Sie sind auf Seite 1von 11

A Quality Cost Model to

Determine Optimal Policies for


Purchased Components
EDWARD D. ARNHEITER, RENSSELAER POLYTECHNIC INSTITUTE
RICHARD J. GIGLIO, UNIVERSITY OF MASSACHUSETTS
© 1998, ASQ

This study develops a technique for predicting pur-


chasing quality costs and studying their behavior as INTRODUCTION
random variables. The resulting model extends prior In the literature, the term quality costs refers to costs
research that treats purchasing costs deterministically incurred when: recovering from or repairing a defect
or not at all, thereby providing a valuable decision
and planning tool for companies that are placing an
(failure costs); detecting defects (appraisal costs);
increasing reliance on purchased components. The and avoiding defects (prevention costs). Prevention
model was tested in the field at a small defense con- and appraisal costs are discretionary because the
tractor. Test results suggest that purchasing costs can amount to be spent in each category can be predeter-
be reduced by using the model to select the lowest cost mined and budgeted. Failure costs are called conse-
policy from a set of three alternatives. quential because their levels are a result of how much
Key words: purchasing quality costs, random vari- the organization chooses to spend on appraisal and
ables, simulation prevention. An understanding of these costs has
strongly influenced manufacturing policies: for exam-
ple, placing a greater emphasis on prevention so as to
avoid failure and detection costs (Hsiang and Lee
1985; Juran and Gryna 1993; Godfrey and Pasewark
1988). Quality costs occur both in parts that are pur-
chased and those that are manufactured onsite. The
American Society for Quality (ASQ) has adopted the
above terminology, and it has become the internation-
ally accepted framework for discussing quality costs.
Specific elements of each of these costs are suggested
by Campanella (1990) and Riahi-Belkaoui (1993).
The trend in many industries is to purchase a larg-
er proportion of components, rather than manufacture
them inhouse. Because of this increased reliance on
purchased components, the study of purchasing quali-
ty costs becomes correspondingly important. There is
relatively little literature related to purchasing quality
costs. Therefore, this study develops mathematical
expressions for purchasing failure costs and purchas-
ing appraisal costs for several different policy alterna-
tives. Corrective action costs are also included in the
model in order to capture one element of purchasing

54 QMJ 98 5, NO. 3/© 1998, ASQ


A Quality Cost Model to Determine Optimal Policies for Purchased Components

prevention. Other purchasing prevention costs such as One classic approach is the Deming k1, k2 model
supplier surveys, rating systems, and supplier quality (1982), which demonstrates that an all-or-nothing
planning are more difficult to quantify and are not policy toward inspection is always less expensive than
considered in this paper. acceptance sampling, provided that the process is sta-
Important quality cost inputs are treated as random ble and under statistical control. Juran and Gryna
variables, with probability distributions estimated from (1993) take a similar approach, except they assume
historical data wherever possible. This model, called the the cost to replace a defective item found at inspection
purchasing quality cost (PQC) model, explicitly consid- is borne by the producer, or is small compared to the
ers inspection, and is particularly applicable to products damage or inconvenience caused by the defective item.
used in critical applications where safety of the end user Therefore, their model assumes no replacement of
is the primary concern. In these situations some form of nonconforming units and ignores scrap or rework costs
product inspection will always be appropriate. associated with rejected lots. As in the Deming model,
the expected cost of each alternative relies on an esti-
mate for the probability of acceptance and rejection of
EXISTING QUALITY COST the lot. Case, Schmidt, and Bennett (1972) provide an
MODELS expression for the expected cost of acceptance sam-
pling similar to the sampling cost expression given in
For years, the common notion of quality cost behavior
the Juran and Gryna model, with two important excep-
has been described by the prevention-appraisal-failure
tions. First, Case, Schmidt, and Bennett assume that it
(PAF) model, which assumes that product perfection is
is uneconomical to sort rejected lots, so instead they
not possible. Therefore, the best business strategy is to
are scrapped completely. In addition, the proportion of
seek an optimal balance between discretionary costs
nonconforming product in the lot (p) is treated as a
(prevention plus appraisal) and consequential costs
random variable, with the frequency distribution deter-
(internal and external failures) that minimizes the
mined from empirical data.
total quality costs. Over the past two decades, leaders in
Godfrey and Pasewark (1988) consider opportunity
the field of quality have demonstrated that in many
costs, long-term market effects, and relationships
instances it is possible to reach perfection at a finite
among costs that affect total quality costs.
cost (Juran 1986), and a model that supports this
Krishnamoorithi (1986) investigates the quantitative
notion of achievable perfection has been developed.
relationship among the four components of quality
cost by using data from 23 quality systems, taken pri-
The PQC model was developed for purchasing marily from published literature. Using nonlinear
quality costs, but the techniques discussed here regression analysis, Krishnamoorithi develops expres-
could certainly be used to develop models that sions for internal and external failure as functions of
include additional quality costs. prevention and appraisal. These functions are used to
assist with quality investment decisions and to justify
improvement projects.
The traditional and the emerging models illustrate Freeman (1995) combines the cost of quality
the theoretical quality levels that minimize total quali- (COQ) concept with the Taguchi loss function in a
ty costs. They represent opposing viewpoints about large-scale Monte Carlo simulation. The purpose of his
which quality level (based on conformance) is opti- model is to show which manufacturing process has the
mal. Neither model, however, is of much use to the most potential for quality cost savings, and to provide a
quality practitioner trying to actually plan spending structured method for measuring the effect of reducing
levels that minimize total quality costs. To that end process variability. Using data from an actual manu-
management decision tools, designed to aid with qual- facturing firm as an example, the simulation suggests
ity cost planning, have also been developed. that by introducing a new test station and reducing the

E. D. ARNHEITER, R. J. GIGLIO/© 1998, ASQ 55


A Quality Cost Model to Determine Optimal Policies for Purchased Components

Table 1 Summary of existing quantitative models.


Author Basic approach and features What the model estimates Quality costs included

Case, Schmidt, Utilizes Pa . Treats the lot Expected cost of (n, c ) • Inspection cost
and Bennett proportion defective (p) as sampling. • Scrap cost (all rejected lots are scrapped)
(1972) a random variable. • Damage cost

Deming Utilizes Pa in (n, c ) sampling Expected cost of • Inspection cost


(1982) cost expression. Includes cost • (n, c ) sampling • Cost to disassemble and reassemble a
to find good replacements. • No inspection bad assembly (combination of internal
• 100% inspection and external failure costs)

Krishnamoorithi Uses nonlinear regression to Total quality costs as a Aggregate values for
(1986) develop expressions for internal percent of sales. • Appraisal
and external failure as functions • Internal and external failure
of prevention and appraisal. • Prevention

Godfrey and Uses historical cost data and Total quality costs • Rework
Pasewark focuses on relationships • Lost profit
(1988) between the cost categories. • Processing customer returns
No probability used. • Cost of lost sales
• Prevention and appraisal (lumped as
defect control costs)

Juran and Gryna Utilizes Pa in (n, c ) sampling Expected cost of • Inspection cost
(1993) cost expression. Ignores cost to • (n, c ) sampling • Damage cost if bad item slips through
find good replacements, and • No inspection inspection
scrap or rework associated with • Inspection
rejected lots. Includes cost to
sort rejected lots.

Freeman Simulates losses due to departures Total of Taguchi loss • Loss to society (using TLF)
(1995) from target dimension using TLF function, warranty costs, • Inspection cost
and adds expected costs of and all costs associated • Warranty cost
inspection and warranty. Includes with either (n, c ) sampling • Scrap and rework cost
inspection of reworked units, or 100% inspection. • Cost of production lost when process

© 1998, ASQ
and cost to find good needs adjusting
replacements. • Cost of process adjustment

variation of an operation, a reduction in the overall None of the existing quantitative models treats
quality cost per unit could be realized. quality costs as random variables. Case, Schmidt, and
A summary of the basic approach and assumptions Bennett (1972) treat the proportion nonconforming
of each quantitative quality cost model, along with the (p) as a random variable, but consider cost parameters
nature of the estimates generated, is shown in Table 1. to be deterministic. Freeman (1995) only incorporates
randomness in the value of the quality characteristic
THE PQC MODEL itself (for example, hole diameter). The PQC model
treats purchasing quality costs as random variables
The review of the existing COQ literature highlights
and realistically captures many of the major purchas-
some deficiencies. First, although numerous theoreti-
ing quality cost elements. The model considers the
cal quality cost models have been developed, there is a
expected cost of three alternative policies.
shortage of research demonstrating their application
1. Incoming evaluation of components
using empirical data. In addition, no one has focused
on the nature of purchasing quality costs, despite their 2. Evaluation of components at the supplier
impact on modern supply chain management prac- 3. Waiving of product evaluation with a review of sup-
tices. In contrast, the PQC model captures quality costs plier data only
uniquely associated with purchased components, such The cost of off-site evaluation (at the supplier), as an
as shipping and travel costs. alternative to incoming evaluation, has not been

56 QMJ 98 5, NO. 3/© 1998, ASQ


A Quality Cost Model to Determine Optimal Policies for Purchased Components

Table 2 How parameters of PQC model relate to purchasing quality cost elements.
Purchasing quality cost element Symbol Description of included cost

Purchasing prevention costs

Corrective action Ca • Failure analysis and investigations into the cause of


supplier rejects

Purchasing appraisal costs

Incoming evaluation and tests k • Unit inspection cost


Source evaluation and control programs T • Travel costs to supplier
Cd • Cost to review supplier data
k • Unit inspection cost
Measurement equipment • Not in model
Qualification of supplier product • Not in model

Purchasing failure costs

Purchased material reject disposition M • Dispositioning costs


Costs S • Scrap costs
Purchased material replacement costs s • Shipping costs to return parts (when not paid for by supplier)

© 1998, ASQ
Rework of supplier rejects ra • Unit rework cost at assembly
Uncontrolled material losses • Not in model

considered in previous literature. The cost parameters Lots rejected during incoming evaluation have
used in the PQC model relate to the major cost two possible routings depending on their production
elements of the purchasing quality cost classification priority. When parts are not urgently needed, the
system, as shown in Table 2. model will include the expected shipping cost to
return the lot to the supplier. When parts are required
Primary Assumptions of the to fill immediate production needs, the model

PQC Model includes the expected in-house sorting costs. In addi-


tion, it is assumed that if a system fails in the field it
As with all quantitative models, important assumptions is most likely due to deficiencies caused at assembly,
were required to develop the PQC model. These or by a poor design, not because of defective pur-
assumptions can be summarized as follows: chased components. This is certainly not always the
• No inspector error exists. case, but it is a realistic assumption for many defense
companies and others who perform numerous tests
• Acceptance sampling is by attributes.
on all subassemblies as well as the final system prior
• Lots rejected during source evaluation are reworked to releasing it to the customer.
or replaced by suppliers. Expressions for the expected cost of incoming eval-
• A source examiner typically selects a smaller sample uation (EC I ), expected cost of source evaluation
than the customer’s incoming department. (ECS ), and the expected cost of waiving evaluation in
favor of data review (ECW ) were developed. The PQC
• Nonconforming components not caught by incom-
model is shown in Table 3. It provides expressions for
ing or source evaluation will usually be discovered
expected costs, as well as summaries of the notation
at assembly or test.
used and the primary assumptions of each expression.
• At assembly, nonconforming components are either The PQC model was developed for purchasing quality
reworked, scrapped, or used as is; that is, they are costs, but the techniques discussed here could certainly
not sent back to the supplier. be used to develop models that include additional
• No provision is made for the cost of finding good quality costs. Mathematical details of the model devel-
replacements. opment are given in the appendix.

E. D. ARNHEITER, R. J. GIGLIO/© 1998, ASQ 57


A Quality Cost Model to Determine Optimal Policies for Purchased Components

Table 3 Expressions for expected costs as defined in the PQC model.


Approach Expected cost expression Notation Assumptions

Sampling Using incoming evaluation: Ca  cost of corrective action (per lot) Bad units found at supplier are
Cd  unit cost to review supplier data reworked or replaced by supplier,
nI k  [(N  nI) (pr ra  ps S)  F  production priority factor (0 or 1) at no cost to customer. Bad units
M]p Pa I  (1  Pa I [(1  F)(s)  k  unit cost of inspection caught at incoming are either
(Ca  M)  Fk (N  nI)] L  number of lots evaluated during visit sorted by customer or returned to
M  disposition costs (per lot) vendor. Bad units making it to
Using source evaluation: pr  probability component can be reworked assembly are either reworked,
ps  probability component needs scrapping scrapped, or used as is. No
ns k  [(N  ns) (pr ra  ps S)  ra  unit cost to rework at assembly provision for finding good
M]p Pas  Cd (nI  ns)  (T/L) s  shipping costs to return lot to supplier replacements.
(for nI  ns) S  unit cost to scrap component
T  travel costs to supplier

Waiving nd  size of supplier data review Bad units found at assembly are
product Cd  unit cost of data review either reworked, scrapped, or
evaluation p [N (pr ra  ps S)  M]  pr  proportion of time we can rework used as is. Even though we do
Cd nd ps  proportion of time we must scrap unit not inspect the units, we still
ra  unit cost to rework at assembly review vendor data.

© 1998, ASQ
S  unit scrap costs
M  disposition costs (per lot)

Table 4 Rules used when selecting input probability distributions for the PQC model.
Probability distribution (@RISK PQC model
functions shown in all caps) Applications Data type parameters

BETASUBJ (minimum, most likely, A heuristic procedure for rough modeling when Continuous p
mean, maximum) actual data are absent. Real-world data indicate that
density functions corresponding to time to complete
Note: a task often have this shape, skewed to the right.
Most likely = mode Also useful for distribution of a random proportion
such as proportion of defective items in a shipment.

DISCRETE ({x1,...xn},{p1,...pn}) For situations with a discrete number of outcomes. Discrete F, L, N, M


For each possible x value, an empirical mass function
p(x) is defined by specifying the proportion of Xi s
equal to x.

HISTOGRM (minimum, maximum, Distribution for grouped data, approximation of Continuous k, ra


{p1,...pn}) arbitrary probability distribution, graphic
approximation of a distribution.

TRIANG (minimum, most likely, Used as a rough model in the absence of data Continuous Cd, S, s
maximum) (heuristic procedure).

Dependency Parameters that have dependency relationships Continuous nI (depends on N)


with other parameters. or discrete n d (  n I)
ns (70% of nI)
c (0 to 1, depends on nI)

Deterministic For parameters whose values are known, or are Continuous T, Ca , pr , ps


© 1998, ASQ

assumed to be some fixed value. Values often or discrete


depend on which supplier is being analyzed.

58 QMJ 98 5, NO. 3/© 1998, ASQ


A Quality Cost Model to Determine Optimal Policies for Purchased Components

SUMMARY OF PROBABILITY utilizing only a few simple distributions for parameter


estimation. Simple probability distribution functions
FUNCTIONS USED IN THE are often very powerful because uncertainty in the
model can be described with only a few values or argu-
SIMULATION ments.
One of the drawbacks with even relatively simple quan- The input distributions used in the PQC model are
titative models is that, in practice, the values of the summarized in Table 4. Each parameter in the model
model parameters are frequently difficult to estimate. is listed in the right-hand column, in the row corre-
For this reason a “rule-of-thumb” was developed, sponding to the approach used for estimating.

Figure 1 The PQC spreadsheet model with @RISK distributions shown.

A B C D E F G
1

5 Parameter estimates used


Symbol Costs are for supplier code B
6 Minimum Most likely Mean Maximum

7 N RiskDiscrete (N!I6:I41,N!J6:J41)

8 ns VLOOKUP (C7,ns!B8:E30,4)

9 nI VLOOKUP (C7,nI!B5:C27,2)

10 nv C9

11 c IF (C9   13,1,0)

12 L RiskDiscrete (L!I6:I16,L!J6:J16)

13 p RiskBetaSubj (D13,E13,F13,G13) 0.02 0.025 0.03 0.05

14 pr 0.300

15 ps 0.100

16 F RiskDiscrete ({0,1},{0.3,0.7})

17 Cd RiskTriang (D17,E17,G17) 15 16 20

18 M RiskDiscrete ({100,160},{0.4,0.6})

19 s RiskTriang (D19,E19,G19) 22 41 59

20 Ca $100

21 ra RiskHistogrm (ra!B7,ra!C7,ra!D7:S7)

22 T $50

23 k RiskHistogrm (k!B7,k!C7,k!D7:O7)

24 S RiskTriang (D24,E24,G24) $ 10 $ 100 $ 1000

25 EC I C9 * C23  ((C7C9) * (C14 * C21  C15 * C24)  C18) * C13 * BINOMDIST (C11,C9,C13,TRUE) 
(1BINOMDIST (C11,C9,C13,TRUE)) * ((1C16) * C19  (C20  100)  C16 * C23 * (C7C9))

26 EC s C8 * C23  ((C7C8) * (C14 * C21  C15 * C24)  C18) * C13 * BINOMDIST (C11,C8,C13,TRUE )
© 1998, ASQ

C17 * (C9 C8)  (C22/C12)

27 EC w (C7 * (C14 * C21  C15 * C24)  C18) * C13  (C17 * C10)

E. D. ARNHEITER, R. J. GIGLIO/© 1998, ASQ 59


A Quality Cost Model to Determine Optimal Policies for Purchased Components

Empirical distributions were used whenever actual Sufficient iterations are performed to develop probabili-
data were available. When data were lacking, but sub- ty distributions of the costs.
jective estimates of the minimum, mode, mean, and Figure 1 shows the PQC model as it was incorporated
maximum could be gathered, then either the beta or within an Excel spreadsheet. The actual cell contents are
triangular distribution functions were used. displayed so that the reader may see how the @RISK
probability distribution functions were integrated.

SIMULATING THE PQC MODEL


The PQC model is incorporated into an Excel spread- Results of the Simulation
sheet, which serves as a platform for running the simu- Results of the simulation for several selected suppliers of
lation and sensitivity analysis. Cells designated for Acme Company are shown in Table 5. (Note: the name
input parameters contain three different types of of the company has been disguised at its request.) For
entries: (1) constants if the parameters were treated each supplier, 1000 iterations of the PQC model were
deterministically; (2) probability distributions if the performed with a total run time of three to four minutes,
parameters were handled stochastically; or (3) refer- utilizing a 486 DX-33 system with 16 MB of RAM.
ences to other cells if there was a dependency relation- During the simulation analysis it became apparent these
ship between variables. Simulations were conducted were the minimum system requirements for running
using @RISK (Palisade Corporation 1996), which pro- such a complex model with the @RISK program.
vides a tool for introducing random variables within Histograms of the results show the vast majority of
the Excel framework, an environment with which most the simulated cost values falling within a fairly narrow
users are familiar. For parameters that are random window. For example, for supplier B, 64 percent of the
variables, @RISK selects sets of values from the user- incoming evaluation expected costs and 51 percent of
specified probability distribution functions, and the the source evaluation expected costs were less than
worksheet is then recalculated using the new values. $50, while 77 percent of the costs associated with the

Table 5 Simulation results for 1000 iterations of the PQC model.


Supplier A Supplier B Supplier C
Std. Std. Std.
Min. Mean Max. Dev. Min. Mean Max. Dev. Min. Mean Max. Dev.
ECI $1 $ 102 $ 1275 151.82 $3 $ 58 $ 828 72.69 $ 13 $ 62 $ 176 28.62

ECs $6 $ 94 $ 776 98.15 $6 $ 61 $ 627 52.84 $ 144 $ 453 $ 813 254.92

ECw $8 $ 37 $ 129 27.05 $4 $ 20 $ 264 22.03 $ 35 $ 46 $ 64 4.59

N 1 10.73 39 9.39 1 5.37 84 8.85 3 3.67 5 0.769

L 1 3.82 16 3.90 1 4.45 12 3.32 1 2.75 6 1.80

p 0.001 0.015 0.025 0.006 0.000 0.015 0.025 0.006 0.020 0.030 0.049 0.006

F 0 0.72 1 0.449 0 0.68 1 0.466 0 0.71 1 0.456

Cd $ 5.08 $ 7.40 $ 9.96 1.042 $ 3.09 $ 5.00 $ 6.82 0.796 $ 15.13 $ 17.07 $ 19.87 1.10

M $ 100 $ 136 $ 160 29.43 $ 100 $ 136 $ 160 29.41 $ 100 $ 136 $ 160 29.32

s $23.17 $ 40.96 $ 58.58 7.63 $ 23.27 $ 40.81 $ 58.51 7.49 $ 23.10 $ 40.67 $ 58.41 7.49

ra $ 0.00 $ 17.52 $ 64.81 15.35 $ 0.01 $ 21.79 $ 92.89 18.40 $ 0.03 $ 22.01 $ 79.60 18.32
© 1998, ASQ

k $ 0.00 $ 21.49 $ 119.89 26.00 $ 0.02 $ 20.44 $ 99.50 21.29 $ 0.13 $ 20.53 $ 73.99 13.81

S $ 131 $ 602 $ 1165 219.35 $ 238 $ 811 $ 1468 265.75 $ 115 $ 601 $ 1192 228.91

60 QMJ 98 5, NO. 3/© 1998, ASQ


A Quality Cost Model to Determine Optimal Policies for Purchased Components

waiver policy were less than $20 (see Figures 2, 3, and determining expected costs in the PQC model. Any
4). This knowledge would likely convince manage- sensitivity study has two aspects.
ment to consider doing less component inspection in 1. What is the rate of change of the variables with
favor of a thorough supplier data review. Similar respect to the output?
results were found for suppliers A and C. The stipula-
2. How statistically significant are these rates of
tion that nonconforming components are caught at
change?
assembly or systems test, and, therefore, should not
reach the hands of the customer, makes the waiver Figure 3 Histogram for ECs (supplier B).
policy even more attractive.
After examining additional suppliers using the PQC Expected cost of source evaluation
model, Acme reached three important conclusions 4000

regarding its purchased parts programs. First, to make


327
source evaluation more cost competitive, the company
300
would need to sharply increase the number of lots
246
checked during trips to nonlocal suppliers. Second, for

Frequency
local suppliers with poor quality, source evaluation is 200 180
the lowest cost alternative. The third conclusion Acme 139
drew from the simulation is that for local suppliers
100
with better quality (that is, average p = .015), waiving
42
component evaluation in favor of a supplier data 24
review is the optimal policy. 0
0.

50

10

15

20

25

30

35
0–

.0

0.

0.

0.

0.

0.

0.
25

0–

0–

0–

0–

0–

0–
–7

SENSITIVITY ANALYSIS
5.
.0

17

27

37
22
12

32
0

5.

5.

5.
5.
5.

5.
0

0
0
0

© 1998, ASQ
Standard deviation = 52.86
Sensitivity analysis was used to identify the input Mean = 60.9
N = 1000.00
distributions that are significant or critical inputs for

Figure 2 Histogram for ECI (supplier B). Figure 4 Histogram for ECw (supplier B).

Expected cost of incoming evaluation policy Expected cost of waiving product evaluation
4000 600
357 533
5000

300 283
400
Frequency

Frequency

200 300
141 233
200
100
69 114
41 33 100
24
36
0
0
0.

50

10

15 125

20

25 225

30

35 325
0–

0.

20

40

60

80

10

12

14 130
.0

0.

0.

0. 5.0

0.

0. 5.0

0.
25

0–
0–

0– 0

0–

0– 0

0–

0– 0

.0

.0

.0

.0

0.

0. 0.0

0.
75

10
.0

37

0–

0–

0– 0
–3


–5
.0

70
7

90
0.
.0

11

15
5.

0.

.0

.0
.
.

0
0

0.
© 1998, ASQ

Standard deviation = 72.73


© 1998, ASQ

Standard deviation = 22.04


Mean = 58.0
Mean = 20.1
N = 1000.00
N = 1000.00

E. D. ARNHEITER, R. J. GIGLIO/© 1998, ASQ 61


A Quality Cost Model to Determine Optimal Policies for Purchased Components

To address the first aspect of sensitivity analysis, Table 7 Simulation sensitivities by supplier.
@RISK includes multivariate stepwise regression rou-
Normalized regression coefficients
tines that enable the determination of the relative
effect of model parameters on cost. In the case of the Parameter Supplier A Supplier B Supplier C

PQC model, this procedure is essentially being used to ECI N 0.4714 0.5747 0.0721
k 0.6762 0.6535 0.9966
identify critical input variables. The idea is that once p 0.0974 0.0869 0.1453
these critical variables are identified, they can become S 0.0000 0.0345 0.0366
the focus of attention when using the PQC model for ra 0.0000 0.0000 0.0111
F 0.0402 0.0000 – 0.0084
planning purposes. M 0.0000 0.0000 0.0285
The second question implies that when interpreting s 0.0000 0.0000 0.0041
the simulation results it is first necessary to validate the ECs N 0.4900 0.6022 0.0000
model and the sensitivity study. The method used here k 0.6223 0.5540 0.0395
S 0.0000 0.0642 0.0000
was to look at the regression R2 values. Any values L – 0.1577 – 0.2542 – 0.8895
below 0.60 represent unstable reported sensitivity statis- ra 0.0000 0.0000 0.0000
p 0.0708 0.0591 0.0000
tics, in which case running the simulation again with M 0.0000 0.0000 0.0000
the same model could yield a different ordering of Cd 0.0000 0.0000 0.0000
input sensitivities. Table 6 contains the R2 values for ECw N 0.9344 0.9175 0.3375
three of Acme’s key suppliers. Since these values are all S 0.1245 0.1118 0.5472
p 0.1727 0.1566 0.5117
relatively large (most are above 0.7), the regression Cd 0.1412 0.0871 0.4858

© 1998, ASQ
coefficients can be used as measures of sensitivity. ra 0.0000 0.0231 0.1329
M 0.0290 0.0000 0.1948
Table 6 Coefficients of multiple determination (R2)
for the PQC model.
The expected cost of waiving inspection (EC W )
Output exhibits more variability between suppliers in terms of
Source Expected cost critical parameters. Lot size (N) is one of the three
Incoming evaluation of waiving
Supplier expected expected component most significant inputs for all suppliers except supplier
costs costs evaluation C. This is likely due to the fact that N for supplier C has
A .69565 .67042 .91719 a standard deviation of only 0.769. This is the smallest
value of all three suppliers. In general, the Acme lot
© 1998, ASQ

B .74446 .73435 .89532


size data exhibit large variability, which increases vari-
C .99826 .79544 .96524
ability of the model output, and is a contributing factor
Summary results of the normalized regression coef- to the critical nature of parameter N. Parameter p is
ficients for all three suppliers are shown in Table 7. critical for all suppliers, which intuitively makes sense
Here, the top three critical parameters are shown in in this case because product evaluation is being waived
bold type. As an example of sensitivity analysis for sup- and expected costs are, therefore, largely influenced by
plier B, parameter k had the largest impact on the the probability that the lot contains a nonconforming
value of incoming expected costs with a sensitivity of component. The third critical variable differs by suppli-
0.6535; N had the second largest impact at 0.5747; and er, with either S or Cd winning out.
so on. This can be interpreted to mean that an increase The results of a sensitivity analysis can also be
of 0.6535 standard deviation of k, leads to +0.6535 graphically summarized using a tornado graph, such
standard deviation change in the output (that is, as the type shown in Figure 5. This chart shows the
incoming expected costs in this case). For incoming coefficient values for regression sensitivities associated
expected costs the dominant parameters (ECI ) are N, with supplier B, using the source evaluation output
k, and p. For source evaluation (ECS ), the critical variable. The length of the bars for each input parame-
parameters are N, k, and L. ter is proportional to the calculated coefficient values.

62 QMJ 98 5, NO. 3/© 1998, ASQ


A Quality Cost Model to Determine Optimal Policies for Purchased Components

Figure 5 Regression coefficients for supplier B (ECs ).


APPENDIX: MATHEMATICAL
Regression sensitivity for ECs
N (.602)
DETAILS OF THE PQC MODEL
Much of the notation needed to develop the PQC model
k (.554) is given in Table 3. Additional parameters not explicitly
L (–.254) defined there are as follows:
S (.064)

© 1998, ASQ
Number of items in the source evaluation sample  ns
p (.059)
Number of items in the incoming evaluation sample  nI
Number of items for which supplier data are reviewed  nd
–0.4 –0.2 0 0.2 0.4 0.6 0.8 1.0 Acceptance number  c
Probability that lot will be accepted by the source
Standard b coefficient
sampling plan  Pas
Probability that lot will be accepted by the incoming
sampling plan  PaI
CONCLUSION Also define a production priority factor (F) such that:


A model that explicitly represents purchasing quality 0 If there is time to send the rejected
costs and the probabilistic nature of cost elements has F = lot back to the supplier
1 If there is no time to send the rejected
been shown to be useful in guiding decisions regarding
lot back to the supplier
a company’s program for purchasing parts. When
computer simulation is combined with a quantitative By combining the inspection cost, acceptance cost, and
model for purchasing quality costs, it becomes possible rejection cost, an expression for the total expected cost when
performing incoming evaluations (ECI) can be developed.
to realistically compare the cost of alternative appraisal
policies regarding choice of suppliers, inspection poli- ECI  nI k  [(N  nI)(pr ra  ps S)  M] p 




cies, and supplier evaluation visits. This technique will


Appr. Purchasing failure cost
undoubtedly lead to more accuracy and confidence Cost incurred if we accept a lot
with the economic decision-making process. with p proportion defective.
The equations and framework developed in this
(1  F)(1  PaI)s  (1  PaI)(Ca  M)  Fk(N  nI)(1  PaI)
paper are valid for general use, providing the primary





assumptions of the PQC model are met. The actual We incur shipping We will always When F  1, parts
results of the simulation, however, will depend on com- only when F  0. have disposition must be sorted by
and corrective the customer.
pany cost data, values for other model parameters, and action.


the selected probability distributions. For example, at


Acme, local suppliers with poor quality were found to be Purchasing failure cost incurred if we reject the lot
best managed with source evaluation. This may not be (rejection cost).

the case with another company, but the objective would  nI k  [(N  nI) (pr ra  ps S)  M] p PaI 
remain the same: to find the best component supplier
(1  PaI)[(1  F)(s)  (Ca  M)  Fk(N  nI)]
based on total expected purchasing quality costs.
By expressing the probability of acceptance (Pi) using the bino-
mial cumulative distribution function, which gives the probability
of finding c or fewer nonconforming units in a sample of size n
with input quality p, the equation for ECI becomes:
c
ECI  nI k  [(N  nI)(pr ra  ps S)  M] p

y0
b(y;nI, p) 

c
[1 
y0
b(y;nI,p)][(1  F)(s)  (Ca  M)  Fk(N  nI)]

E. D. ARNHEITER, R. J. GIGLIO/© 1998, ASQ 63


A Quality Cost Model to Determine Optimal Policies for Purchased Components

Similarly, the complete expression for the expected cost of BIOGRAPHIES


source evaluation can be given as: Edward D. Arnheiter is an assistant professor in the Lally School
of Management and Technology at Rensselaer Polytechnic
ECS  ns k[(Nns)(pr raps S)M] p PasCd (nIns)(T / L)
Institute. Prior to beginning his academic career, Arnheiter spent
c 11 years in industry as an operations management practitioner,
 ns k  [(N  ns)(pr ra  ps S)  M] p 
y0
b(y;ns,p)  in both the defense sector and in consumer products manufactur-
ing. He held managerial positions with several major companies
Cd (nI  ns)  (T / L) including General Electric Defense Systems, Spalding Sports
Worldwide, and Titleist and Foot-Joy Worldwide.
The expected cost of the waiver policy can be expressed as:
Arnheiter has taught numerous courses in advanced quality man-
ECW  p[N (pr ra  ps S)  M]  Cd nd
agement, managerial statistics, and manufacturing systems man-
agement. He received a doctorate in industrial engineering and
operations research from the University of Massachusetts at
REFERENCES Amherst. He may be contacted at the Lally School of
Campanella, J., ed., and the ASQC Quality Costs Committee. Management and Technology, Rensselaer at Hartford, 275
1990. Principles of quality costs. Milwaukee: ASQC Quality Windsor Street, Hartford, CT 06120-2991; 860-548-2430; Fax:
Press. 860-547-0866; E-mail: arnheite@rh.edu .

Case, K. E., J. W. Schmidt, and G. K. Bennett. 1972. Cost-based Richard J. Giglio is a professor in the department of mechanical
acceptance sampling. Industrial Engineering (November): and industrial engineering at the University of Massachusetts at
26 – 31. Amherst. His research interests include economic analysis, cost-
ing, process analysis, and quality. Giglio has extensive industrial
Deming, W. E. 1982. Quality, productivity, and competitive experience in those fields, including full-time employment as a
position. Cambridge, Mass.: Massachusetts Institute of project manager and consultancies with 25 companies.
Technology, Center for Advanced Engineering Study.
Giglio has been the principal investigator of 20 major funded
Freeman, J. M. 1995. Estimating quality costs. Journal of the research projects. His publications include one book, more than
Operational Research Society 46, no. 6:675 – 686. 30 journal articles, and numerous conference proceedings. He
founded the first video-based master of science program in engi-
Godfrey, J. T., and W. R. Pasewark. 1988. Controlling quality
neering management to serve working engineers and managers,
costs. Management Accounting (March): 48 – 51.
and directed that program for 15 years.
Hsiang, T. C., and H. L. Lee. 1985. Zero defects: A quality costs
Giglio earned a Ph.D. in industrial engineering from Stanford
approach. Communications in Statistics — Theory and Methods
University. He may be contacted as follows: Mechanical and
14, no.11:2641 – 2655.
Industrial Engineering Department, University of Massachusetts
Juran, J. M. 1986. Optimum revisited. Quality Progress 19, no. at Amherst, Amherst, MA 01002; 413-545-0646; Fax: 413-
4:10. 545-1027; E-mail: giglio@ecs.umass.edu .

Juran, J. M., and F. M. Gryna. 1993. Quality planning and


analysis. 3d ed. New York: McGraw-Hill.

Krishnamoorithi, K. S. 1986. Predicting quality cost changes


using regression. In 1986 ASQC Quality Congress transac-
tions — Anaheim. Milwaukee: ASQC.

Palisade Corporation. 1996. @RISK, Advanced risk analysis for


spreadsheets. Newfield, N.Y.: Palisade Corporation.

Riahi-Belkaoui, A. 1993. Quality and control — An accounting


perspective. Westport, Conn.: Quorum Books.

64 QMJ 98 5, NO. 3/© 1998, ASQ

Das könnte Ihnen auch gefallen