1. Objective
To outline the work methodology for Priming, Waterproofing and Concrete Topping works to exposed
RC slabs for the Project by means of provision of clear sequences of works in order to achieve a quality
finished works.
METHOD STATEMENT
In overall, to achieve the objective outlined, we propose to segregate the works in following stages for
ease of monitoring:
3. Concrete casting -
- Trial mix shall be conducted at least 30 days before the actual waterproofing concrete is cast.
- Check that the maximum free water/cement ratio is not greater that 0.45(free water-fine aggregate
moisture + admixture)
- Determine the quantity of concrete that to be treated with Pentens T-308. Prepare and measure the
appropriate amount of Pentens T-308.
- Dosage rate: Pentens T-308 - 0.8% by weight of cementitious content.
- Ensure works of stage 5 completed with uniform level and duly verified.
- Proceed to concreting.
METHOD STATEMENT
Prepare Pentens T-308, Pour mixture into the Concreting For water retaining structure
measure and mix with drum of the ready-mix i.e. swimming pool and
water. truck. water tank.
5. Ponding Test -
6. Concrete Topping/Screeding -
The works for each of the above stages are clarified in the following pages.
5. Work Methodology
- Check for defects on RC slab i.e. cracks, oil patches, foreign materials, cracks etc and inform Main
Contractor on rectification required.
METHOD STATEMENT
- Apply Pentens T-805 non-shrink grout to holes and hollow surfaces to achieve uniform level of RC
substrate.
- Apply Pentens T-805 angle fillet at 45 degrees (25mm x 25mm) consistently throughout perimeter of
work area
- Ensure area is dust free and thoroughly cleaned to receive primer material as per manufacturer’s
instructions.
- Treatment to all down pipe, floor traps must be coated with two layers of Pentens T-100 at least
50mm deep and shall extend 50mm up all horizontal or vertical faces.
- Ensure work area applied with waterproofing membrane (stage 3) is fully cured and application
verified/approved.
- Carry out ponding test to work area (minimum ponding of 48-72hrs).
- Proceed with next stage if ponding test approved.
- Note: repeat Stage 3 should ponding test fail.
- Ensure works of stage 5 completed with uniform level and duly verified.
- Remove temporary kickers (where applicable; area required will be applied with additional
waterproofing membrane for ease of overlapping at joints)
- Screed to achieve a fall consistent with architectural design fall and finished.
METHOD STATEMENT
Photo of Application (Pentens T-100):
Surface Preparation Angle Fillet Apply Pentens T-007 as Open the cover of Pentens
primer T-100 and stir thoroughly.
Treatment to outlet Apply three layers of Pentens Completion of Pentens T-100 Finished
T-100 onto construction
surface by using brush, roller
or spray method.
Details Drawing:
METHOD STATEMENT