Faculty of Engineering
Time needed
Activity Predecessor
A - 2
B - 3
C A 4
3
D A,B
E C,D 8
3
F C
G E 2
H F,G 3
1
2. For the following activities draw activity on arrow (AOA) diagram:
Time
Activity description Predecessor
needed
A Build internal components - 7
Modify roof and floor 2
B A
Construct collection stack 3
C B
Pour concrete and install 4
D frame B
2
3. For the following activities draw activity on node (AON) diagram:
2. Calculate the project completion time, ES, EF, LS, LF and total float for each activity.
Mechanical design A - 7 -
Electrical design B - 8 -
Mechanical fabrication C - 6 -
Electrical fabrication D A 6 F.S
Mechanical subassembly E B 6 F.S
Electrical subassembly F B 8 F.S
Assembly fixation G C 4 F.S
Pipes and cables installation H D,E 7 F.S
Start up I F,G,H 3 F.S
2. Calculate the project completion time, ES, EF, LS, LF and total float for each activity.
3
5. The following table shows the different net cash flow values through the entire life of
three projects under consideration, Depending on the below mentioned table :
i. Evaluate these projects economically and decide the best project using NPV method (use
i= 10%.
ii. What he most profitable project using the internal rate of return approach.
iii. What is the most economic project using the payback period approach.