Sie sind auf Seite 1von 61

APPROVED BUDGET FOR THE CONTRACT

Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Bustamante, Brgy. Tagbakin, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 180 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 900.00 sq.m. P 28,900.00 15.00 10.00 25.00 P 7,225.00 P 1,445.00 P 8,670.00 P 37,570.00 P 41.74
200 Aggregate SubBase Course 180.00 cu.m. P 113,700.00 15.00 10.00 25.00 P 28,425.00 P 5,685.00 P 34,110.00 P 147,810.00 P 821.17
201 Aggregate Base Course 59.00 cu.m. P 59,900.00 15.00 10.00 25.00 P 14,975.00 P 2,995.00 P 17,970.00 P 77,870.00 P 1,319.83
311 Portland Cement Concrete Pavement 720.00 sq.m. P 546,404.00 15.00 10.00 25.00 P 136,601.00 P 27,320.20 P 163,921.20 P 710,325.20 P 986.56
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 17,618.58 15.00 10.00 25.00 P 4,404.65 P 880.93 P 5,285.57 P 22,904.15 P 15,269.44

TOTAL P 999,930.85

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT

D.O. No. ____, Series of 2016


Concreting of Local Access Road
Sitio Alabastro, Brgy. Ayusan II, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 475.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 29.97
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.25 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,108.89
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 499,989.54

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Gitna , Brgy. Paiisa, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 475.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 29.97
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.25 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,108.89
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 499,989.54

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Hilirang Buli, Brgy. Lagalag, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 475.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 29.97
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.25 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,108.89
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.80 P 708.42 P 4,251.22 P 18,418.84 P 12,279.23

TOTAL P 499,989.54

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

APPROVED BUDGET FOR THE CONTRACT


Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Hilirang Buli, Brgy. Lagalag, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 140 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 700.00 sq.m. P 21,900.00 15.00 10.00 25.00 P 5,475.00 P 1,095.00 P 6,570.00 P 28,470.00 P 40.67
200 Aggregate SubBase Course 140.00 cu.m. P 87,450.00 15.00 10.00 25.00 P 21,862.50 P 4,372.50 P 26,235.00 P 113,685.00 P 812.04
201 Aggregate Base Course 46.00 cu.m. P 48,400.00 15.00 10.00 25.00 P 12,100.00 P 2,420.00 P 14,520.00 P 62,920.00 P 1,367.83
311 Portland Cement Concrete Pavement 560.00 sq.m. P 414,254.00 15.00 10.00 25.00 P 103,563.50 P 20,712.70 P 124,276.20 P 538,530.20 P 961.66
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 17,618.58 15.00 10.00 25.00 P 4,404.65 P 880.93 P 5,285.57 P 22,904.15 P 15,269.44

TOTAL P 769,960.85
PREPARED/SUBMITTED BY: APPROVED:

ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA


Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Sub-Province, Brgy. Talisay, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 475.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 29.97
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.25 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,108.89
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.09 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 499,989.54

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Panghulan 2, Brgy. Bula, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 475.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 29.97
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.25 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,108.89
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 499,989.54

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

APPROVED BUDGET FOR THE CONTRACT


Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Panghulan I, Brgy. Bula, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 135 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 675.00 sq.m. P 21,900.00 15.00 10.00 25.00 P 5,475.00 P 1,095.00 P 6,570.00 P 28,470.00 P 42.18
200 Aggregate SubBase Course 135.00 cu.m. P 85,450.00 15.00 10.00 25.00 P 21,362.50 P 4,272.50 P 25,635.00 P 111,085.00 P 822.85
201 Aggregate Base Course 44.00 cu.m. P 48,400.00 15.00 10.00 25.00 P 12,100.00 P 2,420.00 P 14,520.00 P 62,920.00 P 1,430.00
311 Portland Cement Concrete Pavement 540.00 sq.m. P 395,092.00 15.00 10.00 25.00 P 98,773.00 P 19,754.60 P 118,527.60 P 513,619.60 P 951.15
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 17,618.58 15.00 10.00 25.00 P 4,404.65 P 880.93 P 5,285.58 P 22,904.16 P 15,269.44

TOTAL P 742,450.26
PREPARED/SUBMITTED BY: APPROVED:

ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA


Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Road Sanitary Landfill, Brgy. San Agustin, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 160 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 800.00 sq.m. P 21,900.00 15.00 10.00 25.00 P 5,475.00 P 1,095.00 P 6,570.00 P 28,470.00 P 35.59
200 Aggregate SubBase Course 160.00 cu.m. P 97,100.00 15.00 10.00 25.00 P 24,275.00 P 4,855.00 P 29,130.00 P 126,230.00 P 788.94
201 Aggregate Base Course 52.00 cu.m. P 48,900.00 15.00 10.00 25.00 P 12,225.00 P 2,445.00 P 14,670.00 P 63,570.00 P 1,222.50
311 Portland Cement Concrete Pavement 640.00 sq.m. P 484,894.00 15.00 10.00 25.00 P 121,223.50 P 24,244.70 P 145,468.20 P 630,362.20 P 984.94
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 17,618.58 15.00 10.00 25.00 P 4,404.65 P 880.93 P 5,285.57 P 22,904.15 P 15,269.44

TOTAL P 874,987.85

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Taal, Brgy. San Pedro, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 475.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 29.97
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.25 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,108.89
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 499,989.54

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

APPROVED BUDGET FOR THE CONTRACT


Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Brgy. Ayusan I San Pedro, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 125 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 625.00 sq.m. P 18,400.00 15.00 10.00 25.00 P 4,600.00 P 920.00 P 5,520.00 P 23,920.00 P 38.27
200 Aggregate SubBase Course 125.00 cu.m. P 76,750.00 15.00 10.00 25.00 P 19,187.50 P 3,837.50 P 23,025.00 P 99,775.00 P 798.20
201 Aggregate Base Course 41.00 cu.m. P 38,650.00 15.00 10.00 25.00 P 9,662.50 P 1,932.50 P 11,595.00 P 50,245.00 P 1,225.49
311 Portland Cement Concrete Pavement 500.00 sq.m. P 374,709.00 15.00 10.00 25.00 P 93,677.25 P 18,735.45 P 112,412.70 P 487,121.70 P 974.24
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 17,618.58 15.00 10.00 25.00 P 4,404.65 P 880.93 P 5,285.57 P 22,904.15 P 15,269.44

TOTAL P 687,417.35
PREPARED/SUBMITTED BY: APPROVED:

ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA


Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Kanluran, Brgy. San Francisco, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 475.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 29.97
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.25 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,108.89
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 499,989.54

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Labak, Brgy. Aquino, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 475.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 29.97
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.25 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,108.89
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 499,989.54

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Marasigan, Brgy. San Isidro, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 100 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 500.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 37.57
200 Aggregate SubBase Course 100.00 cu.m. P 61,650.00 15.00 10.00 25.00 P 15,412.50 P 3,082.50 P 18,495.00 P 80,145.00 P 801.45
201 Aggregate Base Course 32.50 cu.m. P 33,900.00 15.00 10.00 25.00 P 8,475.00 P 1,695.00 P 10,170.00 P 44,070.00 P 1,356.00
311 Portland Cement Concrete Pavement 400.00 sq.m. P 296,162.00 15.00 10.00 25.00 P 74,040.50 P 14,808.10 P 88,848.60 P 385,010.60 P 962.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 549,880.94

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Tabura, Brgy. Del Rosario, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 100 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 500.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 37.57
200 Aggregate SubBase Course 100.00 cu.m. P 61,650.00 15.00 10.00 25.00 P 15,412.50 P 3,082.50 P 18,495.00 P 80,145.00 P 801.45
201 Aggregate Base Course 33.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 8,475.00 P 1,695.00 P 10,170.00 P 44,070.00 P 1,356.00
311 Portland Cement Concrete Pavement 400.00 sq.m. P 296,162.00 15.00 10.00 25.00 P 74,040.50 P 14,808.10 P 88,848.60 P 385,010.60 P 962.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 549,880.94

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

APPROVED BUDGET FOR THE CONTRACT


Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Tabura, Brgy. Del Rosario, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 450.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 31.63
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.00 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,118.45
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.09 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 499,989.54
PREPARED/SUBMITTED BY: APPROVED:

ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA


Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sulukan, Brgy. Anastacia, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 100 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 500.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 37.57
200 Aggregate SubBase Course 100.00 cu.m. P 61,650.00 15.00 10.00 25.00 P 15,412.50 P 3,082.50 P 18,495.00 P 80,145.00 P 801.45
201 Aggregate Base Course 33.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 8,475.00 P 1,695.00 P 10,170.00 P 44,070.00 P 1,356.00
311 Portland Cement Concrete Pavement 400.00 sq.m. P 296,162.00 15.00 10.00 25.00 P 74,040.50 P 14,808.10 P 88,848.60 P 385,010.60 P 962.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 549,880.94

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

APPROVED BUDGET FOR THE CONTRACT


Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sulukan, Brgy. Anastacia, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 90 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 450.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 31.63
200 Aggregate SubBase Course 90.00 cu.m. P 56,850.00 15.00 10.00 25.00 P 14,212.50 P 2,842.50 P 17,055.00 P 73,905.00 P 821.17
201 Aggregate Base Course 29.00 cu.m. P 24,950.00 15.00 10.00 25.00 P 6,237.50 P 1,247.50 P 7,485.00 P 32,435.00 P 1,118.45
311 Portland Cement Concrete Pavement 360.00 sq.m. P 275,034.00 15.00 10.00 25.00 P 68,758.50 P 13,751.70 P 82,510.20 P 357,544.20 P 993.18
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.09 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 499,989.54
PREPARED/SUBMITTED BY: APPROVED:

ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA


Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
School Road , Brgy. Tamisian, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 100 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 500.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 37.57
200 Aggregate SubBase Course 100.00 cu.m. P 61,650.00 15.00 10.00 25.00 P 15,412.50 P 3,082.50 P 18,495.00 P 80,145.00 P 801.45
201 Aggregate Base Course 33.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 8,475.00 P 1,695.00 P 10,170.00 P 44,070.00 P 1,335.45
311 Portland Cement Concrete Pavement 400.00 sq.m. P 296,162.00 15.00 10.00 25.00 P 74,040.50 P 14,808.10 P 88,848.60 P 385,010.60 P 962.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.09 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 549,880.94

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

APPROVED BUDGET FOR THE CONTRACT


Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Tamisian Elem. School, Brgy. Tamisian, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 115 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 575.00 sq.m. P 18,400.00 15.00 10.00 25.00 P 4,600.00 P 920.00 P 5,520.00 P 23,920.00 P 41.60
200 Aggregate SubBase Course 115.00 cu.m. P 71,950.00 15.00 10.00 25.00 P 17,987.50 P 3,597.50 P 21,585.00 P 93,535.00 P 813.35
201 Aggregate Base Course 37.00 cu.m. P 36,650.00 15.00 10.00 25.00 P 9,162.50 P 1,832.50 P 10,995.00 P 47,645.00 P 1,287.70
311 Portland Cement Concrete Pavement 460.00 sq.m. P 339,232.00 15.00 10.00 25.00 P 84,808.00 P 16,961.60 P 101,769.60 P 441,001.60 P 958.70
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 17,618.58 15.00 10.00 25.00 P 4,404.65 P 880.93 P 5,285.57 P 22,904.15 P 15,269.44

TOTAL P 632,457.25
PREPARED/SUBMITTED BY: APPROVED:

ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA


Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Cemetery Road , Brgy. Quipot, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 100 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 500.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 37.57
200 Aggregate SubBase Course 100.00 cu.m. P 61,650.00 15.00 10.00 25.00 P 15,412.50 P 3,082.50 P 18,495.00 P 80,145.00 P 801.45
201 Aggregate Base Course 33.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 8,475.00 P 1,695.00 P 10,170.00 P 44,070.00 P 1,356.00
311 Portland Cement Concrete Pavement 400.00 sq.m. P 296,162.00 15.00 10.00 25.00 P 74,040.50 P 14,808.10 P 88,848.60 P 385,010.60 P 962.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 549,880.94

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Carnation St. ,Brgy. Quipot, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 100 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 500.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 37.57
200 Aggregate SubBase Course 100.00 cu.m. P 61,650.00 15.00 10.00 25.00 P 15,412.50 P 3,082.50 P 18,495.00 P 80,145.00 P 801.45
201 Aggregate Base Course 33.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 8,475.00 P 1,695.00 P 10,170.00 P 44,070.00 P 1,356.00
311 Portland Cement Concrete Pavement 400.00 sq.m. P 296,162.00 15.00 10.00 25.00 P 74,040.50 P 14,808.10 P 88,848.60 P 385,010.60 P 962.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 549,880.94

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
St. Gerald St. ,Brgy. Quipot, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 100 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 500.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 37.57
200 Aggregate SubBase Course 100.00 cu.m. P 61,650.00 15.00 10.00 25.00 P 15,412.50 P 3,082.50 P 18,495.00 P 80,145.00 P 801.45
201 Aggregate Base Course 33.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 8,475.00 P 1,695.00 P 10,170.00 P 44,070.00 P 1,356.00
311 Portland Cement Concrete Pavement 400.00 sq.m. P 296,162.00 15.00 10.00 25.00 P 74,040.50 P 14,808.10 P 88,848.60 P 385,010.60 P 962.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 549,880.94

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

APPROVED BUDGET FOR THE CONTRACT


Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
St. Gerald St. ,Brgy. Quipot, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 60 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 475.00 sq.m. P 5,700.00 15.00 10.00 25.00 P 1,425.00 P 285.00 P 1,710.00 P 7,410.00 P 15.60
200 Aggregate SubBase Course 60.00 cu.m. P 32,350.00 15.00 10.00 25.00 P 8,087.50 P 1,617.50 P 9,705.00 P 42,055.00 P 700.92
201 Aggregate Base Course 20.00 cu.m. P 17,200.00 15.00 10.00 25.00 P 4,300.00 P 860.00 P 5,160.00 P 22,360.00 P 1,118.00
311 Portland Cement Concrete Pavement 240.00 sq.m. P 181,742.00 15.00 10.00 25.00 P 45,435.50 P 9,087.10 P 54,522.60 P 236,264.60 P 984.44
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.09 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 329,959.94
PREPARED/SUBMITTED BY: APPROVED:

ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA


Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Villa Juanita, Brgy. Palagaran, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 120 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 600.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 31.31
200 Aggregate SubBase Course 120.00 cu.m. P 70,850.00 15.00 10.00 25.00 P 17,712.50 P 3,542.50 P 21,255.00 P 92,105.00 P 767.54
201 Aggregate Base Course 39.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 9,362.50 P 1,872.50 P 11,235.00 P 48,685.00 P 1,248.33
311 Portland Cement Concrete Pavement 480.00 sq.m. P 368,097.00 15.00 10.00 25.00 P 92,024.25 P 18,404.85 P 110,429.10 P 478,526.10 P 996.93
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 659,971.44

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Brgy. Lusacan, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 100 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 500.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 37.57
200 Aggregate SubBase Course 100.00 cu.m. P 61,650.00 15.00 10.00 25.00 P 15,412.50 P 3,082.50 P 18,495.00 P 80,145.00 P 801.45
201 Aggregate Base Course 33.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 8,475.00 P 1,695.00 P 10,170.00 P 44,070.00 P 1,335.45
311 Portland Cement Concrete Pavement 400.00 sq.m. P 296,162.00 15.00 10.00 25.00 P 74,040.50 P 14,808.10 P 88,848.60 P 385,010.60 P 962.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.09 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 549,880.94

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Mayo & Liwayway St., Brgy. Lalig, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 120 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 600.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 31.31
200 Aggregate SubBase Course 120.00 cu.m. P 70,850.00 15.00 10.00 25.00 P 17,712.50 P 3,542.50 P 21,255.00 P 92,105.00 P 767.54
201 Aggregate Base Course 39.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 9,362.50 P 1,872.50 P 11,235.00 P 48,685.00 P 1,248.33
311 Portland Cement Concrete Pavement 480.00 sq.m. P 368,097.00 15.00 10.00 25.00 P 92,024.25 P 18,404.85 P 110,429.10 P 478,526.10 P 996.93
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 659,971.44

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
SLSU Road, Brgy. Talisay, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 145 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 60 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 725.00 sq.m. P 18,400.00 15.00 10.00 25.00 P 4,600.00 P 920.00 P 5,520.00 P 23,920.00 P 32.99
200 Aggregate SubBase Course 145.00 cu.m. P 82,900.00 15.00 10.00 25.00 P 20,725.00 P 4,145.00 P 24,870.00 P 107,770.00 P 743.24
201 Aggregate Base Course 47.12 cu.m. P 42,400.00 15.00 10.00 25.00 P 10,600.00 P 2,120.00 P 12,720.00 P 55,120.00 P 1,169.78
311 Portland Cement Concrete Pavement 580.00 sq.m. P 451,394.00 15.00 10.00 25.00 P 112,848.50 P 22,569.70 P 135,418.20 P 586,812.20 P 1,011.75
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 17,618.58 15.00 10.00 25.00 P 4,404.64 P 880.93 P 5,285.57 P 22,904.15 P 15,269.44

TOTAL P 799,977.85

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

APPROVED BUDGET FOR THE CONTRACT


Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
SLSU Road, Brgy. Talisay, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 232 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 1160.00 sq.m. P 36,350.00 15.00 10.00 25.00 P 9,087.50 P 1,817.50 P 10,905.00 P 47,255.00 P 40.74
200 Aggregate SubBase Course 232.00 cu.m. P 145,550.00 15.00 10.00 25.00 P 36,387.50 P 7,277.50 P 43,665.00 P 189,215.00 P 815.58
201 Aggregate Base Course 75.00 cu.m. P 80,850.00 15.00 10.00 25.00 P 20,212.50 P 4,042.50 P 24,255.00 P 105,105.00 P 1,401.40
311 Portland Cement Concrete Pavement 928.00 sq.m. P 692,334.00 15.00 10.00 25.00 P 173,083.50 P 34,616.70 P 207,700.20 P 900,034.20 P 969.86
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 21,068.82 15.00 10.00 25.00 P 5,267.21 P 1,053.44 P 6,320.65 P 27,389.47 P 18,259.64

TOTAL P 1,272,450.17
PREPARED/SUBMITTED BY: APPROVED:

ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA


Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Delfin Ave. , Brgy. Lumingon, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 105 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 525.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 35.78
200 Aggregate SubBase Course 105.00 cu.m. P 64,050.00 15.00 10.00 25.00 P 16,012.50 P 3,202.50 P 19,215.00 P 83,265.00 P 793.00
201 Aggregate Base Course 34.13 cu.m. P 34,450.00 15.00 10.00 25.00 P 8,612.50 P 1,722.50 P 10,335.00 P 44,785.00 P 1,312.38
311 Portland Cement Concrete Pavement 420.00 sq.m. P 314,449.00 15.00 10.00 25.00 P 78,612.25 P 15,722.45 P 94,334.70 P 408,783.70 P 973.29
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 577,489.04

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

APPROVED BUDGET FOR THE CONTRACT


Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Delfin St. , Brgy. Lumingon, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 88 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 440.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 32.35
200 Aggregate SubBase Course 88.00 cu.m. P 52,350.00 15.00 10.00 25.00 P 13,087.50 P 2,617.50 P 15,705.00 P 68,055.00 P 773.35
201 Aggregate Base Course 29.00 cu.m. P 24,200.00 15.00 10.00 25.00 P 6,050.00 P 1,210.00 P 7,260.00 P 31,460.00 P 1,084.83
311 Portland Cement Concrete Pavement 352.00 sq.m. P 270,636.00 15.00 10.00 25.00 P 67,659.00 P 13,531.80 P 81,190.80 P 351,826.80 P 999.51
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.09 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 487,447.14
PREPARED/SUBMITTED BY: APPROVED:

ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA


Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Sitio Pakilan, Brgy. Behia, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 98 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 490.00 sq.m. P 10,950.00 15.00 10.00 25.00 P 2,737.50 P 547.50 P 3,285.00 P 14,235.00 P 29.05
200 Aggregate SubBase Course 98.00 cu.m. P 60,450.00 15.00 10.00 25.00 P 15,112.50 P 3,022.50 P 18,135.00 P 78,585.00 P 801.89
201 Aggregate Base Course 31.85 cu.m. P 29,950.00 15.00 10.00 25.00 P 7,487.50 P 1,497.50 P 8,985.00 P 38,935.00 P 1,222.45
311 Portland Cement Concrete Pavement 392.00 sq.m. P 297,174.00 15.00 10.00 25.00 P 74,293.50 P 14,858.70 P 89,152.20 P 386,326.20 P 985.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 539,951.54

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Centro & School Road, Brgy. Tamisian, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 164 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 820.00 sq.m. P 25,400.00 15.00 10.00 25.00 P 6,350.00 P 1,270.00 P 7,620.00 P 33,020.00 P 40.27
200 Aggregate SubBase Course 164.00 cu.m. P 102,600.00 15.00 10.00 25.00 P 25,650.00 P 5,130.00 P 30,780.00 P 133,380.00 P 813.29
201 Aggregate Base Course 53.00 cu.m. P 55,900.00 15.00 10.00 25.00 P 13,975.00 P 2,795.00 P 16,770.00 P 72,670.00 P 1,371.13
311 Portland Cement Concrete 656.00 sq.m. P 488,094.00 15.00 10.00 25.00 P 122,023.50 P 24,404.70 P 146,428.20 P 634,522.20 P 967.26
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and He 1.50 mo. P 17,618.58 15.00 10.00 25.00 P 4,404.65 P 880.93 P 5,285.57 P 22,904.15 P 15,269.44
- -

TOTAL P 899,947.85

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Centro, Brgy. Bukal, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 100 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 500.00 sq.m. P 14,450.00 15.00 10.00 25.00 P 3,612.50 P 722.50 P 4,335.00 P 18,785.00 P 37.57
200 Aggregate SubBase Course 100.00 cu.m. P 61,650.00 15.00 10.00 25.00 P 15,412.50 P 3,082.50 P 18,495.00 P 80,145.00 P 801.45
201 Aggregate Base Course 33.00 cu.m. P 33,900.00 15.00 10.00 25.00 P 8,475.00 P 1,695.00 P 10,170.00 P 44,070.00 P 1,335.45
311 Portland Cement Concrete Pavement 400.00 sq.m. P 296,162.00 15.00 10.00 25.00 P 74,040.50 P 14,808.10 P 88,848.60 P 385,010.60 P 962.53
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.09 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23
- -

TOTAL P 549,880.94

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor
APPROVED BUDGET FOR THE CONTRACT
Attachment "A"
D.O. No. ____, Series of 2016
Concreting of Local Access Road
Centro, Brgy. Tamisian, Tiaong, Quezon

Project Name and Location

Station :
Length : L = 75 l.m. w = 4.0 m. t = 0.15 m. Contract Duration 45 CD
MARK-UPS TOTAL
ITEM DESCRIPTION QTY UNIT ESTIMATED IN PERCENT MARK-UP TOTAL INDIRECT TOTAL UNIT
VAT
NO. DIRECT COST OCM PROFIT % VALUE COST COST COST
12%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
(5) X (8) 5% (5+9) (9) + (10) (5) + (11) (12) / (3)

105 Subgrade Preparation 375.00 sq.m. P 7,450.00 15.00 10.00 25.00 P 2,607.50 P 372.50 P 2,235.00 P 9,685.00 P 25.83
200 Aggregate SubBase Course 75.00 cu.m. P 42,650.00 15.00 10.00 25.00 P 10,662.50 P 2,132.50 P 12,795.00 P 55,445.00 P 739.27
201 Aggregate Base Course 23.43 cu.m. P 21,450.00 15.00 10.00 25.00 P 5,362.50 P 1,072.50 P 6,435.00 P 27,885.00 P 1,190.14
311 Portland Cement Concrete Pavement 300.00 sq.m. P 228,898.00 15.00 10.00 25.00 P 57,224.50 P 11,444.90 P 68,669.40 P 297,567.40 P 991.89
605 Project Signboard 2.88 sq.m. P 2,655.00 15.00 10.00 25.00 P 663.75 P 132.75 P 796.50 P 3,451.50 P 1,198.44
SPL Construction Safety and Health 1.50 mo. P 14,168.34 15.00 10.00 25.00 P 3,542.08 P 708.42 P 4,250.50 P 18,418.84 P 12,279.23

TOTAL P 412,452.74

PREPARED/SUBMITTED BY: APPROVED:


ELENITA LALUCES-MARQUEZ RAMON ABAD PREZA
Municipal Engineer Municipal Mayor

Das könnte Ihnen auch gefallen