031
14 Jan - 19 Jan 2019
Mahogany Homes
Sitio Marang, San Mateo, Rizal
Prepared by:
Thome Maverick S. Mariano
Debussy G. Panganiban
Executive Summary:
Land Development:
Ziba Builders
Painting Works on Blk 5.
Roofing Works on Blk 5.
Construction of Model Units.
Declogging of Manhole.
Construction of Additional Riprap 44 l.m.
Cut and Fill.
Contract Milestone:
Start Date: May 1, 2018
Finish Date: October 30, 2018
I. MANPOWER REPORT
II. EQUIPMENT
V. PROGRESS PHOTO
ZIBA BUILDERS - 26
MWSS -0
II. Equipment
ZIBA BUILDERS
Total No. of days No. of days Remarks
Operational Non-
Operational
One-Bagger Mixer 1 0 7
Backhoe 1 7 0
07 08 09 10
11 12 13
Ziba Builders 21 22 23 24 25 26 27
THE2
Concreting and Rebar works
44.18% out of 45.65%
Formworks
16.10% out of 16.81%
Roof Framing
100%
Fascia Board
100%
Electrical Roughing Ins
85.00%
Total wt%
69.86%
IV. KEYPLAN MONITORING
SIDEWALK:
TO DATE:
WATERLINES:
TO DATE
RIPRAP
MODEL UNITS:
BLK 1
Poured
BLK 5
Poured