TRANSMISSION LINE SHUTDOWN IMPLEMENTATION FORM

NAME OF GRID OFFICE: Hetauda Grid Division, Hetauda


FOR: 2075 YEAR 08 MONTH 11 DATE
A. Shutdown Request (shutdown may be for User, Grid Owner or Both):
Shutdown Requested by: Er. Bikram K. Amatya (Division chief HGD )
Date Of Shutdown: 2075.08.11
Earliest start time:13:00 to 15:00
Latest completion Time: 2:00 hours
Description of work: Conductor Repairing in 132 KV Pathlaiya-Parwanipur Ckt. 1,2 Tower No. 5
&6
Location of work: 132 Kv Pathlaya-Parwanipur Ckt 1&2
Type of outage (scheduled or form):
Name the person approving the shutdown and date of approval:
In charge supervisor:Hari Pd.Adhikari Safety officer:- Er. Manoj Sha
B. Shutdown Placement

Step Time Description Of Operation (Insert User name) NEA


Disconnection at end-1…. Lock No. User No Lock No ISO

1 ….shall open Circuit Breaker


Disconnection at end –2….
2 ….shall open Circuit Breaker
3 ….shall open isolator
Disconnection at end-1….
4 …….shall open isolator..
Grounding
5 User shall close ground switch at end-
1
6 User shall close ground switch at end-
2

After step six implementing safety officer (ISO) shall inform user’s safety officer (USO) that shutdown has been effective and he
can authorize his personnel to work on his line. No personnel other then the personnel under the supervisor of the supervisor in-
charge are allowed to work on the line. The USO will hold the key for all isolator throughout the shut down and is the only
allowed to work on the line .The USO will hold the key for all isolator throughout the shutdown and is the only person that can
release the shutdown.
C. Shutdown Release
Step Time Description Of Operation ……………….. NEA
1 The User so shall remove the grounding switch at Lock User Lock ISO
end-1 and NEA personnel shall open the No So No
grounding switch at end -2
2 Verify CB is open at end-2
3 ISO shall remove the luck on isolator at end-2
and NEA personnel shall close isolator at end -2
4 Verify CB is open at end-1
5 The User so shall remove the Lock on isolator at
end-1 and operator shall close isolator at end –1
6 User so shall report the LDC that shutdown is
complete and system is ready for operation.
System is very normal operation after completion of shutdown and reconnection.
User Job In charge: NEA Job In charge: