Description Phase 1A Phase 1B

Commencement Date 10/6/16 - 10/7/16 10/6/16 - 8/9/16


Contractual Completion Date 21/6/16 21/6/16
CNC 07/08/16 10/04/17
Day of Delays 420 368
Claimed (days) 320
EOT Approved (days) 84 138
Final Date 15/10/2016 16/2/2017
Total Days 282 284
LD Amount (RM 7,000/days) 1,974,000.00 1,988,000.00
Total Amount (RM) 3,962,000.00
Contract Amount (RM) 3,450,000.00
Amount Paid by Client (RM) 3,009,234.50
VO (RM) 300,957.06
Net (RM) -3,220,277.44

Calculation

Net = ((Contract Amount (RM) +Variation Order (RM)) - Amount Paid by Client (RM) ) - Liquidated Damaged
(RM)
EOT APPROVAL ITEMS (6 DECEMBER 2018)

CONTRACTOR CONSULTANT
ID ICM Proof
DETAILS FROM TO EOT REQUEST DETAILS FROM TO EOT 1A EOT 1B
Submit As-built (PDF) to ICM 10/10/2016 27/10/2017 16 Received As-Built (PDF) from HGSP 10/10/2016 10/10/2016 1 1
Request surveyor peg the boundary line on
site 11/10/2016 13/10/2016 3 3 email

Request HGSP to email the superimpose 13/10/2016 8/11/2016 1 1 MOM


sheet pile and boundary line

The boundary line given by surveyor and


Submit ACAD As-built to ICM 27/10/2016 21/11/2016 21 8/11/2016 23/11/2016 14 14 email
boundary line on plan layout is not tally
8
Received As-built from SSS (PDF) 23/11/2016 1/12/2016 8 8 email
Request As-built (ACAD) 1/12/2016 2/12/2016 1 1 email
Request for urgent meeeting + Stop Work
Consultant respond to As-built 21/11/2016 5/12/2016 12 2/12/2016 5/12/2016 4 4 email
Order
Request another survey drawing done by
Stop Work Order 5/12/2016 6/1/2016 28 5/12/2016 22/12/2016 15 15 email
surveyor (few points)
Difference reference point (SSS Survey
Engineer Instruction to hack Cap Beam 6/1/2017 - 0 22/12/16 17/1/2017 21 21 email
drawing issue)
77 68 68
Request for survey As-built from SSS 10/2/2017 - 1 Submit survey As-built to HGSP 2/10/2017 - 1 0 email
Request SSS to mark the tie-beam on site
2/10/2017 16/2/2017 5 5 email/MOM
for 1A & 1B
Receive the table of list for encroachment
17/2/2017 - 2 2 email
from HGSP
Submit latest As-built drawing from SSS to
20/2/2017 - 0 0
HGSP
Temporary sheet pile support 20/2/2017 - 2 0
9
Email sketches details for tie-beam
23/2/21017 1/3/2017 6 0 email/MOM
rectification work
HGSP counter proposed the details sketches 1/3/2017 3/3/2017 0 0

Tie-beam rectification work method


2/10/2017 20/4/2017 59 statement approval due to incomplete 13/3/2017 20/4/2017 3 0
Method statement rectification work documents
60 19 7
Rectification Work 19/04/2017 21/06/2017 55 Agreed duration for rectification works 1/6/2017 21/6/2017 18 0 Letter
10
55 18 0
Instruction for anchor head trimming & tie-
21/06/2017 28/8/2017 59 21/6/2017 14/7/2017 20 0 email
Final Reminder Work Completion Date beam rectification at CH 73-80
11 Final reminder to carry out work 28/8/2017 - 0 0 letter
Reconfirm line boundary on site 28/8/2017 13/10/2017 40 Pegging work by licensed surveyor (SSS) 4/10/2017 8/10/2017 4 0 email
99 24 0
Rectification Work 13/10/2017 18/10/2017 5 Rectification work 13/10/2017 18/10/2017 0 0 email
12
5 0 0
Checklist before issue certificate of Request and proposed date for site
14/10/2017 10/11/2017 24 19/10/2017 24/10/2017 0 0 email
Practical Completion inspection
Site inspection 25/10/2017 - 0 0 email
Received as built survey from surveyor (SSS) 30/10/2017 - 0 0 email
13
Survey drawing issue 30/10/2017 8/11/2017 9 9 email
Request for final inspection 3/11/2017 10/11/2017 0 0 email
CPC 10/11/2017 - 0 0 letter
24 9 9

Total 320 Total 138 84

* Approved EOT DOES NOT include Sundays


EOT Calculation (Not Inclusive Sunday)

Commence 2016 2017 EOT


Phase Final date
Date Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug (days)
1A 10/7/16 18 27 26 26 26 15 138 17/12/16
1B 8/9/16 19 26 26 13 84 15/12/16
222

LD Calculation (Not Inclusive Sunday)

2016 2017 TOTAL


Phase EOT LD (RM)
Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov (days)
1A 17/12/16 12 26 24 27 25 27 26 26 27 26 26 10 282 1,974,000.00
1B 15/12/16 14 26 24 27 25 27 26 26 27 26 26 10 284 1,988,000.00
3,962,000.00
Claim by Contractor ICM Recommendation
Item Description
Variation Order (RM) Variation Order (RM)
1 Demolish drain 3,340.00 3,020.00
2 Pre-boring 69,800.00 69,800.00
3 Proving Test
- 12m
- 14 m
11,558.33 11,558.33
- 14 m + Post Grout
- 16 m
4 Ground Anchor 16 m 204,975.00 171,600.00
5 Tappered Sheet Pile (Double)
41,550.00 6,051.20
Tappered Sheet Pile (Tripple)
6 Connection Wall 8,248.00 8,248.80
7 Remove Existing Slab & beam (CH160) 11,560.00 11,240.00
8 Reinstall Formwork at Infinity Pool 12,740.00 12,740.00
9 Press down Sheet Pile Phase 1B 97,922.50 84,747.50
10 Excavation Phase 1B 3,600.00 3,600.00
11 Subsoil drain pipe 21,526.68 21,046.38
12 Backfill behind Capping Beam 7,987.30 1,700.00
13 Joint of Sheet Pile 8,392.00 8,392.00
14 Handle, pitch, drive FSP IV Single -15,562.50 -15,562.50
15 Capping Beam 106,501.70 93,236.84
Tie-Beam 34,493.19 26,112.68
16 Rectification Manhole 31,830.00 31,830.00
17 Additional Anchor (16m) 60,450.00 57,200.00
18 Excavation to remove wood at CH 368 1,000.00 840.00
19 Inclinometer test 39,000.00
20 Rectification Work for House Fencing 28,000.00
21 Rectification Work for Capping Beam 80,263.68
22 Rectification Work for Tie-Beam 134,772.00
23 Rectification Work for Void Underneath House 100 1,018.00 1,018.00
24 Rectification Sheet Pile Joints 550.00 550.00
1,005,515.88 608,969.23
0.00
23 Fabricate, Supply, Deliver FSP IV -166,664.00
24 Supply & Deliver FSP III 73,008.00
25 Handle, Pitch & Drive FSP III 6,840.00
26 Earthwork Phase 1A -97,326.20
27 Earthwork Phase 1B -123,870.00
0.00
Grand Total (RM) 300,957.03