Beruflich Dokumente
Kultur Dokumente
Sites Exam ............................................................................................................................................... 2
Materials ................................................................................................................................................. 2
SOIL ......................................................................................................................................................... 5
Concrete .................................................................................................................................................. 9
Management ......................................................................................................................................... 10
Survey .................................................................................................................................................... 20
ROADS ................................................................................................................................................... 20
Fluid ....................................................................................................................................................... 27
Structure ............................................................................................................................................... 29
GENERAL ............................................................................................................................................... 35
Solved Examples ................................................................................................................................... 36
STEEL ..................................................................................................................................................... 59
Collected by Eng: Hany El‐Halwany Page 1 of 63
Sites Exam
1. http://www.objectivebooks.com/2016/04/construction-planning-and-management.html?m=1
2. http://exam2win.com/civil-engineering/construction-planning-and-
management/part1/questions-answers-1.jsp
3. https://engineeringmcqs.blogspot.qa/2014/08/99-top-construction-planning-and.html
4. http://www.indiabix.com/civil-engineering/questions-and-answers/
5. http://highered.mheducation.com/sites/0072443901/student_view0/chapter18/problems_soluti
ons.html
6. http://www.freshbuddies.com/civil-engineering/Concrete%20Technology/001001
7. https://www.slideshare.net/SyedFarazJafri/civil-engineering-competitive-questions-42576400
8. https://www.slideshare.net/BRJROHIT/59105128-civilengineeringobjectivetypequestions
Materials
Volume of one bag cement = 50 Kg / 1440Kg/m3 = 0.035 m3
Le chatelier apparatus is used to carry out SOUNDNESS test OF CEMENT
What is the difference between stress and strength?
Stress is the internal forces developed in material due to external forces
Strength is Ability of material to resist external forces
Add-Mixture are used in concrete for Reduce heat of concrete and increase workability of
concrete
Type of Stress: Axial Stress, Shearing Stress, Bearing Stress and Longitudinal stresses
Poisson's Ratio define as lateral strain over longitudinal strain
The formWork including the props can be removed from beams after 14 days
Concrete slump recommended for foundations 50 to 100 mm
Concrete slump recommended for beams and slabs 30 to 125 mm
The construction joints in buildings are provided after 40 m
Entrained concrete is used in lining walls and roofs for making heat insulated and sound
insulated
Collected by Eng: Hany El‐Halwany Page 2 of 63
The last component added in process of making OPC concrete is Gypsum (Calcium Sulphate)
Slump Metal mould Dimensions: top internal diameter 4 in (100 mm), and bottom internal
diameter 8 in (200 mm) with a height of 1 ft (300 mm).
maximum compressive strength of Concrete after 7 days 65 % and after 14 days 90% and
after 28 days 100%
No of Cubes will be 6 Cubes every 100 m3 (3 will be test after 7 days and 3 after 28 days)
Moist curing of the exposed surfaces of concrete is done at least 7 days
No of slump test per each truck is 2
Workability of concrete mix with low water cement ratio is determined by compaction factor
test
Durability of concrete may be defined as the ability of concrete to resist weathering action,
chemical attack, and abrasion while maintaining its desired engineering properties.
Cement Density = 1440 kg/m3 –
While compacting the concrete by a mechanical vibrator, the slump should not exceed
Bleeding can be controlled in the concrete by adding Cement
Soundness of cement is the property by virtue of which the cement does not undergo any
appreciable expansion (or change in volume) after it has set, thus eliminating any chances of
disrupting the mortar or concrete
Collected by Eng: Hany El‐Halwany Page 3 of 63
Cement: fine aggregates: coarse aggregates
Collected by Eng: Hany El‐Halwany Page 4 of 63
SOIL
Collected by Eng: Hany El‐Halwany Page 5 of 63
Collected by Eng: Hany El‐Halwany Page 6 of 63
The SPT‐N values of dense sand is equal to 20 – 40
modulus of elasticity of rock mass less than rock substance
plasticity index is difference between liquid limit and plastic limit of soil
vertical effective stress = Total vertical Stress – pore water pressure
shear strength of Soil = σ tan ϴ + C (C = 0 for Sand Soil)
The undrained shear strength (su) of a cohesive soil is equal to one‐half the unconfined compressive
strength su = qu/2
For soils, the undrained shear strength (su) is necessary for the determination of the bearing
capacity of foundations
The unconfined compressive strength ( ) is the load per unit area at which the cylindrical
specimen of a cohesive soil falls in compression.
Shearing strength of cohesionless soil depends on confining pressure
Shear Strength of Soil = cohesion + normal stress on the failure plane* tan angle of internal friction
Cohesion is a term used in describing the shear strength soils (KPA) Cohesive shear resistance of
base in kN/m2 10 to 140 kN/m2
γsoil =Wsolid/Vsolid
γw =9.81 Kn/m3
The taper of precast concrete pile should not be more than 2 cm per meter length
The raft slab is projected beyond the outer walls of the structure by 30 to 45 cm
Collected by Eng: Hany El‐Halwany Page 7 of 63
FOS for Sliding in retaining wall = Σ W tan δ (Angle of Friction) / Σ Horizontal Force due to
earth pressure
Horizontal Force due to earth pressure = (1- Sin φ/ 1+ Sin φ) H γd
Safe design load for pile drilled in hard rock depends on Crushing strength of concrete
Tension pile Capacity = α C π D L when α is skin friction factor, C is the Cohesion of soil
Proctor Compaction test used to check the maximum dry density
Collected by Eng: Hany El‐Halwany Page 8 of 63
Concrete
a = ASXFy/0.85XFc’Xb
Mn for rec Section = 0.85Fc’X a X b X (d‐a/2) = As Fy(d‐a/2)
Minimum Reinforcement = 200(bXd) /Fy or 0.20 bd /100 for beam and 0.8 bd/100 for Columns
Maximum reinforcemnt = 4 bd /100 for Beams and 6 bd/100 for Columns
Safe load for Concrete Columns = Fc’ (Ag+(n‐1)As) where n = Es/Ec or = Fc’ (Ag‐As) + FyAs
Bucking Load for Column = π2 EI/L2
The minimum spacing between two reinforcement bars should be at least equal to the maximum
aggregate grain dimension with a margin of 5 mm. For Greece, the maximum aggregate grains
dimension for usual concrete is 32 mm and for self‐compacting concrete is 16 mm.
Maximum spacing of reinforcement in Slab and Footing shall not exceed three times the thickness,
nor 18 in.
The maximum spacing of stirrups used for this purpose should not exceed the smaller of one-half the
effective depth of the member (d/2) or 600 mm
Short Column define if L/b or L/h less than 10 for unbraced Column and 15 for braced
Column
In compression members, the lap length of a bar should not be less than 24 d
The maximum area of compression reinforcement in a beam of cross section 0.04bd
Rectangular section will provide minimum steel reinforcement and maximum section
dimensions
Collected by Eng: Hany El‐Halwany Page 9 of 63
Management
Project: endeavor or undertaken to achieve planned objectives to create a unique product, service
or result‐ Sequence of tasks. Planned from beginning to end
Total float = Late Start (activity 1) – Early Start (Activity 1)
Free Float = Early Start (activity 2) – Early Finish (Activity 1)
Critical path means longest sequence of activities path in a project
Total float, also called float or slack, is the amount of time an activity can be delayed without
delaying the overall project duration. Total float is shared between activities in a sequence.
Free float is the amount of time an activity can be delayed without delaying the early start of any
immediate successor activity.
WBS is the most important content and it is defined the scope of project
OBS organization breakdown structure is described project management team role and relationship
in graphical form
Risk breakdown structure is described risks according to risk categories in the project
Merge activities are the opposite of burst activities, a merge activity is the successor
of more than one activity
Critical Activity is the Activity if it is Delayed it will delay the Project
The direct cost includes the following: Labors & staff cost, project materials (supplies),
plants, transportation and consultant services
Indirect cost & expense during: The project, overhead, profit and administrative equipment
rental, audit and legal
Initial investment F= P (1+I) ^n
Pert is Program evaluation and review Technique
Pert chart the time estimate of activity is calculated by weighted average (beta distribution)
E = (O + 4M + P)/6
Where O is the optimistic value, M is the most likely value, and P is the
pessimistic value.
Collected by Eng: Hany El‐Halwany Page 10 of 63
Cost slope is defined as the ratio of difference between Crash cost & Normal
Under Sub-clause1.5 [Priority of Documents] from FIDIC1999, in a situation of
contractual disputes or ambiguities the priority of documents is set out as:
a) the Contract agreement
b) the Letter of Acceptance
c) the Letter of Tender
d) the Particular conditions
e) the General conditions
f) the Specifications
g) the Drawings
h) the Schedules and any other documents forming part of the Contract
Duration is : Ef‐Es or Lf‐Ls or
Total float is LF‐EF OR LS‐ES
Free Float ij= ESj – EFi, J is the next activity, I is the current activity if you start your project
from Day 0
Free Float ij= ESj – EFi, J ‐1 is the next activity, I is the current activity if you start your
project from Day 1
Late Start of Activity = Late Finish of activity – activity duration + 1
Late Finish of Activity = Late Start of successor activity (The Minimum if you have two
successors) – 1
The difference between total float and free float, is called interfering float
In a precedence diagramming method activities represented as Nodes
Collected by Eng: Hany El‐Halwany Page 11 of 63
Schedule Performance Index (SPI) is a measure of schedule efficiency, expressed as the ratio
of earned value to planned value SPI = EV/PV (if Schedule Performance Index is less than
one, you are behind schedule, if Schedule Performance Index is greater than one ahead of
schedule
Cost Performance Index (CPI) helps you analyze the efficiency of the cost utilized by the
project. It measures the value of the work completed compared to the actual cost spent on
the project CPI = EV/AC if Cost Performance Index is less than one you are over budget
Schedule Variance indication how much ahead or behind the schedule a project is running
SV = EV – PV
Cost Variance it is the difference between the Estimated cost per time and the planned Cost
CV = EV – AC
Earned Value: technique for estimating how a project is doing in terms of its budget and
schedule to obtain an estimate for the resources that will have been used at completion (i.e.
estimated Cost per time)
SPI EV/Pv
CPI EV/AC
SV EV‐PV
CV EV‐AC
Linear Activities.
This happens when the first activity is done, the second activity will start. After the second activity
is done, the third activity will be started.
Burst Activities.
This happens when the first activity is done, the second activity will start. After the second activity
is done, the third and the fourth activities will be started at the same time.
Merge Activities.
This happens when the third activity can only be started after the first and the second activities
are done. Then the fourth activity will start right after the third activity is done.
finish-to-start
First, let’s talk about finish-to-start (FS) dependencies. This is the most common type of
dependency and is the default type of dependency that Project uses. In a finish-to-start
dependency, the second task in the relationship can’t begin until the first task finishes. So, for
example, if you were planning a project to make a wedding cake, you might use a finish-to-start
Collected by Eng: Hany El‐Halwany Page 12 of 63
dependency between the “Bake cake” and “Decorate cake” tasks. When the “Bake cake” task is
finished, the “Decorate cake” task begins
Start-to-start (SS) dependencies are used when the second task in the relationship can’t begin
until after the first task in the relationship begins. Start-to-start dependencies don’t require that
both tasks start at the same time. They simply require that the first task has begun, in order for
the second task to begin. Going back to the wedding cake example, let’s say you had planned to
make the icing for the cake while the cake is baking in the oven. You can’t start making the icing
until the cake has started baking, so you might use a start-to-start dependency between the
“Bake cake” and “Make icing” tasks.
Finish-to-finish (FF) If one of your tasks can’t finish until another one finishes, you can use a
finish-to-finish (FF) dependency between them. Finish-to-finish dependencies don’t require that
both tasks be completed simultaneously. They simply require that the first task be finished, in
order for the second task to finish. The second task can finish any time after the first task finishes.
In our wedding cake example, let’s say there are some finishing touches to the decorations that
you can’t finish until the cake is delivered. You can use a finish-to-finish dependency between the
“Decorate cake” and “Deliver cake” tasks. When the “Decorate cake” task is finished, then the
“Deliver cake” task can be completed.
Collected by Eng: Hany El‐Halwany Page 13 of 63
Start-to-finish (SF) dependency is a little tricky. When you use this type of dependency, you are
saying that the second task in the relationship can’t finish until the first task starts. However, the
second task can finish any time after the first task starts. Going back to our wedding cake
example, let’s say you have a task for billing the customer. It begins when the customer requests
the cake, but it can’t be completed until after the cake delivery has begun. You can use a start-to-
finish dependency between the “Deliver cake” and “Bill customer” tasks, so that when the “Deliver
cake” task has begun, it is okay for the “Bill customer” task to finish.
Collected by Eng: Hany El‐Halwany Page 14 of 63
Collected by Eng: Hany El‐Halwany Page 15 of 63
Collected by Eng: Hany El‐Halwany Page 16 of 63
Preconstruction involves performing preliminary planning and engineering in order to define the
project, identify potential issues, and analyze cost impacts. O'Neal defines Preconstruction as
defining the project scope, schedule, and cost as early as possible with the most efficient use of
resources and money. Our Preconstruction efforts ultimately help the owner determine if the
project is even viable or not. If viable, Preconstruction defines the scope of work enough to
determine a firm cost and schedule for the project.
Collected by Eng: Hany El‐Halwany Page 17 of 63
first step after get the project develop Project Charter
intersection between WPS and OPS is Cost account
Precedence diagram method activity are represents as a Nodes
Dummy Activity; this activity does not actually exist in the project itself, hence
dummy activity, but is used to allow us to correctly represent the relationship
of the activities in a Network Diagram.
1. Initiation phase
2. Definition phase
3. Design phase
4. Development phase
5. Implementation phase
6. Follow-up phase
Negative Float - results when the time difference between the late dates
and the early dates (start or finish) of an activity is negative Hence when
we say negative float it means excess time is not available for an activity
so that activity must have to start before their predecessor activities
complete in order to meet a target finish date in a project schedule else
the project is bound to be delayed (if the float of an activity is negative
delay in its performance is bound to delay the completion of project )
Independent float
In project management, the amount of float on an activity that does not affect
float on preceding or succeeding activities. ES(Total Float – Duration )
Interfering float
Is LF of Activity – ES of Succeeding Activity or Total Float – Free Float
Collected by Eng: Hany El‐Halwany Page 18 of 63
The functional manager will have a very limited role within the Strong Matrix
Organization.
BAC: budget at completion = Total Baseline Costs
EAC: estimate at completion = Money spent to date + (Budgeted cost for the remaining work –
Earned Value) = AC + (BAC – EV)
ETC: estimate to complete = EAC‐AC
Scheduled % = planned value (PV) / budget at completion (BAC)
Performance % = earned value (EV) / budget at completion (BAC)
Collected by Eng: Hany El‐Halwany Page 19 of 63
Survey
Ranging in chain survey means establishing an intermediate point on the line
ROADS
Collected by Eng: Hany El‐Halwany Page 20 of 63
N = G2-G1
Collected by Eng: Hany El‐Halwany Page 21 of 63
Collected by Eng: Hany El‐Halwany Page 22 of 63
Collected by Eng: Hany El‐Halwany Page 23 of 63
Collected by Eng: Hany El‐Halwany Page 24 of 63
Collected by Eng: Hany El‐Halwany Page 25 of 63
Collected by Eng: Hany El‐Halwany Page 26 of 63
Fluid
Maning Equatiojn Q = 1/n (R^2/3)(S^0.5)*A when R=Area of Section /Perimeter of Canal
Over flow rate = flow rate / area
Slope in Sedimentation Tank: 1/20
For Subcritical Flow in open Channel the control section for gradually varied flow at the Downstream
The molar Concentration of water is: 55.60 mole/Liter
Water Molar Mass = 18 g/mol
Collected by Eng: Hany El‐Halwany Page 27 of 63
Collected by Eng: Hany El‐Halwany Page 28 of 63
Structure
From statics, we know how to determine member forces in a truss by using either the method
of joints or the method of sections. Once these forces are known we can determine the axial
deformation of each member by using the equation: NL/EA
The shape factor of standard rolled beam Z Plastic /Z Elastic varies from 1.1 to 1.20
Simple truss (statically determinate) if m = 2j -3 (the number of members plus the number of
support reactions must not exceed the number of joints times 2)
Maximum magnitude of shear stress due to shear force F on a rectangular section of area A at
the neutral axis, is 1.5F/A
E = stress / strain
Collected by Eng: Hany El‐Halwany Page 29 of 63
Shear deflection of a cantilever of length under concentrated load = 1.5PL/AG
The stiftiness factor for a prismatic or any shape beam EI/L
Hoop stress is the stress in the wall of a cylinder in a direction normal to its longitudinal axis, due to
a force acting along the circumference
If a three-hinged parabolic arch carries a uniformly distributed load on its entire span, every
section of the arch resists compressive force
Moment distribution method
Collected by Eng: Hany El‐Halwany Page 30 of 63
Units Conversation:
Lb. /Ft = 14.60 N/m or Kips/Ft = 14.60 KN/m
Kip/in = 1.75 KN/cm
Pa = 1 N/m2 , 1 Kpa = 1 KN/m2 , MPA = N/mm2
Esteel = 200 KN/mm2 = 29000 KSI(Kips/Inch2)
The maximum size of reinforcement bar in concrete slab total Concrete Thickness /8
Collected by Eng: Hany El‐Halwany Page 31 of 63
Collected by Eng: Hany El‐Halwany Page 32 of 63
Collected by Eng: Hany El‐Halwany Page 33 of 63
Collected by Eng: Hany El‐Halwany Page 34 of 63
GENERAL
QSAS: Qatar Sustainability Assessment System
AASHTO : American Association of State Highway and Transportation Officials
what governs in intersection design after capacity : Speed
Pert is Program evaluation and review Technique
pert uses the distribution to calculate the duration normal distribution
QCS: (2010): Qatar Construction Specification
ASTM : American Society for Testing and Materials
Chlorination and Disinfection – Last stage for Sewage Treatment Plant ‐ Killing bacteria and
Add Chlorine
Plastic Index of Clay ‐ High Silt ‐ Medium
Tensile strength in wood (direction wrt grains).
Ethnical should report anything wrong
Accumulation of Sludge in Septic Tank 30 liter /Person
Overflow rate for tank = flow rate/Area
Collected by Eng: Hany El‐Halwany Page 35 of 63
Solved Examples
Collected by Eng: Hany El‐Halwany Page 36 of 63
Collected by Eng: Hany El‐Halwany Page 37 of 63
Collected by Eng: Hany El‐Halwany Page 38 of 63
Collected by Eng: Hany El‐Halwany Page 39 of 63
Collected by Eng: Hany El‐Halwany Page 40 of 63
Collected by Eng: Hany El‐Halwany Page 41 of 63
Collected by Eng: Hany El‐Halwany Page 42 of 63
Collected by Eng: Hany El‐Halwany Page 43 of 63
Collected by Eng: Hany El‐Halwany Page 44 of 63
The undrained shear strength is basically equal to the cohesion
Collected by Eng: Hany El‐Halwany Page 45 of 63
Collected by Eng: Hany El‐Halwany Page 46 of 63
Collected by Eng: Hany El‐Halwany Page 47 of 63
Collected by Eng: Hany El‐Halwany Page 48 of 63
Collected by Eng: Hany El‐Halwany Page 49 of 63
Collected by Eng: Hany El‐Halwany Page 50 of 63
Collected by Eng: Hany El‐Halwany Page 51 of 63
Collected by Eng: Hany El‐Halwany Page 52 of 63
Curvature error comb = 0.0675 D2 m where D is the distance in km
Collimation = refraction ‐ Curvature error
Collected by Eng: Hany El‐Halwany Page 53 of 63
Collected by Eng: Hany El‐Halwany Page 54 of 63
Collected by Eng: Hany El‐Halwany Page 55 of 63
Collected by Eng: Hany El‐Halwany Page 56 of 63
Collected by Eng: Hany El‐Halwany Page 57 of 63
The compacting factor test of cement concrete determines its workability
As a natural material, timber is Anisotropic
Thermal Stress = E α dt
Collected by Eng: Hany El‐Halwany Page 58 of 63
STEEL
-What is the Difference between Steel and Stainless Steel?
-What is the Load Combinations as per BS5950, or AISC (LRFD, ASD)? Including wind loads
-If you have column fixed both ends, on the third length you have axial force 10Kn , what is the
Reactions at both ends?
-What is the difference between Braking Force and the lateral Force for overhead crane?
-Design one Portal Frame Eave height 6.00 m , width is 20 m , Spacing 6.00 m ,Roof Sheet weight is
5 Kg/m2, Spacing of Roof Purlin and Side Girts 1.20 m, Side Sheet height 3.00 m, wind load 80
Kg/m2?
- you have Steel Beam IPE 300 Grade 50 and other beam same Section with Grade 43 and Subjected
to Concentrated Load 10 KN, which beam, deflected with high value?
- Design one Beam Non Composite Section Carry 10KN/m as live Loads with length 6.00 m
-Design Same Previous Beam as a composite Section, with Concrete Thickness 120 mm.
-what is the Deflection Limit for Steel Beam Due to Dead Load + Live Loads?
-How you Design the Strut Beam between two Columns each Columns Carry 10 KN?
-Which section more (I or H Sections) economical for steel column retrained in both direction – Carry
only Axial Force?
-write the Method of statement for erection of Simple portal frame with Any Dimensions?
Collected by Eng: Hany El‐Halwany Page 59 of 63
Relationship between Mass and Force
Mass is the quantity of matter in a body. The mass of an object remains constant, regardless of its
location on earth.
Example: Defining load capacities for building elements, elevator cranes, hoists, bridges, roads,
supports, and bearing surfaces
Force is the external agent that changes or tends to change the condition of rest of a body.
Example: Forces related to the design and construction processes are numerous: bearing capacity,
applied weight (mass under the influence of gravity) of live, dead, and mobile loads, connection load,
etc. Force may be concentrated on a tiny spot or applied over an immense area.
A strand is an arrangement of wires laid helically about a center wire to produce a symmetrical
section.
A rope is a group of strands laid helically around a core composed of either a strand or
another wire rope.
Strands and ropes are manufactured from cold-drawn wire and do not have a definite yield point.
Therefore, a working load or design load is determined by dividing the specified minimum breaking
Strength for a specific size by a suitable safety factor
A rope has lower breaking strength and Modulus of elasticity than a strand
The bolts are torqued is preloaded high enough to ensure head-to-block contact is maintained at all
times
BS 5950 and BS EN 1090 Pt 2 (with reference to BS EN 1993 designs using HR8.8/PT1 fasteners)
states that 1 thread plus thread run out should protrude the outer face of the Nut and the end of the
Bolt. Also for pre-loaded bolts according to EN 14399-3 and EN14399-7, at least four full threads (in
addition to the thread run
out) should remain creal between the bearing surface of the nut and the unthreaded part of the shank.
BS 4604 Pt 1 contains a table which states what the length of Bolt should be based on the use of one
Nut and one Washer (based on BS 4395 dimensions).
Collected by Eng: Hany El‐Halwany Page 60 of 63
Type of Portal Frame
Clear Span Gable Buildings
Multi‐Gable Buildings with or without Interior Columns
Lean‐To Buildings
Space Savers Buildings
Single Slope Buildings with or without Interior Columns
Composite Deck
Composite deck is designed for use with structural concrete, and is manufactured with mechanical
embossments in the webs to create mechanical and chemical bond between the deck and the concrete.
The composite action allows the deck to serve as the tensile reinforcement for positive bending in the
slab, which significantly reduces or eliminates the need for rebar in the slab and lowers material and
labor costs. The strength and durability of the steel provides a solid platform for construction on top
of open web joists, structural steel, light gage framing, or masonry walls. The deck acts as a form for
the concrete and is typically designed so that shoring is not required.
Bracings: Cables / rods braces shall not exceed 15m in length. If a cross bracing contains rods longer
than15m, then the bracing should be broken to two sets of bracings with a strut member between
them so that the rod/cable lengths shall not exceed 15 m.
SHEAR FLOW The connection between the flange plate and the web plate of the built-up section can be
achieved by using intermittent or continuous fillet welds, with the latter more commonly preferred in
design practice. However, care should be taken with continuous fillet welds, especially for thin plates,
as this could lead to a distortion in these plates, creating undesirable residual stresses. The horizontal
shear force per unit length or shear flow at the interface between the web plate and the flange plate is
calculated as follows:
Collected by Eng: Hany El‐Halwany Page 61 of 63
Vh = Vu* Qf / Ix–x
Vu _ Factored vertical shear force, kips,
Qf _ Statical moment of the flange area about the neutral axis of the built‐up section, in.3, and
Ix–x _ Moment of inertia of the built‐up section about the strong axis (x–x), in.4
Characteristic Resistance is the Ultimate Load with a statistical probability factor applied (95%
Fractile). This factor is dependent on the variance of a set of results and also the number of anchors
tested.
Design Resistance is based upon the Characteristic Resistance divided by Partial Safety Factors as
determined from testing. Design Resistance should never be thought of as the load a fixing can
safely hold.
Design Action is a factored load taking into account variable actions and should always be below the
Design Resistance of the anchor.
STAINLESS STEEL is a common name for metal alloys that consist of 10.5% or more
Chromium (Cr) and more than 50% Iron (Fe). Although it is called "stainless", a better term for
it is "highly stain resistant". A somewhat dark metal, it looks bright because it reflects light.
IRON is an element: a pure substance. It rusts (forms iron oxide) on exposure to water and air. One of
its physical properties is that is quite brittle for a metal.
STEEL is a mixture of two elements iron and carbon, with more useful properties than pure iron for
many industrial purposes. So, the main difference is in their carbon and composition.
Steel often melts at around 1370 degrees C (2500°F).
CAST IRON is derived from pig iron, and while it usually refers to gray iron, it also identifies a large
group of ferrous alloys which solidify with a eutectic. The color of a fractured surface can be used to
identify an alloy. White cast iron is named after its white surface when fractured, due to its carbide
impurities which allow cracks to pass straight through. Grey cast iron is named after its grey fractured
surface, which occurs because the graphitic flakes deflect a passing crack and initiate countless new
cracks as the material breaks.
Carbon (C) and silicon (Si) are the main alloying elements, with the amount ranging from 2.1 to
4 wt% and 1 to 3 wt%, respectively. Iron alloys with less carbon content are known as steel. While
this technically makes these base alloys ternary Fe-C-Si alloys, the principle of cast iron solidification
is understood from the binary iron-carbon phase diagram. Since the compositions of most cast irons
are around the eutectic point of the iron-carbon system, the melting temperatures closely correlate,
usually ranging from 1,150 to 1,200 °C (2,102 to 2,192 °F), which is about 300 °C (572 °F) lower
than the melting point of pure iron.
Cast iron tends to be brittle, except for malleable cast irons. With its relatively low melting point,
good fluidity, cast ability, excellent mach inability, resistance to deformation and wear resistance, cast
Collected by Eng: Hany El‐Halwany Page 62 of 63
irons have become an engineering material with a wide range of applications and are used in pipes,
machines and automotive industry parts, such as cylinder heads (declining usage), cylinder blocks and
gearbox cases (declining usage). It is resistant to destruction and weakening by oxidation (rust).
Non-sway” frames A structure or structural frame may be classed as “non-sway” if its sway
deformation is sufficiently small for the resulting secondary forces and moments to be negligible. For
clad structures, provided that the
Stiffening effect of masonry infill wall panels or diaphragms of profiled steel sheeting is not explicitly
taken
Into account, this may be assumed to be satisfied if the sway mode elastic critical load factor
λcr of the frame, under vertical load only, satisfies: λcr >10
In all other cases the structure or frame should be classed as “sway-sensitive”
λcr =H/200δ
H is the storey height
δ is the notional horizontal deflection of the top of the storey relative to the bottom of the storey,due
to the notional horizontal forces from
SWAY-SENSITIVE” FRAMES All structures that are not classed as “non-sway” (including those in which
the stiffening effect of masonry infill wall panels or diaphragms of profiled steel sheeting are explicitly
taken into account), Should be classed as “sway-sensitive”
Except where plastic analysis is used, provided that λcr is not less than 4.0 the secondary forces and
moments should be allowed for as follows:
a) if the resistance to horizontal forces is provided by moment-resisting joints or by cantilever
columns, either by using sway mode in-plane effective lengths for the columns and designing the
beams to remain elastic under the factored loads, or alternatively by using the method specified in b);
b) By multiplying the sway effects by the amplification factor kamp determined from the following:
1) for clad structures, provided that the stiffening effect of masonry infill wall panels or diaphragms of
profiled steel sheeting is not explicitly taken into account:
kamp = λcr/(1.15 λcr-1.5) kamp >1.0
2) for unclad frames, or for clad structures in which the stiffening effect of masonry infill wall panels
or diaphragms of profiled steel sheeting is explicitly taken into account:
kamp = λcr/( λcr-1)
If λcr is less than 4.0 second-order elastic analysis should be used.
Collected by Eng: Hany El‐Halwany Page 63 of 63