OptiX OSN 7500

Commissioning Guide Contents

Contents

1 Preparations for Equipment Commissioning .................................................................................1-1


1.1 Instruments and Tools.................................................................................................................... 1-2
1.2 Engineering Information................................................................................................................ 1-3
1.3 Connection Points Position ............................................................................................................ 1-4
1.4 External Check .............................................................................................................................. 1-6
1.5 Requirements for Commissioning Engineers ................................................................................. 1-7
1.6 Commissioning Items .................................................................................................................... 1-8

T2-040439-20060320-C-1.50 Huawei Technologies Proprietary i


OptiX OSN 7500
Commissioning Guide Figures

Figures

Figure 1-2 Connection points position of OptiX OSN 7500................................................................. 1-4

T2-040439-20060320-C-1.50 Huawei Technologies Proprietary iii


OptiX OSN 7500
Commissioning Guide Tables

Tables

Table 1-1 Organisation of chapter 1 .................................................................................................... 1-1


Table 1-2 Instruments and tools for commissioning ............................................................................. 1-2
Table 1-3 Numbering and functions referred to the connection points .................................................. 1-5
Table 1-4 Testing items ....................................................................................................................... 1-8

T2-040439-20060320-C-1.50 Huawei Technologies Proprietary v


OptiX OSN 7500
Commissioning Guide 1 Preparations for Equipment Commissioning

1 Preparations for Equipment


Commissioning

This chapter describes the preparations for commissioning. Table 1-1 shows the
organisation of this chapter.

Table 1-1 Organisation of chapter 1


Section Describes the …

1.1 Instruments and Tools Instruments and tools needed.


1.2 Engineering Information Engineering documents needed.
1.3 Connection Points Position Connection points position.
1.4 External Check External environment required.
1.5 Requirements for Requirements for commissioning engineers.
Commissioning Engineers
1.6 Commissioning Items Commissioning items.

T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-1


OptiX OSN 7500
1 Preparations for Equipment Commissioning Commissioning Guide

1.1 Instruments and Tools


Table 1-2 shows the instruments and tools for commissioning.

Table 1-2 Instruments and tools for commissioning


Name Used for …

SDH analyser Testing multiplex section switching time, frequency deviation and
jitter at optical or electrical interfaces, and so on.
Optical power Testing the actual received optical power, receiver sensitivity, and
meter receiver overload at optical interfaces.
Fixed attenuator Attenuating strong optical power received at optical interfaces to
avoid damage.
Laptop computer NE commissioning and Ethernet indexes test.
Multimetre Testing voltage, resistance, current intensity.
Fibre jumper Transfer during optical power test of optical interfaces at the ODF
side.
BER tester Testing bit errors at electrical interfaces.
Adjustable Testing receiver overload at optical interfaces and testing receiver
attenuator sensitivity.
Data analyser Testing Ethernet services.
ATM analyser Testing ATM services.

1-2 Huawei Technologies Proprietary T2-040439-20060320-C-1.50


OptiX OSN 7500
Commissioning Guide 1 Preparations for Equipment Commissioning

1.2 Engineering Information


Engineering information includes:
„ Networking diagram
„ IP address allocation diagram
„ Board layout of each NE
„ Fibre and cable connection table
„ Timeslot allocation diagram
„ Board level protection information
„ Clock tracing diagram
„ Orderwire diagram

T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-3


OptiX OSN 7500
1 Preparations for Equipment Commissioning Commissioning Guide

1.3 Connection Points Position


EU08 OU08 MU04 TSB8 D34S D75S ETF8 EFF8 ETS8

5 4 13 6 14 12 15 12

Interface board

19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

GXCS

GSCC EOW AUX

20 29

21 30
22
23 31
32
24
33 PIU

16 25 34
35
17 36
26 18

37 19
27
28

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Processing board
SL64 SL16 SL4 SLH1 SLT1 SEP1 SL1 PQ1 PL3A SPQ4 LWX MR2A BPA EGT2 EFS0 EGS2 EMR0 ADL4

1 2 3 4 5 4 6 7 8 9 10 11 11 11 12 3

Figure 1-1 Connection points position of OptiX OSN 7500

1-4 Huawei Technologies Proprietary T2-040439-20060320-C-1.50


OptiX OSN 7500
Commissioning Guide 1 Preparations for Equipment Commissioning

Table 1-3 Numbering and functions referred to the connection points


Access Point Position Function Description Connection Type
Number (Note)

1 T2SL64 Optical stm-64 connections LC


2 N1SL16, N2SL16 Optical stm-16 connections LC
3 N1SL4, N2SL4, ADL4 Optical stm-4 connections LC
4 N1SL1, N2SL1, N1SLT1, Optical stm-1 connections LC
N1OU08, N2OU08
5 N1SEP1 140 Mbit/s and STM-1 Electrical SMB
Connections
6 N1PL3A, N1D34S 34 and 45 Mbit/s Electrical SMB
Connections
7 N1LWX 10 Mbit/s to 2.5 Mbit/s Optical LC
Connection at WDM side
8 N1LWX 10 Mbit/s to 2.5 Mbit/s Optical LC
Connection at client side
9 N1MR2A Adding/Dropping and Multiplexing LC
Any Adjacent Two Channels
Connections
10 N1BPA Optical booster amplifier connections LC
11 N1EGT2, N2EGS2, Optical 1000Base-SX and LC
N2EMR0 1000Base-LX Connections
12 N1EFT8, N1EFS4, Fast Ethernet access connections RJ-45
N1ETS8, N2EMR0
13 N1MU04 140 Mbit/s and STM-1 Electrical SMB
Connections (access unit)
14 N1D75S 2 Mbit/s Electrical Connections 2mmHM (75
ohm)
15 N1EFF8 Optical fast Ethernet access LC
connections
16 N2GSCC Reset button Button
17 N2GSCC Alarm cut switch Button
18 T1PIU 50 w power output connections Common
socket–4 pin
19 T1PIU -48 v power access connections DB3
20 T1EOW 75-ohm clock connections 1 SMB
21 T1EOW 120-ohm clock connection 2 RJ-45

T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-5


OptiX OSN 7500
1 Preparations for Equipment Commissioning Commissioning Guide

Access Point Position Function Description Connection Type


Number (Note)

22 T1AUX Extended subrack connection RJ-45


23 T1EOW Orderwire connection RJ-45
24 T1EOW Outgoing subnet orderwire RJ-45
connections
25 T1EOW OAM connection RJ-45
26 T1EOW Serial signal connections RJ-45
27 T1EOW COM commissioning Connection RJ-45
28 T1EOW T2000 connection RJ-45
29 T1AUX 75-ohm clock connections 3 SMB
30 T1AUX 120-ohm clock connection 4 RJ-45
31 T1AUX F&f Connection RJ-45
32 T1AUX F1 connection RJ-45
33 T1AUX Cabinet alarm indicator output RJ-45
connection
34 T1AUX Cabinet alarm indicator input RJ-45
concatenation connection
35 T1AUX Alarm concatenation connection RJ-45
36 T1AUX Alarm output connection RJ-45
37 T1AUX Alarm input connection RJ-45
Note: The number in the first column is corresponding to the number in the ring in Figure 1-1.

1.4 External Check


Confirm the following items in advance.

„ The hardware installation check is complete.


„ The T2000 is ready.
„ The T2000-local craft terminal (T2000-LCT) is ready in the laptop.
„ All equipment on each NE has active and standby power supplies. Check
whether alarms need to be output.
„ The interface impedance (75 ohms or 120 ohms) of the DDF on each NE is the
same as that of tributary boards and tributary interface boards.
„ Clock protection is provided. The setting of the clock board is correct. To
achieve clock protection switching, it is required to provide synchronisation

1-6 Huawei Technologies Proprietary T2-040439-20060320-C-1.50


OptiX OSN 7500
Commissioning Guide 1 Preparations for Equipment Commissioning

state message bit (SSMB) in the 2 Mbit/s clock signal and the location of that
message.

1.5 Requirements for Commissioning Engineers


Before using this manual, commissioning engineers should have received training
on optical equipment commissioning and be skillful at using various test tools. The
requirements are as follows.
„ Be familiar with the fundamentals of SDH, PDH, Ethernet, and ATM.
„ Be familiar with the equipment.
„ Be skillful at using the T2000 for service configuration.
„ Be skillful at using the LCT for service configuration.
„ Be skillful at using test tools (for SDH, PDH, Ethernet, and ATM).

T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-7


OptiX OSN 7500
1 Preparations for Equipment Commissioning Commissioning Guide

1.6 Commissioning Items


Table 1-4 lists the testing items.

Table 1-4 Testing items


Item Sub-item

NE Checking hardware
commissioning
Testing and powering on cabinet
Testing subrack functions
Accessing the equipment through the NM
Testing the RESET button
Testing the centralised alarm processing system
Testing the software version
Configuring service for testing
Testing optical or electrical interface indexes
Testing the electrical interfaces connection
Testing the fibre jumper connection
Testing the TPS of electrical interface
Testing the active/standby board switching
Testing bit errors on an NE
Testing the intra-station ECC
Backing up the NE database
Testing NE restarting after power failure
End of commissioning

1-8 Huawei Technologies Proprietary T2-040439-20060320-C-1.50


OptiX OSN 7500
Commissioning Guide 1 Preparations for Equipment Commissioning

Item Sub-item

Network Testing network-wide fibre connection


commissioning
Testing ECC routing
Checking the network-wide software version
Testing service channel availability
Testing Ethernet services
Testing self-healing protection switching
Testing clock protection switching
Testing orderwire
Testing network-wide BER
Other tests
Configuring the services
T2000 function verification

T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-9