WEEKLY PROGRESS REPORT No.

031
14 Jan - 19 Jan 2019

Riza Development Corporation

Mahogany Homes
Sitio Marang, San Mateo, Rizal

Prepared by:
Thome Maverick S. Mariano
Debussy G. Panganiban
Executive Summary:
Land Development:
Ziba Builders
 Painting Works on Blk 5.
 Roofing Works on Blk 5.
 Construction of Model Units.
 Declogging of Manhole.
 Construction of Additional Riprap 44 l.m.
 Cut and Fill.
Contract Milestone:
Start Date: May 1, 2018
Finish Date: October 30, 2018

Elapsed Days: 243


Remaining Days: 0
Total Duration: 176
Variance Days: -74

ZIBA BUILDERS (MAHOGANY HOMES)


DIV. NO PARTICULARS % WT. ON-SITE %WT NO. OF AS PER VARIANCE %
PROGRESS EQUIVALENT DAYS SCHED DAYS VARIANCE
LAPSED
1 General Requirement
Mobilization/Demobilization 1.75% 50.00% 0.87%
Temporary Facilities 1.17% 75.00% 0.87%
Survey Works 2.69% 60.00% 1.61%
2 Earthworks
Clearing&Grubbing 4.36% 85.00% 3.71% 21 4.36% -3.15 -0.65%
Excavation/Cut 0.37% 85.00% 0.31% 12 0.37% -1.80 -0.06%
Compacted Fill 6.86% 90.00% 6.17% 24 6.86% -2.40 -0.69%
Loading/Hauling 10.32% 85.00% 8.77% 24 10.32% -3.60 -1.55%
Haul-out of Unsuitable Matl's 2.97% 85.00% 2.53% 24 2.97% -3.60 -0.45%
3 Roads
Road Tracing 3.99% 100.00% 3.99% 12 3.99% 0.00 0.00%
Sub-grade Preaparation 3.99% 100.00% 3.99% 36 3.99% 0.00 0.00%
Base Preparation 4.16% 100.00% 4.16% 36 4.16% 0.00 0.00%
Road Paving 3.47% 100.00% 3.47% 14 1.73% 0.00 0.00%
Curbs&Gutter 8.12% 100.00% 8.12% 36 8.12% 0.00 0.00%
Sidewalk 9.31% 97.10% 9.04% 36 9.31% -1.04 -0.27%
4 Drainage System
15"Ø RCP 2.60% 100.00% 2.60% 18 2.60% 0.00 0.00%
18"ØRCP 1.54% 100.00% 1.54% 18 1.54% 0.00 0.00%
24"ØRCP 0.64% 100.00% 0.64% 15 0.64% 0.00 0.00%
MANHOLES:
15" 0.94% 100.00% 0.94% 18 0.94% 0.00 0.00%
18" 0.81% 100.00% 0.81% 18 0.81% 0.00 0.00%
24" 0.81% 100.00% 0.81% 15 0.81% 0.00 0.00%
5 Other Structure
Riprap 15.49% 100.00% 15.49% 48 15.49% 0.00 0.00%
Fencing (H=2.7m) 13.67% 65.96% 9.02% 48 13.67% -16.34 -4.65%
100.00% 89.45% 94.40% -4.95%
6 Additionals
Riprap 24 l.m - 100.00% -
Riprap 44 l.m - 36.36% -
Fence Solid Wall H=2.7m - 100.00% -

Action taken to catch up to delay:


 Additional Manpower.
 Have an Overtime work.
TABLE OF CONTENTS

I. MANPOWER REPORT

II. EQUIPMENT

III. WEATHER CONDITION

IV. ONE WEEK LOOK AHEAD

V. PROGRESS PHOTO

VI. KEY PLAN MONITORING


I. Manpower Report (Average per week)

 ZIBA BUILDERS - 26
 MWSS -0

II. Equipment
 ZIBA BUILDERS
Total No. of days No. of days Remarks
Operational Non-
Operational
One-Bagger Mixer 1 0 7
Backhoe 1 7 0

III. Weather Condition

07 08 09 10

11 12 13

SUNNY RAINY FAIR


IV. One Week look ahead.

Ziba Builders 21 22 23 24 25 26 27

1.0 Construction of Riprap 44l.m

2.0 Construction of Model Units

3.0 Roofing Works

4.0 Paiting Works


V. Progress Photo
PREVIOUS TO DATE
Construction of Model Units:
BLK.5 BLK.1

 Stair Rebars.  Allignment of Formworks.


 Concrete Pouring at Stair  Electrical-lines.
 Roofing Works.  Concrete Pouring
 Painting Works.
 Plumbing. DX2
 Concreting and Rebar works
TH1  33.83% out of 38.48%
 Concreting and Rebar works  Formworks
 40.08% out of 41.93%  7.03% out of 8.38%
 Formworks  Electrical Roughing Ins
 16.97% out of 17.97%  85.00%
 Roof Framin  Total wt%
 100%  46.38%
 Fascia Board
 100%
 Electrical Roughing Ins
 85.00%
 Total wt%
 67.55%

THE2
 Concreting and Rebar works
 44.18% out of 45.65%
 Formworks
 16.10% out of 16.81%
 Roof Framing
 100%
 Fascia Board
 100%
 Electrical Roughing Ins
 85.00%
 Total wt%
 69.86%
IV. KEYPLAN MONITORING
SIDEWALK:
TO DATE:

WATERLINES:
TO DATE
RIPRAP

MODEL UNITS:
BLK 1

Poured

BLK 5
Poured