Beruflich Dokumente
Kultur Dokumente
Risk Management
Pre-Design
1. Project Initiation - Initial Meeting and Planning
2. Scoping - Space or Land Acquisition
3. Feasbility - Budgeting
Design
4. Schematic Design - Initial Renderings
5. Design Development - Full Architectural, Design & Engineering
6. Construction Documents - Contract Administration
Construction
7. Delivery Method - Negotiate, Bid & Value Engineer
8. Construction - Award, Project & Safety Management
9. Closeout - Warranty and Shake Owner's Hand
Pre-Planning phase
It assembles the people, information, and budgets needed for an effective evaluation of
the alternatives that will be developed in the Feasibility Study. (e.g., special studies,
customer agency plans, facility requirements, and community characteristics)
Award
Site Possession
Site clearance
Construction
Handing Over
Commencement of work
Timely possession of the site is critical to keeping the
project on schedule.
Reasons:
- manage and operate the construction works;
- maintain satisfactory levels of environmental protection and
- limit disturbance from construction activities.
2) Site Possession
- right to enter the Site, occupy and use the Site and carry out the
specified Works.
Procedure to Site Possession
1) Establishment
1) Establishment (cont.)
1) Establishment (cont.)
i. Reinstatement
ii. Contaminated areas
iii. Disconnection of services
iv. Removal of fencing (subject to instruction)
v. Roads and footpaths
General Requirements
Site accesses, accesses to site offices/compounds and roads in the vicinity of site
access points will be maintained clean as required.
Good housekeeping’ policy and best practice.
Adequate car parking facilities.
Fire Safety
Fire Safety Risk Assessment.
For complex projects, require additional planning, management and implementation
in regards to fire prevention related matters, over and above what is expected for
basic for none complex maintenance projects.
Signage
Lighting
Pest Control
Security
Dust and Air Pollution
Waste and Waste Minimisation
Clearance of Site on Completion
Documentation and records
i. Site file
ii. Client
iii. Contract file
Leadership
– Management responsibilities (supervision from the top of the organisation to the
workforce).
Worker involvement
– Encouraging effective worker involvement, so that every worker plays an active role.
Contractor competence
- Emphasis on the competence of organisations and individuals (qualification, licences,
experience etc).
Temporary works
– Managing temporary works effectively.
3) Site survey (sample)
- Before work commence – photographic survey and written reports.
3) Site survey (sample)
Site Clearance Approach
Other requirements:
- Arrangements and responsibilities for site security after site possession.
- Permanent disposal or temporary storage sites.
- Arrangements and responsibilities for handling of hazardous/
contaminated materials.
- Transport of debris.
- Information and communication management.
Sample of Building Data Sheet
Simple process for a small project
Project schedule (sample)
Project schedule (sample)
Project schedule (sample)
1.0 Pre-Construction Planning Activities