MINUTES OF MEETING

INSPECTION LOADING MEETING


GPU TURNAROUND – UK DEMIN P1 & UK ASU 1 TA 2019
PETRONAS GAS BERHAD (PGB)

MEETING NO. VENUE DATE / DAY TIME

25.02.2019
INSP01 MTC 1000hrs-1300hrs
Monday

SECRETARY AGENDA CHAIRMAN

1. Opening & Introduction.


Mohd Raziemi Razak 2. Welcoming Remark. Mohd Syafiq Ramlee
3. Items Discussion.

ATTENDEES
DEPARTMENT/
NO NAMES INITIAL ATT. REMARK
DESIGNATION
As per attendance list

ACTION DUE
NO DESCRIPTION
BY DATE
1.0 OPENING & INTRODUCTION

1.1 Mr. Syafiq welcomed all attendees and started meeting with recitation Info NA
of Surah Al-Fatihah.

2.0 WELCOMING REMARKS

2.1 Mr. Shafiq briefed on the inspection schedule for DEMIN P1 & ASU 1 TA
2019 for look on maximum inspection activity per day. Info

3.0 ITEMS DISCUSSION

Discussion on DEMIN P1 TA Inspector loading based of peak inspection


activity by 20th March with 7 concurrent equipment at same day.
In summary PGB agreed to load; PGB 16th Mar
3.1 SITE 3 PAX MMSSB
DEMIN P1 WORKSHOP 1 PAX
PSV 1 PAX

Regarding lesson learnt from the previous TA, MMSSB introduced the
QC Runner which is new role in QC team, who has responsibility on
tracking the update.
QC COORDINATOR 1 PAX PGB 16th Mar
3.2
QC STATIC 2 PAX MMSSB
DEMIN P1 QC RUNNER 2 PAX
QC PAINTING 2 PAX
QC WORKSHOP 2 PAX

Open
MINUTES OF MEETING
INSPECTION LOADING MEETING
GPU TURNAROUND – UK DEMIN P1 & UK ASU 1 TA 2019
PETRONAS GAS BERHAD (PGB)

Non-Destructive Testing (NDT) required at DEMIN P1 TA are UTTM and


DPT, arrangement on team loading as follow; PGB
3.3 16th Mar
MMSSB
UTTM 3 PAX
DEMIN P1
DPT 2 PAX AT WORKSHOP

ASU-1 TA involved with 9 nos equipment of concurrent inspection


activity by 6th April with 6 days window duration. Consent from two-
way discussion, Inspector loading as;
BACK-UP DEMIN INSP.
4 PAX PGB
3.4 AT SITE (if required) 16th Mar
MMSSB
AT
ASU 1 1 PAX
WORKSHOP
PSV 1 PAX
PLOC/ISOV 2 PAX

Strategy on ASU-1 QC loading team as below;


STATIC
QC COORDINATOR 1 PAX
QC STATIC 3 PAX
QC RUNNER 2 PAX
PGB
3.5 QC PAINTING 2 PAX
ASU 1 MMSSB 31th Mar
QC WORKSHOP 1 PAX
PLOC
PLOC COORDINATOR 1 PAX
PLOC QC 2 PAX
PSV SUPV CUM AS PSV QC 1 PAX

NDT team required for the whole package of ASU-1 TA as follows;


DPT 4 PAX
UTTM 3 PAX
VIDEOSCOPE 5 TEAM 3 AT WORKSHOP 2 AT SITE PGB 31th Mar
3.6
ASU 1 ECT 5 TEAM 3 AT WORKSHOP 2 AT SITE MMSSB
SUR. REP. &
BY NDE
HARDNESS 1 TEAM
ARRANGEMENT BY TAS
TEST

In order to make sure QC part shall execute with excellent, a few key
success factors considered for better improvement;

3.7 • WCS tracking form to be frequently updated. Info


• Summary update board for inspection activity.
• QC will be full time collaborate with PGB inspector.
• QC runner highly responsible on tracking update.

Open
MINUTES OF MEETING
INSPECTION LOADING MEETING
GPU TURNAROUND – UK DEMIN P1 & UK ASU 1 TA 2019
PETRONAS GAS BERHAD (PGB)

Support and embrace from PGB to ensure all partners can give best
cooperation to further success of UK TA 2019;
3.8 Info
• Convenience of facilities ie: printer/workstation for inspector.
• Pool of box-up cert signed personnel (Alvin, Suhailan, Zul).
• Full time inspection team at site ie: Reviewer, DC.

4.0 END OF MEETING

4.1 The meeting was adjourned at 1300hrs with a closing and doa Info
recitation.

5.0 ACCEPTANCE OF MOM


Prepared by:
Mohd Raziemi Razak
Asst. Scheduler, MMSSB
Reviewed by:
Amran Ali
QC Leader, MMSSB.
Endorsed by:
Muhammad Shukri Mohamad
TA Manager, MMSSB
Endorsed by:
Rosdi Ariff Rahman
QC Executive, GPU-TAS.
Approved by:
M Muhaimin b. A Rahim
TA Manager, GPU-TAS.