Cartel 1
Campamento 1
Descolmatación de río M3 1000 80 0.61 48800
Eliminacion mat excedente M3 18554.97 38.02%
Excavacion Uña M3 1000 1 6.03 6030
Roca Uña M3 1000 1 2.92 2920 0.85 2482.00
Roca Cuerpo M3 1000 1 6.03 6030 0.85 5125.50 7607.5
Perfilado y Refine Talud M2 900 8 7200
100 5 500 7700
0.9065
PRESUPUESTO ANALITICO COSTOS DIRECTOS
COMBUSTIBLE 199757.09
Petroleo D-2 Gal 15980.57 12.50 199757.09
MATERIALES 5402.32
Cartel de Obra Unid. 1.00 500.00 500.00
Campamento y Equipamiento Unid. 1.00 1500.00 1500.00
Herramientas Global 1.00 792.16 792.16
Pintura Gln. 1.00 40.00 40.04
Wincha Unid. 1.00 120.00 120.12
Repuestos Cama Baja Glb. 1.00 2450.00 2450.00
EQUIPOS 289942.58
Teodolito H-E 280.00 7.50 2100.00
Bulldozer D155AX-5 H-M 220.24 209.96 46241.59
Excavadora PC-400 - 306 HP H-M 1103.30 120.73 133201.80
Volquete Volvo NL 10/12 H-M 1585.25 68.38 108399.20
TOTAL COSTO DIRECTO S/. 543331.83
COSTO INDIRECTO 74,090.17
COSTO TOTAL 617,422.00
ANALISIS DE COSTOS UNITARIOS
Proyecto Defensas Ribereñas en el Río Rimac - Sector Huachipa
Lugar Ñaña
S/. 596.00
S/. 1586.00
MATERIALES 0.00
S/. 3300.00
MATERIALES 64.58
Teodolito 1.00 H-E 8.00 7.50 60.00
Wincha Glb. 0.03 120.00 3.43
Pintura Gln. 0.03 40.00 1.14
S/. 176.58
PARTIDA 1.5 Movilización y Desmovilización de Maquinaria
8 horas/día Metrado 7.00
1.00 Vje/día Unidad VJE
Part. Descripción Unidad Cantidad P. Unit. (S/.) P. Parcial (S/.) P. Total (S/.)
COMBUSTIBLES 350.00
Petroleo 3.5 Gln. 28 12.50 350.00
REPUESTOS 350.00
Camión Plataforma 1 Glb. 1.00 350.00 350.00
S/. 780.00
MATERIALES 4000.00
Petróleo Diesel D-2 10.0 Glns 320.00 12.50 4000.00
S/. 10902.72
S/. 2.76
MATERIALES 1.77
Petróleo Diesel D-2 17.0 Glns 0.14 12.50 1.77
S/. 4.54
PARTIDA 2.40 Excavación de Uña
8 horas/día Metrado 6030.00
Rendimiento 600.00 M3/día Unidad M3
Part. Descripción Unidad Cantidad P. Unit. (S/.) P. Parcial (S/.) P. Total (S/.)
MANO DE OBRA 0.17
Capataz 0.50 H-H 0.01 9.00 0.06
Oficial 1.00 H-H 0.01 5.00 0.07
Peón 1.00 H-H 0.01 3.50 0.05
MATERIALES 1.33
Petróleo Diesel D-2 8.0 Glns 0.11 12.50 1.33
EQUIPO Y/O MAQUINARIA 1.61
Excavadora PC 400 1.00 H-M 0.01 120.73 1.61
S/. 3.12
SERVICIOS 3.02
(*) Excavadora PC-400 1.00 H-M 0.03 120.73 3.02
S/. 5.84
(*) Aporte de la Junta de Usuarios Rímac
MATERIALES 5.13
Petróleo Diesel D-2 8.0 Glns 0.41 12.50 5.13
HERRAMIENTAS 0.06
Desgaste de Herramientas % MO 0.05 1.10 0.06
S/. 12.48
PARTIDA 3.30 Transporte de Roca
8 horas/día Metrado 7607.50
Rendimiento 156.00 M3/día Unidad M3
Part. Descripción Unidad Cantidad P. Unit. (S/.) P. Parcial (S/.) P. Total (S/.)
MATERIALES 5.77
Petróleo Diesel D-2 9.0 Glns 0.46 12.50 5.77
S/. 17.31
MATERIALES 4.00
Petróleo Diesel D-2 8.0 Glns 0.32 12.50 4.00
HERRAMIENTAS
Desgaste de Herramientas % MO 0.05 0.98 0.05 0.05
S/. 9.86
TOTAL
CRONOGRAMA DE EJECUCION MENSUAL COSTOS INDIRECTOS
OBRA : DEFENSA RIBEREÑA EN EL RIO RIMAC - SECTOR MONTE BAJO
COMBUSTIBLE 183776.52
Petroleo D-2 Gal 15980.57 11.50 183776.52 2000.00 23000.00 7500.00 86250 3000 34500 4000 46000 -519.43 -5973.48 15980.57 183776.52
MATERIALES #VALUE!
Cartel de Obra Unid. 1.00 500.00 500.00 1.00 500.00 1.00 500.00
Campamento y Equipamiento Unid. 1.00 1500.00 1500.00 1.00 1500.00 1.00 1500.00
Herramientas Global 1.00 #VALUE! #VALUE! 1.00 #VALUE! 1.00 #VALUE!
Pintura Gln. 1.00 40.00 40.04 1.00 40.04 1.00 40.04
Wincha Unid. 1.00 120.00 120.12 1.00 120.12 1.00 120.12
Repuestos Cama Baja Glb. 1.00 2450.00 2450.00 1.00 2450 1.00 2450.00
EQUIPOS #VALUE!
Teodolito H-E 280.00 7.50 2100.00 56.00 420.00 56.00 420 56 420 56 420 56 420 280.00 2100.00
Bulldozer D155AX-5 H-M 220.24 110.38 24310.09 -19.76 -2181.11 240.00 26491.2 220.24 24310.09
Excavadora PC-400 - 306 HP H-M #VALUE! 57.28 #VALUE! #VALUE! #VALUE! 208.00 11914.24 208 11914.24 240 13747.2 240 13747.2 #VALUE! #VALUE!
Excavadora SL-30 III (244 HP.) (*) H-M 190.19 94.96 18060.21 190.19 18060.21 190.19 18060.21
Volquete Volvo NL 10/12 H-M 1585.25 41.42 65660.94 160.00 6627.20 416.00 17230.72 416.00 17230.72 593.25 24572.2955 1585.25 65660.94
TOTAL COSTO DIRECTO S/. #VALUE! #VALUE! 180898.37 82146.96 103951.50 #VALUE! #VALUE!
(*) Aporte de la Junta de Usuarios 18060.21 18,060.21
TOTAL MINAG #VALUE! 173638.16 94,096.96 114751.50 #VALUE! #VALUE!
COSTO DIRECTO #VALUE! 162838.16 82,146.96 103951.50 #VALUE! #VALUE!
COSTO INDIRECTO 23,090.00 10800.00 11950.00 10800.00 12907.49 69,547.49
PRESUPUESTO ANALITICO COSTOS INDIRECTOS
PART DESCRIPCION UND CANTID. P. UNIT. P. PARCIAL P. TOTAL 1 MES 2 MES 3 MES 4 MES 5 MES
20.00 VIATICOS 0.00
Viaticos Glob. 1 0.00 0.00
23.00 COMBUSTIBLE Y LUBRICANTES 6540.00
Gasolina 84 oct Gal 500 12.00 6000.00 6000
Lubricantes Glob. 1 540.00 540.00 540
30.00 BIENES DE CONSUMO 1500.00
Repuestos Camioneta Glob. 1 1500.00 1500.00 1500
27.00 SERVICIOS NO PERSONALES 50,000.00
Coordinador Técnico Mes 5.00 4000.00 20000.00 4000 4000 4000 4000 4000
Residente Obra Mes 5.00 3200.00 16000.00 3200 3200 3200 3200 3200
Administrador de Obra Mes 5.00 1800.00 9000.00 1800 1800 1800 1800 1800
Asistente Administrativo Mes 5.00 1000.00 5000.00 1000 1000 1000 1000 1000
39.00 SERVICIOS DE TERCEROS 7,407.49
Expediente Técnico Glob. 1.00 3000.00 3000.00 3000
Copias, revelados y espiralados Glob. 1.00 1007.49 1007.49 200 200 200 200 207.49
Liquidacion Obra Glob. 1.00 2500.00 2500.00 2500
Legalización de Obra Glob. 1.00 100.00 100.00 100
Servicios Reparación Camioneta Glob. 1.00 800.00 800.00 400 400
49.00 MATERIAL DE ESCRITORIO 3,100.00
Utiles de Oficina Gob. 1.00 3100.00 3100.00 1550 1550
57.00 TELEFONIA MOVIL Y FIJA 1,000.00
Servicios y Tarjetas telefónicas Glb. 1.00 1000.00 1000.00 200 200 200 200 200
COSTO INDIRECTO TOTAL S/. 69,547.49 23090 10800 11950 10800 12907.49