Sie sind auf Seite 1von 10

Technical Note No 93

Building Information Modelling –


Principles for Building envelopes
Building Information Modelling (BIM) is being adopted by the construction industry led in part by some
Main Contractors and driven by Government declarations on public procurement policy. 3-D
modelling has been taken up by architects and engineers for visualisation of space planning and
coordination of elements. BIM is a wide ranging concept that may be operated at many different
levels of complexity and functionality. This paper aims to explain the principles of BIM and set
benchmarks for the use of BIM when designing, constructing and operating building envelopes.

This Technical Note does not consider the merits, advantages or disadvantages of using any
particular software packages. Rather it considers the strategies that should be adopted when
implementing BIM on a project.

Introduction reflect their roles as stakeholders. In reality


even simpler forms of BIM can deliver benefits
BIM is not a new concept; it is an extension of a of economy and efficiency in the design,
very old principle of collaboration between the construction and management of buildings.
various designers and constructors on a
project. This has been embodied in BS 1192: However, it must be remembered that the use
‘Collaborative production of architectural, of BIM has a cost of preparing and sharing
engineering and construction information – data. The costs of implementing BIM on a
Code of practice’, 2007. BS 1192 has evolved project will depend on the additional information
over several decades from a time when all required over and above that normally provided
drawings were prepared using pen and ink. to architects, engineers and contractors. The
BIM places a greater emphasis on the question is often not what it costs but who
information that is captured and shared over pays.
and above the information contained in
conventional drawings. BIM extends the basic The greatest benefits are achieved by:
concept of collaboration to include the building
owners and maintainers who will use the • Investing appropriate effort in developing a
design information throughout the life of the BIM model of appropriate complexity and
building; a later day version of ‘as constructed detail that it delivers the benefits required,
drawings’ and ‘Operation and maintenance in the same way that a drawing should
manuals’. Using BIM; operations and have contained only the necessary detail
management information can be presented in a and information.
much more accessible and interactive format. • Not regarding BIM as an end in itself; BIM
A key part of the BIM lifecycle is that it also should be regarded as a tool in the same
allows information to be gathered post- way that a traditional drawing on paper was
completion to be fed back into the design not a product in itself but was an efficient
process for future projects. method of communication.
• Making clear to all contributors, at the
A Building Information Model is a digital outset, what they are required to do and
representation of the geometrical and functional when.
characteristics of a building. A BIM is a shared
knowledge resource for information about a In the days of paper drawings estimators
building forming a reliable basis for decisions allowed for the cost of design by predicting the
during its life-cycle from earliest conception to number and complexity of drawings required.
demolition This process is more difficult when using CAD
and yet more so when using BIM but the same
As an aspiration it is a basic premise of BIM premise holds true. However, with drawings
that it enables collaboration by different the cost of drawing largely facilitated
stakeholders at different phases of the life cycle manufacture and construction and mainly
of a building. In its more developed forms BIM benefited the contractor who bore the costs,
allows stakeholders to insert, extract, update or with BIM the costs accrued by the contractor
modify information in the BIM to support and may yield benefits to the Client throughout the

1/10
© CWCT 2012
Building information modelling – principles for building envelopes TN 93

life of the building but may not benefit the Richards scale of BIM maturity to define four
contractor through greater efficiency. With BIM levels of BIM as shown in Figure 1.
it is necessary to ascertain the Client
requirements for information on a particular To put the development of BIM into context the
project so that identification, separation and UK Government has announced that all
preparation of that information can be included centrally procured construction projects will be
in tender prices. The specialist contractors delivered using level 2 BIM by 2016. Between
models will contain far too much detail and now and then various Government departments
simplified 3-D models may have to be produced will be ‘switched on’ to BIM use, and in 2012
loaded with inherent data values such as the Ministry of Justice tendered for the first
thermal properties, unit cost, predicted life exemplar schemes to require BIM use and
span, programme information etc. that may be other departments are currently preparing their
requested by consultants, client or principal ‘roadmaps’ to the implementation of BIM
contractor. requirements.

Nearly all building projects that include


Scope of BIM systemised building envelopes are currently
delivered using 2-D CAD, and sometimes 3D-
BIM covers the whole range and complexity of CAD, so what does it take to progress to Level
information from simple drawings to fully 2 BIM? And is it necessary to use 3D-CAD?
interoperable data sets. This range of
possibilities has been formalised as the Bew-

Figure 1 Bew-Richards scale of BIM maturity

These separate BIM models with separate


owners require a means to exchange data
Level 2 BIM requires Building Information between them for purposes of integrating
Models (BIMs) for each construction design and clash detection. Although
package of the building. The BIMs each has a separate owner creating them,
commonly shown on slides at they may be accessible by many parties
presentations are; involved in a project.

• Architecture (AIM) The standard form of delivery of


• Structure (SIM) information to the end user in the case of
• Façilities (FIM) public projects is (at 2012) proposed to be
• Building services (BSIM) the COBie format – a database of all
information contained within the BIM data

2/10
Building information modelling – principles for building envelopes TN 93

developed for a project. COBie data is Level and grade of detail in CAD
most commonly issued as a spreadsheet
as opposed to (or in some cases Traditional drawings of building envelopes
alongside) the original 3-D or 2-D building were classified as;
models produced by the various
stakeholders involved in the design and • General arrangement drawings
construction process. COBie is described • Detail drawings
in more detail later. • Workshop/component drawings
• Construction drawings
The existence of separate BIMs with
separate owners raises the question Whereas these used to be separate
whether the building envelope should be drawings it is possible using CAD to
modelled as part of the AIM or whether combine the general and detailed
there should be an Envelope Information information in a single drawing by layering
Model (EIM). This will depend on the form and the ability to expand or shrink
of construction and the degree of drawings on screen. Whilst all of this
complexity of the façade but in many information is required by the building
cases a separate EIM will be appropriate envelope contractor much of it is of little or
for systemised building envelopes. no value to the Main Contractor, Architect,
Structural Engineer or Client. It is also the
A BIM comprises file based drawings and case that Specialist Contractors will rightly
a supporting library of information. BIMs be reluctant to release detailed drawings
at Level 2 are written by a single owner that allow another contractor to benefit
(although they may be read by others), it is from their design experience and possibly
only at Level 3 that the information is replace them as specialist contractor on
required to be part of a single fully the project.
interoperable Building Information Model
(iBIM). In an iBIM all information is In a BIM environment there is a level of
resident on a common hub using a detail that increases as the project
common data format and library. progresses. Level of Detail (LOD) is
defined on a scale from LOD100 –
conceptual design up to LOD500 – as-built
Drawings comprise lines (and arcs) that information suitable for facilities
are objects with properties of position, management purposes. When providing
length, (radius), thickness, style, and information for use in a BIM it is important
colour. These may be combined to create to know the level of detail of the model.
objects such as rectangles, windows,
doors and so forth. 3-D software However, there will also be a requirement
packages comprise simple volumetric to provide elements drawn to a certain
elements that may be combined to create grade of detail.
objects such as windows or doors.
Additional (non-graphical) information may Including too much information in drawings
be added to an object to create an passed to other parties may make it
enhanced object. Such information may difficult for them to filter and understand
include product information, performance the relevant information and may overload
parameters, supplier details and so on. storage and software capabilities. This is
This information is typically viewed by particularly the case with three
clicking on the object as it appears dimensional models; a simple outline
graphically on screen to reveal a drawing can be handled much faster than
properties dialogue box. The information a complex model when the image is
may be stored within the BIM and/or be required to rotate on the screen. Consider
accessible through an external link. the chair shown in Figure 2.

3/10
Building information modelling – principles for building envelopes TN 93

Figure 2 Appropriate grades of detail

Figure 3 Grade of detail for a tilt-turn window

All three grades of detail are valid models data analysis (particularly for ‘walk
of the chair. Grade 1 will act as a place through’ and ‘spin round’ viewing).
holder and enable fit and clash detection;
it may also be an object with extensive Cross sections through a tilt-turn window
information about the product. Gradel 2 drawn at different levels of resolution are
and Grade 3 levels have enhanced shown in Figure 3. The low resolution
appearance and reality but at a greater drawing is a very rudimentary drawing that
cost of model creation, data storage and provides Grade 1 detail and acts as a
place keeper in a general architectural

4/10
Building information modelling – principles for building envelopes TN 93

model. The medium resolution drawing comprise the majority of building


contains more detail than is normally envelopes.
required for a Grade 3 model and the large
amount of data associated with this To use three dimensional CAD for simpler
drawing will be burdensome when it is constructions is an unnecessary expense
integrated into the whole building model. for the contractor (who will pass it on to
The high resolution drawing contains more the Client), and for reasons of technical
information than is of use to either the capability will limit the number of potential
building design team or the building building envelope contractors when
manager and the associated data will be tendering. Many smaller specialist
unacceptably large to the manager of the contractors do not have the necessary
BIM. software; more importantly there is a
shortage of skilled 3-D CAD operators and
Note that it is important to understand difficulty in up-skilling older more
what to include and what not to include in experienced staff.
a model. In the example given in Figure 3:
In the context of gaining savings and
• It might have been more useful to efficiencies from BIM it will often be better
include the operating handle in the to use 2D-CAD and concentrate on
medium resolution drawing (and even improvements to the supporting library of
in the low resolution version). information rather than to insist on the use
• The internal gaskets and seals could of 3-D CAD.
have been omitted from the medium
resolution drawing. Figure 4 shows a screen shot from typical
• A low resolution drawing showing at design and estimating software used by
least the fixed and opening frames many specialist contractors to design
might have been more useful. simple plane walls. Cross-sections are not
• Where greater detail is required to required as the framing profiles are
inform the site assembly process, and proprietary products of known cross-
that information repeats for every section and properties. In this case the
window, it is more useful and efficient production of a BIM model is a separate
to have a single assembly drawing. exercise and a simple 2-D model at Grade
1 or possibly Grade 2 level of detail is all
that should be expected.
3-D CAD
However, although 3-D CAD may not be
Three dimensional drawing is essential for necessary for the design, manufacture and
building envelopes with very complex construction of a building envelope the
freeform geometry. It is necessary for Main Contractor may wish to include the
designing, manufacturing and setting out building envelope in a 3-D model for clash
these forms of building envelope. detection or to check the interface
However, it is not necessary to use three between the building envelope and the
dimensional drawing for simpler structure. This may be achieved by
envelopes, particularly those comprising generating a very simple 3-D model of the
rectilinear grillages, glazing and infill envelope representing only the inner and
panels forming plane walls or roofs.
These simple forms of construction

5/10
Building information modelling – principles for building envelopes TN 93

Figure 4 Typical design and estimating software

outer surfaces and possibly the brackets envelope may only need to be modelled
supporting the building envelope. This as plane (or curved) surfaces and solid
may be prepared by the Main Contractor elements. It is more important that these
from raw information provided by the are accurately coloured and textured than
Specialist contractor. that they are precisely dimensioned.

Higher order BIM Suppliers and contractors may assist


architects by providing 3-D drawing
4-D BIM introduces time as the fourth objects that can be imported into the AIM.
dimension. This may be used by Main It should be understood that these need to
Contractors to show the construction be different from the modelling packages
sequence. It may be used to model they use for engineering purposes. Many
clashes with cranes and temporary works. drawing packages now allow export in IFC
It is unlikely that the Building envelope format, a generic format accepted in all
contractor will build a 4-D model, rather it BIM software. Many pieces of BIM
will be developed by the main Contractor software also allow the import of various
from information provided by the specialist formats that can be exported from a large
contractor. The geometrical detail in such number of engineering and manufacturing
models may be at a very low grade design packages. In some cases there
sufficient only to act as a place holder. are additional benefits to producing
proprietary models in specific modelling
5-D BIM includes the cost information for formats such as Autodesk Revit or
the different elements while 6-D BIM Graphisoft’s ArchiCAD as this allows
includes the life cycle analysis of the greater use and interoperability but as
different elements. Currently these are not mentioned earlier, any additional benefits
commonly encountered on projects. should be weighed up against cost and
stated requirements.

Early design stage models Manufacturers can produce generic BIM


elements, or families of elements, to be
down loaded and incorporated in project
Architectural design always starts before a
BIM. These may be made available on
specialist contractor is appointed and
their own websites or hosted on sites such
models required at this stage have to be
as NBS BIM Library or BIMStore. These
developed by the architect. These models
generic BIM elements would be expected
require only sufficient detail to provide a
to offer generic performance information
good visual interpretation of the finished
such as U-values, acoustic performance,
building. In this context the building

6/10
Building information modelling – principles for building envelopes TN 93

load/span data and links to literature and containing information to facilitate the
third-party certification. maintenance, repair and upgrading of the
building.
The early design stage model may be
taken forward and developed into the Main The standard format required is the
Contractor’s BIM but it is often more Construction Operations Building
efficient to carry through the bare x, y, z Information Exchange (COBie) template.
coordinates of critical dimensions and form Further information and example
a new BIM that meets the need of spreadsheets are available through the
manufacturing and construction and BIM Task Group.
continues through the service life of the
building. The information required is at an element
or component level and comprises:
Supporting information
• Component description
Supporting information has always been • Location
provided by Specialist contractors for use • Supplier
by Main contractors, Architects and Clients • Performance characteristic
and over recent years this has become • Maintenance requirements
more extensive and detailed. It will
include: COBie templates have been developed
around the needs of building services and
• Component information other high maintenance elements of the
• Performance characteristics building which are easily located by floor,
• Test certificates room and so on. When developing a
• Method statements COBie document for a curtain wall it will
• Installation instructions often be easier to designate it as an
• O&M manuals external element of the building and
reference the components within the wall
BIM Level 2 requires this information to be from a reference drawing viewed from the
in an electronic format which may simply outside rather than by their location within
be .pdf format documents. However, the a room or compartment as viewed from
information has to be coordinated with the inside. In the case of separate windows
drawings and supported by drawings. mounted in a wall of say blockwork
CAD drawings may be prepared as construction it may be easier to simply
enhanced objects with information reference them by room or compartment.
embedded in them. For instance a glass
specification may be revealed by clicking Whichever approach is taken to
on a glazed opening on the drawing. referencing it is important that it is
Maintenance information may be revealed coherent and comprehensive. The
in the same way, may be in a stand-alone provision of reference drawings or marking
maintenance manual or may be accessed of components is essential. Marking may
on a manufacturer’s or specialist be by labelling or printing and it may be
contractor’s website. One thing to be directly readable or barcoded. It is also
borne in mind is the permanence of possible to used RFID (Radio Frequency
information external to the BIM. Identification) tags the cost of which
continues to fall. These can contain large
For simple plane rectilinear facades amounts of information and may be either
greater efficiency may be derived from read or read/write tags. Read/write tags
using enhanced objects in a 2-D CAD are appropriate for items such as
drawing rather than preparing complex 3- actuators which have a service
D drawings that only portray the geometry, requirement but simple passive read only
and by efficiently correlating supporting tags are sufficient for most façade
information with drawings. components. RFID tags have the
COBie advantage that they may be embedded
and do not affect the appearance of the
BIM level 2 requires information to be envelope.
passed to the Building owner/manager at
completion of the project. The minimum The information required in the COBie
format for this information is a spreadsheet should be agreed at the beginning of a

7/10
Building information modelling – principles for building envelopes TN 93

project and it should be remembered that • What is expected from the BIM
it is the information required to operate the o Who is the user of information in
building. This may include the need to the BIM
replace damaged or failed components. o What purpose is it to serve
The information may be given as product • Who will prepare and manage the BIM
information or as a technical performance o What software is to be used
specification. The latter is more robust as o What functionality will it provide
Manufacturers may cease to trade. • Who will provide information
Similarly, if information on maintenance is o What information
given simply as a reference to a o In what format
manufacturer’s website that may not be • Who owns and is responsible for
supported long term, it is more robust to information
have documentation within, or alongside
the COBie in the building manager’s It is clear that whereas a project
ownership. specification would have required the
specialist contractor to provide
The technical information provided for the construction drawings, method statements
different elements of the wall is shown in and O&M manuals, CWCT (2006), it is
Table 1. The lists given are not now necessary to specify any provision of
exhaustive and the exact information information as a separate EIM or the
required will depend on the scope of content and format of data to be handed to
performance of the wall or window. the manager of the BIM. This may be the
basis of pre-qualifying tenderers on a
contract. This should be given in the
Proceeding to a project Employers Information Requirements.

On any project the lead consultant or main The BIM Strategy Report published in
contractor should have prepared a BIM March 2011 concludes that in adopting
Execution Plan that details the information BIM at Level 2 ‘no significant amendments
listed below. While many state that the are required to contracts currently used by
key to BIM is the ‘I’ for information, without the construction industry’. This assumes
clear communication and protocols in that a BIM Execution Plan has been
place the process can easily become prepared. Of course all contributors to the
convoluted and inefficient. BIM have the same duty of care in
preparing information as they do when
When implementing BIM on a project it is they prepare drawings, maintenance
necessary to establish: manuals and so forth.

Glass Window Curtain wall frame Spandrel


Type (layer 1) Frame U-value Frame U-value U-value
Thickness Security Framing system Insulation material
Type (layer 2) Acoustics Framing profiles Surface materials
Thickness Framing system Finish Finish/Colour
Safety/containment Framing profiles Colour
U-value Finish
g-value Colour
Light transmission
Colour

Table 1 Information included in COBie

It is also important to understand the roles BIM Manager is not responsible for the
of the different parties; in particular the accuracy of information supplied and the
BIM Manager is only responsible for role is distinct from that of design
setting the formats and standards and coordinator.
coordinating the flow of information. The

8/10
Building information modelling – principles for building envelopes TN 93

What do we want from BIM? Abbreviations

On any project it is necessary to


understand the benefits that can be AIM Architectural information model
delivered by BIM and the most effective
and efficient way to deliver those benefits. BIM Building information model /
Building information modelling
Table 1 shows the purpose for which BSIM Building services information
building information modelling may be model
used at different stages of a project and
the formats and grades of detail that may CAD Computer aided drawing
be required. EIM Envelope information model
FIM Facilities information model
iBIM Interoperable Building
Further guidance Information Model

BS 1192 gives guidance on the SIM Structural information model


referencing of information contained within
BIM using the uniclass referencing
system. BS ISO 12006-3 also covers the References
topic. Uniclass is a classification system
managed by CPIC (Construction Project BS 1192 Collaborative production of
Information Committee) www.cpic.org.uk. architectural, engineering
and construction
Avanti was a Government funded project information. Code of
to study the uptake of ICT in construction. practice, British Standards
The reports produced are a valuable Institution, 2007.
source of information and may be found at
http://www.cpic.org.uk/en/publications/ava CWCT TN 53 - Method statements
nti/index.cfm (2009) for the construction of
building envelopes, CWCT,
The BIM task group has a website that 2009.
contains useful information at CWCT Standards for Systemised
http://www.bimtaskgroup.org/ (2006) Building Envelopes, CWCT,
2006.
More information on COBie and example
spreadsheets are available at
http://www.bimtaskgroup.org/cobie-uk- ISO 12006 Building construction —
2012/ Organization of information
about construction works —
The ‘BIM Strategy Report’ is available at Part 3: Framework for
http://www.bis.gov.uk/policies/business- object-oriented information,
sectors/construction/research-and- British Standards Institution,
innovation/working-group-on-bimm 2007.

The NBS BIM Library is available at


www.nationalbimlibrary.com/

The BIMStore is available at


www.thebimstore.com/ © CWCT 2012
University of Bath, Claverton Down, Bath,
BA2 7AY
Tel: 01225 386541; Fax: 01225 386556
Email: cwct@bath.ac.uk;
www.cwct.co.uk

9/10
Building Information Modelling – Principles for Building Envelopes TN 93

Information required
from specialist
Stage Purpose Information Format Responsible contractor User
Planning/Scheme Architectural Solid elements or 3-D Architect Co-ordinates of outer Architect
design images plates accurately surface of envelope (if
colour rendered appointed)
Detail design Clash detection Solid elements 3-D Main Contractor Co-ordinates of elements Main Contractor
System company (if appointed)
Construction Construction Solid elements 3-D Main Contractor Co-ordinates of elements Main Contractor
programming System company (if appointed)
Envelope design Manufacture and Various 2-D / 3-D Specialist Contractor N/A
fabrication
Envelope design Checking structural Various 2-D / 3-D Main Contractor/ Co-ordinates of fixings (if Main Contractor
interfaces Specialist Contractor appointed)
Envelope design Checking service Various 2-D / 3-D Main Contractor/ Detail sections Main Contractor
interfaces Specialist Contractor
Envelope design Checking interfaces Various 2-D / 3-D Main Contractor/ Detail sections Main Contractor
with adjacent Specialist Contractor
cladding packages
Construction Construction Method statements .pdf documents Main Contractor/ Method statements Main Contractor
Specialist Contractor (CWCT 2009)
Construction Construction Installation .pdf documents Specialist Contractor Installation drawings Main Contractor
drawings (CWCT 2009)
In use Maintenance O & M manual .pdf documents Specialist Contractor O & M manual Client
/COBie
In use Repairs Component .pdf documents Specialist Contractor Suppliers and Client
information /COBie specification of
components

Table 2 Use of Building Information Modelling

10/10

Das könnte Ihnen auch gefallen