Report
Project Name:
SITE ID,
NAME
SUPERVISOR
NAME
SUBCONTRAC
TOR
Page 1 of 8
DBS Hardware Installation Quality
Report
Page 2 of 8
DBS Hardware Installation Quality
Report
2 Antenna Installation
Sector 2:
Sector 3:
4Mechanical Tilt for each antenna
Sector 1:
Sector 2:
Sector 3:
5.Electriccal Tilt for each antenna
Sector 1:
Sector 2:
Sector 3:
Page 3 of 8
DBS Hardware Installation Quality
Report
Page 4 of 8
DBS Hardware Installation Quality
Report
4 Installation of RF Jumpers
Page 5 of 8
DBS Hardware Installation Quality
Report
5. Excess materials have been dully filled in Passed Failed
the MR and returned to the warehouse.
6. You have confirmed by calling NMC that Passed Failed
the sites has no alarms caused by your
presence in the site: before leaving the site.
7. There are no damages to the landlord’s, Passed Failed
Customer’s property and sites as you leave
the sites
Page 6 of 8
DBS Hardware Installation Quality
Report
8. The paint on the surface is intact. If any Passed Failed
paint is damaged, you must apply touch-up
paint to avoid erosion.
9. Filler panels are installed in the space Passed Failed
reserved for customer equipment
10. The cabinet door can be easily opened or Passed Failed
closed, the lock works properly, and the gag
lever post is secure.
11. All labels, tags, and nameplates are Passed Failed
correct, legible, and complete.
I.
Final Sign-off
Conclusion:
I declare that all the above report for each item has been confirmed by
physical inspection on site and that I will assume full responsibility for any
impact caused by misreporting of actual site status.
The site is complete and ready for cutover.
By Subcontractor: By Airtel:
Name:______________________________ Name:_____________________________
______ _______
Signature:__________________________ Signature:__________________________
_______ _______
Date:_______________________________ Date:______________________________
______ _______
Page 7 of 8
DBS Hardware Installation Quality
Report
Page 8 of 8