Sie sind auf Seite 1von 4

Misr International University – MIU

Faculty of Engineering

GEN 119: Engineering Project Management


Spring Term, 2019
Assignment – 1

[No assignments accepted after Deadline]

1. For the following activities draw activity on node (AON) diagram:

Time needed
Activity Predecessor
A - 2
B - 3
C A 4
3
D A,B
E C,D 8
3
F C
G E 2
H F,G 3

1. Determine different paths and & length

2. The critical path & min completion time

1
2. For the following activities draw activity on arrow (AOA) diagram:

Time
Activity description Predecessor
needed
A Build internal components - 7
Modify roof and floor 2
B A
Construct collection stack 3
C B
Pour concrete and install 4
D frame B

Install temperature sensor 1


E C
Build High temp-burner 4
F D
Install pollution control 2
G system B

Install air pollution device 4


H E,F
Inspect and test 2
I G,H

1. Determine different paths and length

2. The critical path & min completion time

2
3. For the following activities draw activity on node (AON) diagram:

Activity Predecessor Time needed Type of dependency


A - 6 -
B A 5 F.S
C A 6 F.S
D B 8 F.S
E B,C 3 F.S
F B,C 2 F.S
G D,E 9 F.S
H F 6 F.S

1. Determine different paths & the critical path.

2. Calculate the project completion time, ES, EF, LS, LF and total float for each activity.

3. Draw the Gantt chart

4. For the following activities draw activity on node (AON) diagram:

Description Activity Predecessor Time needed Type of dependency

Mechanical design A - 7 -
Electrical design B - 8 -
Mechanical fabrication C - 6 -
Electrical fabrication D A 6 F.S
Mechanical subassembly E B 6 F.S
Electrical subassembly F B 8 F.S
Assembly fixation G C 4 F.S
Pipes and cables installation H D,E 7 F.S
Start up I F,G,H 3 F.S

1. Determine different paths & the critical path.

2. Calculate the project completion time, ES, EF, LS, LF and total float for each activity.

3. Draw the Gantt chart

3
5. The following table shows the different net cash flow values through the entire life of
three projects under consideration, Depending on the below mentioned table :

Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

Project I -$16,000 5,000 8,000 9,000 12,000 10,000 12,000

Project II -$20,000 2,000 4,000 4,000 5,000 3,000 4,000

Project III -$18,000 5,000 8,000 9,000 12,000 10,000 12,000

i. Evaluate these projects economically and decide the best project using NPV method (use
i= 10%.
ii. What he most profitable project using the internal rate of return approach.
iii. What is the most economic project using the payback period approach.

Das könnte Ihnen auch gefallen