section
01 33 00, "Submittals and Substitutions".
3. General closeout requirements are included in Specification Section 01 77 00, "Contract
Closeout".
4. General requirements for submittal of Project Record Documents are included in Section
01 78 39, "Project Record Documents".
48.02 SUBMITTALS
A. Submittal Schedule: Comply with the following schedule for submittal of operating and
maintenance manuals:
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 107 ▪
FILE: Division 01 General Conditions REVISED: 01/01/13
PART 49 PRODUCTS
Not Used
PART 50 EXECUTION
Not Used
END OF SECTION
Revision Log
PART 51 GENERAL
51.01 SUMMARY
A. Section Includes:
1. This Section specifies administrative and procedural requirements for Project Record
Documents to be prepared and submitted by the General Contractor.
2. Project Record Documents required include:
a. Marked-Up Copies of Record Drawings, Specifications, and Product Data
b. Record Samples
c. Miscellaneous Record Submittals
B. Related Sections:
1. General project closeout requirements are included in “Contract Closeout”, Section
01 77 00.
2. General requirements for submittal of Shop Drawings and Product Data are included in
General Conditions and the Section “Submittals and Substitutions,” Section 01 33 00.
3. Specific record copy requirements that expand requirements of this Section are included
in the individual Sections of Divisions 02 through 33.
4. Operating and maintenance data is specified in Section 01 78 23.
51.02 MAINTENANCE OF DOCUMENTS AND SAMPLES
51.03 RECORD DRAWINGS
A. The Contractor shall maintain a white-print set (blue-line or black-line) of Contract Drawings
and Shop Drawings in clean, undamaged condition, with mark-up of actual installations which
vary substantially from the work as originally shown. Mark whichever drawing is most capable
of showing "field" condition fully and accurately; however, where Shop Drawings are used for
mark-up, record a cross reference at corresponding location on working drawings. Mark with
red erasable pencil and, where feasible, use other colors to distinguish between variations in
separate categories of work. Mark-up new information which is recognized to be of
importance to Owner, but was for some reason not shown on either Contract Drawings or
Shop Drawings. Give particular attention to concealed work, which would be difficult to
measure and record at a later date. Note related change order numbers where applicable.
Organize record drawing sheets into manageable sets, bind with durable paper cover sheets,
and print suitable titles, dates, and other identification on cover of each set.
B. Responsibility for Markup: Where feasible, the individual or entity who obtained record data,
whether the individual or entity is the installer, Subcontractor, or similar entity, is required to
prepare the mark-up on Record Drawings.
PART 52 PRODUCTS
Not Used
PART 53 EXECUTION
53.01 RECORDING
A. Post changes and modifications to the Documents as they occur. Do not wait until the end of
the Project.
END OF SECTION
Revision Log
PART 54 GENERAL
54.01 SUMMARY
A. Section Includes:
1. Spare Parts and Materials
B. Related Sections:
1. Refer to individual sections for items listed herein, as well as other requirements.
PART 55 PRODUCTS
Note: Delete Paragraphs below not used on Project.
55.01 EXTRA MATERIALS - GENERAL
A. At the time of building acceptance, deliver to the Owner the following extra materials. Deliver
in original unopened cartons or containers (except paint) with each item properly identified.
55.02 ASPHALT SHINGLES (07 31 13)
A. Furnish minimum of one full square of each type/color/texture shingle used in the work.
Provide in unopened, clearly labeled bundles or containers.
55.03 JOINT SEALANTS (07 92 00)
A. Furnish extra sealant materials from same production run as the materials applied in the
quantities described below. Package materials in unopened, factory-sealed containers with
labels describing contents.
1. Quantity: Furnish one unused tube of each type and color of exterior sealant applied.
55.04 TILING (09 30 00)
A. Furnish extra materials described below that match products installed, are packaged with
protective covering for storage, and are identified with labels describing contents.
1. Tile and Trim Units: Furnish quantity of full-size units equal to one case for each type,
composition, color, pattern, and size indicated.
55.05 ACOUSTIC TILE CEILINGS (09 51 23)
A. Replacement stock amounting to one full box (minimum 12 tiles) of each type.
55.06 PLASTIC-LAMINATE FLOORING (09 62 19)
A. Furnish extra materials matching products installed as described below, packaged with
protective covering for storage and identified with labels clearly describing contents.
1. Flooring: Equal to one full box of amount installed for each pattern and color indicated.
2. Trim: 10 lineal feet of each profile used.
55.07 WOOD PARQUET FLOORING (09 64 23)
A. Furnish extra materials matching products installed, packaged with protective covering for
storage and identified with labels clearly describing contents.
1. Flooring: Equal to one full carton of product installed from same production run as
original material supplied to the project.
2. Include manufacturer’s instruction sheet, including sources and contact information to
obtain recommended adhesives and technical assistance.
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 119 ▪
FILE: Division 01 General Conditions REVISED: 01/01/13
PART 56 EXECUTION
Not Used
END OF SECTION
Revision Log
PART 57 GENERAL
57.01 SUMMARY
A. Section Includes:
1. This Section specifies the administrative requirements, procedural obligations, terms and
conditions and training requirements related to instructing the facility engineering
personnel in the proper care, preservation, operations and maintenance of materials,
finishes, equipment and systems.
a. Preparation and submittal of instructor qualifications, training schedules, and
agendas for various building materials, components, systems and equipment.
b. Instruction of the Owner's personnel and adjunct organizations in the proper
operation and maintenance of all building materials, components, systems and
equipment.
B. Related Sections:
1. Special operating and maintenance data requirements for specific equipment or building
operating systems are included in the appropriate Specification Sections of Divisions 02
through 33.
2. Preparation of Shop Drawings and Product Data are included in Specification Section
01 33 00 (01330), Submittals and Substitutions.
3. General closeout requirements are included in Specification Section 01 77 00 (01770).
Contract Closeout.
4. General requirements for submittal of Project Record Documents are included in Section
01 78 39 (01785), Project Record Documents.
5. Additional training requirements for building systems and/or equipment are delineated in
the appropriate Specification Sections, Divisions 02 through 33.
6. Where training manuals include information on work installed by the Contractor and their
Subcontractors, the Contractor shall be responsible for the preparation of the manuals,
including collection, collation and binding of the material and submittal of data as
specified.
57.02 QUALITY ASSURANCE
A. The status of training deliverables shall be an integral part of the Contractor's coordination
process. The Contractor shall meet with the Owner as required, to discuss progress-to-date,
deficiencies and non-compliance issues.
57.03 TRAINING MANUALS
A. The completed FINAL VERSION of the approved Operation & Maintenance Manuals and the
redlined set of the record "as-built" drawings shall be used as the basis of instruction. The
Contractor is not responsible for providing additional copies of these documents for training
purposes.
57.04 TRAINING HOURS
A. Training shall be conducted during normal working hours. All training shall be completed prior
to the public opening of the hotel property.
END OF SECTION
PART 60 GENERAL
60.01 SUMMARY
A. Special requirements for Indoor Air Quality (IAQ) management during construction operations.
1. Control of emissions during construction.
2. Moisture control during construction.
B. Related Sections:
1. Section 01 11 00 – Summary of Work
2. Section 01 33 00 – Submittal and Substitution Procedures
3. Section 01 74 19 - Construction Waste Management and Disposal
4. Section 01 81 13 – Sustainable Design Requirements.
5. Divisions 01 through 50 Sections for LEED requirements specific to the Work of each of
those Sections. These requirements may or may not include reference to LEED.
60.02 REFERENCES
A. American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (ASHRAE)
Publications:
1. 52.2, "Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency
by Particle Size"
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. D7186 “Standard Practice for Quality Assurance Observation of Roof Construction and
Repair”
2. E2114 “Standard Terminology for Sustainability Relative to the Performance of Buildings”
C. Carpet & Rug Institute (CRI) Publications:
1. Carpet: “Green Label Plus Program”
2. Carpet Cushion: “Green Label Program”
D. Code of Federal Regulations (CFR) Publications:
1. 40 CFR, Part 59, Subpart D-2001, "National Volatile Organic Compound Emission
Standards for Architectural Coatings"
E. U.S. Environmental Protection Agency (EPA) Publications:
1. EPA Protocol for Environmental Requirements, “Testing for Indoor Air Quality, Baseline
IAQ, and Materials”, for Research Triangle Park Campus, Section 01445.
2. “EPA Compendium of Methods for the Determination of Inorganic Compounds in Ambient
Air”
3. “EPA Compendium of Methods for the Determination of Air Pollutants in Indoor Air”
F. Forest Stewardship Council (FSC) Publications:
1. FSC-STD-01-001, "FSC Principles and Criteria for Forest Stewardship"
2. FSC-STD-01-002, "FSC Glossary of Terms"
G. Green Seal, Inc. Publications:
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 129 ▪
FILE: Division 01 General Conditions REVISED: 01/01/13
PART 61 PRODUCTS
61.01 PRODUCT REQUIREMENTS
A. If air handlers must be used during construction, filtration media with a Minimum Efficiency
Reporting Value (MERV) of 8 must be used at each return air grill.
B. Use low-emitting adhesives, sealants, paints, primers, carpets and composite wood products
within the vapor barrier. This includes, but is not limited to:
▪ SECTION 01 11 00 (01110) - SUMMARY OF WORK ▪
▪ PAGE 131 ▪
FILE: Division 01 General Conditions REVISED: 01/01/13
2. Carpet materials shall meet or exceed the requirements of the Carpet & Rug Institute
(CRI)'s “Green Label Plus” Indoor Air Quality Test Program.
END OF SECTION
PART 63 GENERAL
63.01 SUMMARY
A. Section includes general requirements that apply to implementation of commissioning without
regard to specific systems, assemblies, or components.
1. Commissioning is a systematic process to verify that all building systems perform
interactively according to the design intent and the owner’s operational needs. This is
achieved by beginning in the design phase and documenting design intent and continuing
through construction, acceptance and the warranty period with actual verification of
performance. The commissioning process shall encompass and coordinate the
traditionally separate functions of system documentation, equipment startup, control
system calibration, testing and balancing, performance testing and training.
2. Commissioning during the construction phase is intended to achieve the following
specific objectives according to the Contract Documents:
a. Verify that applicable equipment and systems are installed according to the
manufacturer’s recommendations and to industry accepted minimum standards and
that they receive adequate operational checkout by installing contractors.
b. Verify and document proper performance of equipment and systems.
3. The commissioning process does not take away from or reduce the responsibility of the
system designers or installing contractors to provide a finished and fully functioning
product.
4. OPR documentation is included for information only.
B. Related Sections:
1. Section 01 31 00 - Project Management and Coordination: To introduce commissioning
and refers to this Section.
2. Section 01 77 00 - Closeout Procedures: Which defines substantial completion and
functional completion, relative to commissioning.
3. Section 22 08 00 – Commissioning of Plumbing: For commissioning process activities for
plumbing systems, assemblies, equipment, and components.
4. Section 23 08 00 –Commissioning of HVAC: For commissioning process activities for
HVAC&R systems, assemblies, equipment, and components.
5. Section 26 08 00 – Commissioning of Electrical Systems: For commissioning process
activities for integrated automation systems, assemblies, equipment, and components.
63.02 REFERENCES
A. U.S. Green Building Council's (USGBC) Publications:
1. (LEED-NC) Version 2.2 “LEED for New Construction and Major Renovations”
2. (LEED-NC) Version 2.2 “Reference Guide”
63.03 DEFINITIONS
A. Abbreviations. The following are common abbreviations used in the Specifications and in the
Commissioning Plan.
A/E- Architect and design engineers GC- General contractor (prime)
CxA- Commissioning authority MC- Mechanical contractor
B. Acceptance Phase. Phase of construction after startup and initial checkout when functional
performance tests, O&M documentation review and training occurs.
C. Approval. Acceptance that a piece of equipment or system has been properly installed and is
functioning in the tested modes according to the Contract Documents.
D. Architect/Engineer (A/E): The prime consultant (architect) and sub-consultants who comprise
the design team, generally the HVAC mechanical designer/engineer and the electrical
designer/engineer.
E. BoD: Basis of Design. A document that records concepts, calculations, decisions, and
product selections used to meet the OPR and to satisfy applicable regulatory requirements,
standards, and guidelines. The document includes both narrative descriptions and lists of
individual items that support the design process.
F. CxA: Commissioning Authority. An independent agent, not otherwise associated with the A/E
team members or the Contractor, hired by the Owner. The CxA directs and coordinates the
day-to-day commissioning activities. The CxA does not take an oversight role like the CM.
The CxA is part of the Construction Manager (CM) team or shall report directly to the CM.
G. Cx Plan: Commissioning Plan: A document that outlines the organization, schedule, allocation
of resources, and documentation requirements of the commissioning process
H. Datalogging: Monitoring flows, currents, status, pressures, etc. of equipment using stand-
alone dataloggers separate from the control system.
I. Deferred Functional Tests : FTs that are performed later, after substantial completion, due to
partial occupancy, equipment, seasonal requirements, design or other site conditions that
disallow the test from being performed.
J. Deficiency : A condition in the installation or function of a component, piece of equipment or
system that is not in compliance with the Contract Documents (that is, does not perform
properly or is not complying with the design intent)
K. Design Intent: A dynamic document that provides the explanation of the ideas, concepts and
criteria that are considered to be very important to the owner. It is initially the outcome of the
programming and conceptual design phases.
L. Design Narrative or Design Documentation: Sections of either the Design Intent or Basis of
Design.
M. Factory Testing: Testing of equipment on-site or at the factory by factory personnel with an
Owner’s representative present.
HVAC System
Instrumentation and Controls for 23 08 00
thru
HVAC
23 08 00.03
23 08 00
HVAC Power Ventilators thru
23 08 00.03
23 08 00
Air Cooled Refrigerant
thru
Condensers 23 08 00.03
23 08 00
Modular Indoor Air Handling thru
Units
23 08 00.03
23 08 00
Gas Fired Make-up Air Units thru
23 08 00.03
23 08 00
Dedicated Outdoor Air Handling thru
Units 23 08 00.03
23 08 00
Self Contained Air Conditioning
thru
Units 23 08 00.03
23 08 00
Split System Air Conditioners thru
23 08 00.03
23 08 00
Air Coils thru
23 08 00.03
23 08 00
Unit Heaters thru
23 08 00.03
23 08 00
Swimming Pool Dehumidifiers thru
23 08 00.03
PART 65 EXECUTION
65.01 MEETINGS
A. Scoping Meeting. Within 90 days of commencement of construction, the CxA will schedule,
plan and conduct a commissioning scoping meeting with the entire commissioning team in
attendance. Meeting minutes will be distributed to all parties by the CxA. Information gathered
from this meeting will allow the CxA to revise the Commissioning Plan to its “final” version,
which will also be distributed to all parties.
B. Miscellaneous Meetings. Other meetings will be planned and conducted by the CxA as
construction progresses. These meetings will cover coordination, deficiency resolution and
planning issues with particular Subs. The CxA will plan these meetings and will minimize
unnecessary time being spent by Subs. These meetings may be held monthly, until the final 3
months of construction when they may be held as frequently as one per week.
65.02 REPORTING
A. The CxA will provide regular reports to the OR, with increasing frequency as construction and
commissioning progresses.
B. The CxA will regularly communicate with all members of the commissioning team, keeping
them apprised of commissioning progress and scheduling changes through memos, progress
reports, etc.
C. Testing or review approvals and non-conformance and deficiency reports are made regularly
with the review and testing as described in later sections.
END OF SECTION
Revision Log
PART 1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Cast-in place concrete, including formwork, reinforcement, concrete materials,
accessories mix design, placement procedures, and finishes.
B. Related Sections:
1. Section 03 45 00 (03410) - Plant-Precast Structural Concrete
2. Section 03 54 13 (03500) - Cementitious Decks and Underlayment
3. Section 05 50 00 (05500) - Metal Fabrications
4. Section 07 10 00 (07100) – Dampproofing and Waterproofing
5. Section 07 92 00 (07920) - Joint Sealants
6. Section 13 11 00.01 (13151) - Swimming Pools - Exterior
7. Section 13 11 00.02 (13152) - Swimming Pools - Indoor
8. Section 32 13 13 (02751) - Cement Concrete Paving
9. Section 33 00 00 (02500) - Utility Services
1.02 DEFINITIONS
A. Cementitious Materials: Portland cement alone or in combination with one or more of blended
hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and
silica fume.
1.03 REFERENCES
1.04 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Product Data: Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330)
indicating specified items selected for use in project with the following supporting data.
1. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project.
C. Design Mixes: For each concrete mix. Include alternate mix designs when characteristics of
materials, project conditions, weather, test results, or other circumstances warrant
adjustments.
1. Indicate amounts of mix water to be withheld for later addition at Project site.
D. Steel Reinforcement Shop Drawings: Details of fabrication, bending, and placement,
prepared according to ACI 315, "Details and Detailing of Concrete Reinforcement." Include
material, grade, bar schedules, stirrup spacing, bent bar diagrams, arrangement, and supports
of concrete reinforcement. Include special reinforcement required for openings through
concrete structures. Coordinate built-in items including anchor bolts, plates and clips.
E. Formwork Shop Drawings: Prepared by or under the supervision of a qualified professional
engineer detailing fabrication, assembly, and support of formwork. Design and engineering of
formwork are Contractor's responsibility.
▪ DIV 03 CONCRETE ▪
▪ PAGE 1 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 2 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 3 ▪
PART 2 PRODUCTS
2.01 FORM-FACING MATERIALS
A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true,
and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of
joints.
1. Plywood, metal, or other approved panel materials.
2. Exterior-grade plywood panels, suitable for concrete forms, complying with DOC PS 1,
and as follows:
a. High-density overlay, Class 1, or better.
b. Medium-density overlay, Class 1, or better, mill-release agent treated and edge
sealed.
c. Structural 1, B-B, or better, mill oiled and edge sealed.
d. B-B (Concrete Form), Class 1, or better, mill oiled and edge sealed.
B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material.
Provide lumber dressed on at least two edges and one side for tight fit.
C. Forms for Cylindrical Columns, Pedestals, and Supports: Metal, glass-fiber-reinforced plastic,
paper, or fiber tubes that will produce surfaces with gradual or abrupt irregularities not
exceeding specified formwork surface class. Provide units with sufficient wall thickness to
resist plastic concrete loads without detrimental deformation.
D. Pan-Type Forms: Glass-fiber-reinforced plastic or formed steel, stiffened to resist plastic
concrete loads without detrimental deformation.
E. Void Forms: Biodegradable paper surface, treated for moisture resistance, structurally
sufficient to support weight of plastic concrete and other superimposed loads.
F. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch (19 by 19 mm), minimum.
G. Form-Release Agent: Commercially formulated form-release agent that will not bond with,
stain, or adversely affect concrete surfaces and will not impair subsequent treatments of
concrete surfaces.
1. Formulate form-release agent with rust inhibitor for steel form-facing materials.
H. Form Ties: Factory-fabricated, removable or snap-off metal or glass-fiber-reinforced plastic
form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling
of concrete on removal.
1. Furnish units that will leave no corrodible metal closer than 1 inch (25 mm) to the plane of
the exposed concrete surface.
2. Furnish ties that, when removed, will leave holes not larger than 1 inch (25 mm) in
diameter in concrete surface.
▪ DIV 03 CONCRETE ▪
▪ PAGE 4 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 5 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 6 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 7 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 10 ▪
PART 3 EXECUTION
3.01 FORMWORK
A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical,
lateral, static, and dynamic loads, and construction loads that might be applied, until concrete
structure can support such loads.
B. Construct formwork so concrete members and structures are of size, shape, alignment,
elevation, and position indicated, within tolerance limits of ACI 117.
C. Limit concrete surface irregularities, designated by ACI 347R as abrupt or gradual, as follows:
1. Class A, 1/8 inch (3 mm).
2. Class B, 1/4 inch (6 mm).
D. Construct forms tight enough to prevent loss of concrete mortar.
▪ DIV 03 CONCRETE ▪
▪ PAGE 11 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 15 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 16 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 17 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 18 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 19 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 20 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 21 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Textured cementitious finish with integral color applied over concrete at pool areas.
B. Related Sections:
1. Section 01 33 00 (01300) - Submittals: Procedures for submittals
2. Section 32 13 13 (02751) - Cement Concrete Pavement
3. Section 03 30 00 (03300) - Cast-ln-Place Concrete
4. Section 07 92 00 (07920) – Joint Sealants
5. Section 13 11 00.01 (13151) – Swimming Pools - Exterior
4.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. ASTM
2. C150 “Standard Specification for Portland Cement“
3. C171 “Standard Specification for Sheet Materials for Curing Concrete”
4.03 SUBMITTALS
A. Submit "Letter of Conformance" in accordance with Section 01 33 00 (01330) and with the
following supporting data:
1. Product Data:
a. Certificates: Certification from manufacturer indicating that installer is an "Approved
Applicator."
b. Manufacturer's Instructions: Submit for mixing, rate, and technique of application.
2. Samples: 12 inch x 12 inch panel showing pattern, texture and color. Owner approved
sample will be the standard for acceptance of all surfaces finished with synthetic
surfacing.
4.04 QUALITY ASSURANCE
A. Applicator Qualifications: Minimum of five years experience specifically in the field of providing
specified finishes. Installer approved by surfacing manufacturer.
4.05 PROJECT CONDITIONS
A. Environmental Conditions:
1. Temperature: 50 degrees F minimum, and rising.
2. Do not start if rain is predicted within 8 hours.
PART 5 PRODUCTS
5.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufactures:
1. None
▪ DIV 03 CONCRETE ▪
▪ PAGE 22 ▪
PART 6 EXECUTION
6.01 PREPARATION
A. Supervise finishing of concrete substrate.
1. After concrete is tamped and floated, one pass shall be made to remove derby wrinkles
and water depressions.
2. Provide one pass of a nylon bristled push broom immediately after slab has been
trowelled
B. Surfacing may be applied when concrete substrate can be walked on without leaving deep
depressions, but still shows water rise when pressed.
C. Protect walls and adjacent surfaces not to be coated. Protect aluminum members.
6.02 APPLICATION
A. Apply surfacing in accordance with manufacturer's instructions. Use consistency of mix and
application technique to match approved sample panel.
B. Apply in even, straight rows, overlapping to achieve full uniform coverage.
C. Apply a second coat before the first application has lost its water glaze.
D. Troweling:
1. Begin to trowel as water glaze leaves the deck. Establish pattern with the first pass. Hold
trowel level, apply light uniform pressure.
2. Second troweling to follow immediately behind the first; level uneven surface with the
trowel held flat.
▪ DIV 03 CONCRETE ▪
▪ PAGE 23 ▪
END OF SECTION
Revision Log
▪ DIV 03 CONCRETE ▪
▪ PAGE 24 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Plant-Precast Structural Concrete Units, Including the Following:
a. Hollow-Core Slab Units
b. Long-Span Units
c. Structural Framing Units
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-In-Place Concrete
2. Section 07 84 00 (07840) - Firestopping
3. Section 07 92 00 (07920) - Joint Sealants
7.02 REFERENCES
A. American Association of State Highway and Transportation Officials (AASHTO) Publications:
1. M 251 “Standard specifications for laminated elastomeric bridge bearings”
B. American Concrete Institute (ACI) Publications:
1. ACI 318 Building Code Requirements for Structural Concrete
C. American Concrete Institute (ACI) Publications:
1. ACI 216.1/TMS 0216.1, "Standard Method for Determining Fire Resistance of Concrete
and Masonry Construction Assemblies,"
2. 211.1 "Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass
Concrete"
3. 211.2 "Standard Practice for Selecting Proportions for Structural Lightweight Concrete"
4. 305R "Hot Weather Concreting"
5. 306.1: “Standard Specification for Cold Weather Concreting (Reapproved 2002)”
D. ASTM International (ASTM) Publications:
1. A36 “Standard Specification for Carbon Structural Steel”
2. A47 "Standard Specification for Ferritic Malleable Iron Castings"
3. A82 “Standard Specification for Steel Wire, Plain, for Concrete Reinforcement”
4. A108 "Standard Specification for Steel Bar, Carbon and Alloy, Cold-Finished"
5. A123 “Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
Products’
6. A153 "Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware"
7. A184 “Standard Specification for Fabricated Deformed Steel Bar Mats for Concrete
Reinforcement”
8. A185 “Standard Specification for Steel Welded Wire Reinforcement, Plain, for Concrete”
9. A276 “Standard Specification for Stainless Steel Bars and Shapes”
▪ DIV 03 CONCRETE ▪
▪ PAGE 25 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 26 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 27 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 28 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 29 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 30 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 31 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 32 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 34 ▪
▪ DIV 03 CONCRETE ▪
▪ PAGE 36 ▪
PART 9 EXECUTION
9.01 EXAMINATION
A. Examine substrates and conditions for compliance with requirements for installation
tolerances, true and level bearing surfaces, and other conditions affecting performance.
Proceed with installation only after unsatisfactory conditions have been corrected.
9.02 INSTALLATION
A. Bearing Pads: Install bearing pads as precast concrete units are being erected. Set pads on
true, level, and uniform bearing surfaces and maintain in correct position until precast concrete
units are placed.
B. Install precast structural concrete. Shore and brace precast concrete units to maintain
location, stability, and alignment until permanent connections are installed.
C. Welding: Perform welding in compliance with AWS D1.1 and AWS D1.4, with qualified
welders.
1. Protect precast concrete units and bearing pads from damage by field welding or cutting
operations and provide noncombustible shields as required.
2. Repair damaged metal surfaces by cleaning and applying a coat of galvanized repair
paint to galvanized surfaces.
3. Repair damaged metal surfaces by cleaning and repriming damaged painted surfaces.
D. Fasteners: Do not use drilled or powder-actuated fasteners for attaching accessory items to
precast, prestressed concrete units unless approved by Architect.
E. Erection Tolerances: Install precast concrete units level, plumb, square, and true, without
exceeding the recommended erection tolerances in PCI MNL 127, "Recommended Practice
for Erection of Precast Concrete" and as follows:
1. Variations from level or elevation: 1/4” in any 20’ run; 1/2” in any 40’ run; total plus or
minus 1/2” at any location.
2. Variation from position in plan: plus or minus 1/2” maximum at any location.
3. Offsets in alignment of adjacent members at any joint: 1/16” in any 10’ run; 1/4”
maximum.
4. Vertical difference between two adjacents units shall not exceed 3/16”.
F. Grouting Connections and Joints: After precast concrete units have been placed and secured,
grout open spaces at keyways, connections, and joints as follows:
1. Provide forms or other approved method to retain grout in place until hard enough to
support itself. Pack spaces with stiff grout material, tamping until voids are completely
filled. Place grout to finish smooth, level, and plumb with adjacent concrete surfaces.
Keep grouted joints damp for not less than 24 hours after initial set. Promptly remove
grout material from exposed surfaces before it hardens.
9.03 FIELD QUALITY CONTROL
A. Testing: Owner will engage a qualified independent testing and inspecting agency to perform
field tests and special inspections.
B. Field welds and connections using high-strength bolts will be subject to tests and inspections.
▪ DIV 03 CONCRETE ▪
▪ PAGE 37 ▪
END OF SECTION
Revision Log
▪ DIV 03 CONCRETE ▪
▪ PAGE 38 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Gypsum Cement Floor Underlayment.
B. Related Sections:
10.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. C472 “Standard Test Methods for Physical Testing of Gypsum, Gypsum Plasters and
Gypsum Concrete”.
10.03 SUBMITTALS
A. Product Data: For each type of product indicated.
10.04 QUALITY ASSURANCE
A. Installer's Qualifications: An experienced installer who is acceptable to manufacturer, who
has completed cement-based underlayment applications similar in material and extent to that
required for this Project, and whose work has resulted in construction with a record of
successful in-service performance.
10.05 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials in original packages and containers, with seals unbroken, bearing
manufacturer’s labels indicating brand name and directions for storage, mixing with other
components, and application.
B. Store materials to comply with manufacturer’s written instructions to prevent deterioration from
moisture or other detrimental effects.
10.06 PROJECT CONDITIONS
A. Environmental Limitations: Comply with manufacturer’s written recommendations for
substrate temperature and moisture content, ambient temperature and humidity, ventilation,
and other conditions affecting underlayment performance.
B. Close areas to traffic during underlayment application and for time period after application
recommended in writing by manufacturer.
10.07 COORDINATION
A. Coordinate cement-based underlayment with requirements of finish flooring products,
including adhesives, specified in Division 09 Sections.
1. Before installing surface sealers recommended by underlayment manufacturer, if any,
verify compatibility with finish flooring installation adhesives.
PART 11 PRODUCTS
11.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
▪ DIV 03 CONCRETE ▪
▪ PAGE 39 ▪
PART 12 PRODUCTS
12.01 EXAMINATION
A. Examine substrates, with Installer present, for conditions affecting performance of
underlayment including substrate moisture content. Begin underlayment application only after
unsatisfactory conditions have been corrected.
12.02 PREPARATION
A. General: Prepare and clean substrate according to manufacturer’s written instructions for
substrate indicated. Provide clean, dry, neutral-pH substrate for underlayment application.
1. Subfloor shall be structurally sound, clean, and free of mud, oil, grease, or other
contaminants.
B. Prior to installation of Gypsum Cement Underlayment, General Contractor shall inspect the
area to be poured for proper attachment of the subfloor and replace any areas of subfloor that
have weakened or delaminated during construction. All stud wall base plates in doors and
other openings shall be removed.
1. Wood Substrates: Mechanically fasten loose boards and panels to eliminate substrate
movement and squeaks. Sand to remove coatings that might impair underlayment bond
and remove sanding dust.
2. Treat nonmoving substrate cracks to prevent cracks from telegraphing through
underlayment according to manufacturer’s written recommendations.
3. Fill substrate voids to prevent underlayment from leaking.
▪ DIV 03 CONCRETE ▪
▪ PAGE 40 ▪
END OF SECTION
Revision Log
▪ DIV 03 CONCRETE ▪
▪ PAGE 41 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 1 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 2 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 3 ▪
PART 2 PRODUCTS
2.01 MATERIALS, GENERAL
A. Comply with referenced standards and other requirements indicated applicable to each type of
material required.
2.02 MANUFACTURERS
A. Avendra, LLC Preferred Manufactures:
1. None
B. Approved Manufacturers:
1. “Cultured Stone”; Cultured Stone, Division of Owens Corning (800-255-1727)
2. “Eldorado Stone “; Eldorado Stone, A Headwaters Company (800-925-1491)
2.03 ACCESSORIES
A. Flexible Flashing: As specified in Section 04 20 00.
B. Metal Lath: 18 gauge galvanized woven wire mesh, or galvanized [2.5 lb. Flat diamond mesh]
C. Weather Resistant Barrier: Kraft waterproof building paper, UBC Standard 14-1.
D. Water Repellant Coating:
1. As specified in Section 07 19 00.
2. Alternate “Craftshield”; Eldorado Stone, A Headwaters Company (800-925-1491)
2.04 MORTAR AND GROUT MATERIALS
A. Portland Cement: ASTM C150, Type I, of natural color or white, as needed to produce color
indicated.
B. Hydrated Lime: ASTM C207, Type S
C. Aggregate: ASTM C144, and as indicated below:
1. For joints narrower than 1/4 inch, use aggregate graded with 100percent passing the No.
8 sieve and 95 percent the No. 16 sieve.
2. For pointing mortar, use aggregate graded with 100 percent passing the No. 16 sieve.
3. White Mortar Aggregates: Natural white sand or ground white stone.
2.05 SIMULATED STONE FABRICATION
A. General: Fabricate simulated stone in sizes and shapes required to comply with requirements
indicated, including details on Drawings and final Shop Drawings.
B. Carefully inspect finished stones at fabrication plant for compliance with requirements relative
to qualities of appearance, material, and fabrication. Replace defective stones with ones that
do comply.
2.06 MORTAR AND GROUT MIXES
A. General: Comply with referenced standards and with manufacturers' instructions relative to
mix proportions, mixing equipment, mixer speeds, mixing containers, mixing time, and other
procedures needed to produce mortars and grouts of uniform quality and with optimum
performance characteristics.
▪ DIVISION 04 MASONRY ▪
▪ PAGE 4 ▪
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine surfaces to receive simulated stone work, and conditions under which materials will
be installed, with installer present, for compliance with requirements for installation tolerances
and other conditions affecting performance of dimension stonework. Do not proceed with
installation until unsatisfactory conditions have been corrected.
1. For the record, prepare written report, endorsed by installer, listing conditions detrimental
to performance of simulated stone work.
3.02 PREPARATION
A. Advise installers of other work about specific requirements relating to placement of inserts,
flashing reglets, metal anchors, and similar items to be used by stonework installer for
anchoring, supporting, and flashing of dimension stonework. Furnish installers of other work
with Drawings or templates showing locations of these items.
B. Verify items provided by other sections of work are properly sized and located.
C. Sheathed Surfaces: Install one layer of weather-resistant barrier with lap joints of 4-inches
shingle fashion. Apply code approved metal lath, attach using galvanized nails a minimum of
6-inches on center vertically and 16 inches on center horizontally, which penetrate a minimum
of 1-inch into studs. Wrap weather resistant barrier and metal lath a minimum of 16 inches
around all outside and inside corners.
3.03 ERECTION
A. Comply with manufacturer's product data, including product technical bulletins and installation
instructions.
B. General: Install/set all units and accessories accurately, using skilled, experienced personnel,
according to approved shop and setting drawings.
1. Use stone-fitters to perform field-cutting with power saws, when required.
a. Cut masonry units with wet-saw.
C. Clean stone surfaces before setting, using only water or mild cleaning compounds containing
no caustic or abrasives. Clean cut units using a stiff fiber brush and clean water. Allow units
to surface dry prior to placement.
D. Provide chases, reveals, openings, and other spaces required to accommodate other work.
Close up after other work is complete with simulated stone which matches stone already set.
E. Mortar: Apply 3/4 inch of mortar to lath, covering a maximum of 10 square feet at one time.
Press the units firmly into position in soft mortar bed, wiggle and apply slight pressure to unit
to ensure firm bonding causing mortar to extrude slightly around edges of units.
▪ DIVISION 04 MASONRY ▪
▪ PAGE 5 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 6 ▪
END OF SECTION
Revision Log
▪ DIVISION 04 MASONRY ▪
▪ PAGE 7 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Types of masonry work required include:
a. Standard Concrete Masonry Units
b. Face Brick
c. Stone Trim Units
d. Special Masonry Shapes
e. Mortar and Grout
f. Reinforcing Steel
g. Masonry Joint Reinforcement
h. Required Masonry Ties and Anchors
B. Related Sections:
1. Section 04 72 00 - Cast Stone Masonry
2. Section 04 73 00 - Manufactured Stone Masonry
3. Section 07 19 00 (07190) - Water Repellents
4. Section 07 20 00 (07200) - Thermal Protection
5. Section 07 62 00 (07620) - Sheet Metal Flashing and Trim
6. Section 07 92 00 (07920) - Joint Sealants
C. Products installed, but not furnished, under this Section include the following:
1. [Steel Lintels] [and] [Shelf Angles] for unit masonry, furnished under Section 05 50 00,
(05500) - Metal Fabrications.
2. Hollow-metal frames in unit masonry openings, furnished under Section 08 11 13 (08110)
- Hollow Metal Doors and Frames.
4.02 REFERENCES
A. ASTM International Publications:
1. A82 “Standard Specification for Steel Wire, Plain, for Concrete Reinforcement”
2. A185 “Standard Specification for Steel Welded Wire Reinforcement, Plain, for Concrete”
3. A307 "Standard Specification for Carbon Steel Bolts and Studs, 60 000 PSI Tensile
Strength"
4. A496 “Standard Specification for Steel Wire, Deformed, for Concrete Reinforcement”
5. A497 “Standard Specification for Steel Welded Wire Reinforcement, Deformed, for
Concrete”
6. A615 "Standard Specification for Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement"
7. A951 “Standard Specification for Masonry Joint Reinforcement”
▪ DIVISION 04 MASONRY ▪
▪ PAGE 8 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 9 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 10 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 11 ▪
PART 5 PRODUCTS
5.01 FIRE RATINGS: Where fire ratings on masonry walls are shown on the Drawings, the Contractor
shall make certain that the fire-resistant units to be used qualify for the ratings.
5.02 MORTAR AND GROUT MATERIALS
A. Colored Cement Product: Packaged blend made from masonry cement and mortar pigments,
all complying with specified requirements, and containing no other ingredients.
1. Avendra, LLC Preferred Manufacturers:
a. None
▪ DIVISION 04 MASONRY ▪
▪ PAGE 12 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 13 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 14 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 15 ▪
PART 6 EXECUTION
6.01 EXAMINATION
A. Examine conditions, with Installer present, for compliance with requirements for installation
tolerances and other conditions affecting performance.
1. Verify that foundations are within tolerances specified.
2. Verify that reinforcing dowels are properly placed.
3. Proceed with installation only after unsatisfactory conditions have been corrected.
B. Before installation, examine rough-in and built-in construction to verify actual locations of
piping connections.
6.02 INSTALLATION - GENERAL
A. Do not wet concrete masonry units.
B. Cleaning Reinforcing: Before placing, remove loose rust, ice and other coatings from
reinforcing.
▪ DIVISION 04 MASONRY ▪
▪ PAGE 16 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 17 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 18 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 19 ▪
▪ DIVISION 04 MASONRY ▪
▪ PAGE 20 ▪
END OF SECTION
Revision Log
▪ DIVISION 04 MASONRY ▪
▪ PAGE 21 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Structural Steel
B. Related Sections:
1. Section 01 45 00 - Quality Control
2. Section 03 30 00 - Cast-in-Place Concrete
3. Section 05 21 00 - Steel Joist Framing
4. Section 05 31 00 - Steel Decking
5. Section 05 40 00 - Cold-Formed Metal Framing
6. Section 05 50 00 - Metal Fabrications
7. Section 09 90 00 - Painting
8. Section 09 96 00 - High Performance Coatings
1.02 DEFINITIONS
A. Structural Steel: Elements of structural-steel frame, as classified by AISC's "Code of Standard
Practice for Steel Buildings and Bridges," that support design loads.
1.03 PERFORMANCE REQUIREMENTS
A. Structural Performance: Engineer structural steel connections required by the Contract
Documents to be selected or completed by the fabricator to withstand design loadings
indicated.
B. Engineering Responsibility: Engage a fabricator who utilizes a qualified professional engineer
to prepare calculations, Shop Drawings, and other structural data for structural steel
connections.
1.04 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Product Data: Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330)
indicating specified items selected for use in project with the following supporting data.
1. Shop Drawings detailing fabrication of structural steel components.
a. Include details of cuts, connections, splices, camber, holes, and other pertinent data.
b. Indicate welds by standard AWS symbols, distinguishing between shop and field
welds, and show size, length, and type of each weld.
c. Indicate type, size, and length of bolts, distinguishing between shop and field bolts.
Identify high-strength bolted slip-critical, direct-tension, or tensioned shear/bearing
connections.
d. Include Shop Drawings signed and sealed by a qualified professional engineer
responsible for their preparation.
▪ DIVISION 05 METALS ▪
▪ PAGE 1 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 2 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 3 ▪
PART 2 PRODUCTS
2.01 MATERIALS
A. Structural Steel Shapes, Plates, and Bars: As follows:
1. Carbon Steel: ASTM A36.
2. High-Strength, Low-Alloy Columbium-Vanadium Steel: ASTM A572, Grade 50.
3. High-Strength, Low-Alloy Structural Steel: ASTM A588, Grade 50, corrosion resistant.
B. Cold-Formed Structural Steel Tubing: ASTM A500, Grade B.
C. Hot-Formed Structural Steel Tubing: ASTM A501.
D. Steel Pipe: ASTM A53, Type E or S, Grade B.
1. Finish: Black, except where indicated to be galvanized.
2. Carbon-Steel Castings: ASTM A27, Grade 65-35, medium-strength carbon steel.
E. High-Strength Steel Castings: ASTM A148, Grade 80-50.
F. Shear Connectors: ASTM A108, Grade 1015 through 1020, headed-stud type, cold-finished
carbon steel, AWS D1.1, Type B.
G. Anchor Rods, Bolts, Nuts, and Washers: As follows:
1. Unheaded Rods: ASTM A36.
2. Headed Bolts: ASTM A325, Type 1, heavy hex steel structural bolts and heavy hex
carbon-steel nuts.
3. Headed Bolts: ASTM A490, Type 1, heavy hex steel structural bolts and heavy hex
carbon-steel nuts.
4. Washers: ASTM A36.
▪ DIVISION 05 METALS ▪
▪ PAGE 4 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 5 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 6 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 7 ▪
PART 3 EXECUTION
3.01 EXAMINATION
A. Before erection proceeds, and with the steel erector present, verify elevations of concrete and
masonry bearing surfaces and locations of anchorages for compliance with requirements.
B. Do not proceed with erection until unsatisfactory conditions have been corrected.
3.02 PREPARATION
A. Provide temporary shores, guys, braces, and other supports during erection to keep structural
steel secure, plumb, and in alignment against temporary construction loads and loads equal in
intensity to design loads. Remove temporary supports when permanent structural steel,
connections, and bracing are in place, unless otherwise indicated.
3.03 ERECTION
A. Set structural steel accurately in locations and to elevations indicated and according to AISC
specifications referenced in this Section.
▪ DIVISION 05 METALS ▪
▪ PAGE 8 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 9 ▪
END OF SECTION
Revision Log
▪ DIVISION 05 METALS ▪
▪ PAGE 10 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Rough Hardware
2. Loose Bearing and Leveling Plates
3. Loose Steel Lintels
4. Metal Stairs
5. Ladders:
a. Elevator Pit Ladder
b. Roof Ladder
6. Support Angles for Elevator Door Sills
7. Elevator Sump Pit Cover
8. Pipe Bollards
9. Laundry Trench Grate
10. Miscellaneous Metal Trim
11. Steel Framing and Supports for Applications where framing and supports are not
specified in other Sections
12. Stair Nosings for Exterior Concrete Stairs
13. Aluminum Roof Shade Canopy:
B. Related Sections:
1. Section 09 90 00 (09900) - Painting
2. Section 09 96 00 (09960) - High Performance Coatings
3. Section 10 82 13 – Exterior Grilles and Screens
4. Section 14 24 13 (14240) - Hydraulic Elevators
5. Section 32 31 13 (02821) - Fences and Gates
4.02 REFERENCES
A. ASTM International Publications:
1. A27 "Standard Specification for Steel Castings, Carbon, for General Application"
2. A36 "Standard Specification for Carbon Structural Steel".
3. A47 "Standard Specification for Ferritic Malleable Iron Castings"
4. A48 "Standard Specification for Gray Iron Castings"
5. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and Seamless"
▪ DIVISION 05 METALS ▪
▪ PAGE 12 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 13 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 14 ▪
PART 5 PRODUCTS
5.01 FERROUS METALS
A. Metal Surfaces, General: For metal fabrications exposed to view upon completion of the
Work, provide materials selected for their surface flatness, smoothness, and freedom from
surface blemishes. Do not use materials whose exposed surfaces exhibit pitting, seam marks,
roller marks, rolled trade names, roughness, and, for steel sheet, variations in flatness
exceeding those permitted by reference standards for stretcher-leveled sheet.
B. Steel Plates, Shapes, and Bars: ASTM A36
C. Steel Tubing: Cold-formed steel tubing complying with ASTM A500.
D. Steel Pipe: ASTM A53
1. Black finish, unless otherwise indicated.
2. Galvanized finish for exterior installations, unless shown to receive special coatings.
3. Type E, OR S, Grade B, Fy = 35 KSI, unless otherwise indicated, or another weight, type,
and grade required by structural loads.
E. Gray Iron Castings: ASTM A48, Class 30
F. Malleable Iron Castings: ASTM A47, Grade 32510
G. Brackets, Flanges and Anchors: Cast or formed metal of the same type material and finish as
supported rails, unless otherwise indicated.
H. Concrete Inserts: Threaded or wedge type; galvanized ferrous castings, either malleable iron,
ASTM A47, or cast steel, ASTM A27. Provide bolts, washers, and shims as required, hot-dip
galvanized per ASTM A153.
I. Welding Rods: Select in accordance with AWS Specifications for the metal alloy to be
welded.
5.02 NONFERROUS METALS
A. Aluminum Plate and Sheet: ASTM B209/B209M, Alloy 6061-T6.
B. Aluminum Extrusions: ASTM B221/B221M, Alloy 6063-T6.
C. Aluminum Castings: ASTM B26/B26M, Alloy 443.0-F.
D. Aluminum Extruded Structural Pipe and Tubes: ASTM B429/B429M, alloy and temper
recommended in writing by manufacturer for type of use and finish indicated.
▪ DIVISION 05 METALS ▪
▪ PAGE 15 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 16 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 17 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 18 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 19 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 20 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 21 ▪
END OF SECTION
Revision Log
▪ DIVISION 05 METALS ▪
▪ PAGE 22 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Exterior Railings
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-In-Place Concrete
2. Section 05 50 00 (05500) - Metal Fabrications
3. Section 05 73 00 (05720) - Ornamental Handrails and Railings
4. Section 09 90 00 (09900) - Painting
5. Section 09 96 00 (09960) - High Performance Coatings: For Exterior Railings
7.02 REFERENCES
A. ASTM International Publications:
1. A36 "Standard Specification for Carbon Structural Steel".
2. A47 "Standard Specification for Ferritic Malleable Iron Castings"
3. A48 "Standard Specification for Gray Iron Castings"
4. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and Seamless"
5. A780 "Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip
Galvanized Coatings"
6. B633 "Standard Specification for Electrodeposited Coatings of Zinc on Iron and Steel"
7. C1107 "Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)"
8. E488 "Standard Test Methods for Strength of Anchors in Concrete and Masonry
Elements"
9. E985 "Standard Specification for Permanent Metal Railing Systems and Rails for
Buildings"
B. American Iron and Steel Institute (AISI) Publications:
1. SG02 "North American Specification for the Design of Cold-Formed Steel Structural
Members"
C. American Welding Society (AWS) Publications:
1. D1.1 "Structural Welding Code - Steel"
2. D1.3 "Structural Welding Code - Sheet Steel"
D. Federal Specifications (FS) Publications:
1. DOD-P-21035A (formerly MIL-P-21035), Galvanizing Repair Specification
E. National Association of Architectural Metal Manufacturers (NAAMM) Publications:
1. "Metal Finishes Manual"
▪ DIVISION 05 METALS ▪
▪ PAGE 23 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 24 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 25 ▪
PART 8 PRODUCTS
8.01 METALS
A. General: Provide metal forms and types that comply with requirements of referenced
standards and that are free from surface blemishes where exposed to view in the finished unit.
Exposed-to-view surfaces exhibiting pitting, seam marks, roller marks, stains, discolorations,
or other imperfections on finished units are not acceptable.
A. Steel Pipe: ASTM A53; finish, type, and weight class as follows:
1. Black finish, unless otherwise indicated.
2. Galvanized finish where indicated.
3. Type S, Grade A, standard weight (Schedule 40), unless otherwise indicated, or another
weight required by structural loads.
B. Steel Plates, Shapes, and Bars: ASTM A36
C. Gray Iron Castings: ASTM A48, Class 30
D. Malleable Iron Castings: ASTM A47, Grade 32510
1. Bracket:
a. Avendra, LLC Preferred Manufacturers:
1) None
b. Approved Manufacturers:
1) “Model 382”; Julius Blum & Co., Inc. (800-526-6293)
2) Approved Substitution
E. Fittings: Steel Elbows, Tee-Shapes, Wall Brackets, Escutcheons
F. Mounting: Brackets and Flanges: Steel inserts for casting or setting in new and existing
concrete and with steel brackets for embedding into masonry.
G. Cast-In-Place and Post-Installed Anchors in Concrete: Anchors of type indicated below,
fabricated from corrosion-resistant materials with capability to sustain, without failure, load
imposed within a safety factor of 4, as determined by testing per ASTM E488, conducted by a
qualified independent testing laboratory.
1. Sleeves: For steel posts set in concrete, fabricate sleeves from steel pipe not less than 6
inches long with an inside diameter not less than 1/2 inch greater than the outside
diameter of post, with steel plate closure welded to bottom of sleeve.
▪ DIVISION 05 METALS ▪
▪ PAGE 26 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 27 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 28 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 29 ▪
PART 9 EXECUTION
9.01 PREPARATION
A. Coordinate setting drawings, diagrams, templates, instructions, and directions for installation
of anchorages, such as sleeves, concrete inserts, anchor bolts, and miscellaneous items
having integral anchors that are to be embedded in concrete as masonry construction.
Coordinate delivery of such items to project site.
9.02 INSTALLATION
A. Fit exposed connections accurately together to form tight, hairline joints.
B. Perform cutting, drilling, and fitting required for installation of handrails and railings. Set
handrails and railings accurately in location, alignment, and elevation, measured from
established lines and levels and free from rack.
1. Do not weld, cut, or abrade surfaces of handrails and railing components that have been
coated or finished after fabrication and are intended for field connection by mechanical or
other means without further cutting or fitting.
2. Set posts plumb within a tolerance of 1/4 inch in 12 feet.
3. Align rails so that variations from level for horizontal members and from parallel with rake
of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet.
C. Field Welding: Comply with the following requirements:
1. Use materials and methods that minimize distortion and develop strength and corrosion
resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove welding flux immediately.
4. At exposed connections, finish exposed welds and surfaces smooth and blended so that
no roughness shows after finishing and contour of welded surface matches those
adjacent.
D. Corrosion Protection: Coat concealed surfaces of aluminum that will come into contact with
grout, concrete, masonry, wood, or dissimilar metals with a heavy coat of bituminous paint or
zinc chromate primer.
E. Fastening to In-Place Construction: Provide anchorage devices and fasteners where
necessary for securing handrails and railings to in-place construction.
▪ DIVISION 05 METALS ▪
▪ PAGE 30 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 31 ▪
END OF SECTION
Revision Log
▪ DIVISION 05 METALS ▪
▪ PAGE 32 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Aluminum Ornamental Handrails and Railing Systems
B. Related Sections:
1. Section 03 30 00 - Cast-In-Place Concrete
2. Section 04 20 00 - Masonry Units
3. Section 05 52 00 - Handrails and Railings: For handrails and railings fabricated from
round pipe and tube components.
4. Section 08 71 00 - Door Hardware
C. Products Supplied But Not Installed Under This Section:
1. Inserts and anchors preset in masonry and concrete for anchorage of handrails and
railing systems.
10.02 REFERENCES
A. ASTM International Publications:
1. E985 "Standard Specification for Permanent Metal Railing Systems and Rails for
Buildings"
2. B26 "Standard Specification for Aluminum-Alloy Sand Castings"
3. B151 “Standard Specification for Copper-Nickel-Zinc Alloy (Nickel Silver) and Copper-
Nickel Rod and Bar”
4. B209 "Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate"
5. B210 "Standard Specification for Aluminum and Aluminum-Alloy Drawn Seamless Tubes"
6. B221 "Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods,
Wire, Profiles, and Tubes"
7. B247 "Standard Specification for Aluminum and Aluminum-Alloy Die Forgings, Hand
Forgings, and Rolled Ring Forgings"
8. B429 "Standard Specification for Aluminum-Alloy Extruded Structural Pipe and Tube"
9. C1007 "Standard Specification for Installation of Load Bearing (Transverse and Axial)
Steel Studs and Related Accessories"
B. American Welding Society (AWS) Publications:
1. D1.2 "Structural Welding Code--Aluminum"
C. American Society of Civil Engineers (ASCE) Publications:
1. ASCE 7, "Minimum Design Loads for Buildings and Other Structures"
D. Aluminum Association (AA) Publications:
1. "Aluminum Design Manual 2000: Specifications for Aluminum Structures"
10.03 DEFINITIONS
A. Definitions in ASTM E985 for railing-related terms apply to this Section.
▪ DIVISION 05 METALS ▪
▪ PAGE 33 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 34 ▪
PART 11 PRODUCTS
11.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
▪ DIVISION 05 METALS ▪
▪ PAGE 35 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 36 ▪
▪ DIVISION 05 METALS ▪
▪ PAGE 37 ▪
PART 12 EXECUTION
12.01 PREPARATION
A. Coordinate setting drawings, diagrams, templates, instructions, and directions for installation
of anchorage’s, such as sleeves, concrete inserts, anchor bolts, and miscellaneous items
having integral anchors, that are to be embedded in concrete as masonry construction.
Coordinate delivery of such items to project site.
12.02 INSTALLATION
A. Fit exposed connections accurately together to form tight, hairline joints.
B. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for installation of
handrails and railings. Set handrails and railings accurately in location, alignment, and
elevation, measured from established lines and levels and free from rack.
1. Do not weld, cut, or abrade surfaces of handrails and railing components that have been
coated or finished after fabrication and are intended for field connection by mechanical or
other means without further cutting or fitting.
2. Set posts plumb within a tolerance of 1/4 inch in 12 feet.
3. Align rails so that variations from level for horizontal members and from parallel with rake
of steps and ramps for sloping members to not exceed 1/4 inch in 12 feet.
C. Corrosion Protection: Coat concealed surfaces of aluminum alloys which will be in contact
with grout, concrete, masonry, wood, or dissimilar metals, with a heavy coat of bituminous
paint or zinc chromate primer.
D. Adjust handrails and railing systems prior to anchoring to ensure matching alignment at
abutting joints. Space posts at interval indicated, but not less than that required by structural
loads.
E. Fastening to In-Place Construction: Use anchorage devices and fasteners where necessary
for securing handrails and railings to in-place construction.
12.03 RAILING CONNECTIONS
A. Mechanical Connections: Fabricate handrails and railings by connecting members with railing
manufacturer's standard concealed mechanical fasteners and fittings, unless otherwise
indicated. Fabricate members and fittings to produce flush, smooth, rigid, hairline joints.
1. Fabricate splice joints for field connection using epoxy structural adhesive where this is
manufacturer's standard splicing method.
B. Expansion Joints: Install expansion joints no further apart than required to accommodate
thermal movement. Provide slip-joint internal sleeve extending 2 inches beyond joint on either
side. Fasten internal sleeve securely to one side. Locate joint within 6" of post.
▪ DIVISION 05 METALS ▪
▪ PAGE 38 ▪
END OF SECTION
Revision Log
▪ DIVISION 05 METALS ▪
▪ PAGE 39 ▪
PART 1 GENERAL
1.01 SUMMARY
A. This Section includes the following:
1. Framing with the following:
a. Dimension Lumber
b. Engineered Wood Products
1) Laminated Veneer Lumber (LVL)
2) Parallel Strand Lumber (PSL)
3) Laminated Strand Lumber (LSL)
c. Wood-Based Structural-Use Panels
1) Subflooring
2) Underlayment
3) Wall Sheathing
4) Roof Sheathing
5) Backing Panels
d. Wood-Preservative Treated Materials
e. Fire-Retardant-Treated Materials
f. Wall Sheathings
1) Gypsum Wall Sheathing
2) Fiberboard Wall Sheathing
3) Extruded-Polystryrene-Foam Wall Sheathings
2. Fasteners
3. Metal Framing Anchors
4. Rooftop Equipment Bases and Support Curbs
5. Wood Furring, Grounds, Nailers, and Blocking
B. Related Sections:
1. Section 06 15 16 (06150) – Wood Roof Decking
2. Section 06 17 53 (06175) - Shop-Fabricated Wood Trusses
3. Section 06 18 00 (06185) – Glued-Laminated Construction
4. Section 06 20 00 (06200) - Finish Carpentry for nonstructural carpentry items exposed to
view and not specified in another Section.
5. Section 07 42 33 (07420) – Solid Phenolic Exterior Wall Panels
6. Section 07 46 46 (07460) – Fiber Cement Siding
7. Section 07 53 23 (07530) - Ethylene-Propylene-Diene-Monomer (EPDM) Roofing
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Laminated-Veneer Lumber (LVL):
a. None.
2. Parallel-Strand Lumber (PSL):
a. None.
3. Prefabricated Wood I-Joists (TJI):
a. None.
4. Laminated Strand Lumber (LSL):
a. None.
5. Oriented Strand Board (OSB)
a. None.
B. Approved Manufacturers:
1. Wood-Preservative-Treated Materials:
a. “Micro-Guard”; Hoover Treated Wood Products, Inc. (800-531-5558)
b. “MicroPro”; Osmose, Inc. (800-241-0240)
2. Fire-Retardant-Treated Materials, Interior Type A:
a. "Dricon FRT"; Lonza Wood Protection (678-627-2000)
b. “Pryro-Guard”; Hoover Treated Wood Products, Inc. (800-531-5558)
c. "FirePRO"; Osmose, Inc. (800-241-0240)
3. Fire-Retardant-Treated Materials, Exterior Type:
a. “FRX Exterior FRT"; Lonza Wood Protection (678-627-2000)
b. “Exterior Fire-X”; Hoover Treated Wood Products, Inc. (800-531-5558)
4. Laminated-Veneer Lumber (LVL):
PART 3 EXECUTION
3.01 INSTALLATION, GENERAL
A. Discard units of material with defects that impair quality of rough carpentry and that are too
small to use with minimum number of joints or optimum joint arrangement.
B. Set rough carpentry to required levels and lines, with members plumb, true to line, cut, and
fitted.
C. Fit rough carpentry to other construction; scribe and cope as required for accurate fit.
Correlate location of furring, nailers, blocking, grounds, and similar supports to allow
attachment of other construction.
D. Apply field treatment complying with AWPA M4 to cut surfaces of preservative-treated lumber
and plywood.
E. Securely attach rough carpentry work to substrate by anchoring and fastening as indicated,
complying with the following:
1. Engineered Structural drawings
F. Secure blocking for roof edge systems, such as copings or gravel stops, in accordance with
SPRI Wind Design Standards as specified in Section 07 62 00 “Flashing and Sheet Metal” and
the requirements of the International Building Code.
END OF SECTION
Revision Log
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Triangular-Pitched Roof Trusses
2. Scissor Roof Trusses
3. Parallel-Chord Roof Trusses, Top-Chord Bearing
4. Parallel-Chord Roof Trusses, Bottom-Chord Bearing
5. Girder Trusses
6. Parallel-Chord Floor Trusses, Top-Chord Bearing
7. Parallel-Chord Floor Trusses, Bottom-Chord Bearing
8. Truss Accessories
B. Related Sections:
1. Section 05 50 00 (05500) - Metal Fabrications
2. Section 06 10 00 (06100) - Rough Carpentry permanent bracing
4.02 REFERENCES
A. ASTM International Publications:
1. A153 "Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware"
2. A307 "Standard Specification for Carbon Steel Bolts and Studs, 60 000 PSI Tensile
Strength"
3. A563 "Standard Specification for Carbon and Alloy Steel Nuts"
4. A591 "Standard Specification for Steel Sheet, Electrolytic Zinc-Coated, for Light Coating
Weight [Mass] Applications"
5. A653 "Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron
Alloy-Coated (Galvannealed) by the Hot-Dip Process"
6. A666 "Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel
Sheet, Strip, Plate, and Flat Bar"
7. A780 "Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip
Galvanized Coatings"
8. A792 "Standard Specification for Steel Sheet, 55 % Aluminum-Zinc Alloy-Coated by the
Hot-Dip Process"
9. F1667 "Standard Specification for Driven Fasteners: Nails, Spikes, and Staples"
B. The American Society of Mechanical Engineers (ASME) Publications:
1. B18.2.1 "Square and Hex Bolts and Screws, Inch Series"
C. American Wood-Preservers's Association (AWPA) Publications:
1. C2 "Lumber, Timber, Bridge Ties and Mine Ties - Preservative Treatment by Pressure
Processes"
PART 5 PRODUCTS
5.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Fire-Retardant-Treated Materials, Interior Type A:
a. None
2. Fire-Retardant-Treated Materials, Exterior Type:
a. None
3. Metal Connector Plates:
a. None
4. Metal Framing Anchors:
a. None
B. Approved Manufacturers:
PART 6 EXECUTION
6.01 INSTALLATION
A. Do not install wood trusses until supporting construction is in place and is braced and secured.
B. Before installing, splice trusses delivered to Project site in more than one piece.
C. Hoist trusses in place by lifting equipment suited to sizes and types of trusses required,
exercising care not to damage truss members or joints by out-of-plane bending or other
causes.
D. Install and brace trusses according to recommendations of TPI and as indicated.
E. Install trusses plumb, square, and true to line and securely fasten to supporting construction.
F. Space, adjust, and align trusses in location before permanently fastening and as indicated on
drawings.
G. Anchor trusses securely at all bearing points using metal framing anchors. Install fasteners
through each fastener hole in metal framing anchor according to manufacturer's fastening
schedules and written instructions.
H. Securely connect each truss ply required for forming built-up girder trusses.
1. Anchor trusses to girder trusses as indicated.
I. Install and fasten permanent bracing during truss erection and before construction loads are
applied. Anchor ends of permanent bracing where terminating at walls or beams.
1. Install and fasten strongback bracing vertically against vertical web of parallel-chord floor
trusses at centers indicated on Drawings.
J. Install wood trusses within installation tolerances of ANSI/TP1 1.
K. Do not cut or remove truss members.
L. Return wood trusses that are damaged or do not meet requirements to fabricator and replace
with trusses that do meet requirements.
1. Do not alter trusses in the field.
6.02 REPAIRS AND PROTECTION
A. Repair damaged galvanized coatings on exposed surfaces with galvanized repair paint
according to ASTM A780 and manufacturer's written instructions.
B. Protective Coating: Clean and prepare exposed surfaces of embedded-metal connector
plates. Brush apply primer, when part of coating system, and one coat of protective coating.
1. Apply materials to provide minimum dry film thickness recommended by manufacturer of
coating system.
END OF SECTION
SCHEDULE 0 - GENERAL
PRODUCT DATA SHEET 0 - SUMMARY
1.1 Section Includes:
A. Wood Millwork
1. Interior Standing and Running Trim
2. Exterior Standing and Running Trim
B. Wood Shelving
1.2 Related Sections:
1. Section 32 31 29 (02825) - Wood Fences and Gates
A. Section 06 10 00 (06100) - Rough Carpentry
B. Section 07 46 46 (07460) – Fiber-Cement Siding
C. Section 09 21 16 (09255) - Gypsum Board Assemblies
D. Section 09 90 00 (09900) - Painting
E. Section 12 30 00 (06400) - Architectural Woodwork
PRODUCT DATA SHEET 1 - REFERENCES
1.1 American Wood Council / American Forest & Paper Association (AF&PA) Publications:
A. ANSI/AF&PA NDS-2005: "National Design Specification (NDS) for Wood Construction".
1.2 Architectural Woodwork Institute (AWI) Publications:
A. "Architectural Woodwork Quality Standards"
1.3 American Wood-Preservers's Association (AWPA) Publications:
A. C20 "Structural Lumber - Fire-Retardant Treatment by Pressure Processes"
1.4 ASTM International Publications:
A. E84-03: Test Method for Surface-Burning Characteristics of Building Materials
B. A153 "Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware"
C. C1185 "Standard Test Methods for Sampling and Testing Non-Asbestos Fiber-Cement Flat
Sheet, Roofing and Siding Shingles, and Clapboards."
D. C1186 "Standard Specification for Flat Non-Asbestos Fiber-Cement Sheets."
1.5 U.S. Department of Commerce, National Institute of Standards and Technology (NIST)
A. DOC PS 1 "Construction and Industrial Plywood"
B. DOC PS 20 "American Softwood Lumber Standard"
1.6 Hardwood Plywood & Veneer Association (HPVA)
A. ANSI/HPVA HP-1: "American National Standard for Hardwood and Decorative Plywood"
SCHEDULE 1 - PRODUCTS
PRODUCT DATA SHEET 0 - MATERIALS, GENERAL
1.1 Lumber Standards: Comply with DOC PS 20, "American Softwood Lumber Standard," and with
applicable grading rules of inspection agencies certified by ALSC's Board of Review.
1.2 Inspection Agencies: Inspection agencies, and the abbreviations used to reference them,
include the following:
A. Northeastern Lumber Manufacturers Association (NeLMA)
B. National Lumber Grades Authority (Canadian) (NLGA)
C. Redwood Inspection Service (RIS)
D. SPIB - Southern Pine Inspection Bureau
E. West Coast Lumber Inspection Bureau (WCLIB)
F. Western Wood Products Association (WWPA)
1.3 Grade Stamps: Provide lumber with each piece factory marked with grade stamp of inspection
agency evidencing compliance with grading rule requirements and identifying grading agency,
grade, species, moisture content at time of surfacing, and mill.
SCHEDULE 2 - EXECUTION
PRODUCT DATA SHEET 0 - EXAMINATION
1.1 Examine substrates, with Installer present, for compliance with requirements for installation
tolerance and other conditions affecting installation and performance of finish carpentry. Do not
proceed with installation until unsatisfactory conditions have been corrected.
END OF SECTION
Revision Log
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Decorative Solid Mineral Profile Panels.
B. Related Sections:
Note: Edit list below to suit Project.
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 09 21 16 (09255) - Gypsum Board Assemblies: Substrate and Seam Finishing
4. Section 09 90 00 (09900) - Painting
7.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. C840 “Standard Specification for Application and Finishing of Gypsum Board”
2. D256-"Standard Test Methods for Determining the Izod Pendulum Impact Resistance of
Plastics"
3. D638 “Standard Test Method for Tensile Properties of Plastics”
4. D696 "Standard Test Method for Coefficient of Linear Thermal Expansion of Plastics
Between -30°C and 30°C With a Vitreous Silica Dilatometer"
5. D790 “Standard Test Methods for Flexural Properties of Unreinforced and Reinforced
Plastics and Electrical Insulating Materials”
6. D2583-95(2001)e1 "Standard Test Method for Indentation Hardness of Rigid Plastics by
Means of a Barcol Impressor"
7. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
B. Architectural Woodwork Institute (AWI) Publications:
1. "Architectural Woodwork Quality Standards"
7.03 DEFINITIONS
A. Sculptural Panels shall include all items to provide a complete continuous sculptural surface
as specified.
7.04 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: Indicate Decorative Solid Mineral Profile Panel product description,
fabrication information, and compliance with specified performance requirements.
PART 8 PRODUCTS
8.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
PART 9 EXECUTION
9.01 EXAMINATION
A. Verification of Conditions: Examine areas, and conditions under which work is to be
performed. Identify conditions detrimental to proper or timely completion.
1. Verify that substrate is a material listed as an acceptable substrate by the panel
manufacturer.
END OF SECTION
Revision Log
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Cast Polymer
a. Tub and Shower Surrounds
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 10 28 19.21 – Tub and Shower Doors
4. Section 12 30 00 (06400) - Architectural Woodwork
5. Section 12 36 40 (09380) - Cut Natural Stone Tile: Granite Countertops
6. Section 12 36 61 (09385) - Engineered Stone Countertops
7. Section 12 36 61.13 (06610) – Cultured Marble Countertops
8. Division 22 (15) for Plumbing Fixtures
10.02 REFERENCES
A. ASTM International (ASTM) Publications:
1. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
B. Architectural Woodwork Institute (AWI) Publications:
1. "Architectural Woodwork Quality Standards"
C. Federal Specifications (FS) Publications:
1. FS MMM-A-130 - Adhesive, Contact
10.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Include materials, component profiles, fastening methods, assembly methods, joint
details, accessory listings, and schedule of finishes.
a. Include data for fire-retardant treatment from chemical treatment manufacturer and
certification by treating plant that treated materials comply with requirements.
10.04 QUALITY ASSURANCE
A. Tub/Shower surrounds, window stools, and lavatory/vanity countertops shall be supplied by
one manufacturer. Where shown to be the same color, the color of the components shall
match for all items. Refer to Interior Finish Index for colors.
B. Allowable Tolerances:
PART 11 PRODUCTS
11.01 CAST POLYMER
A. Manufacturers:
1. Avendra, LLC Preferred Manufacturers:
a. Simulated Tile Tub/Shower Surrounds:
1) None.
2. Approved Manufacturers:
a. Simulated Tile Tub/Shower Surrounds:
1) Mincey Marble Manufacturing Co. (800-533-1806)
2) MPL Corporation (317-835-9000)
PART 12 EXECUTION
12.01 INSPECTION
A. Verify adequacy of backing and support framing.
12.02 PREPARATION
A. Condition cast polymer materials to average prevailing humidity conditions in installation areas
before installation.
12.03 INSTALLATION
A. All surrounds shall be installed as shown on Drawings and as specified by manufacturer.
B. Install components plumb, level and rigid, scribed to adjacent finishes, in accordance with
approved shop drawings and product data.
C. Tub/Shower Surrounds:
1. Remove all dust and other contaminants from the back side of all panels before
installation.
2. Secure soap dishes to panels with adhesive as recommended by Manufacturer.
3. Hold bottom edge of wall panel above rim of tub and shower for application of sealant as
shown on Drawings.
12.04 ADJUSTING AND CLEANING
A. Keep components clean during installation. Remove adhesives, sealants and other stains.
Keep clean until Date of Substantial Completion. Replace stained and damaged components.
B. Protect surfaces from damage until Date of Substantial Completion. Repair work or replace
damaged work which cannot be repaired to Owner's Representative's satisfaction.
END OF SECTION
Revision Log
PART 13 GENERAL
13.01 SUMMARY
A. Section Includes
1. Decorative Acrylic Resin Panels.
2. Decorative High Impact Thermoplastic Panels.
B. Related Sections:
1. Section 06 82 00 (09541) Glass-fiber reinforced plastic (FRP): For (FRP) wall paneling
and trim accessories.
2. Section 06 40 00 (06400) Architectural Woodwork for wood trim frames for decorative
plastic paneling.
13.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
13.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: For each type of product indicated.
2. Samples for Initial Selection: For plastic paneling and trim accessories.
3. Samples for Verification: For plastic paneling and trim accessories, in manufacturer's
standard sizes.
13.04 QUALITY ASSURANCE
A. Source Limitations: Obtain plastic paneling and trim accessories from single manufacturer.
B. Surface-Burning Characteristics: As determined by testing identical products according to
ASTM E84 by a qualified testing agency. Identify products with appropriate markings of
applicable testing agency.
1. Flame-Spread Index: As indicated.
2. Smoke-Developed Index: As indicated.
3. Testing Agency: Acceptable to authorities having jurisdiction.
13.05 PROJECT CONDITIONS
A. Environmental Limitations: Do not deliver or install plastic paneling until spaces are enclosed
and weathertight and temporary HVAC system is operating and maintaining ambient
temperature and humidity conditions at occupancy levels during the remainder of the
construction period.
PART 15 EXECUTION
15.01 EXAMINATION
A. Examine substrates and conditions, with Installer present, for compliance with requirements
for installation tolerances and other conditions affecting performance of the Work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
15.02 INSTALLATION OF DECORATIVE ACRYLIC RESIN PANELS
A. Provide panels in sizes and locations as indicated on drawings. Install units plumb, level and
true. Secure rigidly in place in accordance with manufacturer’s instructions.
B. Securely mount panels in accordance with manufacturer's instructions, with concealed
fasteners.
15.03 INSTALLATION OF DECORATIVE HIGH IMPACT THERMOPLASTIC PANELS
A. Surface Preparation: Surfaces shall be dust free, smooth, dry, firm and uniformly colored. Do
not install over non-porous surfaces. Do not install panels over new plaster or un-primed
walls. All surfaces shall be reviewed by the installer to determine that surface is suitable for
adherence of adhesives.
B. Prime walls as recommended by panel manufacturer.
C. Provide panels in sizes and locations as indicated on drawings. Install units plumb, level and
true. Cut panels in strict accordance with manufacturer’s recommendations. Secure rigidly in
place in accordance with manufacturer’s instructions.
END OF SECTION
Revision Log
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Sheet Membrane Waterproofing
2. Under-Slab-On-Grade Vapor Retarder
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-In-Place Concrete
2. Section 04 20 00 (04200) - Unit Masonry
3. Section 07 20 00 (07200) – Thermal Protection
1.02 REFERENCES
A. ASTM International Publications:
1. D4263 "Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet
Method"
2. D6506 “Standard Specification for Asphalt Based Protection for Below Grade
Waterproofing”
3. E1745 "Standard Specification for Water Vapor Retarders Used in Contact with Soil or
Granular Fill under Concrete Slabs"
4. E1643 “Standard Practice for Selection, Design, Installation, and Inspection of Water
Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs”
1.03 SYSTEM DESCRIPTION
A. General: Provide waterproofing that prevents the passage of liquid water under hydrostatic
pressure and complies with requirements as demonstrated by testing performed by an
independent testing agency of manufacturer’s current sheet membrane.
1.04 SUBMITTALS
A. Submit "Letter of Conformance" in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Include product data on each type of dampproofing and waterproofing product specified,
including data substantiating that materials comply with specified requirements.
a. Mark each copy to identify applicable products, characteristics, models, options and
other supplemental data to clearly communicate information specific to this project.
B. Samples, 3 x 6 inches minimum size, of each fluid-applied and sheet membrane waterproofing
material specified for Project.
1.05 QUALITY ASSURANCE
A. Installer Qualifications: Engage an experienced Installer who has completed fluid-applied and
sheet membrane waterproofing applications similar in material, design, and extent to that
indicated for Project and that has resulted in construction with a record of successful in-
service performance.
1. Assign work closely associated with waterproofing, including (but not limited to)
waterproofing accessories, and flashings used in conjunction with waterproofing,
PART 2 PRODUCTS
2.01 MATERIALS, GENERAL
A. General Compatibility: Provide products that are recommended by manufacturer to be fully
compatible with indicated substrates.
2.02 SHEET MEMBRANE WATERPROOFING
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. “Bituthene 4000”; Grace Construction Products (800-444-6459)
2. "CCW MiraDRI 860/861"; Carlisle Coatings and Waterproofing Inc. (800-527-7092)
3. “650 Waterproofing Membrane”; Polyguard Products Inc. (800-541-4994)
2.03 UNDER-SLAB-ON-GRADE VAPOR BARRIER:
A. Vapor Barrier Under-Slabs-On-Grade:
1. Plastic Vapor Retarder: ASTM E1745, Class A, with maximum performance rating of
0.01 perm as tested before and after mandatory conditioning (ASTM E1745 Section 7.1
and sub-paragraphs 7.1.1-7.1.5). Provide in lengths and widths required for least number
of seams.
a. Under Slab: 15 mils thick.
2. Accessories:
a. Vapor- Barrier Seam Tape: Pressure-sensitive tape of type recommended by vapor
retarder manufacturer for sealing joints and penetrations in vapor retarder.
Revision Log
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Water Repellent Coating Applied to All Exterior Exposed Masonry Unit Walls
B. Related Sections:
1. Section 04 20 00 (04200) - Masonry Units
4.02 REFERENCES
A. FS SS-W-110 - Water Repellent, Colorless, Silicone Resin Base.
4.03 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Submit product data including detailed test results of materials applied to surfaces similar
to requirements of this Section.
2. Submit manufacturer's instructions for methods and application procedures.
3. Submit manufacturer's certification indicating water repellent coating conforms to or
exceeds requirements stated herein.
4.04 QUALITY ASSURANCE
A. The Contractors involved with work covered by this Section shall have had a minimum of five
years experience using specified techniques for water repellent application.
B. Tradesman must be competent and experienced and shall demonstrate reasonable care
during performance of operations described in this Section.
C. Tests and Approvals:
1. Sample Area: Contractor shall apply a test area of wall surface from two to four square
feet in size for inspection and approval by the Owner’s Representative. Samples of
adjacent materials shall be tested for possible reaction with the water repellent. Such
samples shall be available for inspection by the Owner’s Representative.
2. If any part of this work shall be found defective (because of improper preparation of
surfaces or application of coating) at any time before the final acceptance of the item, the
Contractor shall, at his own expense, make good such defect to the satisfaction of the
Owner’s Representative.
4.05 PROJECT CONDITIONS
A. Protection:
1. Contractor shall provide, at all times, covered access to premises and necessary utilities,
space for storage of material and equipment, etc.
2. All activities shall be in compliance with local and governmental regulations and codes.
3. The surface and atmospheric temperature should be at least 40 degrees F. and rising
during application. Surfaces should be dry. Apply only in well ventilated areas. All
caulking (sealants) should be applied a minimum of 24 hours prior to application, or as
required by sealant manufacturer, whichever is greater, before application of water
repellent.
PART 5 PRODUCTS
5.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. “Hydrozo Enviroseal Double 7"; BASF Building Systems (800-433-9517)
2. "Sure Klean Weather Seal Siloxane WB"; ProSoCo, Inc. (800-255-4255)
PART 6 EXECUTION
6.01 PREPARATION
A. Verify surfaces to receive water repellent coatings are clean, free of efflorescence, oil, grease,
or other foreign matter detrimental to application.
B. Remove loose particles and foreign matter. Remove grease or oil with a solvent, effective
alkaline cleaner, or detergent as instructed by coating manufacturer. Scrub surfaces with
water.
C. Allow surfaces to dry prior to application.
D. Protect all surrounding areas as recommended by the manufacturer or as directed by the
Owner’s Representative.
1. Windows: Windows shall be protected from contact with materials by masking with
polyethylene or other approved techniques.
2. All polished stone, metal, or non-masonry surfaces shall be protected from contact with
the material by masking with polyethylene.
3. Masonry surfaces must be in good repair. All new construction or repointed surfaces
must be allowed to cure for a minimum of 28 days prior to application. Surfaces must be
completely dry.
6.02 APPLICATION
A. Test each surface and/or material to be treated to ensure compatibility and desired water
repellency results. The surface to be treated must be clean and free of all foreign matter and
as dry as possible to ensure penetration of the water repellent.
B. Apply material as supplied - do not dilute or alter material as packaged. Preferred method of
application is with low pressure, airless diaphragm-type spray equipment or with a heavily
saturated roller or brush. Apply in coverage rate as recommended by manufacturer for type of
material.
C. Protect adjacent surfaces not scheduled to receive coating. If applied on unscheduled
surfaces, remove immediately, by manufacturer approved method.
END OF SECTION
Revision Log
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Batt Insulation
a. Unfaced
b. Faced
2. Sound Attenuation Insulation
a. Mineral Fiber
b. Slag-Wool-Fiber/Rock-Wool-Fiber
3. Foundation Wall and Under Slab Insulation
a. Extruded Polystyrene Foam
4. Masonry Cavity Walls
a. Polyisocyanurate Board
5. Vapor Retarder
6. Insulation Baffles (Eave Ventilation Troughs)
B. Related Sections:
1. Section 04 20 00 (04200) - Unit Masonry
2. Section 05 40 00 (05400) - Cold-Formed Metal Framing
3. Section 06 10 00 (06100) - Rough Carpentry
4. Section 06 20 00 (06200) - Finish Carpentry
5. Section 07 10 00 (07100) – Dampproofing and Waterproofing
6. Section 07 24 00 (07240) - Exterior Insulation and Finish Systems (EIFS)
7. Section 07 24 19 (07241) – Water Drainage Exterior Insulation and Finish Systems
(EIFS)
8. Section 07 27 00 (07270) – Air Barriers
9. Section 07 46 46 (07460) – Fiber-Cement Siding
10. Section 07 42 13 (07410) – Metal Wall Panels
11. Section 07 62 00 (07620) - Sheet Metal Flashing and Trim
12. Section 07 84 00 (07840) - Firestopping
13. Section 07 81 29 (07845) - Ceramic Fiber Fireproofing
14. Section 09 21 16 (09255) - Gypsum Board Assemblies
7.02 REFERENCES
A. ASTM International Publications:
1. C578 "Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation"
PART 8 PRODUCTS
8.01 MANUFACTURERS
A. Unfaced Glass Fiber Batt Insulation
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. “ComfortTherm”; Johns-Manville (800-654-3103)
b. “EcoTouch”: Owens-Corning (800-438-7465)
c. “Sustainable Insulation”; CertainTeed Corp (800-223-8990)
d. “EcoBatt”; Knauf Insulation GmbH (800-825-4434)
e. No Substitution.
3. Approved Manufacturers:
PART 9 EXECUTION
9.01 EXAMINATION
A. Require Installer to examine substrates and conditions under which insulation work is to be
performed. A satisfactory substrate is one that complies with requirements of the section in
which substrate and related work is specified. Obtain Installer's written report listing
conditions detrimental to performance of work in this section. Do not proceed with installation
of insulation until unsatisfactory conditions have been corrected.
1. Verify adjacent materials are dry and ready to receive insulation.
2. Verify mechanical and electrical services within insulated spaces have been installed and
tested.
3. Verify substrate surface is flat, free of honeycomb, fins, irregularities, and materials that
will impede adhesive bond.
PART 10 SCHEDULES
10.01 SCHEDULES
A. Attic Insulation: [R=30], [batt fiberglass] insulation.
B. Exterior Wall Insulation: [R=19] batt fiberglass insulation. Completely fill void to thickness of
wall to STC requirements required.
C. Acoustic Insulation in Walls: [Unfaced, batt fiberglass] or [Mineral Fiber Sound-Attenuation],
batt fiberglass insulation friction fit, completely fill void to thickness of wall to STC
requirements required.
D. Acoustic Insulation in Floor/Ceiling assemblies: Faced or Unfaced batt fiberglass insulation to
meet [STC-50].
E. Rigid Board Insulation in Foundation Perimeter: [R-Value as required by code].
END OF SECTION
Revision Log
PART 11 GENERAL
11.01 SUMMARY
A. Section Includes:
1. Water Management Exterior Insulation and Finish Coating Systems Application with
secondary air/moisture barrier system as described and specified herein.
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 07 20 00 (07200) - Thermal Protection
3. Section 07 62 00 (07620) - Sheet Metal Flashing and Trim
4. Section 07 92 00 (07920) – Joint Sealants
11.02 REFERENCES
A. ASTM International Publications:
1. B117 "Standard Practice for Operating Salt Spray (Fog) Apparatus"
2. C150 “Standard Specification for Portland Cement“
3. C1063 “Standard Specification for Installation of Lathing and Furring to Receive Interior
and Exterior Portland Cement-Based Plaster”
4. C1177/C1177M “Standard Specification for Glass Mat Gypsum Substrate for Use as
Sheathing”
5. C1382 Test Method for Determining Tensile Adhesion Properties of Sealants When Used
in Exterior Insulation and Finish Systems (EIFS) Joints”
6. C1397 “Standard Practice for Application of Class PB Exterior Insulation and Finish
Systems”
7. C1481 “Standard Guide for Use of Joint Sealants with Exterior Insulation and Finish
Systems (EIFS)"
8. D578 “Standard Specification for Glass Fiber Strands”
9. D2247 “Standard Practice for Testing Water Resistance of Coatings in 100% Relative
Humidity”
10. D3273 "Standard Test Method for Resistance to Growth of Mold on the Surface of Interior
Coatings in an Environmental Chamber"
11. D3274 “Standard Test Method for Evaluating Degree of Surface Disfigurement of Paint
Films by Fungal or Algal Growth, or Soil and Dirt Accumulation”
12. D1784 “Standard Specification for Rigid Poly(Vinyl Chloride) (PVC) Compounds and
Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds”
13. D4258 "Standard Practice for Surface Cleaning Concrete for Coating"
14. D4261“Standard Practice for Surface Cleaning Concrete Unit Masonry for Coating”
15. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
PART 12 PRODUCTS
12.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. “Sto Essence Therm NExT”; Sto Finish Systems Div. (888-786-3437)
2. “Senerflex Channeled Adhesive Design” System; BASF Wall Systems (800-221-9255).
3. "Outsulation Plus MD EIFS"; Dryvit Systems, Inc. (800-556-7752)
4. “Parex WaterMaster EIFS”; Parex USA (866-516-0061)
5. “Master Wall Inc Rollershield Drainage EIFS”; Master Wall Inc (800-755-0825)
12.02 GENERAL:
A. All components of the wall system shall be obtained from one manufacturer. No substitutions
or addition of other materials will be allowed.
12.03 MATERIALS
A. Compatibility: Provide substrates, air/moisture barrier, integrated flashing, drainage
accessories, adhesive, board insulation, reinforcing meshes, base- and finish-coat materials,
and sealants that are compatible with one another and approved for use by system
manufacturer for Project.
B. Air/Moisture Barrier: A ready mixed acrylic based, fiber reinforced, water-resistive coating.
1. Install layer of air/water resistive barrier to completely cover sheathing before installation
of EIFS system.
2. Air/water resistive Barrier System Accessories: For use at substrate joints and at
openings in the substrate and penetrations through the substrate.
a. Joint Treatment: ready mixed acrylic based, flexible joint compound as
recommended by the manufacturer for use the air/moisture barrier.
b. Grid Tape: Open weave fiberglass mesh tape with pressure sensitive adhesive.
c. Flashing Tape: Self-adhesive type as recommended by the manufacturer for use
with the air/moisture barrier system.
d. Flashing Tape Surface Conditioner: As recommended by manufacturer for use with
system flashing tape.
e. Flexible Flashing Materials: Ready mixed, fluid applied with integral reinforcing
mesh scrim flexible flashing material; EIFS manufacturer’s standard.
PART 13 EXECUTION
13.01 EXAMINATION
A. Prior to application of the wall system, the substrate shall be examined by the installer for
compliance with the Contract Documents and manufacturer's specifications. The Contractor
and Owner’s representative shall be advised of all discrepancies. All substrates shall be free
of surface and excessive internal moisture. Work shall not proceed until unsatisfactory
conditions are corrected.
THE EXTERIOR INSULATION AND FINISH SYSTEM (EIFS) INSTALLED ON THE STRUCTURE
LOCATED AT THE ADDRESS BELOW:
CONFORMS DOES NOT CONFORM
TO:
(EFIS Manufacturer)
RECOMMENDED INSTALLATION PRACTICES AND PROJECT MANUAL SECTION 07 24 19 (07241)
(EIFS SPECIFICATION)
C. The information entered above is offered in testimony that the EIFS installation conforms with the listed EIFS
manufacturer's installation methods and procedures and all applicable model or jurisdictional building codes.
Note: An affidavit shall be received from the sealant installer indicating that the sealant installation conforms
with the EIFS minimum application requirements and sealant manufacturer's installation methods and
procedures and must accompany this declaration. These affidavits must be attached to the EIFS project
warranty for this project.
PART 14 GENERAL
14.01 SUMMARY
A. Section Includes:
1. Fluid-Applied Membrane Air Barrier
a. Vapor Permeable
2. Air-Infiltration Barrier
B. Related Sections:
1. Section 04 20 00 - Unit Masonry
2. Section 05 40 00 - Cold-Formed Metal Framing
3. Section 06 10 00 - Rough Carpentry
4. Section 07 10 00 - Dampproofing and Waterproofing
5. Section 07 20 00 - Thermal Protection
6. Section 07 24 19 – Water Drainage Exterior Insulation and Finish Systems (EIFS)
7. Section 07 62 00 - Sheet Metal Flashing and Trim
8. Section 07 92 00 - Joint Sealants
9. Section 09 21 16 - Gypsum Board Assemblies
14.02 REFERENCES
A. ASTM International Publications:
1. C578 "Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation"
2. C665 "Standard Specification for Mineral-Fiber Blanket Thermal Insulation for Light
Frame Construction and Manufactured Housing"
3. C1177 “Specification for Glass Mat Gypsum Substrate for Use as Sheathing”
4. C1193 "Standard Guide for Use of Joint Sealants"
5. D522 "Standard Test Methods for Mandrel Bend Test of Attached Organic Coatings"
6. D3273 "Standard Test Method for Resistance to Growth of Mold on the Surface of Interior
Coatings in an Environmental Chamber"
7. D4258 "Standard Practice for Surface Cleaning Concrete for Coating"
8. D4397 "Standard Specification for Polyethylene Sheeting for Construction, Industrial, and
Agricultural Applications"
9. D4541 “Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers”
10. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
11. E96 "Standard Test Methods for Water Vapor Transmission of Materials"
12. E119 "Standard Test Methods for Fire Tests of Building Construction and Materials"
13. E136 "Standard Test Method for Behavior of Materials in a Vertical Tube Furnace at
750°C"
PART 15 PRODUCTS
15.01 FLUID-APPLIED MEMBRANE AIR BARRIER - ABOVE GRADE
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers
1. “DuPont Tyvek Fluid Applied WB System”; DuPont Company (800-448-9835)
a. Joint Treatment: "Tyvek Fluid Applied Flashing and Joint Compound, Trowel Grade"
b. Membrane Air Barrier Coating: "DuPont Tyvek Fluid Applied System"
c. Flashing System: "Tyvek FlexWrap" and "Tyvek StraightFlash"
d. Sealant for use with System: “Dupont Sealant for Tyvek Fluid Applied System”
2. "Sto Guard"; Sto Corporation (800-221-2397)
a. Joint Treatment: "Sto Gold Coat with StoGuard Fabric"
b. Membrane Air Barrier Coating: "Sto Gold Coat"
c. Flashing System: "Sto Gold Coat with StoGuard Fabric"
PART 16 EXECUTION
16.01 EXAMINATION
A. Require Installer to examine substrates and conditions under which air barrier work is to be
performed. A satisfactory substrate is one that complies with requirements of the sections in
which substrate and related work is specified. Obtain Installer's written report listing
conditions detrimental to performance of work in this section. Do not proceed with installation
of insulation until unsatisfactory conditions have been corrected.
1. Verify adjacent materials are dry, free of contaminants and ready to receive barrier
system.
2. Verify substrate surface is flat, free of honeycomb, fins, irregularities, and materials that
will impede adhesive bond.
16.02 PREPARATION
A. Clean substrates of substances harmful to membranes, including removal of projections which
might puncture vapor retarders.
B. Inspect sheathing application for compliance with applicable requirement:
1. Exterior gypsum sheathing: GA-253
2. Glass mat faced gypsum sheathing: Consult manufacturer’s published
recommendations.
3. Remove surface contaminants and replace damaged sheathing.
4. Spot surface defects in sheathing with joint treatment as recommended by membrane
manufacturer.
5. Repair cracks, spalls, or other damage in concrete or concrete masonry surfaces
PART 17 GENERAL
17.01 SUMMARY
A. Section Includes:
1. Exterior, Panelized Fiber Cement Cladding System and Accessories to Complete a
Drained and Back-Ventilated Rainscreen
2. Continuous Soffit Vent
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 07 20 00 (09900) – Thermal Protection
4. Section 07 27 00 (07270) - Air Barriers
5. Section 07 92 00 (07900) – Joint Sealants
6. Section 09 90 00 (09900) – Painting
17.02 REFERENCES
A. American Architectural Manufacturers Association (AAMA) Publications:
1. 509 “Voluntary Test and Classification Method of Drained and Back Ventilated Rain
Screen Wall Cladding Systems”
B. ASTM International (ASTM) Publications: (Former American Society for Testing and
Materials)
1. C518 "Standard Test Method for Steady-State Thermal Transmission Properties by
Means of the Heat Flow Meter Apparatus"
2. C1185 "Standard Test Methods for Sampling and Testing Non-Asbestos Fiber-Cement
Flat Sheet, Roofing and Siding Shingles, and Clapboards"
3. C1186 "Standard Specification for Flat Non-Asbestos Fiber-Cement Sheets"
4. D3359 “Standard Test Methods for Measuring Adhesion by Tape Test”
5. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
6. E119 “Standard Test Methods for Fire Tests of Building Construction and Materials”
7. E136 "Standard Test Method for Behavior of Materials in a Vertical Tube Furnace at
750°C"
8. E228 ‘Standard Test Method for Linear Thermal Expansion of Solid Materials with a
Vitreous Silica Dilatometer”
9. E330 “Standard Test Method for Structural Performance of Exterior Windows, Doors,
Skylights and Curtain Walls by Uniform Static Air Pressure Difference”
10. E331 “Standard Test Method for Water Penetration of Exterior Windows, Skylights,
Doors, and Curtain Walls by Uniform Static Air Pressure Difference”
11. G23 (Replaces G152-00ae1, ASTM G153-00ae1, ASTM G25-70(1975) and ASTM E188-
70) -
C. D. National Fire Protection Association (NFPA) Publications:
PART 19 EXECUTION
19.01 EXAMINATION
A. Examine substrates, with Installer present, for compliance with requirements for installation
tolerance and other conditions affecting installation and performance of fiber-cement
products. Do not proceed with installation until unsatisfactory conditions have been
corrected.
19.02 PREPARATION
A. Clean substrates of projections and substances detrimental to application.
B. Do not install panels or components that appear to be damaged or defective. Do not install
wet panels.
C. Air Infiltration Barrier Installation:
1. One layer of air infiltration barrier shall be installed horizontally on walls. Weatherlap
edges and ends minimum 6". Refer to Section 07 20 00.
2. Stagger vertical joints.
3. Install in accordance with air infiltration barrier manufacturer's recommendations.
19.03 INSTALLATION - GENERAL
A. Discard units of material which are unsound, warped, bowed, twisted improperly treated, not
adequately seasoned or too small to fabricate work with minimum of joints or optimum
jointing arrangements. Do not use manufactured units with defective surfaces, sizes, or
patterns.
B. Install the work plumb, level, true, and straight with no distortions. Shim as required using
concealed shims. Install to a tolerance of 1/8" in 8'-0" for plumb and level countertops; and
with 1/16" maximum offset in flush adjoining 1/8" maximum offsets in revealed adjoining
surfaces.
C. Scribe and cut work to fit adjoining work, and refinish cut surfaces or repair damaged finish at
cuts.
D. Countersink nails, fill surface flush, and sand where face nailing is unavoidable.
E. Install to tolerance of 1/8 inch in 96 inches for plumb and level. Install adjoining fiber-cement
siding or trim with 1/32 inch maximum offset for flush installation and 1/16 inch maximum
offset for reveal installation.
F. Coordinate fiber-cement siding with materials and systems in or adjacent to standing and
running trim. Provide cutouts for mechanical and electrical items that penetrate exposed
surfaces of siding or trim.
G. Finish according to specified requirements.
Revision Log
PART 20 GENERAL
20.01 SUMMARY
A. Section Includes:
1. Extent of metal roofing is shown on the Drawings and indicated by provisions of this
Section.
2. The following types of work are specified in this Section:
a. Standing Seam Roof System
b. Flashings
c. Matching Fascia
d. Underlayment.
1) Self-Adhering Sheet Underlayment
B. Related Sections:
1. Section 05 31 00 (05300) - Metal Deck
2. Section 05 40 00 (05400) - Cold-Formed Metal Framing
3. Section 06 10 00 (06100) - Rough Carpentry
4. Section 07 20 00 (07200) - Thermal Protection
5. Section 07 42 13 (07410) – Metal Wall Panels
6. Section 07 62 00 (07620) - Sheet Metal Flashing and Trim
20.02 REFERENCES
A. ASTM International Publications:
1. A653 “Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron
Alloy-Coated (Galvannealed) by the Hot-Dip Process”
2. D1970 “Standard Specification for Self-Adhering Polymer Modified Bituminous Sheet
Materials Used as Steep Roofing Underlayment for Ice Dam Protection”
3. E1646 “Standard Test Method for Water Penetration of Exterior Metal Roof Panel
Systems by Uniform Static Air Pressure Difference”
4. E1680 “Standard Test Method for Rate of Air Leakage Through Exterior Metal Roof
Panel Systems”
B. Sheet Metal and Air Conditioning Contractors' National Association (SMACNA) Publications:
PART 21 PRODUCTS
21.01 ACCEPTABLE MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. "Standing Seam Tee-Panel System"; Berridge Manufacturing Company (800-231-8127)
2. "Dutch Seam (MRD) Panel System"; ATAS International, Inc. (800-468-1441)
3. “Snap-On-Seam SS10-12 Panel System”; Dimensional Metals Inc. (DMI) (800-828-1510)
4. "Snap-Clad Panels"; Petersen Aluminum Corporation (PAC-CLAD) (800-722-7150)
21.02 DESIGN LOADS
A. The basic design loads shall include roof live and snow (where applicable), wind (both
external and internal), and earthquake (where applicable), in addition to dead load. All other
foreign loads, whether they be of static, dynamic, or kinetic nature, shall be considered as
auxiliary loads. Refer to Drawings for design loads.
21.03 ROOF COVERING
A. All roof constructions shall carry the Underwriter's Laboratories, Inc. (UL) Construction (Uplift)
rating of not less than Class 90.
B. Roof System
1. The roof system shall be composed of the following:
a. Panels shall be nominal [11”][12-3/4"] seam on center with snap-on seam. Fabricate
from 0.032 inch Aluminum Coil Coated Sheet, ASTM B209 Alloy, smooth surface.
b. Flouropolymer finish to be Kynar 500. Coating to be two-coat, thermo-cured, full-
strength 70% "Kynar 500" fluouropolymer coating. Manufacturer warrants that
coating shall not blister, peel, crack, chip, or experience rust-through for ten (10)
years.
PART 22 EXECUTION
22.01 PREPARATION
A. Coordinate metal roofing and wall system with rain drainage work, flashing, trim and
construction of decks, parapets, walls, and other adjoining work, to provide a permanently
leakproof, secure and non-corrosive installation.
22.02 INSTALLATION - UNDERLAYMENT
A. Self-Adhering Sheet Underlayment: Install self-adhering sheet underlayment, wrinkle free, on
roof sheathing under sheet metal roofing. Apply primer if required by underlayment
manufacturer. Comply with temperature restrictions of underlayment manufacturer for
installation; use primer rather than nails for installing underlayment at low temperatures.
Apply over entire roof, in shingle fashion to shed water, with end laps of not less than 6 inches
staggered 24 inches between courses. Overlap side edges not less than 3-1/2 inches. Roll
laps with roller. Cover underlayment within 14 days.
B. Install flashings to cover underlayment to comply with requirements specified in Division 07
Section "Sheet Metal Flashing and Trim."
C. Apply slip sheet over underlayment before installing sheet metal roofing.
22.03 INSTALLATION - SHEET METAL ROOFING
A. Manufacturer's Recommendations: Except as otherwise shown or specified, comply with
recommendations and instructions of manufacture of sheet metal being fabricated and
installed.
B. Separate dissimilar metals from each other by painting each metal surface in area of contact
with a bituminous coating, or by applying adhesive polyethylene underlayment to each metal
surface, or by other permanent separation as recommended by manufacturers of dissimilar
metals.
C. Form and fabricate sheets, seams, strips, cleats, valleys, ridges, edge treatments, integral
flashings and other components of metal roofing to profiles, patterns and drainage
arrangements shown, and as required for permanently leakproof construction. Provide for
thermal expansion and contraction of the work. Seal joints as shown, and as required for
leakproof construction. Shop fabricate materials to greatest extent possible.
D. Sealant Type Joints: Where sealant filled joints are used, embed hooked flanges of joint
members not less than 1" into sealant. Form joints to completely conceal sealant. When
ambient temperature is moderate at time of installation (40 deg. to 70 deg. F), set joint
members for 50% movement either way. Adjust setting proportionately for installation at
higher ambient temperatures. Do not install sealant type joints at temperatures below 40 deg.
F. Comply with requirements of Division 07 - Sealant section for the handling and installation
of sealants.
E. Fabricate and install work with lines and corners of exposed units true and accurate. Form
exposed faces flat and free of buckles, excessive waves and avoidable tool marks considering
temper and reflectivity of metal. Provide uniform, neat seams with minimum exposure of
solder, welds, and sealant. Except as otherwise shown, fold back sheet metal to form a hem
on concealed side of exposed edges.
F. Conceal fasteners and expansion provisions where possible in exposed work, and locate so
as to minimize possibility of leakage. Cover and seal fasteners and anchors as required for a
tight installation.
END OF SECTION
PART 23 GENERAL
23.01 SUMMARY
A. Section Includes:
1. Flashing at Roof, Windows, Doors, and other locations as shown on Drawings.
2. Roof Drainage Systems:
a. Gutters
b. Downspouts
3. Aluminum Soffit
4. Vinyl Soffit
5. Gable End Louvers
6. Aluminum Formed Cap Flashings (Copings)
7. Fasteners
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 07 20 00 (07200) - Thermal Protection
3. Section 07 24 00 (07240) - Exterior Insulation and Finish Systems (EIFS)
4. Section 07 27 00 (07270) – Air Barriers
5. Section 07 31 13 (07311) - Asphalt Shingles
6. Section 07 42 13 (07410) – Metal Wall Panels
7. Section 07 46 00 (07460) - Siding
8. Section 07 51 16 (07512) - Built-Up Coal Tar Roofing
9. Section 07 53 21 (07530) - Elastomeric Membrane Roofing
10. Section 07 61 00 (07610) - Sheet Metal Roofing
11. Section 07 72 33 (07720) - Roof Specialties: Roof Hatches
12. Section 07 92 00 (07920) – Joint Sealants
13. Section 08 11 13 (08110) - Steel Doors and Frames
14. Section 08 32 13 (08163) - Sliding Aluminum-Framed Glass Doors
15. Section 08 41 13 (08410) - Aluminum Entrances and Storefronts
16. Section 08 42 29 (08460) - Automatic Entrance Doors
17. Section 08 51 13 (08520) - Aluminum Windows
18. Section 08 53 00 (08560) - Plastic Windows
19. Section 23 81 13 (15735) - Packaged Terminal Air-Conditioning Units
20. Section 23 37 00 (15850) - Air Inlets & Outlets
PART 24 PRODUCTS
24.01 ALUMINUM FLASHING AND SHEET METAL
A. Materials:
1. Aluminum Sheet: ASTM B209, Alloy 3003, Temper H14, AA-C22A41, minimum .032
inch thick (20 ga) sheet.
a. Finish: 5-year Fluoropolymer 2-Coat System: Manufacturer's standard 2-coat,
thermocured system consisting of specially formulated inhibitive primer and
fluouropolymer color topcoat containing not less than 70 percent polyvinylidene
fluoride resin by weight; complying with AAMA 2604 where exposed.
2. Fasteners: Concealed type; of same material as flashings; sized to suit application.
3. Size and shape as shown on Drawings.
4. Color: Refer to Exterior Finish Index.
24.02 MEMBRANE FLASHING
A. Wall Flashing:
1. Avendra, LLC Preferred Manufacturers:
a. None
PART 25 EXECUTION
25.01 INSTALLATION - GENERAL
A. Comply with manufacturer's instructions and recommendations for handling and installation of
flashing and sheet metal work.
B. Performance: Coordinate the work with other work for the correct sequencing of items which
make up the entire membrane or system of weatherproofing or waterproofing and rain
drainage. It is required that the flashing and sheet metal work be permanently watertight, and
not deteriorate in excess of manufacturer's published limitations.
C. Examine substrates and conditions under which sheet metal flashing and trim are to be
installed and verify that work may properly commence. Do not proceed with installation until
unsatisfactory conditions have been corrected.
END OF SECTION
Revision Log
PART 26 GENERAL
26.01 SUMMARY
A. Section Includes:
1. Prefabricated roof hatches with integral support curbs, operable hardware, and
counterflashings.
2. Prefabricated Rail System
3. Ladder Safety Post
B. Related Sections:
1. Section 07 53 23 (07530) - Ethylene-Propylene-Diene-Monomer (EPDM) Roofing
2. Section 07 62 00 (07620) - Sheet Metal Flashing and Trim
26.02 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Submit product data which shall include general construction, configurations, jointing
methods, and locations when applicable, and fastening methods. Include manufacturer's
instructions.
26.03 QUALITY ASSURANCE
A. Standards: Comply with the following:
1. SMACNA’s Architectural Sheet Metal Manual” details for fabrication of units, including
flanges and cap flashing to coordinate with type of roofing indicated.
2. NRCA’s “Roofing and Waterproofing Manual” details for installing units.
26.04 PROJECT CONDITIONS
A. Verify that other trades with related work are complete before installing roof hatch and rail
system. Coordinate installation with roof membrane and roof insulation manufacturer’s instructions.
B. Refer to the Construction Documents, shop drawings, and manufacturer’s installation
instructions.
C. Mounting surfaces shall be straight and secure; substrates shall be of proper width.
D. Observe all appropriate OSHA safety guidelines for this work
E. Coordinate layout and installation of roof accessories with interfacing and adjoining
construction to provide a leak-proof, weather-tight, secure, and non-corrosive installation.
1. With [Architect's] [Owner’s Representative] approval, adjust location of roof accessories
that would interrupt roof drainage routes
PART 27 PRODUCTS
27.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
PART 28 EXECUTION
28.01 INSTALLATION
A. General: Comply with manufacturer’s written instructions. Coordinate installation of roof
accessories with installation of roof deck, roof insulation, flashing, roofing membranes,
penetrations, equipment, and other construction involving roof accessories to ensure that each
element of the Work performs properly and that combined elements are waterproof and
weathertight. Anchor roof accessories securely to supporting structural substrates so they are
capable of withstanding lateral and thermal stresses, and inward and outward loading
pressures.
B. Install roof accessory items according to construction details of NRCA’s “Roofing and
Waterproofing Manual,” unless otherwise indicated.
C. Separation: Separate metal from incompatible metal or corrosive substrates, including wood,
by coating concealed surfaces, at locations of contact, with bituminous coating or providing
other permanent separation.
END OF SECTION
Revision Log
PART 29 GENERAL
29.01 SUMMARY
A. Section Includes:
1. Concealed Sprayed-on Fireproofing
a. New structural steel, unpainted.
2. Protection of Adjacent Surfaces from Overspraying
B. Related Sections:
1. Section 05 12 00 (05120) - Structural Steel
2. Section 05 31 00 (05310) - Steel Deck
29.02 QUALITY ASSURANCE
A. Fire-Test-Response Characteristics: Provide sprayed-on fireproofing products identical to
those used in assemblies tested for the following fire-test-response characteristics, per test
method indicated below, by UL or another testing and inspecting agency acceptable to
authorities having jurisdiction. Identify packages (bags) containing fireproofing with
appropriate classification markings of applicable testing and inspecting agency.
1. Fire-Resistance Ratings: As indicated by reference to fire-resistive designs listed in UL
"Fire Resistance Directory", or in the comparable publication of another testing and
inspecting agency acceptable to authorities having jurisdiction, for fire-resistive
assemblies where sprayed-on fireproofing serves as direct-applied protection, tested per
ASTM E119.
2. Surface-burning Characteristics: As indicated for each sprayed-on fireproofing product
required, tested per ASTM E84.
B. Installer Qualifications: Engage an experienced installer certified, licensed, or otherwise
qualified by the sprayed-on fireproofing manufacturer as having the necessary experience,
staff, and training to install manufacturer's products per specified requirements. A
manufacturer's willingness to sell its sprayed-on fireproofing products to the Contractor or to
an installer engaged by the Contractor does not in itself confer qualification on the buyer.
C. Single-Source Responsibility: Obtain sprayed-on fireproofing materials from a single
manufacturer for each different product required.
D. Provide fireproofing products containing no detectable asbestos as determined according to
the method specified in 40 CFR Part 763, Subpart F, Appendix A, Section 1, Polarized Light
Microscopy.
29.03 REFERENCES
A. ASTM International Publications:
1. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
2. E119 "Standard Test Methods for Fire Tests of Building Construction and Materials"
3. E605 “Standard Test Methods for Thickness and Density of Sprayed Fire-Resistive
Material (SFRM) Applied to Structural Members”
PART 30 PRODUCTS
30.01 CONCEALED SPRAYED-ON FIREPROOFING MATERIALS
A. Manufacturers:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers
a. "Monokote Type MK-6"; Grace Construction Products, W.R. Grace & Co. (800-778-
2880)
B. General: For concealed applications of sprayed-on fireproofing, provide manufacturer's
standard products complying with requirements indicated in this article for material
composition and physical properties representative of installed products.
C. Material Composition: Composition indicated below:
1. Cementitious fireproofing consisting of factory-mixed, dry formulation of gypsum or
portland cement binders and lightweight mineral or synthetic aggregates mixed with
water at project site to form a slurry or mortar for conveyance and application.
D. Physical Properties: Minimum values, unless otherwise indicated, or higher values required to
attain designated fire-resistance ratings, measured per standard test methods referenced with
each property listed below:
1. Bond Strength: 150 lbf per sq. ft. as determined per ASTM E736 under the following
conditions:
a. Field-test sprayed-on fireproofing that is applied to flanges of wide-flange structural
steel members on surfaces matching those that will exist for remainder of steel
receiving fireproofing.
b. Minimum sprayed-on fireproofing thickness tested in laboratory shall be 0.75 inch.
2. Compressive Strength: 5.21 lbf per sq. inch as determined in the laboratory per
ASTM E761. Minimum sprayed-on fireproofing thickness tested shall be 0.75 inch and
the minimum dry density shall be as specified, but not less than 15 pcf.
PART 31 EXECUTION
31.01 EXAMINATION
A. Examine substrates with installer present to determine if they are in satisfactory condition to
receive sprayed-on fireproofing. A substrate is in satisfactory condition if it complies with the
following:
1. Substrates comply with requirements in the Section where the substrate and related
materials and construction are specified.
2. Substrates are free of oil, grease, rolling compounds, incompatible primers, loose mill
scale, dirt, or other foreign substances capable of impairing bond of fireproofing with
substrate under conditions of normal use or fire exposure.
3. Objects penetrating fireproofing, including clips, hangers, support sleeves, and similar
items, are securely attached to substrates.
END OF SECTION
Revision Log
PART 32 GENERAL
32.01 SUMMARY
A. Section Includes:
1. Mineral Fiber Blanket Fireproofing.
B. Related Sections:
1. Section 07 84 00 (07840) - Firestopping
2. Section 23 31 13 (15185) – Metal Ducts
3. Division 23 Sections for additional requirements
32.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and
Materials):
1. C1338 “Standard Test Method for Determining Fungi Resistance of Insulation Materials
and Facings
2. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
3. E119 (UL 263) “Standard Test Methods for Fire Tests of Building Construction and
Materials”
4. E814 (UL 1479) “Standard Test Method for Fire Tests of Penetration Firestop Systems”
5. E2336 “Standard Test Methods for Fire Resistive Grease Duct Enclosure Systems”
B. International Standards Organization (ISO):
1. 6944 “Fire Resistive Tests - Ventilation Ducts”
C. National Fire Protection Association (NFPA) Publications:
1. 96 “Standard for Ventilation Control and Fire Protection of Commercial Cooking
Operations”
D. Underwriter's Laboratories, Inc. (UL) Standards:
1. 723 “Test for Surface Burning Characteristics of Building Materials”
2. 1479 “Standard for Fire Tests of Through-Penetration Firestops”
3. 2221 “Standard for Tests of Fire Resistive Grease Duct Enclosure Assemblies”
32.03 SYSTEM DESCRIPTION
A. Performance Requirements:
1. Fireproofing System: Provide a fire rated assembly rating for grease duct assembly.
Grease duct enclosure shall have been tested in accordance with an approved testing
agency acceptable to local code jurisdiction, and shall be listed in UL Fire Protection
Equipment Directory as an approved Grease Duct Enclosure.
PART 33 PRODUCTS
33.01 MANUFACTURER
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. "3M Fire Barrier Duct Wrap 615+"; 3M Building and Commercial Services Division (800-
328-1687)
2. “Thermal Ceramics FireMaster FastWrap XL or Pyroscat DuctWrap XL”; Thermal
Ceramics Inc. (706-796-4306
3. “FyreWrap”; Unifrax (716-278-3800)
4. Approved Substitution.
PART 34 EXECUTION
34.01 EXAMINATION
A. Examine surfaces and adjacent areas in which Work under this Section is to be performed.
Report in writing to the Owner’s Representative] prevailing conditions that may adversely
affect satisfactory execution of Work. Do not proceed with Work until unsatisfactory conditions
have been corrected.
B. Starting Work constitutes acceptance of the existing conditions and this Contractor shall then,
at their expense, be responsible for correcting all unsatisfactory and defective Work
encountered.
34.02 INSTALLATION
A. Comply with manufacturer's instructions for particular conditions of installation in each case.
Consult with manufacturer's technical representative for conditions not covered by printed
instructions.
END OF SECTION
Revision Log
PART 35 GENERAL
35.01 SUMMARY
A. Section Includes:
1. Penetrations through fire-resistance-rated floor and roof construction, including both
empty openings and openings containing cables, pipes, ducts, conduits, and other
penetrating items.
2. Penetrations through fire-resistance-rated walls and partitions, including both empty
openings and openings containing cables, pipes, ducts, conduits, and other penetrating
items.
3. Joints at walls, floors, top of wall (head of wall) at floor and roof assemblies, edge of floor
slabs at exterior walls, and openings around structural members which penetrate floor
and wall assemblies.
B. Related Sections:
1. Section 07 81 33 (07265) - Mineral Fiber Fireproofing
2. Refer to Divisions 21/22/23 and 26/27 Sections for additional requirements.
35.02 REFERENCES
A. ASTM International Publications:
1. E119 "Standard Test Methods for Fire Tests of Building Construction and Materials"
2. E814 “Standard Test Method for Fire Tests of Through-Penetration Fire Stops”
3. E1966, “Standard Test Method for Fire Resistive Joint Systems”
4. E2174, “Standard Practice for On-site Inspection of Installed Fire Stops”
5. E2307, “Standard Test Method for Determining Fire Resistance of Perimeter Fire Barrier
Systems Using Intermediate-Scale, Multi-story Test Apparatus”
B. Code of Federal Regulations (CFR) Publications:
1. 40 CFR 763, Subpart F, Appendix A, Section 1 “Polarized Light Microscopy"
C. Underwriter's Laboratories, Inc. (UL) Standards
1. "Fire Resistance Directory"
2. 1479 “Fire Tests of Through-Penetration Firestops”
3. 2079 “Tests for Fire Resistance of Building Joint Systems”
D. Warnock Hersey, ETL SEMKO division of Intertek (WHI) Publications:
1. "Certification Listings"
E. Omega Point Laboratories, Inc. ETL SEMKO division of Intertek (OPL) Publications:
1. “Directory of Listed Building Products, Materials and Assemblies”
F. South Coast Air Quality Management District (SCAQMD):
1. “South Coast Rule #1168 Architectural Coatings”
PART 36 PRODUCTS
36.01 APPROVED MANUFACTURERS:
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. 3M Brand Fire Protection Products (800-328-1687)
2. Hilti, Inc. (800-879-6000)
3. Specified Technologies Inc. (STI) (800-992-1180)
4. ProSet Systems, Inc. (800-262-5355)
36.02 FIRESTOPPING - GENERAL
A. Use only firestop products that have been UL 1479 or ASTM E814 tested for specific fire-rated
construction conditions conforming to construction assembly type, penetrating item type,
annular space requirements, and fire-rating involved for each separate instance.
B. Compatibility: Provide firestopping composed of components that are compatible with each
other, the substrates forming openings, and the items, if any, penetrating the firestopping
under conditions of service and application, as demonstrated by firestopping manufacturer
based on testing and field experience.
1. For penetrations involving CPVC piping, provide through-penetration firestop systems
which include materials that have been tested to be compatible with CPVC piping.
C. Accessories: Provide components for each firestopping system that are needed to install fill
materials and to comply with the "System Performance Requirements" paragraph under
“System Description” in Part 1. Use only components specified by the firestopping
manufacturer and approved by the qualified testing and inspecting agency for the designated
fire-resistance-rated systems. Accessories include, but are not limited to, the following items:
1. Permanent Forming/Damming/Backing Materials, Including the following:
a. Semi-refractory Fiber (mineral wool) Insulation
b. Ceramic Fiber
PART 37 EXECUTION
37.01 EXAMINATION
A. Examine substrates and conditions, with installer present, for compliance with requirements
for opening configurations, penetrating items, substrates, and other conditions affecting
performance of firestopping. Do not proceed with installation until unsatisfactory conditions
have been corrected.
37.02 PREPARATION
A. Surface Cleaning: Clean out openings and joints immediately prior to installing firestopping to
comply with recommendations of firestopping manufacturer and the following requirements:
1. Remove all foreign materials from surfaces of opening and joint substrates and from
penetrating items that could interfere with adhesion of firestopping.
2. Clean opening and joint substrates and penetrating items to produce clean, sound
surfaces capable of developing optimum bond with firestopping. Remove loose particles
remaining from cleaning operation.
3. Remove laitance and form release agents from concrete.
B. Priming: Prime substrates where recommended by firestopping manufacturer using that
manufacturer's recommended products and methods. Confine primers to areas of bond. Do
not allow spillage and migration onto exposed surfaces.
C. Masking Tape: Use masking tape to prevent firestopping from contacting adjoining surfaces
that will remain exposed upon completion of work and that would otherwise be permanently
stained or damaged by such contact or by cleaning methods used to remove smears from
firestopping materials. Remove tape as soon as it is possible to do so without disturbing
firestopping's seal with substrates.
37.03 INSTALLATION - THROUGH-PENETRATION FIRESTOPS
A. General: Comply with the "System Performance Requirements" paragraph under “System
Description” in Part 1, and the firestop manufacturer's installation instructions and drawings
pertaining to products and applications indicated.
END OF SECTION
Revision Log
PART 38 GENERAL
38.01 SUMMARY
A. Section Includes:
1. Clean and Prepare Joint Surfaces
2. Sealant and Backing Materials including primers, backer rods, bond breakers and
accessories.
B. Related Sections:
1. Section 04 20 00 (04200) - Unit Masonry
2. Section 07 24 19 (07241) - Water Drainage Exterior Insulation and Finish Systems (EIFS)
3. Section 07 62 00 (07600) - Sheet Metal Flashing and Trim
4. Section 07 84 00 (07840) - Firestopping
5. Section 08 11 13 (08110) - Steel Doors and Frames
6. Section 08 32 13 (08163) - Sliding Aluminum-Framed Glass Doors
7. Section 08 14 00 (08200) - Wood and Plastic Doors
8. Section 08 41 13 (08410) - Aluminum Framed Entrances and Storefronts
9. Section 08 51 13 (08520) - Aluminum Windows
10. Section 08 80 00 (08800) - Glazing
11. Section 09 21 16 (09255) - Gypsum Board Assemblies
12. Section 09 30 00 (09310) - Tiling
13. Section 09 72 00 (09950) - Wall Coverings
14. Section 09 90 00 (09900) - Painting
38.02 REFERENCES
A. ASTM International Publications:
1. C834 “Standard Specification for Latex Sealants”
2. C920 “Standard Specification for Elastomeric Joint Sealants”
3. C1193 "Standard Guide for Use of Joint Sealants"
4. C1248 “Standard Test Method for Staining of Porous Substrate by Joint Sealants”
5. ASTM D1056 “Standard Specification for Flexible Cellular Materials-Sponge or Expanded
Rubber”
B. Code of Federal Regulations (CFR) Publications:
1. 21 CFR, Part 177 “Indirect Food Additives: Polymers”
C. Federal Specifications (FS) Publications:
1. TT-S-1543B Sealing Compound; Silicone Rubber Base (For Caulking, Sealing)
D. Underwriter's Laboratories, Inc. (UL) Standards
PART 39 PRODUCTS
39.01 MANUFACTURERS
A. Products listed below shall be as offered by one of the following manufacturers:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. Dow Corning Corp. (800-248-2481)
b. General Electric (GE) Silicones (800-255-8886)
c. BASF Building Systems (952-496-6000)
d. Bostik Inc. (800-523-2678)
PART 40 EXECUTION
40.01 EXAMINATION
A. Examine joints indicated to receive joint sealers, with Installer present, for compliance with
requirements for joint configuration, installation tolerances and other conditions affecting joint
sealer performance. Do not proceed with installation of joint sealers until unsatisfactory
conditions have been corrected. Beginning of Installation means acceptance of all existing
conditions making this Contractor responsible for correcting all unsatisfactory and defective
work encountered at his expense.
40.02 PREPARATION
A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealers to
comply with recommendations of joint sealer manufacturers and the following requirements:
1. Remove all foreign material from joint substrates which could interfere with adhesion of
joint sealer, including dust; paints, except for permanent, protective coatings tested and
approved for sealant adhesion and compatibility by sealant manufacturer; old joint
sealers; oil; grease; waterproofing; water repellents; water; surface dirt; and frost.
2. Clean concrete, masonry, unglazed surfaces of ceramic tile and similar porous joint
substrate surfaces, by brushing, grinding, blast cleaning, mechanical abrading, or a
combination of these methods to produce a clean, sound substrate capable of developing
optimum bond with joint sealers. Remove loose particles remaining from above cleaning
operations by vacuuming or blowing out joints with oil-free compressed air. Remove
laitance and form release agents from concrete.
B. Joint Priming: Prime joint substrates where indicated or where recommended by joint sealer
manufacturer based on preconstruction joint sealer-substrate tests or prior experience. Apply
primer to comply with joint sealer manufacturer's recommendations. Confine primers to areas
of joint sealer bond, do not allow spillage or migration onto adjoining surfaces.
D. The information entered above is offered in testimony that the Sealant installation conforms with the listed
sealant manufacturer's installation methods and procedures and the EIFS manufacturer's minimum
recommendations..
END OF SECTION
Revision Log
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Interior Hollow Metal Doors and Frames
2. Exterior Hollow Metal Doors and Frames
B. Related Sections:
1. Section 07 92 00 (07920) – Joint Sealants
2. Section 08 14 00 (08200) - Wood Doors
3. Section 08 71 00 (08710) - Door Hardware
4. Section 08 80 00 (08800) - Glazing
5. Section 09 90 00 (09900) - Painting
1.02 REFERENCES
A. ASTM International (ASTM) Publications:
1. A153 "Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware"
2. A568 "Standard Specification for Steel Sheet, Carbon, and High-Strength, Low-Alloy,
Hot-Rolled and Cold-Rolled, General Requirements for"
3. A591 "Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron
Alloy-Coated (Galvannealed) by the Hop-Dip Process"
4. A653 "Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron
Alloy-Coated (Galvannealed) by the Hot-Dip Process"
5. A924 "Standard Specification for General Requirements for Steel Sheet, Metallic-Coated
by the Hot-Dip Process"
6. A1008 "Standard Specification for Steel Sheet, Cold-Rolled, Carbon, Structural, High-
Strength Low-Alloy and High-Strength Low-Alloy with Improved Formability"
7. A1011 "Standard Specification for Steel Sheet and Strip, Hot-Rolled, Carbon, Structural,
High-Strength Low-Alloy and High-Strength Low-Alloy with Improved Formability"
8. C143 “Standard Test Method for Slump of Hydraulic Cement Concrete”
9. C476 “Standard Specification for Grout for Masonry”
10. E90 "Standard Test Method for Laboratory Measurement of Airborne Sound
Transmission Loss of Building Partitions and Elements"
11. E413 “Classification for Rating Sound Insulation”
12. E2074 "Standard Test Method for Fire Tests of Door Assemblies, Including Positive
Pressure Testing of Side-Hinged and Pivoted Swinging Door Assemblies"
B. American National Standards Institute (ANSI) Publications:
1. ANSI/SDI A250.3 "Test Procedure and Acceptance Criteria for Factory Applied Finish
Painted Steel Surfaces for Steel Doors and Frames"
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 1 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 2 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 3 ▪
PART 2 PRODUCTS
2.01 DISTRIBUTOR
A. Avendra, LLC Preferred Manufacturers:
1. Contract Hardware, Inc. (404-350-9408)
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 4 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 5 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 6 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 7 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 8 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 9 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 10 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 11 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 12 ▪
END OF SECTION
Revision Log
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 13 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Types of doors required include the following:
a. Wood Doors with Wood Veneer Faces:
1) Solid Core Flush Doors at Back-of House (except where shown as 2-Panel).
b. Composite Wood Doors:
1) Two-Panel Design at Public Space, Back-of-House (except where shown as
Flush), Guestroom Entry, and Guestroom Connecting Doors.
2) Two-Panel Design at Guestroom Bath, Bedroom, and Closet Doors.
3) Two-Panel Design on Bathroom side, and flush with surface-applied Mirror on
Bedroom Side, at Accessible Guestroom Baths.
4) Three-Panel Sliding Door with Glass Lites at Breakfast Room to Serving.
c. Interior Stile and Rail Wood Doors
1) Two-Panel Design at Public Space, Back-of-House (except where shown as
Flush), Guestroom Entry, and Guestroom Connecting Doors.
2) Two-Panel Design at Guestroom Bath, Bedroom, and Closet Doors.
3) One-Panel Design with Inset Mirror on Bedroom Side at Accessible Guestroom
Bath.
4) Three-Panel Sliding Door with Glass Lites at Breakfast Room to Serving.
2. Types of Wood Frames required include the following:
a. Pre-Finished Wood Frames (Option)
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 08 11 13 (08110) – Hollow Metal Doors and Frames
4. Section 08 41 13 (08410) – Aluminum Framed Entrances and Storefronts
5. Section 08 71 00 (08710) - Door Hardware
6. Section 08 80 00 (08800) - Glazing
7. Section 09 90 00 (09900) - Painting
4.02 REFERENCES
A. Window and Door Manufacturers Association (WDMA) Publications:
1. I.S.1-A "Architectural Wood Flush Doors"
2. I.S.6, "Industry Standard for Wood Stile and Rail Doors"
B. Architectural Woodwork Institute (AWI) Publications:
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 14 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 15 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 16 ▪
PART 5 PRODUCTS
5.01 DISTRIBUTORS
A. Avendra, LLC Preferred Distributor:
1. Contract Hardware, Inc. (800-266-3418)
a. Contact: Mark Tew
5.02 INTERIOR FLUSH WOOD DOORS
A. Manufacturers:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 17 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 18 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 19 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 20 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 21 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 22 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 23 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 24 ▪
PART 6 EXECUTION
6.01 EXAMINATION
A. Examine installed door frames prior to hanging door.
1. Verify that frames comply with indicated requirements for type, size, location, and swing
characteristics and have been installed with plumb jambs and level heads.
2. Reject doors with defects.
B. Do not proceed with installation until unsatisfactory conditions have been corrected.
6.02 INSTALLATION
A. Hardware: For installation see Section 08 71 00 “Door Hardware”.
B. Manufacturer's Instructions: Install wood doors to comply with manufacturer's instructions and
of referenced AWI standard and as indicated.
1. Install fire-rated doors in corresponding fire-rated frames in accordance with
requirements of NFPA 80.
C. Job-Fit Doors:
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 25 ▪
END OF SECTION
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 26 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Access Doors and Frames of the Following Types:
a. Wall Access Doors
b. Moisture Resistant Access Doors
c. Ceiling Access Doors
d. Floor/Ceiling System Access Doors
e. Sprinkler System Access Doors
B. Related Sections:
1. Section 04 20 00 (4200) - Unit Masonry
2. Section 09 21 16 (09255) - Gypsum Board Assemblies
3. Section 09 21 16.23 (09265) - Gypsum Board Shaft-Wall Assemblies
4. Section 09 51 23 (09512) - Acoustical Tile Ceilings
5. Section 09 90 00 (09900) - Painting
6. Division 21, 22 and 23 Sections for coordination of access to valves and other concealed
items.
7.02 REFERENCES
A. ASTM International (ASTM) Publications:
1. E119 "Standard Test Methods for Fire Tests of Building Construction and Materials"
B. National Association of Architectural Metal Manufacturers (NAAMM) Publications:
1. "Metal Finishes Manual"
C. National Fire Protection Association (NFPA) Publications:
1. NFPA 80 “Standard for Fire Doors, Fire Windows”
2. NFPA 252 “Standard Methods of Fire Tests of Door Assemblies”
D. Underwriter's Laboratories, Inc. (UL) Standards
1. UL 10B "Standard for Fire Tests of Door Assemblies"
2. UL 263 "Standard for Fire Tests of Building Construction and Materials"
7.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Shop Drawings and Samples:
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 27 ▪
PART 8 PRODUCTS
8.01 SHOP PAINTING
A. Apply a primed finish to all ferrous metal surfaces furnished under this Section. Clean and
chemically treat metal surfaces to assure maximum paint adherence. Follow with a dip or
spray coat of rust-inhibitive metallic oxide, zinc chromate, or synthetic resin primer on all
exposed surfaces. Finished surfaces shall be smooth and free from irregularities and rough
spots. Each coat of paint shall be separately baked or oven dried. The time and temperature
for drying shall be in accordance with manufacturer's recommendations for developing
maximum hardness and resistance to abrasion.
8.02 ACCESS UNITS
A. Wall Access Doors (Non-rated):
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. "WB Series”; J.L. Industries (800-554-6077)
b. "Type RDW"; Karp Associates, Inc. (800-888-4212)
c. "Model NW Series”; Nystrom Building Products (800-547-2635)
d. "Style DW"; Milcor, Inc., a brand of Commercial Products Group of Hart & Cooley,
Inc. (800-624-8642)
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 28 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 29 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 30 ▪
PART 9 EXECUTION
9.01 GENERAL
A. Verify rough openings for door and frame are correctly sized and located.
B. Beginning of installation means acceptance of existing conditions.
9.02 INSTALLATION
A. Install units and their accessories in accordance with final Shop Drawings, manufacturer's
data, and as herein specified.
B. Install frame plumb and level in wall and ceiling openings. Position to provide convenient
access to concealed work requiring access. Secure rigidly in place.
9.03 ADJUSTMENT
A. Check and readjust operating finish hardware items in work just prior to final inspection.
B. Remove and replace defective work including doors or frames which are warped, bowed, or
otherwise damaged.
9.04 TOUCH-UP
A. Immediately after erection of work, sand smooth any rusted or damaged areas of prime coat
and touch-up of compatible air drying primer.
9.05 PROTECTION:
A. Protect doors and frames from damage during transportation and at the job site; store at the
site under cover on wood blocking or on suitable floors. After installation, protect doors and
frames from damage during subsequent construction activities. Damaged work will be
rejected and shall be replaced with new work. Factory enameled finished work shall be
shipped in cartons or other suitable containers.
9.06 CLEANING:
A. Upon completion, metal surfaces of doors and frames that are completely factory finished
shall be thoroughly cleaned and touched-up as recommended by the door manufacturer.
END OF SECTION
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 31 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 32 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Interior and Exterior Aluminum Storefront Framing, Doors, Door Frames, Lights, and
Fixed Windows.
2. Anchors, Brackets, and Attachments
3. Door Hardware
4. Perimeter Sealant
B. Work Installed but Furnished Under Other Sections:
1. Section 08 71 00 (08710) - Door Hardware: Additional Door hardware items other than
specified in this Section, and keying requirements.
C. Related Sections:
1. Section 07 92 00 (07920) - Joint Sealants
2. Section 08 51 13 (08520) - Aluminum Windows
3. Section 08 71 00 (08710) - Door Hardware
4. Section 08 80 00 (08800) - Glazing
10.02 REFERENCES
A. American Architectural Manufacturers Association (AAMA) Publications:
1. AAMA “Storefront and Entrance Manual”
2. 10 "Care and Handling of Architectural Aluminum from Shop to Site"
3. 609 / 610-02 "Cleaning and Maintenance Guide for Architecturally Finished Aluminum"
4. 611 “Voluntary Specification for Anodized Architectural Aluminum”
5. 2603 "Voluntary Specification, Performance Requirements and Test Procedures for
Pigmented Organic Coatings on Aluminum Extrusions and Panels"
6. 2604 "Voluntary Specification, Performance Requirements and Test Procedures for High
Performance Organic Coatings on Aluminum Extrusions and Panels"
7. 2605 "Voluntary Specification, Performance Requirements and Test Procedures for
Superior Performing Organic Coatings on Aluminum Extrusions and Panels"
B. American National Standards Institute (ANSI) Publications:
1. ANSI/AAMA 101 "Voluntary Specifications for Aluminum, Vinyl (PVC) and Wood
Windows and Glass Doors"
C. ASTM International (ASTM) Publications:
1. A36 “Standard Specification for Carbon Structural Steel”
2. A123 “Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
Products’
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 33 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 34 ▪
PART 11 PRODUCTS
11.01 MANUFACTURERS
A. For purpose of designating design and quality of aluminum storefront system, fixed window
system, Drawings and Specifications are based on the following:
1. Storefront and Fixed Window Framing System: Insulated Glazing (Tempered)
a. Avendra, LLC Preferred Manufacturers:
1) None
b. Approved Manufacturers:
1) "Trifab VersaGlaze 451T", Kawneer North America, an Alcoa Company. (770-
449-5555)
2) “FG-3000 MultiPlane", Oldcastle BuildingEnvelope (formally Vistawall) (866-
653-2278)
3) “System 403 T”, EFCO Corporation (800-221-4169)
2. Entry Doors:
a. Style and rail tubular member door framing system by same manufacturer of
storefront framing system, compatible with specified framing system.
b. Style: as indicated on Drawings.
c. Provide nonremovable glazing stops on outside of door.
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 35 ▪
B. All exposed aluminum surfaces shall have a manufactured-applied, [10] year warrantied,
Fluoropolymer free from blemishes and surface defects.
1. Color: Refer to Exterior Finish Index.
C. All aluminum surfaces shall be Class II, Clear Anodic Finish: AA-M12C22A31 (Mechanical
Finish: nonspecular as fabricated; Chemical Finish: etched, medium matte; Anodic Coating:
Architectural Class II, clear coating 0.010 mm or thicker) complying with AAMA 611.
11.04 FABRICATION
A. Aluminum door shall have tight hairline joints where rails are fitted against stiles and shall be
fastened by means of tensioned steel tie rods in top and bottom rails. Doors shall have an
adjusting mechanism in the toprail to provide for minor clearance adjustments. Glass stops
shall be snap-in type with bulb type glazing strips. Weather stripping shall be pile.
B. Store front sections shall be square cut and assembled with the proper clips and screws as
provided by the manufacturer to form neat hairline joints. All fastenings shall be concealed
except those specifically detailed by the Architect at certain transition areas. All glazing
gaskets shall be cut over length and installed in slight linear compression to prevent shrinkage
from the corners. All framing shall be erected square and true into correct size rough
openings prepared by others and in strict accord with the Architectural Drawings.
C. Doors: Reinforce doors as required for installing hardware, including electronic strikes and
card readers.
1. At pairs of exterior doors, provide sliding weather stripping retained in adjustable strip
mortised into door edge.
2. At exterior doors, provide weather sweeps applied to door bottoms.
D. Hardware Installation: Factory install hardware to the greatest extent possible. Cut, drill, and
tap for factory-installed hardware before applying finishes.
11.05 HARDWARE
A. Entrance door hardware shall be supplied with doors as follows, unless indicated otherwise:
1. Continuous Hinges, 780-112 HD, Hager, Kynar finish, color to match door.
2. Push/Pull, Style “CO-12” by Kawneer, or approved substitution by other listed
manufacturer, No. 26D Finish.
3. Closers, surface mounted type, LCN 4041-CUSH, cover to be 689 finish.
4. Weather Stripping (3 sides)
5. Bottom Sweep
6. Handicapped Threshold, clear aluminum mill finish.
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 36 ▪
PART 12 EXECUTION
12.01 INSPECTION
A. Verify wall openings and adjoining air and vapor seal materials are ready to receive work of
this Section.
B. Beginning of installation means acceptance of existing conditions.
12.02 INSTALLATION
A. Install doors, frames, glazing and hardware in accordance with manufacturer's instructions
and AAMA “Storefront and Entrance Manual” guide specifications.
B. Use anchorage devices to securely attach frame assembly to structure.
C. Align assembly plumb and level, free of warp or twist. Maintain assembly dimensional
tolerances, aligning with adjacent work.
D. Coordinate attachment and seal of air and vapor barrier materials. Install sill flashings where
required.
E. Weathertight Construction: Install sill members and other members in a bed of sealant or with
joint filler or gaskets, to provide weathertight construction.
1. Refer to Section 07 92 00 “Joint Sealants” for installation requirements.
F. Apply one coat of bituminous paint to concealed aluminum and steel surfaces in contact with
cementitious, stone or other dissimilar materials.
G. Install glass and infill panels in accordance with Section 08 80 00 (08800) using exterior wet
method of glazing.
H. Install perimeter non-hardening, non-skinning type sealant, and installation requirements in
accordance with Section 07 92 00 (07920).
I. Adjust operating hardware
12.03 TOLERANCES
A. Variation from Plane: 0.03 inches per foot maximum or 0.25 inches per 30 feet, whichever is
less.
B. Misalignment of Two Adjoining Members Abutting in Plane: 0.015 inches.
12.04 CLEANING
A. Remove protective material from prefinished aluminum surfaces.
B. Wash-down exposed surfaces using a solution of mild detergent in warm water, applied with
soft, clean wiping cloths. Take care to remove dirt from corners. Wipe surfaces clean.
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 37 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 38 ▪
PART 13 GENERAL
13.01 SUMMARY
A. Section Includes:
1. [Bi-parting] Sliding Unit, with Fixed Sidelites
B. Related Sections:
1. Section 07 92 00 (07920) - Joint Sealants
2. Section 08 41 13 (08410) - Aluminum Entrances and Storefront
3. Section 08 71 00 (08710) - Door Hardware
4. Section 08 80 00 (08800) - Glazing
5. Division 26 (16) - Electrical: Wiring
13.02 REFERENCES
A. American Architectural Manufacturers Association (AAMA) Publications:
1. 2604 "Voluntary Specification, Performance Requirements and Test Procedures for High
Performance Organic Coatings on Aluminum Extrusions and Panels"
2. 2605 "Voluntary Specification, Performance Requirements and Test Procedures for
Superior Performing Organic Coatings on Aluminum Extrusions and Panels"
B. American Society of Civil Engineers (ASCE) Publications:
1. 7 "Minimum Design Loads for Buildings and Other Structures"
C. ASTM International (ASTM) Publications:
1. B209 "Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate"
2. B221 "Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods,
Wire, Profiles, and Tubes"
3. E283 “Standard Test Method for Determining Rate of Air Leakage Through Exterior
Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the
Specimen”
D. American National Standards Institute (ANSI) /Builders Hardware Manufacturers Association
(BHMA) Publications:
1. ANSI/BHMA A156.10, "Power Operated Pedestrian Doors"
2. ANSI/BHMA A156.19 – “Power Assist and Low Energy Power Operated Doors”
E. American Welding Society (AWS) Publications:
1. D1.2 "Structural Welding Code--Aluminum"
2. A5.10 "Specification For Bare Aluminum And Aluminum-Alloy Welding Electrodes And
Rods"
3. BHMA A156.19 – American National Standard for Power Assist and Low Energy Power
Operated Doors.
F. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 39 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 40 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 41 ▪
PART 14 PRODUCTS
14.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. "Unislide OHC Series [Bi-Parting] [Single-Slide]"; Besam, An Assa Abloy Group
Company (866-237-2687)
a. Exterior: "Unislide OC-S"
b. Interior: "Unislide OC-A" with Access Control Package
B. Approved Manufacturers:
1. “Dura-Glide, Series 2000, Bi-Parting”; Stanley Access Technologies LLC, Security
Solutions Product Group (860-677-2861)
a. Exterior: “Model 7-2260”
b. Interior: “Model 7-2260”
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 42 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 43 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 44 ▪
PART 15 EXECUTION
15.01 INSPECTION
A. The automatic entrance door installer must examine the areas and conditions under which the
automatic entrances are to be installed and notify the General Contractor in writing of
conditions detrimental to the proper functioning of the entrance and the timely completion of
the work. Do not proceed with the work until unsatisfactory conditions have been corrected in
a manner acceptable to the installer.
15.02 INSTALLATION
A. Comply with manufacturer's specifications and recommendations. Set units plumb, level, and
true. Fit frame joints to produce hairline joints free of burrs and distortion. Rigidly secure non-
movement joints. Seal joints watertight.
1. Where aluminum will contact dissimilar metals, protect against galvanic action by painting
contact surfaces with primer or by applying sealant or tape recommended by
manufacturer for this purpose.
2. Where aluminum will contact concrete or masonry, protect against corrosion by painting
contact surfaces with bituminous paint.
B. Sealants:
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 45 ▪
END OF SECTION
Revision Log
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 46 ▪
PART 16 GENERAL
16.01 SUMMARY
A. Section Includes:
1. Operating and Fixed Aluminum Window Units
a. Horizontal Sliding Units
2. Perimeter Sealant
3. Glass and Glazing
4. Wood Blocking, Shims, Anchors, Clips, and all accessories necessary for a complete
installation.
5. All Aluminum Trim and Closure Pieces
6. All Operable Window and Door Hardware
B. Related Sections:
1. Section 07 62 00 (07620) - Sheet Metal Flashing and Trim
2. Section 0792 00 (07920) – Joint Sealants
3. Section 08 32 13 (08163) – Sliding Aluminum Framed Glass Doors
4. Section 08 41 13 (08410) - Aluminum Entrances and Storefront
5. Section 08 80 00 (08800) - Glazing
16.02 REFERENCES
A. The Aluminum Association (AA)
1. "Aluminum Design Manual 2000: Specifications for Aluminum Structures"
B. American Architectural Manufacturers Association (AAMA) Publications:
1. 611 “Voluntary Specification for Anodized Architectural Aluminum”
2. 1503 "Voluntary Test Method for Thermal Transmittance and Condensation Resistance
of Windows, Doors and Glazed Wall Sections"
3. 2400 "Standard Practice for Installation of Windows with a Mounting Flange in Stud
Frame Construction"
4. 2604 "Voluntary Specification, Performance Requirements and Test Procedures for High
Performance Organic Coatings on Aluminum Extrusions and Panels"
5. 2605 "Voluntary Specification, Performance Requirements and Test Procedures for
Superior Performing Organic Coatings on Aluminum Extrusions and Panels"
C. American National Standards Institute (ANSI) Publications:
1. ICC A117.1-2009 “Accessible and Useable Buildings and Facilities”
2. Z97.1 "Performance Specifications and Methods of Test for Safety Glazing Materials
Used in Buildings"
D. Americans with Disabilities Act (ADA)
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 47 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 48 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 49 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 50 ▪
PART 17 PRODUCTS
17.01 MATERIALS
A. Window Units:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. Traco, A Division of Kawneer, a part of Alcoa Building & Construction Systems (800-
837-7002)
1) Horizontal Sliding: TR-6400 Series
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 51 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 52 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 53 ▪
PART 18 EXECUTION
18.01 INSTALLATION - GENERAL
A. Installation Details: Before proceeding with the manufacturing of the windows and doors, the
Window Contractor shall submit complete installation details for approval by the [Owner's
Representative]. These Drawings shall show elevations of windows, full-sized details of all
sections of windows, collateral materials and details of anchorage. Supplemental data shall
contain calculations of moments of inertia on frames and mullion connections plus instructions
for storage, handling, and erection of windows and sliding doors. Conform to AAMA 2400 for
Nail Fin Installation.
B. Verify wall openings and adjoining air and vapor seal materials are ready to receive work of
this Section.
C. Beginning of installation means acceptance of existing conditions.
D. Align window frame plumb and level, free of wrap or twist. Maintain dimensional tolerances,
aligning with adjacent work.
E. Coordinate attachment and seal of air and vapor barrier materials. Install under sill flashings,
if required.
F. Pack fibrous insulation in shim spaces at perimeter to maintain continuity of thermal barrier.
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 54 ▪
END OF SECTION
Revision Log
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 55 ▪
PART 19 GENERAL
19.01 SUMMARY
A. Section Includes:
1. Horizontal Sliding and Fixed Vinyl Window Units
2. Perimeter Sealant
3. Glass and Glazing
4. Wood Blocking, Shims, Anchors, Clips, and all accessories necessary for a complete
installation.
5. All Trim and Closure Pieces
6. All Operable Window Hardware
B. Related Sections:
1. Section 07 46 00 (07460) - Siding
2. Section 07 62 00 (07620) - Sheet Metal Flashing and Trim
3. Section 07 92 00 (07920) – Joint Sealants
19.02 REFERENCES
A. Glass Association of North America (GANA)
1. "GANA Glazing Manual"
B. Insulating Glass Certification Council (IGCC)
C. Insulating Glass Manufacturers Alliance (IGMA) Publications:
1. Glazing Guidelines
D. National Fenestration Rating Council (NFRC)
E. Screen Manufacturers Association (SMA) Publications:
1. 1004 "Specifications for Aluminum Tubular Frame Screens for Windows"
F. Window and Door Manufacturers Association (WDMA) Publications:
1. ANSI/AAMA/WDMA 101/I.S.2/NAFS-02 “Voluntary Performance Specification for
Windows, Skylights and Glass Doors”
2. AAMA/WDMA/CSA 101/I.S.2/A440-08 “Standard/Specification for Windows, Doors and
Unit Skylights
19.03 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Submit Shop Drawings and product data that include wall opening and component
dimensions; wall opening tolerances required; anchorage and fasteners; affected related
work; and installation requirements and instructions.
a. Provide samples of materials as may be requested without cost to Owner, i.e.,
metal, glass, fasteners, anchors, frame sections, mullion section, etc.
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 56 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 57 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 58 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 59 ▪
END OF SECTION
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 60 ▪
PART 22 GENERAL
22.01 SUMMARY
A. Section Includes:
1. All the finish hardware including all screws, bolts, and other devices required to complete
the work.
2. Lock cylinders for locks specified in other Sections.
3. Miscellaneous hardware.
4. Hardware furnished for shop or factory installation on doors and frames.
5. Keys and Keying.
B. Related Sections:
1. Section 08 11 13 - Steel Doors and Frames
2. Section 08 14 00 - Wood and Plastic Doors
3. Section 25 51 10 – Integrated Automation Control of Guestroom Equipment
4. Division 26 Sections - Coordination with items requiring electrical connections.
22.02 REFERENCES
A. Perform all work in accordance with the following:
1. American National Standards Institute (ANSI) Publications:
a. ICC A117.1-2009 “Accessible and Useable Buildings and Facilities”
b. ANSI/BHMA A 156.1 "Butts & Hinges"
c. ANSI/BHMA A 156.2 "Bored and Preassembled Locks and Latches"
d. ANSI/BHMA A 156.3 "Exit Devices"
e. ANSI/BHMA A 156.4 "Door Controls - Closers"
f. ANSI/BHMA A 156.5 "Auxiliary Locks and Associated Products"
g. ANSI/BHMA A 156.6 "Architectural Door Trim"
h. ANSI/BHMA A 156.13 "Mortise Locks & Latches"
i. ANSI/BHMA A 156.17 "Self-Closing Hinges & Pivots"
j. ANSI/BHMA A 156.18 "Materials & Finishes"
k. ANSI/BHMA A 156.21 "Thresholds"
l. ANSI/BHMA A 156.22 "Gasketing and Edge Seal Systems"
m. ANSI/BHMA A 156.23 "Electromagnetic Locks"
n. ANSI/BHMA A 156.25 “Electrified Locking Devices”
o. ANSI/BHMA A 156.26 "Continuous Hinges"
p. ANSI/BHMA A 156.28 "Keying Systems"
2. ANSI/DHI Publications:
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 61 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 62 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 63 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 64 ▪
PART 23 PRODUCTS
23.01 DISTRIBUTORS
A. Avendra, LLC Preferred Manufacturers:
1. Contract Hardware, Inc. (800-266-3418)
a. Contact: Mark Tew
23.02 MANUFACTURERS
A. Hardware manufacturers are specified for each hardware item to establish a standard of
quality and minimum functional requirements. In the hardware schedule at the end of this
Section, product model numbers are used as part of this description to assist in identifying
individual items.
B. Items of a particular hardware category, i.e., locksets, closers, hinges shall be of the same
manufacturer.
C. Avendra, LLC Preferred Manufacturers:
1. None
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 65 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 66 ▪
b. No Substitutions
4. Guest Room Locking System, Front Desk System
a. Avendra, LLC Preferred Manufacturers:
1) None
b. Approved Manufacturers:
1) Basis-of-Design Product: Subject to compliance with requirements, provide
“System 6000” by Saflok, a Kaba Group Company, or one of the following:
2) No Substitutions
c. Microprocessor based Front Desk Controller System shall be a PC base network
RFID encoding, handheld key encoding system with remote system printer and lock
integration (LPI) feature. Include the following:
1) Main PC Base computer, RS232 Cable and support hardware.
2) [2] or [1] Each Network RFID keycard encoder station and power supply. Verify
quantity with owner
3) 1 Each Basic System Items: Manuals, etc.
4) 1 Each System Printer with Serial Cable
5) Keycards: Generic reusable plastic RFID keycards. Quantity: 2000.
d. System shall be designed for the following features:
1) Password access to front desk system
2) Transaction log of last 4,000 transactions
3) Simple three-step check in progress
4) Encoder must encode and validate cards
5) Encoder must be able to "read a card"
6) Fail-safe key cards in case of catastrophic power failure
7) Handheld Unit: Password protected and be able to program up to 50 locks. In
addition HHU associated with the Front Desk System. This unit will be used for
lock interrogation, diagnostics and programming. Program shall include:
(a) Set time clock
(b) Perform diagnostic check
(c) Interrogate up to last 100 entries: time, date and card identification
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 67 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 68 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 69 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 70 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 71 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 72 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 73 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 74 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 75 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 76 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 77 ▪
PART 24 EXECUTION
24.01 INSPECTION
A. Verify that doors and frames are ready to receive work and dimensions, are as indicated on
Shop Drawings, and as instructed by the manufacturer.
B. Beginning of installation means acceptance of existing conditions.
24.02 INSTALLATION
A. Install each hardware item in compliance with manufacturer's instructions and
recommendations. Wherever cutting and fitting is required to install hardware onto or into
surfaces which are later to be painted or finished in another way, install each item completely
and then remove and store in a secure place during the finish application. After completion of
the finished, reinstall each item. Do not install surface-mounted items until finishes have been
completed on the substrate.
B. Conform to [2010 ADA Standards] and [ANSI ICC A117.1-2009] for positioning requirements
for the Disabled.
C. All door closers shall be installed out of public sight wherever possible.
24.03 FASTENINGS
A. Suitable size, quantity, and material with finish to match the hardware.
B. Machine screws for attaching hardware to metal.
C. Self-tapping screws for attaching kickplate to hollow metal or wood mineral core doors.
D. Full thread type screws for attaching butt hinges to wood or mineral core doors.
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 78 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 79 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 80 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 81 ▪
NOTE: PROVIDE KEY SWITCH FOR ELECTRO MAG LOCK. LOCATE AS DIRECTED BY
OWNER’S REPRESENTATIVE.
NOTE: AT LOCKOUT DOORS ONLY: PROVIDE FUNCTION THAT ALLOWS DOOR TO BE
UNLOCKED AT ALL TIMES BY CODING RFID CARD. USING INSIDE DEADBOLT OVERIDES AND
LOCKS DOOR
NOTE: DELETE WALL STOP AT LOCATIONS WHERE DOOR DOES NOT SWING AGAINST
WALL.
NOTE: DELETE HINGES IF DOOR/FRAME ARE FURNISHED PREHUNG.
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 82 ▪
NOTE: DELETE WALL STOP AT LOCATIONS WHERE DOOR DOES NOT SWING AGAINST
WALL.
NOTE: DELETE HINGES IF DOOR/FRAME ARE FURNISHED PREHUNG.
NOTE: FOR CLOSETS SHOWN TO HAVE A LIGHT FIXTURE, INCLUDE THE FOLLOWING:
1 EA DOOR POSITION
SWITCH DPS-M-WH WHITE SEC
NOTE: FOR CLOSETS SHOWN TO HAVE A LIGHT FIXTURE, INCLUDE THE FOLLOWING:
1 EA DOOR POSITION
SWITCH DPS-M-WH WHITE SEC
1 EA RELAY 110 V (BY OTHERS)
1 EA POWER SUPPLY LOW VOLTAGE (BY OTHERS)
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 83 ▪
1 EA OH CONCEALED
CLOSER 0608090N X LCP US26D RIX
1 EA EXIT DEVICE EL33NL-OP US26D VDI
1 EA CYLINDER 34 US26D SAR
1 EA LOCK QUANTUM RFID X BLE (LESS DEAD BOLT)
X GALA US32D SAF
1 EA ELEC POWER
TRANSFER EPT10 VDI
1 EA POWER SUPPLY PS914 VDI
1 EA FLOOR STOP 1233 US26D TRM
1 EA OH CONCEALED
CLOSER 0608090N X LCP US26D RIX
1 EA EXIT DEVICE EL33NL-OP US26D VDI
1 EA CYLINDER 34 US26D SAR
1 EA LOCK QUANTUM RFID X BLE (LESS DEAD BOLT)
X GALA US32D SAF
1 EA ELEC POWER
TRANSFER EPT10 VDI
1 EA POWER SUPPLY PS914 VDI
1 EA DOOR VIEWER U696B US26D IVES
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 84 ▪
1 EA PUSH BUTTON
RELEASE MUSHROOM BUTTON 32310 SAF
1 EA KEYSWITCH 653-04 US32D SCE
1 EA CYLINDER 41 (@ KEYSWITCH) US32D SAR
1 EA REMOTE CONTROL
UNIT FLUSH MTD. 94770 RFID X BLE SAF
1 EA POWER SUPPLY 32280 SAF
1 EA AIPHONE INTERCOM
SYSTEM LEM-1 DLS AIP
PEM
25.14 HW SET - T16 ELECTRICAL / SERVER CLOSET / MEETING ROOM STORAGE / IN-A-
PINCH STORAGE / LAUNDRY STORAGE/ WORKROOM CLOSET
SINGLE DOORS 17, 18, 20, 21, 24, 27
EACH DOOR TO HAVE:
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 85 ▪
25.17 HW SET – T18 ELEVATOR MACHINE ROOM, SECOND FLOOR MECHANICAL ROOM
SINGLE DOORS 60
EACH DOOR TO HAVE:
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 86 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 87 ▪
1 EA POCKET DOOR
SET DN 150 TRACK 12’ # 89021U1501210 626 RIC
2 EA SOFT CLOSE 8910107026510 626 RIC
1 EA PULL RM7920 X 12” 626 RIC
1 EA SLIDING DOOR
TOP TRACK 89021U45310–DN 50 TRACK
(TOP TRACK U45) 626 RIC
1 EA WALL BRACKET 89021BRAU21W310 626 RIC
1 SET FITTING SET 8910100217271–FITTING SET DN 50 626 RIC
1 EA GUIDE 246204110092–WALL MOUNT
LOWER GUIDE 626 RIC
1 EA PULL RM7920 X 12” 626 RIC
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 88 ▪
END OF SECTION
Revision Log
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 89 ▪
PART 26 GENERAL
26.01 SUMMARY
A. Section Includes:
1. Section includes glass and glazing for:
a. Float Glass
b. Tempered Glass
c. Insulated Units
d. Fire Protective Rated Safety Glass
B. Related Sections:
1. Section 07 92 00 (07920) – Joint Sealants
2. Section 08 11 13 (08110) - Steel Doors and Frames
3. Section 08 14 00 (08200) - Wood Doors
4. Section 08 41 13 (08410) - Aluminum-Framed Entrances and Storefronts
5. Section 08 42 29 (08460) – Automatic Entrance Doors
6. Section 08 51 13 (08520) - Aluminum Windows
7. Section 08 53 00 (08560) – Plastic Windows
26.02 REFERENCES
A. American Architectural Manufacturers Association (AAMA) Publications:
1. 800-92 “Voluntary Specifications and Test Methods for Sealants”
B. American National Standards Institute (ANSI) Publications:
1. ANSI/AAMA 101 "Voluntary Specifications for Aluminum, Vinyl (PVC) and Wood
Windows and Glass Doors"
C. ASTM International (ASTM) Publications:
1. C920 “Standard Specification for Elastomeric Joint Sealants”
2. C1036 “Standard Specification for Flat Glass”
3. C1048 “Standard Specification for Heat-Treated Flat Glass—Kind HS, Kind FT Coated
and Uncoated Glass”
4. C1172 “Standard Specification for Laminated Architectural Flat Glass”
5. C1376 “Standard Specification for Pyrolytic and Vacuum Deposition Coatings on Glass”
6. E1300 “Standard Practice for Determining Load Resistance of Glass in Buildings”
7. E2190 “Standard Specification for Insulating Glass Unit Performance and Evaluation”
D. Consumer Product Safety Commission (CPSC) Publications:
1. 16 CFR 1201 - “Safety Standard for Architectural Glazing Materials “
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 90 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 91 ▪
PART 27 PRODUCTS
27.01 ACCEPTABLE GLASS MANUFACTURERS
A. All glass shall be new material, graded under ASTM 1036.
B. All glass in related area shall be from one manufacturer.
27.02 GLASS MATERIALS
A. Refer to Drawings for location of glass.
B. Glass [I]: Clear Float Glass: ASTM C1036, Type 1 (transparent glass, flat), Class 1 (clear),
Quality q3 (glazing select), as manufactured by one of the following:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. PPG Industries (800-377-5267)
b. Pilkington North America (800-221-0444)
c. Old Castle Glass, a CRH Company (800-899-8455)
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 92 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 93 ▪
Note: Include TPS Spacer below for use with CFRST LEED Volume Program.
Delete Manufacturer’s standard Dual-Seal paragraphs above.
h. Sealing System:
1) Spacer Material: Thermal Plastic Spacer (TPS), IGMAC approved low-
conductance spacer bar material with integrated desiccant.
2) Approved Manufacturers:
(a) “TPS Warm edge spacer”; Traco, A Division of Kawneer, a part of Alcoa
Building & Construction Systems (800-837-7002)
(b) “SureSeal TPS Spacer Bar”; Virginia Glass and Mirror (800-368-3011)
(c) “TPS Warm Edge Glass”; Floral Glass and Mirror (631 851-0561)
(d) “Warm Edge Spacer”; Technoform North America (330-487-6600)
27.03 FIRE-PROTECTIVE GLAZING PRODUCTS
A. Fire-Protective, Ceramic Glazing Material: Proprietary product in the form of two plies of
laminated clear ceramic flat sheets, permanently labeled with appropriate marks of testing and
inspecting agency, acceptable to authorities having jurisdiction, showing product complies with
fire-protective installation indicated, and as follows:
1. Safety Glass: Shall conform to ASTM C1048, and Federal Standard
CPSC 16 CFR 1201.
2. Polished on both surfaces, transparent with minimum visible light transmission of 85
percent.
3. Positive Pressure: Shall meet requirements of positive pressure test standards UL 10C.
4. NFPA 252 for Door Assemblies.
5. NFPA 257 for Window Assemblies.
6. Manufacturers:
a. Avendra, LLC Preferred Manufacturers:
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 94 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 95 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 96 ▪
PART 28 EXECUTION
28.01 EXAMINATION: Require Glazier to inspect work of glass framing erector for compliance with
manufacturing and installation tolerances, including those for size, squareness, offsets at corners;
for presence and functioning of weep system; for existence of minimum required face or edge
clearances; and for effective sealing of joinery. Obtain Glazier's written report listing conditions
detrimental to performance of glazing work. Do not allow glazing work to proceed until
unsatisfactory conditions have been corrected.
28.02 PREPARATION: Clean glazing channels and other framing members to receive glass,
immediately before glazing. Remove coatings which are not firmly bonded to substrates. Remove
lacquer from metal surfaces where elastomeric sealants are indicated for use.
28.03 GLAZING - GENERAL
A. Comply with combined printed recommendations of glass manufacturers, of manufacturers of
sealants, gaskets and other glazing materials, except where more stringent requirements are
indicated, including those of referenced glazing standards.
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 97 ▪
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 98 ▪
END OF SECTION
Revision Log
▪ DIVISION 08 OPENINGS ▪
▪ PAGE 99 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Shaft Enclosures
2. Chase Enclosures
3. Stair Enclosures
B. Related Sections:
1. Section 07 84 00 (07480) - Firestopping
2. Section 07 92 00 (07920) – Joint Sealants
3. Section 09 21 16 (09255) - Gypsum Board Assemblies
4. Section 09 90 00 (09900) - Painting
1.02 DEFINITIONS
A. Gypsum Board Construction Terminology: Refer to ASTM C1396 for definitions of terms for
gypsum board construction not defined in this Section or in other referenced standards.
1.03 REFERENCES
A. ASTM International (ASTM) Publications:
1. A653 "Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron
Alloy-Coated (Galvannealed) by the Hot-Dip Process"
2. C442 “Standard Specification Gypsum Backing Board, Gypsum Coreboard, and Gypsum
Shaftliner Board”
3. C475 “Standard Specification for Joint Compound and Joint Tape for Finishing Gypsum
Board”
4. C645 “Standard Specification for Nonstructural Steel Framing Members“
5. C754 “Standard Specification for Installation of Steel Framing Members to Receive
Screw-Attached Gypsum Panel Products”
6. C834 “Standard Specification for Latex Sealants”
7. C840 “Standard Specification for Application and Finishing of Gypsum Board”
8. C919 “Standard Practice for Use of Sealants in Acoustical Applications
9. C954 “Standard Specification for Steel Drill Screws for the Application of Gypsum Panel
Products or Metal Plaster Bases to Steel Studs from 0.033 in. to 0.112 in. in Thickness”
10. C1002 “Standard Specification for Steel Self-Piercing Tapping Screws for the Application
of Gypsum Panel Products or Metal Plaster Bases to Wood Studs or Steel Studs”
11. C1047 “Standard Specification for Accessories for Gypsum Wallboard and Gypsum
Veneer Base”
12. C1278 “Standard Specification for Fiber-Reinforced Gypsum Panel"
▪ DIVISION 09 FINISHES ▪
▪ PAGE 1 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 2 ▪
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. G-P Gypsum Corporation (800-225-6119)
2. National Gypsum Company, Gold Bond Building Products Div. (800-628-4662)
3. United States Gypsum Co. (800-950-3839)
4. CertainTeed Corporation, a subsidiary of Saint-Gobain (800-233-8990)
5. Temple-Inland Forest Products Corp. - Gypsum Products (800-231-6060)
6. ClarkDietrich Building Systems LLC (513-870-1100)
▪ DIVISION 09 FINISHES ▪
▪ PAGE 3 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 4 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 5 ▪
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 6 ▪
PART 4 GENERAL
4.01 SUMMARY
1. Non-Load Bearing Interior Steel Framing
a. Interior Partitions
b. Suspended and Furred Ceilings
2. Gypsum Board, Screw-Attached to Wood Framing and Furring Members, and Required
Accessories
3. Gypsum Board, Screw-Attached to Steel Framing and Furring Members, and Required
Accessories
4. Glass-Mat, Mold & Mildew Resistant Interior Wall Panel
5. Sound Deadening Boards
6. Exterior Cement Board Ceilings.
7. Tile-Backer Boards
8. Glass Fiber Reinforced Gypsum Soffits
9. Clothes Dryer Recessed Vent Box.
B. Related Sections:
1. Section 01 35 16 (01120) – Alteration Project Procedures
2. Section 01 73 29 (01730) – Cutting and Patching.
3. Section 02 41 19 (01738) – Selective Structure Demolition
4. Section 05 40 00 (05400) – Cold-Formed Metal Framing
5. Section 06 10 00 (06100) - Rough Carpentry
6. Section 06 20 00 (06200) - Finish Carpentry
7. Section 07 20 00 (07200) - Thermal Protection
8. Section 07 84 00 (07480) - Firestopping
9. Section 07 92 00 (07920) – Joint Sealants
10. Section 09 21 16.23 (09265) - Gypsum Board Shaft-Wall Assemblies
11. Section 09 30 00 (09310) - Tiling
12. Section 09 94 13 (09941) - Textured Finishing
13. Section 09 51 23 (09512) - Acoustical Tile Ceilings
14. Section 09 72 00 (09950) – Wall Coverings
15. Section 09 90 00 (09900) - Painting
4.02 REFERENCES
A. American Iron and Steel Institute (AISI) Publications:
1. “AISI’s Code of Standard Practice for Cold-Formed Steel Structural Framing”
▪ DIVISION 09 FINISHES ▪
▪ PAGE 7 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 8 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 9 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 10 ▪
PART 5 PRODUCTS
5.01 GYPSUM BOARD PRODUCTS
A. General: Provide gypsum board of types indicated in maximum lengths available that will
minimize joints in each area and correspond with support system indicated.
1. Thickness: Provide gypsum board in widths of 48 inches and thickness indicated or, if
not otherwise indicated, in 5/8 inch thickness to comply with ASTM C840 for application
system and support spacing indicated.
B. Gypsum Wallboard: ASTM C1396 and as follows:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. G-P Gypsum Corporation (800-225-6119)
b. National Gypsum Company. (800-628-4662)
c. United States Gypsum Co. (800-950-3839)
d. CertainTeed Corporation, a subsidiary of Saint-Gobain (800-233-8990)
e. Continental Building Products (Lafarge North America Inc.) (866-349-7786)
f. Temple-Inland Forest Products Corp. - Gypsum Products (800-231-6060)
3. [Type: Regular for vertical surfaces, unless otherwise indicated]
4. Type: Type X [where required for fire-resistance-rated assemblies].
5. Type: Type C [where required for fire-resistance-rated assemblies] [where required for
sound rated wall assemblies].
6. Type: Sag-resistant Type for Ceiling Surfaces
7. Edges: Tapered and Featured (rounded or beveled) for prefilling.
C. Glass-Mat, Mold & Mildew Resistant Interior Wall Panel
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. "DensArmor Plus Interior Guard"; G-P Gypsum Corporation (800-225-6119)
b. “GreenGlass Interior Gypsum Board”; Temple-Inland Forest Products Corp. -
Gypsum Products (800-231-6060)
c. “Sheetrock Brand Glass-Mat Panels Mold Tough Firecode X”; United States
Gypsum Co. (800-950-3839)
3. ASTM C1658, glass-mat faced, enhanced mold & mildew resistant gypsum core
wallboard. Conforming to the physical properties of ASTM C1396 and ASTM C1177.
Rating of 10 "No Mold Growth" as tested for 4 weeks according to ASTM D3273.
a. Surfaces to be Painted: Coated inorganic glass mat-faced back front.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 11 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 12 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 13 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 14 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 15 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 16 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 17 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 18 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 19 ▪
PART 6 EXECUTION
6.01 EXAMINATION
A. Examine substrates with Installer present, to which gypsum board assemblies attach or abut,
installed hollow metal frames, cast-in-anchors, and structural framing, with Installer present,
for compliance with requirements for installation tolerances and other conditions affecting
performance of assemblies specified in this Section. Do not proceed with installation until
unsatisfactory conditions have been corrected.
6.02 CEILING ANCHORAGES
A. Coordinate installation of ceiling suspension systems with installation of overhead structural
assemblies to ensure that inserts and other provisions for anchorages to building structure
have been installed to receive ceiling hangers that will develop their full strength and at
spacing required to support ceilings.
Note: Delete Article below if no Steel Framing.
6.03 INSTALLATION - STEEL FRAMING, GENERAL
A. Steel Framing Installation Standard: Install steel framing to comply with ASTM C754 and with
ASTM C840 requirements that apply to framing installation.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 20 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 21 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 22 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 23 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 24 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 25 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 26 ▪
END OF SECTION
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 27 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Floor and Wall Tile and Accessories
2. Crack Suppression Membrane
3. Leveling Coat, Mortar, Grouts, and Adhesives
4. Shower Pan Liners
B. Related Sections:
1. Section 03 30 00 (07920) – Cast-In-Place Concrete
2. Section 07 92 00 (07920) – Joint Sealants
3. Section 09 21 16 (09255) - Gypsum Board Assemblies
4. Section 12 36 40 (09380) – Stone Countertops
5. Section 12 36 61 (09385) - Simulated Stone Countertops
6. Section 12 36 61.13 (09385) – Cultured Marble Countertops
7. Section 13 11 00.01 (13151) - Swimming Pools - Exterior
8. Section 13 11 00.02 (13152) - Swimming Pools - Interior
9. Division 22 (15) for Plumbing Fixtures
7.02 REFERENCES
A. Tile Council of North America, Inc. (TCNA):
1. "Hand Book for Ceramic, Glass, and Stone Tile Installation", 2015 Edition or later.
2. TCNA Technical Bulletin: “ Coefficient of Friction and the DCOF AcuTest”, 2013
B. American National Standards Institute (ANSI)
1. A108/A118/A136.1 - “American Standard Specification for the Installation of Ceramic
Tile”.
2. A108.5 - Ceramic Tile Installed with Dry-Set Portland Cement Mortar.
3. A108.6 - Specifications for Ceramic Tile Installed with Chemical-Resistant, Water-
Cleanable Tile-Setting and -Grouting Epoxy
4. A108.10 - Specifications for Installation of Grout in Tilework.
5. A118 - Latex-Portland Cement Mortar4
6. A118.1 - Dry-Set Portland Cement Mortar
7. A118.3 - Chemical-Resistant, Water-Cleanable, Tile-Setting and -Grouting Epoxy and
Water-Cleanable Tile-Setting Epoxy Adhesive
8. A118.4 – “Latex-Portand Cement Mortar”
9. A118.7 – “Polymer Modified Cement Grouts”
▪ DIVISION 09 FINISHES ▪
▪ PAGE 28 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 29 ▪
PART 8 PRODUCTS
8.01 FLOOR AND WALL TILE
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Ceramic Technics Ltd. (770-740-0050)
2. Caesar Ceramics USA, Inc. (Ceramiche Caesar) (732-610-6967)
3. Crossville, Inc. (931-484-2110)
4. Dal-Tile Corporation (630-789-1479)
5. Designer Tile & Stone (800-959-8453)
6. Florida Tile Industries, Inc. (301-929-8453)
7. Global Architectural Products, Div. of Global Granite & Marble (314-743-1081)
8. GranitiFiandre (727-522-6655)
9. Latco Products (800-422-6860)
▪ DIVISION 09 FINISHES ▪
▪ PAGE 30 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 31 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 32 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 33 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 34 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 35 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 36 ▪
PART 9 EXECUTION
9.01 INSPECTION:
A. Installer must examine the areas and conditions under which flooring and accessories are to
be installed and notify the Contractor in writing of conditions detrimental to the proper and
timely completion of the work. Do not proceed with the work until unsatisfactory conditions
have been corrected in a manner acceptable to the installer.
9.02 PREPARATION:
A. Prior to laying flooring, vacuum and remove all contaminates from surfaces to be covered and
inspect subfloor. Start of flooring installation indicates acceptance of subfloor conditions and
full responsibility for completed work. Use leveling compound as recommended by flooring
manufacturer for filling small cracks and depressions in subfloors.
1. Concrete Subfloors:
a. Slab substrates are dry and free of curing compounds, sealers, hardeners, residual
adhesives, adhesive removers, and other materials whose presence would interfere
with bonding of tile adhesive or mortar and comply with surface finish requirements
of ANSI A108.01. Determine adhesion and dryness characteristics by performing
bond and moisture tests recommended by manufacturer.
b. Subfloor Moisture Conditions: Before installing flooring Contractor shall verify that
Moisture emission rate of not more than 3 lb/1000 sq. ft./24 hours when tested by
calcium chloride moisture test in compliance with CRI 104, 6.2.1 and does not
exceed the capacity of the specified adhesive or mortar, with subfloor temperatures
not less than 55 deg F, or as recommended by manufacturer.
c. New concrete surfaces shall be wood-floated or broom finished. Overtroweled slabs
are not acceptable.
B. For installations of Tiles 24” x 24”, 18” x 38” or larger:
1. Interior Floors: This Contractor shall use cement based, self leveling underlayment to
insure flat substrate to receive tile, full mortar coverage of tile and substrate, and tile
installation free of lippage.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 37 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 38 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 39 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 40 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 41 ▪
G. ARDEX
Mortar - Floor “ARDEX X-5” “ARDEX X-5” “ARDEX X-5” “ARDEX X-5”
Adhesive – Gypsum “ARDEX D14 “ARDEX X 5 “ARDEX X 5 “ARDEX X 5
Wall Board Type I Flexible Thinset Flexible Thinset Flexible Thinset
Premixed Tile Mortar” Mortar” Mortar”
Adhesive
(Mastic)”
Adhesive – Gypsum “ARDEX X 5 “ARDEX X 5 “ARDEX X 5 “ARDEX X 5
Wall Board (LVP) Flexible Thinset Flexible Thinset Flexible Thinset Flexible Thinset
Mortar” Mortar” Mortar” Mortar”
Grout See Note 1 See Note 1
Note 1: Laticrete "Spectra LOCK Pro Grout" and Mapei “Opticolor” are the grout products recommended
by Marriott
END OF SECTION
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 42 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Suspended Metal Grid Systems Complete With Wall Trim
2. Ceiling Tiles
B. Related Sections:
1. Divisions 21 (13), 23 (15), and 26 (13) Sections for light fixtures, sprinklers, and air-
distribution components.
10.02 REFERENCES
A. ASTM International Publications:
1. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
2. C635 “Standard Specification for the Manufacture, Performance, and Testing of Metal
Suspension Systems for Acoustical Tile and Lay-in Panel Ceilings”
3. C636 “Standard Practice for Installation of Metal Ceiling Suspension Systems for
Acoustical Tile and Lay-In Panels”
4. E1264 “Standard Classification for Acoustical Ceiling Products”
B. United States Department of Agriculture Food Safety and Inspection Service (USDA FSIS)
Requirements
10.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Product Data: Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330)
indicating specified items selected for use in project with the following supporting data.
1. Manufacturer's product and maintenance data for each type of ceiling system and
accessory.
2. Samples: Min 6” x 6” samples of specified acoustical panel, 8” long samples of exposed
wall molding, trim and suspension system (main runner and cross-tee).
10.04 QUALITY ASSURANCE
A. Qualifications of Installers:
1. The suspended ceiling Subcontractor shall have a record of successful installations of
similar ceilings acceptable to the Architect.
2. For the actual fabrication and installation of all components of the system, use only
personnel who are thoroughly trained and experienced in the skills required and
completely familiar with the requirements established for this work.
B. In addition to complying with all pertinent codes and regulations, suspension system shall be
installed according to ASTM C636, Installation of Metal Ceiling Suspension System for
Acoustical Tile and Lay-in Panels.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 43 ▪
PART 11 PRODUCTS
11.01 STRUCTURAL EXPOSED SUSPENSION SYSTEM
A. Avendra, LLC Preferred Manufacturers:
1. Armstrong World Industries, Inc. (888-234-5464)
B. Approved Manufacturers:
1. System used shall be as shown in Interior Finish Index or approved substitution by:
a. Chicago Metallic Corp. (800-323-7164)
b. USG Interiors, Inc. (800-950-3839)
C. Type I Grid:
a. Acceptable Products:
1) “DX-24 Grid System”; USG Interiors, Inc.
2) “Prelude XL 15/16” Exposed Tee System”; Armstrong World Industries, Inc.
3) “200 Snap-Grid System”; Chicago Metallic Corp.
4) Armstrong World Industries, Inc.
2. System used shall be double web, direct hung exposed system.
a. General: The systems shall be such that the ceiling panels may be removed without
damage; that the main runner and cross runners may be removed and replaced
without deforming the runners or disturbing the balance of the grid system.
3. Main Runners
a. Acceptable Products:
1) “7300 Series” with 1-1/2" ht., 15/16" face, steel; Armstrong World Industries,
Inc.
2) “Number DX-24” with 1-1/2" ht., 15/16" face, steel; USG Interiors, Inc.
3) “Number 211” with 1-1/2" ht., 15/16" face, steel; Chicago Metallic Corp.
b. The main runner shall have a non-directional bayonet coupling.
4. Cross Runners: Designed to support lay-in lighting fixtures and to receive acoustical tile
at sides of fixture opening.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 44 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 45 ▪
PART 12 EXECUTION
12.01 SURFACE CONDITIONS
A. Inspection: Prior to all work of this Section, carefully inspect the installed work of all other
trades and verify that all such work is complete to the point where this installation may
properly commence. Verify that suspended ceiling systems are installed in strict accordance
with all pertinent codes and regulations, and the manufacturer's recommendations.
B. Discrepancies: In the event of discrepancy, immediately notify the Owner’s Representative.
Do not proceed in areas of discrepancy until all such discrepancies have been fully resolved.
12.02 INSTALLATION
A. General:
1. Install acoustical panel, suspension system and accessories in compliance with
manufacturers instructions and requirements of ASTM C636.
2. Install ceiling system in a true and even plane with straight line courses laid out
symmetrically about center lines of area or as indicated. Border tile shall be minimum 6"
wide and neatly fit against vertical surfaces to form a tight fit.
3. Provide metal edge angle at perimeter of units as detailed on Drawings. Cut and fit
around light fixtures, diffusers, etc.
B. Lay-In Ceiling System:
1. Hanging main tees parallel in a flat plane by means of #10 gauge wire hangers attached
to construction above. Hangers shall be spaced not over 4'-0" along the main tees and
within 6" of the ends and splices of main tees, and other interruptions. Main tees shall be
spaced 2'- 0" o.c. Cross tees shall be interlocked to main tees and spaced as required to
support tile edges.
2. Attachment to ducts, pipes, etc. will not be permitted. Bridge under obstructions with a
grid of 1-1/2" cold rolled channels or other suitable members to support ceiling grid.
3. Install wall angle at perimeter of walls, partitions, columns, pipes, and other obstructions
that extend above the ceiling. Securely attach with appropriate fastening devices at
maximum 16" o.c. Form reveal of same depth and width as that formed between edge of
panel and flange at exposed suspension grid. Neatly cut and fit around light fixtures,
diffusers, etc. Provide wall angles fabricated to diameter required to fit penetrations.
4. Insert ceiling panels, installing hold down clips on panels extending over partitions and
where required to maintain fire ratings.
5. At all locations where ceiling tiles are cut, the cut edges of the tiles shall match the
premanufactured edges (i.e. cut edges are to be beveled to match beveled edged tiles).
Exposed cut edges are to be painted to match face of tile with paint as approved by tile
manufacturer.
12.03 ADJUSTING AND CLEANING
A. Completely remove all finger prints and traces of soil and damage from the surfaces of grid
and acoustical materials, using only those cleaning materials recommended for that purpose
by the manufacturer of the material being cleaned.
B. Replace units which are damaged or improperly installed.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 46 ▪
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 47 ▪
PART 13 GENERAL
13.01 SUMMARY
A. Section Includes:
1. High-Pressure Plastic-Laminate Flooring
B. Related Sections:
1. Section 09 30 00 (09310) - Tiling
2. Section 09 65 00 (09650) - Resilient Flooring
3. Section 09 68 00 (09680) - Carpeting
13.02 REFERENCES
A. ASTM International Publications:
1. F710 “Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring”
13.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Submit manufacturer's product and maintenance data for each type of flooring and
accessory.
a. Certification by flooring manufacturer that products supplied for flooring installation
comply with local regulations controlling use of volatile organic compounds (VOCS).
2. Submit color selection in the form of actual sections of flooring, including accessories, for
each type of plastic-laminate flooring required showing full range of colors and patterns
available.
13.04 QUALITY ASSURANCE
A. Single-Source Responsibility for Flooring: Obtain each type, color and pattern of flooring from
a single source with resources to provide products of consistent quality in appearance and
physical properties without delaying progress of the work.
B. Installer Qualifications: Firm experienced in installation or application of systems similar in
complexity to those required for this Project, including specific requirements indicated.
1. Acceptable to or licensed by manufacturer.
C. Field Samples Prepare field samples for Owner's review and to establish requirements for
ratings and finish texture.
1. Correct areas or modify method of installation as directed by Owner's Representative to
comply with specified requirements.
2. Maintain field samples accessible to serve as a standard of quality for this Section.
3. Field samples shall consists of a 10 foot square panel for review by Owner's
Representative.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 48 ▪
PART 14 PRODUCTS
14.01 MANUFACTURERS:
A. Avendra, LLC Preferred Manufactures:
1. None
B. Approved Manufacturers:
1. WilsonArt International, Inc. (800-433-3222)
14.02 HIGH PRESSURE DECORATIVE LAMINATE FLOORING
A. Composite panel consisting of high-pressure laminate surfacing and high pressure laminate
balancing backer bonded to high density fiberboard (HDF) core with moisture resistant
adhesive.
B. Color & Pattern: Refer to Interior Finish Index.
C. All flooring shall be the maximum extent possible of a single batch number.
14.03 RESILIENT BASE
A. Refer to Section 09 65 00 (09650).
14.04 INSTALLATION ACCESSORIES
A. Trowelable Underlayments and Patching Compounds: Latex-modified, portland-cement-
based formulation provided or approved by tile manufacturer for applications indicated.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 49 ▪
PART 15 EXECUTION
15.01 INSPECTION:
A. Installer must examine the areas and conditions under which plastic-laminate flooring and
accessories are to be installed and notify the Contractor in writing of conditions detrimental to
the proper and timely completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected in a manner acceptable to the Installer.
15.02 CONCRETE SUBFLOORS:
A. Verify that concrete slabs comply with ASTM F710 and the following:
1. Slab substrates are dry and free of curing compounds, sealers, hardeners, and other
materials whose presence would interfere with bonding of adhesive. Determine adhesion
and dryness characteristics by performing bond and moisture tests recommended by tile
manufacturer.
2. Finishes of subfloors comply with tolerances and other requirements specified in
Division 03 Section, "Cast-In-Place Concrete" for slabs receiving resilient flooring.
3. Subfloor Moisture Conditions: Before installing flooring Contractor shall verify that
Moisture emission rate of not more than 3 lb/1000 sq. ft./24 hours when tested by calcium
chloride moisture test in compliance with CRI 104, 6.2.1, with subfloor temperatures not
less than 55 deg F, or as recommended by manufacturer.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 50 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 51 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 52 ▪
END OF SECTION
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 53 ▪
PART 16 GENERAL
16.01 SUMMARY
A. Section Includes:
1. Vinyl Composition Tile
2. Sheet Vinyl Flooring
3. Resilient Base
4. PVC Thresholds
5. Solid Vinyl Transition Edges
6. Stair Nosings
B. Related Sections:
1. Section 09 30 00 (09310) - Tiling
2. Section 09 68 00 (09680) - Carpeting
3. Section 14 24 23 (14240) - Hydraulic Elevators
16.02 REFERENCES
A. ASTM International Publications:
1. C241 “Standard Test Method for Abrasion Resistance of Stone Subjected to Foot Traffic”
2. C503 “Standard Specification for Marble Dimension Stone (Exterior)”
3. D2047 “Standard Test Method for Static Coefficient of Friction of Polish-Coated Flooring
Surfaces as Measured by the James Machine”
4. D2240 “Standard Test Method for Rubber Property—Durometer Hardness”
5. D3389 “Standard Test Method for Coated Fabrics Abrasion Resistance (Rotary Platform,
Double-Head Abrader)”
6. E648/NFPA 253 “Standard Test Method for Critical Radiant Flux of Floor-Covering
Systems Using a Radiant Heat Energy Source”
7. E662/NFPA 258 “Standard Test Method for Specific Optical Density of Smoke Generated
by Solid Materials”
8. F710 “Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring”
9. F1066 “Standard Specification for Vinyl Composition Floor Tile”
B. Carpet & Rug Institute (CRI)
1. Standard for Installation of Commercial Carpet CRI 104, Current Edition
C. Code of Federal Regulations (CFR)
1. 40 CFR 763 - Asbestos: Appendix A - Transmission Electron Microscopy Analytical
Methods
▪ DIVISION 09 FINISHES ▪
▪ PAGE 54 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 55 ▪
PART 17 PRODUCTS
17.01 VINYL COMPOSITION TILES:
A. Avendra, LLC Preferred Manufactures:
1. Armstrong World Industries, Inc. (800-442-4212 x 2)
B. Approved Manufacturers:
1. Tarkett (800-899-8916)
a. To access the Tarkett National Account Program set up for Marriott inventory &
pricing, you must order through the online portal at:
http://mobileb2b.tarkettna.com/DistributorPortal/externalredirect/cep.
b. After registering and setting up your password, orders can then be placed. You will
be required to provide the Program Code and Program Access codes listed below to
register. All orders should be placed directly with Tarkett via this portal and will be
serviced via their authorized service channel provider nationally.
1) Program Code: 152798
2) Program Access Code #776630.
c. Please ensure that only those authorized to be a partner and participate in the
Marriott International National Account Program have access to this information.
d. For problems contact Theresa Thomas (440-708-9318) or Kevin Tierney (713-204-
7664).
▪ DIVISION 09 FINISHES ▪
▪ PAGE 56 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 57 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 58 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 59 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 60 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 61 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 62 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 63 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 64 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 65 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 66 ▪
END OF SECTION
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 67 ▪
PART 19 GENERAL
19.01 SUMMARY
A. Section Includes:
1. Resilient Athletic Flooring
a. Adhesive and Accessories
B. Related Sections:
1. Section 09 65 00 (09650) – Resilient Flooring
19.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. D2047 “Standard Test Method for Static Coefficient of Friction of Polish-Coated Flooring
Surfaces as Measured by the James Machine”
2. D2240 “Standard Test Method for Rubber Property—Durometer Hardness”
3. D5516 “Standard Test Method for Evaluating the Flexural Properties of Fire-Retardant
Treated Softwood Plywood Exposed to Elevated Temperatures”
4. E648/NFPA 253 “Standard Test Method for Critical Radiant Flux of Floor-Covering
Systems Using a Radiant Heat Energy Source”
5. E662/NFPA 258 “Standard Test Method for Specific Optical Density of Smoke
Generated by Solid Materials”
6. E1745 "Standard Specification for Water Vapor Retarders Used in Contact with Soil or
Granular Fill under Concrete Slabs"
7. F710 “Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring”
8. F970-00 “Standard Test Method for Static Load Limit”
9. F1869 “Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete
Subfloor Using Anhydrous Calcium Chloride”
10. G21-96 “Standard Practice for Determining Resistance of Synthetic Polymeric Materials
to Fungi”
B. Carpet & Rug Institute (CRI) Publications:
Standard for Installation of Commercial Carpet CRI 104, Current Edition
C. Occupational Safety & Health Administration (OSHA) Regulations:
1. OSHA Regulation 29 CFR Toxic and Hazardous Substances 1910-1200 Hazard
Communication
19.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 68 ▪
PART 20 PRODUCTS
20.01 RESILIENT ATHLETIC FLOORING:
A. Avendra, LLC Preferred Manufactures:
1. None
▪ DIVISION 09 FINISHES ▪
▪ PAGE 69 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 70 ▪
PART 21 EXECUTION
21.01 INSPECTION:
A. Installer must examine the areas and conditions under which resilient flooring and accessories
are to be installed and notify the Contractor in writing of conditions detrimental to the proper
and timely completion of the work. Do not proceed with the work until unsatisfactory
conditions have been corrected in a manner acceptable to the Installer.
1. Visually inspect for evidence of moisture, alkaline salts, carbonation, dusting, mold, or
mildew.
2. Failure to call attention to defects or imperfections will be construed as acceptance and
approval of the subfloor. Installation indicates acceptance of substrates with regard to
conditions existing at the time of installation.
21.02 PREPARATION
A. General: Comply with manufacturer's installation specifications for preparing substrates to
receive products indicated.
B. Sweep and vacuum clean substrates to be covered by floor coverings immediately before
installation. After cleaning, examine substrates for moisture, alkaline salts, carbonation, and
dust. Proceed with installation only after unsatisfactory conditions have been corrected.
C. This Contractor to remove coatings, including curing compounds, adhesives, plastics, and
other substances that are incompatible with flooring adhesives and that contain soap, wax, oil,
or silicone, by using a terrazzo or concrete grinder, a drum sander, or a polishing machine
equipped with a heavy-duty wire brush. Surface to receive new flooring shall be prepared,
including removal of existing materials not acceptable for proper installation of new materials,
as required by manufacturer. Do not use solvents.
1. Prep floor according to ASTM F710 criteria.
D. Use leveling compound as recommended by flooring manufacturer for filling small cracks and
depressions in subfloors.
E. Apply concrete slab primer, if recommended by flooring manufacturer, prior to application of
adhesive. Apply in compliance with manufacturer's directions.
21.03 CONCRETE SUBFLOORS
A. Concrete subfloors to be placed a minimum of twenty-eight (28) days prior to the installation of
rubber athletic flooring.
B. Verify that concrete slabs comply with ASTM F710 and the following:
1. Slab substrates are dry and free of curing compounds, sealers, hardeners, residual
adhesives, adhesive removers, and other materials whose presence would interfere with
bonding of adhesive. Determine adhesion and dryness characteristics by performing
bond and moisture tests recommended by manufacturer.
2. Finishes of subfloors comply with tolerances and other requirements specified in
Division 03 Section, "Cast-In-Place Concrete" for slabs receiving resilient flooring.
3. Subfloor Moisture Conditions: Before installing flooring Contractor shall verify that
Moisture emission rate of not more than 3 lb/1000 sq. ft./24 hours when tested by calcium
chloride moisture test in compliance with CRI 104, 6.2.1 and does not exceed the
▪ DIVISION 09 FINISHES ▪
▪ PAGE 71 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 72 ▪
END OF SECTION
Revision Log
SECTION 09 68 00 (09680) - CARPETING
PART 22 GENERAL
22.01 SUMMARY
A. Section Includes:
1. Preparation of Surfaces to Receive Carpeting.
2. Carpet:
a. Furnished by Owner, installed by Contractor
b. Stretch-in Installation
c. Direct-Glue-Down Installation
d. Double-Glue-Down Installation
e. Carpet with Attached-Cushion Installation
f. Carpet with Preapplied Adhesive Installation
3. Carpet Cushion:
a. Furnished by Owner, installed by Contractor
4. Accessories, including tack strips, adhesives tapes and all other required accessories.
5. Transition edges
6. Carpet stair nosings
B. Related Documents:
1. Seam Layout Drawings provided by Marriott International
2. Marriott International FF & E Specification Manual.
C. Related Sections:
1. Section 03 30 00 (03300) - Cast-in-Place Concrete
2. Section 03 54 13 (03500) - Cementitious Decks and Underlayment
3. Section 09 65 00 (09650) - Resilient Flooring
▪ DIVISION 09 FINISHES ▪
▪ PAGE 73 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 74 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 75 ▪
PART 23 PRODUCTS
23.01 MATERIALS
A. Carpet: Refer to Interior Finish Index
23.02 CARPET CUSHIONS
A. The following carpet cushion information is provided solely for use by the Contractor to
determine locations.
B. Rubber padding - 50 oz. Badger waffle type pad shall be installed in Guest Rooms and suites
unless TredMor pad is specified.
C. Rubber padding - 68 oz. Granite IV flat type pad shall be installed in Public Areas and Guest
Room Corridors unless Tred-Mor pad or direct glue-down is specified.
1. Rubber padding shall be cemented to the floor with a liquid mastic around the perimeter
and in an use pattern across the field.
2. Rubber padding joints shall be at a right angle to all carpet seams. When this is not
practical, shift the pad so that the joints are several inches from the carpet seams. All
padding joints shall be taped.
D. Tred-Mor Padding:
1. 1562 used in Ambulatory Guest Rooms (except at ADA accessible Guest Rooms)
2. 2568 used in Guest Room Corridors and other Public Areas not listed below
3. 2580 used in Assembly Areas
23.03 ACCESSORIES
A. Seaming: Hot-melt seaming adhesive or similar product recommended by carpet
manufacturer for taping seams and buttering cut edges at backing to form secure seams and
prevent pile loss at seams.
B. Hot melt tape – (all stretch installation areas except Dubl-Stik installations)
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. “6 inch - Super 3S Tape”; ORCON (800-227-0601)
C. Carpet and Accessory Adhesives: (All direct glue-down areas except double-stik installations)
1. Non-staining type as recommended by carpet manufacturer for use intended, complying
with the following:
▪ DIVISION 09 FINISHES ▪
▪ PAGE 76 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 77 ▪
PART 24 EXECUTION
24.01 EXAMINATION
A. Examine substrates, areas, and conditions for compliance with requirements for maximum
moisture content, alkalinity range, installation tolerances, and other conditions affecting carpet
performance. Verify that substrates and conditions are satisfactory for carpet installation and
comply with requirements specified.
B. Concrete Subfloors: General Contractor shall verify that concrete slabs comply with
ASTM F710 and the following:
1. Slab substrates are dry and free of curing compounds, sealers, hardeners, and other
materials that may interfere with adhesive bond. Determine adhesion and dryness
characteristics by performing bond and moisture tests recommended by the carpet and
▪ DIVISION 09 FINISHES ▪
▪ PAGE 78 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 79 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 80 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 81 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 82 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 83 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 84 ▪
END OF SECTION
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 85 ▪
PART 25 GENERAL
25.01 SUMMARY
A. Section Includes:
1. Vinyl Wall Covering
2. Prime Coat on Walls
3. Adhesives and Cleaning of Adjacent Surfaces
4. All accessories for complete installation
B. Related Sections:
1. Section 09 21 16 (09255) - Gypsum Board Assemblies
2. Section 09 90 00 (09900) - Painting
25.02 REFERENCES
A. ASTM International (ASTM) Publications:
1. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
2. F793 “Standard Classification of Wall-covering by Durability Characteristics”
B. Gypsum Association (GA) Publications:
1. Recommended Levels of Gypsum Board Finish - GA-214-M-97
C. National Fire Protection Association (NFPA) Publications:
1. NFPA 265: Standard Methods of Fire Tests for Evaluating Room Fire Growth
Contribution of Textile Coverings on Full Height Panels and Walls
25.03 SYSTEM DESCRIPTION
A. Contractor is responsible for receiving and handling on site and installing wall covering
material furnished by Owner and will fill out and process all receiving reports furnished by
Owner.
B. Provide strippable adhesive and primer for all wall covering.
C. Contractor shall provide wall covering quantity take-offs to the Owner within 45 days of award
of the contract.
25.04 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Provide certification by the manufacturer that products supplied comply with local
regulations controlling use of volatile organic compounds (VOC's).
2. Provide maintenance data including methods for maintaining wallcovering as well as
precautions for use of cleaning materials and methods that could be detrimental to
finishes and performance.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 86 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 87 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 88 ▪
PART 27 EXECUTION
27.01 INSPECTION
A. Examine substrates for compliance with requirements for moisture content and other
conditions affecting performance of Work of this Section. Do not proceed with installation until
unsatisfactory conditions have been corrected.
1. Refer to Section 09 21 16 (09255) - Gypsum Board Assemblies for the levels of gypsum
board finish per GA-214 required for a proper substrate to apply the wall coverings.
a. Wall Covering: Level 4 Finish required.
b. Graphic Wall Cover: Level 5 Finish required.
B. Ensure surfaces to receive all covering are clean, true, and free to irregularities. Inspect
surfaces before commencing work and report defects in writing to the Owner's representative.
C. Ensure wall surface flatness tolerances do not vary more than 1/8" in 10 feet, nor vary at a
rate greater than 1/16" per running foot.
D. Schedule installation of wallcovering as late as possible in the construction schedule to
prevent damage during construction and movement of materials.
E. Inspect wall covering for defects. Do not install defective wall covering. Notify Owner's
representative of any defects immediately.
1. Notify the [Owner's Representative] of variations in color or pattern match. Do not
continue with work until instructed by [Owner's Representative].
27.02 PREPARATION
A. Comply with manufacturers written instructions for surface preparation.
B. Test surfaces to receive wallcovering with a moisture meter. Do not install wallcovering on
surfaces with a moisture content exceeding 4%.
C. Clean substrates of substances that could impair wall covering's bond, including mold, mildew,
oil, grease, incompatible primers, and dirt.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 89 ▪
END OF SECTION
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 90 ▪
PART 28 GENERAL
28.01 SUMMARY
A. Section Includes:
1. This Section includes surface preparation and the application of paint materials to
exposed interior and exterior items and surfaces scheduled. Surface preparation, prime
and finish coats specified are in addition to shop-priming and surface treatments.
2. Paint all exposed surfaces, whether or not colors are designated, except where a surface
or material is indicated not to be painted or is to remain natural. Where an item or
surface is not mentioned, paint the same color as similar adjacent materials or surfaces.
If color or finish is not designated, the Owner will select from standard colors or finishes
available.
3. Except in mechanical and electrical rooms, paint all exposed plumbing, heating, fire
protection, and electrical material to match the walls and ceilings of that area unless
noted otherwise. This shall include, but not be limited to, pipes, sprinkler piping,
insulation, conduit, ducts, access panels, grilles, diffusers, hangers, exposed steel and
iron supports, HVAC and electrical equipment that do not have a factory applied finish,
whether the adjacent surfaces receive paint or not, and the like. Include dampers or
baffles behind grilles.
4. Unless noted otherwise, painting is not required on pre-finished items, finished metal
surfaces, concealed surfaces, operating parts, sprinkler heads, or labels.
a. All louvers and grilles to be painted to] [color as shown in Interior Finish Index] [.]
b. Labels: Do not paint over Underwriter's Laboratories, FMG or other code-required
labels, or equipment name, identification, performance rating, or nomenclature
plates.
B. Related Sections:
1. Section 08 11 13 (08110) - Steel Doors and Frames: Prime coat on new hollow metal
work shall be furnished under this Section.
2. Prime coat on lintels shall be furnished under the Division 05 Sections.
3. Section 09 21 16 (09255) - Gypsum Board Assemblies: Spray applied textured coating
specified in).
4. Section 09 96 00 (09960) - High-Performance Coatings: Prime and finish coat for
exposed exterior ferrous metal items [and ferrous metal items located within Interior Pool
areas] shall be furnished under that Section. Refer to that Section for items included.
28.02 REFERENCES
A. Underwriter's Laboratories, Inc. (UL) Standards
B. FM Global (FMG): Standards
C. ASTM International (ASTM) Publications:
1. D16 “Standard Terminology for Paint, Related Coatings, Materials, and Applications”
2. D2824 “Standard Specification for Aluminum-Pigmented Asphalt Roof Coatings,
Nonfibered, Asbestos Fibered, and Fibered without Asbestos”
3. D1187 “Standard Specification for Asphalt-Base Emulsions for Use as Protective
Coatings for Metal; 1997 (Re-approved 2002)”
▪ DIVISION 09 FINISHES ▪
▪ PAGE 91 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 92 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 93 ▪
PART 29 PRODUCTS
29.01 MANUFACTURERS
A. Except where noted otherwise, all finishing materials, thinners, etc., shall be the best quality,
first line materials as manufactured by one of the following manufacturers:
▪ DIVISION 09 FINISHES ▪
▪ PAGE 94 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 95 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 96 ▪
PART 30 EXECUTION
30.01 EXAMINATION
A. Examine substrates and conditions under which painting will be performed for compliance with
requirements. Do not begin application until unsatisfactory conditions have been corrected.
1. Start of painting will be construed as Applicator's acceptance of surfaces and conditions
within a particular area.
30.02 SURFACES TO BE COATED
A. Unless noted otherwise, paint access doors, panels, registers, diffusers, light fixture trim,
metal speaker covers and grilles the same color as adjacent surfaces. Paint access doors
and panels in open position.
B. Paint interiors of ducts showing through registers and grilles flat black.
C. Paint prime coated or previously painted hinges the same as door frame to which they are
attached.
D. Finish edges of doors to match faces.
E. Do not paint electrical device face plates or devices, sprinkler heads, smoke alarms or
thermostats/covers.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 97 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 98 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 99 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 100 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 101 ▪
END OF SECTION
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 102 ▪
PART 31 GENERAL
31.01 SUMMARY
A. Section Includes:
1. Spray Applied Textured Finish and Primer
a. Textured Finish for Ceilings.
b. Textured Finish for Walls.
B. Related Sections:
1. Section 01 35 16 (01120) – Alteration Project Procedures
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 07 92 00 (07920) – Joint Sealants
4. Section 09 21 16 (09255) – Gypsum Board Assemblies
5. Section 09 21 16.23 (09265) - Gypsum Board Shaft-Wall Assemblies
6. Section 09 72 00 (09950) – Wall Coverings
7. Section 09 90 00 (09900) - Painting
31.02 REFERENCES
A. ASTM International (ASTM) Publications:
1. C11 “Standard Terminology Relating to Gypsum and Related Building Materials and
Systems”
2. C475 “Standard Specification for Joint Compound and Joint Tape for Finishing Gypsum
Board”
3. C840 “Standard Specification for Application and Finishing of Gypsum Board”
4. E84 “Standard Test Method for Surface Burning Characteristics of Building Materials”
5. E90 “Standard Test Method for Laboratory Measurement of Airborne Sound
Transmission Loss of Building Partitions and Elements”
6. E119 “Standard Test Methods for Fire Tests of Building Construction and Materials”
7. E413 “Classification for Rating Sound Insulation”
B. Gypsum Association (GA) Publications:
1. GA-214 “Recommended Levels of Gypsum Board Finish”
2. GA-216 “Application and Finishing Of Gypsum Panel Products”
3. GA-505 for definitions of terms for gypsum board assemblies not defined in this Section
C. United States Gypsum Co. (USG):
1. "Gypsum Construction Handbook"
▪ DIVISION 09 FINISHES ▪
▪ PAGE 103 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 104 ▪
PART 32 PRODUCTS
32.01 SPRAY APPLIED TEXTURED FINISH
A. Texture finish for Ceilings:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. “Sheetrock Brand Wall and Ceiling Spray Texture QT”; United States Gypsum Co.
(800-950-3839)
b. "ProForm Perfect Spray"; National Gypsum Company, Gold Bond Building Products
Div. (800-628-4662)
3. Texture: Refer to Interior Finish Index.
4. Finish color: Refer to Interior Finish Index.
5. Uniform color with no areas or spots of discoloration.
B. Texture Finish for Walls:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. "Sheetrock Brand Wall and Ceiling Spray Texture - Unaggregated "Tuf Tex" -
Spatter Knockdown, United States Gypsum Co. (312-606-4000)
▪ DIVISION 09 FINISHES ▪
▪ PAGE 105 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 106 ▪
PART 33 EXECUTION
33.01 EXAMINATION
A. Examine substrates with Installer present, to which textured finish will be applied, for
compliance with requirements for installation tolerances and other conditions affecting
performance of finishes specified in this Section.
B. Installer shall examine areas and conditions under which coating work is to be applied and
notify the Contractor in writing of conditions detrimental to proper and timely completion of the
work.
C. Do not proceed with installation until unsatisfactory conditions have been corrected.
33.02 PREPARATION - SPRAY APPLIED TEXTURED FINISH
A. General: Remove hardware and hardware accessories, plates, machined surfaces, light
fixtures, and similar items already installed that are not to be coated. If removal is impractical
or impossible because of size or weight of item, provide surface-applied protection before
surface preparation and coating.
1. After completing coating operations in each area, reinstall items removed using workers
skilled in trades involved.
B. Cleaning: Before applying coatings or other surface treatments, clean substrates of
substances in accordance with manufacturer’s recommendations that could impair bond of
coating systems. Remove oil and grease before cleaning.
1. Schedule cleaning and coating application so dust and other contaminants from cleaning
operations will not fall on wet, newly coated surfaces.
C. Surface Preparation: Clean and prepare surfaces to be coated according to the
manufacturer's written instructions for the particular substrate conditions, and as specified.
1. Surface Preparation and Primer: Prepare and apply primer to gypsum panels and other
surfaces receiving texture finishes according to texture finish manufacturer's instructions.
Apply primer only to surfaces that are clean, dry, and smooth. Primer: Apply at not less
than manufacturer's recommended spreading rate, to establish a total dry film thickness
recommended by coating manufacturer.
2. Accent Walls may require special wall preparation, refer to manufacturer’s
recommendations.
3. Gypsum Board Preparation:
a. Treat joints and fastener heads in accordance with spray applied finish
manufacturer’s recommendations and Section 09 21 16 “Gypsum Board
Assemblies”.
b. Fill and smooth scratches and scuffs in gypsum board surfaces.
c. Allow gypsum board joint treatment and fillers to thoroughly dry before application.
4. Cementitious Surfaces: Prepare concrete, concrete masonry, precast concrete, and
similar surfaces to be coated. Remove efflorescence, chalk, dust, dirt release agents,
▪ DIVISION 09 FINISHES ▪
▪ PAGE 107 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 108 ▪
END OF SECTION
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 109 ▪
PART 34 GENERAL
34.01 SUMMARY
A. Section Includes:
1. Special coating for exterior [and] [, indoor pool area] [and] exposed ferrous metals.
2. Epoxy Floor Coating
3. Concrete Stain/Sealer
4. This Section includes surface preparation and the application of special coating materials
to items scheduled.
a. Surface preparation, prime and finish coats specified are in addition to shop-priming
and surface treatments.
5. Paint all exposed surfaces, whether or not colors are designated, except where a surface
or material is indicated not to be painted or is to remain natural. Where an item or
surface is not mentioned, paint the same color as similar adjacent materials or surfaces.
If color or finish is not designated, the [Owner’s Representative] will select from standard
colors or finishes available.
6. Painting is not required on pre-finished items, operating parts, or labels.
a. Labels: Do not paint over Underwriter's Laboratories, Factory Mutual or other code-
required labels, or equipment name, identification, performance rating, or
nomenclature plates.
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-in-Place Concrete
2. Section 03 54 13 (03500) - Cementitious Decks and Underlayment
3. Section 05 52 00 (05520) - Handrails and Railings
4. Section 08 11 13 (08110) - Steel Doors and Frames
5. Section 09 90 00 (09900) - Painting
34.02 REFERENCES
A. ASTM International (ASTM) Publications:
1. D16 “Standard Terminology for Paint, Related Coatings, Materials, and Applications”
B. The Society for Protective Coatings (SSPC) Publications:
1. SP - Surface Preparation Standards and Specifications
a. SSPC-SP 1, “Solvent Cleaning”
b. SSPC-SP 3 "Power Tool Cleaning"
c. SSPC-SP 6/NACE No. 3, “Commercial Blast Cleaning”
d. SSPC-SP 10/NACE No. 2, “Near-White Blast Cleaning”
e. SSPC-SP 11, “Power Tool Cleaning to Bare Metal”
C. The Painting and Decorating Contractors of America (PDCA)
▪ DIVISION 09 FINISHES ▪
▪ PAGE 110 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 111 ▪
PART 35 PRODUCTS
35.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Exterior [and Interior Pool] Exposed Ferrous Metals:
a. The Sherwin-Williams Company (800-321-8194)
2. Epoxy Coating for Concrete Floors (Interior):
a. The Sherwin-Williams Company (800-321-8194)
3. Concrete Stain/Sealer
a. The Sherwin-Williams Company (800-321-8194)
B. Approved Manufacturers:
1. and Interior Pool] Exposed Ferrous Metals:
a. Tnemec Company, Inc. (800-356-3041)
▪ DIVISION 09 FINISHES ▪
▪ PAGE 112 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 113 ▪
PART 36 EXECUTION
36.01 EXAMINATION
A. Examine substrates and conditions under which painting will be performed for compliance with
requirements. Do not begin application until unsatisfactory conditions have been corrected.
B. Start of coating work will be construed as the applicator's acceptance of surfaces within
particular area.
▪ DIVISION 09 FINISHES ▪
▪ PAGE 114 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 115 ▪
▪ DIVISION 09 FINISHES ▪
▪ PAGE 116 ▪
END OF SECTION
Revision Log
▪ DIVISION 09 FINISHES ▪
▪ PAGE 117 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Decorative Merchandising Slotted Display Wall.
1.02 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Submit product data which shall include physical dimensions, operational features, color
and finish, anchorage details, rough-in measurements, location, and details.
2. Submit manufacturer's installation instructions.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. “MegaWall Aluminum Slatwall”; MegaWall, Inc. (616-647-4190)
2. Approved Substitution
2.02 DISPLAY WALL
A. 1-sided Aluminum Panel Color: Powdercoated finish, custom color as shown on Drawings.
B. Panel Groove Insert Color: Color as shown on Drawings.
C. Overall Panel Dimension: As shown on Drawings.
D. Groove Spacing: 1-inch on centers.
E. Installation Method: Hidden Fastener system.
PART 3 EXECUTION
3.01 INSTALLATION
A. Install unit and level on wall. Secure rigidly in place in accordance with manufacturer's
instructions.
END OF SECTION
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 1 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Interior and Exterior Graphic Plaques, Characters and Accessories.
a. [Furnished by Owner, installed by Contractor:]
1) Directional Signage
2) Identification Signage
3) Projection Mounted Signage
4) Stair and Elevator Signage
5) Informational Signage
6) Letters and Graphics
7) Parking Lot Signage
8) Key Card Signage
9) Porte Cochere Signage
10) Guest Room Signage
11) Exercise Room Signage
12) Pool Signage
13) Fire Pit Emergency Shutoff Signage
14) Fire Pit Warning Plaque Signage
2. Exterior Signs:
a. [Furnished by Owner, installed by Contractor:]
1) Channel Letter Signs
2) Single-Faced, Wall Mounted Signs
3) Monument Signs
4) Pylon Signs
3. Mounting Devices and Fittings.
4. Preparation of camera-ready artwork needed to produce the complete graphics package,
unless otherwise noted.
B. Related Sections:
1. Sign Manual – Interior Graphics Package
2. Sign Manual – Exterior Graphics Package
3. Section 10 31 00 – Manufactured Fireplaces: For Emergency Shut Off and Warning
Plaque signage installed at Fire Pit
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 2 ▪
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 3 ▪
PART 5 PRODUCTS
5.01 INTERIOR SIGNAGE MANUFACTURER/FABRICATOR
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Graphic Systems Inc.; (316-267-4171)
a. Contact: Jackie Diffenbaugh
2. Cornelius Brand Signage, a Forms + Surfaces Company (800-553-7722)
a. Contact: Jessica Nagoda (800-451-0410 x 5332; jessica.nagoda@forms-
surfaces.com
3. HOTELSIGNS.com; (888-273-8726)
a. Contact: Crystal Simpson (888-273-8726)
b. Contact: Kristin Alexin (888-273-8726)
4. Approved Substitution by Marriott International
5.02 MATERIALS – INTERIOR SIGNAGE
A. Basis of Design: Refer to “Sign Manual – Interior Graphics Package” for sign types, designs,
and graphic information.
B. Acrylic: Produced by Rohm and Haas or approved substitution. Acrylic shall be cut straight
and true, free of saw marks, burrs, scratches or other imperfections.
C. Vinyl: Pressure sensitive adhesive backed vinyl with integral color as manufactured by one of
the following:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. 3M (888-364-3577)
b. Approved substitution
D. Polycarbonate Sheet: Manufactured by extrusion process, coated on both surfaces with
abrasion-resistant coating.
E. Finishes:
1. Signs: Produced by photographic silk-screen stencils unless otherwise noted. Hand-cut,
frisketed, or die-cut images will not be accepted.
2. Silk-screening inks: As manufactured by one of the following:
a. Avendra, LLC Preferred Manufacturers:
1) None
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 4 ▪
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 5 ▪
PART 6 EXECUTION
6.01 PREPARATION
A. Examination:
1. Examine areas for conditions detrimental to completion of the delivery and installation
work. Report findings to the [Architect][Owner’s Representative] immediately. Do not
proceed with work until unsatisfactory conditions have been corrected or until advised in
writing by the Owner.
2. Starting work constitutes acceptance of conditions under which the work is to be
performed. After such acceptance Contractor shall, at his own expense, be responsible
for correcting all unsatisfactory and defective work resulting from such unsatisfactory
conditions.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 6 ▪
END OF SECTION
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 7 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Extent of toilet partitions is indicated on Drawings.
2. Styles of toilet compartments include:
a. Plastic Laminate Finished, Floor-Anchored, Overhead Braced
3. Styles of Screens include:
a. Plastic Laminate Finished, Floor-Anchored
B. Related Sections:
1. Section 09 21 16 (09255) - Gypsum Board Assemblies
2. Section 09 30 00 (09310) - Tiling
3. Section 10 28 00 (10800) - Toilet, Bath, and Laundry Accessories
7.02 REFERENCES
A. Americans with Disabilities Act (ADA) II Public Accommodations
1. Americans with Disabilities Act Accessibility Guidelines (ADAAG)
B. ASTM International (ASTM) Publications:
1. A167 “Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel
Plate, Sheet, and Strip”
C. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. LD 3 - 2000 “High Pressure Decorative Laminates (HPDL)”
7.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: Submit manufacturer's detailed technical data for materials, fabrication,
and installation, including catalog cuts of anchors, hardware, fastenings, and
accessories.
2. Shop Drawings: Submit shop drawings for fabrication and erection of toilet partition
assemblies not fully described by product drawings, templates, and instructions for
installation of anchorage devices built into other work.
7.04 QUALITY ASSURANCE
A. Field Measurements: Take field measurements prior to preparation of shop drawings and
fabrication where possible, to ensure proper fitting of work. However, allow for adjustments
within specified tolerances wherever taking field measurements before fabrication might delay
work.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 8 ▪
PART 8 PRODUCTS
8.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Accurate Partitions Corp. (708-442-6800)
a. Toilet Compartments: “Floor Anchored/Overhead Braced Mounting Style”
b. Urinal Screens: Floor mounted with post supports.
2. Knickerbocker Partition Corp. (516-546-0550)
a. Toilet Comp: “Metropolitan:
b. Urinal Screens: Floor mounted with post supports.
3. Metpar Corporation (888-638-7271)
a. Toilet Compartments: "Corinthian FP-500"
b. Urinal Screens: Type "PF"
4. Flush-Metal Partition Corporation (718-784-3380)
a. Toilet Compartments: "Flushite"
b. Urinal Screens: "PS-Post Supported"
5. Bobrick Washroom Equipment (818-764-1000)
a. Toilet Compartments: No. 1042 Series, Overhead Braced
b. Urinal Screens: No. 1043 Designer Series: 1541 Classic Series, Floor-Anchored.
6. Global Partitions (516-586-3330)
a. Toilet Compartments: “Floor Anchored/Overhead Braced”
b. Urinal Screens: Floor mounted with Post Support
7. Hadrian Manufacturing, Inc. (800-536-1469)
a. Toilet Compartments: "Headrail Braced"
b. Urinal Screens: Floor mounted with Post Support
8.02 MATERIALS
A. General: Provide materials which have been selected for surface flatness and smoothness.
Exposed surfaces which exhibit pitting, seam marks, roller marks, stains, discolorations,
telegraphing of core material, or other imperfections on finished units are not acceptable.
B. Plastic Laminate: NEMA std. LD-3, minimum 0.050 inch thick, color and pattern as indicated
in Interior Finish Index.
C. Core Material for Plastic Laminate: Manufacturer's standard plywood or particleboard in
thickness to provide normal dimension of 1 inch minimum for all components.
D. Concealed Anchorage Reinforcement: Minimum 12 gauge galvanized steel sheet.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 9 ▪
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 10 ▪
END OF SECTION
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 11 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Wall Protection Corner Guards
B. Related Sections:
10.02 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Provide manufacturer's technical data, installation instructions, setting drawings,
templates, instructions, and directions for installation of anchorage devices in other work.
10.03 DELIVERY, STORAGE, AND HANDLING
A. Do not deliver guards to site until rooms in which they are to be installed are ready to receive
them.
B. Store packages to prevent physical damage or wetting.
C. Pack all parts individually in a manner to protect finish.
D. Maintain protective covers on all units until final clean-up.
10.04 WARRANTY
A. Work of this Section shall be jointly warrantied by the manufacturer and the installer for a
period of one year after final payment. Any material or workmanship that is judged defective
during this period shall be replaced at no cost to the Owner.
PART 11 PRODUCTS
11.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. IPC Door and Wall Protection Systems, Inpro Corp. (800-543-1729)
B. Approved Manufacturers:
1. Grand Entrance, A Division of Construction Specialties, Inc. (888-424-6287)
2. Balco, Inc. (800-628-0449)
3. Korogard Wall Protection Systems, a Division of RJF International Corporation (800-628-
0449)
11.02 WALL PROTECTION CORNER GUARDS
A. Surface mounted corner guards of various materials. Provide backing in walls for mounting.
B. Corner Guards: “Rigid extruded PVC, 90 degree type”; adhesive applied.
1. Size:
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 12 ▪
PART 12 EXECUTION
12.01 INSTALLATION
A. Attach retainers to wall with appropriate anchorage devices furnished by manufacturer. Snap-
lock covers onto retainers after paint or wallcoverings have been applied.
B. Install guards, accessories, and items in accordance with manufacturer's printed instructions.
C. Use concealed fastenings wherever possible.
D. Install true, plumb, and level, securely and rigidly anchored to substrate in accordance with
manufacturer's instructions for each item and each type of substrate construction.
1. Attach with manufacturer’s recommended adhesive.
END OF SECTION
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 13 ▪
PART 13 GENERAL
13.01 SUMMARY
A. Section Includes:
1. Toilet Accessories
2. Bath Accessories
3. Attachment hardware
B. Related Sections:
1. Section 05 50 00 (05500) - Metal Fabrications
2. Section 06 10 00 (06100) - Rough Carpentry: Blocking
3. Section 08 80 00 (08800) - Glazing: Unframed mirrors, tub and shower glass
4. Section 09 30 00 (09310) - Tiling: Coordinate installation of accessories
5. Section 10 21 13 (10165) - Toilet Compartments: Coordinate installation of accessories
6. Section 10 28 19.21 – Tub and Shower Doors: Coordinate installation
13.02 REFERENCES
A. ASTM International Publications:
1. A167 - “Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel
Plate, Sheet, and Strip”
2. A666 “Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel
Sheet, Strip, Plate, and Flat Bar”
B. American National Standards Institute (ANSI)
1. ICC/ANSl A117.1-2009 , “Accessible and Useable Buildings and Facilities”
C. Americans with Disabilities Act (ADA) II Public Accommodations
13.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: Mark each copy to identify applicable products, characteristics, models,
options and other supplemental data to clearly communicate information specific to this
project.
13.04 QUALITY ASSURANCE
A. Provide products of the same manufacturer for each type of accessory unit and for units
exposed in the same area.
13.05 DELIVERY, STORAGE, AND HANDLING
A. Do not deliver accessories to site until rooms in which they are to be installed are ready to
receive them.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 14 ▪
PART 14 PRODUCTS
14.01 DISTRIBUTORS
A. Avendra, LLC Preferred Distributor:
1. Contract Hardware, Inc. (800-266-3418)
a. Contact: Mark Tew
2. Home Depot Supply
a. Contact: Rajan Batra (703-404-4567)
14.02 MANUFACTURERS
A. See Toilet & Bath Accessory Matrix for list of which Manufacturer's are approved for
use on a specific item.
B. Avendra, LLC Preferred Manufacturers:
1. Franklin Brass, Liberty Hardware Manufacturing Corp., A Masco Company (800-421-
3375)
2. WingIts LLC (877-894-6448)
C. Approved Manufacturers:
1. American Specialties, Inc. (ASI) (914-476-9000)
2. Bobrick Washroom Equipment, Inc. (818-503-1630)
3. Gamco, A Bobrick Company (800-421-3375)
4. Hafele America Co. (HEWI) (336-889-2322)
5. Preferred Bath Accessories LLC. (336-575-0080)
6. Mincey Marble Manufacturing Co. (800-533-1806)
7. Shower Solutions USA, Inc. (407-314-2176)
8. Symmons Industries, Inc. (800-796-6667)
14.03 MATERIALS - TOILET ACCESSORIES
A. 18-8 (Type 302) stainless steel alloy of at least 22 gauge in all elements of cabinet work.
Unless shown otherwise, all exposed stainless steel to have a #4 Satin finish or Satin chrome
finish where applicable with all elements of a unit to have brushing in one direction.
B. Exposed surfaces to be protected with a factory applied PVC film to be left in place until final
clean-up.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 15 ▪
PART 15 EXECUTION
15.01 PREPARATION
A. Deliver inserts and rough-in frames to job site and in appropriate time for building-in. Provide
templates and rough-in measurements as required.
B. Before starting work, notify Owner’s Representative in writing of any conflicts detrimental to
installation or operation of units.
C. Verify with Owner’s Representative exact location of accessories.
15.02 INSTALLATION
A. Install fixtures, accessories, and items in accordance with manufacturer's printed instructions.
B. Use concealed fastenings wherever possible.
C. Install true, plumb, and level, securely and rigidly anchored to substrate in accordance with
manufacturer's instructions for each item and each type of substrate construction.
1. Wood blocking shall be provided at grab bars and fold down shower seats, and as shown
on Drawings.
2. Strap metal may be used for all other areas, as approved by Owner’s Representative,
unless indicated otherwise.
D. Fasteners for all accessory mounting to be theft-resistant.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 16 ▪
PART 17 GENERAL
17.01 SUMMARY
A. Section Includes:
1. Fixed Glass Panel at Shower
2. Attachment hardware
B. Related Sections:
1. Section 05 50 00 (05500) - Metal Fabrications
2. Section 06 10 00 (06100) - Rough Carpentry: Blocking
3. Section 06 61 13 (06610) -Cultured Marble Fabrications
4. Section 08 80 00 (08800) - Glazing: Unframed mirrors, tub and shower glass
5. Section 09 30 00 (09310) - Tiling: Coordinate installation of accessories
6. Section 10 21 13 (10165) - Toilet Compartments: Coordinate installation of accessories
7. Section 10 28 00 (10800) - Toilet Bath And Laundry Accessories
17.02 REFERENCES
A. ASTM International Publications:
1. A167 - “Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel
Plate, Sheet, and Strip”
2. A666 “Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel
Sheet, Strip, Plate, and Flat Bar”
B. American National Standards Institute (ANSI)
1. ICC/ANSl A117.1-2009 , “Accessible and Useable Buildings and Facilities”
C. Americans with Disabilities Act (ADA) II Public Accommodations
17.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: Mark each copy to identify applicable products, characteristics, models,
options and other supplemental data to clearly communicate information specific to this
project.
2. Shop Drawings: For tub and shower doors and enclosures.
17.04 QUALITY ASSURANCE
A. Provide products of the same manufacturer for each type of accessory unit and for units
exposed in the same area.
B. Coordinate with Tub and Shower Surrounds specified in Section 06 61 13 “Cultured Marble
Fabrications”.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 17 ▪
PART 18 PRODUCTS
18.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Continental Group (614-679-1201)
2. ProjectStone by Belstone (877-667-8663)
3. Mincey Marble Manufacturing Co. (800-533-1806)
18.02 MATERIALS
A. 18-8 (Type 302) stainless steel alloy of at least 22 gauge. Unless shown otherwise, all
exposed stainless steel to have a #4 Satin finish or Satin chrome finish where applicable with
all elements of a unit to have brushing in one direction.
B. Exposed surfaces to be protected with a factory applied PVC film to be left in place until final
clean-up.
C. Stainless steel tubing: 18 ga., Type 304, seamless welded.
D. Glazing: Safety glazing materials complying with 16 CFR 1201, Category II, with permanently
etched identification acceptable to authorities having jurisdiction.
E. Provide frameless glass panels with mounting and operating hardware of types and sizes
required to support imposed loads.
F. Fasteners, screws, and bolts: Hot dip galvanized. Expansion shields: Fiber, lead, or rubber
as recommended by accessory manufacturer for component substrate.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 18 ▪
*********************************************************************************************
18.03 FIXED GLASS PANEL AT SHOWER (453)
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. “Model Number MM-FG4086-P”; Mincey Marble Manufacturing Co. (800-533-1806)
2. Approved substitution by ProjectStone by Belstone
3. Approved substitution by Continental Group
C. Materials:
1. Glass Fixed Panel (A):
a. Clear, tempered, polished edges.
b. Size: Refer to Drawings for width and height.
2. U Channels for Fixed Panel (B1): (One side of glass panel):
a. Finish: Polished Chrome (Bright Anodized)
3. Fasteners: All fasteners to be by the manufacturer.
4. Adhesives: Type as per manufacturer’s recommendations.
5. Sealant: Silicone type as per manufacturer’s recommendations
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 19 ▪
PART 19 EXECUTION
19.01 PREPARATION
A. Deliver inserts and rough-in frames to job site and in appropriate time for building-in. Provide
templates and rough-in measurements as required.
B. Before starting work, notify Owner’s Representative in writing of any conflicts detrimental to
installation or operation of units.
C. Set units level, plumb, and true to line, without warp or rack of frames and panels, and anchor
securely in place.
D. Fasten components securely in place, with provisions for thermal movement. Install with
concealed fasteners unless otherwise indicated.
E. Install components to drain and return water to tub or shower.
F. Install doors to produce smooth operation and tight fit at contact points.
G. Verify with Owner’s Representative exact location of accessories.
19.02 INSTALLATION
A. Install all enclosures in accordance with manufacturer's printed instructions.
B. Use concealed fastenings wherever possible.
C. Install true, plumb, and level, securely and rigidly anchored to substrate in accordance with
manufacturer's instructions for each item and each type of substrate construction.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 20 ▪
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 21 ▪
PART 20 GENERAL
20.01 SUMMARY
A. Section Includes:
1. Fire Pit Insert
2. All Required Accessories
B. Related Sections:
1. Section 10 14 00 (10400) – Signage: for Fire Pit Emergency Shut Off and Warning
Plaque signage.
2. Division 23 Sections:
a. Gas pipe to fire pit and connection to fire pit burner.
3. Division 26 Sections: Wall switch connected to gas log electronic ignition.
20.02 SUBMITTALS
A. Submit "Letter of Conformance" in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Submit product data, mark each copy to identify applicable products, characteristics,
models, options and other supplemental data to clearly communicate information specific
to this project.
2. Shop Drawings and Samples: Submit copies of Shop Drawings of all items specified
herein to Architect for approval. Obtain approval of drawings prior to proceeding with
manufacturing. Shop Drawings shall indicate: elevations; details; location in the building
of each item; conditions at openings with various wall thicknesses and materials; typical
and special details of construction; methods of assembling sections; locations and
installations requirements for hardware; size, shape, and thickness of materials; and
joints and connections.
20.03 QUALITY ASSURANCE
A. Installer Qualifications: Firm with not less than 5 years of experience in installation of fireplace
units of type, quantity, and installation methods similar to work of this Section.
B. All materials shall be installed in accordance with the manufacturer's printed directions.
C. Comply with the fire-resistance ratings as indicated and as required by governing authority
and codes. Provide materials, accessories, and application procedures which have been
listed by UL.
D. Verify that components and proposed installation comply with local and state requirements for
both gas and wood burning fireplaces.
20.04 DELIVERY, STORAGE, AND HANDLING
A. All materials shall be delivered in their original unopened packages and stored in an enclosed
shelter providing protection from damage and exposure to the elements. Damaged or
deteriorated materials shall be removed from the premises.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 22 ▪
PART 22 EXECUTION
22.01 GENERAL
A. Contractor shall inspect site conditions to which work is to be installed. Report discrepancies
to Architect in writing.
B. Examine roughing-in for gas piping and electrical control wiring to verify actual locations of
connections before equipment installation.
1. Provide underground gas line and associated trenching and filling in compliance with
Division 33 Sections or the requirements of the local natural gas utility supplier and
authorities having jurisdiction. Comply with requirements of Section 23 11 23 - Facility
Natural Gas Piping for piping inside of building.
C. Verify that Fire Pit dimensions, clearances, combustion air ventilation and drainage are in
accordance with manufacturer’s published directions and listing requirements of the
equipment being installed.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 23 ▪
END OF SECTION
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 24 ▪
PART 23 GENERAL
23.01 SUMMARY
A. Section Includes:
1. Fire Extinguishers and Brackets
2. Fire Extinguisher Cabinets
3. Fire Hose and Valve Cabinet
4. Accessories
B. Related Sections:
23.02 REFERENCES
A. National Fire Protection Association (NFPA) Publications:
1. 10 “Portable Fire Extinguishers”
B. Underwriter's Laboratories, Inc. (UL) Standards:
1. 4A-“60BC classification”
23.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Submit product data which shall include physical dimensions, operational features, color
and finish, anchorage details, rough-in measurements, location, and details.
2. Submit manufacturer's installation instructions.
23.04 QUALITY ASSURANCE
A. Conform to NFPA 10 requirements for extinguishers.
23.05 OPERATION AND MAINTENANCE DATA
A. Do not install extinguishers when ambient temperatures may cause freezing.
PART 24 PRODUCTS
24.01 ACCEPTABLE MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Larsen's Manufacturing Company (800-527-7367).
2. JL Industries, an Activar Inc. Company (800-554-6077).
3. Modern Metal Products, a Division of Technico, Inc. (800-435-5544)
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 25 ▪
24.04 CABINETS:
A. Items specified below are by Larsen's Manufacturing Co. Equivalent products by listed
manufacturer will be acceptable. Verify type with Contractor.
1. Wall mounted on Bracket (FE): "MP10" Extinguisher with "B2" bracket.
2. Semi-recessed Fire Extinguisher Cabinet (FEC-1): "MP10" Extinguisher with “Gemini
Series Model [FS-]G-2409-6R"; semi-recessed cabinet, projecting 2-1/2", rough opening
of 10-1/2"W x 25"H x 4"D.
3. Surface Mounted Fire Extinguisher Cabinet (FEC-2): "MP10" Extinguisher with “Gemini
Series Model [FS-]G-2409-SM "; surface-mounted cabinet.
4. Recessed Fire Hose and Valve Cabinet with Fire Extinguisher (FVC-1): "MP10"
Extinguisher with "[FS-]G-3238-R"; Recessed Fire Hose and Valve Cabinet, projecting 2-
1/2", rough opening of 34-1/8"W x 40-1/8"H x 9-1/8"D.
5. Semi-recessed Fire Hose and Valve Cabinet with Fire Extinguisher (FVC-2): "MP10"
Extinguisher with "[FS-]G-3238-RL"; Semi-Recessed Fire Hose and Valve Cabinet,
projecting 2-1/2", rough opening of 33"W x 39"H x 6"D.
B. Cabinet:
1. Semi-Recessed Fire Extinguisher Cabinet: 18 gauge steel with acrylic thermosetting
enamel finish box construction, rolled-edge trim type, matching continuous hinge, pull
handle, 1/4” Frameless Acrylic door, baked enamel coated steel trim.
a. Door Style to be Larson “Gemini" series door with black vertical letters on white
background stating equipment in cabinet, or approved substitution by other listed
manufacturers.
1) Provide lock similar to “Larsen-Loc” on all cabinets.
b. Finish: White finish for box and trim.
c. Provide black text “FIRE EXTINGUISHER” on side of cabinet where required by
code.
2. Surface Mounted Fire Extinguisher Cabinet: 18 gauge steel with acrylic thermosetting
enamel finish box construction, matching continuous hinge, pull handle, 1/4” Frameless
Acrylic door, baked enamel coated steel trim..
a. Door Style to be Larson “Gemini" series door with black vertical letters on white
background stating equipment in cabinet, or approved substitution by other listed
manufacturers.
1) Provide lock similar to “Larsen-Loc” on all cabinets.
b. Finish: White finish for box and trim.
3. Recessed Fire Hose and Valve Cabinet: 18 gauge steel with acrylic thermosetting
enamel finish box construction, flat trim type, matching continuous hinge, pull handle, 1/4”
Frameless Acrylic door, baked enamel coated steel trim.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 26 ▪
PART 25 EXECUTION
25.01 INSPECTION
A. Verify rough openings for cabinet are correctly sized and located.
B. Beginning of installation means acceptance of existing conditions.
25.02 INSTALLATION
A. Install cabinets plumb and level in wall openings. Secure rigidly in place in accordance with
manufacturer's instructions.
END OF SECTION
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 27 ▪
PART 26 GENERAL
26.01 SUMMARY
A. Section Includes:
1. Locker Units with Hinged Doors
2. Base, Top, and Filler Panels
3. Hooks, Latches, and Hardware
4. Attachment Hardware
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry: Blocking for attachment
26.02 SYSTEM DESCRIPTION
A. Lockers: Three-tier locker. Provide standard recessed padlock handle, number plate bases,
end panels, filler panels, matching sloped top and top filler panels.
26.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Submit Shop Drawings and product data that clearly indicate locker types, sizes,
configurations, layout of groups of lockers, benches, accessories, and numbering plan.
2. Submit manufacturer's installation instructions and actual color samples, on squares of
same metal to be used for fabrication.
26.04 DELIVERY, STORAGE, AND HANDLING
A. Store and protect locker finishes and adjacent surfaces from damage during installation.
PART 27 PRODUCTS
27.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. “Industrial”; Lyon Workspace Products LLC (800-433-8488)
a. Color: No. BN 931 – B6
2. “Standard Lockers”; Republic Storage Systems Company (800-477-1255)
a. Color: No. 89 Cork
3. “Vanguard Lockers”; Penco Products, Inc. (800-562-1000)
a. Color: No. 073 Champagne
4. “Emperor Locker System”; Hadrian Manufacturing, Inc. (905-333-0300)
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 28 ▪
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 29 ▪
PART 28 EXECUTION
28.01 PREPARATION
A. Verify bases are properly sized and located.
28.02 INSTALLATION
A. Install metal lockers complete with accessories according to manufacturer's
recommendations. Install plumb, level, rigid, flush and in-line.
B. Anchor lockers with appropriate anchor devices to suit materials encountered, to floor and
walls. Apply fasteners through back-up reinforcing plates where necessary to avoid metal
distortion, using concealed fasteners.
C. Bolt adjoining locker units together to provide rigid installation.
D. Install end panels, filler panels, and tops to completely close-off all openings.
E. Anchor lockers to floors and walls at intervals recommended by manufacturer but no greater
than 36 inches (910 mm). Install anchors through back-up reinforcing plates where necessary
to avoid metal distortion, using concealed fasteners.
1. Install recess trim to recessed lockers using concealed fasteners. Provide hairline joints
and concealed splice plates.
2. Install sloping top units to lockers using concealed fasteners. Provide hairline joints and
concealed splice plates.
3. Install finished end panels to conceal exposed ends of non-recessed lockers.
28.03 ADJUST AND CLEAN
A. Adjust doors and latches to operate easily without bending. Verify that integral locking
devices are operating properly.
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 30 ▪
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 31 ▪
PART 29 GENERAL
29.01 SUMMARY
A. Section Includes:
1. Metal Storage Shelving
29.02 SUBMITTALS
A. Submit "Letter of Conformance" in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Mark each copy to identify applicable products, characteristics, models, options and other
supplemental data to clearly communicate information specific to this project.
2. Color Chart: Each product specified.
29.03 QUALITY ASSURANCE
A. Installer Qualifications: Manufacturer's authorized representative who is trained and approved
for installation of units required for this Project.
B. Source Limitations: Obtain metal storage shelving through one source from a single
manufacturer.
29.04 DELIVERY, STORAGE, AND HANDLING
A. Deliver metal storage shelving palleted, wrapped, or crated to provide protection during transit
and Project-site storage.
29.05 PROJECT CONDITIONS
A. Environmental Limitations: Do not deliver or install metal storage shelving until spaces are
enclosed and weatherproof, wet work in spaces is completed and dry, and ambient
temperature is being maintained at the levels indicated for Project when occupied for its
intended use.
29.06 COORDINATION
A. Coordinate locations and installation of metal storage shelving that may interfere with ceiling
systems including lighting, HVAC, and sprinklers.
PART 30 PRODUCTS
30.01 STORAGE SHELVING
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. "Open Clip Type Shelving" - Republic Storage Systems Company (800-477-1255)
2. "Clip - Support Shelving" - Adapto Storage Products, (800-923-2786)
3. "8000 Series" - - Lyon Workspace Products, LLC (800-433-8488)
4. "Clipper Shelving" - Penco Products, Inc (800-562-1000)
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 32 ▪
PART 31 EXECUTION
31.01 INSTALLATION
A. Set units plumb, level and square. Do not secure to adjacent walls. Adjust for rigidity.
END OF SECTION
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 33 ▪
PART 32 GENERAL
32.01 SUMMARY
A. Section Includes:
1. Wire Closet Shelves
a. Furnished by Owner, installed by Contractor
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
32.02 SYSTEM DESCRIPTION
A. Contractor is responsible for receiving and handling on site and installing wire closet shelving
materials furnished by Owner and will fill out and process all receiving reports furnished by
Owner.
32.03 QUALITY ASSURANCE
A. Installer Qualifications: Engage an experienced installer who has completed five projects
similar in material, design, and extent to that indicated for this Project and with a record of
successful in-service performance.
B. Source Limitations: Obtain metal storage shelving through one source from a single
manufacturer.
C. Mockups: Provide a sample application in one Guest Room for acceptance by the Owner's
representative and to serve as a sample standard of quality for the balance of the work.
Rework sample room if necessary to obtain Owner's acceptance.
32.04 DELIVERY, STORAGE, AND HANDLING
A. Deliver storage shelving palleted, wrapped, or crated to provide protection during transit and
Project-site storage.
32.05 PROJECT CONDITIONS
A. Environmental Limitations: Do not deliver or install metal storage shelving until spaces are
enclosed and weatherproof, wet work in spaces is completed and dry, and ambient
temperature is being maintained at the levels indicated for Project when occupied for its
intended use.
PART 33 PRODUCTS
33.01 WIRE CLOSET SHELVES
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. The Container Store
a. Contact: Brandon Leonard (972-538-6547)
C. Materials:
1. Furnished by the Owner.
a. Refer to the Interior Design Specification Manual for product information
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 34 ▪
END OF SECTION
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 35 ▪
PART 35 GENERAL
35.01 SUMMARY
A. Section Includes:
1. Ground Set Aluminum Flagpoles and Accessories
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-in-Place Concrete: For concrete footings for flagpoles, if
any, and if not specified in this Section.
2. Div. 26 (16) Section for Exterior Lighting
35.02 SYSTEM DESCRIPTION
A. Performance Requirements:
1. Structural Performance: Provide flagpoles capable of withstanding the effects of wind
loads as determined according to the building code in effect for this Project or NAAMM
FP 1001, "Guide Specifications for Design Loads of Metal Flagpoles," whichever is more
stringent.
2. Base flagpole design on maximum standard-size flag suitable for use with pole or flag
size indicated, whichever is more stringent.
35.03 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Product Data: For each type of flagpole required. Include installation instructions.
2. Shop Drawings: Show general layout, jointing, grounding method, and anchoring and
supporting systems. Include details of foundation system for ground-set poles.
35.04 QUALITY ASSURANCE
A. Source Limitations: Obtain each flagpole as a complete unit from a single manufacturer,
including fittings, accessories, bases, and anchorage devices.
B. Certify that pole will withstand 90 mph winds with 8' x 12' flag.
C. Design Data:
1. The engineering design of the flagpole foundation is the manufacturer’s responsibility.
Submit design analysis calculations.
2. Shop drawings and calculations shall be signed and stamped by a structural engineer
licensed in the state where project is located.
35.05 DELIVERY, STORAGE, AND HANDLING
A. General: Spiral wrap flagpoles with heavy kraft paper or other weathertight wrapping and
enclose in a hard fiber tube or other protective container.
PART 36 PRODUCTS
36.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 36 ▪
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 37 ▪
PART 37 EXECUTION
37.01 PREPARATION
A. Prepare in-ground flagpoles by painting below-grade portions with a heavy coat of bituminous
paint.
B. Excavation: For foundation, excavate to neat clean lines in undisturbed soil. Remove loose
soil and foreign matter from excavation and moisten earth before placing concrete.
C. Provide forms where required due to unstable soil conditions and for perimeter of flagpole
base at grade. Secure forms, foundation tube, fiberglass sleeve, or anchor bolts in position,
braced to prevent displacement during concreting.
D. Place concrete immediately after mixing. Compact concrete in place by using vibrators.
Moist-cure exposed concrete for not less than 7 days or use a nonstaining curing compound.
Trowel exposed concrete surfaces to a smooth, dense finish, free of trowel marks, and
uniform in texture and appearance. Provide positive slope for water runoff to base perimeter.
37.02 FLAGPOLE INSTALLATION
A. General: Install flagpoles where shown and according to Shop Drawings and manufacturer's
written instructions.
B. Foundation-Tube Installation: Install flagpole in foundation tube, seated on bottom plate
between steel centering wedges. Plumb flagpole and install hardwood wedges to secure
flagpole in place. Place and compact sand in foundation tube and remove hardwood edges.
Seal top of foundation tube with a 2" layer of elastomeric sealant and cover with flashing
collar.
END OF SECTION
Revision Log
▪ DIVISION 10 SPECIALTIES ▪
▪ PAGE 38 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Laundry and Dry Cleaning Equipment.
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry.
2. Section 10 28 00 (10800) - Toilet, Bath, and Laundry Accessories: Coordinate
equipment lists and schedules.
3. Section 12 30 00 (06400) - Architectural Woodwork.
4. Division 23 (15) - Mechanical
5. Division 26 (16) - Electrical
6. Food Service & Laundry Equipment Product Manual
1.02 SUBMITTALS
A. Submit "Letter of Conformance" in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Product Data: Mark each copy to identify applicable products, characteristics, models,
options and other supplemental data to clearly communicate information specific to this
Project.
2. Shop Drawings:
a. Indicate cabinet sizes, materials, details of construction, methods of fastening,
location of built-in appliances and erection details.
b. Indicate locations of plumbing and electrical rough-ins.
3. Samples: Submit samples of wood finish.
1.03 QUALITY ASSURANCE
A. Reference Standards: Applicable requirements of standards and specifications referenced
herein apply to the work of this Section.
B. Regulatory Requirements:
1. Conform to all applicable codes for utility requirements.
2. Products Requiring Electrical Connection: Listed and classified by UL as suitable for the
purpose specified and indicated.
3. All gas-fired equipment shall be AGA-Approved and provided with 100% safety pilot
lights. Any electric ignition devices or high-heat sensors shall be UL Listed and AGA-
Approved.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Store products clear of floor in a manner to prevent damage.
B. Coordinate size of access and route to place of installation.
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 1 ▪
PART 2 PRODUCTS
2.01 EQUIPMENT
A. Refer to Food Service & Laundry Equipment Product Manual
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify condition of existing conditions before starting work. Verify ventilation outlets, service
connections, and supports are correct and in required location. Verify that electric power is
available and of the correct characteristics.
3.02 INSTALLATION
A. Install items in accordance with manufacturers' instructions. Verify water and drains are
correct and in the required locations.
B. Insulate to prevent electrolysis between dissimilar metals.
C. Weld and grind joints in steel work tight, without open seams, where necessary due to
limitations of sheet sizes or installation requirements.
D. Sequence installation and erection to ensure correct mechanical and electrical utility
connections are achieved.
E. Cut, fit, and patch where necessary. Provide cutting and patching of items of this section
required for installation or services of equipment. Any field cutting, joining, or patching shall
be shop quality, match the surrounding material, and be fully finished and regrained.
F. Cut and drill components for service outlets, fixtures, and fittings.
G. Use anchoring devices appropriate for equipment and expected usage. Wall blocking to be
provided of a size and strength necessary to support all wall mounted equipment.
H. Provide clear silicone sealant to achieve clean joint with adjacent building finishes and
between abutting components.
3.03 ADJUSTING
A. Adjust equipment and apparatus to ensure proper working order and conditions.
B. Remove and replace equipment creating excessive noise or vibration.
3.04 CLEANING
A. Remove masking or protective covering from stainless steel and other finished surfaces.
B. Wash and clean equipment.
C. Polish glass, plastic, hardware, accessories, fixtures, and fittings.
END OF SECTION
Revision Log
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 2 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Deposit Boxes
B. Related Sections:
1. Section 05 50 00 (05500) - Metal Fabrications:
2. Section 06 10 00 (06100) - Rough Carpentry:
3. Section 12 30 00 (06400) - Architectural Woodwork:
4.02 SUBMITTALS
A. Submit "Letter of Conformance" in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Mark each copy to identify applicable products, characteristics, models, options and other
supplemental data to clearly communicate information specific to this Project.
PART 5 PRODUCTS
5.01 DEPOSIT BOXES
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Amphion, a Division of Executive Safe and Security Corporation (800-520-2677)
a. Model TPS-9LT without envelope slot
b. Model TPS-9SLT with envelope slot (Option)
2. Approved Substitution
C. Custom Sizes and Configuration:
1. Model TPS-9LT: Provide 4 Openings 5” x 5”, 2 openings 5” x 10-3/8”, 2 openings 5” x 16-
1/2” for laptop and 1 opening 10-1/8” x 10-3/8” without slotted door and anti-flush baffles.
2. Model TPS-9SLT: Provide 4 Openings 5” x 5”, 2 openings 5” x 10-3/8”, 2 openings 5” x
16-1/2” for laptop and 1 opening 10-1/8” x 10-3/8” with slotted door and anti-flush baffles.
D. Overall Dimensions: 31” H x 16-1/2” x 24”D
E. Door Face Material: Polished Aluminum with black filled numbers.
PART 3 EXECUTION
3.01 INSTALLATION
A. Install in accordance with equipment manufacturer's instructions.
B. Coordinate with approved shop drawings for millwork and Section 12 30 00 (06400) -
Architectural Woodwork.
C. Refer to Section 11 25 13.01 for cut sheet of registration equipment.
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 3 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Cooktops
a. Ceran-Glass Type
b. Glass Type
2. Range Hood
3. Ranges:
a. Glass Ceramic Top Type
4. Microwave Ovens:
a. Over the Range Mounted
b. Countertop Mounted
5. Refrigerator with Ice Maker
6. Disposals
7. Dishwashers:
a. 24 Inch Unit
b. 18 Inch Unit
8. Built-in Barbeque at Patio
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 12 30 00 (06400) - Architectural Woodwork
3. Section 10 28 00 (10800) - Toilet, Bath, and Laundry Accessories
4. Section 11 23 00 (11110) - Commercial Laundry and Dry Cleaning Equipment
5. Div. 22 (15) Sections: Plumbing Fixtures and Equipment
6. Div. 26 (16) Sections: Basic Electrical Materials and Methods
4.02 REFERENCES
A. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
B. US Environmental Protection Agency (EPA)/US Department of Energy Program:
1. ENERGY STAR Performance Rating System
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 4 ▪
PART 5 PRODUCTS
5.01 PRODUCTS
A. Products: Subject to compliance with requirements, provide one of the appliances indicated
for each designation in the Residential Appliance Schedule at the end of Part 3.
5.02 MANUFACTURERS (AS IDENTIFIED IN THE APPLIANCE SCHEDULE)
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. GE Appliances Sales (800-770-4651)
a. Contact: Lester Baldwin (800-551-5146 x 5058)
2. Broan-NuTone LLC, A Nortek Company (800-558-1711)
3. Kenyon International, Inc.
a. Contact: Suzanne Owens (860-664-4906)
4. Whirlpool Corporation
a. Contact: Adrian Nelson (800-551-5146 x 5127)
5. KitchenAid Home Appliances, a Whirlpool Brand (800-551-5146 x 5058)
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 5 ▪
PART 6 EXECUTION
6.01 EXAMINATION
A. Examine roughing-in for plumbing, mechanical, and electrical services, with Installer present,
to verify actual locations of services before residential appliance installation.
1. Proceed with installation only after unsatisfactory conditions have been corrected.
6.02 INSTALLATION
A. General: Comply with manufacturer's written instructions.
B. Built-in Equipment: Securely anchor units to supporting cabinets or countertops with
concealed fasteners. Verify that clearances are adequate for proper functioning and rough
openings are completely concealed.
C. Freestanding Equipment: Place units in final locations after finishes have been completed in
each area. Verify that clearances are adequate to properly operate equipment.
D. Utilities: Refer to Division 22 and 26 for plumbing and electrical requirements.
6.03 ADJUSTING AND CLEANING
A. Test each item of residential appliances to verify proper operation. Make necessary
adjustments.
B. Verify that accessories required have been furnished and installed.
C. Remove packing material from residential appliances and leave units in clean condition, ready
for operation.
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 6 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 7 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 8 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 9 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 10 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 11 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 12 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 13 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 14 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 15 ▪
END OF SECTION
Revision Log
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 16 ▪
PART 8 GENERAL
8.01 SUMMARY
A. Section Includes:
1. Pull Down, Folding Type, Access Ladder
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
8.02 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) with the
following supporting data:
1. Provide manufacturer's technical data and installation instructions for each item of
equipment. Provide setting drawings, templates, instructions, and directions for
installation of anchorage devices in other work.
8.03 QUALITY ASSURANCE
A. Provide products of the same manufacturer for each type of unit and for units exposed in the
same area.
8.04 DELIVERY, STORAGE, AND HANDLING
A. Do not deliver equipment to site until rooms in which they are to be installed are ready to
receive them.
B. Store packages to prevent physical damage or wetting.
C. Pack accessories individually in a manner to protect accessory and its finish.
D. Maintain protective covers on all units until final clean-up.
E. Protection:
1. Protect adjacent or adjoining finished surfaces and work from damage during installation
of work of this Section.
8.05 WARRANTEE
A. Work of this Section shall be jointly guaranteed by the manufacturer and the installer for a
period of one year after final payment. Any material or workmanship that is judged defective
during this period shall be replaced at no cost to the Owner.
PART 9 PRODUCTS
9.01 PULL DOWN ACCESS LADDER
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. "Attic Master Model No. A2512"; Werner Co. (888-523-3371)
2. Approved Substitution
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 17 ▪
PART 10 EXECUTION
10.01 PREPARATION
A. Deliver inserts and rough-in frames to job site and in appropriate time for building-in. Provide
templates and rough-in measurements as required.
B. Before starting work, notify Owner’s Representative in writing of any conflicts detrimental to
installation or operation of units.
C. Verify with Owner’s Representative exact location of units.
10.02 INSTALLATION - GENERAL
A. Install units and accessories, in accordance with manufacturer's printed instructions.
B. Use concealed fastenings wherever possible.
C. Install true, plumb, and level, securely and rigidly anchored to substrate in accordance with
manufacturer's instructions for each item and each type of substrate construction.
END OF SECTION
Revision Log
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 18 ▪
PART 11 GENERAL
11.01 SUMMARY
A. Section Includes:
1. Food Service Equipment
2. Vending Equipment
3. Buffet Shield System (Sneeze Guard)
B. Related Sections:
1. Section 01 79 00 (01820) - Training
2. Section 06 10 00 (06100) - Rough Carpentry
3. Section 10 28 00 (10800) - Toilet, Bath, and Laundry Accessories
4. Section 12 36 06 (06415) – Metal Countertops: Stainless Steel Countertops not
associated with Food Service Equipment.
5. Section 12 32 13 (06400) - Manufactured Wood-Veneer-Faced Casework
6. Section 12 32 16 (06400) - Manufactured Plastic Laminate Clad Casework
7. Division 23 (15) Sections: Plumbing Fixtures and Equipment
8. Division 26 (16) Sections: Basic Electrical Materials and Methods
9. Food Service & Laundry Equipment Product Manual
11.02 QUALITY ASSURANCE
A. Reference Standards: Applicable requirements of standards and specifications referenced
herein apply to the work of this Section.
B. Regulatory Requirements:
1. Conform to all applicable codes for utility requirements.
2. Products Requiring Electrical Connection: Listed and classified by UL as suitable for the
purpose specified and indicated.
All gas-fired equipment shall be AGA-Approved and provided with 100% safety pilot
lights. Any electric ignition devices or high-heat sensors shall be UL Listed and AGA-
Approved.
11.03 DELIVERY, STORAGE, AND HANDLING
A. Store products clear of floor in a manner to prevent damage.
B. Coordinate size of access and route to place of installation.
11.04 PROJECT CONDITIONS
A. Coordinate the work with location and placement of utilities. Coordinate characteristics of
utilities with requirements of food service equipment.
B. Schedule Work to immediately follow installation of utilities and precede installation of room
finishes. Coordinate with Owner.
C. Sequence installation to ensure utility connections are achieved in an orderly and expeditious
manner.
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 19 ▪
PART 13 EXECUTION
13.01 EXAMINATION
A. Verify condition of existing conditions before starting work. Verify ventilation outlets, service
connections, and supports are correct and in required location. Verify that electric power is
available and of the correct characteristics.
13.02 INSTALLATION
A. Install items in accordance with manufacturers' instructions. Verify water and drains are
correct and in the required locations.
B. Insulate to prevent electrolysis between dissimilar metals.
C. Weld and grind joints in steel work tight, without open seams, where necessary due to
limitations of sheet sizes or installation requirements.
D. Sequence installation and erection to ensure correct mechanical and electrical utility
connections are achieved.
E. Cut, fit, and patch where necessary. Provide cutting and patching of items of this section
required for installation or services of equipment. Any field cutting, joining, or patching shall
be shop quality, match the surrounding material, and be fully finished and regrained.
F. Cut and drill components for service outlets, fixtures, and fittings.
G. Use anchoring devices appropriate for equipment and expected usage. Wall blocking to be
provided of a size and strength necessary to support all wall mounted equipment.
H. Provide clear silicone sealant to achieve clean joint with adjacent building finishes and
between abutting components.
13.03 ADJUSTING
A. Adjust equipment and apparatus to ensure proper working order and conditions.
B. Remove and replace equipment creating excessive noise or vibration.
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 20 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 21 ▪
PART 14 GENERAL
14.01 SUMMARY
A. Section Includes:
1. Manually Operated Front Projection Screens
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 09 51 23 (09512) - Acoustical Tile Ceilings
14.02 PERFORMANCE REQUIREMENTS
A. Structural Performance: Engineer structural steel connections required by the Contract
Documents to be selected or completed by the fabricator to withstand design loadings
indicated.
B. Engineering Responsibility: Engage a fabricator who utilizes a qualified professional engineer
to prepare calculations, Shop Drawings, and other structural data for structural steel
connections.
14.03 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data:
1. Product Data: For each type of product specified.
2. Submit Shop Drawings clearly indicating screen sizes and layout, method of attachment,
accessories, trim profiles details, finish, and manufacturer's installation instructions.
14.04 QUALITY ASSURANCE
A. Single Source Responsibility: Obtain each type of projection screen required from a single
manufacturer as a complete unit, including necessary mounting hardware and accessories.
B. Coordination of Work: Coordinate layout and installation of projection screens with other
construction supported by, or penetrating through, ceilings, including light fixtures, HVAC
equipment, fire suppression system, and partitions.
14.05 DELIVERY, STORAGE, AND HANDLING
A. Do not deliver projection screens until building is enclosed, other construction within spaces
where screens will be installed are substantially complete, and installation of screens is ready
to take place.
B. Protect screens from damage during delivery, handling, storage, and installation.
PART 15 PRODUCTS
15.01 MANUAL-OPERATED WALL PROJECTION SCREEN
A. General: Provide wall or ceiling-mounted projection screen. Screen to have steel case with
flat back and baked enamel finish and fitted with power-coated steel end caps concealing
roller ends with integral bearing surface to support roller.
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 22 ▪
PART 16 EXECUTION
16.01 INSTALLATION
A. General: Install projection screens at locations indicated in compliance with screen
manufacturer's instructions.
B. Install front projection screens within ceiling alcove, with screen cases in position and
relationship to adjoining construction as indicated, securely anchored to supporting substrate,
and in manner that produces a smoothly operating screen with plumb and straight vertical
edges and plumb and flat viewing surfaces when screen is lowered.
16.02 PROTECTION AND CLEANING
A. Protect projection screens after installation from damage during construction. If, despite such
protection, damage occurs, remove and replace damaged components or entire unit as
required to provide units in their original, undamaged condition.
END OF SECTION
Revision Log
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 23 ▪
PART 17 GENERAL
17.01 SUMMARY
A. Section Includes:
1. Complete Game Court
2. Game Court Equipment
3. Game Court Light System
B. Related Sections:
1. Section 31 10 00 (02200) - Site Preparation
2. Section 31 20 00 (02300) - Earthwork
3. Section 32 13 13 (02751) - Cement Concrete Paving
4. Division 26 (16) - Electrical
17.02 SUBMITTALS
A. Submit manufacturer’s product data and shop drawings showing details of play court,
equipment, and lighting.
17.03 QUALITY ASSURANCE
A. Manufacturer's installation standards apply.
PART 18 PRODUCTS
18.01 PLAY COURT
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Connor Sport Court International, Inc. (800-421-8112)
a. Contact: Heidi Miller
2. Approved Substitution by Marriott International
C. Components:
1. Game Court Surface Colors and Configuration: Green main court area surrounded by a
red border. Refer to Drawings for approved Court size.
2. Modular Court Surface: “PowerGame” modular outdoor, all weather, non-abrasive, sport
surfacing designed for basketball, tennis, and multi-purpose use. Provide open grid
design.
a. Tiles: 12” x 12” x 5/8” high impact copolymer polypropylene suspended modules
with solid reinforced support legs, and positive locking system.
3. Include painted white and black court identification lines and 4 perimeter edge transition
lines per approved Drawings.
18.02 SYSTEM DESCRIPTION
A. Package to be "The Residence Inn Sport Court Package with PowerGame Modular Surfacing"
and shall include the following:
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 24 ▪
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 25 ▪
Revision Log
▪ DIVISION 11 EQUIPMENT ▪
▪ PAGE 26 ▪
Residence Inn Guestroom Possibilities Prefab - Wood Shaker Style (Single Panel) at
Kitchen and Dressing
Public Space Possibilities Custom Plastic Laminate /
Custom Wood Veneer (The Market)
Back-of-House Possibilities Custom Wood Veneer
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 1 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Custom Cabinet Units
a. Wood, Transparent Finish, Custom Cabinet Units
2. Cabinet Hardware
3. Decorative Glass for Guestroom Cabinets
B. Related Sections:
1. Section 06 61 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 08 80 00 (08800) – Glazing
4. Section 12 32 16 (06400) – Manufactured Plastic Laminate Clad Casework
5. Section 12 35 30.13 (06400) – Kitchen Casework
6. Section 12 36 23 (09415) - Plastic Countertops
7. Section 12 36 40 (09380) - Stone Countertops
8. Section 12 36 61 (09835) – Simulated Stone Countertops
9. Section 12 36 61.13 (06620) – Cultured Marble Countertops
10. Section 12 36 61.16 (06620) – Solid Surfacing Countertops
11. Division 22 (15) for Plumbing Fixtures
1.02 REFERENCES
A. Architectural Woodwork Institute (AWI) / Architectural Woodwork Manufacturers Association of
Canada (AWMAC) /Woodwork Institute (WI) Publications:
1. "Architectural Woodwork Standards (AWS)"
B. ASTM International (ASTM) Publications:
1. C1048 “Standard Specification for Heat-Treated Flat Glass—Kind HS, Kind FT Coated
and Uncoated Glass”
2. D523 “Standard Test Method for Specular Gloss”
3. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
C. American National Standards Institute (ANSI) Publications:
1. A135.4 Basic Hardboard
2. ANSI/KCMA A161.1 “Performance and Construction Standard for Kitchen and Vanity
Cabinets
3. A161.2 “Standards for Fabricated High Pressure Decorative Laminate Countertops”
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 2 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 3 ▪
PART 2 PRODUCTS
2.01 APPROVED MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. MillRock RiverRun Casework (540-438-5973)
2. R.B. Woodcraft, Inc. (315-474-2429)
3. J. Suss Industries Inc. (866-769-5666)
2.02 WOOD, TRANSPARENT FINISH CUSTOM BOX CABINET UNITS - GENERAL
A. Quality Standard:
1. Perform work to meet the requirements of Custom Grade in accordance with the
"Architectural Woodwork Standards (AWS)", unless noted otherwise manufactured from
solid stock meeting the following requirements:
a. Minor warp which can be held flat and straight with normal nailing.
b. Natural and manufacturing defects in excess of those permitted in the grade
specified are permitted if such defects are to be covered by adjoining members or
otherwise concealed.
c. Trim members for application on flat surfaces shall have the reverse side "backed
out", except members with exposed ends.
d. "Custom grade" pieces shall be smoothly machined with top flat surfaces machine
sanded. Depressed flat surfaces and molded contours shall be smoothly machined.
B. Design:
1. Style of face construction for base, wall, and full-height units, if any, with drawer fronts,
doors, and fixed panels as follows:
a. Face Frame or Frameless.
1) All cabinets shall be the same construction type for the entire Project.
b. Cabinet and Door Interface: Flush (Full) Overlay.
c. Flush Panel Doors.
d. Flush Panel Drawer Fronts.
e. Color: Refer to Interior Finish Index
2. Grain Direction:
a. Vertical on doors, horizontal on drawer fronts.
b. Lengthwise on face frame members.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 4 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 5 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 6 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 7 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 8 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 9 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 10 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 11 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 12 ▪
PART 3 EXECUTION
3.01 INSPECTION
A. Verify adequacy of backing and support framing.
3.02 INSTALLATION
A. All cabinets and shelving shall be installed as shown on Drawings and as specified by
manufacturer.
B. Set and secure casework in place rigid, plumb, and level.
C. Cabinets: Install without distortion so doors and drawers fit openings properly and are
accurately aligned. Adjust hardware to center doors and drawers in openings and to provide
unencumbered operation. Complete installation of hardware and accessory items as
indicated.
1. Secure cabinet and counter bases to floor using appropriate angles and anchorages.
2. Install cabinets with no more than 1/8 inch in 96-inch sag, bow, or other variation from a
straight line.
3. Maintain veneer sequence matching of cabinets with transparent finish.
4. Carefully scribe casework which is against other building materials, leaving gaps of 1/32
inch maximum. Do not use additional overly trim for this purpose.
5. Carefully fit equipment to be installed into millwork. Provide filler pieces when required.
D. Fasteners:
1. Use purpose designed fixture attachments at concealed locations for wall-mounted
components.
2. Use threaded steel concealed joint fasteners to align and secure adjoining cabinet units
and counter tops.
3. Countersink anchorage devices at exposed locations used to wall-mount components,
and conceal with solid plugs of species to match surrounding wood. Finish flush with
surrounding surfaces.
4. Install countertops with no more than 1/8 inch in 96-inch sag, bow, or other variation from
a straight line.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 13 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Custom Cabinet Units
a. Plastic Laminate Clad Custom Cabinet Units
2. Cabinet Hardware
B. Related Sections:
1. Section 06 61 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 12 32 13 (06400) – Manufactured Wood-Veneer-Faced Casework
4. Section 12 35 30.13 (06400) – Kitchen Casework
5. Section 12 36 23 (09415) - Plastic Countertops
6. Section 12 36 40 (09380) - Stone Countertops
7. Section 12 36 61 (09835) – Simulated Stone Countertops
8. Section 12 36 61.13 (06620) – Cultured Marble Countertops
9. Section 12 36 61.16 (06620) – Solid Surfacing Countertops
10. Division 22 (15) for Plumbing Fixtures
4.02 REFERENCES
A. Architectural Woodwork Institute (AWI) / Architectural Woodwork Manufacturers Association of
Canada (AWMAC) /Woodwork Institute (WI) Publications:
1. "Architectural Woodwork Standards (AWS)"
B. ASTM International (ASTM) Publications:
1. C1048 “Standard Specification for Heat-Treated Flat Glass—Kind HS, Kind FT Coated
and Uncoated Glass”
2. D523 “Standard Test Method for Specular Gloss”
3. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
C. American National Standards Institute (ANSI) Publications:
1. A135.4 Basic Hardboard
2. ANSI/KCMA A161.1 “Performance and Construction Standard for Kitchen and Vanity
Cabinets
3. A161.2 “Standards for Fabricated High Pressure Decorative Laminate Countertops”
4. A208.1 "Standards for the Performance of Particleboard"
D. Federal Specifications (FS) Publications:
1. FS MM-L-736 - Lumber, Hardwood
2. FS MMM-A-130 - Adhesive, Contact
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 14 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 15 ▪
PART 5 PRODUCTS
5.01 APPROVED MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. MillRock RiverRun Casework (540-438-5973)
2. R.B. Woodcraft, Inc. (315-474-2429)
3. J. Suss Industries Inc. (866-769-5666)
5.02 PLASTIC LAMINATE CUSTOM BOX CABINET UNITS
A. Quality Standard:
1. Perform work to meet the requirements of Custom Grade in accordance with the
"Architectural Woodwork Standards (AWS)", unless noted otherwise manufactured from
solid stock meeting the following requirements:.
a. Minor warp which can be held flat and straight with normal nailing.
b. Natural and manufacturing defects in excess of those permitted in the grade
specified are permitted if such defects are to be covered by adjoining members or
otherwise concealed.
c. Trim members for application on flat surfaces shall have the reverse side "backed
out", except members with exposed ends.
B. Design:
1. Style of face construction for base, wall, and full-height units, if any, with drawer fronts,
doors, and fixed panels as follows:
a. Face Frame or Frameless.
1) All cabinets shall be the same construction type for the entire Project.
b. Flush Panel Doors.
c. Flush Panel Drawer Fronts.
2. Grain Direction:
a. Vertical on doors, horizontal on drawer fronts.
b. Lengthwise on face frame members.
c. Vertical on end panels.
d. Side to side on bottoms and tops of units.
e. Vertical on knee-space panels.
f. Horizontal on aprons.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 16 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 17 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 18 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 19 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 20 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 21 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 22 ▪
Note 1: At drawer slides for large drawers, verify potential loading and adjust slide type to
accommodate loads. For drawers over 16” wide and less than 24” wide use Accuride
7432. For applications wider than 24” use Accuride 3640.
Note 2: All locks in the same component to be on the same key, (i.e. All locks in the market t and
bar shall be on same key.) unless noted otherwise.
Other millwork items on the hotel property with locks shall be keyed separately.
Ensure master key is different at each hotel in the system.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 23 ▪
Note 1: At drawer slides for large drawers, verify potential loading and adjust slide type to
accommodate loads. For drawers over 16” wide and less than 24” wide use Accuride
7432. For applications wider than 24” use Accuride 3640.
Note 2: All locks in the same component to be on the same key, (i.e. All locks in the market t and
bar shall be on same key.) unless noted otherwise.
Other millwork items on the hotel property with locks shall be keyed separately.
Ensure master key is different at each hotel in the system.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 24 ▪
Note 1: At drawer slides for large drawers, verify potential loading and adjust slide type to
accommodate loads. For drawers over 16” wide and less than 24” wide use Accuride
7432. For applications wider than 24” use Accuride 3640.
Note 2: All locks in the same component to be on the same key, (i.e. All locks in the market t and
bar shall be on same key.) unless noted otherwise.
Other millwork items on the hotel property with locks shall be keyed separately.
Ensure master key is different at each hotel in the system.
Note 1: At drawer slides for large drawers, verify potential loading and adjust slide type to
accommodate loads. For drawers over 16” wide and less than 24” wide use Accuride
7432. For applications wider than 24” use Accuride 3640.
Note 2: All locks in the same component to be on the same key, (i.e. All locks in the market t and
bar shall be on same key.) unless noted otherwise.
Other millwork items on the hotel property with locks shall be keyed separately.
Ensure master key is different at each hotel in the system.
J. Cabinet Hardware Schedule:
ITEM MODEL NO. MANUFACTURER
GUESTROOM
Kitchen (Refer to Section
12 35 30.13)
Bath: Vanity Drawer Pulls 8233-96 x Brushed Nickel J.G. Edelen
Bath: Vanity Towel Bar 8233-256 x Brushed Nickel J.G. Edelen
EMPLOYEE LOUNGE
Kitchen: Cabinet Door Pulls 3490-1-3/4 in. x Brushed Edelen
Nickel – Mount Verticlly
WELCOME DESK
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 25 ▪
Note 1: At drawer slides for large drawers, verify potential loading and adjust slide type to
accommodate loads. For drawers over 16” wide and less than 24” wide use Accuride
7432. For applications wider than 24” use Accuride 3640.
Note 2: All locks in the same component to be on the same key, (i.e. All locks in the market t and
bar shall be on same key.) unless noted otherwise.
Other millwork items on the hotel property with locks shall be keyed separately.
Ensure master key is different at each hotel in the system.
K. Exposed Wall Shelving: “No. 80 x No. 182”; Knape & Vogt Manufacturing Co.; inset type,
adjustable on 1" centers.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 26 ▪
PART 6 EXECUTION
6.01 INSPECTION
A. Verify adequacy of backing and support framing.
6.02 INSTALLATION
A. All cabinets and shelving shall be installed as shown on Drawings and as specified by
manufacturer.
B. Set and secure casework in place rigid, plumb, and level.
C. Cabinets: Install without distortion so doors and drawers fit openings properly and are
accurately aligned. Adjust hardware to center doors and drawers in openings and to provide
unencumbered operation. Complete installation of hardware and accessory items as
indicated.
1. Secure cabinet and counter bases to floor using appropriate angles and anchorages.
2. Install cabinets with no more than 1/8 inch in 96-inch sag, bow, or other variation from a
straight line.
3. Maintain veneer sequence matching of cabinets with transparent finish.
4. Carefully scribe casework which is against other building materials, leaving gaps of 1/32
inch maximum. Do not use additional overly trim for this purpose.
5. Carefully fit equipment to be installed into millwork. Provide filler pieces when required.
D. Fasteners:
1. Use purpose designed fixture attachments at concealed locations for wall-mounted
components.
2. Use threaded steel concealed joint fasteners to align and secure adjoining cabinet units
and counter tops.
3. Countersink anchorage devices at exposed locations used to wall-mount components,
and conceal with solid plugs of species to match surrounding wood. Finish flush with
surrounding surfaces.
4. Install countertops with no more than 1/8 inch in 96-inch sag, bow, or other variation from
a straight line.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 27 ▪
END OF SECTION
Revision Log
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 28 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Cabinet Units
a. Wood Premanufactured Cabinets
1) Location: Guestroom Kitchen
2) Location: Guestroom Dressing Area
3) Location: Employee Lounge
2. Decorative Glass for Guestroom Cabinets
3. Cabinet Hardware
B. Related Sections:
1. Section 06 61 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 06 61 13 (06610) - Cultured Marble Fabrications
4. Section 08 80 00 (08800) – Glazing
5. Section 12 32 13 (06400) – Manufactured Wood-Veneer-Faced Casework
6. Section 12 32 16 (06400) – Manufactured Plastic Laminate Clad Casework
7. Section 12 36 23 (09415) - Plastic Countertops
8. Section 12 36 40 (09380) - Stone Countertops
9. Section 12 36 61 (09835) – Simulated Stone Countertops
10. Section 12 36 61.13 (06620) – Cultured Marble Countertops
11. Section 12 36 61.16 (06620) – Solid Surfacing Countertops
12. Division 22 (15) for Plumbing Fixtures
7.02 REFERENCES
A. Architectural Woodwork Institute (AWI) / Architectural Woodwork Manufacturers Association of
Canada (AWMAC) /Woodwork Institute (WI) Publications:
1. "Architectural Woodwork Standards (AWS)"
B. ASTM International (ASTM) Publications:
1. C1048 “Standard Specification for Heat-Treated Flat Glass—Kind HS, Kind FT Coated
and Uncoated Glass”
2. D523 “Standard Test Method for Specular Gloss”
3. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
C. American National Standards Institute (ANSI) Publications:
1. A135.4 Basic Hardboard
2. A161.2 “Standards for Fabricated High Pressure Decorative Laminate Countertops”
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 29 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 30 ▪
PART 8 PRODUCTS
8.01 APPROVED MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. MillRock RiverRun Casework (540-438-5973)
a. Residence Inn Gen 9 Possibilities Décor Package: “Possibilities Shaker Style”
[Frameless] Construction.
2. J Suss Industries (866-769-5666)
a. Residence Inn Gen 9 Possibilities Décor Package: “EuroPossibilities Style”
Framelesss Construction.
8.02 ABINET UNITS - GENERAL
A. Quality Standard:
1. Provide cabinets that comply with KCMA A161.1, unless noted otherwise manufactured
meeting the following requirements:
a. Minor warp which can be held flat and straight with normal nailing.
b. Natural and manufacturing defects in excess of those permitted in the grade
specified are permitted if such defects are to be covered by adjoining members or
otherwise concealed.
c. Trim members for application on flat surfaces shall have the reverse side "backed
out", except members with exposed ends.
B. Design:
1. Style of face construction for base, wall, and full-height units, if any, with drawer fronts,
doors, and fixed panels as follows:
a. Face Frame or Frameless.
1) All cabinets shall be the same construction type for the entire Project.
b. Cabinet and Door Interface: Flush (Full) Overlay.
c. Single Fixed Panel Doors.
d. Flush Panel Drawer Fronts.
e. Interior Finish: Classic Maple Thermoset Decorative Overlay (Melamine)
2. Grain Direction:
a. Vertical on doors, horizontal on drawer fronts.
b. Lengthwise on face frame members.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 31 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 32 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 33 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 34 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 35 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 36 ▪
PART 9 EXECUTION
9.01 INSPECTION
A. Verify adequacy of backing and support framing.
9.02 INSTALLATION
A. All cabinets and shelving shall be installed as shown on Drawings and as specified by
manufacturer.
B. Set and secure casework in place rigid, plumb, and level.
C. Cabinets: Install without distortion so doors and drawers fit openings properly and are
accurately aligned. Adjust hardware to center doors and drawers in openings and to provide
unencumbered operation. Complete installation of hardware and accessory items as
indicated.
1. Secure cabinet and counter bases to floor using appropriate angles and anchorages.
2. Install cabinets with no more than 1/8 inch in 96-inch sag, bow, or other variation from a
straight line.
3. Maintain veneer sequence matching of cabinets with transparent finish.
4. Carefully scribe casework which is against other building materials, leaving gaps of 1/32
inch maximum. Do not use additional overly trim for this purpose.
5. Carefully fit equipment to be installed into millwork. Provide filler pieces when required.
6. Provide cutouts for plumbing fixtures, inserts, appliances, outlet boxes, and other fixtures
and fittings.
D. Fasteners:
1. Use purpose designed fixture attachments at concealed locations for wall-mounted
components.
2. Use threaded steel concealed joint fasteners to align and secure adjoining cabinet units
and counter tops.
3. Countersink anchorage devices at exposed locations used to wall-mount components,
and conceal with solid plugs of species to match surrounding wood. Finish flush with
surrounding surfaces.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 37 ▪
END OF SECTION
Revision Log
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 38 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Metal Laminated to Wood Core
a. Countertops and Backsplashes
b. Aprons
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 06 61 13 (06610) – Cultured Marble Fabrications
4. Section 11 40 00 (11400) – Food Service Equipment: For all Countertops related to
Food Service Equipment
5. Section 11 31 00 (11450) – Residential Appliances
6. Section 12 30 00 (06400) - Architectural Woodwork
7. Section 12 36 23 (06415) – Plastic Countertops
8. Section 12 36 40 (09380) - Stone Countertops
9. Section 12 36 61 (09385) - Engineered Stone Countertops
10. Section 12 36 61.13 (09385) – Cultured Marble Countertops
11. Division 23 (15) Sections: Plumbing Fixtures and Equipment
12. Division 26 (16) Sections: Basic Electrical Materials and Methods
10.02 REFERENCES
A. Code of Federal Regulations (CFR) Publications:
1. 40 CFR, Part 59, Subpart D 2001, "National Volatile Organic Compound Emission
Standards for Architectural Coatings"
B. American National Standards Institute (ANSI) Publications:
1. A208.1 Mat-Formed Wood Particleboard
C. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A240/A 240M “Standard Specification for Chromium and Chromium-Nickel Stainless
Steel Plate, Sheet, and Strip for Pressure Vessels and for General Applications”
2. A666 “Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel
Sheet, Strip, Plate, and Flat Bar”
3. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
D. Architectural Woodwork Institute (AWI) Publications:
1. "Architectural Woodwork Quality Standards"
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 39 ▪
PART 11 PRODUCTS
11.01 MATERIALS
A. Stainless-Steel Sheet: ASTM A240/A240M or ASTM A666, Type 304, stretcher-leveled
standard of flatness, minimum 0.050-inch thick (18 gauge).
B. Filler Materials and Electrodes: Provide type and alloy of filler metal and electrodes as
recommended by producer of metal to be welded or brazed and as necessary for strength,
corrosion resistance, and compatibility in fabricated items.
1. Use filler metals that will match the color of metal being joined and will not cause
discoloration.
C. Particleboard Core:
1. ANSI A208.1, Grade M-2.
D. Fire-Retardant Core:
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 40 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 41 ▪
PART 12 EXECUTION
12.01 INSPECTION
A. Verify adequacy of backing and support framing.
12.02 INSTALLATION
A. All countertops and shelving shall be installed as shown on Drawings and as specified by
manufacturer.
B. Set and secure countertops in place rigid, plumb, and level.
C. Anchor securely by screwing through corner blocks of base cabinets or other supports into
underside of countertop.
D. Fasteners:
1. Use purpose designed fixture attachments at concealed locations for wall-mounted
components.
2. Use threaded steel concealed joint fasteners to align and secure adjoining counter tops.
3. Install countertops with no more than 1/8 inch in 96-inch sag, bow, or other variation from
a straight line.
12.03 ADJUSTING AND CLEANING
A. Verify that installed countertops are free from surface blemishes, and scratches, that metal
surfaces remain fully bonded to supporting substrates, and that supporting substrates are not
damaged from handling, installation, or exposure to excessive amounts of moisture. Perform
minor repairs and touch-up damaged finishes that can be adequately performed in the field.
Return damaged metal countertops to fabricator for repair or replacement if damaged product
cannot be repaired to a like new and undamaged condition in the field.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 42 ▪
Revision Log
END OF SECTION
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 43 ▪
PART 13 GENERAL
13.01 SUMMARY
A. Section Includes:
1. Plastic Laminate
a. Countertops and Backsplashes
b. Aprons
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 06 61 13 (06610) – Cultured Marble Fabrications
4. Section 12 30 00 (06400) - Architectural Woodwork
5. Section 12 36 40 (09380) - Stone Countertops
6. Section 12 36 61 (09385) - Engineered Stone Countertops
7. Section 12 36 61.13 (09385) – Cultured Marble Countertops
13.02 REFERENCES
A. American National Standards Institute (ANSI) Publications:
1. A161.2 “Performance Standards for Fabricated High Pressure Decorative Laminate
Countertops”
2. A208.1 “Particleboard”
B. ASTM International (ASTM) Publications:
1. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
C. Federal Specifications (FS) Publications:
1. MM-L-736 “Lumber, Hardwood”
2. MMM-A-130 “Adhesive, Contact”
D. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. LD3 “High Pressure Decorative Laminates”
E. National Institute of Standards and Technology (NIST)
1. PS 1 “Construction and Industrial Plywood”
2. PS 20 “American Softwood Lumber Standard”
3. PS 51 “Hardwood and Decorative Plywood”
4. PS 58 “Basic Hardboard”
13.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 44 ▪
PART 14 PRODUCTS
14.01 MATERIALS:
A. Plastic Laminate: Shall be standard grade, 1/16" thick, general purpose material complying
with current NEMA LD-3 Grade HGS for flat countertops [and HGP for postformed]. Comply
with ANSI A161.2. Pattern and color shown in [Interior Finish Index].
1. Approved Manufacturers:
a. Lamin-Art (800-323-7624)
b. Nevamar Company, LLC (800-638-4380)
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 45 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 46 ▪
PART 15 EXECUTION
15.01 INSPECTION
A. Verify adequacy of backing and support framing.
15.02 INSTALLATION
A. All countertops and shelving shall be installed as shown on Drawings and as specified by
manufacturer.
B. Set and secure countertops in place rigid, plumb, and level.
C. Anchor securely by screwing through corner blocks of base cabinets or other supports into
underside of countertop.
D. Fasteners:
1. Use purpose designed fixture attachments at concealed locations for wall-mounted
components.
2. Use threaded steel concealed joint fasteners to align and secure adjoining counter tops.
3. Install countertops with no more than 1/8 inch in 96-inch sag, bow, or other variation from
a straight line.
15.03 PLASTIC LAMINATE
A. Installation:
1. The plastic laminate shall be bonded to a suitable substrate. Rigid setting type adhesive
is recommended. The temperature of the materials, surfacing, substrate, and adhesive,
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 47 ▪
END OF SECTION
Revision Log
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 48 ▪
PART 16 GENERAL
16.01 SUMMARY
A. Section Includes:
1. Interior Granite
a. Vanity Tops
b. Countertops
c. Backsplashes
d. Aprons
e. Tub Seat
f. Whirlpool Built-In Tops
g. Casework Faces (Vertical)
h. Credenza Tops
i. Accent / Border Tile
j. Wall Base
k. Sills
l. Thresholds
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 07 92 00 (07920) - Joint Sealants
4. Section 09 30 00 (09310) - Tiling
5. Section 12 32 13 (06400) - Manufactured Wood-Veneer-Faced Casework
6. Section 12 32 16 (06400) - Manufactured Plastic Laminate Clad Casework
7. Section 12 36 23 (06415) – Plastic Countertops
8. Section 12 36 61 (09385) - Simulated Stone Countertops
9. Section 12 36 61.13 (09385) – Cultured Marble Countertops
10. Division 22 (15) for Plumbing Fixtures
16.02 REFERENCES
A. ASTM International (ASTM) Publications:
1. C503 “Standard Specification for Marble Dimension Stone (Exterior)”
2. C615 “Standard Specification for Granite Dimension Stone”
B. American National Standards Institute (ANSI) Publications.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 49 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 50 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 51 ▪
PART 17 PRODUCTS
17.01 MATERIALS, GENERAL
A. Comply with referenced standards and other requirements indicated applicable to each type of
material required.
B. Provide matched slabs, coordinated for each type, variety, color, and quality of stone required.
C. The use of colored tints, dyes, or waxes applied to stone shall NOT be permitted
17.02 GRANITE
A. Granite Building Stone Standard: ASTM C615, free from cracks, chips, stains, or other
defects, uniform in tone and coloring.
B. Manufacturers:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Marriott Stone Supplier Program Manufacturers:
a. Granite Tech, Inc. (610-274-1494)
1) Contact: Bill Skalish (610-274-1494)
b. Belstone, a ProjectStone Company (877-667-8663)
1) Contact: Scott Smith (818-373-4900)
2) Contact: Jacqui Ford (240-423-2296)
c. J.G. Edelen Company, Inc. (410-918-1200)
1) Contact: Dino Arcuri (570-650-0196)
2) Contact: Kelly Smith (410-918-1200)
d. MeridienStone (866-342-0001)
1) Contact: Drew Murray (706-837-0008)
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 52 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 53 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 54 ▪
PART 18 EXECUTION
18.01 EXAMINATION
A. Examine surfaces to receive stone materials, and conditions under which stonework will be
installed, with installer present, for compliance with requirements for installation tolerances
and other conditions affecting performance of stonework. Do not proceed with installation until
unsatisfactory conditions have been corrected.
B. Verify adequacy of backing and support framing.
18.02 PREPARATION
A. Advise installers of other work about specific requirements relating to placement of inserts,
flashing reglets, and similar items to be used by stonework installer for anchoring, supporting,
and flashing of dimension stonework. Furnish installers of other work with Drawings or
templates showing locations of these items.
B. Clean stone surfaces that have become dirty or stained prior to setting to remove soil, stains,
and foreign materials. Clean stones by thoroughly scrubbing stones with fiber brushes
followed by clear water. Use only mild cleaning compounds that contain no caustic or harsh
filler or abrasives. Allow stone to dry before installing.
18.03 INSTALLATION - COUNTERTOPS
A. General: Install countertops, except for vanities, over plywood subtops with a full spread of
water-cleanable epoxy adhesive.
B. Install components plumb, level and rigid, scribed to adjacent finishes, in accordance with
approved shop drawings and product data.
1. Tops:
a. Flat and true to within 1/8" of a flat surface over a 10' length.
b. Allow a minimum of 1/16" to a maximum of 1/8" clearance between surface and
each wall.
C. Fit countertops around projections and to adjacent construction. Smooth and clean field cut
edges. Ensure that trim will completely cover cut edges.
D. Bond seams with stone seam adhesive and draw tight as countertops are set. Mask areas of
countertops adjacent to seams to prevent adhesive smears. Use clamps to ensure countertop
units are properly aligned and seams are minimum width.
E. Complete cutouts not finished in shop. Mask areas of countertops adjacent to cutouts while
cutting to prevent damage.
F. Install backsplash and end splash by adhering to wall with water-cleanable epoxy adhesive.
Leave 1/16-inch gap between countertop and splash for filling with sealant. Use temporary
shims to ensure uniform spacing.
G. Apply sealant to seams and to gap between countertops and splashes; comply with Section
07 92 00 (07920) "Joint Sealants."
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 55 ▪
END OF SECTION
Revision Log
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 56 ▪
PART 19 GENERAL
19.01 SUMMARY
A. Section Includes:
1. Cast Polymer
a. Window Stools (Interior Sills)
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 06 61 13 (06610) – Cultured Marble Fabrications
4. Section 12 30 00 (06400) - Architectural Woodwork
5. Section 12 36 23 (06415) – Plastic Countertops
6. Section 12 36 40 (09380) - Stone Countertops
7. Section 12 36 61 (09385) - Engineered Stone Countertops
19.02 REFERENCES
A. Federal Specifications (FS) Publications:
1. FS MMM-A-130 - Adhesive, Contact
B. Architectural Woodwork Institute (AWI) Publications:
1. "Architectural Woodwork Quality Standards"
C. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
19.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Submit Shop Drawings and product data. Include materials, component profiles,
fastening methods, assembly methods, joint details, accessory listings, and schedule of
finishes.
a. Include data for fire-retardant treatment from chemical treatment manufacturer and
certification by treating plant that treated materials comply with requirements.
19.04 QUALITY ASSURANCE
A. Tub/Shower surrounds, window stools and lavatory/vanity countertops shall be supplied by
one manufacturer. Where shown to be the same color, the color of the components shall
match for all items. Refer to Interior Finish Index for colors.
B. Allowable Tolerances:
1. Variation in component size: +/- 1/8 inch.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 57 ▪
PART 20 PRODUCTS
20.01 CAST POLYMER:
A. Manufacturers:
1. Avendra, LLC Preferred Manufacturers:
a. Window Stools:
1) None.
2. Approved Manufacturers:
a. Window Stools:
1) Mincey Marble Manufacturing Co. (800-533-1806)
2) MPL Corporation (317-835-9000)
B. Fire Hazard Ratings:
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 58 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 59 ▪
END OF SECTION
Revision Log
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 60 ▪
PART 22 GENERAL
22.01 SUMMARY
A. Section Includes:
1. Engineered Stone
a. Vanity Tops
b. Countertops
c. Backsplashes
d. Aprons
e. Tub Seat
f. Whirlpool Built-In Tops
g. Casework Faces (Vertical)
h. Credenza Tops
i. Accent / Border Tile
j. Wall Base
k. Sills
l. Thresholds
B. Engineered Glass
a. Countertops
b. Backsplashes
C. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry
2. Section 06 20 00 (06200) - Finish Carpentry
3. Section 07 92 00 (07920) - Joint Sealants
4. Section 09 30 00 (09310) - Tiling
5. Section 12 32 13 (06400) - Manufactured Wood-Veneer-Faced Casework
6. Section 12 32 16 (06400) - Manufactured Plastic Laminate Clad Casework
7. Section 12 36 23 (06415) – Plastic Countertops
8. Section 12 36 40 (09380) - Stone Countertops
9. Section 12 36 61.13 (09385) – Cultured Marble Countertops
10. Division 22 (15) for Plumbing Fixtures
22.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. C97 - Test Method for Absorption and Bulk Specific Gravity of Dimensional Stone.
2. C99 - Test Method for Modulus of Rupture of Dimension Stone.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 61 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 62 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 63 ▪
PART 23 PRODUCTS
23.01 ENGINEERED STONE MATERIALS:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Marriott Stone Supplier Program Manufacturers:
a. Granite Tech, Inc. (610-274-1494)
1) Contact: Bill Skalish (610-274-1494)
2) NSF/ANSI 51 Certification: No
b. Belstone(877-667-8663)
1) Product: “ecoQUARTZ”
2) Contact: Scott Smith (818-373-4900)
3) Contact: Jacqui Ford (240-423-2296)
4) NSF/ANSI 51 Certification: Yes
c. J.G. Edelen Company, Inc. (410-918-1200)
1) Contact: Dino Arcuri (570-650-0196)
2) Contact: Kelly Smith (410-918-1200)
3) NSF/ANSI 51 Certification: No
d. MeridienStone (866-342-0001)
1) Contact: Drew Murray (706-837-0008)
2) NSF/ANSI 51 Certification: No
3. Approved Manufacturers:
a. None
23.02 ENGINEERED GLASS MATERIALS:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Marriott Stone Supplier Program Manufacturers:
a. Granite Tech, Inc. (610-274-1494)
1) Product: “Milk Glass”
2) Contact: Bill Skalish (610-274-1494)
3) NSF/ANSI 51 Certification: No
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 64 ▪
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 65 ▪
PART 24 EXECUTION
24.01 EXAMINATION
A. Examine surfaces to receive simulated stone materials, and conditions under which work will
be installed, with installer present, for compliance with requirements for installation tolerances
and other conditions affecting performance of work. Do not proceed with installation until
unsatisfactory conditions have been corrected.
B. Verify adequacy of backing and support framing.
24.02 PREPARATION
A. Condition engineered stone to average prevailing humidity conditions in installation areas
before installation.
24.03 INSTALLATION - COUNTERTOPS
A. All countertops and other locations, shall be installed as shown on Drawings and as specified
by manufacturer.
B. Install components plumb, level and rigid, scribed to adjacent finishes, in accordance with
approved shop drawings and product data.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 66 ▪
END OF SECTION
Revision Log
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 67 ▪
PART 25 GENERAL
25.01 SUMMARY
A. Section Includes:
1. The complete installation of all furniture and fixtures which are furnished by Owner.
B. Related Sections:
1. Section 06 10 00 (06100) - Rough Carpentry: Blocking for wall mounted furniture and
fixtures.
25.02 QUALITY ASSURANCE
A. Qualified installer shall have experience in installation methods similar to work of this section.
25.03 DELIVERY, STORAGE AND HANDLING
A. The Contractor shall receive and store all items furnished by Owner.
B. The storage area shall be secure and dry with temperatures maintained above 40 degrees F.
at all times.
C. For each delivery, the Contractor shall fill out receiving reports. Each delivery shall be
inspected for damage. All damage shall be noted on the carriers delivery slip as well as the
receiving report. Receiving reports and carriers delivery slips shall be forwarded to the Owner
immediately upon receipt of delivery. If damaged material is not reported when discovered,
the Contractor assumes full responsibility.
PART 26 PRODUCTS
26.01 MATERIALS
A. Headboard Mounting Items:
1. 2 ea 3" x 3/16" toggle bolts.
2. Silicone adhesive.
3. Lead shields (concrete walls only).
4. 2 ea 2" #10 pan head screws for each cleat.
B. Box Spring and Bed Frame Mounting Items:
1. 4 ea #10 x 3/4" pan headed screws.
C. Artwork and Framed Mirror Mounting Items:
1. 2 ea 1/8" x 3" toggle bolts for each item.
2. Lead shields (concrete walls only)
3. 2 each 2" #10 pan head screws (concrete walls only).
PART 27 EXECUTION
27.01 INSTALLATION
A. Contractor shall exercise care when installing items so as not to damage or soil adjacent
areas and surface.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 68 ▪
END OF SECTION
Revision Log
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 69 ▪
PART 28 GENERAL
28.01 SUMMARY
A. Section includes:
1. Bicycle Racks
B. Related Sections include the following:
1. Section 03 30 00 (03300) - Cast-in-Place Concrete
28.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A36 “Standard Specification for Carbon Structural Steel”
2. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and Seamless"
3. A135 “Standard Specification for Electric-Resistance-Welded Steel Pipe”
4. A500 "Standard Specification for Cold-Formed Welded and Seamless Carbon Steel
Structural Tubing in Rounds and Shapes"
5. A513 Standard Specification for Electric-Resistance-Welded Carbon and Alloy Steel
Mechanical Tubing
6. A1011 "Standard Specification for Steel Sheet and Strip, Hot-Rolled, Carbon, Structural,
High-Strength Low-Alloy and High-Strength Low-Alloy with Improved Formability"
B. National Association of Architectural Metal Manufacturers (NAAMM) Publications:
1. "Metal Finishes Manual for Architectural and Metal Products"
28.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
1. Product Data: For each type of product indicated.
2. Samples for Verification: For each type of exposed finish required, prepared on Samples
of size indicated below.
a. Size: Not less than 6-inch long linear components.
3. Material Certificates: For site furnishings, signed by manufacturers.
4. Maintenance Data: For site furnishings to include in maintenance manuals.
B. LEED Submittals:
1. Credit MRc4.1 and 4.2: Recycled Content:
a. List of proposed materials with recycled content.
b. Product Data or other documentation for each product/material highlighting recycled
content information.
c. Complete the LEED Materials Submittal Form as provided in Section 01 33 00
“Submittal and Substitution Procedures, for products in this Section.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 70 ▪
PART 29 PRODUCTS
29.01 MATERIALS
A. Steel and Iron: Free of surface blemishes and complying with the following:
1. Plates, Shapes, and Bars: ASTM A36/A 36M.
2. Steel Pipe: Standard-weight steel pipe complying with ASTM A53, or electric-resistance-
welded pipe complying with ASTM A135.
3. Tubing: Cold-formed steel tubing complying with ASTM A500.
4. Mechanical Tubing: Cold-rolled, electric-resistance-welded carbon or alloy steel tubing
complying with ASTM A513, or steel tubing fabricated from steel complying with
ASTM A1011 and complying with dimensional tolerances in ASTM A500; zinc coated
internally and externally.
5. Sheet: Commercial steel sheet complying with ASTM A1011.
B. Plastic: Color impregnated, color and UV-light stabilized, and mold resistant.
1. Recycled Polyethylene: Fabricated from not less than 97 percent recycled, purified,
fractional-melt plastic resin with not less than 73 percent recycled postconsumer waste
by weight HDPE.
2. Anchors, Fasteners, Fittings, and Hardware: Installer to provide Anchors per
manufacturer’s recommendations.
29.02 BICYCLE RACKS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. “Multi-Loop Bike Rack, Model #WA2-07-SM-MF”; BRP Enterprises, Inc. (888-438-5311)
2. “RB-07”; AAA Ribbon Rack Co., Division of Brandir Interanational, Inc. (800-849-3488)
3. “BRCS-107”; Secure Site Design LLC, an affiliate of Victor Stanley, Inc. (800-368-2573)
C. Bicycle Rack Construction:
1. Frame:
a. [7] Bicycles
b. Dimensions: 3”d x 40”h x 60”
c. Material: Steel
d. Pipe O.D: Minimum 2-3/8-inches
e. Pipe wall thickness: 0.154-inch
f. Style: Wave
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 71 ▪
PART 30 EXECUTION
30.01 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for
correct and level finished grade, mounting surfaces, installation tolerances, and other
conditions affecting performance.
1. Proceed with installation only after unsatisfactory conditions have been corrected.
30.02 INSTALLATION - GENERAL
A. Comply with manufacturer's written installation instructions unless more stringent
requirements are indicated. Complete field assembly of site furnishings where required.
B. Unless otherwise indicated, install site furnishings after landscaping and paving have been
completed.
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 72 ▪
END OF SECTION
Revision Log
▪ DIVISION 12 FURNISHINGS ▪
▪ PAGE 73 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Pool & Spa Constructed of Gunite and Shotcrete System.
a. The Pool Contractor shall be responsible for design and installation of indoor pool
and spa system.
2. Pool Contractor shall be responsible for submitting and securing necessary approvals
and permits, including payment of fees, and expenses for the preparation of any required
documentation.
B. Related Sections:
1. Section 07 92 00 (07920) - Joint Sealants
2. Section 09 30 00 (09310) - Tiling
3. Division 22 (15) and 26 (16) Specifications for the following:
a. Excavation for electrical and plumbing lines.
b. Pool deck hose bibs.
c. Cold water supply within pool equipment room.
d. Gas line for pool heaters.
e. Conduit wiring, receptacles and disconnects to the pool equipment room.
f. Pool heater flues.
g. Filter room, decks, sealing of joints between pool and deck, shall be provided as
work of other sections.
h. Connection of floor & deck drains and hose bibs is specified in Division 22.
i. Connection of pool heater to gas source and heater vent piping in equipment room
shall be performed by Contractor.
j. Provisions for combustion air.
k. Connection of automatic water fill system and fill spout cold water lines from water
source in equipment room is specified in Division 22.
l. Connection of all pool equipment, starters and switches; grounding of pool, pool
equipment, pool lights and niches, and wiring of pool & spa lights from electrical
panel in equipment room is specified in Division 26.
m. On Projects that include emergency generator, the underwater pool niche lights shall
be connected to emergency power.
4. Section 31 20 00 (02300) - Earthwork
5. Section 33 10 00 (02500) - Utility Services
PART 2 PRODUCTS
2.01 MANUFACTURERS: The following manufacturers are approved for use as identified in the
individual paragraphs below:
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. A & B Brush
2. Action/Haviland (800-333-0400)
3. American Olean Tile Co. (800-933-8453)
4. American Products
5. Anchor Industries, Inc. (800-544-4445)
6. Aqua Creek Products (888-687-3552)
7. Berkeley (Sta-Rite Water Systems) ( 888-237-5353)
8. Bio-Lab, Inc. (800-959-7946)
9. Blue White Industries (714-893-8529)
10. Cal-June, Inc. (818-761-3516)
11. Dal-Tile Corp. (800-933-8453)
12. Federal Stone Industries, Inc. ( 800-513-5030)
13. Frost Co. (Inter-Fab) (800-737-5386)
14. A. J. Giammanco & Associates, Inc. (Lion Pool Products) (800-546-6766)
15. Gould Pumps, Inc (315-568-2811)
16. Grace Construction Products (800-778-2880)
17. Guardex (Bio-Lab) (800-959-7946)
18. Halogen Supply (800-777-7946)
19. Hydrotech (Bio Lab). (800-795-7946)
20. Inlays Inc. (800-426-6873
21. Jandy (707.776.8200)
22. Lochinvar Corp. (615-889-8900)
23. Mameco International, Inc.; a Division of Tremco, Inc. (800-321-6412)
24. Mec-O-Matic (Pulsafeeader) (800-333-6677)
25. Mortex Manufacturing, Inc. (800-338-3255)
b. Mix one part cement to 4 1/2 parts of sand based on dry, loose volume (minimum
3,000 psi compressive strength in 28 days).
c. Portland cement and water: As specified hereinafter.
4. Shotcrete:
a. Transit mix (ready-mix) materials conforming to aggregate specified above for
"Gunite" and with the additional following grading for pea gravel:
Sieve Size Percent by Weight
1/2" 100
3/8" 90
b. Mix Strength: Minimum 5,000 psi compressive strength in 28 days.
c. Submit design mix and certify material for weight, water content and mixing time.
d. Portland Cement and Water: As specified hereinafter.
5. Portland Cement: ASTM C150, Type I or II.
6. Water: Potable.
7. Forms: Exterior plywood, APA-B8 Plyform Class 1, mill-oiled.
8. Form Oil: Lacquer or resin type compatible with mill-oil.
9. Reinforcing Steel: ASTM A615 grade 40.
10. Gauging Wires: Piano wire, 0.027" thick.
B. Ceramic Tiling:
1. [Refer to Interior Finish Index]
2. Unglazed Ceramic Mosaic tile at Step Nosings:
a. Avendra, LLC Preferred Manufacturers:
1) None
b. Approved Manufacturers:
1) Dal-Tile Corp
2) American Olean Tile Co.
3. Provide certification by manufacturer for use in indoor pools.
4. Pool Tile: [Refer to Drawings and Interior Finish Index for size and location] at water line
below coping cap and at spa seating areas.
B. Underwater Lights:
(Coordinate with Section 16510(26 51 00))
1. 100W/300W/12V Light
(Two) Pac-Fab PHL-301/PHL-300
2. Light Niche Pac-Fab 425.4
C. Deck Fittings:
1. Grab Rail, 1.90-1/2” OD x .065 S. R. Smith
Stainless Steel with smooth grip finish
2. Deck Anchor S. R. Smith AS-100B
3. Escutcheon Plate S. R. Smith IEP-100
4. Ladder 3 tread 1.90” OD x .065” S. R. Smith SRS 506
Stainless Steel with mirror finish.
Provide every 75’ at perimeter
E. Safety Accessories:
1. Life Buoy (24" Approx.) Cal-June, Inc. U.S.C.G.
2. Throw Line w/ Floating Balls (Verify AJ Giammanco [60’]
that minimum length of line is equal to
width of pool)
3. Life Hook Rainbow #153 Double Arm
(R221026/R221030)
4. Life Hook Pole Rainbow 820-16 (R191116)
5. Life Hook Pole Adapter Frost A-14420 w/Brass
Bolts and Wing Nuts
END OF SECTION
Revision Log
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Furnish and install a complete new [in-ground] hydraulic passenger elevator system
including, but not limited to, the elevator cab, elevator entrances, hydraulic cylinder
assembly, motor, pump, and controls. The new elevator system shall be furnished and
installed in complete accordance with the Specifications and Drawings.
B. Work Included in Other Sections:
1. General Contractor to provide the following:
a. Confirm length, width, and clear overhead dimensions for hoistway, and provide size
as required, as approved by Architect and elevator manufacturer.
b. Provide all structural supports for guide rails and other mechanisms, as located by
elevator manufacturer.
c. Sill supports and grouting inside of hoistway for doors.
2. Telephone Cable by Division 27 (16).
3. Electrical
a. Include auxiliary contact in mainline electrical disconnect switch to signal elevator
controller loss of power is shutoff of disconnect switch.
C. Related Sections:
1. Section 04 20 00 (04200) - Masonry Units
2. Section 05 12 00 (05120) - Structural Steel: Hoisting Beam
3. Section 05 50 00 (05500) - Metal Fabrications: Pit Ladders, Sump Pit Cover
4. Section 09 90 00 (09900) - Painting
5. Division 23 (15) - Heating, Ventilation, and Air Conditioning
a. Ventilation and temperature control of elevator equipment room.
6. Division 26 (16) - Electrical
a. Electrical service to main disconnect in elevator machine room, electrical power for
elevator installation and testing, electrical disconnecting device to elevator
equipment prior to activation of sprinkler system, electrical service for machine
room, machine room and pit receptacles with ground fault current protection, lighting
in machine room and pit, wiring for telephone service to machine room.
b. Telephone Systems; ADAAG-required emergency communications equipment.
7. Division 28 (13) - Fire Protection
a. Fire and smoke detectors; fire alarm signal lines to contacts in the machine room.
1.02 REFERENCES
A. Americans with Disabilities Act (ADA) II Public Accommodations
1. “Americans with Disabilities Act Accessibility Guidelines “(ADAAG)
PART 3 EXECUTION
3.01 INSPECTION
A. Examine work of other Sections on which the work of this Section depends. Report defects to
Owner's representative in writing which may affect work of this Section or equipment
operation.
1. Review shaft size, machine room size, pit and over-travel dimensions shown on the
Drawings and report in writing if changes are required to accommodate manufacturer's
standard equipment.
2. Failure to furnish such statements will be interpreted to mean that this Contractor agrees
to meet all requirements under this Section, and conflicts with the work of other trades
will not result in added expense to Owner.
B. Ensure that shafts and openings for moving equipment are plumb, level, and in-line and that
pit is to proper depth with ladder.
C. Ensure that Machine Room is properly illuminated, heated, and ventilated and equipment
foundations correctly located, complete with floor and access door.
3.02 PREPARATION
A. Before fabrication of controls, take necessary job site measurements and verify where work is
governed by other Sections. Check measurement of space for equipment and means of
access for installation and operation. Obtain dimensions from site for preparation of Shop
Drawings.
Revision Log
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Linen (laundry) Chutes
B. Related Documents:
1. Marriott’s Fire Protection and Life Safety Design Standards (Module 14).
C. Related Sections:
1. Section 07 62 00 (07620) - Sheet Metal Flashing and Trim
2. Section 21 10 00 (13900) - Fire Suppression
3. Division 22 and 26: Hook-ups for water and electrical services.
4.02 REFERENCE STANDARDS
A. American National Standards Institute (ANSI) Publications
B. National Fire Protection Association (NFPA) Publications:
1. 13 “Installation of Sprinkler Systems”
2. 82. “Standard on Incinerators and Waste and Linen Handling Systems and Equipment”
C. Underwriter's Laboratories, Inc. (UL)
4.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Mark each copy to identify applicable products, characteristics, models, options and other
supplemental data to clearly communicate information specific to this project.
2. Product Data: Submit manufacturer's product specifications, standard details, installation
instructions and general recommendations for total pre-engineered chute system. Mark-
up data sheets to indicate actual selections for sizes and other details of installation.
3. Shop Drawings: Submit 1/4" scale section/elevation drawing, 1/2" scale typical landing
plans, and 1-1/2" scale details of chute fabrication. Distinguish between factory
fabrication and field assembly work. Show required piping, wiring connections and
conduit runs for wiring.
4. Quality Control Submittals:
a. Test Reports: Fire rating, in duplicate.
5. Certifications:
a. Contractor’s Certification that:
1) Manufacturer’s certification that installer of manufacturer’s product is approved.
b. Applicable standards: NFPA 82, standards as referenced herein.
PART 5 PRODUCTS
5.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Chute Source LLC, (330-733-3996)
2. Midland Chutes (847-678-4007)
3. US Chutes Corp. (800-872-4883)
4. Chutes International (800-882-4883)
5.02 LINEN CHUTE
A. Chute Sections: 16 gage aluminized steel per NFPA 82, 24" diameter.
1. Factory assemble sections to greatest extent possible. Disassemble only as necessary
for shipping and handling limitations. Clearly mark for reassembly and coordinated
installation.
2. Design sections to flash inside sections below, with no bolts, clips or other projections
inside chute to snag flow of materials.
3. Except for joints required for shipment and installation, provide factory welded or lock-
seamed tight joints.
4. Provide expansion joint in chute between supporting grid floor frames.
B. Vent: Extend full diameter chute section through roof; [terminate top 4'-0" above roof]. Equip
16 gage aluminized steel vent cap with ventilation air space around full diameter of vent riser,
insect screen, condensation gutter, roof flashing. [Provide roof curb at low slope roofs,
installed by roofing contractor.]
C. Door Units:
1. UL Labeled Door Units: Provide UL 1-1/2 hour labeled door units with 30-minute
temperature rise of 250 deg. F., (139 deg. C.), complete with closers.
2. Chute Intake Door/Frame Units: Provide self-closing units at each landing and at heights
above floor as indicated. Use manufacturer’s recommended heights if not otherwise
PART 6 EXECUTION
6.01 EXAMINATION
A. Examine areas in which Work is to be performed. Report in writing, to Owner’s
Representative, all prevailing conditions that will adversely affect satisfactory execution of
Work. Do not proceed with work until unsatisfactory conditions have been corrected.
B. Starting Work constitutes acceptance of the existing conditions and this Contractor shall then,
at their expense, be responsible for correcting all unsatisfactory and defective Work
encountered.
6.02 INSTALLATION
A. General: Comply with chute manufacturer's instructions and recommendations. Assemble
components with tight, non-leaking joints and anchor securely to supporting structure with
sufficient anchorages to withstand impact and wind loading stresses on vent units. Provide for
thermal expansion movement of chute sections. Except as otherwise indicated, install chutes
plumb, without offsets of obstructions, for free fall of materials within chutes. Install chute
systems complete with doors, and with safety and fire-resistive components and accessories.
B. Intake and Discharge Doors: Install doors at heights and locations indicated. Provide
anchorages, wall/chute interfaces, self-closing operation, self-latching and similar features of
installation to comply with labeling and fire-resistive requirements for fire-resistive door
construction. Interface door units with throat sections of chutes in a manner which will ensure
safe, snag-proof, sanitary depositing of materials in chutes by users.
1. Coordinate foot-pedal door operator installation with door and enclosure wall installation.
END OF SECTION
Revision Log
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Piping Materials and Fittings
2. Joining Materials
3. Dielectric Fittings
4. Mechanical Sleeve Seals
5. Piping Specialties
6. Piping Installation
7. Equipment Installation
8. Concrete Bases.
9. Erection of Metal Supports
10. Erection of Wood Supports
11. Cutting and Patching
12. Grouting
B. Related Documents:
1. Marriott’s Fire Protection and Life Safety Design Standards (Module 14):
a. Marriott’s Fire Protection and Life Safety Design Standards apply to all Marriott
International Brands as well as Owned, Managed and Franchised properties.
b. Marriott’s Fire Protection and Life Safety Design Standards include Design
Standards, performance criteria, reference standards and life safety process
verification that define a comprehensive fire protection program.
C. Related Sections:
1. Section 21 10 00 (13900) – Fire Suppression Systems
1.02 DEFINITIONS
A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred
spaces, pipe and duct shafts, unheated spaces immediately below roof, spaces above
ceilings, unexcavated spaces, crawl spaces, and tunnels.
B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied
spaces and mechanical equipment rooms.
C. Exposed, Exterior Installations: Exposed to view outdoors, or subject to outdoor ambient
temperatures and weather conditions. Examples include rooftop locations.
D. Concealed, Interior Installations: Concealed from view and protected from physical contact by
building occupants. Examples include above ceilings and in duct shafts.
E. Concealed, Exterior Installations: Concealed from view and protected from weather conditions
and physical contact by building occupants, but subject to outdoor ambient temperatures.
Examples include installations within unheated shelters.
PART 2 PRODUCTS
2.01 JOINING MATERIALS
A. Refer to individual Division 22 piping Sections for special joining materials not listed below.
B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system
contents.
1. ASME B16.21, nonmetallic, flat, asbestos-free, 1/8-inch maximum thickness, unless
thickness or specific material is indicated.
a. Full-Face Type: For flat-face, Class 125, cast-iron and cast-bronze flanges.
b. Narrow-Face Type: For raised-face, Class 250, cast-iron and steel flanges.
2. AWWA C110, rubber, flat face, 1/8 inch thick, unless otherwise indicated; and full-face or
ring type, unless otherwise indicated.
C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.
D. Plastic, Pipe-Flange Gasket, Bolts, and Nuts: Type and material recommended by piping
system manufacturer, unless otherwise indicated.
E. Solder Filler Metals: ASTM B32.
1. Alloy Sn95 or Alloy Sn94: Approximately 95 percent tin and 5 percent silver, with 0.10
percent lead content.
2. Alloy E: Approximately 95 percent tin and 5 percent copper, with 0.10 percent maximum
lead content.
3. Alloy HA: Tin-antimony-silver-copper zinc, with 0.10 percent maximum lead content.
4. Alloy HB: Tin-antimony-silver-copper nickel, with 0.10 percent maximum lead content.
5. Alloy Sb5: 95 percent tin and 5 percent antimony, with 0.20 percent maximum lead
content.
F. Brazing Filler Metals: AWS A5.8.
1. BCuP Series: Copper-phosphorus alloys.
2. BAg1: Silver alloy.
PART 3 EXECUTION
3.01 PIPING SYSTEMS - COMMON REQUIREMENTS
A. General: Install piping as described below, unless piping Sections specifies otherwise.
Individual Division 21 piping Sections specifies unique piping installation requirements.
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Pipe and Fittings.
2. Sprinklers.
B. Related Documents:
1. Marriott’s Fire Protection and Life Safety Design Standards (Module 14):
a. Marriott’s Fire Protection and Life Safety Design Standards apply to all Marriott
International Brands as well as Owned, Managed and Franchised properties.
b. Marriott’s Fire Protection and Life Safety Design Standards include Design
Standards, performance criteria, reference standards and life safety process
verification that define a comprehensive fire protection program.
C. Related Sections:
1. Section 21 05 00 (15050) – Common Work Results for Fire Suppression
2. Section 28 31 00 (13850) - Fire Alarm and Detection Systems: Wire and connection of
sprinkler flow and tamper switches
4.02 SYSTEM DESCRIPTION
A. The Fire Protection Subcontractor is responsible for code compliance, research, design,
coordination, and installation of a complete and functional hydraulically calculated sprinkler
system (and standpipe system, if required) that meets the approval of and is in accordance
with all applicable regulations and requirements of the following and as further specified:
1. Current editions of NFPA 13, 14, 20, 25, and 96.
2. Applicable Codes.
3. Authorities having jurisdiction.
B. Alarm system devices including alarm valves, flow switches, pressure switches, tamper
switches and coordination with Fire Alarm and Detection Subcontractor.
C. Shop drawings and calculations prepared and submitted in accordance with the requirements
of all Authorities Having Jurisdiction.
D. Obtaining all permits and approvals of the fire protection system.
E. Field acceptance testing.
4.03 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 with the following
supporting data:
1. Product Data:
a. Mark each copy to identify applicable products, characteristics, models, options and
other supplemental data to clearly communicate information specific to this project.
b. Submit separate "Letter of Conformance" for each specified item.
PART 5 PRODUCTS
5.01 MANUFACTURERS
A. All sprinkler system equipment is to be UL Listed.
5.02 PIPE AND FITTINGS
A. Piping - Class I, Schedule 40 ASTM black steel piping for branches and Class I Schedule 10
ASTM black steel for mains..
1. Piping (piping only, excluding fittings) for dry systems shall be galvanized steel.
2. Alternate: CPVC or XL Thin-wall for wet sprinkler pipe.
B. Exposed piping and fittings in kitchen shall be chrome-plated.
5.03 KITCHEN HOOD AND DUCT FIRE SUPPRESSION
A. Provide a complete "Ansul Piranha” automatic, water-assisted, wet chemical, fier suppression
system by Tyco Fire & Security for protection of the exhaust duct and all grease-producing
cooking surfaces located under canopy hoods. The system, including all of its components
shall be UL Standard 300 listed.
B. Kitchen hood and duct system flow switch (or control units of the Ansul fire suppression
system) to perform these functions:
1. Send fire alarm signal to FACP
2. Disconnect gas and all electric for cooking appliances and lighting under the hood
(manual reset is required).
3. Shut-off kitchen hood make-up air handler.
5.04 SPRINKLERS
A. Sprinkler heads shall be UL Listed.
B. Sprinkler heads and escutcheons shall have a white finish unless noted otherwise.
1. Concealed sprinklers are not acceptable.
C. Sprinklers: Fast-response 68 degrees C – 74 degrees C (155 degrees F – 165 degrees F),
recessed or semi-recessed type heads throughout, except as follows:
Room/Space Head Type Temp. Rating
Attic Systems Quick Response – ventilated 100 degrees C (212 degrees F)
Quick Response – 141 degrees C (286 degrees F)
unventilated
Drypipe Systems Quick Response 100 degrees C (212 degrees F)
Mech./Elect. Quick Response 68 degrees C – 74 degrees C
Elevator Machinery Quick Response 100 degrees C (212 degrees F)
Swimming Pools Corrosion - proof- 68 degrees C – 77degrees C
Quick response (155 degrees F –170 degrees F)
Porches Dry-side wall, corrosion- 100 degrees C (212 degrees F)
PART 6 EXECUTION
6.01 INSTALLATION
A. Install and support fire protection system to resist all applicable seismic forces per
requirements.
B. Locate wet pipe and dry pipe inspector test valves and associated sight glasses at remote
ends of system, in accessible locations. Provide drain pipes to exterior. Do not discharge onto
sidewalks or landscaping.
C. Under no circumstance shall wet sprinkler pipes be routed through attics or other unheated
spaces.
D. Access panels for service and access to valves in enclosed ceiling and walls.
6.02 TESTING
A. Before a property is opened to the public, the fire protection system shall be fully operational,
contractor tested, and approval obtained from Marriott’s Fire Protection Department. In order
to obtain Marriott’s approval, the fire protection system shall be operated by the contractor
under simulated emergency conditions in the presence of Marriott Fire Protection personnel
and the contractor shall demonstrate compliance with Marriott’s standards.
B. Automatic Sprinkler System:
1. Contractor shall flush and pressure test system prior to Marriott’s observation of the test
of water flow and tamper switches.
C. Kitchen Hood and Duct Fire Suppression:
1. Contractor shall pre-test all coordinated components by activation of kitchen hood and
duct flow switch or control unit.
2. Contractor shall demonstrate compliance by operating initiating devices, activating
coordinated alarms, gas, electric, and hood supply air fan shut-downs.
D. Provide all equipment necessary to perform test.
E. Refer to Submittals Paragraph for required certifications and documents to be provided with
closeout documents.
6.03 TRAINING
A. Conduct training as specified in Section 01 79 00 (01820) - "Training”.
B. Train Owner's maintenance personnel on procedures and schedules for troubleshooting,
servicing, and maintaining system.
C. Schedule training with Owner with at least seven days’ advance notice.
Note: Delete paragraph below if fire pump is not required.
END OF SECTION
Revision Log
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Piping materials and fittings.
2. Joining materials.
3. Dielectric fittings.
4. Mechanical sleeve seals.
5. Piping Specialties
6. Grouting
7. Piping Insulation.
8. Equipment Installation.
9. Concrete Bases.
10. Erection of Metal Supports.
11. Erection of Wood Supports
12. Cutting and Patching
B. Related Sections:
1. Section 01 31 00 - Project Management and Coordination
2. Section 01 73 29 - Cutting and Patching
3. Section 01 78 43 - Spare Parts and Materials
4. Section 01 79 00 - Training
5. Section 01 78 23 - Operating and Maintenance Data
6. Section 03 30 00 - Cast-in-Place Concrete
7. Section 06 10 00 - Rough Carpentry
8. Section 07 62 00 - Sheet Metal Flashing and Trim
9. Section 07 84 00 - Firestopping
10. Section 08 31 00 - Access Doors
11. Section 09 90 00 - Painting
12. Section 22 05 53 – Identification for Plumbing Piping and Equipment: Labeling and
identifying plumbing systems and equipment.
13. Section 31 20 00 – Earth Moving
1.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B1.20.1 "Pipe Threads, General Purpose, Inch"
2. B16.21 "Nonmetallic Flat Gaskets for Pipes Flanges"
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 1 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 2 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 3 ▪
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Dielectric Unions:
a. None
2. Dielectric Flanges:
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 4 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 5 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 6 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 7 ▪
PART 3 EXECUTION
3.01 PIPING SYSTEMS - COMMON REQUIREMENTS
A. General: Install piping as described below, unless piping Sections specifies otherwise.
Individual Division 22 piping Sections specifies unique piping installation requirements.
B. General Locations and Arrangements: Drawing plans, schematics, and diagrams indicate
general location and arrangement of piping systems. Indicated locations and arrangements
were used to size pipe and calculate friction loss, expansion, pump sizing, and other design
considerations. Install piping as indicated, unless deviations to layout are approved on
Coordination Drawings as required by Division 01 Sections and as outlined in Part 1 of this
section.
C. Install piping at indicated slope.
D. Install components with pressure rating equal to or greater than system operating pressure.
E. Install piping in concealed interior and exterior locations, except in equipment rooms and
service areas.
F. Install piping free of sags and bends.
G. Install exposed interior and exterior piping at right angles or parallel to building walls.
Diagonal runs are prohibited, unless otherwise indicated.
H. Install piping tight to slabs, beams, joists, columns, walls, and other building elements. Allow
sufficient space above removable ceiling panels to allow for ceiling panel removal.
I. Install piping to allow application of insulation plus 1-inch clearance around insulation.
J. Locate groups of pipes parallel to each other, spaced to permit valve servicing.
K. Install fittings for changes in direction and branch connections.
L. Install couplings according to manufacturer's written instructions.
M. Install pipe escutcheons for pipe penetrations of concrete and masonry walls, wall board
partitions, and suspended ceilings according to the following:
1. Chrome-Plated Piping: Cast brass, one piece, with set screw, and polished chrome-
plated finish.
2. Uninsulated Piping Wall Escutcheons: Cast brass or stamped steel, with set screw.
3. Uninsulated Piping Floor Plates in Utility Areas: Cast-iron floor plates.
4. Insulated Piping: Cast brass with concealed hinge, set screws, and chrome-plated finish.
5. Piping in Utility Areas: Cast brass or stamped steel, with set-screw or spring clips.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 8 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 9 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 10 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 11 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 12 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Basic Motor Requirements
2. Polyphase Motors
3. Single Phase Motors
B. Related Sections:
1. Division 22 Sections for application of motors and reference to specific motor
requirements for motor-driven equipment.
4.02 REFERENCES
A. Institute of Electrical and Electronics Engineers (IEEE) Publications:
1. 112 “Standard Test Procedure for Polyphase Induction Motors and Generators”
B. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. MG 1 “Motors and Generators”
C. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
4.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: Show nameplate data and ratings; characteristics; mounting
arrangements; size and location of winding termination lugs, conduit entry, and grounding
lug; and coatings.
4.04 QUALITY ASSURANCE
A. Comply with NFPA 70.
B. Listing and Labeling: Provide motors specified in this Section that are listed and labeled.
1. Terms "Listed and Labeled": As defined in the National Electrical Code, Article 100.
PART 5 PRODUCTS
5.01 BASIC MOTOR REQUIREMENTS
A. Basic requirements apply to mechanical equipment motors, unless otherwise indicated.
B. Motors 1/2 HP and Larger: Polyphase.
C. Motors smaller than 1/2 HP: Single phase.
D. Frequency Rating: 60 Hz.
E. Voltage Rating: Determined by voltage of circuit to which motor is connected.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 13 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 14 ▪
PART 6 EXECUTION
6.01 ADJUSTING
A. Use adjustable motor mounting bases for belt-driven motors.
B. Align pulleys and install belts.
C. Tension according to manufacturer's written instructions.
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 15 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Thermometers.
2. Pressure Gages.
3. Water Meters.
B. Related Sections:
1. Section 21 10 00 (13900) – Fire Suppression Systems: For fire-pump flow-measuring
systems.
2. Section 22 11 23 (15194) - Natural Gas Piping: For gas meters.
3. Division 22 (15) Plumbing Equipment Sections that specify meters and gages as part of
factory-fabricated equipment.
4. Section 32 84 00 (02810) - Irrigation Systems: For irrigation water sub-meters outside
the buildings.
5. Section 33 00 00 (02500) - Utilities: For water meters outside the building.
7.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B40.100 “Pressure Gauges and Gauge Attachments”
2. B40.5 “Snubbers”
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. E1-03a“Standard Specification for ASTM Thermometers”
C. American Water Works Association (AWWA) Publications:
1. C700-02 AWWA Standard for Cold-Water Meters -- Displacement Type, Bronze Main
Case
2. C701-02 Standard for Cold-Water Meters -- Turbine Type, for Customer Service
3. M6 “Water Meters: Selection, Installation, Testing, and Maintenance (M6)”
7.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 16 ▪
PART 8 PRODUCTS
8.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Liquid-in-Glass Thermometers:
a. None.
2. Pressure Gages:
a. None.
B. Approved Manufacturers:
1. Liquid-in-Glass Thermometers:
a. Ashcroft, Inc. (800-328-8258)
b. Marsh Bellofram (800-727-5646)
c. Weiss Instruments, Inc. (631-207-1200)
2. Pressure Gages:
a. Ashcroft, Inc. (800-328-8258)
b. Marsh Bellofram (800-727-5646)
c. Weiss Instruments, Inc. (631-207-1200)
3. Water Meters and Submeters:
a. As required by the local authority having jurisdiction.
8.02 THERMOMETERS, GENERAL
A. Scale Range: Temperature ranges for services listed are as follows:
1. Domestic Hot and Cold Water: 30 to 240 deg F, with 2-degree scale divisions.
B. Accuracy: Plus or minus 1 percent of range span or plus or minus one scale division to
maximum of 1.5 percent of range span.
8.03 THERMOMETERS - LIQUID-IN-GLASS
A. Description: ASTM E1-03a.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 17 ▪
PART 9 EXECUTION
9.01 INSTALLATION - METER AND GAGE, GENERAL
A. Install meters, gages, and accessories according to manufacturer's written instructions for
applications where used.
9.02 INSTALLATION - THERMOMETER
A. Install thermometers and adjust vertical and tilted positions.
B. Install in the following locations:
1. Domestic hot water supply main (downstream of storage tank).
2. Domestic hot water return main.
3. Domestic hot water storage tank.
4. Domestic water heater discharge.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 18 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 19 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 20 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Valves.
B. Related Sections:
1. Section 22 05 53 (15075) – Identification for Plumbing Piping and Equipment: For valve
tags and charts.
2. Division 22 Plumbing Piping System Sections: Special purpose valves
10.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B1.20.1 "Pipe Threads, General Purpose, Inch"
2. B16.1 “Cast Iron Pipe Flanges and Flanged Fittings”
3. B16.5 “Pipe Flanges and Flanged Fittings”
4. B16.18 “Cast Copper Alloy Solder Joint Pressure Fittings”
5. B16.22 “Wrought Copper and Copper Alloy Solder Joint Pressure Fittings”
6. B16.24 “Cast Copper Alloy Pipe Flanges and Flanged Fittings: Classes 150, 300, 400,
600, 900, 1500 and 2500”
7. B31.1 “Power Piping”
8. B31.9 “Building Services Piping”
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and Seamless"
2. A126 "Standard Specification for Gray Iron Castings for Valves, Flanges, and Pipe
Fittings"
3. A395 “Standard Specification for Ferritic Ductile Iron Pressure-Retaining Castings for Use
at Elevated Temperatures”
4. B62 “Standard Specification for Composition Bronze or Ounce Metal Castings”
5. B209 "Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate"
6. B283 “Standard Specification for Copper and Copper-Alloy Die Forgings (Hot-Pressed)”
7. B584 “Standard Specification for Copper Alloy Sand Castings for General Applications”
10.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data for each valve type. Include body material, valve design, pressure and
temperature classification, end connection details, seating materials, trim material and
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 21 ▪
PART 11 PRODUCTS
11.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Ball and Gate Valves
a. None
2. Balancing Valves
a. None
3. Check Valves
a. None
4. Blending Valves
a. None
5. Digital Reticulating Valves
a. None
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 22 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 23 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 24 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 25 ▪
PART 12 EXECUTION
12.01 EXAMINATION
A. Examine piping system for compliance with requirements for installation tolerances and other
conditions affecting performance of valves. Do not proceed with installation until
unsatisfactory conditions have been corrected.
B. Examine valve interior for cleanliness, freedom from foreign matter, and corrosion. Remove
special packing materials, such as blocks, used to prevent disc movement during shipping and
handling.
C. Operate valves from fully open to fully closed positions. Examine guides and seats made
accessible by such operation.
D. Examine threads on valve and mating pipe for form and cleanliness.
E. Examine mating flange faces for conditions that might cause leakage. Check bolting for
proper size, length, and material. Check gasket material for proper size, material composition
suitable for service, and freedom from defects and damage.
F. Do not attempt to repair defective valves; replace with new valves.
12.02 INSTALLATION
A. Install valves as indicated, according to manufacturer's written instructions.
B. Piping installation requirements are specified in other Division 22 Sections. Drawings indicate
the general arrangement of piping, fittings, and specialties.
C. Install valves with unions or flanges at each piece of equipment arranged to allow servicing,
maintenance, and equipment removal without system shutdown.
D. Locate valves for easy access and provide separate support where necessary.
E. Install valves in horizontal piping with stem at or above the center of the pipe and in a position
to allow full stem movement.
F. Installation of Check Valves: Install for proper direction of flow as follows:
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 26 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 27 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 28 ▪
PART 13 GENERAL
13.01 SUMMARY
A. Section Includes:
1. Hangers and Supports for Plumbing System Piping and Equipment.
B. Related Sections:
1. Section 05 50 00 (05500) - Metal Fabrications
2. Section 09 90 00 (09900) - Painting
3. Section 21 10 00 (13900) - Fire Suppression Systems
4. Section 22 05 48 (15070) – Vibration and Seismic Control for Plumbing Piping and
Equipment
13.02 DEFINITIONS
A. MSS: Manufacturers Standardization Society for the Valve and Fittings Industry.
B. Terminology: As defined in MSS SP-90, "Guidelines on Terminology for Pipe Hangers and
Supports.
13.03 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B31.9 “Building Services Piping”
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A36 “Standard Specification for Carbon Structural Steel”
2. A780 "Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip
Galvanized Coatings"
3. C552 “Standard Specification for Cellular Glass Thermal Insulation”
4. C1107 "Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)"
C. American Welding Society (AWS) Publications:
1. D1.1 "Structural Welding Code - Steel"
D. Metal Framers Manufacturing Associations (MFMA) Publications:
1. MFMA-2 “Metal Framing Standards Publication”
13.04 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data:
a. For each type of pipe hanger, channel support system component, and thermal-
hanger shield insert indicated.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 29 ▪
PART 14 PRODUCTS
14.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Pipe Hangers, Supports, and Components:
a. None
2. Channel Support Systems:
a. None
3. Thermal-Hanger Shield Inserts:
a. None
4. Powder-Actuated and Mechanical Anchor Fastener Systems:
a. None
B. Approved Manufacturers:
1. Pipe Hangers, Supports, and Components:
a. Unistrut, a part of Atcore International (800-521-7730)
b. Cooper B-Line, Inc. (618-654-2184)
c. Grinnell Mechanical Products, A Tyco International Company (800-500-4768)
d. National Pipe Hanger Corporation (609-261-5353)
2. Channel Support Systems:
a. Unistrut, a part of Atcore International (800-521-7730)
b. Cooper B-Line, Inc. (618-654-2184)
c. Grinnell Mechanical Products, A Tyco International Company (800-500-4768)
d. National Pipe Hanger Corporation (609-261-5353)
3. Thermal-Hanger Shield Inserts:
a. Carpenter & Patterson, Inc. (301.333.4631)
b. Erico (Michigan Hanger) (440-248-0100)
c. PHS Industries, Inc. (800-626-2336)
4. Powder-Actuated and Mechanical Anchor Fastener Systems:
a. Gunnebo Fastening Corp. (800-336-1640)
b. Hilti, Inc.(800-879-8000)
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 30 ▪
PART 15 EXECUTION
15.01 HANGER AND SUPPORT APPLICATIONS
A. Specific hanger requirements are specified in Sections specifying equipment and systems.
B. Comply with MSS SP-69 for pipe hanger selections and applications that are not specified in
piping system Specification Sections.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 31 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 32 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 33 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 34 ▪
PART 16 GENERAL
16.01 SUMMARY
A. Section Includes:
1. Vibration Isolators.
2. Seismic Controls.
3. Vibration Isolation Bases.
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-In-Place Concrete
2. Section 09 90 00 (09900) - Painting
3. Section 22 05 00 (15050) – Common Work Results for Plumbing
4. Section 22 05 29 (15060) - Hangers and Supports for Plumbing Piping and Equipment:
for pipe hanger restraints.
5. Division 22 Piping Sections for flexible pipe connectors.
16.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A36 “Standard Specification for Carbon Structural Steel”
16.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: Indicate types, styles, materials, and finishes for each type of isolator
specified. Include load deflection curves.
2. Shop Drawings: Show designs and calculations, certified by a professional engineer, as
required by the local authority, for the following:
a. Design Calculations: Calculations for selection of vibration isolators, design of
vibration isolation bases, and selection of seismic restraints.
b. Vibration Isolation Base Details: Detail fabrication, including anchorages and
attachments to the structure and to the supported equipment. Include auxiliary
motor slides and rails, and base weights.
c. Seismic Restraint Details: Detail fabrication and attachment of restraints and
snubbers.
C.
16.04 COORDINATION
A. Coordinate layout and installation of vibration isolation and seismic-restraint devices with other
construction that penetrates ceilings or is supported by them, including light fixtures, HVAC
equipment, fire-suppression-system components, and partition assemblies.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 35 ▪
PART 17 PRODUCTS
17.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Cooper B-Line Systems, Inc. (800-851-7415)
2. Kinetics Noise Control, Inc. (877-457-2695)
3. Mason Industries, Inc. (631-348-0282)
17.02 VIBRATION ISOLATORS
A. Isolator Pads: Oil and water resistant and factory cut to sizes that match requirements of the
equipment supported.
1. Rubber Isolator Pads: Elastomer (neoprene or silicone) arranged in single or multiple
layers and molded with a nonslip pattern and steel baseplates of sufficient stiffness to
provide uniform loading over the pad area.
2. Load Range: From 10 to 50 psig and a deflection not less than 0.08 inch per 1 inch of
thickness. Do not exceed a loading of 50 psig.
B. Rubber Isolator Mounts: Double-deflection type, with molded, oil-resistant rubber or neoprene
isolator elements, with encapsulated top- and baseplates. Factory-drilled and tapped top plate
for bolted equipment mounting. Factory-drilled baseplate for bolted connection to structure.
Color-code to indicate capacity range.
C. Spring Isolators: Freestanding, laterally stable, open-spring-type isolators.
1. Outside Spring Diameter: Not less than 80 percent of the compressed height of the
spring at rated load.
2. Minimum Additional Travel: 50 percent of the required deflection at rated load.
3. Lateral Stiffness: More than 1.2 times the rated vertical stiffness.
4. Overload Capacity: Support 200 percent of rated load, fully compressed, without
deformation or failure.
5. Baseplates: Factory drilled for bolting to structure and bonded to a 1/4-inch- thick, rubber
isolator pad attached to the baseplate underside. Size baseplates to limit floor loading to
100 psig.
6. Top Plates: Provide threaded studs for fastening and leveling equipment.
7. Finishes: Manufacturer's standard corrosive-resistant finish.
D. Restrained Spring Isolators: Vertically restrained, freestanding, laterally stable, steel open-
spring-type isolators.
1. Housing: Welded steel with resilient vertical limit stops to prevent spring extension due to
wind loads or when weight is removed. Factory-drilled baseplate for bolting to structure
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 36 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 37 ▪
PART 18 EXECUTION
18.01 INSTALLATION
A. Install and anchor vibration-, sound-, and seismic-control products according to
manufacturer's written instructions and authorities having jurisdiction.
B. Anchor interior mounts, isolators, hangers, and snubbers to vibration isolation bases. Bolt
isolator baseplates to structural floors as required by authorities having jurisdiction.
C. Anchor exterior mounts, isolators, hangers, and snubbers to vibration isolation bases. Bolt
isolator baseplates to structural supports as required by authorities having jurisdiction.
D. Install pipe connectors at connections for equipment supported on vibration isolators.
18.02 SEISMIC CONTROL
A. Snubbers: Install the required number of seismic snubbers on each spring-mounted piece of
equipment. Locate snubbers as close as possible to the vibration isolators and bolt to
supporting structure.
18.03 ADJUSTING AND CLEANING
A. Adjust limit stops on restrained spring isolators to mount equipment at normal operating
height. After equipment installation is complete, adjust limit stops so they are out of contact
during normal operations.
B. Adjust thrust restraints for a maximum of 1/4 inch of movement at start and stop
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 38 ▪
PART 19 GENERAL
19.01 SUMMARY
A. Section Includes:
1. Identifying Devices and Labels for Plumbing Piping and Equipment
B. Related Sections:
1. Section 22 05 00 (15050) – Common Work Results for Plumbing
19.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. A13.1 “Scheme for the Identification of Piping Systems”
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. C1036 “Standard Specification for Flat Glass”
19.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: For identification materials and devices.
2. Samples: Of color, lettering style, and graphic representation required for each
identification material and device.
19.04 QUALITY ASSURANCE
A. Comply with ASME A13.1, "Scheme for the Identification of Piping Systems" for lettering size,
length of color field, colors, and viewing angles of identification devices.
19.05 SEQUENCING AND SCHEDULING
A. Coordinate installation of identifying devices with completion of covering and painting of
surfaces where devices are to be applied.
B. Install identifying devices before installing acoustical ceilings and similar concealment.
PART 20 PRODUCTS
20.01 GENERAL
A. General: Products specified are for applications referenced in other Division 22 Sections. If
more than single type is specified for listed applications, selection is Installer's option.
B. Pipes Including Insulation: Full-band pipe markers, extending 360 degrees around pipe at
each location.
20.02 IDENTIFYING DEVICES AND LABELS
A. Lettering and Graphics:
1. Utilize manufacturer's standard preprinted captions as selected by Owner's
Representative.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 39 ▪
PART 21 EXECUTION
21.01 LABELING AND IDENTIFYING PIPING SYSTEMS
A. Install pipe markers on each system as indicated below. Include arrows showing normal
direction of flow.
1. Domestic Cold Water.
2. Domestic Hot Water.
3. Domestic Hot Water Return.
4. Sanitary Drain.
5. Storm Drain.
6. Condensate.
7. Vent.
B. Marker Type: Plastic markers, with application systems. Install on pipe insulation segment
where required for hot, noninsulated pipes.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 40 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 41 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 42 ▪
PART 22 GENERAL
22.01 SUMMARY
A. Section Includes:
1. Insulation Materials
2. Jackets
3. Accessories and Attachments
4. Vapor Retarders
5. Under Lavatory Pipe Insulation
B. Related Sections:
1. Section 07 84 00 (07840) - Firestopping: Firestopping materials and requirements for
penetrations through fire and smoke barriers.
2. Section 22 05 29 (15060) - Hangers and Supports for Plumbing Piping and Equipment:
For pipe insulation shields and protection saddles.
22.02 REFERENCES
A. ASTM International (ASTM) Publications:
1. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
2. C195 “Standard Specification for Mineral Fiber Thermal Insulating Cement”
3. C196 “Standard Specification for Expanded or Exfoliated Vermiculite Thermal Insulating
Cement”
4. C449 “Standard Specification for Mineral Fiber Hydraulic-Setting Thermal Insulating and
Finishing Cement”
5. C450 “Standard Practice for Fabrication of Thermal Insulating Fitting Covers for NPS
Piping, and Vessel Lagging”
6. C547 “Standard Specification for Mineral Fiber Pipe Insulation”
7. C553 “Standard Specification for Mineral Fiber Blanket Thermal Insulation for
Commercial and Industrial Applications”
8. C921 “Standard Practice for Determining the Properties of Jacketing Materials for
Thermal Insulation”
22.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: Identify thermal conductivity, thickness, and jackets (both factory and field
applied, if any), for each type of product indicated.
2. Shop Drawings:
a. Submit Manufactures data for each type of insulation used.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 43 ▪
PART 23 PRODUCTS
23.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Mineral-Fiber Insulation:
a. None
B. Approved Manufacturers:
1. Mineral-Fiber Insulation:
a. CertainTeed Corp. (610-647-3011)
b. Knauf Insulation. (800-825-4434)
c. Owens-Corning Fiberglas Corp. (800-447-3759)
2. Under Lavatory Pipe Insulation:
a. “Truebro Lav Guard 2”; IPS Corp; (901-583-5001)
23.02 INSULATION MATERIALS
A. Mineral-Fiber Insulation:
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 44 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 45 ▪
PART 24 EXECUTION
24.01 EXAMINATION
A. Examine substrates and conditions for compliance with requirements for installation and other
conditions affecting performance of insulation application.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
24.02 PREPARATION
A. Surface Preparation: Clean and dry pipe and fitting surfaces. Remove materials that will
adversely affect insulation application.
24.03 GENERAL APPLICATION REQUIREMENTS
A. Apply insulation materials, accessories, and finishes according to the manufacturer's written
instructions; with smooth, straight, and even surfaces; free of voids throughout the length of
piping, including fittings, valves, and specialties.
B. Refer to schedules at the end of this Section for materials, forms, jackets, and thicknesses
required for each piping system.
C. Use accessories compatible with insulation materials and suitable for the service. Use
accessories that do not corrode, soften, or otherwise attack insulation or jacket in either wet or
dry state.
D. Apply insulation with longitudinal seams at top and bottom of horizontal pipe runs.
E. Apply multiple layers of insulation with longitudinal and end seams staggered.
F. Do not weld brackets, clips, or other attachment devices to piping, fittings, and specialties.
G. Seal joints and seams with vapor-retarder mastic on insulation indicated to receive a vapor
retarder.
H. Keep insulation materials dry during application and finishing.
I. Apply insulation with tight longitudinal seams and end joints. Bond seams and joints with
adhesive recommended by the insulation material manufacturer.
J. Apply insulation with the least number of joints practical.
K. Apply insulation over fittings, valves, and specialties, with continuous thermal and vapor-
retarder integrity, unless otherwise indicated. Refer to special instructions for applying
insulation over fittings, valves, and specialties.
L. Hangers and Anchors: Where vapor retarder is indicated, seal penetrations in insulation at
hangers, supports, anchors, and other projections with vapor-retarder mastic.
1. Apply insulation continuously through hangers and around anchor attachments.
2. For insulation application where vapor retarders are indicated, extend insulation on
anchor legs at least 12 inches from point of attachment to pipe and taper insulation ends.
Seal tapered ends with a compound recommended by the insulation material
manufacturer to maintain vapor retarder.
3. Install insert materials and apply insulation to tightly join the insert. Seal insulation to
insulation inserts with adhesive or sealing compound recommended by the insulation
material manufacturer.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 46 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 47 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 48 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 49 ▪
PART 25 GENERAL
25.01 SUMMARY
A. This Section includes the following:
1. The purpose of this section is to specify Division 22 responsibilities in the commissioning
process.
a. The systems to be commissioned are listed in Section 01 91 13.
b. Commissioning requires the participation of Division 22 to ensure that all systems
are operating in a manner consistent with the Contract Documents. The general
commissioning requirements and coordination are detailed in Division 01. Division
22 shall be familiar with all parts of Division 01 and the commissioning plan issued
by the CxA and shall execute all commissioning responsibilities assigned to them in
the Contract Documents.
B. Related Sections:
1. Section 01 91 13 – General Commissioning Requirements.
2. Section 22 08 00.01 – Plumbing Testing Requirements
3. Section 22 08 00.02 – Plumbing Prefunctional Checklists
4. Section 22 08 00.03 – Plumbing Sample Functional Test Procedures
C. Related Work:
1. Refer to Section 01 91 13 for a listing of all Sections where commissioning requirements
are found.
2. Refer to Section 01 91 13 for systems to be commissioned and Sections 22 08 00
through 22 08 00.03 for functional testing requirements.
25.02 RESPONSIBILITIES
A. Plumbing Contractor. The commissioning responsibilities applicable to the Plumbing
Contractor of Division 22 are as follows (all references apply to commissioned equipment
only):
1. Construction and Acceptance Phases
a. Include and itemize the cost of commissioning in the contract price.
b. In each purchase order or subcontract written, include requirements for submittal
data, commissioning documentation, O&M data and training.
c. Attend a commissioning scoping meeting and other meetings necessary to facilitate
the Cx process.
d. Provide a copy of the O&M manuals of commissioned equipment, through normal
channels, to the CxA for review and approval.
e. Develop a full start-up and initial checkout plan using manufacturer’s start-up
procedures and the prefunctional checklists from the CxA for all commissioned
equipment. Submit to CxA for review and approval prior to startup. Refer to Section
01 91 13 for further details on start-up plan preparation.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 50 ▪
PART 26 PRODUCTS
26.01 TEST EQUIPMENT
A. Division 22 shall provide all test equipment necessary to fulfill the testing requirements of this
Division.
B. Refer to Section 01 91 13 for additional Division 22 requirements.
PART 27 EXECUTION
27.01 STARTUP
A. The plumbing contractor shall follow the start-up and initial checkout procedures listed in the
Responsibilities list in this Section and in Section 01 91 13. Division 22 has start-up
responsibility and is required to complete systems and sub-systems so they are fully
functional, meeting the design objectives of the Contract Documents. The commissioning
procedures and functional testing do not relieve or lessen this responsibility or shift that
responsibility partially to the commissioning agent or Owner.
B. Functional testing is intended to begin upon completion of a system. Functional testing may
proceed prior to the completion of systems or sub-systems at the discretion of the CxA and
GC. Beginning system testing before full completion does not relieve the Contractor from fully
completing the system, including all prefunctional checklists as soon as possible.
27.02 FUNCTIONAL PERFORMANCE TESTS
A. Refer to Section 01 91 13 for a list of systems to be commissioned and to Section 01 91 13,
Article 3.06 “Documentation, Non-Conformance and Approval Of Tests” for a description of
the process and to Sections 22 08 00 through 22 08 00.03 for specific details on the required
functional performance tests.
27.03 TESTING DOCUMENTATION, NON-CONFORMANCE AND APPROVALS
A. Refer to Section 01 91 13 for specific details on non-conformance issues relating to
prefunctional checklists and tests.
B. Refer to Section 01 91 13 for issues relating to functional performance tests.
27.04 DEFERRED TESTING
A. Refer to Section 01 91 13 for requirements of deferred testing.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 51 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 52 ▪
PART 28 GENERAL
28.01 SUMMARY
A. This Section includes the following:
1. This Section specifies the functional testing requirements for Division 22 systems and
equipment.
B. Related Sections:
1. Section 01 91 13 – General Commissioning Requirements.
2. Section 22 08 00 – Commissioning of Plumbing
3. Section 22 08 00.02 – Plumbing Prefunctional Checklists
4. Section 22 08 00.03 – Plumbing Sample Functional Test Procedures
28.02 INCLUDED SYSTEMS AND EQUIPMENT
A. The following is a list of the equipment and system test requirements included in this section:
1. Fuel Fired Domestic Water Heaters
2. Domestic Water Pumps
3. Plumbing Fixtures
4. Sump Pumps
28.03 DESCRIPTION
A. This Section specifies the functional testing requirements for Division 22 systems and
equipment. From these requirements, the Commissioning Authority (CxA) shall develop step-
by-step procedures to be executed by the Subcontractors or the Commissioning Authority.
The general functional testing process, requirements and test method definitions are
described in Section 01 91 13. The test requirements for each piece of equipment or system
contain the following:
1. The contractors responsible to execute the tests, under the direction of the CxA.
2. A list of the integral components being tested.
3. Prefunctional checklists associated with the components.
4. Functions and modes to be tested.
5. Required conditions of the test for each mode.
6. Special procedures.
7. Required methods of testing.
8. Required monitoring.
9. Acceptance criteria.
10. Sampling strategies allowed.
28.04 PREREQUISITES
A. The following applicable generic prerequisite checklist items are listed on each written
functional test form and shall be completed and checked off by CxA prior to functional testing:
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 53 ▪
PART 29 PRODUCTS
Not Used.
PART 30 EXECUTION
30.01 DOMESTIC HOT WATER SYSTEM
A. Parties Responsible to Execute Functional Test
1. Plumbing contractor or vendor: assist in testing sequences, correct deficiencies.
2. CxA: perform and document testing.
3. Owners Representative:witness
B. Integral Components or Related Equipment Being Tested Prefunctional Checklist
1. Hot water heaters (heaters, mixing valves, Domestic Hot Water System circulating
pumps, recirculation pumps).
C. Prerequisites: The applicable prerequisite checklist items listed in the beginning of Section
22 08 00.01 shall be listed on each functional test form and checked off prior to functional
testing. The commissioning agent will also spot-check misc. items and calibrations on the
prefunctional checklists previously completed by the installer, before the beginning of
functional testing.
D. Functions / Modes Required To Be Tested, Test Methods and Seasonal Test Requirements
1. The following testing requirements are in addition to and do not replace any testing
requirements elsewhere in this Division.
1.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 54 ▪
E. Special Procedures
1. None
F. Required Monitoring
1. None
G. Acceptance Criteria (referenced by function or mode ID)
1. 1 - 5. For the conditions, sequences and modes tested, the fan’s integral components
and related equipment respond to changing conditions and parameters appropriately as
expected, as specified and according to acceptable operating practice.
H. Sampling Strategy for Identical Units
1. No sampling. Test all units.
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 55 ▪
PART 31 GENERAL
31.01 SUMMARY
A. This Section includes the following:
1. Prefunctional Checklists (PC) in a form format. The Prefunctional Checklists consist of
Instructions Sheets and Record Sheets.
B. Related Sections:
1. Section 01 33 00 - Submittal and Substitution Procedures
2. Section 01 91 13 – General Commissioning Requirements.
3. Section 22 08 00 – Commissioning of Plumbing
4. Section 22 08 00.01 – Plumbing Testing Requirements
5. Section 22 08 00.03 – Plumbing Sample Functional Test Procedures
31.02 DESCRIPTION
A. The PC procedures displayed in a form format here are intended to provide the Contractor
with an example of the format and an indication of the rigor of the required prefunctional
checklists (Instruction Sheets and Record Sheets) and documentation for various equipment
types. Though they were not developed specifically for this project, they are generally
applicable.
B. The checklists contain items for both Division 22 and 26 contractors to perform.
C. Those executing the checklists are only responsible to perform items that apply to the specific
application at hand. These checklists do not take the place of the manufacturer’s
recommended checkout and start-up procedures or report. Some checklist procedures may
be redundant of some checkout procedures that will be documented on typical factory field
checkout sheets. Double documenting is required in those cases.
D. Refer to Section 01 91 13 for additional requirements regarding prefunctional checklists,
startup and initial checkout. Items that do not apply should be noted along with the reasons
on the form. If supplied Prefunctional Checklist forms are not used for documenting, one of
similar rigor and clarity shall be used. Contractors assigned responsibility for sections of the
checklist shall be responsible to see that checklist items by their subcontractors are completed
and checked off.
E. The following is a list of the equipment and systems which will require Prefunctional Checklists
(Instruction Sheets and Record Sheets) to be completed by the Contractors.
1. Fuel Fired Domestic Water Heaters
2. Domestic Water Pumps
3. Plumbing Fixtures
4. Sump Pumps
F. Refer to Section 01 33 00 - Submittal and Substitution Procedures for Prefunctional
Checklists.
PART 32 PRODUCTS
Not Used
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 56 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 57 ▪
PART 34 GENERAL
34.01 SUMMARY
A. This Section includes the following:
1. This Section contains the Functional Testing Procedures for Plumbing Systems
B. Related Sections:
1. Section 01 33 00 - Submittal and Substitution Procedures
2. Section 01 91 13 – General Commissioning Requirements.
3. Section 22 08 00 – Commissioning of Plumbing
4. Section 22 08 00.01 – Plumbing Testing Requirements
5. Section 22 08 00.02 – Plumbing Prefunctional Checklists
34.02 DESCRIPTION
A. The CxA will use the functional testing requirements in Sections 22 08 00 thru 22 08 00.03
and the testing protocols specified in Section 01 91 13 for developing site-specific functional
test procedures and forms for this project. For illustrative purposes, sequences of operation
associated with a few pieces of the equipment for which tests are included are also provided.
B. The following is a list of the equipment and systems which will require Prefunctional Checklists
(Instruction Sheets and Record Sheets) to be completed by the Contractors.
1. Fuel Fired Domestic Water Heaters
2. Domestic Water Pumps
3. Plumbing Fixtures
4. Sump Pumps
C. Refer to Section 01 33 00 - Submittal and Substitution Procedures for Prefunctional
Checklists.
PART 35 PRODUCTS
Not Used
PART 36 EXECUTION
Not Used
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 58 ▪
PART 37 GENERAL
37.01 SUMMARY
A. Section Includes:
1. Pipe and Tube Materials.
2. Fittings.
3. Joining Materials.
4. Polyethylene Encasement.
B. Related Sections:
1. Section 22 05 00 (15050) – Common Work Results for Plumbing
2. Section 22 05 29 (15060) - Hangers and Supports for Plumbing Piping and Equipment
3. Section 22 05 23 (15110) – General Duty Valves for Plumbing Piping
4. Section 22 05 19 (15122) - Meters and Gages for Plumbing Piping.
5. Section 22 10 03 (15430) - Plumbing Specialties
6. Section 31 20 00 (02300) - Earthwork
7. Section 33 00 00 (02500) - Utility Services: for exterior water service piping.
37.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B1.20.1 "Pipe Threads, General Purpose, Inch"
2. B16.18 “Cast Copper Alloy Solder Joint Pressure Fittings”
3. B16.22 “Wrought Copper and Copper Alloy Solder Joint Pressure Fittings”
4. B16.24 “Cast Copper Alloy Pipe Flanges and Flanged Fittings: Classes 150, 300, 400,
600, 900, 1500 and 2500”
5. B31.9 “Building Services Piping”
B. ASTM International (ASTM) Publications:
1. A47 "Standard Specification for Ferritic Malleable Iron Castings"
2. A536 "Standard Specification for Ductile Iron Castings"
3. A674 “Standard Practice for Polyethylene Encasement for Ductile Iron Pipe for Water or
Other Liquids”
4. B32 "Standard Specification for Solder Metal"
5. B75 “Standard Specification for Seamless Copper Tube”
6. B88 “Standard Specification for Seamless Copper Water Tube”
7. B584 “Standard Specification for Copper Alloy Sand Castings for General Applications”
8. D1785 “Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40,
80, and 120”
9. F437 “Standard Specification for Threaded Chlorinated Poly(Vinyl Chloride) (CPVC)
Plastic Pipe Fittings, Schedule 80”
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 59 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 60 ▪
PART 38 PRODUCTS
38.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. CVPC Piping:
a. None
B. Approved Manufacturers:
1. CPVC Piping:
a. “Flowguard Gold”; Lubrizol (440-943-4200)
b. “Corzam”; Lubrizol (440-943-4200)
c. Spears Manufacturing; (800-862-1499)
38.02 PIPE AND TUBE MATERIALS
A. General: Applications of the following pipe and tube materials are indicated in Part 3 "Piping
Applications" Article.
B. Soft Copper Tube: ASTM B88, Types K and L, water tube, annealed temper.
C. Hard Copper Tube: ASTM B88, Types L, water tube, drawn temper.
D. Ductile-Iron Pipe: AWWA C151, 250-psig minimum pressure rating with mechanical- or push-
on-joint bell, plain spigot end, and AWWA C104 cement-mortar lining. Include AWWA C111
ductile-iron gland, rubber gasket, and steel bolts with mechanical-joint pipe. Include
AWWA C111 rubber gasket with push-on-joint pipe.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 61 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 62 ▪
PART 39 EXECUTION
39.01 EXCAVATION
A. Refer to Section 31 20 00 - "Earth Moving" for excavating, trenching, and backfilling.
39.02 PIPING APPLICATIONS
A. Transition and special fittings with pressure ratings at least equal to piping pressure rating
may be used in applications below, unless otherwise indicated.
B. Flanges may be used on aboveground piping, unless otherwise indicated.
C. Fitting Option: Mechanically formed tee-branch outlets and brazed joints may be used on
aboveground copper tubing.
D. Underground, Service Entrance Piping: Do not use flanges or valves underground. Use the
following:
1. 2-Inch NPS (DN50) and Smaller: Soft copper tube, Type K (Type A); copper, solder-joint
pressure fittings; and soldered joints.
2. 2-1/2- to 3-1/2-Inch NPS (DN65 to DN90): Soft copper tube, Type K (Type A); copper,
solder-joint pressure fittings; and soldered joints.
3. 4- to 8-Inch NPS (DN100 to DN200): Ductile-iron pipe and fittings, and mechanical or
push-on joints.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 63 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 64 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 65 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 66 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 67 ▪
PART 40 GENERAL
40.01 SUMMARY
A. Section Includes:
1. Packaged Domestic Water Booster Pumps
B. Related Sections:
1. Section 01 81 13 - Sustainable Design Requirements
2. Section 03 30 00 (03300) - Cast-in-Place Concrete: for concrete bases.
3. Section 21 10 00 (13900) - Fire Suppression Systems: for fire-suppression pumps.
4. Section 22 05 00 (15050) – Common Work Results for Plumbing
5. Section 22 05 13 (15090) – Common Motor Requirements for Plumbing Equipment: for
general motor requirements.
6. Section 22 05 23 (15110) – General Duty Valves for Plumbing Piping
7. Section 22 11 16 (15140) - Domestic Water Piping
8. Section 22 11 23 (15440) - Domestic Water Pumps
40.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B31.9 “Building Services Piping”
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and Seamless"
2. B88 “Standard Specification for Seamless Copper Water Tube”
3. B584 “Standard Specification for Copper Alloy Sand Castings for General Applications”
C. Hydraulic Institute (HI) Publications:
1. ANSI/HI 1.1-1.5 “Centrifugal Pumps Nomenclature, Definitions, Applications and
Operation”
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 68 ▪
PART 41 PRODUCTS
41.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Packaged Domestic Water Booster Pumps:
a. None
B. Approved Manufacturers:
1. Packaged Domestic Water Booster Pumps:
a. Aurora Pump (630-859-7000)
b. Peerless Pump Co. (800-879-0182)
c. SynchroFlo, Inc. (770-447-4443)
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 69 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 70 ▪
PART 42 EXECUTION
42.01 EXAMINATION
A. Examine roughing-in of water distribution piping to verify actual locations of connections
before packaged booster pump installation.
42.02 CONCRETE
A. Install concrete bases of dimensions indicated for packaged booster pumps. Refer to Section
03 30 00 - "Cast-in-Place Concrete" and Section 22 05 00 - "Common Work Results for
Plumbing."
42.03 INSTALLATION
A. Install packaged booster pumps according to manufacturer's written instructions and with
access for periodic maintenance, including removing motors, impellers, couplings, and
accessories.
1. Install units with total of 7.5 hp or less, with rubber-isolator mount or spring-isolator
vibration isolators.
2. Install units with total of more than 7.5 hp, with concrete-filled, inertia-base vibration
isolation bases and spring-isolator vibration isolators.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 71 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 72 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 73 ▪
PART 43 GENERAL
43.01 SUMMARY
A. Section Includes:
1. Domestic Water Inline Pumps
B. Related Sections:
1. Section 22 05 23 - General Duty Valves for Plumbing Piping
2. Section 22 05 19 - Meters and Gages for Plumbing Piping
3. Section 22 11 16 - "Domestic Water Piping
4. Section 22 11 23.13 (15444) - Domestic Water Packaged Booster Pumps: for booster
systems.
5. Section 22 34 00 (15486) – Fuel-Fired Domestic Water Heaters.
6. Division 26 Sections for power-supply wiring, field-installed disconnects, electrical
devices, and motor controllers.
43.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. B36 “Standard Specification for Brass Plate, Sheet, Strip, And Rolled Bar”
2. B584 “Standard Specification for Copper Alloy Sand Castings for General Applications”
B. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
C. Underwriter's Laboratories, Inc. (UL) Standards:
1. 486A “Standard For Wire Connectors and Soldering Lugs for Use With Copper
Conductors”
2. 486B “Standard for Wire Connectors for Use With Aluminum Conductors”
3. 778 “Standard for Motor-Operated Water Pumps”
43.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections:
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data:
a. Include certified performance curves and rated capacities of selected models;
shipping, installed, and operating weights; furnished specialties; and accessories for
each type and size of pump specified. Indicate pumps' operating point on curves.
2. Maintenance Data: For each pump specified to include in maintenance manuals
specified in Division 01.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 74 ▪
PART 44 PRODUCTS
44.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Domestic Water Inline Pumps:
a. Grundfos (913-227-3400)
b. Armstrong Pumps, Inc. (716-693-8813)
c. ITT Industires (201-760-9800)
d. Taco, Inc. (401-942-2360)
44.02 GENERAL
A. Description: Factory-assembled and -tested, single-stage, centrifugal pump units; complying
with UL 778; suitable for potable-water service; with all-bronze or stainless-steel construction
and components in contact with water made of corrosion-resistant materials.
B. Motors: Comply with requirements in Section 22 05 13 "Common Motor Requirements for
Plumbing Equipment" with built-in thermal-overload protection appropriate for motor size and
duty.
C. End Connections for NPS 2 (DN50) and Smaller: Threaded. Pumps available only with
flanged ends may be furnished with threaded companion flanges.
D. End Connections for NPS 2-1/2 (DN65) and Larger: Flanged.
E. Finish: Manufacturer's standard paint applied to factory-assembled and -tested units before
shipping.
F. Manufacturer's Preparation for Shipping: Clean flanges and exposed machined metal
surfaces and treat with anticorrosion compound after assembly and testing. Protect flanges,
pipe openings, and nozzles.
44.03 DOMESTIC WATER IN-LINE PUMPS
A. Description: Horizontal in-line circulator, rated for 125-psig minimum working pressure and
minimum continuous water temperature of 225 deg F.
1. Construction: Radially split, all-bronze casing.
2. Impeller: ASTM B36, rolled brass; or ASTM B584, cast bronze; overhung, single suction,
and keyed to shaft.
3. Seal: Mechanical.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 75 ▪
PART 45 EXECUTION
45.01 EXAMINATION
A. Examine roughing-in of water distribution piping to verify actual locations of connections
before pump installation.
45.02 INSTALLATION
A. Install pumps according to manufacturer's written instructions and with access for periodic
maintenance, including removing motors, impellers, couplings, and accessories.
B. Support pumps and piping so weight of each is not supported by the other.
45.03 CONNECTIONS
A. Piping installation requirements are specified in other Division 22 Sections. Drawings indicate
general arrangement of piping and specialties. The following are specific connection
requirements:
1. Connect water distribution piping to pumps. Install suction and discharge pipe equal to or
greater than size of pump nozzles. Refer to Section 22 11 16 - "Domestic Water Piping."
2. Install shutoff valve and strainer on suction side of pumps, and check valve and throttling
valve on discharge side of pumps. Install valves same size as connected piping. Refer
to Section 22 05 23 - "General Duty Valves for Plumbing Piping" for general-duty valves.
3. Install pressure gages at suction and discharge of pumps. Install at integral pressure-
gage tappings where provided or install pressure-gage connectors in suction and
discharge piping around pumps. Refer to Section 22 05 19 - "Meters and Gages for
Plumbing Piping" for pressure gages and gage connectors.
B. Electrical wiring and connections are specified in Division 26 Sections.
C. Ground equipment.
1. Tighten electrical connectors and terminals according to manufacturer's published
torque-tightening values. If manufacturer's torque values are not indicated, use those
specified in UL 486A and UL 486B.
45.04 COMMISSIONING
A. Check suction piping connections for tightness.
B. Final Checks before Starting: Perform the following preventive maintenance operations:
1. Lubricate oil-lubricated-type bearings.
2. Verify that pump is free to rotate by hand and that pump for handling hot liquids is free to
rotate with pump hot and cold. Do not operate pump if it is bound or drags, until cause of
trouble is determined and corrected.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 76 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 77 ▪
PART 46 GENERAL
46.01 SUMMARY
A. Section Includes:
1. Pipe Materials.
2. Fittings.
3. Joining Materials.
B. Related Sections:
Note: Edit list below to suit Project.
1. Section 07 84 00 (07840) - Firestopping: for fire-barrier sealers.
2. Section 08 31 00 (08310) - Access Doors: for access panels to concealed components.
3. Section 09 90 00 (09900) - Painting: for field-applied finishes for piping.
4. Section 11 31 00 (11450) -Residential Appliances: for drainage and vent services for
clothes washers.
5. Section 11 40 00 (11400) - Food Service Equipment: for drainage and vent services for
food service equipment.
6. Section 22 05 00 (15050) – Common Work Results for Plumbing
7. Section 22 05 29 (15060) - Hangers and Supports for Plumbing Piping and Equipment
8. Section 22 05 53 (15075) – Identification for Plumbing Piping and Equipment.
9. Section 22 07 00 (15083) - Plumbing Insulation.
10. Section 22 30 00 (15430) - Plumbing Equipment.
11. Section 22 40 00 (15410) - Plumbing Fixtures.
12. Section 31 20 00 (02300) – Earth Moving: for excavating, trenching, and backfilling.
13. Section 33 00 00 (02500) - Utilities
14. Section 33 46 00 (02620) - Subdrainage
46.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B31.9 “Building Services Piping”
2. B16.1 “Cast Iron Pipe Flanges and Flanged Fittings”
3. B16.4 “Gray Iron Threaded Fittings: (Classes 125 and 250)”
4. B16.12 “Cast Iron Threaded Drainage Fittings”
5. B16.23 “Cast Copper Alloy Solder Joint Drainage Fittings: DWV”
6. B16.29 “Wrought Copper and Wrought Copper Alloy Solder Joint Drainage Fittings-DWV”
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A48 "Standard Specification for Gray Iron Castings"
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 78 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 79 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 80 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 81 ▪
PART 48 EXECUTION
48.01 EXCAVATION
A. Refer to Section 31 20 00 - "Earth Moving" for excavating, trenching, and backfilling.
48.02 PIPING APPLICATIONS
A. Transition and special fittings with pressure ratings at least equal to piping pressure rating
may be used in applications below, unless otherwise indicated.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 82 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 83 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 84 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 85 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 86 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 87 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 88 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 89 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 90 ▪
PART 49 GENERAL
49.01 SUMMARY
A. Section Includes:
1. Backflow Preventers
2. Water Regulators
3. Thermostatic Mixing Valves
4. Clothes Washer Drain & Supply
5. Hydrants
6. Trap Primer Valves
7. Drain Valves
8. Backwater Valves
9. Floor Drains
10. Roof Drains
11. Grease Interceptors
12. Oil Interceptors
13. Lint Interceptors
14. Miscellaneous Piping Specialties
B. Related Sections:
1. [Section 07 31 13 (07311) - Asphalt Shingles]
2. [Section 07 61 00 (07610) - Sheet Metal Roofing]
3. [Section 07 53 23 (07530) - Ethylene-Propylene-Diene-Monomer (EPDM) Roofing]
4. [Section 07 62 00 (07620) - Sheet Metal Flashing and Trim]
5. Section 22 05 00 (15050) – Common Work Results for Plumbing
6. Section 22 05 23 (15110) – General Duty Valves for Plumbing Piping
7. Section 22 05 53 (15075) – Identification for Plumbing Piping and Equipment: for labeling
and identifying requirements.
8. Section 22 05 19 (15122) - Meters and Gages for Plumbing Piping
9. Section 22 11 16 (15140) - Domestic Water Piping
10. Section 22 13 16 (15150) - Drainage and Vent Piping
11. Section 22 40 00 (15410) – Plumbing Fixtures and Plumbing Fixture Matrix
49.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. A112.1.2 “Air Gaps in Plumbing Systems (For Plumbing Fixtures and Water-Connected
Receptors)”
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 91 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 92 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 93 ▪
PART 50 PRODUCTS
50.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Backflow Preventers:
a. None
2. Water Regulators:
a. None
3. Thermostatic Water Mixing Valves:
a. None
4. Clothes Washer Drain & Supply
a. None
5. Hydrants:
a. None
6. Water Hammer Arresters:
a. None
7. Trap Seal Primer Valves:
a. None
8. Backwater Valves:
a. None
B. Approved Manufacturers:
1. Backflow Preventers:
a. Watts Water Technologies, Inc. (978-688-1811)
b. Zurn Industries, Inc.; Wilkins Div. (805-238-7100)
2. Water Regulators:
a. Conbraco Industries, Inc. (704-847-9191)
b. Watts Water Technologies, Inc. (978-688-1811)
c. Zurn Industries, Inc.; Wilkins Div. (805-238-7100)
3. Thermostatic Water Mixing Valves:
a. Lawler Manufacturing Co., Inc. (800-763-2709)
b. Leonard Valve Co. (401-461-1200)
c. Symmons Industries, Inc. (617-848-2250)
4. Clothes Washer Drain & Supply
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 94 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 95 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 96 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 97 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 98 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 99 ▪
PART 51 EXECUTION
51.01 PLUMBING SPECIALTY INSTALLATION
A. General:
1. Install plumbing specialty components, connections, and devices according to
manufacturer's written instructions.
2. Install expansion joints on vertical risers, stacks, and conductors as indicated.
3. Fasten wall-hanging plumbing specialties securely to supports attached to building
substrate if supports are specified and to building wall construction if no support is
indicated.
4. Fasten recessed, wall-mounting plumbing specialties to reinforcement built into walls.
5. Secure supplies to supports or substrate.
6. Install traps on plumbing specialty drain outlets. Omit traps on indirect wastes unless
trap is indicated.
7. Locate drainage piping as close as possible to bottom of floor slab supporting fixtures
and drains.
8. Install escutcheons at wall, floor, and ceiling penetrations in exposed finished locations
and within cabinets and millwork. Use deep-pattern escutcheons if required to conceal
protruding pipe fittings.
9. Include wood-blocking reinforcement for recessed and wall-mounting plumbing
specialties.
B. Backflow Preventers:
1. Install backflow preventers of type, size, and capacity indicated, at each water-supply
connection to mechanical equipment and systems, and to other equipment and water
systems as indicated. Comply with authorities having jurisdiction. Locate backflow
preventers in same room as connected equipment. Install air-gap fitting on units with
atmospheric-vent connection and pipe relief outlet drain to nearest floor drain. Do not
install bypass around backflow preventer.
C. Pressure Regulators:
1. Install pressure regulators with inlet and outlet shutoff valves and balance valve bypass.
Install pressure gages on inlet and outlet. Refer to Section 22 05 19 - “Meters and
Gauges for Plumbing Piping”.
D. Hose Bibbs:
1. Install hose bibbs with integral or field-installed vacuum breaker.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 100 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 101 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 102 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 103 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 104 ▪
PART 52 GENERAL
52.01 SUMMARY
A. Section Includes:
1. Commercial Water Softeners
2. Chemicals
3. Water Testing Sets
B. Related Sections:
1. Section 22 07 00 (15083) - Pipe Insulation: for softener-piping insulation.
52.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. ASME
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. D859 "Test Method for Silica in Water"
2. D1067 "Test Methods for Acidity or Alkalinity of Water"
3. D1068 "Test Methods for Iron in Water"
4. D1126 "Test Method for Hardness in Water"
5. D1129 "Terminology Relating to Water"
6. D3370 "Practices for Sampling Water from Closed Conduits"
C. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
D. NFS International (NFS) Publications:
1. NSF/ANSI 44 "Residential Cation Exchange Water Softeners"
2. NSF/ANSI 61 "Drinking Water System Components--Health Effects"
E. Underwriter's Laboratories, Inc. (UL) Standards:
1. 486A “Standard For Wire Connectors and Soldering Lugs for Use With Copper
Conductors”
2. 486B “Standard for Wire Connectors for Use With Aluminum Conductors”
52.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections:
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data:
a. Include rated capacities; shipping, installed, and operating weights; ion-exchange
resins; salt purity and form; furnished specialties; and accessories.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 105 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 106 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 107 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 108 ▪
PART 54 EXECUTION
54.01 CONCRETE BASES
A. Install concrete bases of dimensions indicated for equipment. Refer to Section 03 30 00
(03300) - "Cast-in-Place Concrete" and Section 21/22/23 95 00 (15050) "Basic Mechanical
Materials and Methods."
54.02 WATER SOFTENER INSTALLATION
A. Install water softener equipment on concrete bases, level and plumb, according to
manufacturer's written instructions, layout drawings, original design, and referenced
standards. Maintain manufacturer's recommended clearances. Arrange units so controls and
devices needing servicing are accessible.
B. Anchor tanks and floor-mounting accessories to substrate.
C. Install seismic restraints for tanks and floor-mounting accessories and anchor to substrate
(where required).
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 109 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 110 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 111 ▪
PART 55 GENERAL
55.01 SUMMARY
A. Section Includes:
1. Gas fired water heaters.
2. Storage tanks.
3. Expansion tanks.
4. Accessories.
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-in-Place Concrete
2. Section 22 05 00 (15050) – Common Work Results for Plumbing
3. Section 22 05 23 (15110) – General Duty Valves for Plumbing Piping
4. Section 22 05 19 (15122) - Meters and Gages for Plumbing Piping
5. Section 22 11 23 (15440) – Domestic Water Pumps
6. Section 22 30 00 (15430) - Plumbing Equipment
7. Section 22 51 00 (15550) - Breechings, Chimneys, and Stacks
55.02 REFERENCES
A. American National Standards Institute (ANSI) Publications:
1. Z21.10.3 “Gas Water Heaters - Volume III, Storage Water Heaters with Input Ratings
Above 75,000 Btu per Hour, Circulating and Instantaneous”
2. Z21.13 “Gas-Fired Low Pressure Steam and Hot Water Boilers”
3. Z21.15 “Manually Operated Gas Valves for Appliances, Appliance Connector Valves and
Hose End Valves”
4. Z21.18 “Gas Appliance Pressure Regulators”
5. Z21.20 “Automatic Gas Ignition Systems and Components”
6. Z21.21 “Automatic Valves for Gas Appliances (same as CSA 6.5)”
7. Z21.22 “Relief Valves for Hot Water Supply Systems”
B. American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE)
Publications:
1. 90.1 “Energy Code for Commercial and High-Rise Residential Buildings”
2. 90.2 “Energy Code for New Low-Rise Residential Buildings”
C. The American Society of Mechanical Engineers (ASME) Publications:
1. “(The 2004) ASME Boiler and Pressure Vessel Code”
2. B1.20.1 "Pipe Threads, General Purpose, Inch"
3. B16.5 “Pipe Flanges and Flanged Fittings: NPS 1/2 through 24”
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 112 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 113 ▪
PART 56 PRODUCTS
56.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Gas Fired Water Heaters: (Power Vent, Storage Type)
a. None
2. Gas Fired Water Heaters: (High Efficiency, Separated Combustion)
a. None
3. Expansion Tanks:
a. None
B. Approved Manufacturers
1. Gas Fired Water Heaters: (Power Vent, Storage Type)
a. Lochinvar Corporation. (615-889-8900)
b. A. O. Smith Water Products Co. (800-527-1953)
2. Gas Fired Water Heaters: (High Efficiency, Separated Combustion)
a. Lochinvar Corporation. (615-889-8900)
b. A. O. Smith Water Products Co. (800-527-1953)
c. Raypak, Inc., a Rheem Company (805-278-5300)
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 114 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 115 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 116 ▪
PART 57 EXECUTION
57.01 CONCRETE BASES
A. Install concrete bases of dimensions indicated. Refer to Section 03 30 00 "Cast-in-Place
Concrete" and Section 22 05 00 - "Common Work Results for Plumbing."
57.02 WATER HEATER INSTALLATION
A. Install commercial water heaters on concrete bases.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 117 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 118 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 119 ▪
PART 58 GENERAL
58.01 SUMMARY
A. Section Includes:
1. Plumbing Fixture Standards
2. Miscellaneous Fixture Standards
3. Miscellaneous Component Standards
B. Related Sections:
1. Section 07 92 00 (07920) - Joint Sealant: For sealing between fixtures and walls, floors,
and counters.
2. Section 22 05 00 (15050) – Common Work Results for Plumbing
3. Section 22 05 23 (15110) – General Duty Valves for Plumbing Piping
4. Section 22 30 00 (15430) - Plumbing Equipment
58.02 REFERENCES
A. American National Standards Institute (ANSI) Publications:
1. A117.1 “Accessible and Useable Buildings and Facilities”
2. Z124.1 “Plastic Bathtub Units”
3. Z124.1a, and Z124.1b
4. Z124.5 “Plastic Toilet (Water Closet) Seats”
5. Z124.6 “Plastic Sinks”
6. Z358.1 “Emergency Eyewash and Shower Equipment”
B. Air-Conditioning and Refrigeration Institute (ARI) Publications:
1. 1010 “Self-Contained, Mechanically Refrigerated Drinking-Water Coolers”
C. The American Society of Mechanical Engineers (ASME) Publications:
1. A112.6.1.M “Floor Affixed Supports for Off-the-Floor Plumbing Fixtures for Public Use”
2. A112.18.1 “Plumbing Fixture Fittings”
3. A112.19.2 “Vitreous China Plumbing Fixtures and Hydraulic Requirements for Water
Closets and Urinals”
4. A112.19.3 “Stainless Steel Fixtures (Designed for Residential Use)”
5. A112.19.4M “Porcelain Enameled Formed Steel Plumbing Fixtures”
6. A112.19.5 “Trim for Water-Closet Bowls, Tanks and Urinals”
7. A112.19.8M “Suction Fittings for Swimming & Wading Pools Spas Hot Tubs & Whirlpool
Bathtub Appliances”
8. A112.21.1M “Floor Drains”
9. B1.20.1 "Pipe Threads, General Purpose, Inch"
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 120 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 121 ▪
PART 59 PRODUCTS
59.01 MANUFACTURERS
A. See Plumbing Fixture Matrix for list of which Manufacturer's are approved for use on a
specific item.
B. Approved Manufacturers:
1. American Standard, Inc. (800-442-1902)
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 122 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 123 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 124 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 125 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 126 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 127 ▪
PART 60 EXECUTION
60.01 EXAMINATION
A. Examine roughing-in for potable, hot- and cold-water supply piping systems; soil, waste, and
vent piping systems; and supports. Verify that locations and sizes of piping and locations and
types of supports match those indicated, before installing and connecting fixtures. Use
manufacturer's roughing-in data when roughing-in data are not indicated.
B. Examine walls, floors, and cabinets for suitable conditions where fixtures are to be installed.
C. Do not proceed until unsatisfactory conditions have been corrected.
60.02 APPLICATIONS
A. Include supports for plumbing fixtures according to the following:
1. Carriers: For wall-hanging water closets and fixtures supported from wall construction.
2. Chair Carriers: For wall-hanging urinals, lavatories, sinks, drinking fountains, and electric
water coolers.
3. Heavy-Duty Chair Carriers: For accessible urinals, lavatories, and other fixtures where
indicated.
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 128 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 129 ▪
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 130 ▪
END OF SECTION
Revision Log
▪ DIVISION 22 PLUMBING ▪
▪ PAGE 131 ▪
TUB-06
NOTE-A Refer to Section 06 61 13 and "Tub and
Shower Surround Product Manual" for
Tub Surrounds
BATHTUB (A)
TUB- "Princeton Recess Bath" 2391.202.020 (R) or White American Standard Companies Inc.
BTB01A 60" x 30" x 14" 2390.202.020 (L)
TUB- "Align" Bath/Shower Trim Kit with T2193NHHC/62370 Chrome Moen Incorporated
TRM14M shower arm and flange for Fixed (Polished)
Shower Head w/ red/blue Index w/
Diverter Tub Spout and Pressure
Balance Valve / Less showerhead
TUB- "Compel" Series Tub/Shower Trim with T14661-LHD & Chrome Delta Faucet Company
TRM14D shower arm and flange for Fixed R10000-UNWS (Polished)
Shower Head w/ red/blue Index / with
Tub Spout and Pressure Balance Valve
/ Less showerhead
TUB- "Parma" Series Single Handle D510058LST & Chrome Danze, a brand of Globe Union
TRM14G Tub/Shower Trim with Diverter on Valve D113000BT-SS (Polished) Branded Products
w/ shower arm and flange for Fixed
Shower Head w/ red/blue Index w/ Tub
Spout and Pressure Balance Valve /
Less showerhead
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
TUB- "Clearflo" Bathtub Drain with Overflow 7160-AF-CP Chrome Kohler Company
DR01K (Polished)
TUB- "Lift & Turn Bath Waste with Overflow" 1221LAT Chrome McGuire Mfg. Co., Inc.
DR02Mc (Polished)
TUB- "Lift & Turn Bath Drains" 41-852 Chrome Gerber Plumbing Fixtures, a brand
DR02G (Polished) of Globe Union Branded Products
SHOWER HEADS - WALL MOUNT
NOTE- THERE ARE THREE (3) FLOW RATE
CATEGORIES OF SHOWER HEADS
LISTED BELOW.
SELECT ONLY ONE OF THE
CATEGORIES AND DELETE THE
CATEGORIES NOT USED FOR THE
PROJECT.
2.5 GPM SHOWER HEAD - WALL MOUNT (D1)
NOTE- RECOMMENDED GPM FOR
OPTIMUM GUEST SATISFACTION
AND SHOWERING EXPERIENCE.
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
TUB- "Grail Series Touch Clean" RP48590 Chrome Delta Faucet Company
SHR10D Multifunction Shower Head (Polished)
(3-Settings)
2.50 GPM
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
TUB- "H2O Kinetic Technology Touch Clean" 52638-20-PK Chrome Delta Faucet Company
SHR30D Multifunction Shower Head (Polished)
(5-Settings)
2.00 GPM (WaterSense Certified)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
TUB-07
NOTE-A Refer to Section 06 61 13 and "Tub and
Shower Surround Product Manual" for
Tub Surrounds
BATHTUB (A)
TUB- "Princeton Recess Bath" 2391.202.020 (R) or White American Standard Companies Inc.
BTB01A 60" x 30" x 14" 2390.202.020 (L)
TUB- "Align" Shower Trim Kit with shower arm T2193NHHC/62370 Chrome Moen Incorporated
TRM14M and flange for Fixed Shower Head w/ (Polished)
red/blue Index / with diverter Tub Spout
and Pressure Balance Valve / Less
showerhead
TUB- "Compel" Series Tub/Shower Trim with T14461-LHD & Chrome Delta Faucet Company
TRM14D shower arm and flange for Fixed R10000-UNWS & (Polished)
Shower Head w/ red/blue Index / with 50560
Tub Spout, supply elbow and Pressure
Balance Valve / Less showerhead
TUB- "Parma" Series Single Handle D510058LST & Chrome Danze, a brand of Globe Union
TRM14G Tub/Shower Trim with Diverter on Valve D113000BT-SS (Polished) Branded Products
w/ shower arm and flange for Fixed
Shower Head w/ red/blue Index w/ Tub
Spout and Pressure Balance Valve /
Less showerhead
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
TUB- "Clearflo" Bathtub Drain with Overflow 7160-AF-CP Chrome Kohler Company
DR01K (Polished)
TUB- "Pop-up Bath Waste with Overflow" 1221PU Chrome McGuire Mfg. Co., Inc.
DR01Mc (Polished)
TUB- "Pop-up Bath Drains" 41-802 Chrome Gerber Plumbing Fixtures, a brand
DR01G (Polished) of Globe Union Branded Products
SHOWER HEADS - HAND HELD
NOTE- THERE ARE TWO (2) FLOW RATE
CATEGORIES OF HAND HELD
SHOWER HEADS LISTED BELOW.
SELECT ONLY ONE OF THE
CATEGORIES AND DELETE THE
CATEGORIES NOT USED FOR THE
PROJECT.
2.5 GPM SHOWER HEAD - HAND HELD (D1)
NOTE- RECOMMENDED GPM FOR
OPTIMUM GUEST SATISFACTION
AND SHOWERING EXPERIENCE.
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
TUB- Hand Held Shower / Supply Elbow / 60" 180238/A726/A714/A7 Chrome Moen Incorporated
SHR20M metal shower hose. Provide In-Line 25 (Polished)
Vacuum Breaker for Hand held Shower
Head (By Trim Manufacturer).
(5-settings)
2.50 GPM
TUB- "Personal Hand Held Shower" / Supply 55020 Chrome Delta Faucet Company
SHR20D Elbow / 60" metal shower hose. (Polished)
Provide In-Line Vacuum Breaker for
Hand held Shower Head (By Trim
Manufacturer).
(5-settings)
2.50 GPM
TUB- "Neo Hand Held Shower" / Supply VS-3010 Chrome Speakman Company
SHR20S Elbow / 60" metal shower hose. (Polished)
Provide In-Line Vacuum Breaker for
Hand held Shower Head (By Trim
Manufacturer).
(50-settings)
2.50 GPM
ALTERNATE 2.0 GPM SHOWER HEAD - HAND
HELD (D2)
NOTE- 2.0 GPM FOR USE WHERE
REDUCED WATER CONSUMPTION
IS DESIRED.
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
TUB- "H2O Kinetic Technology Touch Clean" 59445-PK Chrome Delta Faucet Company
SHR40D Multifunction Handshower / Supply (Polished)
Elbow / 60" metal shower hose.
Provide In-Line Vacuum Breaker for
Hand held Shower Head (By Trim
Manufacturer).
(5-Settings)
2.00 GPM (WaterSense Certified)
TUB- "Neo Hand Held Shower" / Supply VS-3010-E2 Chrome Speakman Company
SHR40S Elbow / 60" metal shower hose. (Polished)
Provide In-Line Vacuum Breaker for
Hand held Shower Head (By Trim
Manufacturer).
(50-settings)
2.00 GPM (WaterSense Certified)
SHOWER HEAD - WALL MOUNT (E)
NOTE- Refer to Fixed Shower Heads listed Chrome
under TUB-06 (Polished)
BATH / SHOWER DIVERTER (F)
TUB- "Serin In-Wall Diverter Trim" with 3-way T064.430.002 & Chrome American Standard Companies Inc.
DV03A Diverter Valve (For Fixed to Handheld R430 (Polished)
Shower Head)
TUB- "Align In-Wall Diverter Trim" with 3-way 3360/T4192 Chrome Moen Incorporated
DV03M Diverter Valve (For Fixed to Handheld (Polished)
Shower Head)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
TUB- "Parma" Series 3-Function Diverter Trim D560958T & Chrome Danze, a brand of Globe Union
DV03G with Valve (For Fixed to Handheld D130000-SS (Polished) Branded Products
Shower Head)
TUB- Transfer Valve &"Dia" Trim (For Fixed Included with BATH / Chrome Symmons Industries Inc.
TRM15SY to Handheld Shower Head) SHOWER TRIM & (Polished)
VALVE (B)
SHR- Cast Marble Shower Base with integral TR-OS(L of R)-72x34 SC-CR MPL Corporation
SHB08M flanges, w/ Slip-resistant finish, offset Cream -
P Trench Drain with Brushed Nickel Matte Finish
Trench Drain Cover
(coordinate left or right).
72" x 34" x 4"
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SHR- "Align" Shower Trim Kit with shower arm T2192NHHC/62370 Chrome Moen Incorporated
TRM16M and flange for Fixed Shower Head w/ (Polished)
red/blue Index / with Pressure Balance
Valve / Less showerhead
SHR- "Compel" Series Shower Trim with T14261-LHD & Chrome Delta Faucet Company
TRM16D shower arm and flange for Fixed R10000-UNWS (Polished)
Shower Head w/ red/blue Index with
Pressure Balance Valve / Less
showerhead
SHR- "Parma" Series Single Handle Shower D510558LST & Chrome Danze, a brand of Globe Union
TRM16G Trim with shower arm and flange for D112000BT-SS (Polished) Branded Products
Fixed Shower Head w/ red/blue Index
with Pressure Balance Valve / Less
showerhead
SHR- "Dia" Round Shower Valve with red/blue CD0100-3501-CYL- Chrome Symmons Industries Inc.
TRM16SY Index / Arm & Flange for Fixed Shower L/HD-X & 86-1X-BODY (Polished)
Head / "Temptrol Pressure Balance
Mixing Valve / Less showerhead
SHOWER HEAD - WALL MOUNT (C)
NOTE- Refer to Fixed Shower Heads listed Chrome
under TUB-06 (Polished)
SHOWER DRAIN (D)
SHR- Shower Drain for use with Pre-formed K-9132 Chrome Kohler Company
DR03K shower base and with 2" caulking (Polished)
connection. (Verify connection type)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SHR- Cast Marble Shower Base with integral TR-OS(L of R)-66x34 SC-CR MPL Corporation
SHB09M flanges, w/ Slip-resistant finish, offset Cream -
P Trench Drain with Brushed Nickel Matte Finish
Trench Drain Cover
(coordinate left or right).
66" x 34" x 4"
SHOWER TRIM & VALVE (B)
SHR- "Serin Bath/Shower Trim Kit" with T064.501WDXH.002 & Chrome American Standard Companies Inc.
TRM16A shower arm and flange w/ red/blue R110SS (Polished)
Index / with Pressure Balance Valve
and Supply Elbow / Less showerhead
and spout
SHR- "Align" Shower Trim Kit with shower arm T2192NHHC/62370 Chrome Moen Incorporated
TRM16M and flange for Fixed Shower Head w/ (Polished)
red/blue Index / with Pressure Balance
Valve / Less showerhead
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SHR- "Parma" Series Single Handle Shower D510558LST & Chrome Danze, a brand of Globe Union
TRM16G Trim with shower arm and flange for D112000BT-SS (Polished) Branded Products
Fixed Shower Head w/ red/blue Index
with Pressure Balance Valve / Less
showerhead
SHR- "Dia" Round Shower Valve Trim with CD0100-3501-CYL- Chrome Symmons Industries Inc.
TRM16SY red/blue Index / Arm & Flange for Fixed L/HD-X & 86-1X-BODY (Polished)
Shower Head / "Temptrol" Pressure
Balance Mixing Valve / Less
showerhead
SHOWER HEAD - WALL MOUNT (C)
NOTE- Refer to Fixed Shower Heads listed Chrome
under TUB-06 (Polished)
SHOWER DRAIN (D)
SHR- Shower Drain for use with Pre-formed K-9132 Chrome Kohler Company
DR03K shower base and with 2" caulking (Polished)
connection. (Verify connection type)
SHR- Shower Drain for use with Pre-formed 42150 Chrome Oatey
DR03O shower base and with 2" caulking (Polished)
connection. (Verify connection type)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SHR- Cast Marble Roll-In Shower Base with RISHP-3162 SC-CR MPL Corporation
SHB06M integral fiberglass flanges, w/ Slip- Cream -
P resistant finish, Center drain Matte Finish
62" (60" Clear) x 31" x 1-1/2" (at
entrance)
SHOWER TRIM & VALVE (B)
SHR- "Serin Bath/Shower Trim Kit" with T064.501WDXH.002 & Chrome American Standard Companies Inc.
TRM16A shower arm and flange w/ red/blue R110SS (Polished)
Index / with Pressure Balance Valve
and Supply Elbow / Less showerhead
and spout
SHR- "Align" Shower Trim Kit with shower arm T2192NHHC/62370 Chrome Moen Incorporated
TRM16A and flange for Fixed Shower Head w/ (Polished)
red/blue Index / with Pressure Balance
Valve / Less showerhead
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SHR- "Parma" Series Single Handle Shower D510558LST & Chrome Danze, a brand of Globe Union
TRM16G Trim with shower arm and flange for D112000BT-SS (Polished) Branded Products
Fixed Shower Head w/ red/blue Index
with Pressure Balance Valve / Less
showerhead
SHR- "Dia" Shower Valve Trim Only with CD0100-3505-CYL-X Chrome Symmons Industries Inc.
TRM17SY red/blue Index / Arm & Flange for Fixed & 86-2X-BODY & 4- (Polished)
Shower Head / Less showerhead / 458-E BODY
"Temptrol Pressure Balance Mixing
Valve & Diverter Valve / (Use w/
Speakman or Kohler Shower Head Unit
below)
BATH / SHOWER DIVERTER (C)
SHR- "Serin In-Wall Diverter Trim" with 3-way T064.430.002 & Chrome American Standard Companies Inc.
DV03A Diverter Valve (For Fixed to Handheld R430 (Polished)
Shower Head)
SHR- "Align" In-Wall Diverter Trim" with 3-way 3360/T4192 Chrome Moen Incorporated
DV03A Diverter Valve (For Fixed to Handheld (Polished)
Shower Head)
SHR- "Compel" Series 3-Function Diverter T11861 & Chrome Delta Faucet Company
DV03D Trim with Valve (For Fixed to Handheld R11000 (Polished)
Shower Head)
SHR- "Parma" Series 3-Function Diverter Trim D560958T & Chrome Danze, a brand of Globe Union
DV03G with Valve (For Fixed to Handheld D130000-SS (Polished) Branded Products
Shower Head)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SHR- Shower Drain for use with Pre-formed 42150 Chrome Oatey
DR03O shower base and with 2" caulking (Polished)
connection. (Verify connection type)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SNK- Single-Handle Lavatory Faucet with 523LF-HDF Chrome Delta Faucet Company
FCT03D red/blue index and grid drain (Polished)
1.50 GPM
5" Spout / 4" Centers
SNK- "Coralais" Single Control with Red/Blue K-15198-F-CP Chrome Kohler Company
FCT03K index and Grid Drain (Polished)
1.50 GPM (WaterSense Certified)
4-5/8" Spout / 4" Centers
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SNK- Single-Handle Lavatory Faucet with 523LF-HDF Chrome Delta Faucet Company
FCT02D red/blue index and grid drain (Polished)
1.50 GPM
5" Spout / 4" Centers
SNK- "Coralais" Single Control with Sidespray K-15172-XF-CP Chrome Kohler Company
FCT15K and Lever Handle / red/blue Index (Polished)
2.20 GPM
10" Swing Spout
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SNK- "Studio Undercounter Sink" 0614.000.020 White American Standard Companies Inc.
BWL10A Bowl: 18-1/4" x 12-1/8" x 6" /
Undermount
SNK- "Compel" Series Single Handle deck 561LF-MPU Chrome Delta Faucet Company
FCT17D mount w/ red/blue Index on handle. (Polished)
1.50 GPM
7-1/2" High
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SNK- "Dia" Single Handle Lavatory Faucet SLS-3512-1.5 Chrome Symmons Industries Inc.
FCT17SY with red/blue index (Polished)
1.50 GPM
7-5/16" High
SNK- "Parma" Series Single Handle Bar Sink D151558 Chrome Danze, a brand of Globe Union
FCT18G Faucet with red/blue index (Polished) Branded Products
1.50 GPM
13-1/16" Spout
SNK- "Dia" Single Handle Bar Sink Faucet SPB-3510-1.5 Chrome Symmons Industries Inc.
FCT18SY with red/blue index (Polished)
1.50 GPM
11" Spout
SINK STRAINER (C)
SNK- "Duostrainer" K-6672-NA (2") or Chrome Kohler Company
STR01K K-6673-NA (3") (Polished)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SNK- "Parma" Series Single Handle Bar Sink D151558 Chrome Danze, a brand of Globe Union
FCT18G Faucet with red/blue index (Polished) Branded Products
1.50 GPM
13-1/16" Spout
SNK- "Dia" Single Handle Bar Sink Faucet SPB-3510-1.5 Chrome Symmons Industries Inc.
FCT18SY with red/blue index (Polished)
1.50 GPM
11" Spout
SINK STRAINER (C)
SNK- "Duostrainer" K-6672-NA (2") or Chrome Kohler Company
STR01K K-6673-NA (3") (Polished)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SVS- "Knoxford" - threaded spout for hose K-8928-CP Chrome Kohler Company
FCT09K connection, lever handles and pail hook (Polished)
4-5/8" Wall-to-spout outlet / 8" Centers
SVS- 2-Handle Service Sink Faucet- threaded 8230 Chrome Moen Incorporated
FCT09M spout for hose connection, lever (Polished)
handles and pail hook
9-3/8" Wall-to-spout outlet / 8" Centers
SVS- "Sink Faucet Wallmount" wall-mount - 28C2063 Chrome Delta Faucet Company
FCT09D threaded spout for hose connection, (Polished)
lever handles, with vacuum breaker
3.2" spout / 8" Centers
SINK STRAINER (C)
SVS- Sink Strainer 4331.013.002 Chrome American Standard Companies Inc.
STR01A (Polished)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SVS- "Molded-Stone Floor Mouonted Serv-A- FLTD II White Fiat Products, A Crane Plumbing
BWL08F Sink" Twin Compartment - One-Piece Company
Molded construction with complete drain
assembly, twin drain waste coupling, 4
legs, levelers and stopper.
40"W x 24"D x 33-3/4"H (Basin: 12-
1/2"D) / Floor Mounted
FAUCET (B)
SVS- Faucet - Laundry Tub 93.600 Chrome EL Mustee and Sons, Inc
FCT10MS 6" High Rise Swing Spout / 4" Centers (Polished)
SVS- Faucet - Two-Handle Deck Faucet A-1 Chrome Fiat Products, A Crane Plumbing
FCT10F 6-1/4" Swing Spout / 4" Centers (Polished) Company
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
SVS- "Hollister" Single Compartment Sink K-12793-0 & White Kohler Company
SVR02K with Wall Brackets K-1814-P
(Optional for use when space is limited)
28" x 22" (Basin 26" x 16" x 11-1/8") /
Wall Mounted
FAUCET (B)
SVS- Lavatory Gooseneck Spout 7522.155.002 Chrome American Standard Companies Inc.
FCT10A 11-7/8" Gooseneck Spout (Polished)
SVS- Lavatory Gooseneck Spout and Foot 54T5434A Chrome Delta Faucet Company
FCT12D Pedal Mixing Valve Control (Polished)
5" Gooseneck Spout
KNEE CONTROL (C)
SVS- Self-Closing Double Knee-Action Valve 7676.129.002 Chrome American Standard Companies Inc.
KNC01A (Polished)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- "AVALANCHE 1.28 Gravity Toilet" HE-21-812 White Gerber Plumbing Fixtures, a brand
WCL14G 1.28 GPF (WaterSense Certified) of Globe Union Branded Products
29-5/8"H x 17-1/4"W x 29-1/8" D (15-
1/4" Rim Height) / Floor Mounted
(See Toilet Seat Note 4 Below)
WCL- "Drake Close Coupled Toilet" CST744S White Toto USA, Inc.
WCL01T 28" x 19-1/2" x 14-5/8" / Floor Mounted
(See Toilet Seat Note 4 Below)
WCL- "Avalanche Two-Piece Super Toilet" 21-812 White Gerber Plumbing Fixtures, a brand
WCL01G 1.60 GPF (WaterSense Certified) of Globe Union Branded Products
29-1/8" x 17-1/4" x 28-5/8" (14-3/8" H
Rim Height) / Floor Mounted
(See Toilet Seat Note 4 Below)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- "Rise and Shine" Closed Front 5324.019.020 White American Standard Companies Inc.
TS03A
WCL- "Traditional Soft Close" Closed Front SS154 White Toto USA, Inc.
TS02T
WCL- "Drake Close Coupled Toilet" CST744S White Toto USA, Inc.
WCL01T 1.60 GPF
28" x 19-1/2" x 14-5/8" / Floor Mounted
(See Toilet Seat Note 4 Below)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- "Rise and Shine" Closed Front 5324.019.020 White American Standard Companies Inc.
TS03A
WCL- "Cachet" Closed Front (Quiet Close) K-4636-0 White Kohler Company
TS04K
WCL- "Traditional Soft Close" Closed Front SS154 White Toto USA, Inc.
TS02T
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- "Drake Close Coupled Toilet" CST744SL White Toto USA, Inc.
WCL02T 1.60 GPF
28" x 19-1/2" x 16-1/2" / Floor Mounted
(See Toilet Seat Note 4 Below)
WCL- "Avalanche ErgoHeight Two-Piece 21-818 White Gerber Plumbing Fixtures, a brand
WCL03G Super Toilet" of Globe Union Branded Products
1.60 GPF (WaterSense Certified)
28 7/8" x 17 1/2" x 30 1/2" (16-1/2" H
Rim Height) / Floor Mounted
(See Toilet Seat Note 4 Below)
WATER CLOSET (ADA) (A2) - ALTERNATE FOR
WATER CONSERVATION
WCL- "Highline Class Five Toilet" K-3999-0 White Kohler Company
WCL09K 1.28 GPF (WaterSense Certified)
29-3/4" x 18" x 31-1/4" (16-1/2" H Rim
Height) / Floor Mounted
(See Toilet Seat Note 4 Below)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- "Traditional Soft Close" Closed Front SS154 White Toto USA, Inc.
TS02T
WCL- "Drake Close Coupled Toilet" CST744SL White Toto USA, Inc.
WCL02T 1.60 GPF
28" x 19-1/2" x 16-1/2" / Floor Mounted
(See Toilet Seat Note 4 Below)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- "Rise and Shine" Closed Front 5324.019.020 White American Standard Companies Inc.
TS03A
WCL- "Cachet" Closed Front (Quiet Close) K-4636-0 White Kohler Company
TS04K
WCL- "Traditional Soft Close" Closed Front SS154 White Toto USA, Inc.
TS02T
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- "Commercial Elongated Top Spud Bowl" 25-830 White Gerber Plumbing Fixtures, a brand
WCL04G 1.60 GPF (WaterSense Certified) of Globe Union Branded Products
27-1/2" x 14-1/2" x 14-3/4" (14-3/4" H
Rim Height) / Floor Mounted 10" Rough
(See Toilet Seat Note 4 Below)
WATER CLOSET (A2) - ALTERNATE FOR WATER
CONSERVATION
WCL- "Wellworth High Effiency Bowl" K-4406-0 White Kohler Company
WCL11K 1.28 GPF
28-1/4" x 14-7/8" x 15" (15" H Rim
Height) / Floor Mounted
(See Toilet Seat Note 4 Below)
TOILET SEAT (B)
WCL- Elongated Seat, Open Front w/ No 2155CTJ White Church Seats, A Division of Bemis
TS03CH Cover. "Just-Lift" Integrated Hinge Manufacturing Company
system. "Sta-Tite" Fastening System. -
See Note 4
WCL- Open Front w/ No Cover 5901.100.020 White American Standard Companies Inc.
TS02A
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- Exposed Flush Valves - Manual 81T201 Chrome Delta Faucet Company
FLV01D Operation (Polished)
ADA Compliant
1.60 GPF
/ Wall Mounted
FLUSH VALVE (C2) - UPGRADE OPTION
WCL- Selectronic Sensor Operated, 6065.161.002 Chrome American Standard Companies Inc.
FLV03A Concealed Flush Valve (Polished)
ADA Compliant
1.60 GPF
/ Wall Mounted
WCL- Electronic Exposed TECK Flush Valves 81T201BTA Chrome Delta Faucet Company
FLV03D ADA Compliant (Polished)
1.60 GPF
/ Wall Mounted
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- "ADA Compliant Elongated Top Spud 25-730 White Gerber Plumbing Fixtures, a brand
WCL05G Bowl" of Globe Union Branded Products
1.60 GPF (WaterSense Certified)
27" x 14-1/2" x 17" (17" H Rim Height) /
Floor Mounted 10" Rough
(See Toilet Seat Note 4 Below)
TOILET SEAT (B)
WCL- Elongated Seat, Open Front w/ No 2155CTJ White Church Seats, A Division of Bemis
TS03CH Cover. "Just-Lift" Integrated Hinge Manufacturing Company
system. "Sta-Tite" Fastening System. -
See Note 4
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- Exposed Flush Valves - Manual 81T201 Chrome Delta Faucet Company
FLV01D Operation (Polished)
ADA Compliant
1.60 GPF
/ Wall Mounted
FLUSH VALVE (C2) - UPGRADE OPTION
WCL- Selectronic Sensor Operated, 6065.161.002 Chrome American Standard Companies Inc.
FLV03A Concealed Flush Valve (Polished)
ADA Compliant
1.60 GPF
/ Wall Mounted
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
WCL- Electronic Exposed TECK Flush Valves 81T201BTA Chrome Delta Faucet Company
FLV03D ADA Compliant (Polished)
1.60 GPF
/ Wall Mounted
FLUSH VALVE (C3) - ALTERNATE FOR WATER
CONSERVATION TO BE USED WITH 1.28 GPF
WATER CLOSET
WCL- Selectronic Sensor Operated, 6065.121.002 Chrome American Standard Companies Inc.
FLV07A Concealed Flush Valve (Polished)
ADA Compliant
1.28 GPF
/ Wall Mounted
WCL- Electronic Exposed TECK Flush Valves 81T201BTA-48 Chrome Delta Faucet Company
FLV07D ADA Compliant (Polished)
1.28 GPF
/ Wall Mounted
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
URN- Exposed Flush Valves - Manual 81T231 Chrome Delta Faucet Company
FLV02D Operation (Polished)
ADA Compliant
1.0 GPF (Field Adjust)
/ Wall Mounted
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
URN- Electronic Exposed TECK Flush Valves 81T231BTA-38 Chrome Delta Faucet Company
FLV04D ADA Compliant (Polished)
1.0 GPF
/ Wall Mounted
FLUSH VALVE (B3) - ALTERNATE FOR WATER
CONSERVATION TO BE USED WITH 0.50 GPF
URINAL
URN- Selectronic Sensor Operated Flush 6063.051.002 Chrome American Standard Companies Inc.
FLV08A Valve (Polished)
ADA Compliant
0.50 GPF
/ Wall Mounted
URN- M-Power Sensor Operated Flush Valve 8315 Chrome Moen Incorporated
FLV08M ADA Compliant with manual override (Polished)
0.50 GPF
/ Wall Mounted
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
URN- Electronic Exposed TECK Flush Valves 81T231BTA-38 Chrome Delta Faucet Company
FLV04D ADA Compliant (Polished)
1.0 GPF
/ Wall Mounted
FLUSH VALVE (B3) - ALTERNATE FOR WATER
CONSERVATION TO BE USED WITH 0.50 GPF
URINAL
URN- Selectronic Sensor Operated Flush 6063.051.002 Chrome American Standard Companies Inc.
FLV08A Valve (Polished)
ADA Compliant
0.50 GPF
/ Wall Mounted
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
URN- Electronic Exposed TECK Flush Valves 81T231BTA-05 Chrome Delta Faucet Company
FLV08D ADA Compliant (Polished)
0.50 GPF
/ Wall Mounted
MOP- Mop Service Basin - 1 Piece, Molded MSBID2424-100 White Fiat Products, A Crane Plumbing
MSK01f stone Construction, integrally molded Company
center drain with seal. Removable
stainless steel strainer.
24" x 24" x 10" / Floor Mounted
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
MOP- 2-Handle Service Sink Faucet- threaded 8230 Chrome Moen Incorporated
FCT09M spout for hose connection, lever (Polished)
handles and pail hook
9-3/8" Wall-to-spout outlet / 8" Centers
MOP- Exposed Yoke Wall Mount Utility Faucet 28T9 Polished Delta Faucet Company
FCT11D with Top Brace Chrome
/ Wall Mounted
MOP- Exposed Yoke Wall Mount Utility Faucet 830-AA-000 Polished Fiat Products, A Crane Plumbing
FCT09F with with vacuum breaker, adjustable Chrome Company
wall brace, pail hook and 3/4" thread on
spout
/ Wall Mounted
HOSE HOLDER (C)
MOP- Heavy Duty 5/8" diameter, 31" Rubber 65.700 Stainless E.L. Mustee & Sons
HSH01M Hose and Spring Loaded Molded Steel
S Rubber Hose Hoder on Stainless Steel
Wall Plate
/ Wall Mounted
MOP- Heavy Duty 5/8" diameter, 36" Rubber 8199 Stainless Moen Incorporated
HSH01M Hose and Spring Loaded Molded Steel
Rubber Hose Hoder on Stainless Steel
Wall Plate
3-1/2" x 5" / Wall Mounted
MOP- Heavy Duty 5/8" diameter, 48" Rubber 28T911 Stainless Delta Faucet Company
HSH01D Hose and Spring Loaded Molded Steel
Rubber Hose Hoder on Stainless Steel
Wall Plate
3" x 5" / Wall Mounted
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
MOP- Three spring-loaded, molded rubber 28T910 Stainless Delta Faucet Company
MPH01D mop holders attached to stainless steel Steel
wall plate.
3" x 24" / Wall Mounted
MOP- Three spring-loaded, molded rubber 889-CC-000 Stainless Fiat Products, A Crane Plumbing
MPH01F mop holders attached to stainless steel Steel Company
wall plate.
3" x 24" / Wall Mounted
WALL GUARD (E)
MOP- 12" High, 20 Gauge, #304 Stainless 67.2424 Stainless E.L. Mustee & Sons
WGD01M Steel wall guard Steel
S / Wall Mounted
MOP- Two (2), 12" High, 20 Gauge, #304 MSG2424-000 Stainless Fiat Products, A Crane Plumbing
WGD01F Stainless Steel wall guard plus corner Steel Company
bracket
/ Wall Mounted
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
Note 1: Items shown with "(UPG)" or "(Upgrade)", are an upgrade to standard items.
Note 2: Standard Finish for Guestroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 3: Standard Finish for Public & Employee Restroom Trim is Chrome (Polished or Bright) (Noted otherwise if not available).
Note 4: Church or Bemis Seats are suggested due to improved mounting brackets.
12/1/15 Residence Inn Plumbing Fixture Matrix (22-224000b-R-Plumbing Fixture Matrix)
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. HVAC Pipe and Pipe Fittings
2. Joining Materials
3. HVAC Sleeves
4. HVAC Sleeve Seals
5. HVAC Specialties
6. HVAC Piping System Installation
7. HVAC Equipment Installation
8. Concrete Bases.
9. Erection of Metal Supports
10. Erection of Wood Supports
11. Cutting and Patching
B. Related Sections:
1. Section 01 31 00 - Project Management and Coordination
2. Section 01 73 29 - Cutting and Patching
3. Section 01 78 43 - Spare Parts and Materials
4. Section 01 79 00 - Training
5. Section 01 78 23 - Operating and Maintenance Data
6. Section 03 30 00 - Cast-in-Place Concrete
7. Section 06 10 01 - Rough Carpentry
8. Section 07 62 00 - Sheet Metal Flashing and Trim
9. Section 07 84 00 - Firestopping
10. Section 08 31 00 - Access Doors
11. Section 09 90 00 - Painting
12. Section 23 05 53 – Identification for HVAC Piping and Equipment: Labeling and
identifying HVAC systems and equipment.
13. Section 31 20 00 – Earth Moving
1.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and Seamless"
▪ DIVISION 23 HVAC ▪
▪ PAGE 1 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 2 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 3 ▪
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. HVAC Sleeve Seals:
a. None
B. Approved Manufacturers:
1. HVAC Sleeve Seals:
a. Metraflex Inc. (800-621-4347)
b. PSI-Thunderline/Link-Seal (800-423-2410)
2.02 JOINING MATERIALS
A. Solder Filler Metals: ASTM B32.
1. Alloy Sn95 or Alloy Sn94: Approximately 95 percent tin and 5 percent silver, with 0.10
percent lead content.
2. Alloy E: Approximately 95 percent tin and 5 percent copper, with 0.10 percent maximum
lead content.
3. Alloy HA: Tin-antimony-silver-copper zinc, with 0.10 percent maximum lead content.
4. Alloy HB: Tin-antimony-silver-copper nickel, with 0.10 percent maximum lead content.
5. Alloy Sb5: 95 percent tin and 5 percent antimony, with 0.20 percent maximum lead
content.
B. Brazing Filler Metals: AWS A5.8.
1. BCuP Series: Copper-phosphorus alloys.
2. BAg1: Silver alloy.
3. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall
thickness and chemical analysis of steel pipe being welded.
2.03 HVAC SLEEVES
A. Sleeves: The following materials are for wall, floor, slab, and roof penetrations:
1. Steel Sheet Metal: 0.0239-inch minimum thickness, galvanized, round tube closed with
welded longitudinal joint.
2. Steel Pipe: ASTM A53, Type E, Grade A, Schedule 40, galvanized, plain ends.
3. Cast Iron: Cast or fabricated "wall pipe" equivalent to ductile-iron pressure pipe, with plain
ends and integral water stop, unless otherwise indicated.
4. Stack Sleeve Fittings: Manufactured, cast-iron sleeve with integral clamping flange.
Include clamping ring and bolts and nuts for membrane flashing.
▪ DIVISION 23 HVAC ▪
▪ PAGE 4 ▪
PART 3 EXECUTION
3.01 HVAC PIPING SYSTEMS - COMMON REQUIREMENTS
A. General: Install HVAC piping as described below, unless piping Sections specifies otherwise.
Individual Division 23 Piping Sections specifies unique piping installation requirements.
B. General Locations and Arrangements: Drawing plans, schematics, and diagrams indicate
general location and arrangement of piping systems. Install piping as indicated, unless
deviations to layout are approved on Coordination Drawings as required by Division 01
Sections and as outlined in Part 1 of this section.
C. Install components with pressure rating equal to or greater than system operating pressure.
D. Install piping in concealed interior and exterior locations, except in equipment rooms and
service areas.
E. Install piping free of sags and bends.
F. Install exposed interior and exterior piping at right angles or parallel to building walls.
Diagonal runs are prohibited, unless otherwise indicated.
G. Install piping tight to slabs, beams, joists, columns, walls, and other building elements. Allow
sufficient space above removable ceiling panels to allow for ceiling panel removal.
H. Install piping to allow application of insulation plus 1-inch clearance around insulation.
I. Install sleeves for pipes passing through concrete and masonry walls, and concrete floor and
roof slabs.
1. Cut sleeves to length for mounting flush with both surfaces.
a. Exception: Extend sleeves installed in floors of mechanical equipment areas or other
wet areas 2 inches above finished floor level. Extend cast-iron sleeve fittings below
floor slab as required to secure clamping rings where required.
2. Build sleeves into walls and slabs as work progresses.
3. Install sleeves large enough to provide 1/4-inch annular clear space between sleeve and
pipe or pipe insulation.
4. Use Type S, Grade NS, Class 25, Use O, neutral-curing silicone sealant.
▪ DIVISION 23 HVAC ▪
▪ PAGE 5 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 6 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 7 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Basic Motor Requirements
2. Polyphase Motors
3. Single Phase Motors
B. Related Sections:
1. Division 23 Sections for application of motors and reference to specific motor
requirements for motor-driven equipment.
4.02 REFERENCES
A. Institute of Electrical and Electronics Engineers (IEEE) Publications:
1. 112 “Standard Test Procedure for Polyphase Induction Motors and Generators”
B. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. MG 1 “Motors and Generators”
C. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
4.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: Show nameplate data and ratings; characteristics; mounting
arrangements; size and location of winding termination lugs, conduit entry, and grounding
lug; and coatings.
4.04 QUALITY ASSURANCE
A. Comply with NFPA 70.
B. Listing and Labeling: Provide motors specified in this Section that are listed and labeled.
1. Terms "Listed and Labeled": As defined in the National Electrical Code, Article 100.
PART 5 PRODUCTS
5.01 BASIC MOTOR REQUIREMENTS
A. Basic requirements apply to mechanical equipment motors, unless otherwise indicated.
B. Motors 1/2 HP and Larger: Polyphase.
C. Motors Smaller than 1/2 HP: Single phase.
▪ DIVISION 23 HVAC ▪
▪ PAGE 8 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 9 ▪
PART 6 EXECUTION
6.01 ADJUSTING
A. Use adjustable motor mounting bases for belt-driven motors.
B. Align pulleys and install belts.
C. Tension according to manufacturer's written instructions.
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 10 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Meters and gages for HVAC systems.
B. Related Sections:
1. Section 01 81 13 - Sustainable Design Requirements
2. Division 23 - HVAC equipment Sections that specify meters and gages as part of factory-
fabricated equipment.
7.02 REFERENCES
A. American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE)
Publications:
1. 62.1 “Ventilation for Acceptable Indoor Air Quality (ANSI Approved)”
2. 90.1 “Energy Code for Commercial and High-Rise Residential Buildings”
B. New Buildings Institute (NBI) Publications:
1. “Core Performance Guide”
C. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. E1 “Standard Specification for ASTM Liquid-in-Glass Thermometers”
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B40.1 “Pressure Gauges and Gauge Attachments”
2. B40.5 “Snubbers”
B. American Water Works Association (AWWA) Publications:
1. ANSI/AWWA C700 “AWWA Standard for Cold-Water Meters – Displacement Type,
Bronze Main Case”
2. ANSI/AWWA C701 “AWWA Standard for Cold-Water Meters—Turbine Type, for
Customer Service”
3. ANSI/AWWA C706 “AWWA Standard for Direct-Reading, Remote-Registration Systems
for Cold-Water Meters”
7.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
1. Product Data: Include scale range, ratings, and calibrated performance curves for each
meter, gage, fitting, specialty, and accessory specified.
2. Shop Drawings: Include schedule indicating manufacturer's number, scale range,
fittings, and location for each meter and gage.
3. Product Certificates: Signed by manufacturers of meters and gages certifying accuracies
under specified operating conditions and compliance with specified requirements.
▪ DIVISION 23 HVAC ▪
▪ PAGE 11 ▪
PART 8 PRODUCTS
8.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Liquid-in-Glass Thermometers:
a. None
2. Pressure Gages:
a. None
3. Test Plugs:
a. None
4. Venturi-Type Flow Elements:
a. None
5. Water Meters:
a. None
B. Approved Manufacturers:
1. Liquid-in-Glass Thermometers:
a. Ashcroft, Inc. (800-328-8258)
b. Miljoco Corp. (888-888-1496)
c. Trerice: H. O. Trerice Co. (888-873-7423)
2. Pressure Gages:
a. Ashcroft, Inc. (800-328-8258)
b. Miljoco Corp. (888-888-1496)
c. Trerice: H. O. Trerice Co. (888-873-7423)
3. Test Plugs:
a. Flow Design, Inc. (800-275-3568)
b. Peterson Equipment Co., Inc. (214-544-7584)
c. Trerice: H. O. Trerice Co. (888-873-7423)
4. Venturi-Type Flow Elements:
a. Flow Design, Inc. (800-275-3568)
b. Gerand Engineering Co. (952-374-1320)
c. Preso Meters Corp. (800-632-7337)
5. Water Meters:
▪ DIVISION 23 HVAC ▪
▪ PAGE 12 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 13 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 14 ▪
PART 9 EXECUTION
9.01 METER AND GAGE INSTALLATION, GENERAL
A. Install meters, gages, and accessories according to manufacturer's written instructions for
applications where used.
9.02 THERMOMETER INSTALLATION
A. Install thermometers and adjust vertical and tilted positions.
B. Install in the following locations:
1. Inlet and outlet of each hydronic system boiler.
2. Elsewhere as indicated on the drawings.
C. Install separable sockets in vertical position in piping tees where fixed thermometers are
indicated.
1. Install with socket extending a minimum of 2 inches into fluid.
2. Fill sockets with oil or graphite and secure caps.
D. Install thermometer wells in vertical position in piping tees where test thermometers are
indicated.
1. Install with stem extending a minimum of 2 inches into fluid.
2. Fill wells with oil or graphite and secure caps.
9.03 PRESSURE-GAGE INSTALLATION
A. Install pressure gages in piping tees with pressure-gage valve located on pipe at most
readable position.
▪ DIVISION 23 HVAC ▪
▪ PAGE 15 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 16 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. General Duty Valves Common to Several Mechanical Piping Systems.
B. Related Sections:
1. Section 01 81 13 - Sustainable Design Requirements
2. Section 23 05 00 - Common Work Results for HVAC
3. Section 23 31 13.51 - Hydronic Piping - Metal
4. Section 23 31 13.52 - Hydronic Piping - Plastic
5. Division 23 piping Sections for specialty valves applicable to those Sections only.
6. Division 23 Section "Identification for HVAC Piping and Equipment" for valve tags and
charts.
7. Division 23 Section "Instrumentation and Control for HVAC" for control valves and
actuators.
10.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A126 "Standard Specification for Gray Iron Castings for Valves, Flanges, and Pipe
Fittings"
2. B32 "Standard Specification for Solder Metal"
3. B62 “Standard Specification for Composition Bronze or Ounce Metal Castings”
4. B584 “Standard Specification for Copper Alloy Sand Castings for General Applications”
5. B828 “Standard Practice for Making Capillary Joints by Soldering of Copper and Copper
Alloy Tube and Fittings”
B. The American Society of Mechanical Engineers (ASME) Publications:
1. B1.20.1 "Pipe Threads, General Purpose, Inch"
2. B16.1 “Cast Iron Pipe Flanges and Flanged Fittings”
3. B16.5 “Pipe Flanges and Flanged Fittings”
4. B16.10 “Face-to-Face and End-to-End Dimensions of Valves”
5. B16.18 “Cast Copper Alloy Solder Joint Pressure Fittings”
6. B16.24 “Cast Copper Alloy Pipe Flanges and Flanged Fittings: Classes 150, 300, 400,
600, 900, 1500 and 2500”
7. B16.34 “Valves Flanged, Threaded and Welding End”
8. B31.1 “Power Piping”
9. B31.9 “Building Services Piping”
▪ DIVISION 23 HVAC ▪
▪ PAGE 17 ▪
PART 11 PRODUCTS
11.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
▪ DIVISION 23 HVAC ▪
▪ PAGE 18 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 19 ▪
PART 12 EXECUTION
12.01 EXAMINATION
A. Examine piping system for compliance with requirements for installation tolerances and other
conditions affecting performance of valves. Do not proceed with installation until
unsatisfactory conditions have been corrected.
B. Examine valve interior for cleanliness, freedom from foreign matter, and corrosion. Remove
special packing materials, such as blocks, used to prevent disc movement during shipping and
handling.
C. Operate valves from fully open to fully closed positions. Examine guides and seats made
accessible by such operation.
D. Examine threads on valve and mating pipe for form and cleanliness.
E. Examine mating flange faces for conditions that might cause leakage. Check bolting for
proper size, length, and material. Check gasket material for proper size, material composition
suitable for service, and freedom from defects and damage.
F. Do not attempt to repair defective valves; replace with new valves.
12.02 INSTALLATION
A. Install valves as indicated, according to manufacturer's written instructions.
▪ DIVISION 23 HVAC ▪
▪ PAGE 20 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 21 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 22 ▪
PART 13 GENERAL
13.01 SUMMARY
A. Section Includes:
1. Hangers And Supports For HVAC System Piping And Equipment.
B. Related Sections:
1. Section 05 50 00 (05500) - Metal Fabrications
2. Section 09 90 00 (09900) - Painting
3. Section 23 05 48 (15070) – Vibration and Seismic Control for HVAC Piping and
Equipment
13.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B31.9 “Building Services Piping”
B. American Welding Society (AWS) Publications:
1. D1.1 "Structural Welding Code - Steel"
C. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A36 “Standard Specification for Carbon Structural Steel”
2. A780 "Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip
Galvanized Coatings"
3. C552 “Standard Specification for Cellular Glass Thermal Insulation”
4. C1107 "Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)"
D. Metal Framing Manufacturers Association (MFMA)
E. Manufacturers Standardization Society of the Valve and Fittings Industry. (MSS) Publications:
1. SP-6 “Standard Finishes for Contact Faces of Pipe Flanges and Connecting-End Flanges
of Valves and Fittings”
2. SP-58 “Pipe Hangers and Supports - Materials, Design, and Manufacture”
3. SP-69 “ANSI/MSS Edition Pipe Hangers and Supports - Selection and Application”
4. SP-89 “Pipe Hangers and Supports -Fabrication and Installation Practices”
13.03 DEFINITIONS
A. MSS: Manufacturers Standardization Society for the Valve and Fittings Industry.
B. Terminology: As defined in MSS SP-90, "Guidelines on Terminology for Pipe Hangers and
Supports.
13.04 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
▪ DIVISION 23 HVAC ▪
▪ PAGE 23 ▪
PART 14 PRODUCTS
14.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Pipe Hangers, Supports, and Components:
a. None
2. Channel Support Systems:
a. None
3. Thermal-Hanger Shield Inserts:
a. None
4. Powder-Actuated and Mechanical Anchor Fastener Systems:
a. None
B. Approved Manufacturers:
1. Pipe Hangers, Supports, and Components:
a. Cooper B-Line, Inc. (618-654-2184)
b. Grinnell Mechanical Products, A Tyco International Company (800-500-4768)
c. National Pipe Hanger Corporation (609-261-5353)
2. Channel Support Systems:
a. Cooper B-Line, Inc. (618-654-2184)
b. Grinnell Mechanical Products, A Tyco International Company (800-500-4768)
c. National Pipe Hanger Corporation (609-261-5353)
3. Thermal-Hanger Shield Inserts:
a. Carpenter & Patterson, Inc. (301.333.4631)
b. Erico (Michigan Hanger) (440-248-0100)
c. PHS Industries, Inc. (800-626-2336)
▪ DIVISION 23 HVAC ▪
▪ PAGE 24 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 25 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 26 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 27 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 28 ▪
PART 16 GENERAL
16.01 SUMMARY
A. Section Includes:
1. Heat Tracing
B. Related Sections:
1. Section 01 81 13 - Sustainable Design Requirements
2. Section 23 05 53 - Identification for HVAC Piping and Equipment
3. Section 23 07 00 - HVAC Insulation
4. Section 23 31 13.51 - Hydronic Piping - Metal
5. Section 23 31 13.52 - Hydronic Piping - Plastic
6. Section 23 81 46 – Water Source Heat Pumps
16.02 REFERENCES
A. Institute of Electrical and Electronics Engineers (IEEE) Publications:
1. 515.1 “IEEE Standard for the Testing, Design, Installation, and Maintenance of Electrical
Resistance Heat Tracing for Commercial Applications”
B. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
C. Underwriter's Laboratories, Inc. (UL) Standards:
1. 486A “Standard For Wire Connectors and Soldering Lugs for Use With Copper
Conductors”
2. 486B “Standard for Wire Connectors for Use With Aluminum Conductors”
16.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
1. Product Data: For each type of product indicated.
2. Shop Drawings: Diagram power, signal, and control wiring and differentiate between
manufacturer-installed and field-installed wiring.
3. Field Test Reports: Indicate and interpret test results for compliance with performance
requirements.
4. Maintenance Data: For electric heating cables to include in maintenance manuals.
16.04 QUALITY ASSURANCE
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70
“National Electrical Code”, Article 100, by a testing agency acceptable to authorities having
jurisdiction, and marked for intended use.
▪ DIVISION 23 HVAC ▪
▪ PAGE 29 ▪
PART 17 PRODUCTS
17.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Heat Tracing System:
a. None
B. Approved Manufacturers:
1. Heat Tracing System:
a. Chromalox; Wiegard Industrial Division; Emerson Electric Company (800-443-2640)
b. Delta-Therm Corporation (800-526-7887)
c. Nelson Heat Tracing Systems (918-627-5530)
d. Tyco Thermal Controls (800-545-6258)
17.02 HEAT TRACING SYSTEM
A. Provide electric heating tape system for piping located at the exterior of the building. Heating
tape and accessories shall be installed by tradespersons skilled in this type of work. Methods
of installation, electrical connections and similar requirements, shall be in strict accordance
with the tape manufacturer's recommendations. Tape shall be neatly attached along the pipe
length and under the pipe insulation. Heating tape shall be cut to desired length required.
B. Freeze-protection tracing shall be an electrical heating strip of self-limiting, flexible, parallel
circuit construction, consisting of a continuous inner core of semi-conductive material between
two (2) 16 AWG parallel tinned-copper bus wires and enclosed in a copper-tinned braided wire
sheath and a modified polyolefin dielectric outer jacket. Cable shall be wrapped and
overlapped on valves, according to manufacturer's recommendations. The cable shall be
designed for self-controlling its wattage output in response to actual pipe temperature, without
overheating. Cable shall be of type which cannot burn out where overlapped. Cable shall
have a watts/ft. thermal rating at 50 degrees F. as recommended by the supplier for the
diameter of piping being traced. Cable shall be UL listed.
C. Provide necessary lengths of heater strips, connector kits, end seal kits, glass tape, signs and
an ambient sensing thermostat to deactivate the freeze-protection system during warmer
weather. Locate signs on exterior surface of insulation at frequent intervals to indicate the
presence of electrical tracing equipment to personnel.
D. Provide the junction boxes, connection kits and the installation of the ambient sensing
thermostat. The entire installation shall conform with the requirements of the heating cable
manufacturer's requirements and NFPA 70 “National Electrical Code”. Power wiring to the
system will be provided under Division 26. System shall be suitable for operating at voltage
indicated on the drawings.
17.03 ACCESSORIES
A. Cable Installation Accessories: Fiberglass tape, heat-conductive putty, cable ties, silicone end
seals and splice kits, and installation clips all furnished by manufacturer, or as recommended
in writing by manufacturer.
B. Warning Labels: Refer to Section 23 05 53 "Identification for HVAC Piping and Equipment."
▪ DIVISION 23 HVAC ▪
▪ PAGE 30 ▪
PART 18 EXECUTION
18.01 EXAMINATION
A. Examine areas and conditions for compliance with requirements for installation tolerances,
other specific conditions, and other conditions affecting performance of water-source heat
pumps. Do not proceed with installation until unsatisfactory conditions have been corrected.
B. Examine piping and electric rough installations for water-source heat pumps to verify actual
locations of piping connections before installation.
18.02 INSTALLATION
A. Examine surfaces and substrates to receive heating cables for compliance with requirements
for installation, tolerances, and other conditions affecting performance.
1. Ensure surfaces and pipes in contact with electric heating cables are free of burrs and
sharp protrusions.
2. Ensure pipe testing is complete.
3. Ensure surfaces and substrates are level and plumb.
B. Test cables for electrical continuity before installing.
C. Test cables for insulation resistance before installing.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
18.03 INSTALLATION
A. Cut cable to lengths required. Install cables and components in accordance with
manufacturer's recommendations.
B. Install electric heating cable across expansion joints according to manufacturer's written
recommendations using slack cable to allow movement without damage to cable.
C. Install electric heating cables after piping has been tested and before insulation is installed.
D. Install electric heating cables according to IEEE 515.1.
E. Install insulation over piping with electric cables according to Section 23 07 00 "HVAC
Insulation."
F. Install warning tape on piping insulation where piping is equipped with electric heating cables.
G. Set field-adjustable switches and circuit-breaker trip ranges.
H. Protect installed heating cables, including non-heating leads, from damage.
18.04 CONNECTIONS
A. Electrical installation requirements are specified in Division 26 Sections. Drawings indicate
general arrangement of wiring, conduit, and specialties.
▪ DIVISION 23 HVAC ▪
▪ PAGE 31 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 32 ▪
PART 19 GENERAL
19.01 SUMMARY
A. Section Includes:
1. Vibration Isolators.
2. Seismic Controls.
3. Vibration Isolation Bases.
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-In-Place Concrete
2. Section 04 20 00 (04200) - Unit Masonry
3. Section 05 12 00 (05120) - Structural Steel
4. Section 06 10 01 (06100) - Rough Carpentry
5. Section 09 90 00 (09900) - Painting
6. Section 23 05 00 (15050) – Common Work Results for HVAC
7. Section 23 05 29 (15060) - Hangers and Supports for HVAC Piping and Equipment: for
pipe hanger restraints.
8. Section 23 31 13 (15815) - Metal Ducts: for flexible duct connectors.
19.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A36 “Standard Specification for Carbon Structural Steel”
19.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: Indicate types, styles, materials, and finishes for each type of isolator
specified. Include load deflection curves.
2. Shop Drawings: Show designs and calculations, certified by a professional engineer, as
required by the local authority, for the following:
a. Design Calculations: Calculations for selection of vibration isolators, design of
vibration isolation bases, and selection of seismic restraints.
b. Vibration Isolation Base Details: Detail fabrication, including anchorages and
attachments to the structure and to the supported equipment. Include auxiliary
motor slides and rails, and base weights.
c. Seismic Restraint Details: Detail fabrication and attachment of restraints and
snubbers.
▪ DIVISION 23 HVAC ▪
▪ PAGE 33 ▪
PART 20 PRODUCTS
20.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None
B. Approved Manufacturers:
1. Cooper B-Line Systems, Inc. (800-851-7415)
2. Kinetics Noise Control, Inc. (877-457-2695)
3. Mason Industries, Inc. (631-348-0282)
20.02 VIBRATION ISOLATORS
A. Isolator Pads: Oil and water resistant and factory cut to sizes that match requirements of the
equipment supported.
1. Rubber Isolator Pads: Elastomer (neoprene or silicone) arranged in single or multiple
layers and molded with a nonslip pattern and steel baseplates of sufficient stiffness to
provide uniform loading over the pad area.
2. Load Range: From 10 to 50 psig and a deflection not less than 0.08 inch per 1 inch of
thickness. Do not exceed a loading of 50 psig.
B. Rubber Isolator Mounts: Double-deflection type, with molded, oil-resistant rubber or neoprene
isolator elements, with encapsulated top- and baseplates. Factory-drilled and tapped top plate
for bolted equipment mounting. Factory-drilled baseplate for bolted connection to structure.
Color-code to indicate capacity range.
C. Spring Isolators: Freestanding, laterally stable, open-spring-type isolators.
1. Outside Spring Diameter: Not less than 80 percent of the compressed height of the
spring at rated load.
2. Minimum Additional Travel: 50 percent of the required deflection at rated load.
3. Lateral Stiffness: More than 1.2 times the rated vertical stiffness.
4. Overload Capacity: Support 200 percent of rated load, fully compressed, without
deformation or failure.
▪ DIVISION 23 HVAC ▪
▪ PAGE 34 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 35 ▪
PART 21 EXECUTION
21.01 INSTALLATION
A. Install and anchor vibration-, sound-, and seismic-control products according to
manufacturer's written instructions and authorities having jurisdiction.
B. Anchor interior mounts, isolators, hangers, and snubbers to vibration isolation bases. Bolt
isolator baseplates to structural floors as required by authorities having jurisdiction.
C. Anchor exterior mounts, isolators, hangers, and snubbers to vibration isolation bases. Bolt
isolator baseplates to structural supports as required by authorities having jurisdiction.
D. Install pipe connectors at connections for equipment supported on vibration isolators.
21.02 SEISMIC CONTROL
A. Snubbers: Install the required number of seismic snubbers on each spring-mounted piece of
equipment. Locate snubbers as close as possible to the vibration isolators and bolt to
supporting structure.
21.03 ADJUSTING AND CLEANING
A. Adjust limit stops on restrained spring isolators to mount equipment at normal operating
height. After equipment installation is complete, adjust limit stops so they are out of contact
during normal operations.
B. Adjust thrust restraints for a maximum of 1/4 inch of movement at start and stop
▪ DIVISION 23 HVAC ▪
▪ PAGE 36 ▪
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 37 ▪
PART 22 GENERAL
22.01 SUMMARY
A. Section Includes:
1. Identifying Devices and Labels
B. Related Sections:
1. Section 23 05 00 (15050) – Common Work Results for HVAC
22.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. C1036 “Standard Specification for Flat Glass”
B. The American Society of Mechanical Engineers (ASME) Publications:
1. A13.1 “Scheme for the Identification of Piping Systems”
22.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: For identification materials and devices.
2. Samples: Of color, lettering style, and graphic representation required for each
identification material and device.
22.04 QUALITY ASSURANCE
A. Comply with ASME A13.1, "Scheme for the Identification of Piping Systems" for lettering size,
length of color field, colors, and viewing angles of identification devices.
22.05 SEQUENCING AND SCHEDULING
A. Coordinate installation of identifying devices with completion of covering and painting of
surfaces where devices are to be applied.
B. Install identifying devices before installing acoustical ceilings and similar concealment.
PART 23 PRODUCTS
23.01 GENERAL
A. General: Products specified are for applications referenced in other Division 23 Sections. If
more than single type is specified for listed applications, selection is Installer's option.
B. Pipes Including Insulation: Full-band pipe markers, extending 360 degrees around pipe at
each location.
▪ DIVISION 23 HVAC ▪
▪ PAGE 38 ▪
PART 24 EXECUTION
24.01 LABELING AND IDENTIFYING PIPING SYSTEMS
A. Install pipe markers on each system as indicated below. Include arrows showing normal
direction of flow.
▪ DIVISION 23 HVAC ▪
▪ PAGE 39 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 40 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 41 ▪
PART 25 GENERAL
25.01 SUMMARY
A. Section Includes:
1. Balancing airflow within distribution systems, including sub-mains, branches, and
terminals, to indicated quantities according to specified tolerances.
2. Adjusting total HVAC systems to provide indicated quantities.
3. Measuring electrical performance of HVAC and plumbing equipment.
4. Setting quantitative performance of HVAC and plumbing equipment.
5. Verifying that automatic control devices are functioning properly.
6. Reporting results of the activities and procedures specified in this Section.
7. Adjustment of recirculating domestic hot water return system.
8. Verify performance of package terminal air conditioning units.
B. Related Sections:
1. Testing and adjusting requirements unique to particular systems and equipment are
included in the Sections that specify those systems and equipment.
2. Field quality-control testing to verify that workmanship quality for system and equipment
installation is specified in system and equipment Sections.
25.02 REFERENCES
A. Associated Air Balance Council (AABC): "National Standards for Testing, Adjusting and
Balancing"
B. Air Movement & Control Association International, Inc. (AMCA): 201, "Fans and Systems
C. National Environmental Balancing Bureau (NEBB): “Procedural Standards for Testing,
Adjusting and Balancing of Environmental Systems”
D. Sheet Metal and Air Conditioning Contractors' National Association (SMACNA): "HVAC
Systems--Duct Design"
25.03 DEFINITIONS
A. Adjust: To regulate fluid flow rate and air patterns at the terminal equipment, such as to
reduce fan speed or adjust a damper.
B. Balance: To proportion flows within the distribution system, including sub-mains, branches,
and terminals, according to design quantities.
C. Draft: A current of air, when referring to localized effect caused by one or more factors of high
air velocity, low ambient temperature, or direction of airflow, whereby more heat is withdrawn
from a person's skin than is normally dissipated.
D. Procedure: An approach to and execution of a sequence of work operations to yield
repeatable results.
E. Report Forms: Test data sheets for recording test data in logical order.
▪ DIVISION 23 HVAC ▪
▪ PAGE 42 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 43 ▪
PART 26 PRODUCTS
Not Used
PART 27 EXECUTION
27.01 EXAMINATION
A. Examine Contract Documents to discover conditions in systems' designs that may preclude
proper testing, adjusting, and balancing of systems and equipment and submit “Contract
Documents Examination Report”.
1. Contract Documents are defined in the General and Supplementary Conditions of the
Contract.
2. Verify that balancing devices, such as test ports, gage cocks, thermometer wells, flow-
control devices, balancing valves and fittings, and manual volume dampers, are required
by the Contract Documents. Verify that quantities and locations of these balancing
devices are accessible and appropriate for effective balancing and for efficient system
and equipment operation.
3. Examine Engineer’s design data, including HVAC and Plumbing system descriptions,
statements of design assumptions for environmental conditions and systems’ output, and
statements of philosophies and assumptions about HVAC and Plumbing systems and
equipment controls.
B. Examine approved submittal data of HVAC and Plumbing systems and equipment including
sheet metal duct fabrication and plumbing piping shop drawings to ensure that the distribution
system is reasonably complete and sufficiently designed to accurately balance the complete
building. Submit “Submitting Examination Report”.
▪ DIVISION 23 HVAC ▪
▪ PAGE 44 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 45 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 46 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 47 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 48 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 49 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 50 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 51 ▪
PART 28 GENERAL
28.01 SUMMARY
A. Section Includes:
1. Insulation Materials
2. Jackets
3. Accessories and Attachments
4. Vapor Retarders
B. Related Sections:
1. Section 07 84 00 (07840) - Firestopping: Firestopping materials and requirements for
penetrations through fire and smoke barriers.
2. Section 22 07 00 (15083) - Plumbing Insulation
3. Section 23 31 13 (15815) - Metal Ducts: For duct liner.
28.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A666 “Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel
Sheet, Strip, Plate, and Flat Bar”
2. C533 “Standard Specification for Calcium Silicate Block and Pipe Thermal Insulation”
3. C534 “Standard Specification for Preformed Flexible Elastomeric Cellular Thermal
Insulation in Sheet and Tubular Form”
4. C612 “Standard Specification for Mineral Fiber Block and Board Thermal Insulation”
5. C921 “Standard Practice for Determining the Properties of Jacketing Materials for
Thermal Insulation”
6. C1126 “Standard Specification for Faced or Unfaced Rigid Cellular Phenolic Thermal
Insulation”
7. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
B. Military Specifications:
1. MIL-C-20079H “Cloth, Glass; Tape, Textile Glass and Thread, Glass and Wire-
Reinforced Glass”
28.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data:
a. Identify thermal conductivity, thickness, and jackets (both factory and field applied)
for each type of product indicated.
▪ DIVISION 23 HVAC ▪
▪ PAGE 52 ▪
PART 29 PRODUCTS
29.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Mineral-Fiber Insulation:
a. None
2. Mineral-Fiber Blanket Thermal Insulation:
a. None
3. Closed-Cell Phenolic-Foam Insulation:
a. None
4. Flexible Elastomeric Thermal Insulation:
a. None
B. Approved Manufacturers:
1. Mineral-Fiber Insulation:
a. CertainTeed Corp. (610-647-3011)
b. Knauf Insulation. (800-825-4434)
c. Owens-Corning Fiberglas Corp. (800-447-3759)
2. Mineral-Fiber Blanket Thermal Insulation:
a. CertainTeed Corp. (610-647-3011)
▪ DIVISION 23 HVAC ▪
▪ PAGE 53 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 54 ▪
PART 30 EXECUTION
30.01 EXAMINATION
A. Examine substrates and conditions for compliance with requirements for installation and other
conditions affecting performance of insulation application.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
30.02 PREPARATION
A. Surface Preparation: Clean and dry surfaces to receive insulation. Remove materials that will
adversely affect insulation application.
30.03 GENERAL APPLICATION REQUIREMENTS
A. Apply insulation materials, accessories, and finishes according to the manufacturer's written
instructions; with smooth, straight, and even surfaces; and free of voids throughout the length
of ducts and fittings.
B. Refer to schedules at the end of this Section for materials, forms, jackets, and thicknesses
required for each duct system.
C. Use accessories compatible with insulation materials and suitable for the service. Use
accessories that do not corrode, soften, or otherwise attack insulation or jacket in either wet or
dry state.
D. Apply multiple layers of insulation with longitudinal and end seams staggered.
E. Seal joints and seams with vapor-retarder mastic on insulation indicated to receive a vapor
retarder.
F. Keep insulation materials dry during application and finishing.
G. Apply insulation with tight longitudinal seams and end joints. Bond seams and joints with
adhesive recommended by the insulation material manufacturer.
▪ DIVISION 23 HVAC ▪
▪ PAGE 55 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 56 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 57 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 58 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 59 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 60 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 61 ▪
PART 31 GENERAL
31.01 SUMMARY
A. This Section includes the following:
1. The purpose of this section is to specify Division 23 responsibilities in the commissioning
process.
a. The systems to be commissioned are listed in Section 01 91 13.
b. Commissioning requires the participation of Division 23 to ensure that all systems
are operating in a manner consistent with the Contract Documents. The general
commissioning requirements and coordination are detailed in Division 01. Division
23 shall be familiar with all parts of Division 01 and the commissioning plan issued
by the CxA and shall execute all commissioning responsibilities assigned to them in
the Contract Documents.
B. Related Sections:
1. Section 01 91 13 – General Commissioning Requirements
2. Section 23 08 00.01 – HVAC Testing Requirements
3. Section 23 08 00.02 – HVAC Prefunctional Checklists
4. Section 23 08 00.03 – HVAC Sample Functional Test Procedures
5. Section 23 09 00 – Instrumentation and Control of HVAC
6. Section 26 08 00 – Commissioning of Electrical Systems
7. Section 26 08 00.01 – Electrical Systems Testing Requirements
8. Section 26 08 00.02 – Electrical Systems Prefunctional Checklists
9. Section 26 08 00.03 – Electrical Systems Sample Functional Test Procedures
C. Related Work:
1. Refer to Section 01 91 13 for a listing of all Sections where commissioning requirements
are found.
2. Refer to Section 01 91 13 for systems to be commissioned and Sections 23 08 00.01
through 23 08 00.03 for functional testing requirements.
31.02 REFERENCES
A. Associated Air Balance Council (AABC)
B. National Environmental Balancing Bureau (NEBB)
C. American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE)
Publications:
1. ANSI/ASHRAE 111 “Testing, Adjusting, and Balancing of Building HVAC Systems”
31.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
▪ DIVISION 23 HVAC ▪
▪ PAGE 62 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 63 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 64 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 65 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 66 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 67 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 68 ▪
PART 32 PRODUCTS
32.01 TEST EQUIPMENT
A. Division 23 shall provide all test equipment necessary to fulfill the testing requirements of this
Division.
B. Refer to Section 01 91 13 for additional Division 23 requirements.
▪ DIVISION 23 HVAC ▪
▪ PAGE 69 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 70 ▪
PART 34 GENERAL
34.01 SUMMARY
A. This Section includes the following:
1. This Section specifies the functional testing requirements for Division 23 systems and
equipment.
B. Related Sections:
1. Section 01 91 13 – General Commissioning Requirements.
2. Section 23 08 00 – Commissioning of HVAC
3. Section 23 08 00.02 – HVAC Prefunctional Checklists
4. Section 23 08 00.03 – HVAC Sample Functional Test Procedures
34.02 INCLUDED SYSTEMS AND EQUIPMENT
A. The following is a list of the equipment and system test requirements included in this section:
1. Instrumentation and Controls for HVAC
2. Exhaust Fans
3. Terminal Units
a. Fuel Fired Unit Heaters
b. Electric Baseboard
c. Electric Unit Heaters
4. Air Handling Units
a. Gas Fired Make-up Air Units
b. Packaged Outdoor Air Handling Units
c. Split System Air Conditioners
5. Water Source Heat Pump
a. Boilers
b. Heat Pumps
c. Cooling Towers
d. Pumps
e. Heat exchangers
6. Swimming Pool Dehumidifiers
7. Test and Balance Work (TAB)
▪ DIVISION 23 HVAC ▪
▪ PAGE 71 ▪
__ All related equipment has been started up and start-up reports and prefunctional checklists
submitted and approved ready for functional testing:
__ All control system functions for this and all interlocking systems are programmed and operable
per contract documents, including final setpoints and schedules with debugging, loop tuning and
sensor calibrations completed.
__ Piping system flushing complete and required report approved.
__ Water treatment system complete and operational.
__ Vibration control report approved (if required).
__ Test and balance (TAB) complete and approved for the hydronic system.
__ All A/E punchlist items for this equipment corrected.
__ These functional test procedures reviewed and approved by installing contractor.
__ Safeties and operating ranges reviewed by the CxA.
__ Test requirements and sequences of operation attached.
__ Schedules and setpoints attached.
__ False loading equipment, system and procedures ready.
__ Crankcase heaters have been on long enough for immediate startup.
__ Sufficient clearance around equipment for servicing.
__ Record of all values for pre-test setpoints changed to accommodate testing has been made and a
check box provided to verify return to original values (control parameters, limits, delays, lockouts,
schedules, etc.).
▪ DIVISION 23 HVAC ▪
▪ PAGE 72 ▪
PART 35 PRODUCTS
Not Used.
PART 36 EXECUTION
36.01 AIR HANDLER UNITS (AHU)
A. Parties Responsible to Execute Functional Test:
1. Controls contractor: operate the controls to activate the equipment as needed.
2. Mechanical contractor: Witnesses, document testing, assist in testing, and correct
deficiencies.
3. CxA: to witness, direct and document testing.
4. Owners Representative: witness
B. Integral Components or Related Equipment Being Tested:
Prefunctional Checklist
AHU and components (fans, coils, valves, ducts, VFD): Air Handling Units
Ductwork
Energy Recovery Wheel
C. Prerequisites
1. The applicable prerequisite checklist items listed in Section 23 08 00.01 shall be listed on
each functional test form and checked off prior to functional testing. The commissioning
agent will also spot-check misc. items and calibrations on the prefunctional checklists
previously completed by the installer, before the beginning of functional testing.
▪ DIVISION 23 HVAC ▪
▪ PAGE 73 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 74 ▪
Remarks:
SF cfm not required if not monitored
RF cfm not required if not monitored
G. Acceptance Criteria (referenced by function or mode ID):
1. 1 - 21. For the conditions, sequences and modes tested, the AHU, integral components
and related equipment respond to varying loads and changing conditions and parameters
appropriately as expected, as specified and according to acceptable operating practice.
2. 2. AHU with supporting systems shall be able to maintain the SA temperature within 1.0F
either side of the deadband of the current setpoint without excessive hunting.
3. 7. AHU and controls shall control the duct static pressure so that it does not drift more
than an amount equal to 10% of the setpoint value either side of the deadband without
excessive hunting.
H. Sampling Strategy for Identical Units:
1. AHU’s shall not have any sampling--test all units. However, 25% of the units may have
monitoring be the verification method for modes listed with Monitoring or Both as testing
methods, with no less than three units being fully tested per the above requirements.
2. All units not included in the sampling testing and monitoring shall be fully monitored for
the monitoring modes listed above in the monitoring section.
36.02 INSTRUMENTATION AND CONTROLS FOR HVAC (If Applicable)
A. Parties Responsible to Execute Functional Test
▪ DIVISION 23 HVAC ▪
▪ PAGE 75 ▪
Test Method
Manual (demonstration),
Function / Mode Monitoring, Either or Both
MISC. FUNCTIONS
1. All specified functions and features are set up, debugged and fully Verbal discussion of
operable features
2. Power failure and battery backup and power-up restart functions Demonstration
3. Specified trending and graphing features demonstration See equipment trends
4. Global commands features Demonstration
5. Security and access codes Demonstration
6. Occupant over-rides (manual, telephone, key, keypad, etc.) Demonstration
7. O&M schedules and alarms Demonstration
8. Scheduling features fully functional and setup, including holidays Observation in terminal
screens or printouts
9. Date and time setting in central computer and verify field panels read Demonstration
the same time
10. Included features not specified to be setup are installed (list) Demonstration
11. Occupancy sensors and controls Demonstration
12. Demonstrate functionality of field panels using local operator keypads Demonstration of 100% of
and local ports (plug-ins) using portable computer/keypad panels and 10% of ports
13. All graphic screens and value readouts completed Demonstration
14. Setpoint changing features and functions Done during equipment
testing
15. Communications to remote sites Demonstration
▪ DIVISION 23 HVAC ▪
▪ PAGE 76 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 77 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 78 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 79 ▪
Remarks:
SF cfm not required if not monitored
RF cfm not required if not monitored
O. Acceptance Criteria (referenced by function or mode ID):
1. 1 - 21. For the conditions, sequences and modes tested, the AHU, integral components
and related equipment respond to varying loads and changing conditions and parameters
appropriately as expected, as specified and according to acceptable operating practice.
2. 2. AHU with supporting systems shall be able to maintain the SA temperature within 1.0F
either side of the deadband of the current setpoint without excessive hunting.
3. 7. AHU and controls shall control the duct static pressure so that it does not drift more
than an amount equal to 10% of the setpoint value either side of the deadband without
excessive hunting.
P. Sampling Strategy for Identical Units:
1. AHU’s shall not have any sampling--test all units. However, 25% of the units may have
monitoring be the verification method for modes listed with Monitoring or Both as testing
methods, with no less than three units being fully tested per the above requirements.
2. All units not included in the sampling testing and monitoring shall be fully monitored for
the monitoring modes listed above in the monitoring section.
▪ DIVISION 23 HVAC ▪
▪ PAGE 80 ▪
Boilers
Cooling Towers
Pumps
Heat Exchanger
Ductwork
Solids Separator
C. Prerequisites:
1. The applicable prerequisite checklist items listed in Section 23 08 00.01 shall be listed on
each functional test form and checked off prior to functional testing. The commissioning
agent will also spot-check misc. items and calibrations on the prefunctional checklists
previously completed by the installer, before the beginning of functional testing.
D. Functions / Modes Required To Be Tested, Test Methods and Seasonal Test Requirements:
1. The following testing requirements are an addition to and do not replace any testing
requirements elsewhere in this Division.
Function / Mode Test Method Required
Manual, Seasonal
Monitoring, Test1
Either or
Both3
General
1. Test each sequence in the sequence of operations, and other Manual
significant modes and sequences not mentioned; including startup,
shutdown, unnoccupied & manual modes and power failure. Test
functionality of this piece of equipment or system in all control
strategies or interlocks with which it is associated.
In addition to, or as part of (1) above, the following modes or tests are required:
2. Mixed & supply air, & reset temperature control functions. Both
3. Economizer functions. Both Cooling
4. Fan interlocks. Either
▪ DIVISION 23 HVAC ▪
▪ PAGE 81 ▪
12 Sensor and actuator calibration checks: on duct static pressure Manual Design
. sensor on SAT, MAT, OSAT, OSA & RA damper and valve
positions, SF cfm reading with TAB, and other random checks
(EMS readout against hand-held calibrated instrument or
observation must be within specified tolerances)
13 Verify schedules and setpoints to be reasonable and appropriate
.
1
Cooling season, Heating season or Both. “Design” means within 5°of season design (ASHRAE 2 1/2%), or 95% of loading
design. A blank cell denotes no special seasonal test is required and that test can be executed during any season, if condition
simulation is appropriate.
2
Seasonal test not required if seasonal conditions can be adequately simulated.
3
Refer to Special Procedures
E. Special Procedures:
1. Reduced Testing for Smaller Units. For standard application AHU’s less than 15 tons,
the following modifications to the testing requirements apply:
a. Either Manual or Monitoring will satisfy the verification requirement--where Both are
listed, choose one.
b. Testing Modes 6, 8, 11, 13 and 16 are not required.
F. Required Monitoring:
1. All points listed below which are control system monitored points shall be trended by the
controls contractor. Refer to the Monitoring section at the beginning of Section
23 08 00.01 for additional monitoring details.
▪ DIVISION 23 HVAC ▪
▪ PAGE 82 ▪
Remarks:
▪ DIVISION 23 HVAC ▪
▪ PAGE 83 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 84 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 85 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 86 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 87 ▪
2. Verify that final settings of all valves, splitters, dampers and Demonstration
other adjustment devices have been permanently marked by the
TAB Contractor.
3. Verification that the air system is being controlled to the lowest Demonstration
possible static pressure while still meeting design loads, less
diversity. This shall include a review of TAB methods, control
setpoints established by TAB and a physical verification of at
least one leg from fan to diffuser having all balancing dampers
wide open and that during full cooling of all TUs taking off
downstream of the static pressure sensor, the TU on the critical
leg has its damper 90% or more open.
1
Failure of an item is defined as follows:
For air flow of supply and return: a deviation of more than 10% of instrument reading
For minimum outside air flow: 20% of instrument reading (30% for reading at intermediate supply flow for inlet vane or VFD
OSA compensation system using linear proportional control)
For temperatures: a deviation of more than 1°F
For air and water pressures: a deviation of more than 10% of full scale of test instrument reading
For sound pressures: a deviation of more than 3 decibels. (Variations in background noise must be considered)
2
Examples of a “system” are: the air distribution system served by one air handler. Systems can be defined smaller if inaccuracies in
TAB work within the smaller defined system will have little or no impact on connected systems.
3
Cooling season, Heating season or Both. “Design” means within 5°of season design (ASHRAE 2 1/2%), or 95% of loading design. A
blank cell denotes no special seasonal test is required and that test can be executed during any season, if condition simulation is
appropriate.
F. Special Procedures:
1. None
G. Required Monitoring:
1. None
H. Acceptance Criteria:
1. Provided in footnote to test table above.
▪ DIVISION 23 HVAC ▪
▪ PAGE 88 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 89 ▪
PART 37 GENERAL
37.01 SUMMARY
A. This Section includes the following:
1. Prefunctional Checklists (PC) in a form format. The Prefunctional Checklists consist of
Instructions Sheets and Record Sheets.
B. Related Sections:
1. Section 01 33 00 - Submittal and Substitution Procedures
2. Section 01 91 13 – General Commissioning Requirements.
3. Section 23 08 00 – Commissioning of HVAC
4. Section 23 08 00.01– HVAC Testing Requirements
5. Section 23 08 00.03– HVAC Sample Functional Test Procedures
37.02 DESCRIPTION
A. The PC procedures displayed in a form format here are intended to provide the Contractor
with an example of the format and an indication of the rigor of the required prefunctional
checklists (Instruction Sheets and Record Sheets) and documentation for various equipment
types. Though they were not developed specifically for this project, they are generally
applicable.
B. The checklists contain items for both Division 23 and 26 contractors to perform.
C. Those executing the checklists are only responsible to perform items that apply to the specific
application at hand. These checklists do not take the place of the manufacturer’s
recommended checkout and start-up procedures or report. Some checklist procedures may
be redundant of some checkout procedures that will be documented on typical factory field
checkout sheets. Double documenting is required in those cases.
D. Refer to Section 01 91 13 for additional requirements regarding prefunctional checklists,
startup and initial checkout. Items that do not apply should be noted along with the reasons
on the form. If supplied Prefunctional Checklist forms are not used for documenting, one of
similar rigor and clarity shall be used. Contractors assigned responsibility for sections of the
checklist shall be responsible to see that checklist items by their subcontractors are completed
and checked off.
E. The following is a list of the equipment and systems which will require Prefunctional Checklists
(Instruction Sheets and Record Sheets) to be completed by the Contractors.
1. Packaged Outdoor Air Handling Unit (Each Unit)
2. Boilers
3. Water-Source Heat Pumps
4. Cooling Towers
5. Pumps Heat Exchangers
6. Solids Separator
7. Instrumentation and Controls for HVAC (If Applicable)
▪ DIVISION 23 HVAC ▪
▪ PAGE 90 ▪
PART 38 PRODUCTS
Not Used
PART 39 EXECUTION
Not Used
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 91 ▪
PART 40 GENERAL
40.01 SUMMARY
A. This Section includes the following:
1. This Section contains the Functional Testing Procedures for Mechanical Systems
B. Related Sections:
1. Section 01 33 00 - Submittal and Substitution Procedures
2. Section 01 91 13 – General Commissioning Requirements.
3. Section 23 08 00 – Commissioning of HVAC
4. Section 23 08 00.01 – HVAC Testing Requirements
5. Section 23 08 00.02 – HVAC Prefunctional Checklists
40.02 DESCRIPTION
A. The CxA will use the functional testing requirements in Sections 23 08 00 thru 23 08 00.03
and the testing protocols specified in Section 01 91 13 for developing site-specific functional
test procedures and forms for this project. For illustrative purposes, sequences of operation
associated with a few pieces of the equipment for which tests are included are also provided.
B. The following is a list of the equipment and systems which will require Prefunctional Checklists
(Instruction Sheets and Record Sheets) to be completed by the Contractors.
1. Dedicated Outdoor Air Unit (Each Unit)
2. Instrumentation and Controls for HVAC
3. Boilers
4. Water-Source Heat Pumps
5. Cooling Towers
6. Pumps Heat Exchangers
7. Solids Separator
8. Fuel Fired Unit Heater (Each Unit)
9. Electric Unit Heater (Each Unit)
10. Exhaust Fan (Each Unit)
11. Electric Baseboard (Each Space Served)
12. Swimming Pool Dehumidifiers
13. Gas Fired Make-up Air Unit (Each Unit)
C. Refer to Section 01 33 00 - Submittal and Substitution Procedures for Prefunctional
Checklists.
PART 41 PRODUCTS
Not Used
▪ DIVISION 23 HVAC ▪
▪ PAGE 92 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 93 ▪
PART 43 GENERAL
43.01 SUMMARY
A. Section Includes:
1. Control Panels
2. Thermostats
3. Actuators
4. Dampers
5. Wiring
B. Related Sections:
1. Section 23 09 93 (15940) - Sequence of Operations for HVAC Controls
2. Section 23 73 40 (15731) – Gas Fired Makeup Air Units
3. Section 23 74 33 (15733) – Dedicated Outdoor Air Units
4. Section 23 81 13.13 (15735) – Packaged Terminal Air Conditioning Units
5. Section 23 81 13.15 (15738) – Vertical Packaged Terminal Air Conditioning Units
6. Section 23 81 26 (15738) – Split System Air Conditioners
7. Section 23 09 93 (15940) - Sequence of Operations for HVAC Controls
8. Section 25 51 10 – Integrated Automation Control of Guestroom Equipment
9. Section 26 05 19 (16120) – Low Voltage Electrical Power Conductors and Cables
43.02 REFERENCES
A. Air Movement & Control Association International, Inc. (AMCA) Publications:
1. 500D "Laboratory Methods of Testing Dampers for Rating"
B. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. DC 3 “Residential Controls—Electrical Wall-Mounted Room Thermostats”
C. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
2. 90A “Standard for the Installation of Air Conditioning and Ventilating Systems”
D. Sheet Metal and Air Conditioning Contractors' National Association (SMACNA)
E. Underwriter's Laboratories, Inc. (UL) Standards:
1. 486A “Standard For Wire Connectors and Soldering Lugs for Use With Copper
Conductors”
2. 486B “Standard for Wire Connectors for Use With Aluminum Conductors”
▪ DIVISION 23 HVAC ▪
▪ PAGE 94 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 95 ▪
PART 44 PRODUCTS
44.01 CONTROL PANELS
A. MANUFACTURERS
1. Avendra, LLC Preferred Manufacturers:
a. None.
2. Approved Manufacturers:
a. Siemens USA (800-964-4114).
b. Invensys Controls (formally Siebe Environmental Controls) (630-260-3400)
c. Honeywell Inc., Automation and Control Solutions (800-345-6770)
d. Automated Logic Controls, a Unit of United Technologies Corp. (770-429-3000)
B. Local Control Panels: Unitized cabinet with suitable brackets for wall or floor mounting,
located adjacent to each system under automatic control. Provide common keying for all
panels.
1. Fabricate panels of 0.06-inch thick, furniture-quality steel, or extruded-aluminum alloy,
totally enclosed, with hinged doors and keyed lock and with manufacturer's standard
shop-painted finish.
2. Panel-Mounted Equipment: Mounted transformers, relays, and automatic switches;
except safety devices. Mount devices with adjustments accessible through front of panel.
3. Door-Mounted Equipment: Flush-mount (on hinged door) manual switches, including
damper-positioning switches, changeover switches, thermometers, and gages.
44.02 THERMOSTATS
A. Manufacturers:
1. Avendra, LLC Preferred Manufacturers:
a. PSG Controls, Inc. (215-257-3621)
1) “HotelStat Model 5-10506” (Cooling Units with Electric Heat)
2) “HotelStat Model 5-10505” (Heat Pump with backup Electric Heat)
3) “Model T5-10502” (First Company SPX Series VTAC Cooling Units with
Electric Heat)
4) “Model T5-10501HP” (First Company SPX Series VTAC Heat Pump with
backup Electric Heat)
2. Approved Manufacturers:
a. Carrier Corp.; Carrier Air Conditioning Division, United Technologies Corporation
(800-827-7435 x 3496).
▪ DIVISION 23 HVAC ▪
▪ PAGE 96 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 97 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 98 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 99 ▪
PART 45 EXECUTION
45.01 EXAMINATION
A. Verify that duct-, pipe-, and equipment-mounted devices and wiring are installed before
proceeding with installation.
45.02 INSTALLATION
A. Install equipment level and plumb.
B. Verify location of thermostats and other exposed control sensors with plans and room details
before installation, unless otherwise indicated on the mechanical, electrical, or architectural
drawings. Locate all wall mounted devices 60 inches above the floor.
C. Install guards on thermostats in the following locations:
1. Where indicated on drawings.
D. Install damper motors on duct exterior. Do not locate operators exposed to outdoor
temperatures. Arrange actuators to “Fail Safe” in the event of power failure.
E. Install labels and nameplates to identify control components according to Section 23 05 53
(15075) - " Identification for HVAC Piping and Equipment."
45.03 ELECTRICAL WIRING AND CONNECTION INSTALLATION
A. Install raceways, boxes, and cabinets according to Division 26.
B. Install building wire and cable according to Section 26 05 19 (16120) - "Low Voltage Electrial
Power Conductors and Cables."
C. Install signal and communication cable according to Division 26.
1. Conceal cable, except in mechanical rooms and areas where other conduit and piping
are exposed.
2. Install exposed cable in raceway.
3. Bundle and harness multi-conductor instrument cable in place of single cables where
several cables follow a common path.
4. Fasten flexible conductors, bridging cabinets and doors, along hinge side; protect against
abrasion. Tie and support conductors.
5. Number-code or color-code conductors for future identification and service of control
system, except local individual room control cables.
D. Connect manual-reset limit controls independent of manual-control switch positions.
Automatic duct heater resets may be connected in interlock circuit of power controllers.
E. Connect hand-off-auto selector switches to override automatic interlock controls when switch
is in hand position.
F. All wall-mounted space sensors such as thermostats shall be securely anchored to an
electrical box. Do not mount devices directly to the wall surfaces.
G. Identification: Labor or color code each filed wire and conduit at each controller and controlled
device.
▪ DIVISION 23 HVAC ▪
▪ PAGE 100 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 101 ▪
PART 46 GENERAL
46.01 SUMMARY
A. Section Includes:
1. Control Sequences for HVAC Systems, Subsystems, and Equipment.
B. Related Sections:
1. Section 23 09 00 (15900) - Instrumentation and Control for HVAC.
46.02 SEQUENCES
A. (PTAC) Package Terminal Air Conditioning Units.
1. Service: As shown on the drawings.
2. Integral (remote) thermostat shall cycle fan, compressor and electric heat to maintain
space set point temperature.
3. Remove temperature limiters.
B. (FCU) Split System Fan Coil Units
1. Service: As shown on the drawings.
2. Where required, duct mounted addressable Smoke Detector shall stop unit and notify
building fire alarm system upon detection of smoke.
3. Provide complete with fan selector and sub-base with fan ON/OFF/AUTO switch.
4. With system switch in “AUTO” position, heating or cooling shall be provided as required
via automatic changeover, fan shall run continuously.
5. With system switch in “COOL” position, cooling shall cycle on in stages when space
temperature exceeds thermostat set point.
6. With system switch in “HEAT” position, heat shall cycle on in stages when space
temperature is below thermostat set point.
7. In all occupied sequences, the outside air damper shall be set to the minimum position.
C. (EUH) Electric Unit Heaters.
1. Service: As shown on the drawings.
2. Integral thermostat shall cycle fan and resistance heat to maintain space set point
temperature.
D. (ECH) Electric Cabinet Unit Heaters
1. Service: As shown on the drawings.
2. Integral thermostat shall cycle resistance heating, element to maintain space set point
temperature.
E. (EWH) Electric Wall Heaters
1. Service: As shown on the drawings.
▪ DIVISION 23 HVAC ▪
▪ PAGE 102 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 103 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 104 ▪
PART 48 GENERAL
48.01 SUMMARY
A. Section Includes:
1. Pipe, Fittings and Joining Materials.
2. Protective Coating.
3. Piping Specialties.
4. Valves.
B. Related Sections:
1. Section 09 90 00 (09900) - Painting
2. Section 22 34 00 (15486) – Fuel-Fired, Domestic Water Heaters
3. Section 23 05 00 (15050) – Common Work Results for HVAC
4. Section 23 05 29 (15060) - Hangers and Supports for HVAC Piping and Equipment: For
pipe hanger restraints.
5. Section 33 00 00 (02500) - Utility Services: For natural gas service piping, specialties,
and accessories outside the building.
48.02 REFERENCES
A. American National Standards Institute (ANSI) Publications:
1. Z21.15/CGA 9.1 “Manually Operated Gas Valves for Appliances, Appliance Connector
Valves and Hose End Valves”
2. Z21.21 “Automatic Valves for Gas Appliances (same as CSA 6.5)”
3. Z21.24/CGA 6.10 “Connectors for Gas Appliances”
4. Z21.41/CSA 6.9 “Quick Disconnect Devices for Use with Gas Fuel Appliances”
5. Z21.70 “Earthquake Actuated Automatic Gas Shutoff Systems”
B. The American Society of Mechanical Engineers (ASME) Publications:
1. B1.20.1 "Pipe Threads, General Purpose, Inch"
2. B16.1 “Cast Iron Pipe Flanges and Flanged Fittings”
3. B16.3 “Malleable Iron Threaded Fittings”
4. B16.5 “Pipe Flanges and Flanged Fittings”
5. B16.9 “Factory-Made Wrought Buttwelding Fittings”
6. B16.11 “Forged Fittings, Socket-Welding and Threaded”
7. B16.24 “Cast Copper Alloy Pipe Flanges and Flanged Fittings: Classes 150, 300, 400,
600, 900, 1500 and 2500”
8. B16.33 “Manually Operated Metallic Gas Valves for Use in Gas Piping Systems up to 125
psi (Sizes NPS ½ through NPS 2)”
▪ DIVISION 23 HVAC ▪
▪ PAGE 105 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 106 ▪
PART 49 PRODUCTS
49.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Corrugated, Stainless-Steel Tubing Systems:
a. None.
2. Appliance Connector Valves:
a. None.
3. Gas Valves, NPS 2 (DN 50) and Smaller:
a. None.
4. Plug Valves, NPS 2-1/2 (DN 65) and Larger:
a. None.
5. Automatic Gas Valves:
a. None.
6. UL -Listed Earthquake Valves:
a. None.
7. Service Pressure Regulators:
a. None.
B. Approved Manufacturers:
1. Corrugated, Stainless-Steel Tubing Systems:
a. Omega Flex, Inc. (800-355-1039)
b. Titeflex Corporation (800-765-2525)
c. Tru-Flex Metal Hose Corp. (800-255-6291)
d. B&K Industries, Inc. (800-782-2385)
e. Cimberio Valve Co. (877-228-9246)
f. Conbraco Industries, Inc.; Apollo Div. (704-841-6000)
2. Gas Valves, NPS 2 (DN 50) and Smaller:
a. Crane Valves (800-323-3679)
b. Milwaukee Valve Co., Inc. (262-432-2700)
c. Mueller Co.; Mueller Gas Products Div. (217-423-4471)
3. Plug Valves, NPS 2-1/2 (DN 65) and Larger:
a. Milliken Valve Co., Inc. (610-861-8803)
b. Mueller Co.; Mueller Gas Products Div. (217-423-4471)
4. Automatic Gas Valves:
a. ASCO General Controls (800-524-1023)
▪ DIVISION 23 HVAC ▪
▪ PAGE 107 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 108 ▪
PART 50 EXECUTION
50.01 PREPARATION
A. Comply with NFPA 54 (ANSI Z223.1), "Prevention of Accidental Ignition" Paragraph.
50.02 SERVICE ENTRANCE PIPING
A. Extend fuel gas piping and connect to fuel gas distribution for service entrance to building.
1. Exterior fuel gas distribution system piping, service pressure regulator, and service meter
will be provided by gas utility.
B. Install strainer upstream from each earthquake valve. Refer to Section 22 10 13 - "Plumbing
Specialties" for strainers.
50.03 CONCRETE BASE INSTALLATION
A. Locate bases at service meters and service regulators.
B. Excavate earth and make level beds to support bases. Set bases level with top surface
projecting approximately 3 inches above grade.
50.04 PIPING APPLICATIONS
A. Flanges, unions, transition, and special fittings with pressure ratings same as or higher than
system pressure rating may be used in applications below, unless otherwise indicated.
B. Fuel Gas Piping, 0.5 psig or Less: Use the following:
1. NPS 3/4 (DN 20) steel pipe, malleable-iron threaded fittings, and threaded joints.
2. NPS 3/4 and NPS 1 (DN 20 and DN 25): Steel pipe, malleable-iron threaded fittings, and
threaded joints.
a. Option: Soft copper tube, copper fittings, and brazed joints may be used for runouts
at individual appliances.
▪ DIVISION 23 HVAC ▪
▪ PAGE 109 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 110 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 111 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 112 ▪
PART 51 GENERAL
51.01 SUMMARY
A. Section Includes:
1. Piping, special-duty valves, and hydronic specialties for hot-water heating and condenser
water systems; makeup water for these systems; drain lines; and condensate drain
piping.
B. Related Sections:
1. Section 01 81 13 - Sustainable Design Requirements
2. Section 23 05 00 - Common Work Results for HVAC: For general piping materials and
installation requirements.
3. Section 23 05 29 - Hangers and Supports for HVAC Piping and Equipment: For pipe
supports, product descriptions, and installation requirements. Hanger and support
spacing is specified in this Section.
4. Section 23 05 23 - General-Duty Valves for HVAC Piping: For general-duty ball, butterfly,
and check valves.
5. Section 23 05 19 - Meters and Gages for HVAC Piping: For thermometers, flow meters,
and pressure gages.
6. Division 23 - HVAC equipment Sections that specify meters and gages as part of factory-
fabricated equipment.
51.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and Seamless"
2. A126 "Standard Specification for Gray Iron Castings for Valves, Flanges, and Pipe
Fittings"
3. A234 “Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel
for Moderate and High Temperature Service”
4. A536 "Standard Specification for Ductile Iron Castings"
5. A733 ”Standard Specification for Welded and Seamless Carbon Steel and Austenitic
Stainless Steel Pipe Nipples”
6. B32 "Standard Specification for Solder Metal"
B. The American Society of Mechanical Engineers (ASME) Publications:
1. “Boiler and Pressure Vessel Code”
2. B16.4 “Gray Iron Threaded Fittings: (Classes 125 and 250)”
3. B16.5 “Pipe Flanges and Flanged Fittings”
4. B16.22 “Wrought Copper and Copper Alloy Solder Joint Pressure Fittings”
5. B16.39 “Malleable Iron Threaded Pipe Unions”
▪ DIVISION 23 HVAC ▪
▪ PAGE 113 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 114 ▪
PART 52 PRODUCTS
52.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Grooved Mechanical-Joint Fittings and Couplings:
a. None
2. Flow Control Valves:
a. None
3. Globe Type Check Valves at Pumps:
a. None
4. Safety Relief Valves:
a. None
5. Diaphragm-Type Expansion Tanks:
a. None
6. Air Separators:
a. None
7. Make-up Water Valves:
a. None
8. Chemical Water Treatment Products:
a. None
B. Approved Manufacturers:
1. Grooved Mechanical-Joint Fittings and Couplings:
a. Victaulic Company of America. (800-742-5842)
b. Tyco Grinnell Mechanical Products. (800-558-5236)
c. Approved Substitution.
▪ DIVISION 23 HVAC ▪
▪ PAGE 115 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 116 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 117 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 118 ▪
PART 53 EXECUTION
53.01 PIPE APPLICATIONS
A. Hot Water and Condenser Water System, 2-Inch NPS and Smaller: Use Schedule 40 steel
pipe with Class 125/150 threaded joints or Type L drawn-temper copper tubing with soldered
joints.
B. Hot Water and Condenser Water System, 2-1/2-Inch NPS and Larger: Use Schedule 40 steel
pipe with welded and flanged joints or grooved mechanical joints rated at Class 125/150.
C. Cold Water Make-Up Piping, All Sizes: Use Type L drawn-temper copper tubing with soldered
joints.
D. Condensate Drain Piping, All Sizes: Use Type L drawn-temper copper tubing with soldered
joints and Type DWV fittings.
53.02 VALVE APPLICATIONS
A. General-Duty Valve Applications: Unless otherwise indicated, use the following valve types:
1. Shutoff Duty: Use ball, and butterfly valves.
2. Throttling Duty: Use flow control valves.
B. Install shutoff-duty valves at each branch connection to supply and return mains, at supply
and return connections to each piece of equipment, and elsewhere as indicated.
C. Install flow control valves and balancing cocks on the outlet of each coil, circulating pump and
elsewhere as required to facilitate system balancing.
D. Install drain valves at low points in mains, risers, branch lines, and elsewhere as required for
system drainage.
E. Install check valves on each pump discharge and elsewhere as required to control flow
direction.
F. Install safety relief valves on heat exchangers and elsewhere as required by ASME Boiler and
Pressure Vessel Code. Pipe discharge to floor without valves. Comply with ASME Boiler and
Pressure Vessel Code, Section VIII, Division 1, for installation requirements.
G. Install make-up water valves on domestic cold water piping to the hydronic systems.
53.03 PIPING INSTALLATIONS
A. Install piping according to Section 23 05 00 “Common Work Results for HVAC".
B. Locate groups of pipes parallel to each other, spaced to permit applying insulation and
servicing of valves.
▪ DIVISION 23 HVAC ▪
▪ PAGE 119 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 120 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 121 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 122 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 123 ▪
END OF SECTION
▪ DIVISION 23 HVAC ▪
▪ PAGE 124 ▪
PART 54 GENERAL
54.01 SUMMARY
A. Section Includes:
1. Polypropylene hydronic piping system, including associated fittings, and specialties within
the building.
B. Related Sections:
1. Section 01 81 13 - Sustainable Design Requirements
2. Section 23 05 00 - Common Work Results for HVAC: For general piping materials and
installation requirements.
3. Section 23 05 29 - Hangers and Supports for HVAC Piping and Equipment: For pipe
supports, product descriptions, and installation requirements. Hanger and support
spacing is specified in this Section.
4. Section 23 05 23 - General-Duty Valves for HVAC Piping: For general-duty ball, butterfly,
and check valves.
5. Section 23 05 19 - Meters and Gages for HVAC Piping: For thermometers, flow meters,
and pressure gages.
6. Division 23 - HVAC equipment Sections that specify meters and gages as part of factory-
fabricated equipment.
54.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. E84 "Standard Test Method for Surface Burning Characteristics of Building Materials"
2. F2389 “Standard Specification for Pressure-rated Polypropylene (PP) Piping Systems”
B. Canadian Standards Association (CSA) Publications:
1. CSA B137.11 “Polypropylene (PP-R) Pipe and Fittings for Pressure Applications”
C. NSF Internatinal (NSF) Publications:
1. NSF/ANSI 14 “Plastics Piping System Components and Related Materials”
D. Underwriter's Laboratories, Inc. (UL) Standards:
1. CAN/ULC-S102.2-03 “Standard Method of Test for Surface Burning Characteristics of
Flooring, Floor Coverings, and Miscellaneous Materials and Assemblies”
54.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
1. Product Data: Material list naming each product to be used identified by manufacturer
and product number.
2. Shop Drawings: Detail fabrication of pipe anchors, hangers, special pipe support
assemblies, alignment guides, expansion joints and loops, and their attachment to the
▪ DIVISION 23 HVAC ▪
▪ PAGE 125 ▪
PART 55 PRODUCTS
55.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Polypropylene Piping and Accessories:
▪ DIVISION 23 HVAC ▪
▪ PAGE 126 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 127 ▪
PART 56 EXECUTION
56.01 PIPING APPLICATIONS
A. Install listed pipe materials and joining methods below in the following applications:
1. Hot Water and Condenser Water System, All Sizes: Use polypropylene (PP-R) piping in
SDR 6, 7.4 or 11 based on the required minimum pressure rating and use temperature.
56.02 FUSION WELDING OF JOINTS
A. Install fittings and joints using socket-fusion, elecrofusion, or butt-fusion as applicable for the
fitting or joint type. All fusion-weld joints shall be made in accordance with the pipe and fitting
manufacturer’s specifications and product standards.
B. Fusion-weld tooling, welding machines, and electrofusion devices shall be as specified by the
pipe and fittings manufacturer.
C. Prior to joining, the pipe and fittings shall be prepared in accordance with F 2389 and the
manufacturer’s specifications.
D. Joint preparation, setting and alignment, fusion process, cooling times and working pressure
shall be in accordance with the pipe and fitting manufacturer’s specifications.
56.03 VALVE APPLICATIONS
A. Install ball valves close to main on each branch and riser serving 2 or more equipment
connections and where indicated.
B. Install ball valves on inlet to each equipment item and elsewhere as indicated.
C. Install drain valve at base of each riser, at low points of horizontal runs, and where required to
drain hydronic piping system.
D. Install swing check valve on discharge side of each pump and elsewhere as indicated.
E. Install ball valves in each hot-water circulating loop and discharge side of each pump.
56.04 PIPING INSTALLATIONS
A. Install hangers and supports at intervals specified in the applicable Plumbing or Mechanical
Code and as recommended by pipe manufacturer.
B. Support vertical piping at each floor and as specified in the applicable Plumbing or Mechanical
Code.
▪ DIVISION 23 HVAC ▪
▪ PAGE 128 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 129 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 130 ▪
PART 57 GENERAL
57.01 SUMMARY
A. Section Includes:
1. Vertical Inline Pumps.
2. End-Suction Pumps.
B. Related Sections:
1. Section 01 81 13 - Sustainable Design Requirements
2. Section 23 05 00 - Common Work Results for HVAC.
3. Section 23 05 13 - Common Motor Requirements for HVAC Equipment
4. Section 23 05 48 - Vibration and Seismic Controls for HVAC Piping and Equipment
5. Section 23 05 93 - Testing, Adjusting, and Balancing for HVAC
6. Section 23 31 13.51 - Hydronic Piping - Metal
7. Section 23 31 13.52 - Hydronic Piping - Plastic
57.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A36 “Standard Specification for Carbon Structural Steel”
2. B584-09a “Standard Specification for Copper Alloy Sand Castings for General
Applications”
B. Hydraulic Institute Publications:
1. ANSI/HI 1.1-1.2 "Centrifugal Pumps for Nomenclature and Definition"
C. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
D. Underwriter's Laboratories, Inc. (UL) Standards:
1. 486A “Standard For Wire Connectors and Soldering Lugs for Use With Copper
Conductors”
2. 486B “Standard for Wire Connectors for Use With Aluminum Conductors”
3. 778 “Standard for Motor-Operated Water Pumps”
57.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
1. Product Data: Include certified performance curves and rated capacities; shipping,
installed, and operating weights; furnished specialties; final impeller dimensions; and
accessories for each type of product indicated. Indicate pump's operating point on
curves.
▪ DIVISION 23 HVAC ▪
▪ PAGE 131 ▪
PART 58 PRODUCTS
58.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Vertical In-Line Pumps:
a. None
2. End-Suction Pumps:
a. None
B. Approved Manufacturers:
1. Vertical In-Line Pumps:
a. "Series 4360"; Armstrong Pumps, Inc. (716-693-8813)
b. "Series 80"; Bell & Gossett ITT; Div. of ITT Fluid Technology Corp. (847-966-3700)
▪ DIVISION 23 HVAC ▪
▪ PAGE 132 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 133 ▪
PART 59 EXECUTION
59.01 EXAMINATION
A. Examine equipment foundations and anchor-bolt locations for compliance with requirements
for installation.
1. Examine roughing-in for piping systems to verify actual locations of piping connections
before pump installation.
2. Examine foundations and bases for suitable conditions where pumps are to be installed.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
59.02 PUMP INSTALLATION
A. Install pumps according to manufacturer's written instructions.
1. Install pumps according to HI 1.1-1.2, "Centrifugal Pumps for Nomenclature and
Definitions."
B. Install pumps to provide access for periodic maintenance, including removing motors,
impellers, couplings, and accessories.
C. Support pumps and piping separately so piping is not supported by pumps.
D. Set base-mounted pumps on concrete foundation. Disconnect coupling halves before setting.
Do not reconnect couplings until alignment operations have been completed.
1. Support pump baseplate on rectangular metal blocks and shims, or on metal wedges with
small taper, at points near foundation bolts to provide a gap of 3/4 to 1-1/2 inches
between pump base and foundation for grouting.
2. Adjust metal supports or wedges until pump and driver shafts are level. Check coupling
faces and suction and discharge flanges of pump to verify that they are level and plumb.
59.03 ALIGNMENT
A. Align pump and motor shafts and piping connections after setting them on foundations, after
grout has been set and foundation bolts have been tightened, and after piping connections
have been made.
▪ DIVISION 23 HVAC ▪
▪ PAGE 134 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 135 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 136 ▪
PART 60 GENERAL
60.01 SUMMARY
A. Section Includes:
1. Tubes.
2. Fittings.
3. Joining Materials.
4. Specialties.
B. Related Sections:
1. Section 07 92 00 (07920) - Joint Sealants
2. Section 07 84 00 (07840) - Firestopping: Firestopping materials and requirements for
penetrations through fire and smoke barriers.
3. Section 23 05 00 (15050) – Common Work Results for HVAC
4. Section 23 05 29 (15060) - Hangers and Supports for HVAC Piping and Equipment: for
pipe hanger restraints.
5. Section 23 05 53 (15075) – Identification for HVAC Piping and Equipment
6. Section 23 07 00 (15083) - HVAC Insulation
60.02 REFERENCES
1. ASHRAE 15, "Safety Code for Mechanical Refrigeration."
B. The American Society of Mechanical Engineers (ASME) Publications:
1. “Boiler and Pressure Vessel Code”
2. B16.22 “Wrought Copper and Copper Alloy Solder Joint Pressure Fittings”
3. B31.5 “Refrigeration Piping and Heat Transfer Components”
C. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. B88 “Standard Specification for Seamless Copper Water Tube”
2. B280 “Standard Specification for Seamless Copper Tube for Air Conditioning and
Refrigeration Field Service”
D. American Welding Society (AWS) Publications:
1. A5.8 "Specification for Filler Metals For Brazing And Braze Welding"
E. Manufacturers Standardization Society of the Valve and Fittings Industry. (MSS) Publications:
1. SP-69 “ANSI/MSS Edition Pipe Hangers and Supports - Selection and Application”
F. Underwriter's Laboratories, Inc. (UL) Standards:
1. 207 “Standard for Refrigerant-Containing Components and Accessories, Nonelectrical”
2. 429 “Standard for Electrically Operated Valves”
▪ DIVISION 23 HVAC ▪
▪ PAGE 137 ▪
PART 61 PRODUCTS
61.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Refrigerant Valves and Specialties:
a. None.
B. Approved Manufacturers:
1. Refrigerant Valves and Specialties:
a. Henry Pratt Company, Subsidiary of Mueller Water Products, Inc. (877-436-7966)
b. Parker-Hannifin Corporation; Refrigeration & Air Conditioning Division (800-272-
7537)
c. Sporlan Valve Company (314-647-2775)
61.02 TUBES
A. Use pre-charged tubing where possible.
B. Soft Copper Tube: ASTM B280, Type ACR, annealed temper.
▪ DIVISION 23 HVAC ▪
▪ PAGE 138 ▪
PART 62 EXECUTION
62.01 EXAMINATION
A. Examine roughing-in for compliance with requirements for installation tolerances and other
conditions affecting performance of refrigerant piping. Do not proceed with installation until
unsatisfactory conditions have been corrected.
62.02 APPLICATIONS
A. Above ground, within Building: Type ACR drawn-copper tubing.
B. Below ground for 2-Inch NPS (DN50) and Smaller: Type L (Type B) annealed-copper tubing
installed in schedule 40 PVC sleeve.
62.03 INSTALLATION
A. Install refrigerant piping according to ASHRAE 15.
B. Basic piping installation requirements are specified in Section 23 05 00 (15050) - "Common
Work Results For HVAC."
C. Install piping in short and direct arrangement, with minimum number of joints, elbows, and
fittings.
D. Arrange piping to allow normal inspection and service of compressor and other equipment.
Install valves and specialties in accessible locations to allow for service and inspection.
E. Install piping with adequate clearance between pipe and adjacent walls and hangers, or
between pipes for insulation installation. Use sleeves through floors, walls, or ceilings, sized
to permit installation of full-thickness insulation. Maximum fill: 40%
F. Below ground, install copper tubing in schedule 40 PVC conduit. Vent conduit outdoors.
G. Insulate suction lines.
1. Do not install insulation until system testing has been completed and all leaks have been
eliminated.
H. Install branch lines to parallel compressors of equal length, and pipe identically and
symmetrically.
I. Install copper tubing in rigid or flexible conduit in locations where copper tubing will be
exposed to mechanical injury.
J. Slope refrigerant piping as follows:
▪ DIVISION 23 HVAC ▪
▪ PAGE 139 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 140 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 141 ▪
PART 63 GENERAL
63.01 SUMMARY
A. Section Includes:
1. Sheet Metal Materials.
2. Duct Liner.
3. Sealant Materials.
4. Hangers and Supports.
5. Duct Fabrication.
B. Related Sections:
1. Section 07 81 33 (07845) – Mineral-Fiber Fireproofing: For fire-resistant grease duct
wrap assemblies.
2. Section 07 84 00 (07840) - Firestopping: For fire-resistant sealants for use around duct
penetrations and fire-damper installations in fire-rated floors, partitions, and walls.
3. Section 08 31 00 (08310) - Access Doors: For wall- and ceiling-mounted access doors
for access to concealed ducts.
4. Section 23 05 93 (15950) - Testing, Adjusting, and Balancing: For air balancing and final
adjusting of manual-volume dampers.
5. Section 23 07 00 (15081) – HVAC Insulation: For duct insulation.
6. Section 23 33 00 (15820) – Air Duct Accessories: For dampers, sound-control devices,
duct-mounted access doors and panels, turning vanes, and flexible ducts.
7. Section 23 37 00 (15850) - Air Outlets and Inlets
63.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A36 “Standard Specification for Carbon Structural Steel”
2. A336 “Standard Specification for Alloy Steel Forgings for Pressure and High-
Temperature Parts”
3. A480 “Standard Specification for General Requirements for Flat-Rolled Stainless and
Heat-Resisting Steel Plate, Sheet, and Strip”
4. A653 "Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron
Alloy-Coated (Galvannealed) by the Hot-Dip Process”
5. C168 “Standard Terminology Relating to Thermal Insulation”
6. C411 “Standard Test Method for Hot-Surface Performance of High-Temperature Thermal
Insulation”
7. C916 “Standard Specification for Adhesives for Duct Thermal Insulation”
8. C920 “Standard Specification for Elastomeric Joint Sealants”
▪ DIVISION 23 HVAC ▪
▪ PAGE 142 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 143 ▪
PART 64 PRODUCTS
64.01 SHEET METAL MATERIALS
A. Galvanized, Sheet Steel: Lock-forming quality; ASTM A653, G90 coating designation; mill-
phosphatized finish for surfaces of ducts exposed to view.
B. Carbon-Steel Sheets: ASTM A366, cold-rolled sheets; commercial quality; with oiled,
exposed matte finish.
C. Stainless Steel: ASTM A480, Type 316, sheet form with No. 4 finish for surfaces of ducts
exposed to view; and Type 304, sheet form with No. 1 finish for concealed ducts.
D. Reinforcement Shapes and Plates: Galvanized steel reinforcement where installed on
galvanized, sheet metal ducts; compatible materials for aluminum and stainless-steel ducts.
E. Tie Rods: Galvanized steel, 1/4-inch minimum diameter for 36-inch length or less; 3/8-inch
minimum diameter for lengths longer than 36 inches.
64.02 DUCT LINER
A. General: Comply with NFPA 90A or NFPA 90B and NAIMA's "Fibrous Glass Duct Liner
Standard."
B. Materials: ASTM C1071 with coated surface exposed to airstream to prevent erosion of glass
fibers.
1. Thickness: 1 inch.
2. Thermal Conductivity (k-Value): 0.26 at 75 deg F mean temperature.
3. Fire-Hazard Classification: Maximum flame-spread rating of 25 and smoke-developed
rating of 50, when tested according to ASTM C411.
4. Liner Adhesive: Comply with NFPA 90A or NFPA 90B and ASTM C916.
5. Mechanical Fasteners: Galvanized steel, suitable for adhesive attachment, mechanical
attachment, or welding attachment to duct without damaging liner when applied as
recommended by manufacturer and without causing leakage in duct.
a. Tensile Strength: Indefinitely sustain a 50-lb- tensile, dead-load test perpendicular
to duct wall.
▪ DIVISION 23 HVAC ▪
▪ PAGE 144 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 145 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 146 ▪
PART 65 EXECUTION
65.01 DUCT INSTALLATION - GENERAL
A. Duct installation requirements are specified in other Division 23 Sections. Drawings indicate
general arrangement of ducts, fittings, and accessories.
B. Construct and install each duct system for the specific duct pressure classification indicated.
C. Install round ducts in lengths not less than 12 feet, unless interrupted by fittings.
D. Install ducts with fewest possible joints.
E. Install fabricated fittings for changes in directions, changes in size and shape, and
connections.
F. Install couplings tight to duct wall surface with a minimum of projections into duct.
G. Install ducts, unless otherwise indicated, vertically and horizontally, parallel and perpendicular
to building lines; avoid diagonal runs.
H. Install ducts close to walls, overhead construction, columns, and other structural and
permanent enclosure elements of building.
I. Install ducts with a clearance of 1 inch, plus allowance for insulation thickness.
J. Conceal ducts from view in finished spaces. Do not encase horizontal runs in solid partitions,
unless specifically indicated.
K. Coordinate layout with suspended ceiling, fire- and smoke-control dampers, lighting layouts,
and similar finished work.
L. Electrical Equipment Spaces: Route ductwork to avoid passing through transformer vaults,
electrical equipment spaces and enclosures, and through elevator equipment rooms.
M. Non-Fire-Rated Partition Penetrations: Where ducts pass through interior partitions and
exterior walls, and are exposed to view, conceal space between construction opening and
duct or duct insulation with sheet metal flanges of same metal thickness as duct. Overlap
opening on four sides by at least 1-1/2 inches.
▪ DIVISION 23 HVAC ▪
▪ PAGE 147 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 148 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 149 ▪
PART 66 GENERAL
66.01 SUMMARY
A. Section includes:
1. Manual-Volume Dampers
2. Fire Dampers
3. Turning Vanes
4. Duct-Mounted Access Doors
5. Flexible Connectors
6. Flexible Ducts
7. Zone Control Exhaust Terminals
8. Accessories
B. Related Sections:
1. Section 08 31 00 (08310) - Access Doors and Panels: For wall- and ceiling-mounted
access doors and panels.
2. Section 23 05 53 - Identification for HVAC Piping and Equipment.
3. Section 23 05 93 - Testing, Adjusting, and Balancing for HVAC.
4. Section 23 37 00 (15850) - Air Outlets and Inlets.
5. Section 25 51 00 – Integrated Automation Control of Guestroom Equipment
6. Section 28 31 00 (13850) - Fire Alarm and Detection Systems: For duct-mounted fire
and smoke detectors.
66.02 REFERENCES
A. North American Insulation Manufacturers Association (NAIMA) Publications:
1. AH124 "Fibrous Glass Duct Liner Standard."
B. National Fire Protection Association (NFPA) Publications:
1. 90A “Standard for the Installation of Air Conditioning and Ventilating Systems”
2. 90B “Standard for the Installation of Warm Air Heating and Air-Conditioning Systems”
C. Sheet Metal and Air Conditioning Contractors' National Association (SMACNA) Publications:
1. “Fire Damper and Heat Stop Guide for Air Handling Systems”
2. “HVAC Duct Construction Standards—Metal and Flexible”
D. Underwriter's Laboratories, Inc. (UL) Standards:
1. 181 “Standard for Factory-Made Air Ducts and Air Connectors”
2. 181B “Closure Systems for Use With Flexible Air Ducts and Air Connectors”
3. 555 “Fire Dampers”
▪ DIVISION 23 HVAC ▪
▪ PAGE 150 ▪
PART 67 PRODUCTS
67.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Manual Volume Dampers
▪ DIVISION 23 HVAC ▪
▪ PAGE 151 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 152 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 153 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 154 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 155 ▪
PART 68 EXECUTION
68.01 INSTALLATION
A. Install duct accessories according to applicable details shown in SMACNA's "HVAC Duct
Construction Standards—Metal and Flexible" for metal ducts and NAIMA's "Fibrous Glass
Duct Construction Standards" for fibrous-glass ducts.
B. Install volume dampers in lined duct; avoid damage to and erosion of duct liner.
C. Provide test holes at fan inlet and outlet and elsewhere as indicated.
D. Install fire dampers according to manufacturer's UL-approved written instructions.
1. Install fusible links in fire dampers.
E. Install duct access panels for access to both sides of duct coils. Install duct access panels
downstream from volume dampers, fire dampers, turning vanes, automatic dampers, smoke
detectors, outside and exhaust air plenums equipment, and other locations as indicated.
1. Install duct access panels to allow access to interior of ducts for cleaning, inspecting,
adjusting, and maintaining accessories and terminal units.
2. Install access panels on side of duct where adequate clearance is available.
F. Label access doors according to Section 23 05 53 "Identification for HVAC Piping and
Equipment."
G. Provide flexible connections at fan and building joints.
H. Install automatic dampers supplied by the automatic temperature control system
manufacturer. Notch end of rod and label duct/casing to indicate open and closed blade
position.
I. Install zone control exhaust terminals and make required control and electrical connections.
J. Provide volume dampers at following locations:
1. In all duct splits and branch connections of supply, return, and exhaust systems.
2. Ducts connecting to common plenums.
3. Ducts serving single outlet.
4. At open return duct in hung ceiling.
5. Other locations as indicated on drawings.
K. Provide access doors in following locations and as indicated on the Drawings.
1. Automatic dampers: linkage side.
2. Main balancing dampers.
3. Fire dampers.
▪ DIVISION 23 HVAC ▪
▪ PAGE 156 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 157 ▪
PART 69 GENERAL
69.01 SUMMARY
A. Section Includes:
1. Centrifugal Roof Ventilators.
2. Up-blast Roof Exhaust Fans (Kitchen Hood Exhaust).
3. Ceiling-Mounted Ventilators.
4. In-Line Centrifugal Fans.
5. Attic Ventilators
6. Motors
7. Factory Finishes
8. Quality Control
B. Related Sections:
1. Section 23 05 00 (15050) – Common Work Results for HVAC
2. Section 23 05 48 (15070) - Mechanical Sound, Vibration and Seismic Control.
3. Section 23 05 53 (15075) – Identification for HVAC Piping and Equipment
4. Section 23 05 13 (15090) – Common Motor Requirements for HVAC Equipment
5. Section 23 05 93 (15950) - Testing, Adjusting, and Balancing for HVAC
6. Section 23 09 00 (15900) – Instrumentation and Control for HVAC
7. Section 26 29 13 (16420) - Enclosed Controllers: For motor starters.
8. Section 26 51 00 (16510) – Interior Lighting: Light Fixture Matrix For Guestroom Toilet
Ceiling Mounted Ventilators.
C. Products Supplied But Not Installed Under This Section:
1. Roof curbs for roof-mounted exhaust fans.
69.02 REFERENCES
A. Air Movement & Control Association International, Inc. (AMCA) Publications:
1. 99 "Standards Handbook" (Revised 2003)
2. 210 "Laboratory Methods of Testing Fans for Aerodynamic Performance Rating"
3. 300 "Reverberant Room Method for Sound Testing of Fans"
4. 301 "Methods for Calculating Fan Sound Ratings from Laboratory Test Data"
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. B117 "Standard Practice for Operating Salt Spray (Fog) Apparatus"
C. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. MG 1 “Motors and Generators”
▪ DIVISION 23 HVAC ▪
▪ PAGE 158 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 159 ▪
PART 70 PRODUCTS
70.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Centrifugal Roof Ventilators:
a. None.
2. Up-blast Roof Exhaust Fans:
a. None.
3. Ceiling-Mounted Ventilators:
a. None.
4. In-Line Centrifugal Fans:
a. None.
5. Attic Ventilators:
a. None.
B. Approved Manufacturers:
1. Centrifugal Roof Ventilators:
a. Carnes Co. (608-845-6411)
b. Loren Cook Company (417-869-6474)
▪ DIVISION 23 HVAC ▪
▪ PAGE 160 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 161 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 162 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 163 ▪
PART 71 EXECUTION
71.01 EXAMINATION
A. Examine areas and conditions for compliance with requirements of installation tolerances and
other conditions affecting performance of the power ventilators. Do not proceed with
installation until unsatisfactory conditions have been corrected.
71.02 INSTALLATION
A. Install power ventilators according to manufacturer's written instructions.
B. Support units using the vibration-control devices indicated. Vibration-control devices are
specified in Section 23 05 48 - "Vibration, and Seismic Control for HVAC Piping and
Equipment."
1. Secure roof-mounted fans to roof curbs with cadmium-plated hardware.
a. Installation of roof curbs is specified in Division 07 Sections.
2. Suspend units from structural steel support frame using threaded steel rods and vibration
isolation springs.
3. Ceiling Units: Suspend units from structure using steel wire or metal straps.
C. Install units with clearances for service and maintenance.
D. Label units according to requirements specified in Section 23 05 53 "Identification for HVAC
Piping and Equipment."
71.03 CONNECTIONS
A. Duct installation and connection requirements are specified in other Division 15 Sections.
Drawings indicate the general arrangement of ducts and duct accessories. Make final duct
connections with flexible connectors.
B. Electrical: Conform to applicable requirements in Division 26 Sections.
▪ DIVISION 23 HVAC ▪
▪ PAGE 164 ▪
▪ DIVISION 23 HVAC ▪
▪ PAGE 165 ▪
END OF SECTION
Revision Log
▪ DIVISION 23 HVAC ▪
▪ PAGE 166 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Supporting Devices For Electrical Components.
2. Electricity-Metering Components.
3. Concrete Equipment Bases.
4. Electrical Demolition.
5. Cutting And Patching For Electrical Construction.
6. Touchup Painting.
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-In-Place Concrete.
2. Section 07 84 00 (07840) - Firestopping.
3. Section 09 90 00 (09900) - Painting.
1.02 REFERENCES
A. American Welding Society (AWS) Publications:
1. D1.1 "Structural Welding Code - Steel"
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and Seamless"
C. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
D. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. 250 “Enclosures for Electrical Equipment (1000 Volts Maximum)”
1.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data: For electricity-metering equipment.
2. Shop Drawings: Dimensioned plans and sections or elevation layouts of electricity-
metering equipment.
3. Field Test Reports: Indicate and interpret test results for compliance with performance
requirements.
1.04 QUALITY ASSURANCE
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
B. Comply with NFPA 70.
C. All work to be in accordance with latest requirements of the N.E.C. and all other applicable
codes and regulations of authorities having jurisdiction over the work.
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 1 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 2 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 3 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 4 ▪
END OF SECTION
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 5 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 6 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 7 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 8 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 9 ▪
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 10 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 11 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 12 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 13 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 14 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 15 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 16 ▪
PART 10 GENERAL
10.01 SUMMARY
Note: Edit list below to suit Project.
A. Section Includes:
1. Raceways include the following:
a. RMC.
b. PVC, Schedule 40 or 80.
c. EMT.
d. FMC.
e. LFMC.
f. LFNC.
g. RNC.
h. Wireways.
Note: Delete surface raceway if not required.
i. Surface raceways.
2. Boxes, enclosures, and cabinets include the following:
a. Device boxes.
b. Floor boxes.
c. Outlet boxes.
d. Pull and junction boxes.
e. Cabinets and hinged-cover enclosures.
B. Related Sections:
1. Section 07 84 00 (07840) - Firestopping.
2. Section 26 05 00 (16050) – Common Work Results for Electrical: For raceways and box
supports.
3. Section 26 27 26 (16140) - Wiring Devices: For devices installed in boxes and for floor-
box service fittings.
10.02 REFERENCES
A. American National Standards Institute (ANSI) Publications:
1. C80.1 “Electrical Rigid Steel Conduit (ERSC)”
2. C80.3 “Steel Electrical Metallic Tubing (EMT)”
B. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. ANSI/NEMA FB 1 “Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit, Electrical
Metallic Tubing, and Cable”
2. ANSI/NEMA OS 1 “Sheet-Steel Outlet Boxes, Device Boxes, Covers, and Box Supports”
3. 250 “Enclosures for Electrical Equipment (1000 Volts Maximum)”
4. RN 1 “Polyvinyl Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and
Intermediate Metal Conduit”
5. TC 2 “Electrical Polyvinyl Chloride (PVC) Tubing and Conduit”
6. TC 3 “Polyvinyl Chloride (PVC) Fittings for Use with Rigid PVC Conduit and Tubing”
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 17 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 18 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 19 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 20 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 21 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 22 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 23 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 24 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 25 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 26 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 27 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 28 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 29 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 30 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 31 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 32 ▪
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 33 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 34 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 35 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 36 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 37 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 38 ▪
PART 22 GENERAL
22.01 SUMMARY
A. This Section includes the following:
1. The purpose of this section is to specify Division 26 responsibilities in the commissioning
process.
a. The systems to be commissioned are listed in Section 01 91 13.
b. Commissioning requires the participation of Division 26 to ensure that all systems
are operating in a manner consistent with the Contract Documents. The general
commissioning requirements and coordination are detailed in Division 01. Division
26 shall be familiar with all parts of Division 01 and the commissioning plan issued
by the CxA and shall execute all commissioning responsibilities assigned to them in
the Contract Documents.
B. Related Sections:
1. Section 01 91 13 – General Commissioning Requirements.
2. Section 26 08 00.01 – Electrical System Testing Requirements
3. Section 26 08 00.02 – Electrical System Prefunctional Checklists
4. Section 26 08 00.03 – Electrical System Sample Functional Test Procedures
C. Related Work:
1. Refer to Section 01 91 13 for a listing of all Sections where commissioning requirements
are found.
2. Refer to Section 01 91 13 for systems to be commissioned and Sections 26 08 00
through 26 08 00.03 for functional testing requirements.
22.02 RESPONSIBILITIES
A. Electrical Contractors. The commissioning responsibilities applicable to the electrical
contractor are as follows (all references apply to commissioned equipment only):
1. Construction and Acceptance Phases
a. Include the cost of commissioning in the contract price, if not yet let.
b. In each purchase order or subcontract written, include requirements for submittal
data, O&M data and training.
c. Attend a commissioning scoping meeting and other necessary meetings scheduled
by the CxA to facilitate the Cx process.
d. Contractors shall provide cut sheets and shop drawing submittals to the CxA of
commissioned equipment.
e. Provide additional requested documentation, prior to normal O&M manual
submittals, to the CxA for development of start-up and functional testing procedures.
1) Typically this will include detailed manufacturer installation and start-up,
operating, troubleshooting and maintenance procedures, full details of any
owner-contracted tests, fan and pump curves, full factory testing reports, if any,
and full warranty information, including all responsibilities of the Owner to keep
the warranty in force clearly identified. In addition, the installation and checkout
materials that are actually shipped inside the equipment and the actual field
checkout sheet forms to be used by the factory or field technicians shall be
submitted to the Commissioning Agent.
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 39 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 40 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 41 ▪
PART 25 GENERAL
25.01 SUMMARY
A. This Section includes the following:
1. This Section specifies the functional testing requirements for Division 22 systems and
equipment.
B. Related Sections:
1. Section 01 91 13 – General Commissioning Requirements.
2. Section 26 08 00 – Commissioning of Electrical Systems
3. Section 26 08 00.02 – Electrical Systems Prefunctional Checklists
4. Section 26 08 00.03 – Electrical Systems Sample Functional Test Procedures
25.02 INCLUDED SYSTEMS AND EQUIPMENT
A. The following is a list of the equipment and system test requirements included in this section:
1. Lighting Controls
25.03 DESCRIPTION
A. This section specifies the functional testing requirements for Division 26 systems and
equipment. From these requirements, the Commissioning Authority (CxA) shall develop step-
by-step procedures to be executed by the subcontractors or the Commissioning Authority.
The general functional testing process, requirements and test method definitions are
described in Section 01 91 13. The test requirements for each piece of equipment or system
contain the following:
1. The contractors responsible to execute the tests, under the direction of the CxA.
2. A list of the integral components being tested.
3. Prefunctional checklists associated with the components.
4. Functions and modes to be tested.
5. Required conditions of the test for each mode.
6. Special procedures.
7. Required methods of testing.
8. Required monitoring.
9. Acceptance criteria.
10. Sampling strategies allowed.
25.04 PREREQUISITES
A. The following applicable generic prerequisite checklist items are listed on each written
functional test form and shall be completed and checked off by CxA prior to functional testing:
__ All related equipment has been started up and start-up reports and prefunctional
checklists submitted and approved ready for functional testing:
__ All control system functions for this and all interlocking systems are programmed and
operable per contract documents, including final setpoints and schedules with debugging,
loop tuning and sensor calibrations completed.
__ All A/E punchlist items for this equipment corrected.
__ These functional test procedures reviewed and approved by installing contractor.
__ Safeties and operating ranges reviewed by the CxA.
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 42 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 43 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 44 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 45 ▪
PART 28 GENERAL
28.01 SUMMARY
A. This Section includes the following:
1. Prefunctional Checklists (PC) in a form format. The Prefunctional Checklists consist of
Instructions Sheets and Record Sheets.
B. Related Sections:
1. Section 01 33 00 - Submittal and Substitution Procedures
2. Section 01 91 13 – General Commissioning Requirements.
3. Section 26 08 00 – Commissioning of Electrical Systems
4. Section 26 08 00.01 – Electrical Systems Testing Requirements
5. Section 26 08 00.03 – Electrical Systems Sample Functional Test Procedures
28.02 DESCRIPTION
A. The PC procedures displayed in a form format here are intended to provide the Contractor
with an example of the format and an indication of the rigor of the required prefunctional
checklists (Instruction Sheets and Record Sheets) and documentation for various equipment
types. Though they were not developed specifically for this project, they are generally
applicable.
B. The checklists contain items for Division 26 contractors to perform. Division 26 contractor has
additional responsibilities to complete Division 22 and 23 checklists.
C. Those executing the checklists are only responsible to perform items that apply to the specific
application at hand. These checklists do not take the place of the manufacturer’s
recommended checkout and start-up procedures or report. Some checklist procedures may
be redundant of some checkout procedures that will be documented on typical factory field
checkout sheets. Double documenting is required in those cases.
D. Refer to Section 01 91 13 for additional requirements regarding prefunctional checklists,
startup and initial checkout. Items that do not apply should be noted along with the reasons
on the form. If supplied Prefunctional Checklist forms are not used for documenting, one of
similar rigor and clarity shall be used. Contractors assigned responsibility for sections of the
checklist shall be responsible to see that checklist items by their subcontractors are completed
and checked off.
E. The following is a list of the equipment and systems which will require Prefunctional Checklists
(Instruction Sheets and Record Sheets) to be completed by the Contractors.
1. Lighting Controls (Each Space Served)
2. Divisions 22 and 23 – Refer to 22 08 00.02 and 23 08 00.02
F. Refer to Section 01 33 00 - Submittal and Substitution Procedures for Prefunctional
Checklists.
PART 29 PRODUCTS
Not Used
PART 30 EXECUTION
Not Used
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 46 ▪
PART 31 GENERAL
31.01 SUMMARY
A. This Section includes the following:
1. This Section contains the Functional Testing Procedures for Mechanical Systems
B. Related Sections:
1. Section 01 33 00 - Submittal and Substitution Procedures
2. Section 01 91 13 – General Commissioning Requirements.
3. Section 26 08 00 – Commissioning of Electrical Systems
4. Section 26 08 00.01 – Electrical Systems Testing Requirements
5. Section 26 08 00.02 – Electrical Systems Prefunctional Checklists
31.02 DESCRIPTION
A. The CxA will use the functional testing requirements in Sections 26 08 00.01 and the testing
protocols specified in Section 01 91 13 for developing site-specific functional test procedures
and forms for this project. For illustrative purposes, sequences of operation associated with a
few pieces of the equipment for which tests are included are also provided.
B. The following is a list of the equipment and systems which will require Prefunctional Checklists
(Instruction Sheets and Record Sheets) to be completed by the Contractors.
1. Lighting Controls (Each Space Served)
C. Refer to Section 01 33 00 - Submittal and Substitution Procedures for Prefunctional
Checklists.
PART 32 PRODUCTS
Not Used
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 47 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 48 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 49 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 50 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 51 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 52 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 53 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 54 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 55 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 56 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 57 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 58 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 59 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 60 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 61 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 62 ▪
PART 40 GENERAL
40.01 SUMMARY
A. Section Includes:
1. Receptacles, Connectors, Switches, and Finish Plates.
B. Related Sections:
1. Section 00 31 13.43 (00370) - Interior Finish Index
2. Section 25 51 10 – Integrated Automation Control of Guestroom Equipment
3. Section 26 05 53 (16075) – Identification for Electrical Systems.
40.02 REFERENCES
A. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. WD 1 “General Color Requirements for Wiring Devices”
2. WD 6 “Wiring Devices—Dimensional Requirements”
B. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
C. Underwriter's Laboratories, Inc. (UL) Publications:
1. 486A “Standard For Wire Connectors and Soldering Lugs for Use with Copper
Conductors”
2. 486B “Standard for Wire Connectors for Use with Aluminum Conductors”
3. 498 “Attachment Plugs and Receptacles”
4. 1310 “Standard for Class 2 Power Units”
40.03 DEFINITIONS
A. GFCI: Ground-fault circuit interrupter.
40.04 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Maintenance Data: For materials and products to include in maintenance manuals
specified in Division 01.
40.05 QUALITY ASSURANCE
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction.
B. Comply with NEMA WD 1.
C. Comply with NFPA 70.
40.06 COORDINATION
A. Receptacles for Owner-Furnished Equipment: Match plug configurations.
1. Cord and Plug Sets: Match equipment requirements.
40.07 EXTRA MATERIALS
A. Furnish extra materials described in Section 01 78 43 (01790) “Spare Parts and Materials”
that match products installed and that are packaged with protective covering for storage and
identified with labels describing contents. Deliver extra materials to Owner.
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 63 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 64 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 65 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 66 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 67 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 68 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 69 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 70 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 71 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 72 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 73 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 74 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 75 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 76 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 77 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 78 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 79 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 80 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 81 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 82 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 83 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 84 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 85 ▪
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 86 ▪
PART 55 GENERAL
55.01 SUMMARY
A. Section Includes:
1. Interior Lighting Fixtures
2. Lamps
3. Ballasts
4. Exit Signs
5. Emergency Lighting Units
6. Accessories
B. Related Sections:
1. Section 09 51 23 (09512) - Acoustical Tile Ceilings
2. Section 26 05 00 (16050) - Common Work Results For Electrical.
3. Section 26 56 00 (16520) - Exterior Lighting
4. Section 26 60 00 (16580) - Lighting Accessories: For programmable lighting control
systems, time switches, additional photoelectric relays, power relays, and contactors.
55.02 REFERENCES
A. American National Standards Institute (ANSI) Publications:
1. C82.4 “Ballasts for High – Intensity – Discharge and Low Pressure Sodium Lamps
(Multiple-Supply Type)”
B. Institute of Electrical and Electronics Engineers, Inc. (IEEE) Publications:
1. C62.41 “Surge Voltages in Low-Voltage AC Power Circuits”
C. Illuminating Engineering Society (IES) Publications:
1. LM-79 “Approved Method: Electrical and Photometric Measurements of Solid-State
Lighting Products”
2. LM-80 “Approved Method: Measuring Lumen Maintenance of LED Light Sources”
D. National Fire Protection Association (NFPA) Publications:
1. NFPA 70 "National Electric Code"
2. NFPA 101 “Life Safety Code®”
E. Underwriter's Laboratories, Inc. (UL) Publications:
1. 486A “Standard For Wire Connectors and Soldering Lugs for Use with Copper
Conductors”
2. 486B “Standard for Wire Connectors for Use with Aluminum Conductors”
3. 924 “Emergency Lighting and Power Equipment”
55.03 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. For each type of lighting fixture indicated, arranged in order of fixture designation.
Include data on features, accessories, and the following:
a. Dimensions of fixtures.
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 87 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 88 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 89 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 90 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 91 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 92 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 93 ▪
END OF SECTION
Revision Log
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 94 ▪
D08 Track Philips Lightolier Lytespan Radius 1-Circuit surface track - line ceiling Halogen 1 Philips
Track System consisting of voltage - matte white 3000K 50PAR20/HAL/FL
the following components: Dimmable 50W PAR 20 #229211
(1) 9104WH - 4' Track Mean Lamp (Mercury picograms
(1) 9163WH - Floating Lumens = 550 per lumen-hr=0)
Canopy (Attach to J-Box)
(4) 8201WH/8227WH - Track
Head w/Arch Shield
D66 Under Cabinet Kichler Lighting 10581WH 1" x 5"W x 21-1/2"L Under Kitchen Wall poly/tempe Under Xenon 3
Cabinet light red glass- Cabinet 18 Watt (Mercury picograms
w/transformer, white, diffuser Mean Lamp per lumen-hr=TBD)
Hi-Low on/off switch Lumens = TBD
Non-dimmable
D68 PG400 Ceiling Ashley Lighting, Inc. 073021-098-014D 14" Square, 3-1/4" Brushed Nickel, ceiling Fluorescent 2 Philips EL/mdt 13W
Drop Flush Mount 2700K GU 24
Non-dimmable T6 Circuline 4- #222851
pin base, dbl (Mercury picograms
bulb per lumen-hr=366.67)
Mean Lamp
Lumens = 900
D100 LM412, Vanity Wall Scott Lamp 3176 4.5"W x 24"H x 14" Satin Nickel wall Fluorescent 1 Philips
ED403 Sconce Company, Inc. Drop w/Optional Linen 3100K F24T5/830/HO/ALTO
Acrylic 24W Mini Bi- #290197
Dimmable Pin T-5 (Mercury picograms
Mean Lamp per lumen-hr=21.05)
Lumens =
1900
D121 Cove - LED Philips Lightolier Concealed White LED 1.25" Diam x 1.37"H Concealed Cove cove LED 2700K 3 (6") LED
CWL271212 x 12" L light with 110 degree or (Mercury picograms
(Configure CWL271212 and Or x 110 degree beam. Mean Lamp 5 per lumen-hr=0)
CWL270612, (1) CWLPC120 1.25" Diam x 1.37"H Gray injection Lumens = 135 (12")
Pwr Cord) x 6"L molded housing. per 12"
NOTE: Use combination of Integral power driver.
lengths to achieve disired 67/135 Lumens per
length. 6"/12".
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
D121 Cove - LED RSL - Roberts Step- RW12-LED-2850-FL .46"W x .75"H Concealed lighiting cove LED 2850K LED
(ALT1) Light Systems channel with lamps (Mercury picograms
1" o.c. 23 Lumens Mean Lamp per lumen-hr=0)
per LED. Remote DC Lumens = 230
driver. Not on per 12"
dimmer. 50,000 hr life
Non-dimmable
D144 X505 Back Lit Mirror Electric Mirror LLC NOV-CUSTOM-41.00 x 36.00 41"W x 36"H x 3"D "Nuria" Mirror with 2 Wall Fluorescent 4
vertical edges T5HO (Mercury picograms
frosted left and right Mean Lamp per lumen-hr=TBD)
sides, back lit with Lumens = TBD
polished edges.
D146 X402 Pendant Project Light PL217498 5" x 5" x 33" Ceiling pendant ceiling Fluorescent 1
fixture with frosted Spring lamp (Mercury picograms
white encasement GU-24 per lumen-hr=TBD)
(upper 9" frosted, Mean Lamp
lower 3" clear) Lumens = TBD
Brushed nickel base
and silver cord
D147 X-403 Surface Kichler Lighting MS131762-IN4C 16"W x 4"H Flush Mount ceiling ceiling Fluorescent 2 TCP #32032 32W
fixture, off white Circline G10Q & TCP #32022 22W
painted linen on Mean Lamp (Mercury picograms
acrylic with bushed Lumens = TBD per lumen-hr=TBD)
stainless trim
D149 X-405 Surface Ashley Lighting, Inc. 73145-OW3-010D 6.5"H x 15" Diam Semi-Flush Ceiling Frosted ceiling Fluorescent 1 TCP #32040 with
pendant fixture with White 3100K threaded Bracket
bushed nickel body. Circline #12818BCRTOEM
Non-dimmable Mean Lamp (Mercury picograms
Lumens = per lumen-hr=TBD)
2800
D155 X506 Back Lit Mirror Electric Mirror LLC NOV-CUSTOM-34.00 x 36.00 34"W x 36"H x 3"D "Nuria" Mirror with 2 Wall Fluorescent 4
vertical edges 3000K (Mercury picograms
frosted left and right T5HO per lumen-hr=TBD)
sides, back lit with Mean Lamp
polished edges. Lumens = TBD
D187 X504 Back Lit Mirror Electric Mirror LLC NOV-CUSTOM-50.00 x 36.00 50"W x 36"H x 3"D "Nuria" Mirror with 2 Wall Fluorescent 4
vertical edges 3000K (Mercury picograms
frosted left and right T5HO per lumen-hr=TBD)
sides, back lit with Mean Lamp
polished edges. Lumens = TBD
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
D193 LM-416INT Pendant Trend Lighting Basics by Trend " Harmony" 19"dia x 9" H X 60" Pendant with crsytal ceiling incandescent 3 TCP #4892330K
BP9709 Max Drop w/ 5" x 5" beaded silver sheen or CFL 23 watt CFL
x 1" H escutcheon shade with metalic equivalent (Mercury picograms
INTERIM FIXTURE UNTIL plate. silver finish. 3000K per lumen-hr=TBD)
DESIGN COMPLETE med base
sockets, Type
A or CFL
equivalent
Mean Lamp
Lumens = TBD
D208 PG-401 Sconce Kichler Lighting MS139959NI 11.5" W x 4" D x 11" Wall sconce with white Wall CFL (Lamp 2 TCP #33113Q30K
H steel brushed nickel acrylic not included) (Mercury picograms
faceplate and diffuser GU24 Quad per lumen-hr=TBD)
rectangle linen top and Mean Lamp
hardback shade with bottom Lumens = TBD
gray square pattern
on rigth hand side of
shade which wraps
around side of shade
self fold.
Non-dimmable
F05 L29 Box Philips Daybrite 2LP3GA3CF40R-33AL-UNV- 24" x 24" White parabolic recessed Fluorescent 3 Philips PL-L
1/3-EB-2WC (Accommodates 3000K 40W/830/4P/RS/IS
Standard & Tegular 40W T5 #300426
Grid Ceiling) Mean Lamp (Mercury picograms
Non-dimmable Lumens = per lumen-hr=23.57)
2970
F07 L31 Strip Philips Daybrite SJ232-UNV-1/2-EB 24" x 48" white parabolic Recessed Fluorescent 3 Philips
Non-dimmable 3000K F32T8/TL830/ALTO
F032T8 #281519
Mean Lamp (Mercury picograms
Lumens = per lumen-hr=25.30)
2800
F09 L33 Lensed Box Philips Daybrite 2DPG432-FS01-UNV-1/4-EB 2'W x 4'L White acrylic Recessed Fluorescent 4 Philips
Non-dimmable 3000K F32T8/TL830/ALTO
F032T8 #281519
Mean Lamp (Mercury picograms
Lumens = per lumen-hr=25.30)
2800
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
F09 (ALT) L30 Box Philips Daybrite 2LP3GA332-36AL-UNV-1/3- 2'W x 4'L White acrylic recessed Fluorescent 3 Philips
EB-2WC Non-dimmable 3000K F32T8/TL830/ALTO
F032T8 #281519
Mean Lamp (Mercury picograms
Lumens = per lumen-hr=25.30)
2800
F24a Strip Light Philips Daybrite SN 4S 132 HPF UNVHI 48" Indirect ceiling Fluorescent 1 Philips
Non-dimmable 3000K F32T8/TL830/ALTO
F032 / 830XP #246678
/ ECO T8 (Mercury picograms
Octron per lumen-hr=25.30)
Mean Lamp
Lumens =
2800
F24a Strip Light Philips Daybrite SN 4S 132 HPF UNVHI 48" Indirect undercabi Fluorescent 1 Philips
Non-dimmable net 3000K F32T8/TL830/ALTO
F032 / 830XP #246678
/ ECO T8 (Mercury picograms
Octron per lumen-hr=25.30)
Mean Lamp
Lumens =
2800
F24b Strip Light Philips Daybrite SN 3S 125 HPF UNVHI 36" Indirect undercabi Fluorescent 1 Philips
Non-dimmable net 3000K F25T8/TL830/PLUS/AL
F025 / 830XP TO
/ ECO T8 #145565
Octron (Mercury picograms
Mean Lamp per lumen-hr=27.64)
Lumens =
2050
F24c Strip Light Philips Daybrite SN 2S 117 HPF UNVHI 24" Indirect undercabi Fluorescent 1 Philips
Non-dimmable net 3000K F17T8/TL830/PLUS/AL
F017 / 830XP TO
/ ECO T8 #145524
Octron (Mercury picograms
Mean Lamp per lumen-hr=43.59)
Lumens =
1300
F24d Strip Light Philips Daybrite SN 1S 115 HPF UNVHI 18" Indirect undercabi Fluorescent 1 Philips
Non-dimmable net 3000K F15T8/WW/ALTO
F15T8 #382986
Mean Lamp (Mercury picograms
Lumens = 660 per lumen-hr=383.84)
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
L10 N/A LED Box Philips Daybrite 2DLG49L835-4-D-UNV-OCC- 2'-0" x 4'-0" Recessed LED with DR Acrylic Ceiling LED 3500K LED
SDIM switched dimming (Suitable Integrated LED (Mercury picograms
ballast and for Grid Mean Lamp per lumen-hr=0)
integrated and Slot Lumens = TBD
occupancy sensor Ceiling
3500K. Dim from types)
100% to 40% when
unoccupied.
Dimmable
L12 N/A Undercabinet Philips Color (1) 523000027-50 EW Profile 41.375" L x .88" H x 39.25" LED Polycarbon Surface LED 3000K LED
Powercore 1.77" W (incl Undercabinet light, ate (Mercury picograms
(1) 120000065-00 Permanent terminator and 3000K, ultra low Mean Lamp per lumen-hr=0)
Wiring Compartment and jumper connection) profile white, 120 vt Lumens =
Terminator hard wired, aluminum 1042
(1) 108000035-00 6"jumper Dimmable
L22 N/A Down Philips Lightolier 1004ICLED-1013CDL30K 5" diameter 5" Downlight with recessed LED 3000K 1 LED
Clear Annodized Integrated LED (Mercury picograms
Reflector Mean Lamp per lumen-hr=0)
Dmmable Lumens = 742
L29 N/A Box Philips Daybrite 2CLG36L835-2-D-UNV 24" x 24" White parabolic Recessed LED 3500K LED
(Accommodates (Mercury picograms
Standard & Tegular Mean Lamp per lumen-hr=0)
Grid Ceiling) Lumens =
Non-dimmable 3668
L30 N/A Box Philips Daybrite 2CLG54L835-4-D-UNV 24" x 48" white Lensed Recessed LED 3500K LED
Non-dimmable (Mercury picograms
Mean Lamp per lumen-hr=0)
Lumens =
5448
L31 N/A Strip Philips Daybrite DWAE43L835-4-UNV 7"W x 5 3/16"H x Wrap Around Lens acrylic surface LED 3500K LED
50"L Non-dimmable (Mercury picograms
Mean Lamp per lumen-hr=0)
Lumens =
4293
L33 N/A Lensed Box Philips Daybrite 2CLG74L835-4-D-UNIV 2'W x 4'L White acrylic Recessed LED LED
Non-dimmable (Mercury picograms
Mean Lamp per lumen-hr=0)
Lumens =
7400
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
L33 N/A Box Philips Daybrite 2'W x 4'L White acrylic recessed LED LED
(ALT) Non-dimmable (Mercury picograms
Mean Lamp per lumen-hr=0)
Lumens = TBD
L38 Recessed Philips Lightolier C2L04DL30K25RUZ10V- 1.75" diameter LED Dowmlight, Phospor recessed LED 3000K 1 LED
Downlight - LED C2LDLCCDP Clear (Mercury picograms
Dimmable Mean Lamp per lumen-hr=0)
Lumens = 400
L43 N/A Downlight Philips Lightolier 1004ICLED-1013CDL30K- 5" Diam Aperture UL Fire Rated recessed LED 3000K 1 LED
16FR2X16 Enclosure, Clear Integrated LED (Mercury picograms
Reflector, White Mean Lamp per lumen-hr=0)
Flange Lumens = 742
Dimmable
L46 N/A Recessed Philips Lightolier 1101LED15N27D1-1113 6" diameter LED Recessed recessed LED 2700K 1 LED
Downlight - LED Downlight, Wet 1500 Lumen (Mercury picograms
Location, Clear Integrated LED per lumen-hr=0)
Reflector, White Mean Lamp
Flange Lumens =
Dimmable 1500
L47 N/A Recessed Philips Lightolier 1050LRN06D1 - 5" Diameter Shallow Frame In Kit Solite Lens recessed LED 2700K 1 LED
Downlight - LED 1050LRN0627 - IC Rated, Wet 600 Lumen (Mercury picograms
1050RNDLWB Location, Solite Integrated LED per lumen-hr=0)
Lens, White Baffle, Mean Lamp
White Flange Lumens = 600
Dimmable
L51 Recessed Philips Lightolier 1101LED15N27D1-1113 6.75" diameter LED Recessed Recessed LED 2700K 1 LED
Downlight, Clear 1500 Lumen (Mercury picograms
Reflector, White Integrated LED per lumen-hr=0)
Flange Mean Lamp
Dimmable Lumens =
1764
L57 N/A Down Philips Lightolier 1101LED09N27D1-1146 6.75" diameter Specular Clear Alzak recessed LED 2700K 1 LED
Dimmable 900 Lumen (Mercury picograms
Integrated LED per lumen-hr=0)
Mean Lamp
Lumens = 995
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
L74 n/a Ceiling Surface Eaton Halo SLD405930WHJB 4" Diamter LED Round Edgelit Ceiling LED LED 1 LED
Aperature Surface Frosted 3000K (Mercury picograms
Mount Light (intall 1500 Lumen per lumen-hr=0)
into compatible Jbox) Integrated LED
(Suitable for Grid Mean Lamp
and Slot Ceiling Lumens =
types) 1764
Dimmable
L80 N/A Deco LED Insight Lighting DFLED/120/35K/WM/INT-X/W 3- 5/8" H x 31- 1/8" Wet listed, clear wall LED 1 LED
W x 10- 5/8" D natatorium rated. lighting 3500K (Mercury picograms
Cold rolled steed, grade Integrated LED per lumen-hr=TBD)
powder-coated finish. acrylic Mean Lamp
Non-dimmable Lumens =
7193
L200 LM404 INT N/A Pendant Trend Lighting Basics by Trend "Luminary" 15" diam x 60" max Hand woven ceiling incandescent 1 11 Watt LED med
BP6009 drop with 5"x 5" x 1" aluminum wire or CFL base,
(INTERIM FIXTURE UNTIL H escutcheon plate metallic Silver equivalent GE #68015
DESIGN COMPLETE) Sphere. Clear silver med base (Mercury picograms
44" adjustable cord sockets, Type per lumen-hr=TBD)
A or CFL
equivalent
Mean Lamp
Lumens = N/A
L201 LM408 N/A Pendant D'Style DSTY-I-CH-RI408A 38" Diam x 42" H Metal tube cirular ceiling LED 8 Grainger #6XWK7,
with 6" Diam chandelier with LED Candleabra GE #61545-
escutcheon plate bulbs on stainless base screw in LED2CAC/ES/TP
steel wires, hung by Mean Lamp (Mercury picograms
10' black power cord Lumens = N/A per lumen-hr=0)
with 10' SS airplane
support wire.
L202 X408 N/A Sconce Ashley Lighting, Inc. 72108-XUT8 16" W x 6" H x 5" D Double Wall Sconce Wall
(Mercury picograms
Mean Lamp per lumen-hr=TBD)
Lumens = TBD
L504 N/A Site Philips Gardco ECF-1-4-215LA-641A-NW- 24.2" x 13" x 1.3" Low profile LED Type IV On Pole LED 4000K 1 LED
UNV-NP luminaire, Aluminum L505 Integrated LED (Mercury picograms
Finish Mean Lamp per lumen-hr=0)
Non-dimmable Lumens =
19991
L505 N/A Pole Philips Wide-Lite SSS-25-5-11-D1-NP 5" Square x 25' Pole Pole, Aluminum Conc. Pad
Finish (Mercury picograms
Mean Lamp per lumen-hr=N/A)
Lumens = N/A
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
L510 N/A Site Philips Gardco ECF-1-5-215LA-641A-NW- 24.2" x 13" x 1.3" Low profile LED Type IV pole - LED 4000K 1 LED
UNV-NP luminaire , Aluminum L505 Integrated LED (Mercury picograms
Finish (L504 w/ Type Mean Lamp per lumen-hr=0)
4 distribution) Lumens =
Non-dimmable 19980
O01 Jelly Jar Philips Quality RLW26HFLCGC-1 8.6"W x 10.38"H White powder coated glass wall Compact 1 Philips PL-T
Exceline aluminum with cage. Fluorescent 26W/830/4P/ALTO
Heat and shock 3000K #268235
resistant optical PL-T 26/4PIN (Mercury picograms
chamber. Lamp Mean Lamp per lumen-hr=110.29)
included with fixture. Lumens =
Non-dimmable 1530
O03 Pool Light Provided by Pool underwater pool light glass wall Incandescent
Manufacturer (Mercury picograms
Mean Lamp per lumen-hr=TBD)
Lumens = TBD
R01 L22 Down Philips Lightolier 1001F13U / 1001CL 5" diameter Specular Clear Alzak recessed Compact 1 Philips PL-C
Non-dimmable Fluorescent 13W/830/4P/ALTO
3000K #383265
13w quad 4 pin (Mercury picograms
Mean Lamp per lumen-hr=150.54)
Lumens = 775
R02 L57 Down Philips Lightolier 1101F2642UMW26/1101CL 6.75" diameter Specular Clear Alzak recessed Compact 1 Philips PL-T
Non-dimmable Fluorescent 26W/830/4P/ALTO
3000K #268235
26w triple tube (Mercury picograms
Mean Lamp per lumen-hr=110.29)
Lumens =
1530
R02D L51 Down Philips Lightolier 1101FD 2642MX1 / 1101CL 6.75" diameter Specular Clear Alzak recessed Compact 1 Philips PL-T
Dimmable Fluorescent 42W/830/4P/ALTO
3000K #268730
42w triple tube (Mercury picograms
Mean Lamp per lumen-hr=62.04)
Lumens =
2720
R06 Recessed Philips Lightolier 1101LED15N27D1-1113 6" diameter LED Recessed recessed LED 2700K 1 LED
Downlight - LED Downlight, Wet 1500 Lumen (Mercury picograms
Location, Clear Integrated LED per lumen-hr=0)
Reflector, White Mean Lamp
Flange Lumens =
Dimmable 1500
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
R08A Down Philips Lightolier 1154CD / 1100IC 6.75" diameter Clear Diffuse Cone recessed Halogen 1 Philips
Dimmable 3000K 90PAR38/HAL/FL
90 PAR 38 #202341
Flood (Mercury picograms
Mean Lamp per lumen-hr=0)
Lumens =
1350
R09 L53 Down Philips Lightolier 1002 P1 / 1013 5" diameter Specular Clear Alzak recessed Halogen 1 Philips
Dimmable 3000K 75PAR38/HAL/FL
75 PAR 30 #144865
Flood (Mercury picograms
Mean Lamp per lumen-hr=0)
Lumens =
1050
R11 L43 Downlight Philips Lightolier 1001F13ICU / 1001HCL / 5" Diam Aperture UL Fire Rate recessed Compact 1 32W/830/4P/ALTO
16FR2X10 Enclosure w/Frame- Fluorescent #268029
in Kit and Clear 3000K (Mercury picograms
Reflector Trim 13w quad 4 pin per lumen-hr=165.44)
Non-dimmable Mean Lamp
Lumens =
1020
R29 L34 Down Philips Lightolier C3LVE1 / C3MRACLW 3" Diam Aperture Wall washer w/ ceiling Halogen 1 Philips 50MR16/FL36
locking device 3000K EXN
Dimmable MR 16 FL #378059
Mean Lamp (Mercury picograms
Lumens = 850 per lumen-hr=0)
R29D N/A Dimmer Philips Controls OH500QEI 2.75" X 4.58" Dimmer - Ivory wall
(Mercury picograms
Mean Lamp per lumen-hr=N/A)
Lumens = N/A
R41 Down Philips Lightolier 1101F2642U / 1101HCLO 6.75" diameter Specular Clear Alzak recessed Compact 1 Philips PL-T
/ Opal Lens - for Fluorescent 42W/830/4P/ALTO
sloped ceiling 3000K #268730"
Non-dimmable PLT42 4pin (Mercury picograms
Mean Lamp per lumen-hr=62.04)
Lumens =
2720
R59 Down Philips Lightolier 1101FD2642M7U / 6.75" diameter Specular Clear Alzak recessed Compact 1 Philips
1101HCLO / Opal Lens / For Fluorescent PL-T
sloped ceilings 3000K 42W/830/4P/ALTO
Dimmable PLT42 4 pin #268730
Mean Lamp (Mercury picograms
Lumens = per lumen-hr=62.04)
2720
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
R68 Down - Wall Philips Lightolier 1101FD2642M7U / 6.75" Aperature Single Wall Recessed Compact 1 Philips
Washer 1101HCLSW Wash/Specular Fluorescent PL-T
Clear Alzak / For 3000K 42W/830/4P/ALTO
sloped ceilings PLT42 4 pin #268730
Dimmable Mean Lamp (Mercury picograms
Lumens = per lumen-hr=62.04)
2720
T05 Dome Technical 11730 / 32WH-HP 14" Round White White Swirl ceiling Fluorescent 1
Consumer Products 32w circleline (Mercury picograms
Mean Lamp per lumen-hr=TBD)
Lumens = TBD
T06 Exhast Panasonic FV-08VRE1 Can size is 12 3/4" L Recessed Can fan Acrylic ceiling LED 3000K 1 LPHT14D
Fan/Light x 8 1/4" W x 7 1/2" with light w/white 1 - 14 watt (Mercury picograms
D, Trim Ring is 6 1/2" baffle replaceable per lumen-hr=0)
round Non-dimmable GU24 base
Mean Lamp
Lumens = 575
X01 Exit Philips Chloride ER55L3W (R or G) (with N/A Universal arrows / universal LED LED
Battery) Single or 2-Sided LED comes w/ (Mercury picograms
or (R=Red Letter Color fixture per lumen-hr=0)
55L3W (R or G) - W (with out / G=Green Letter Mean Lamp
Battery) Color) Lumens = TBD
Non-dimmable
X03 Emergency Philips Chloride 6M25WJ2 N/A emergency battery - wall Low Voltage 2 6V, 9 watt
white 9 watt (Mercury picograms
For use with X01 Mean Lamp per lumen-hr=0)
Non-dimmable Lumens = TBD
Z01 N/A Flood Philips Hadco 1020 H LED18 NF W 7" x 6" Uplight - Bronze Stake LED 3000K 1 Philips 18PAR38/END
Narrow Flood 18 PAR 38 #202341
Dimmable LED (Mercury picograms
(lamp included) per lumen-hr=0)
Mean Lamp
Lumens =
1200
Z05 Sconce Kichler Lighting 49271RZ 8"W x 14"H Rubbed Bronze wall ???Compact 1 A21
Non-dimmable Fluorescent (Mercury picograms
3000K per lumen-hr=TBD)
100 W
incandescent
or 23-30 watt
CFL
Mean Lamp
Lumens = TBD
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
Z07 Decorative Kichler Lighting 49275RZ 26" x 12" Lantern Fixture, v ???incandesce 1 tbd
Rubbed Bronze nt Metal Halide PhilipsMHC250/U/M/3K
Non-dimmable tbd 150 MH /ALTO
Mean Lamp (Mercury picograms
Lumens = per lumen-hr=TBD)
10500
Z08 Decorative Philips Hadco SP - 5894 - N 10' Pole Conc. Pad N/A
Pole for Z07 N/A (Mercury picograms
Mean Lamp per lumen-hr=N/A)
Lumens = N/A
Z24 Pole & Light Connor Sport Court Lighting System Provided by
International, Inc. Section 11 68 23 (Included in (Mercury picograms
Game Court Package) Mean Lamp per lumen-hr=TBD)
Lumens = TBD
Z28 Emergency Philips Lightolier 1101F2642UEM / 1101HCLF 6-3/4" x 7-3/4" Exterior appropriate Spun Recessed Fluorescent 1 Philips PL-T
for wet location. Aluminum, 3000K 32W/830/4P/ALTO
Non-dimmable fresnel lens PL-T32/4Pin #268326
Mean Lamp (Mercury picograms
Lumens = per lumen-hr=82.72)
2040
Z42 Exterior Lukas Lighting CL914 5'-2" x 1'-10" Diam Exterior Pendant - 3 Acrylic Stem Fluorescent 3 Philips F25T8 Adv835,
Pendant FT Body Custom Mtd, Vertical ALTO, 17w, linear T8
Pendant Clear Jbox, Mean Lamp (Mercury picograms
Frosted Acrylic Outer Wind tie Lumens = per lumen-hr=33.6)
Cylinder / White Safety 1405
Acrylic Inner Cylinder cable
Finish Powder
Coated
Non-dimmable
Z43 Exterior Lukas Lighting CLK913 7'-4" x 2'-2" Diam Exterior Pendant - 4 Acrylic Stem Fluorescent 3 Philips F25T8 Adv835,
Pendant FT Body Custom Mtd, Vertical ALTO, 17w, linear T8
Pendant Clear Jbox, Mean Lamp (Mercury picograms
Frosted Acrylic Outer Wind tie Lumens = per lumen-hr=21.6)
Cylinder / White Safety 2185
Acrylic Inner Cylinder cable
Finish Powder
Coated
Non-dimmable
NOTE 1: Items with an ID X-Ref # are items purchased through Marriott’s Procurement Division as FF&E items (Furniture, Fixture, Equipment) if this service is selected by Owner. Confirm with Owne
hardwired lighting fixtures in the scope of the General Contractor, or whether to remove if they are provided by Marriott Procurement Services.
NOTE 2: Mark Numbers followed by an "ALT" = Alternative supplier of fixture. Mark Numbers followed by an "OPT" = Optional Choice of fixture.
NOTE 3: The “LED Option Mark” Column provides a Mark number for an optional LED fixture. The spec for this fixture is found within this Matrix. This column has been added to provide options for
in their hotels over the long term and have lower maintenance through the life of the fixture.
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 95 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 96 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 97 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 98 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 99 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 100 ▪
PART 61 GENERAL
61.01 SUMMARY
A. Section Includes:
1. Time Switches
2. Photoelectric Relays
3. Multi-pole Lighting Relays and Contactors.
4. Hearing Impaired Door Annunciator
B. Related Sections:
1. Section 10 14 00 (10400) - Signage
2. Section 26 05 00 (16050) - Common Work Results For Electrical.
3. Section 26 05 19 (16120) - Low-Voltage Electrical Power Conductors and Cables.
4. Section 26 05 33 (16130) - Raceways and Boxes For Electrical Systems.
5. Section 26 05 53 (16075) - Identification for Electrical Systems.
6. Section 26 24 00 (16440) - Switchboards and Panelboards
7. Section 26 27 26 (16140) - Wiring Devices: For wall-box dimmers and manual light
switches.
61.02 REFERENCES
A. American National Standards Institute (ANSI) Publications:
1. C62.41 “IEEE Recommended Practice for Surge Voltages in Low-Voltage AC Power
Circuits”
B. National Electrical Manufacturer’s Association (NEMA) Standards Publications:
1. ICS 2 “Industrial Control and Systems Controllers, Contactors and Overload Relays
Rated 6000 Volts”
C. National Fire Protection Association (NFPA) Publications:
1. NFPA 70 "National Electric Code"
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 101 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 102 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 103 ▪
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 104 ▪
END OF SECTION
▪ DIVISION 26 ELECTRICAL ▪
▪ PAGE 105 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Supporting Devices for Communication Components.
2. Concrete Equipment Bases.
3. Cutting and Patching For Communication Construction.
4. Touchup Painting.
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-In-Place Concrete.
2. Section 07 84 00 (07840) - Firestopping.
3. Section 09 90 00 (09900) - Painting.
4. Division 26 and 28 Sections
1.02 REFERENCES
A. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A53 "Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded
and Seamless"
B. American Welding Society (AWS) Publications:
1. D1.1 "Structural Welding Code - Steel"
C. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
D. U.S. Architectural & Transportation Barriers Compliance Board:
1. Americans with Disabilities Act (ADA)
1.03 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in Project with the following supporting data:
1. Product Data: For electricity-metering equipment.
2. Shop Drawings: Dimensioned plans and sections or elevation layouts of electricity-
metering equipment.
3. Field Test Reports: Indicate and interpret test results for compliance with performance
requirements.
1.04 QUALITY ASSURANCE
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
B. Comply with NFPA 70.
C. All work to be in accordance with latest requirements of NFPA 70 and all other applicable
codes and regulations of authorities having jurisdiction over the work.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 1 ▪
PART 2 PRODUCTS
2.01 SUPPORTING DEVICES
A. Material: Cold-formed steel, with corrosion-resistant coating acceptable to authorities having
jurisdiction.
B. Metal Items for Use Outdoors or in Damp Locations: Hot-dip galvanized steel.
C. Slotted-Steel Channel Supports: Flange edges turned toward web, and 9/16-inch diameter
slotted holes at a maximum of 2 inches o.c., in webs.
1. Channel Thickness: Selected to suit structural loading.
2. Fittings and Accessories: Products of the same manufacturer as channel supports.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 2 ▪
PART 3 EXECUTION
3.01 ELECTRICAL EQUIPMENT INSTALLATION
A. Headroom Maintenance: If mounting heights or other location criteria are not indicated,
arrange and install components and equipment to provide the maximum possible headroom.
B. Materials and Components: Install level, plumb, and parallel and perpendicular to other
building systems and components, unless otherwise indicated.
C. Equipment: Install to facilitate service, maintenance, and repair or replacement of
components. Connect for ease of disconnecting, with minimum interference with other
installations.
D. Right of Way: Give to raceways and piping systems installed at a required slope.
E. Coordinate work with other trades and install conduit and boxes to clear embedded ducts,
openings, etc. and all structural features.
F. Unless otherwise noted, mounting heights, as shown, are from finished floor to top of
panelboard and to centerline of other equipment. Coordinate all mounting heights with
contract drawings, local code requirements, and all ADA.requirements.
1. Toggle (snap) switch: 4’-0”.
2. Enclosed circuit breaker: 5’-0”
3. Disconnect (safety) switch: 5’-0”.
4. Motor starter: 5’-0”.
5. Panelboard: 6’-6”.
3.02 COMMUNICATION SUPPORTING DEVICE APPLICATION
A. Damp Locations, [Pool Equipment Rooms], Storage Rooms and Outdoors: Hot-dip
galvanized materials or nonmetallic, U-channel system components.
B. Dry Locations: Steel materials.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 3 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 4 ▪
END OF SECTION
Revision Log
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 5 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Premises Wiring For Telephone Distribution, Including Installations For Service By Local
Telephone Exchange Carrier.
B. Related Sections:
1. Section 26 05 26 (16060) - Grounding and Bonding for Electrical Systems.
2. Section 26 05 33 (16130) - Raceways and Boxes for Electrical Systems.
3. Section 26 05 53 (16075) – Identification for Electrical Systems.
4. Section 27 20 00 (16740) - Communication and Data Processing Equipment.
4.02 REFERENCES
A. American National Standards Institute / Insulated Cable Engineers Association, Inc.
(ANSI/ICEA) Publications:
1. ANSI/ICEA S-80-576 ”Category 1 & 2 Individually Unshielded Twisted Pair Indoor Cables
for Use in Communications Wiring Systems”
B. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
C. Telecomunications Industry Association" (TIA) Publications:
1. 569-B “Commercial Building Standard for Telecommunication Pathways and Spaces”
2. 570-B “Residential Telecommunications -- Infrastructure Standard”
D. Underwriter's Laboratories, Inc. (UL) Standards:
1. 486A “Standard For Wire Connectors and Soldering Lugs for Use with Copper
Conductors”
2. 486B “Standard for Wire Connectors for Use with Aluminum Conductors”
4.03 DEFINITIONS
A. Local Exchange Carrier: Telephone utility or other entity that provides an access line from a
local exchange into the premises.
B. Exchange Access Line: Circuit carrying telephone service into the premises.
C. Distribution Circuit: Circuit from the network interface device to a distribution device, such as
a terminal block or junction box.
D. Station Circuit: Circuit from a distribution device to a telecommunications outlet.
E. Telecommunications Outlet: Telephone jack for connecting equipment to communication
circuits.
4.04 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in Project.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 6 ▪
PART 5 PRODUCTS
5.01 COMPONENTS
A. Comply with TIA 570-B.
B. Telecommunications and Auxiliary Disconnect Outlets: Four-position modular, latching, plug-
type, jack-in, flush-mounting wall plate, unless otherwise indicated.
C. Wall Plates: Designed for telephone service. Match those indicated for power receptacle
outlets in same spaces for materials and finish. For wall telephone units, include provision for
support of unit.
D. Distribution and Station Cable: Category [5e][6], Four-pair, No. 24 AWG, solid-copper,
unshielded, twisted-pair construction in PVC sheath. Verify with MEP drawings
1. Comply with ANSI/ICEA S-80-576.
2. Plenum cable is listed for use in plenums.
E. Cabinets: Comply with Section 26 05 33 "Raceways and Boxes for Electrical Systems."
Furnish cabinets with backboard.
F. Backboard: 3/4-inch fireproofed interior grade plywood. Where installed in wire closet, height
and width shall cover entire wall up to 96 inches above floor, unless otherwise indicated.
PART 6 EXECUTION
6.01 INSTALLATION
A. Telephone Service: Comply with local telephone exchange carrier's requirements for details
of telephone service.
B. Install outlet boxes and telecommunications outlets.
C. Install cable without damaging conductors and jacket.
1. Do not bend cable to a smaller radius than minimum recommended by manufacturer.
D. Install premises wiring in raceways, where raceway is in an accessible location, otherwise
premises wiring shall be plenum rated and installed per manufacturer’s instructions.
1. Install cables in walls unless walls are solid or filled with insulation. In solid walls, install
in raceway and terminate raceway with a bushing in ceiling space above outlet.
2. Install cables without raceway where concealed in accessible ceiling space, unless
otherwise indicated.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 7 ▪
END OF SECTION
Revision Log
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 8 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Wire, Cable, Connecting Devices, Installation, And Testing For Wiring Systems To Be
Used As Signal Pathways For Voice And High-Speed Data Transmission.
a. Mounting Elements
b. Twisted-Pair Cables, Connectors, and Terminal Equipment
c. Fiber-Optic Cables, Connectors, and Terminal Equipment
B. Related Sections include the following:
1. Section 26 05 26 (16060) - Grounding and Bonding for Electrical Systems.
2. Section 26 05 33 (16130) - Raceways and Boxes for Electrical Systems.
3. Section 26 05 53 (16075) – Identification for Electrical Systems.
4. Section 26 05 36 (16139) - Cable Trays for Electrical Systems.
5. Section 27 10 00 (16710) – Structured Cabling.
7.02 REFERENCES
A. InteNational Electrical Testing Association (NETA) Publications:
1. ATS “Standard for Acceptance Testing Specifications”
B. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
C. Telecomunications Industry Association" (TIA) Publications:
1. 568-A “Commercial Building Wiring Standard”
2. 568-B “Commercial Building Telecommunications Cabling Standards - Parts 1, 2, 3
Complete”
3. 569-B “Commercial Building Standard for Telecommunication Pathways and Spaces”
4. TSB-67 “Transmission Performance Specifications for Field Testing of Unshielded
Twisted-Pair Cabling Systems”
7.03 DEFINITIONS
A. EMI: Electromagnetic interference.
B. IDC: Insulation displacement connector.
C. LAN: Local area network.
D. PVC: Polyvinyl chloride.
E. STP: Shielded twisted pair.
F. UTP: Unshielded twisted pair.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 9 ▪
PART 8 PRODUCTS
8.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. Cable:
a. None.
2. Terminal and Connector Components, and Distribution Racks:
a. Leviton Mfg. Co., Inc. (800-323-8920)
B. Approved Manufacturers:
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 10 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 11 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 12 ▪
PART 9 EXECUTION
9.01 EXAMINATION
A. Examine pathway elements intended for cable. Check raceways, cable trays, and other
elements for compliance with space allocations, installation tolerances, hazards to cable
installation, and other conditions affecting installation. Proceed with installation only after
unsatisfactory conditions have been corrected.
9.02 APPLICATION OF MEDIA. Verify with General Contractorr
A. Backbone Cable for Data Service: Use UTP cable complying with [Category 5e] [Category 6]
of TIA 568-A, fiber-optic cable for runs between equipment rooms and wiring closets and for
runs between wiring closets if over 100 meters.
B. Backbone Cables for Voice Service: Use UTP cable complying with [Category 5e] [Category
6] of TIA 568-A for runs between equipment rooms and wiring closets and for runs between
wiring closets.
C. Horizontal Cables for Data Service: Use UTP cable complying with [Category 5e] [Category 6]
of TIA 568-A for runs between wiring closets and workstation outlets.
D. Horizontal Cables for Voice Service: Use UTP cable complying with [Category 5e] [Category
6] of TIA 568-A for runs between wiring closets and workstation outlets.
9.03 INSTALLATION
A. Wiring Method: Install wiring in raceway where raceway is in an accessible location and cable
tray except within consoles, cabinets, desks counters and above accessible ceilings where
plenum wiring method may be used. Conceal raceway and wiring except in unfinished
spaces.
B. Install cable using techniques, practices, and methods that are consistent with Category 5e
rating of components and that ensure Category 5e performance of completed and linked
signal paths, end to end.
C. Install cable without damaging conductors, shield, or jacket.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 13 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 14 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 15 ▪
END OF SECTION
Revision Log
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 16 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Master Antenna Television Systems Using [An Internal Antenna System, and a Satellite
Earth-Station System of the Receive-Only Type] As the Signal Source.
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-in-Place Concrete.
2. Section 05 12 00 (05120) - Structural Steel.
3. Section 07 31 13 (07311) – Asphalt Shingles
4. Section 07 53 23 (07530) - Ethylene-Propylene-Diene-Monomer (EPDM) Roofing.
5. Section 07 61 00 (07610) - Sheet Metal Roofing
6. Section 26 05 53 (16075) – Identification for Electrical Systems.
7. Section 26 35 33 (16280) - Power Factor Correction Equipment
10.02 DEFINITIONS
A. CATV: Community antenna television.
B. MATV: Master antenna television.
C. NTSC: National television system committee.
D. RF: Radio frequency.
10.03 SUBMITTALS
A. Product Data: Include detailed manufacturer's specifications for each component specified.
Include data on features, ratings, and performance.
B. Shop Drawings: For television equipment. Include plans, elevations, sections, details, and
attachments to other Work.
1. Design Calculations: Calculate requirements and perform structural analysis for installed
products including selection of seismic restraints, signed and sealed by the qualified
professional engineer responsible for their preparation.
2. Include dimensioned plan and elevation views of components and enclosures, and
details of control panels. Show access and workspace requirements.
3. Wiring Diagrams: Power, signal, and control wiring. Differentiate between manufacturer-
installed and field-installed wiring.
C. Product Certificates: Signed by manufacturers of television equipment and components
certifying that products furnished comply with requirements.
D. Installer Certificates: Signed by manufacturer certifying that installers comply with
requirements.
E. Field Test Reports: Indicate and interpret test results for compliance with performance
requirements of installed systems.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 17 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 18 ▪
PART 11 PRODUCTS
11.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. MATV System Components:
a. None
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 19 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 20 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 21 ▪
PART 12 EXECUTION
12.01 EXAMINATION
A. Examine pathway elements intended for cable. Check raceways, cables trays, and other
elements for compliance with space allocations, installation tolerances, hazards to cable
installation, and other conditions affecting installation.
B. Examine roughing-in for antenna to verify actual locations of cable connections before
antenna installation.
C. Examine walls, floors, roofs, equipment bases, and roof supports for suitable conditions where
television equipment is to be installed.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
12.02 INSTALLATION
A. Outdoor Installation: Comply with ANSI C2, "National Electrical Safety Code."
B. Install surge suppressors where ac-power-operated devices are not protected against voltage
transients by integral surge suppressors specified in UL 1449. Install surge suppressors at
the devices' power-line terminals. Comply with Section (26 35 33) 16280 “Power Filters And
Conditioners”.
C. Support and anchor antenna towers, masts, and mountings.
1. Concrete Foundations: Reinforced concrete complying with Section (03 30 00) 03300
"Cast-in-Place Concrete."
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 22 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 23 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 24 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 25 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 26 ▪
END OF SECTION
Revision Log
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 27 ▪
PART 13 GENERAL
13.01 SUMMARY
A. Section Includes
1. Equipment for Amplifying, Distributing, and Reproducing Sound Signals.
B. Related Sections:
1. Section 26 05 26 (16060) - Grounding and Bonding for Electrical Systems.
2. Section 26 05 33 (16130) - Raceways and Boxes for Electrical Systems.
3. Section 26 05 53 (16075) – Identification for Electrical Systems.
4. Section 27 20 00 (16740) - Communication and Data Processing Equipment.
13.02 DEFINITIONS
A. Channels: Separate parallel signal paths, from sources to loudspeakers or loudspeaker
zones, with separate amplification and switching that permit selection between paths for
speaker alternative program signals.
B. Zone: A separate group of loudspeakers and associated supply wiring that may be arranged
for selective switching between different channels.
C. VU: Volume unit.
13.03 PERFORMANCE REQUIREMENTS
A. System Functions: Include the following:
1. Selectively connecting separate zones to different signal channels.
2. Selectively amplifying sound among various microphone outlets and other inputs.
3. Communicating simultaneously to all zones regardless of zone or channel switch
settings.
4. Reproducing high-quality sound that is free from noise and distortion at all loudspeakers
at all times during equipment operation, including standby mode with inputs off; and
output free from non-uniform coverage of amplified sound.
13.04 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indication items
indicating specified items selected for use in Project with the following supporting data:
1. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, required
clearances, method of field assembly, components, and location of each field connection.
a. Console layouts.
b. Control panels.
c. Rack arrangements.
2. Maintenance Data: For equipment to include in maintenance manuals specified in
Section 01 83 00 (01830) “Operating and Maintenance Data”.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 28 ▪
PART 14 PRODUCTS
14.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None.
B. Approved Manufacturers:
1. DMX, Inc. (800-345-5000)
2. Muzak (800-331-3340)
14.02 EQUIPMENT
A. Coordinate features to form an integrated system. Match components and interconnections
for optimum performance of specified functions.
B. Equipment: Modular type, using solid-state components, fully rated for continuous duty,
unless otherwise indicated. Select equipment for normal operation on input power usually
supplied at 110 to 130 V, 60 Hz.
C. Waterproof Equipment: Listed and labeled for duty outdoors or in damp locations (pool).
D. Products: Provide the following products subject to conformance with the requirements
specified.
1. AEI Propac cassette deck.
2. TOA P-912 MK2 amplifier and University 1701 MOH amplifier.
3. Volume Control, one for pool/spa room and one for meeting/breakfast room.
4. Speakers as required per layout.
14.03 PREAMPLIFIERS
A. Comply with EIA SE-101-A; either separately mounted or as an integral part of power
amplifier.
B. Output Power: Plus 4 dB above 1 mW at matched power-amplifier load.
C. Total Harmonic Distortion: Less than 1 percent.
D. Frequency Response: Within plus or minus 2 dB from 20 to 20,000 Hz.
E. Input Jacks: Minimum of two. One matched for low-impedance microphone; the other
matchable to cassette deck, CD player, or radio tuner signals without external adapters.
F. Minimum Noise Level: Minus 55 dB below rated output.
G. Controls: On/off, input levels, and master gain.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 29 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 30 ▪
PART 15 EXECUTION
15.01 INSTALLATION
A. Install equipment to comply with manufacturer's written instructions.
B. Wiring Method: Install wiring in raceway except within consoles, desks, and counters.
Conceal cable and raceway except in unfinished spaces.
C. Wiring Method: Install wiring in raceway where raceway is in an accessible location except
within consoles, cabinets, desks, and counters and except in accessible ceiling spaces and in
gypsum-board partitions where cable wiring method may be used. Use plenum cable in
environmental air spaces, including plenum ceilings. Conceal cable and raceway except in
unfinished spaces.
D. Install exposed cables parallel and perpendicular to surfaces or exposed structural members,
and follow surface contours. Secure and support cables by straps, staples, or similar fittings
so designed and installed to avoid damage to cables. Secure cable at intervals not exceeding
30 inches (760 mm) and not more than 6 inches from cabinets, boxes, or fittings.
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 31 ▪
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 32 ▪
END OF SECTION
Revision Log
▪ DIVISION 27 COMMUNICATIONS ▪
▪ PAGE 33 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Intrusion Detection Sensors
2. Signal Equipment
3. System Controls
4. Alarm Displays
5. Alarm Indicating Devices
B. Related Sections:
1. Section 26 05 00 (16050) - Common Work Results for Electrical
2. Section 26 05 53 (16075) - Identification for Electrical Systems
3. Section 26 35 33 (16280) - Power Factor Correction Equipment
4. Section 27 05 00 (16050) - Common Work Results for Communications
5. Section 28 23 00 (13740) - Video Surveillance
6. Section 28 31 00 (13850) - Fire Alarm and Detection Systems
1.02 REFERENCES
A. FM Global (FMG): Standards
B. Institute of Electrical and Electronics Engineers (IEEE) Publications:
1. C62.41 “Surge Voltages In Low-Voltage AC Power Circuits”
C. National Burglar and Fire Alarm Association (NBFAA)
D. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
2. 72 “National Fire Alarm Code”
E. Underwriter's Laboratories, Inc. (UL) Standards:
1. 681 “Installation and Classification of Burglar and Holdup Alarm Systems”
2. 1076 “Proprietary Burglar Alarm Units and Systems”
3. 1449 “Transient Voltage Surge Suppressors”
4. 1610 “Central-Station Burglar-Alarm Units”
5. 1641 “Installation and Classification of Residential Burglar Alarm Systems”
1.03 DEFINITIONS
A. Hard-Wired System: Alarm, supervisory, and detection devices that are directly connected,
through individual dedicated conductors, to central-control unit.
B. Zone: A space or area for which an intrusion must be detected and uniquely identified, the
sensor or group of sensors assigned to perform the detection, and any interface equipment
between the sensors and the communication link to central-control unit.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. ADT Security Services, Inc. , a Tyco International Business (800-238-8988).
B. Approved Manufacturer:
1. No substitutions accepted.
2.02 EQUIPMENT
A. Protection from Power Line Surges: Use integral surge suppressors listed in UL 1449 and
complying with IEEE C62.41, Category B. Include the following features:
1. Suppression Level: 300 V.
2. Maximum Response Time: 5 nanoseconds.
3. Circuit: Multistage, using inductors and silicon-avalanche zener diodes or equivalent.
4. Indicator Lamp: Labeled neon or LED located on control unit and arranged to extinguish
on failure of protection.
5. Fuses: Externally accessible.
B. System- and Equipment-Interference Resistance: Not affected by radiated-radio-frequency
interference and electrical induction of 15 V/m over a frequency range of 10 to 10,000 MHZ
and conducted interference signals up to 0.25-V RMS injected into power supply lines at 10 to
10,000 MHZ.
C. Tamper Protection: Tamper switches on detection devices, control units, annunciators, pull
boxes, junction boxes, cabinets, and other system components indicated to provide an alarm
signal when unit is opened or partially disassembled. Central-control unit identifies tamper
alarms and indicates location in alarm display.
D. Products: Provide the following products subject to conformance with the requirements
specified. Note: Connections shall be made to the relays (NO/NC) to provided fire alarm
control panel for fire alarm and fire alarm trouble.
1. “Focus 200 Control Dual Line Control Communicator with F-200 Interactive Keypad and
Standby Batteries”; ADT Security Systems, Inc.
a. Location: Telephone room.
b. Quantity: 1
2. “F-200 Interactive Keypad”; ADT Security Services, Inc.
a. Location: Administrative Office vestibule area.
b. Quantity: 1
3. Each: “Hold Up Button, ADT 270SN-ADT with Reset Tool”; ADT Security Services, Inc.
a. Location: Located at each check-in podium (if this is a traditional front desk then at
each end of the Front Desk) and on the work counter located in the Workroom.
PART 3 EXECUTION
3.01 INSTALLATION
A. Install system according to NFPA 70, NFPA 72, applicable codes, and manufacturer's written
instructions.
B. Comply with UL 681 and/or 1641.
END OF SECTION
Revision Log
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. CCTV Closed Circuit Television System.
B. Related Sections:
1. Section 26 05 00 (16050) - Common Work Results for Electrical
2. Section 26 05 53 (16075) - Identification for Electrical Systems
3. Section 26 35 33 (16280) - Power Factor Correction Equipment
4. Section 27 05 00 (16050) - Common Work Results for Communications
5. Section 28 16 00 (13730) – Intrusion Detection
6. Section 28 31 00 (13850) - Fire Alarm and Detection Systems
4.02 REFERENCES
A. Institute of Electrical and Electronics Engineers (IEEE) Publications:
1. C2 “ASC C2 Eighth Interim Collection of the National Electrical Safety Code”
2. C62.41 “Surge Voltages In Low-Voltage AC Power Circuits”
B. National Fire Protection Association (NFPA) Publications:
1. 70 "National Electric Code"
2. 72 “National Fire Alarm Code”
C. Underwriter's Laboratories, Inc. (UL) Standards:
1. 486A “Standard For Wire Connectors and Soldering Lugs for Use With Copper
Conductors”
2. 486B “Standard for Wire Connectors for Use With Aluminum Conductors”
3. 1449 “Transient Voltage Surge Suppressors”
4.03 DEFINITIONS
A. CCTV: Closed Circuit Television.
4.04 SYSTEM DESCRIPTION
A. Video cameras, camera outlets, camera controls, monitors, video switches, signal processing
equipment, control stations, distribution components, a videotape recorder, and accessories to
generate video images, process them, and distribute them.
B. System shall display images on monitors and provide for remote control of video-camera
equipment.
4.05 SUBMITTALS
A. Product Data: Include detailed manufacturer's specifications for each component specified.
Include data on features, ratings, and performance.
B. Shop Drawings: For CCTV equipment. Include plans, elevations, sections, details, and
attachments to other Work.
PART 6 EXECUTION
6.01 EXAMINATION
A. Install products in accordance with manufacturer’s recommendations.
B. Install all cable, and complete cable and power connections to all system devices.
C. Wire all system components in accordance with the National Electrical Code, NFPA and any
other authority having jurisdiction.
D. All equipment shall be firmly secured in place with all supports and fastenings providing a
safety factor of at least three. Provide adequate ventilation for all equipment.
END OF SECTION
Revision Log
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Automatic and Manual Fire Alarm System, complete per Marriott’s Fire Protection and
Life Safety Design Standards (Module 14), and applicable local, state and national codes
B. Related Documents:
1. Marriott’s Fire Protection and Life Safety Design Standards (Module 14):
a. Marriott’s Fire Protection and Life Safety Design Standards include Design
Standards, performance criteria, reference standards and life safety process
verification that define a comprehensive fire protection program.
C. Related Sections:
1. Section 14 24 23 (14240) – Elevators.
2. Section 21 10 00 (13900) - Fire Protection.
3. Section 27 05 00 (16050) – Common Work Results for Electrical
7.02 QUALITY ASSURANCE
A. Equipment shall be manufactured by a firm who has been actively manufacturing fire alarm
systems of the type required and shall have supplied similar equipment to comparable
installations and rendered satisfactory service for a minimum of 10 years. All components of
the fire alarm system shall be manufactured by the vendor supplying the equipment, and
standard products of a single manufacturer.
B. Material and equipment shall be new and UL listed.
PART 8 PRODUCTS
8.01 MANUFACTURERS
A. Avendra, LLC Preferred Manufacturers:
1. None.
B. Approved Manufacturers:
1. Tyco Integrated Fire and Security
a. Contact: William Glover (443-259-3352)
b. Email: wglover@tyco.com
a. Approved Models:
1) “EST/ADT 3000 Life Safety Control Panel Platform”
2) “EST Quickstart Series Intelligent Life Safety Control Panels”
3) “EST io 500 Intelligent Life Safety System”
4) “CP-3500” (replaces CP-3000, CP300D and CP300DA)
5) CP-3500D (replaces CP-3000, CP300D and CP300DA)
2. SimplexGrinnell –Tyco Fire & Security
a. Contact: John Morgan (978-731-7352)
PART 9 EXECUTION
9.01 INSTALLATION
A. Install system in accordance with Marriott’s Fire Protection and Life Safety Design Standards
(Module 14), all national, state and local codes, UL standards, and the manufacturer's
published instructions.
END OF SECTION
Revision Log
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Erosion and Sedimentation Control.
2. Site Demolition:
a. Selective Site Demolition:
1) Demolition of retaining walls, foundations, pavements, curbs and gutters,
drainage structures, and utilities, and backfilling voids resulting from removals
or demolition.
b. Building Demolition: Demolition of Structures.
3. Site Clearing:
a. Protection of Existing Trees
b. Removal of Trees and Other Vegetation
c. Topsoil Stripping and Stockpiling
d. Clearing and Grubbing
e. Removing Above-Grade Improvements, As Indicated On Drawings
B. Related Sections:
1. Section 01 50 00 (01500) - Construction Facilities and Temporary Controls
2. Section 31 20 00 (02300) – Earth Moving
1.02 QUALITY ASSURANCE
A. Regulatory Requirements:
1. Conform to applicable local code for demolition of structures, safety of adjacent
structures, dust control and runoff control.
2. Obtain required permits and licenses from authorities. Pay associated fees including
disposal charges.
3. Notify affected utility companies before starting work and comply with their requirements.
4. Do not close or obstruct roadways, sidewalks or hydrants without permits.
5. Conform to applicable regulatory procedures when discovering hazardous or
contaminated materials.
6. Test soils around buried tanks for contamination.
B. Contractor shall provide methods to ensure pollution control during the demolition period.
C. In addition to complying with all pertinent codes, the Contractor will also comply with the
requirements of those insurance carriers providing coverage for existing structures and this
work.
1. Comply with governing EPA notification regulations before starting selective demolition.
Comply with hauling disposal regulations of authorities having jurisdiction.
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 1 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 2 ▪
PART 2 PRODUCTS
2.01 FILL MATERIALS
A. Specified in Section 31 20 00 (02300) – Earth Moving
PART 3 EXECUTION
3.01 PREPARATION
A. Provide, erect, and maintain erosion control devices, temporary barriers and security devices
at locations indicated as specified in Section 01 50 00 (01500) and as shown on Drawings.
B. Protect existing landscaping materials, appurtenances and structures and other features
indicated to remain.
C. Prevent movement or settlement of adjacent structures: Provide bracing and shoring.
D. Mark location of utilities. Protect and maintain in safe and operable condition the utilities to
remain. Prevent interruption of existing utility service to occupied or used facilities, except
when authorized in writing by authorities having jurisdiction. Provide temporary services during
interruptions to existing utilities as acceptable to governing authorities and the Owner.
3.02 SITE DEMOLITION
A. General:
1. Document existing conditions of adjacent areas prior to start of demolition.
2. Conduct demolition to minimize interference with adjacent structures or pavements.
3. Cease operations immediately if adjacent structures appear to be in danger. Notify
authority having jurisdiction. Do not resume operations until directed.
4. Conduct operations with minimum interference to public or private access. Maintain
access and egress at all times.
5. Obtain written permission from adjacent property owners when demolition equipment will
traverse, infringe upon or limit access to their property.
6. Sprinkle Work with water to minimize dust. Provide hoses and water connections for this
purpose.
7. Comply with governing regulations pertaining to environmental protection.
8. Clean adjacent structures and improvements of dust, dirt, and debris caused by
demolition operations. Return adjacent areas to condition existing prior to start of work.
B. Pollution Controls:
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 3 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 4 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 5 ▪
END OF SECTION
Revision Log
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 6 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Excavation and Grading To Levels and Elevations Indicated on the Drawings.
2. Preparation of Subgrade For Building Slabs, Walks, and Pavements.
3. Drainage Course for Slabs-On-Grade.
4. Excavation and Backfilling Trenches Within Building Lines.
5. On Site and Imported Fill to Bring Areas To Elevations Indicated On Drawings.
B. Related Sections:
1. Section 00 31 32 (00320) - Geotechnical Data
2. Section 01 50 00 (01500) - Construction Facilities and Temporary Controls
3. Section 03 30 00 (03300) - Cast-In-Place Concrete
4. Section 31 20 00 (02200) - Site Clearing
5. Section 31 12 16 (02740) – Asphalt Paving
6. Section 31 13 13 (02751) - Concrete Paving
7. Section 32 90 00 (02900) – Planting: Final grading, together with placement and
preparation of topsoil for lawns and planting.
8. Excavating and Backfilling or Fire Suppression, Plumbing, HVAC , Electrical and
Communications Work: Refer to Drawings and Divisions 21, 22, 23, 26, & 27 Sections
for excavation and backfill required in conjunction with underground utilities and buried
plumbing, HVAC, electrical and communication appurtenances.
4.02 DEFINITIONS
A. Excavation: Removal of material encountered above subgrade elevations.
1. Additional Excavation: Excavation below subgrade elevations as directed by Architect.
Additional excavation and replacement material will be paid for according to Contract
provisions for changes in the Work.
2. Bulk Excavation: Excavations more than 10 feet in width and pits more than 30 feet in
either length or width.
B. Unauthorized excavation consists of removal of materials beyond indicated subgrade
elevations or dimensions without specific direction of [Owner’s Representative]. Unauthorized
excavation, as well as remedial work directed by [Owner’s Representative] shall be at
Contractor's expense.
1. Under footings, foundation bases, or retaining walls, fill unauthorized excavation by
extending indicated bottom elevation of footing or base to excavation bottom, without
altering required top elevation with engineered fill. Lean concrete fill may be used to
bring elevations to proper position, when acceptable to Owner’s Representative.
2. In locations other than those above, backfill and compact unauthorized excavations as
specified for authorized excavations of same classifications, unless otherwise directed by
Owner’s Representative.
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 7 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 8 ▪
PART 5 PRODUCTS
5.01 SOIL MATERIALS
A. Satisfactory soil materials are defined as those complying with ASTM D2487 soil classification
groups GW, GP, GM, SM, SW, and SP.
B. Unsatisfactory soil materials are defined as those complying with ASTM D2487 soil
classification groups GC, SC, ML, MH, CL, CH, OL, OH, and PT, or a combination of these
symbols.
5.02 FILL MATERIALS
A. The Contractor shall include the cost of all required fill in their proposal.
B. All fill material, unless noted otherwise herein, shall be a clean fill material free of debris and
organic matter and shall have a plasticity index of less than 20. Material shall be free of rock,
stone, or broken concrete larger than 4 inches in the largest dimension.
5.03 GRANULAR FILL MATERIAL
A. Granular fill materials shall be bank run gravel or sand, or processed stone which meets the
gradation criteria of the Unit Soil Classification System for Well Graded Gravel (GW) or sand
(SW or SP). Maximum particle size shall pass a 2-inch sieve.
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 9 ▪
PART 6 EXECUTION
6.01 PREPARATION
A. Prior to construction, all existing sod, topsoil, and vegetation along with any soft/loose
deposits that become obvious thereafter shall be completely removed from within the
proposed building and pavement limits, and areas to be cut or receive fill.
B. Refer to Section 31 20 00 (02200) for protection, excavation, filling and grading around
existing trees.
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 10 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 11 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 12 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 13 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 14 ▪
END OF SECTION
Revision Log
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 15 ▪
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Soil treatment below slabs-on-grade for subterranean insects, within limits of foundation
system.
2. Soil treatment at interior and exterior foundation perimeter, for subterranean insects.
7.02 DEFINITIONS
A. EPA - Federal Insecticide, Fungicide, and Rodenticide Act.
B. PCO - Pest Control Operator
7.03 SUBMITTALS
A. Submit product data under provision that indicate toxicants to be used, composition by
percentage, dilution schedule, and intended application rate.
B. Certification that products comply with U.S. Environmental Protective Agency (EPA)
regulations for termiticides.
1. Include the EPA-Registered Label for termiticide and borate products.
7.04 QUALITY ASSURANCE
A. Applicator: Professional Pest Control Operator licensed according to regulations of authorities
having jurisdiction to apply soil treatment system in jurisdiction where Project is located and
who is an experienced installed who employs workers trained and approved by manufacturer
to install manufactured products.
B. Materials: Provide certification that toxicants conform to requirements of the EPA and the
authority having jurisdiction.
C. Material Packaging: Manufacturer's labels and seals identifying content. Label with a Federal
Registration Number, to comply with EPA regulations and authorities having jurisdiction.
D. Regulatory Requirements:
1. Conform to U.S. Government and State requirements for application licensing and
authority to use toxicant chemicals.
7.05 PROJECT RECORD DOCUMENTS
A. Accurately record moisture content of soil before treatment, date, and rate of application,
areas of application, diary of meter readings and corresponding soil coverage.
7.06 PROJECT CONDITIONS
A. Restrictions: Do not apply soil treatment solution until excavating, filling, and grading
operations are completed, except as otherwise required in construction operations.
B. Environmental Limitations: To ensure penetration, do not treat soil that is water saturated or
frozen. Do not treat soil while penetration is occurring. Comply with EPA-Registered Label
requirements and requirements of authorities having jurisdiction.
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 16 ▪
PART 8 PRODUCTS
8.01 SOIL TREATMENT
A. Termiticide: Provide an EPA-registered termiticide complying with requirements of authorities
having jurisdiction, in a soluble or emulsible, concentrated formulation that dilutes with water
or foaming agent, and formulated to prevent termite infestation. Use only soil treatment
solutions that are not harmful to plants. Provide quantity required for application at the label
volume and rate for the maximum termiticide concentration allowed for each specific use,
according to the product's EPA-Registered Label.
PART 9 EXECUTION
9.01 EXAMINATION
A. Examine substrates, areas, and conditions, with Applicator present, for compliance with
requirements for moisture content of the soil, interfaces with earthwork, slab and foundation
work, landscaping, and other conditions affecting performance of termite control. Proceed
with application only after unsatisfactory conditions have been corrected.
9.02 PREPARATION
A. General: Comply with the most stringent requirements of authorities having jurisdiction and
with manufacturer's written instructions for preparing substrate. Remove all extraneous
sources of wood cellulose and other edible materials such as wood debris, tree stumps and
roots, stakes, formwork, and construction waste wood from soil and around foundations.
B. Soil Treatment Preparation: Remove foreign matter and impermeable soil materials that could
decrease treatment effectiveness on areas to be treated. Loosen, rake, and level soil to be
treated, except previously compacted areas under slabs and footings. Termiticides may be
applied before placing compacted fill under slabs if recommended by termiticide manufacturer.
C. Fit filling hose connected to water source at the site with a backflow preventer, complying with
requirements of authorities having jurisdiction.
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 17 ▪
END OF SECTION
Revision Log
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 18 ▪
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Bored Piles:
a. Drilled Concrete Piers and Shafts
B. Related Sections:
1. Section 00 31 32 (00320) - Geotechnical Data
2. Section 01 45 00 (01450) - Quality Control: Procedures for Testing and Inspection.
3. Section 03 30 00 (03300) - Cast-in-Place Concrete: Concrete and concrete
reinforcement.
10.02 REFERENCES
A. ASTM International (ASTM) Publications:
1. A252 “Welded and Seamless Steel Pipe Piles”.
10.03 DESIGN REQUIREMENTS
A. Load Carrying Capacities: Indicated on Structural Drawings.
10.04 SUBMITTALS
A. General: Submit the following in accordance with Conditions of Contract and Division 01
Specification Sections.
B. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) indicating
specified items selected for use in project with the following supporting data.
1. Product Data
2. Reports; Drilled Piers: Submit the following reports:
a. Concrete materials test reports as proposed for use in concrete mixes.
b. Preliminary pier report of actual allowable bearing capacity at bottom of each shaft,
issued as soon as possible after testing each excavation.
c. Certified pier report for each pier, recording actual elevation at bottom and top, final
centerline location at top, variation of shaft from plumb, result of all tests performed,
levelness of bottom seepage of water and top of any casing left in place, any
unusual conditions, corrective measures and construction changes, variation of
dimensions from excavation, completion of excavation, inspection, testing, and
placement of concrete, delays in concreting, and location of construction joints in
shaft, and any other data as may be required.
10.05 QUALITY ASSURANCE
A. Installer Qualifications: Company specializing in performing Work of this Section with minimum
10 years documented experience.
B. Pre-lnstallation Meeting:
1. Convene a pre-installation meeting at site, one week prior to commencing Work . Require
attendance of parties directly affecting Work of this Section, including, but not limited to,
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 19 ▪
PART 11 PRODUCTS
11.01 MATERIALS
A. Casing: ASTM A252, Grade 1, Grade 2, and Grade 3 single length steel pipe.
1. Wall: Plain,1/4 inch minimum thickness
2. 2. Ends: Plain.
3. 3 Diameter: Outside diameter not less than indicated shaft sizes.
B. Concrete: Specified in Section 03 30 00 (03300) using Type I or II cement, 3/4 inch aggregate
size, 3,000 psi 28 day strength, 5-7 inch slump.
C. Reinforcement: Specified in Section 03 30 00 (03300).
D. Reinforcing Cage Support and Alignment System
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. “Centraligner Pier Sleds and Hijacker Pier Bolsters”; Pieresearch (800-656-0417)
b. Approved substitution
3. Products:
a. Pier Bolster: Unit consisting of a fabricated concrete support with minimum
compressive strength of 8,500 psi with integral tie wires.
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 20 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 21 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 22 ▪
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 23 ▪
END OF SECTION
Revision Log
▪ DIVISION 31 EARTHWORK▪
▪ PAGE 24 ▪
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Hot-Mix Asphalt Paving
2. Pavement markings, including temporary markings before sealer coat and final markings
after sealer coat.
B. Related Sections:
1. Section 31 10 00 (02200) – Site Clearing
2. Section 31 20 00 (02300) – Earth Moving
3. Section 32 13 13 (02751) - Concrete Paving
1.02 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) and with the
following supporting data:
1. Product Data: For each product specified include technical data and tested physical
performance properties.
2. Job Mix Designs: For each job mix proposed for the work.
3. Material Certificates: Provide copies of materials certificates signed by material producer
and Contractor certifying that each material item complies with, or exceeds, specified
requirements, including job mix design.
1.03 QUALITY ASSURANCE
A. Provide hot-mix asphalt pavement according to the materials, workmanship, and other
applicable requirements of the standard specifications of the State Department of
Transportation (DOT), or of authorities having jurisdiction.
B. Use locally available materials and gradations which meet standard state highway
specifications and exhibit satisfactory records of previous installations.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Deliver pavement-marking materials to Project site in original packages with seals unbroken
and bearing manufacturer’s labels containing brand name and type of material, date of
manufacturer, and directions for storage.
B. Store pavement-marking materials in a clean, dry, protected location and within temperature
range required by manufacturer. Protect stored materials from direct sunlight.
1.05 PROJECT CONDITIONS
A. Weather Limitations: Apply prime and tack coats when ambient temperature is above 50 deg.
F., and when temperature has not been below 35 deg. F. for 12 hours immediately prior to
application. Do not apply when base is wet or contains an excess of moisture.
B. Construct asphalt concrete surface course when atmospheric temperature is above 40 deg.
F., and when base is dry. Base course may be placed when air temperature is above 30 deg.
F. and rising.
PART 2 PRODUCTS
2.01 AGGREGATES
A. General: Use materials and gradations that have performed satisfactorily in previous
installations.
B. Coarse Aggregate: Sound; angular crushed stone; crushed gravel; or properly cured, crushed
blast-furnace slag; complying with ASTM D692.
C. Fine Aggregate: Sharp-edged natural sand or sand prepared from stone; gravel, properly
cured blast-furnace slag, or combinations thereof; complying with ASTM D1073.
1. For hot-mix asphalt, limit natural sand to a maximum of 20 percent by weight of the total
aggregate mass.
D. Mineral Filler: Rock or slag dust, hydraulic cement, or other inert material complying with
ASTM D242, if recommended by applicable DOT standards.
2.02 ASPHALT MATERIALS
A. Asphalt Cement: Comply with ASTM D3381; Table 2 AC-10, AC-20, or AC-30, viscosity
grade, depending on local mean annual air temperature as indicated below:
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that subgrade is dry and in suitable condition to support paving and imposed loads.
B. Notify General Contractor in writing of any unsatisfactory conditions. Do not begin paving
installation until these conditions have been satisfactorily corrected.
3.02 SURFACE PREPARATION
A. General: Immediately before placing asphalt minerals, remove loose and deleterious material
from substrate surfaces. Ensure that prepared subgrade is ready to receive paving.
1. Sweep loose granular particles from surface of unbound-aggregate base course. Do not
dislodge or disturb aggregate embedded in compacted surface of base course.
B. Herbicide Treatment: Apply herbicide according to manufacturer's recommended rates and
written application instructions. Apply to dry, prepared subgrade or surface of
compacted-aggregate base before applying paving materials.
1. Mix herbicide with prime coat when formulated by manufacturer for that purpose.
C. Prime Coat: Apply uniformly over surface of compacted-aggregate base at a rate of 0.15 to
0.50 gal./sq. yd. Apply enough material to penetrate and seal, but not flood, surface. Allow
prime coat to cure for 72 hours minimum.
1. If prime coat is not entirely absorbed within 24 hours after application, spread sand over
surface to blot excess asphalt. Use just enough sand to prevent pickup under traffic.
Remove loose sand by sweeping before pavement is placed and after volatiles have
evaporated.
2. Protect primed substrate from damage until ready to receive paving.
D. Base Coat: Apply over compacted subgrade. Apply material to penetrate and seal, but not
flood surface. Cure and dry as long as necessary to attain penetration and evaporation of
volatile.
E. Tack Coat: Apply to contact surfaces of previously constructed asphalt or Portland cement
concrete and surfaces abutting or projecting into asphalt concrete pavement.
F. Allow to dry until at proper condition to receive paving.
G. Exercise care in applying bituminous materials to avoid smearing of adjoining concrete
surfacing. Remove and clean damaged surfaces.
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Extent of portland cement concrete paving is shown on Drawings, including curbs,
walkways, approaches, pavement, and exterior stairs.
2. Colored, imprinted, and textured concrete paving.
3. Pavement-Marking Paint
4. Paving Joint Sealers
B. Related Sections:
1. Section 03 30 00 (03300) – Cast-In-Place Concrete
2. Section 31 10 00 (02200) – Site Clearing
3. Section 31 10 00 (02200) – Earth Moving
4. Section 32 12 16 (02740) - Asphalt Paving
4.02 REFERENCE STANDARDS
A. American Association of State Highway and Transportation Officials (AASHTO) Publications:
1. M248 “Ready-Mixed White and Yellow Traffic Paints”
B. American Concrete Institute (ACI) Publications:
1. 117 "Standard Specifications for Tolerances for Concrete Construction and Materials"
2. 301 "Standard Specification for Structural Concrete"
C. American National Standards Institute (ANSI) Publications:
1. A117.1 “Standard on Accessible and Usable Buildings and Facilities”
D. ASTM International (ASTM) Publications:
1. A82 “Standard Specification for Steel Wire, Plain, for Concrete Reinforcement”
2. A185 “Standard Specification for Steel Welded Wire Reinforcement, Plain, for Concrete”
3. A307 "Standard Specification for Carbon Steel Bolts and Studs, 60 000 PSI Tensile
Strength"
4. C309 “Standard Specification for Liquid Membrane-Forming Compounds for Curing
Concrete”
5. A615 "Standard Specification for Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement"
6. A775 “Standard Specification for Epoxy-Coated Steel Reinforcing Bars”
7. C94 “Standard Specification for Ready-Mixed Concrete”
8. C260 “Standard Specification for Mortar for Unit Masonry”
9. C881 “Standard Specification for Epoxy-Resin-Base Bonding Systems for Concrete”
10. C920 “Standard Specification for Elastomeric Joint Sealants”
PART 6 EXECUTION
6.01 SURFACE PREPARATION
A. Proof-roll prepared subbase surface to check for unstable areas and need for additional
compaction. Do not begin paving work until such conditions have been corrected and
subgrade is ready to receive paving.
B. Remove loose material from compacted subbase surface immediately before placing
concrete.
6.02 EDGE FORMS AND SCREED CONSTRUCTION
A. Set, brace, and secure edge forms, bulkheads, and intermediate screed guides for pavement
to required lines, grades, and elevations. Install forms to allow continuous progress of work
and so forms can remain in place at least 24 hours after concrete placement
B. Check completed formwork for grade and alignment to following tolerances:
1. Top of forms not more than 1/4 inch in 10 feet.
2. Vertical face on longitudinal axis not more than 1/4 inch in 10 feet.
C. Clean forms after each use and coat with form release agent as required to ensure separation
from concrete without damage.
D. Slope step treads at 1/4 inch per foot to drain.
6.03 STEEL REINFORCEMENT
A. General: Comply with CRSI's "Manual of Standard Practice" for fabricating reinforcement,
with recommendations in CRSI's "Placing Reinforcing Bars" and as specified in Division 03
Sections, for placing and supporting reinforcement.
B. Install fabricated bar mats in lengths as long as practicable. Handle units to keep them flat
and free of distortions. Straighten bends, kinks, and other irregularities, or replace units as
required before placement. Set mats for a minimum 2" overlap to adjust mats.
6.04 JOINTS
A. General: Construct expansion, weakened-plane (contraction), and construction joints true to
line with face perpendicular to surface of concrete. Construct transverse joints at right angles
to the centerline, unless otherwise indicated.
1. When joining existing structures, place transverse joints to align with previously placed
joints, unless otherwise indicated.
2. Use a bonding agent at locations where fresh concrete is placed against hardened or
partially hardened concrete surfaces.
END OF SECTION
Revision Log
PART 7 GENERAL
7.01 SUMMARY
A. Section Includes:
1. Wood Fences and Gates
B. Related Sections:
1. Section 05 73 00 (05720) - Ornamental Handrails and Railings
2. Section 09 90 00 (09900) - Painting: Painting steel gates
3. Section 31 20 00 (02300) – Earth Moving
4. Section 32 31 13 (02821) - Chain Link Fences and Gates
7.02 REFERENCES
A. American Society of Testing Materials (ASTM):
1. ASTM A36 “Standard Specification for Carbon Structural Steel”
2. ASTM A123 “Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and
Steel Products’
3. ASTM A153 "Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel
Hardware"
4. ASTM A500 "Standard Specification for Cold-Formed Welded and Seamless Carbon
Steel Structural Tubing in Rounds and Shapes"
B. American Welding Society (AWS)
1. AWS D1.1 "Structural Welding Code - Steel"
7.03 SUBMITTALS
A. Submit “Letter of Conformance” in accordance with Section 01 33 00 (01330) and with the
following supporting data:
1. Product Data and manufacturer’s written instructions for care, installation and
maintenance.
B. Shop Drawings:
1. Show Dimensions, fencing layout, finish, weight and size of members, methods of
fastening, and installation details of fence and gates. Provide coordination drawings
where inserts or sleeves are required.
PART 8 PRODUCTS
8.01 WOOD FENCES AND GATES
A. Wood Materials: Western Red Cedar; WRCLA.
1. Fence (Slats) Boards and Trim: Surfaced One Side, Two Edges (S1S2E); Standard
Grade and Better; size and location as indicated on Drawings.
PART 9 EXECUTION
9.01 INSTALLATION
A. Construct plumb, square, level and anchored securely with smooth miters and field cuts after
joining. Provide adequate support for anchoring.
B. Install gates plumb, level, and secure for full opening without interference. Adjust hardware for
smooth operation.
C. Set posts in concrete footings as shown on Drawings.
D. Expansion Bolts:
1. Install in snug fittings, smoothly drilled holes in accordance with the manufacturer's
written instructions.
2. Place bolts so load acts in shear.
END OF SECTION
Revision Log
PART 10 GENERAL
10.01 SUMMARY
A. Section Includes:
1. Irrigation System: Lawn sprinkler system
B. Related Sections:
1. Section 31 20 00 (02300) – Earth Moving
2. Section 32 90 00 (02900) - Planting
3. Section 33 00 00 (02500) - Utilities
10.02 REFERENCES
A. American Society of Testing Materials (ASTM):
1. ASTM D1784 “Rigid Poly(Vinyl Chloride) (PVC) Compounds and Chlorinated Poly(Vinyl
Chloride) (CPVC) Compounds”
2. ASTM D2241 “Poly (Vinyl Chloride) (PVC) Pressure-Rated Pipe (SDR Series)”
3. D2466 “Poly (Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 40”
B. American Welding Society (AWS)
1. D1.1 "Structural Welding Code - Steel"
10.03 DEFINITIONS
A. Circuit Piping: Downstream from control valves to sprinklers, specialties, and drain valves.
Piping is under pressure during flow.
B. Drain Piping: Downstream from circuit-piping drain valves. Piping is not under pressure.
C. Pressure Piping: Downstream from point of connection to water distribution piping to and
including control valves. Piping is under water distribution system pressure.
D. The following are industry abbreviations for plastic materials:
1. PVC: Polyvinyl chloride plastic
10.04 SYSTEM DESCRIPTION
A. All irrigation systems to be furnished and installed as a subcontract to Section 32 90 00
(02900) - Planting.
B. Design Requirements for Lawn Sprinkler System:
1. Provide 100% coverage as described in Design Guideline Standards, unless otherwise
specified herein. Layout portions of irrigation system not indicated on Drawings to meet
specified coverage in compliance with local codes and regulations.
2. Provide complete irrigation system including trenching and backfilling for all pipes, values
and drain pits, providing mains, laterals, risers, fittings, sprinkler heads, values,
controllers, electric wiring, and necessary specialties and accessories.
3. Provide sleeves beneath parking areas, walkways, roads, and driveways where required.
PART 11 PRODUCTS
11.01 MANUFACTURERS
A. Unless Noted Otherwise, provide products by the following:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. Rain Bird Corporation (520-741-6100)
b. Approved Substitution
11.02 PIPE AND PIPE FITTINGS
A. Irrigation Mains:
1. Pipe: ASTM D1784, PVC Class-200, SDR-21, 260 psi maximum.
2. Joint: ASTM D2241 bell end type.
3. Fittings: Schedule 40, ASTM D2466 solvent cement type.
B. Zone Lateral Lines:
1. Pipe: ASTM D1784, PVC Class-200, SDR-21.
2. Joints: ASTM D2241 bell end.
3. Fittings: ASTM D2466 Sockettype.
C. Pipe shall be marked continuously and permanently with the following information:
Manufacturer's name, nominal pipe size, class or schedule, and NSF approval, and type of
pipe.
11.03 VALVES
A. Gate Valves:
1. 3 Inch and Larger: Iron body, non-rising stem, threaded ends.
2. 2 1/2 Inch and Smaller: Type 1, class 150 psi, threaded ends.
B. Station Control Valves:
C. Maintenance:
1. After substantial completion of the installation of landscape-related materials, maintain
system for 60 days.
END OF SECTION
Revision Log
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Water Distribution:
a. Site Domestic and Fire Protection Waterlines and Appurtenances
2. Sanitary Sewerage:
a. Sanitary Sewage Systems, Manholes, and Cleanouts
B. Related Sections:
1. Section 03 30 00 (03300) - Cast-in-Place Concrete: Concrete for thrust blocks and
manholes.
2. Section 31 20 00 (02300) - Earth Moving: Trenching and backfilling for utilities.
3. Section 33 46 00 (02620) - Subdrainage: Storm sewers and subdrainage systems.
1.02 REFERENCES
A. The American Society of Mechanical Engineers (ASME) Publications:
1. B16.18 “Cast Copper Alloy Solder Joint Pressure Fittings”.
2. B16.22 “Wrought Copper and Copper Alloy Solder Joint Pressure Fittings”.
B. ASTM International (ASTM) Publications: (Former American Society for Testing and Materials)
1. A48 "Standard Specification for Gray Iron Castings"
2. A746 “Specification for Ductile Iron Gravity Sewer Pipe”
3. B88 “Standard Specification for Seamless Copper Water Tube”
4. C12 “Practice for Installing Vitrified Clay Pipe Lines”
5. C14 “Specification for Concrete Sewer, Storm Drain, and Culvert Pipe”
6. C55 “Specification for Concrete Building Brick”
7. C76 “Specification for Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe”
8. C425 “Specification for Compression Joints for Vitrified Clay Pipe and Fittings”
9. C443 “Specification for Joints for Circular Concrete Sewer and Culvert Pipe, Using
Rubber Gaskets”
10. C478 “Specification for Precast Reinforced Concrete Manhole Sections”
11. C700 “Standard Specification for Vitrified Clay Pipe, Extra Strength, Standard Strength,
and Perforated”
12. C923 “Specification for Resilient Connectors Between Reinforced Concrete Manhole
Structures and Pipes”
13. D1785 “Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40,
80, and 120”
14. D2241 “Specification for Polyvinyl Chloride (PVC) Pressure Rated Pipe (SDR Series).6”
15. D3034 “Specification for Type PSM Polyvinyl Chloride (PVC) Sewer Pipe and Fittings”
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 1 ▪
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 2 ▪
PART 2 PRODUCTS
2.01 WATER PIPE
A. Pipe sizes less than 3 inch that are installed below grade and outside building shall comply
with one or combination of following:
1. Seamless Copper Tubing: Type "K" soft copper to comply with ASTM B88 latest edition
and installed with wrought copper (95-5 Tin Antimony solder joint) fittings in accordance
with ASME B16.22.
2. Polyvinyl Chloride (PVC) Water Pipe: Pipe shall conform to ASTM D2241 with an SDR 21
rating and shall be continually marked with manufacturer's name, pipe size, cell
classification, SDR rating, and ASTM D1785 classification. Pipe joints shall be integrally
molded bell ends in accordance with ASTM D3139 with factory supplied elastomeric
gaskets and lubricant.
B. Pipe sizes 3 inch and larger that are installed below grade and outside building shall comply
with one of the following:
1. Ductile Iron Water Pipe: In accordance with ANSI/AWWA C151, Fittings shall be either
mechanical joint or push-on joint complying with ANSI/AWWA C110 or
ANSI/AWWA C111 (CLASS So).
2. Polyvinyl Chloride (PVC) Water Pipe: Pipe shall meet the requirements of AWWA C900
and comply with ASTM D2241, rated SDR 21 (Class 150). Pipe shall be continually
marked as for smaller pipes. Pipe joints shall be integrally molded bell ends in
accordance with ASTM D3034, Table 2, with factory supplied elastomeric gaskets and
lubricant.
2.02 SEWER PIPE
A. Polyvinyl Chloride (PVC) Pipe:
1. ASTM D3034, Rated SDR 35 unless otherwise required by local utility having jurisdiction.
Continuously mark pipe with manufacturer's name, pipe size, cell classification, SDR
rating, and ASTM D3034 classification.
2. ASTM D3034, Table 2; pipe joints with integrally molded bell ends and factory supplied
elastomeric gaskets and lubricant.
B. ABS or PVC Composite Pipe:
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. Truss Pipe"; Contech Engineered Solutions (800-338-1122)
3. ASTM D2680 for composite pipe and fittings.
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 3 ▪
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 4 ▪
B. Locked Mechanical Joint fittings shall be installed where pressure line vertical changes in
direction are required and, if approved by the Owner and governing authority, may be installed
in lieu of the above thrust blocking requirements.
C. Trace Wire: Magnetic detectable conductor, clear brightly colored plastic covered, imprinted
with "DOMESTIC WATER SERVICE" or "SEWER SERVICE" in large letters.
D. Pipe Joints: Mechanical clamp ring type, stainless steel expanding and contracting sleeve,
neoprene ribbed gasket for positive seal.
E. Fittings: Same material as pipe molded or formed to suit pipe size and end design, in required
tee, bends, elbows, cleanouts, reducers, traps and other configurations required.
2.08 MANHOLES
A. Precast Concrete: Reinforced precast concrete in accordance with ASTM C890 with gaskets
in accordance with ASTM C923. Construct manholes as shown on the Drawings but not less
than 4 foot 0 inch inside diameter.
B. Cast-ln-Place Concrete: Non-reinforced cast-in-place concrete shall be constructed of 3500
psi concrete specified in Section 03 30 00.
C. Concrete Brick Masonry Units: ASTM C55, Grade N Type I- Moisture Controlled normal
weight of same Grade, Type and weight as block units, nominal modular size of 3 5/8” x 5/8” x
2 1/4”.
D. Mortar and Grout: Mortar for finishing and sealing shall be Class "C". Honeycombing less than
2 inches deep shall be repaired using Class "D" mortar.
E. Brick Transition Reinforcement: Formed steel 8 gage wire with galvanized finish.
F. Lid and Frame: ASTM A48, Class 30B Heavy Duty Cast iron construction, machined flat
bearing surface, removable lid, closed or open as indicated on Drawings; with sealing gasket.
1. Avendra, LLC Preferred Manufacturers:
a. None
2. Approved Manufacturers:
a. Neenah Foundry Company (920-725-7000)
G. Manhole Steps:
1. Avendra, LLC Preferred Manufacturers:
a. None
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 5 ▪
PART 3 EXECUTION
3.01 PREPARATION
A. Hand trim excavations to required elevations. Correct over excavation with fine aggregate.
B. Remove large stones or other hard matter which could damage pipe or impede consistent
backfilling or compaction.
C. Cut pipe ends square, ream pipe and tube ends and remove burrs.
D. Remove scale and dirt, on inside and outside, before assembly.
E. Prepare pipe for connections to equipment with flanges or unions.
F. Remove large stones or other hard matter which could damage pipe or impede consistent
backfilling or compaction.
G. Coordinate placement of inlet and outlet pipe or pipe sleeves as indicated on Drawings.
3.02 BEDDING
A. Excavate pipe trench and place bedding material in accordance with Section 31 20 00
“Earth Moving for work of this Section. Provide trench wall shoring as required.
B. Place bedding material at trench bottom, level fill materials in one continuous layer not
exceeding 6 inches compacted depth, each layer. Place compacted bedding material to
elevation of paving subgrade as indicated on Drawings.
C. Maintain optimum moisture content of bedding material to attain required compaction density.
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 6 ▪
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 7 ▪
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 8 ▪
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 9 ▪
SD P
L = 133200
B. Visible Leakage: All visible leaks shall be repaired regardless of the amount of leakage.
C. Acceptance of Installation: If any test of pipe laid in place discloses leakage greater than that
specified, the Contractor shall, at his own expense, locate the leak and make repairs as
necessary until the leakage is within the specified allowance. Contractor shall supply all water
for testing at no expense to the Owner.
D. Provide one copy of results of meter test and hydrostatic pressure test to the Owner and utility
company upon completion of water distribution backfilling operations.
E. Sewerline Tests:
1. Alignment and Deflection Tests:
F. Ball Test: Prior to other tests all sewer lines should be cleaned and tested for major defects by
flushing with an appropriately sized sewer cleaning ball. Precleaning by high velocity jet or
other method may be necessary.
G. Visual Test: All sewer lines shall be inspected visually by the Contractor to verify accuracy of
alignment and freedom from debris and obstructions. The full diameter of the pipe should be
visible when viewed between consecutive manholes. The method of test may be photography,
closed circuit television or visually ramping with mirrors and lights.
H. Deflection Testing: The maximum allowable pipe deflection is 7.5%. The Contractor may, at
his option, use a deflectometer, calibrated television or photography.
1. Pressure and Infiltration Tests:
a. Perform pressure and infiltration tests in accordance with applicable local Public
Works Department Standard Specifications and requirements.
END OF SECTION
Revision Log
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 10 ▪
PART 4 GENERAL
4.01 SUMMARY
A. Section Includes:
1. Subdrainage: Subsurface Drainage Board
2. Storm Drainage: Storm Drainage Pipe and Fittings
B. Related Sections:
1. Section 31 20 00 (02300) – Earth Moving: Trenching and backfilling for utilities.
2. Section 33 00 00 (02500) - Utilities: Manholes and appurtenances
4.02 REFERENCES
A. American Society for Testing and Materials (ASTM):
1. ASTM A760 - Specification for Pipe, Corrugated Steel, Zinc Coated, (Galvanized).
2. ASTM C12 - Practice for Installing Vitrified Clay Pipe Lines.
3. ASTM C76 - Specification for Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe.
4. ASTM C443 - Specification for Joints for Circular Concrete Sewer and Culvert Pipe,
Using Rubber Gaskets.
5. ASTM D2321 - Recommended Practice for Underground Installation of Flexible
Thermoplastic Sewer Pipe.
6. ASTM D3034 - Specification for Type PSM Polyvinyl Chloride (PVC) Sewer Pipe and
Fittings.
4.03 DEFINITIONS
A. Bedding: Fill placed under, beside and directly over pipe, prior to start of backfill operations.
4.04 SUBMITTALS
A. Submit "Letter of Conformance" in accordance with Section 01 33 00 (01330) and with the
following supporting data:
1. Product Data: Indicating pipe, pipe accessories, and fittings.
2. Manufacturer's Installation Instructions: Indicate special procedures required to install
products specified.
B. Project Record Documents: Accurately record the following.
1. Actual locations of pipe runs, connections, manholes, catch basins, cleanouts, and invert
elevations.
2. Identify and describe unexpected variations to subsoil conditions and location of
uncharted utilities.
4.05 QUALITY ASSURANCE
A. Regulatory Requirements: Conform to local Public Works Standard Specifications for
materials and installation of the work of this Section.
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 11 ▪
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 12 ▪
PART 6 EXECUTION
6.01 PREPARATION
A. Hand trim excavations to required elevations. Correct over excavation with fine aggregate.
B. Remove large stones or other hard matter which could damage piping or impede consistent
backfilling or compaction.
6.02 BEDDING
A. Excavate pipe trench as specified in Section 31 20 00 (02300) – Earth Moving. Hand trim
excavation for accurate placement of pipe to elevations indicated.
B. Place bedding material at trench bottom, level materials in continuous layers not exceeding 6
inches compacted depth, each layer. Place compacted bedding material to elevation of paving
subgrade as indicated on Drawings.
C. Maintain optimum moisture content of bedding material to attain required compaction density.
D. Remove excess backfill and excavated material from site.
6.03 INSTALLATION - PIPE
A. Install pipe, fittings, and accessories in accordance with ASTM C12, ASTM D2321 or
manufacturer's published instructions and state or local requirements. Seal joints watertight.
B. Install pipe on minimum 4 inch bedding as specified in Section 31 20 00 (02300).
C. Lay pipe to slope gradients indicated on Drawings.
D. Install aggregate at sides and over top of pipe. Provide top cover to minimum compacted
thickness equal to paving subgrade indicated on Drawings.
E. Refer to Section 31 20 00 (02300) for trenching requirements. Do not displace or damage pipe
when compacting.
F. Refer to Section 33 00 00 (02500) - Utility Systems for manhole requirements.
G. Connect to municipal storm sewer systems, manholes, and inlets as indicated on Drawings.
6.04 INSTALLATION - CATCH BASINS, INLETS, AND JUNCTION BOXES
A. Form bottom of excavation clean and smooth to elevation indicated on Drawings.
B. Form and place cast-in-place concrete base pad, with provision for storm sewer pipe to be
placed at required elevations.
C. Form and place cast-in-place concrete walls, sleeved at required elevation, to receive storm
sewer pipe as indicated on Drawings.
D. Form and place cast-in-place top of structure as indicated on Drawings.
E. Mount grate and frame level, in grout, secured to top section at elevation indicated.
6.05 CONSTRUCTION
A. Interface with Other work: Coordinate the Work with termination of storm sewer connection
outside building including connection to municipal storm sewer system.
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 13 ▪
END OF SECTION
Revision Log
▪ DIVISION 33 UTILITIES ▪
▪ PAGE 14 ▪